SOP Foundation - Transmission Line
SOP Foundation - Transmission Line
Contents
1. Objective ....................................................................................................................................... 3
2. Scope ............................................................................................................................................. 3
3. References ..................................................................................................................................... 3
4. Acronyms ...................................................................................................................................... 4
5. Roles and Responsibility: .............................................................................................................. 4
6. Standard Machines and Tools: ..................................................................................................... 5
7. Tower Foundation –PPE Matrix .................................................................................................... 6
8. Flow Chart: Tower Foundation Activity: ....................................................................................... 7
9. Flow Chart: Selection of Workman and Tools & Tackles .............................................................. 8
10. Pre Operational Checks ................................................................................................................ 9
I. Excavation by blasting method.............................................................................. 10
II. Shoring, Benching and Sloping types.................................................................... 12
III. Well Point Requirement: (Exceptional Case) ..................................................... 12
11. Operational Procedure: .............................................................................................................. 13
A. Pit Marking ............................................................................................................ 13
B. Excavation ............................................................................................................ 14
C. Excavation in Unequal Ground Level................................................................. 15
D. Well Point Requirement: (Exceptional Case) ..................................................... 15
E. PCC (Plain Cement Concrete) .............................................................................. 16
F. Stub setting by Template and Prop Setting ........................................................... 17
G. Reinforcement Rod Binding ............................................................................... 19
H. Formwork and Shuttering .................................................................................. 20
I. Concreting ............................................................................................................ 21
12. Form Box Removal / Curing / Backfilling ................................................................................... 36
13. Post Operational Checks ............................................................................................................. 37
14. Checklist, Records, Permits and Other Requirements ................................................................ 37
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
1. Objective
To establish the procedures for Foundation and concreting activities for tower locations in
Transmission Line Projects
2. Scope
This SOP is applicable in all KEC projects and shall be followed by all KEC Employees, Sub-
contractors and their employees.
This SOP is applicable to all configurations of A/C & D/C Transmission tower foundations
Type D –Angle & Dead end tower – 30 to 60 degrees and dead end
3. References
A. QMS Work Procedure
B. HSE Manual
4. Acronyms
Tractor with Trolley Under Ground Utility Detector Chop Saw Cutter
PPE MATRIX
Pit RCC
PCC Stub Bar Chimney
PPE List Survey Marking & Concretin Earthing Curing Backfilling
Concreting Setting Binding concreting
Excavation g
Safety Helmet
Safety Shoes
Gumboot
Nose mask
Thermo Latex Hand Gloves
PVC Hand Gloves
Goggles
Full Body Harness
Ear Muf/ Ear Plug
Shoulder Pad
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
PIT MARKING
CURING
DESHUTTERING
BACKFILLING
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
SELECTION OF MANPOWER
SCREENING OF WORKMEN
Trial Pit UG Utility Detector
F. In case of working within city limits, excavation clearance permit should be
obtained from the concerned authorities before excavation. (Wherever applicable)
G. Ensure that the machines have valid registration and fitness certificates. (Equipment
fitness report for vehicle & earth moving equipment)
H. Valid driving licenses of the vehicle drivers.
I. Ensure the vehicle speed is low while approaching to site
J. Before excavating, soil classification test shall be conducted to classify the soil type
as per the standard requirement. This will help in deciding the angle of repose
(slope).
K. As per the foundation classification (DRY, WET, DFR, FS, PS, and WBC) and type of
tower, pit marking shall be done.
L. As per the foundation classification (DRY, WET, DFR, FS, PS, and WBC) and type of
tower, pit marking shall be done.
M. Rigid ladder made of FRP / Steel should be used for easy ingress / egress into the
excavated pit. No bamboo ladder is permitted.
N. Ensure excavated pits are properly barricaded and caution boards are displayed in
local language.
