1cubicle Panel - Method Statement

Uploaded by

Iqbal Zamali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views5 pages

1cubicle Panel - Method Statement

Uploaded by

Iqbal Zamali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

METHODE OF STATEMENT Page

CUBICLE PANEL INSTALATION


1 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001

METHOD STATEMENT
CUBICLE PANEL INSTALLATION

STATUS REV
Approved by Pj
Checked by FS
For tender purpose only 00 Prepared by FS
METHODE OF STATEMENT Page

CUBICLE PANEL INSTALATION


2 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001

CONTENT/DAFTAR ISI
Description Pages

COVER 1

LIST OF CONTENT/DAFTAR ISI 2

1.0 PURPOSE/TUJUAN 3

2.0 REFERENCE DOCUMENT/REFERENSI DOKUMEN 3

3.0 RESPONSIBILITY/TANGGUNG JAWAB 3

4.0 TERMINOLOGY/TERMINOLOGI 3

5.0 INSTALLATION PROCEDURE/PREOSEDUR PEMASANGAN 3

1. General/Umum 3

2. Preparation/Persiapan 3

3. Tools/Peralatan 3

4. PPE & Work Safe Action /APD dan Tindakan Keselamatan Kerja 4

5. Emergency Responsible 4

6. Cubicle Panel Installation 4

6.0 CLEANING/KEBERSIHAN 5
METHODE OF STATEMENT Page

CUBICLE PANEL INSTALATION


3 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001

1 PURPOSE/TUJUAN

To describe the work methodology of Cubicle Panel installation / untuk


menggambarkan metode Kerja pemasangan Cubicle panel.

2. REFERENCE DOCUMENT/REFERENSI DOCUMENT

Equipment Layout & General Arrangement Drawing / Layout Equipment & Gambar
General Arrangement .

3 RESPONSIBILITY/TANGGUNG JAWAB

Project Manager, Site Manager and HSE Officers are responsible to socialize and
implement this procedure / Site Manager, HSE Manager and Officers yang
bertanggung jawan untuk mensosialisasikan dan menerapkan prosedur ini.

4 TERMINOLOGY/TERMINOLOGI

OKI : PT. OKI Pulp and Paper


PPE : Personal Protective
Equipment JSA : Job Safety
Analysis
HSE : Health Safety Environment

5 INSTALLATION PROCEDURE/PROSEDUR PEMASANGAN

1. General/Umum

Ensure all workers have to know their jobs will be done / Pastikan semua pekerja
telah mengetahui pekerjaan yang akan di lakukan.

2. Preparation/Persiapan

2.1 Survey location before execution / Melakukan pengecekan lokasi.


2.2 Make sure procedure and JSA have been approved / Pastikan prosedur
dan JSA sudah di setujui.
2.3 Materials mobilisation / Mobilisasi material.
2.4 Conduct Tool Box Safety Meeting / Melakukan rapat keselamatan kerja.
2.5 Prepare all drawing as required / Mempersiapkan semua gambar yang di butuhkan.
2.6 Inspection All tools and materials / Melakukan pengecekan peralatan dan material.

3. Tools/Peralatan

Truck Crane,Tools box , Drilling Machine,,Hand Pallet, Hand Jack, Pipe Galvanize, Level
Measurement.
METHODE OF STATEMENT Page

CUBICLE PANEL INSTALATION


4 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001

4. PPE & Work Safe Action /APD dan Tindakan Keselamatan Kerja

 Safety Induction OKI


 PPE (Safety helmet,Safety shoes,Safety glases,Hand
glove,Masker and Ear plugs)
 Socialisation JSA,Work Permit, Lifting Permit and Work Methods
 Coordination with responsible area and client before starting the jobs
 Sign work / Warning tape

5. Emergency Responsible

 OKI Resceu Team


 Clinic OKI
 Aswin L.Tobing (PM-Exabb 088212365079)
 Turino (Elect Coord-Exabb 08228209859)
 Andreas (SM-Exabb 082175915161)
 Ahmad Romli (SM-Exabb 08128112513)
 Boby Nusbaba (Safety-Exabb 081386236666

6. Cubicle Panel Installation

6.1 All personnel shall be wear complete PPE/ Setiap pekerja diwajibkan

mengenakan APD lengkap.

6.2 Check Drawing/ persiapan gambar yang akan di kerjakan

6.3 Allocate personnel in the area cubicle panel will be install /

Tempatkan pekerja di area panel kubikel yang akan di pasang.

6.4 Prepare lifting cubicle panel./ mempersiapkan pengangkatan panel kubikel.

6.5 Parking CRANE in the level area./ Parkir CRAN di area yang rata.

6.6 Operated CRANE as per procedure./Operasikan crane sesuai procedure

6.7 Tie-in belt sling to the hole location/lifting lug on top of panel

/Kaitkan sling belt pada lubang di atas panel.

- Verify if holes are provided in wood cases


- Verify belt slings have proper rating
- Verify belt slings have update inspection and provide documentation.
- For information only ( verify all measurements due to tight
condition,ensure bottom of cubicle is level with floor after removal
of wooden case of panel)
- Provide ITP for meggering & torquing
- Provide vendor data for meggering & torquing
- Provide calibration documents for megger, torque wrench.
METHODE OF STATEMENT Page

CUBICLE PANEL INSTALATION


5 of 5
Doc. No. MOS-
Contract No. Date: Rev.00
TOHOMA-001

6.8 Lift and lower slowly the cubicle panel and put on in the floor / angkat

dan turunkan panel kubikel pelan-pelan dan letakkan di atas lantai

6.9 Make sure the panel position safe and level / Pastikan posisi panel aman dan rata

6.10 Open wooden case panel /membuka box kayu panel

6.11 Laying pipe galvanize ¾” under cubicle panel / Pasang pipa galvanis

¾” di bawah panel cubicle

6.12 Moving slowly cubicle panel till the position panel place /Menggeser

panel pelan2 sampai ke posisi tempat panel.

6.13 Install Bolt & nuts after all panel in the room ,seating and levelling./

pasang baut dan nut setelah semua panel di dalam ruangan ,setting

dan ratakan .

6.14 Setting panel on the base frame / memasang panel di base frame

6.15 Perform megger check of each cubicle before installing busbar joints

6.16 Ensure all cubicle are same level and jointed perfectly / pastikan

semua panel levelnya sama dan terhubung sempurna

6.17 Joint the busbar between cubicles and ensure all busbar are same

level. Check torque all bolt of busbar joint as recommendation from

vendor./sambung busbar di antara panel dan pastikan sambungan

sempurna dan torsi sesuai dengan rekomondasi vendor

6.18 Tightning all bolt & nut /mengencangkan semua baut dan mur.

6.19 Re-check and finishing /memeriksa kembali dan finishing

6. CLEANING

Making Cleaning and/or House keeping work area properly / melakukan pembersihan area
kerja.