METHODE OF STATEMENT Page
CUBICLE PANEL INSTALATION
1 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001
METHOD STATEMENT
CUBICLE PANEL INSTALLATION
STATUS REV
Approved by Pj
Checked by FS
For tender purpose only 00 Prepared by FS
METHODE OF STATEMENT Page
CUBICLE PANEL INSTALATION
2 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001
CONTENT/DAFTAR ISI
Description Pages
COVER 1
LIST OF CONTENT/DAFTAR ISI 2
1.0 PURPOSE/TUJUAN 3
2.0 REFERENCE DOCUMENT/REFERENSI DOKUMEN 3
3.0 RESPONSIBILITY/TANGGUNG JAWAB 3
4.0 TERMINOLOGY/TERMINOLOGI 3
5.0 INSTALLATION PROCEDURE/PREOSEDUR PEMASANGAN 3
1. General/Umum 3
2. Preparation/Persiapan 3
3. Tools/Peralatan 3
4. PPE & Work Safe Action /APD dan Tindakan Keselamatan Kerja 4
5. Emergency Responsible 4
6. Cubicle Panel Installation 4
6.0 CLEANING/KEBERSIHAN 5
METHODE OF STATEMENT Page
CUBICLE PANEL INSTALATION
3 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001
1 PURPOSE/TUJUAN
To describe the work methodology of Cubicle Panel installation / untuk
menggambarkan metode Kerja pemasangan Cubicle panel.
2. REFERENCE DOCUMENT/REFERENSI DOCUMENT
Equipment Layout & General Arrangement Drawing / Layout Equipment & Gambar
General Arrangement .
3 RESPONSIBILITY/TANGGUNG JAWAB
Project Manager, Site Manager and HSE Officers are responsible to socialize and
implement this procedure / Site Manager, HSE Manager and Officers yang
bertanggung jawan untuk mensosialisasikan dan menerapkan prosedur ini.
4 TERMINOLOGY/TERMINOLOGI
OKI : PT. OKI Pulp and Paper
PPE : Personal Protective
Equipment JSA : Job Safety
Analysis
HSE : Health Safety Environment
5 INSTALLATION PROCEDURE/PROSEDUR PEMASANGAN
1. General/Umum
Ensure all workers have to know their jobs will be done / Pastikan semua pekerja
telah mengetahui pekerjaan yang akan di lakukan.
2. Preparation/Persiapan
2.1 Survey location before execution / Melakukan pengecekan lokasi.
2.2 Make sure procedure and JSA have been approved / Pastikan prosedur
dan JSA sudah di setujui.
2.3 Materials mobilisation / Mobilisasi material.
2.4 Conduct Tool Box Safety Meeting / Melakukan rapat keselamatan kerja.
2.5 Prepare all drawing as required / Mempersiapkan semua gambar yang di butuhkan.
2.6 Inspection All tools and materials / Melakukan pengecekan peralatan dan material.
3. Tools/Peralatan
Truck Crane,Tools box , Drilling Machine,,Hand Pallet, Hand Jack, Pipe Galvanize, Level
Measurement.
METHODE OF STATEMENT Page
CUBICLE PANEL INSTALATION
4 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001
4. PPE & Work Safe Action /APD dan Tindakan Keselamatan Kerja
Safety Induction OKI
PPE (Safety helmet,Safety shoes,Safety glases,Hand
glove,Masker and Ear plugs)
Socialisation JSA,Work Permit, Lifting Permit and Work Methods
Coordination with responsible area and client before starting the jobs
Sign work / Warning tape
5. Emergency Responsible
OKI Resceu Team
Clinic OKI
Aswin L.Tobing (PM-Exabb 088212365079)
Turino (Elect Coord-Exabb 08228209859)
Andreas (SM-Exabb 082175915161)
Ahmad Romli (SM-Exabb 08128112513)
Boby Nusbaba (Safety-Exabb 081386236666
6. Cubicle Panel Installation
6.1 All personnel shall be wear complete PPE/ Setiap pekerja diwajibkan
mengenakan APD lengkap.
6.2 Check Drawing/ persiapan gambar yang akan di kerjakan
6.3 Allocate personnel in the area cubicle panel will be install /
Tempatkan pekerja di area panel kubikel yang akan di pasang.
6.4 Prepare lifting cubicle panel./ mempersiapkan pengangkatan panel kubikel.
6.5 Parking CRANE in the level area./ Parkir CRAN di area yang rata.
6.6 Operated CRANE as per procedure./Operasikan crane sesuai procedure
6.7 Tie-in belt sling to the hole location/lifting lug on top of panel
/Kaitkan sling belt pada lubang di atas panel.
- Verify if holes are provided in wood cases
- Verify belt slings have proper rating
- Verify belt slings have update inspection and provide documentation.
- For information only ( verify all measurements due to tight
condition,ensure bottom of cubicle is level with floor after removal
of wooden case of panel)
- Provide ITP for meggering & torquing
- Provide vendor data for meggering & torquing
- Provide calibration documents for megger, torque wrench.
METHODE OF STATEMENT Page
CUBICLE PANEL INSTALATION
5 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001
6.8 Lift and lower slowly the cubicle panel and put on in the floor / angkat
dan turunkan panel kubikel pelan-pelan dan letakkan di atas lantai
6.9 Make sure the panel position safe and level / Pastikan posisi panel aman dan rata
6.10 Open wooden case panel /membuka box kayu panel
6.11 Laying pipe galvanize ¾” under cubicle panel / Pasang pipa galvanis
¾” di bawah panel cubicle
6.12 Moving slowly cubicle panel till the position panel place /Menggeser
panel pelan2 sampai ke posisi tempat panel.
6.13 Install Bolt & nuts after all panel in the room ,seating and levelling./
pasang baut dan nut setelah semua panel di dalam ruangan ,setting
dan ratakan .
6.14 Setting panel on the base frame / memasang panel di base frame
6.15 Perform megger check of each cubicle before installing busbar joints
6.16 Ensure all cubicle are same level and jointed perfectly / pastikan
semua panel levelnya sama dan terhubung sempurna
6.17 Joint the busbar between cubicles and ensure all busbar are same
level. Check torque all bolt of busbar joint as recommendation from
vendor./sambung busbar di antara panel dan pastikan sambungan
sempurna dan torsi sesuai dengan rekomondasi vendor
6.18 Tightning all bolt & nut /mengencangkan semua baut dan mur.
6.19 Re-check and finishing /memeriksa kembali dan finishing
6. CLEANING
Making Cleaning and/or House keeping work area properly / melakukan pembersihan area
kerja.