O. Adequate line clearance is to be maintained while working near live lines.
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
Up to 11 4.6
33 5.1
66 5.49
132 6.1
220 7.015
400 8.84
765 12.24
800 12.48
a) Ensure all blasting operation shall be carried out by Licensed blaster and all
safety precautions have been taken.
b) Be aware of free boulders movement on hilly terrain.
c) Control blasting procedure shall be adopted while working near existing
transmission lines, villages, houses or any structure which can be impacted by
the blast.
d) Ensure contractor possesses all the relevant forms as mentioned in The
Explosives Act and Rules.
e) Ensure a contractor is having Licensed Shot Firer’s (Form no. 30) check its
validity.
f) Ensure blasting shall not be done during thunderstorm / lightning.
g) Ensure Explosives & Detonators are transported separately.
h) Ensure Explosives & blasting caps are stored in separate place.
i) Ensure no metal tools shall be used during blasting process.
j) Ensure not to carry blasting cap in pockets.
k) Ensure not to load any hole other than required.
l) Ensure nose mask, Goggles, ear muff, Gloves are worn by Rock drillers while
drilling the hole.
m) Ensure that control blasting is done to prevent flying of rocks.
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
A. Pit Marking
a) Pit Making is the first and foremost important part of tower foundation. Pit
marking is done only after the soil classification approval for type of casting
done. Pit Marking is calculated using foundation drawings duly approved by
client.
b) A typical pit marking calculation is shown below
O,E
PIT SIZE
P
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
B. Excavation
a) Ensure that all excavation shall be carried out as per the approved drawing
b) Check for any HT / LT lines if present Line Clearance shut down shall be
obtained
c) Ensure angle of repose or slope is maintained depending on the soil type
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
c) Ensure the stacking of the excavated soil
shall be stored at safe distance from the
pit
d) Ensure the heap of the stacking shall not
exceed 1.8 m. Ensure shoring done on
water logged / soil. Check whether the
shoring components are good enough to
withstand the pressure of the load
e) In sandy area please ensure that all the
workmen are using Dust Hood Mask
a) The depth of actual excavation at the pit centre is measured with reference
to the ground level at the centre of the tower location.
b) A typical example of determining the actual depth of excavation of the pits
is shown below.
a) In general, Template shall be used in all locations for Stub setting. In Special
cases like Special Towers, RC Towers, Hilly Terrains, Water logged areas,
Sandy Soil where template setting is not feasible, stub setting using props
May be preferred
b) Stub Setting Template Method
i. A stub setting template is a specific tool for a type, design & make of
tower. It is a light rigid steel framework and is used to hold the tower
stubs at the correct alignment and slope during the concreting work. The
template is adjustable type which can suit the standard tower as well as
towers with standard extensions.
ii. The template is lifted and placed on jacks. Eight jacks are used, two for
each corner of the template. The jacks are supported on sleepers which
are placed across the pits so that the load of the template is distributed
away from the excavated pits. The lengths of the sides and diagonals of
the template are measured. These are compared with those given in the
drawing and corrected as required.
iii. The template is centered on the location with the help of the plumb lines.
The template is levelled and the height of the base of the template above
ground level is kept.
iv. The stubs are then fixed on the legs of the template. The distance
between the end of the stub and the base of the pit is checked with
reference to the foundation drawing. If the distance is less, then the pit is
accordingly excavated. In case the distance is more, the extra excavation
is filled with lean concrete of 1 : 3 : 6 mix and allowed to set before
further activities are taken up. Never use sand to fill the extra excavation
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
v. Ensure the person shall take precautions from pinch / shear injury while
handling jack
vi. Ensure the workman wears full body harness while working on chimney
box.
vii. During Prop setting, check the condition of ground level for firmness and
rigidity. Anchoring shall be done on ground if required.
viii. Ensure stubs are supported by Pipes / Angles to prevent accidental fall of
stub on workmen inside the pit.
ix. Use ladder wherever the height of fall could be more than 1.5 m
x. A Typical Prop Setting drawing and slope calculation using this drawing is
shown below for reference.
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
d) Provide chair rods for reinforcement as per drawing to avoid deflection of the
top reinforcement.
e) Ensure that any workmen is not alone in excavated pit
f) Battery operated Rebar Tying machine shall be used for tying of rebar joints.
Advantages of rebar tying machine is mentioned below.
d) Ensure sufficient manpower is engaged for shifting the formwork and shuttering
materials as per the resource plan.
