Rework Request Form

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
431 views1 page

Rework Request Form

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Rework Request

REQUEST DATE
REWORK REQUEST _____ /______________ /20_______
ATG/CVL/2017/RR/01
REQUEST INITIATOR / REWORK EXECUTOR DETAILS

Project Name Area on Site Client Instruction Number (if any) Claimable / Not Claimable

Rework to be Executed / To
Requestor Name CVI Reference Number (if any) Site Observation by
be Supervised by
Employee Number / Short Employee Number / Employee Number /
| | Internal Reference Number GENERATED BY DOCUMENT CONTROLLER |
Code Short Code Short Code
IS IT ATTRIBUTABLE TO SUBCONTRACTOR TICK HERE YES TICK HERE NO NAME OF SUBCONTRACTOR (IF YES)
REWORK DETAILS
PLANNED REWORK REQUIREMENT PLANNED RESOURCE REQUIREMENT PLANNED COST

Description of Rework Building / Location Discipline Reason for Rework Material / Machinery / Manpower Approx. Cost (OMR)

Material Code No: Details: Qty: UoM:

Equipment Details: Equipment Hrs:

Manpower (Position Details): Man Hrs:

Planned Duration of Rework: Planned Start Date: Planned Finish Date: Grand Total:

REMARKS

APPROVAL SIGNATURES

REQUESTOR SITE FOREMAN SITE QS PROJECT MANAGER

NAME NAME NAME NAME

EMPLOYEE NUMBER EMPLOYEE NUMBER EMPLOYEE NUMBER EMPLOYEE NUMBER

POSITION / DESIGNATION POSITION / DESIGNATION POSITION / DESIGNATION POSITION / DESIGNATION

SIGNATURE / DATE SIGNATURE / DATE SIGNATURE / DATE SIGNATURE / DATE

Process Guidelines
1. Planned Cost will be entered by the Quantity Surveyor (QS).
2. Rework will commence only after the form is filled and duly approved upto Project Manager level.
3. Tracking of actual manpower used for executing Rework will be through Daily Activity Log book. The same will be recorded in Daily Activity Log book under applicable WBS. Discipline will be the applicable Discipline (3 digits); Activity Group shall be applicable Activity Group (3 digits) and Activity Code shall be '9998' (4 digits)
4. Progress photographs before and after re-work and associated day worksheets shall be maintained.
5. For each Rework request, copy of duly filled form along with updated REWORK - LOG SHEET shall be forwarded to Cluster Manager and Divisional Planning Manager for information.