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
I. Concreting
a) General Preliminaries:
i. All wet locations must be kept completely dewatered both during the
placing of the concrete and for 24 hours after completion. There should
be no disturbance to concrete by water during this period. All
arrangement for dewatering shall be made before starting the work of
concreting.
ii. The base pad of required depth as per foundation drawing is then placed
using the specified concrete mix and allowed to set.
iii. In case of RCC type foundation, the cover of 50 mm shall be provided all
around between the reinforcement steel and the sides of the frustum /
chimney
iv. The steel reinforcement shall be placed on the pad as per the design and
the bar bending schedule.
v. The shuttering for the first step of the foundation is first placed on the
pad and concrete is poured within the shuttering. After pouring of every
150 mm of concrete, vibrator is used for proper compaction.
vi. The above procedure is repeated for all the steps of the foundations one
by one till the chimney level is reached.
i. After the frustum part is poured, the earthing connection is fitted on the
designated stub / stubs. Earthing is provided on Leg 1. Additional
earthing, if required, is provided on Leg 3. Counterpoise earthing is
provided on all legs.
ii. The chimney portion of the form box is fitted on the frustum. The
earthing connection is passed through the joint of the two parts of the
chimney. The chimney is centered and fixed so that equal spacing from
the stub is available all around. The chimney is bolted to the frustum
portion and slurry of sand and water is applied at the joints to prevent
leakage of cement slurry.
iii. The concrete is then poured into the chimney portion. After pouring of
every 450 mm of concrete, poking rod or vibrator is used to avoid voids in
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
vi. Testing of the concrete is to be got done as specified in the Standard Field
Quality Plan (SFQP) annexed with the work order. Samples of the
concrete in form of concrete cubes of size 150*150*150 shall be taken as
per the requirements and procedures given therein
i. All the materials required for RMC should be stored in such a way as to
prevent the risk of contamination. Different materials shall be stored
separately by taking due precautions and care, to avoid intermixing.
ii. For storage of cement and aggregates the instructions given in IS 4082
should be followed.
iii. Stock piles should be arranged in such a way so as to prevent
intermingling of adjacent materials. Different size fractions of aggregate
(say 10-20 mm, below 10 mm) should be stored separately. Coarse and
fine aggregate may be of different types and from different sources, and
accordingly these should be separately stored. (Picture below for
reference)
iv. For better performance & quality, storage bins must be used to store
materials. Open stock-piles are prone to contamination & there is no
control over moisture content during wet season. Moisture probe can
effectively measure water content of the aggregates.
v. The handling procedures of loading and unloading aggregate should be
such as to reduce the segregation to minimum. This can be done by using
rock ladders below the conveyor belts
vi. The RMC manufacturer shall ensure suitable transfer & feed systems.
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
vii. Various aspects to be looked into for material storage and handling are
listed in the check list for this item.
iii. Additionally, for concrete of Road and Bridge work the guidelines given in
section 1707, 1708.1 and 1708.2 of MORT &H specifications published by
IRC (Fifth revision) 2013 as given in references in Annexure I shall be
referred to.
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
h) Batching Controls
i. Batching controls are the part of the batching equipment that provides
means for operating batching device for an individual material. They may
be mechanical, hydraulic, pneumatic, electrical, etc. or a combination of
these means. A batching system is a combination of batching devices and
batching controls necessary for the accurate and consistent batching of
concrete ingredients in the desired proportions.
ii. Normally, a batching system would include batching devices and controls
for cementitious materials, aggregates, water, and admixtures. Adequate
dosing outlets must be available for different admixtures & fibers. High
strength concrete with silica fume will need at least four outlets.
i) System Requirements
j) Mixing
k) Transport of Concrete
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
i. Ready Mixed Concrete shall be transported from the mixer to the point of
placing as rapidly as possible and practicable by methods that will
maintain the workability and will prevent segregation loss of any
constituents or ingress of water or foreign matter. The concrete then
shall be placed as soon as possible after delivery.
ii. It shall always be emphasized that concrete should be laid in the position
without any loss of time to avoid reduction in workability, setting and
stiffening of concrete. This aspect becomes very critical in case of Ready
Mixed Concrete where the time interval in between mixing and placing of
concrete is considerable. As concrete stiffens with passage of time, delay
in placement of concrete reduces workability of concrete. In addition,
after some time setting of concretes may also take place.
iii. Reduction in workability may lead to difficulty in placement of concrete.
Thus, while planning for use of Ready Mixed Concrete, the aspect of loss
of workability in the likely transit time involved should be taken into
account. By measuring slump/ compacting factor immediately after
mixing at RMC plant and after a lapse of predetermined time (i.e.
anticipated average transit time), loss of workability may be estimated.
Desired workability at the time of delivery should be clearly specified in
the specification or tender conditions.
iv. The ticketing system is given in Annexure ‘G’ of IS 4926 shall be referred.
The producer shall ensure that a proper delivery ticket is issued which
should contain quantity of concrete loaded, the raw material content of
the concrete mix, time of delivery from mixer, truck/lorry number,
signature of Plant operator etc. The standard proforma as given in
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
Annexure B shall be filled and given to driver of truck/lorry who will hand
over the same to the supervisor in charge of site. The delivery ticket will
form the basis of invoicing.
v. The transport of RMC to site shall be by transit mixer and agitators. They
shall confirm to IS 5892
vi. Before the delivery of concrete produced in Ready Mixed Plant/ captive
Batching Plant it is the responsibility of the producer to ensure that each
truck mixer is inspected to confirm its compliance with the requirements
given in check list of this section.
i. The concrete shall be delivered at the site of work and discharge shall be
completed with-in Two hours of adding mixing water to the dry mix of
cement and aggregate
ii. Concrete received after the transit time, as specified above, shall not be
accepted. (Specify the transit time limit by deducting anticipated time
required for placement of concrete from initial setting time specified in
approved Mix proportion (Design mix)).
iii. Concrete, thereafter, shall be placed in position with-in the designed
initial setting time. At the end of initial setting time, the left-over portion
of concrete, if any, shall be rejected
i. Under any circumstances addition of any water shall not be allowed after
the initial mixing of concrete, as re-tempering will reduce the
compressive strength of concrete.
o) Pumping of RMC
i. The RMC can be placed into position by using pump, in such case it is a
pump able concrete. Similarly, the RMC can be placed by using other
methods such as buckets, cradles, conveyor belts; chutes etc. in such case
the RMC will be non- pumpable. However most of the RMC nowadays is a
pumpable concrete. Hence detail information about mix proportioning,
types of pumps, pumping pressures, formwork and its stability,
compaction methods is necessary for the quality concrete.
TRANSPORT OF CONCRETE
TICKETING SYSTEM
CHECKLIST - 1
MATERIAL STORAGE AND HANDLING
Description Observations
4.1 CEMENTITIOUS MATERIALS
4.1.1 CEMENT
[Link]. Condition of silos /bins and the cement feeding area, are they
weather-proof ?
Pl. specify:- Good/Bad
Yes/No
[Link]. How is cement supplied – Bags/ Bulk
a) If supplied in bags – Describe how it is stored.
(In weather-proof, damp-proof, well ventilated and reasonably free from
dust, check for test reports; identification tags indicating date of receipt of
lot and type. Quarantine area for damaged bags )
b) If supplied in bulk – Describe how it is fed to silo and from silo to mixer;
whether the loading and handling system permits free flow & easy
discharge of cement.
[Link]
[Link] Describe the provisions for storage for each size and type for
aggregates. ( Does the system prevents mixing of different sizes and
types; are there proper signboards etc )
[Link]. What adequate precautions taken to prevent intermixing of
aggregates with dust ,mud, soil and other deleterious materials. Are they
adequate ?
[Link] What provision regarding water sprinklers or other system made
to bring down the temperature of aggregates in hot weather ?
4.1.4. WATER
[Link] What is the source of water ?
Is sufficient quality and required quantity available? Are test reports
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
Description Observations
4.1.5. CHEMICAL ADMIXTURES
[Link] – What chemical admixtures are being used ? what is the shelf life
? what specifications are supplied by manufacturer; Test reports
availability; Are they OK? Are the admixtures supplied with proper marking
and information as per clause 10.1 & 10.2 of IS9103.
CHECKLIST - 2
BATCHING AND MIXING CONTROL EQUIPMENT
Description Observations
5.1 SCALES
5.1.1 What type of Scale is there? Are they readable by the by batch operator from
his position? Is SCADA system installed?
5.1.2 Have the preset controls been calibrated in increments not exceeding 5kg or
less each for cement and mineral admixtures, 10 kg or less for aggregates and 2
kg or less for water ? (Clause E-1 (c) of Annex E of IS 4926 ) Pl. specify.
5.1.3 For continuous mixer plants has the calibration been done in increments not
exceeding 10 kg/m 3 each for cement and mineral admixtures, 25 kg/m 3 for
aggregates and 10 lit/m 3 for water ? (Clause E-1 (d) of Annex E of IS 4926 ) Pl.
specify.
5.1.4 Do the digital read-outs have a scale increment not exceeding 2 kg each for
cement and mineral admixtures, 10 kg for aggregate and 1 liter of water ? (Clause
E-1 (e) of Annex E of IS 4926 ) Pl. specify.
5.1.5 What is the frequency of recheck of scales carried out ( at least every 3
months for electrical/ load cell system ) ? (Clause E-1 (j) of Annex E of IS 4926 ) Pl.
specify.
5.1.6 Is the recalibration done promptly and correction carried out if the plant is
moved or non compliance is indicated in the 3-month rechecking ? Pl. specify.
5.1.7 What is the record of calibration of weighing and measuring system ? Is it
maintained properly.
5.1.8 Are adequate permanent facilities provided for the application of test weights
KEC INTERNATIONAL LIMITED
Document Name Work Instructions
Description Observations
5.2. WEIGH BATCHERS (Clause 9.1.2 and 9.1.3 of IS 4926 )
5.2.1 Are the hoppers for weighing cement, aggregates, and also water and
admixtures ( if measured by weight ) consist of suitable containers freely
suspended from a scale, and are they equipped with necessary charging and
discharging mechanisms ?
5.2.2 Are the hoppers capable of receiving maximum rated load without contact of
the weighted material with charging mechanism ?
5.2.3 Are hoppers self-cleaning and fitted with means to facilitate complete
discharge ? What is the observation?
5.2.4 Are vibrator or other equipment installed in such a way as not to affect
accuracy of weighing ?
5.4 DISPENSERS FOR LIQUID ADMIXTURES (Clause 9.1.2 and 9.1.3 of IS 4926 )
Chemical admixtures shall be added to the concrete mixture with the help of a
dispenser – a device for batching of liquid admixtures ; preferably with an agitator..
Admixtures shall not be administered manually.
5.4.1 How are liquid admixtures measured (Volume/ Weight)
5.4.2 Whether each dispenser of liquid admixture has been provided with an
accurately calibrated container (if measured by volume) in which the admixture can
be collected when it is desired to check the accuracy of measurement & within
tolerances .
Description Observations
5.6. BATCHING SYSTEMS
5.6.1 Batcher Controls
[Link] Weigh Batcher Controls:- Cementitious materials and aggregates must be
batched by weight; water and admixtures may be batched in a weigh batcher or by
volume . Check and specify about this.
Automatic Control – When actuated by a single starting signal, an automatic weigh-
batcher control shall start the weighing operation of cementitious materials,
aggregate, water, or admixture, and stop the flow automatically when the
designated weight has been reached. Pl. check and write details.
5.7 RECORDERS :
5.7.1 Are the devices (Digital only) that provide a permanent record of the quantity
of cementitious materials, aggregate, water or admixture measured into a particular
batch of concrete. Whether Digital recorders are installed for each of the aforesaid
material.
5.7.2 Pl. check and specify about the following points ;Are recorders :-
1) Properly protected, that is, provided with effective security to prevent tampering
with records.
2) Provide traceability of the particular batch with the corresponding delivery ticket.
3) Register the quantity of ingredients batched; such as cementitious, aggregates,
water, admixture etc.
CHECKLIST - 3
TRANSPORT OF CONCRETE
Description Observations
6.2 DELIVERY FLEET INSPECTION
6.2.1 Hardened concrete built up in mixer drum and on blades
[Link] Are the truck mixers maintained in an efficient and clean
condition ?
[Link] Is there an appreciable accumulation of hardened concrete in
the mixer drum and on the mixer blades ?