Saudi Aramco Test Report

This document is a test report for Low Voltage Power and Control Cable, detailing the continuity and insulation resistance testing conducted for the Jafurah Upstream TCF Installation project. The report includes test procedures, acceptance criteria, and results, indicating that the tests were performed in accordance with Saudi Aramco standards. The findings confirm that the cables meet the required insulation resistance values and are acceptable for use.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views5 pages

Saudi Aramco Test Report

This document is a test report for Low Voltage Power and Control Cable, detailing the continuity and insulation resistance testing conducted for the Jafurah Upstream TCF Installation project. The report includes test procedures, acceptance criteria, and results, indicating that the tests were performed in accordance with Saudi Aramco standards. The findings confirm that the cables meet the required insulation resistance values and are acceptable for use.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

SAUDI ARAMCO ID/PIEU-31-Dec-2018 - Rev. 2018.12.00 (Standards Cutoff - Dec 31,2018) Rev.2018.12.

00 31-Dec-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Low Voltage Power and Control Cable, Continuity and
SATR-P-3203 4-Mar-19 ELECT- 674
Megger Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Jafurah Upstream TCF Installation 6600050449 A.M.A.H.Al Tamimi Partners Co.


EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
MDP-307 /MDP-308A/B/C; 309A/B;310 LV T00
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
TD-708450-AB-001 3
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
4/3/23 8:30 AM SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SATIP-P-104-01 4.1
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W H

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. TEST PROCEDURE AND CHECKLIST

Inspection shall be performed by the project approved Quality Control


Schedule Q
A1 Inspector (QCI) and witness point shall be coordinated with the
Att. IV Sec. 3 √
Contractor and Company.
Testing is to be carried out ONLY on de-energized cables. Cables shall
SAES-P-104
A2 be tested for their de-energized state before starting test on them.
Sec. 3.2 √
NFPA 70, NEC 110.3 & NETA ATS 2009, 5.1
Inspect cable wires for crimping and proper connection in accordance
SAES-P-104
A3 with schematic diagram.
Sec. 3.2 √
NETA ATS 2009, 7.3.2.1.4
Perform continuity test of each core of cable drum to ensure no
SAES-P-104
A4 conductor is broken with certified and calibrated Ohm-meter.
Sec. 3.2 √
NETA ATS - 2009, 7.3.2.3.2.3
All wires should be left grounded when not on test, during the testing of
SAES-P-104
A5 other wire, until completely discharged.
Sec. 3.2 √
NFPA 70, NEC 110.3 & NETA ATS 2009, 5.1
Low voltage (600, 450/750, or 600/1000 V rated) wires, including
SAES-P-104
A6 splices to existing wires, shall be 1000 V DC megger tested after
Sec. 13.1 √
installation and prior to placing in service (during commissioning).

If cable ends are exposed for testing, they shall be re-sealed (water
SAES-P-104
A7 and dust-proof seals) and firmly secured when not terminated.
Sec. 3.2 √
NFPA 70, NEC 110.3, manufacturer's instructions

Site Test Records and Receipt documents are to be carefully SAES-P-104


A8
presented in original. Sec. 3.2 √

B. TEST EQUIPMENT AND MATERIALS CRITERIA

1. Digital / Analog Multimeter for Continuity Test.

2. Megger for Insulation Resistance Test.

3. For measurement of time, the instruments’ accuracy shall be ±1% or better.

4. The test equipment calibration cycle shall not exceed twelve months.
Schedule Q, Att. IV, Sec. 7

Test Equipment Manufacturer: Serial Number:

Scale Range and accuracy: Calibration date:

Calibration Company and Technician: Calibration Expiration Date:

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-31-Dec-2018 - Rev. 2018.12.00 (Standards Cutoff - Dec 31,2018) Rev.2018.12.00 31-Dec-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Low Voltage Power and Control Cable, Continuity and
SATR-P-3203 4-Mar-19 ELECT- 674
Megger Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Jafurah Upstream TCF Installation 6600050449 A.M.A.H.Al Tamimi Partners Co.

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

C. TEST RESULTS

D. CONCLUSIONS

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Minimum insulation-resistance values should not be less than 50
SAES-P-104
D1 megohms.
Sec. 3.2
NETA ATS - 2009, 7.3.2.3.2.2
Investigate deviations between adjacent phases. SAES-P-104
D2
NETA ATS - 2009, 7.3.2.3.2.4 Sec. 3.2
If cable megger test result from conductor to sheath is less than 20 M
SAES-P-104
D3 Ohms, the cable shall not be used.
4.1
NFPA 70, NEC 110.3
Test results are acceptable and in accordance with Saudi Aramco Schedule Q
D4
Engineering Standards and contractual requirements. Att. II

REMARKS:

ATTACHMENT(S):
1. Attachment - 1 SA-P-040 SA Pre-Com Form, Low Voltage Cables, March 2006
REFERENCE DOCUMENTS:
1. Schedule G - Material, Tools and Equipment (Pro Forma MP-IK-LS Contract), March 2006
2. Schedule Q - Quality Requirements (Pro Forma Contract), February 2008
3. Pre-Commissioning Form (SA-P-040) Low Voltage Cables, March 2006
4. Acceptance Testing Specifications - NETA (2009)
5. SAES-P-104 Wiring Methods and Materials, 08 August 2010
NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing states
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization concerned
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer
indicates compliance with appropriate standards or performance in a specified manner.

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-31-Dec-2018 - Rev. 2018.12.00 (Standards Cutoff - Dec 31,2018) Rev.2018.12.00 31-Dec-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Low Voltage Power and Control Cable, Continuity and
SATR-P-3203 4-Mar-19 ELECT- 674
Megger Insulation Resistance Testing
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

Jafurah Upstream TCF Installation 6600050449 A.M.A.H.Al Tamimi Partners Co.

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.
Name, Title, Department, Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Company, Initials and Name, Initials and Date:
Date:
DAVE BAUTISTA JOEMAR S. DOROMAL
QC Inspector PID Representative
Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
RAFI CADA
QC Supervisor Proponent and Others
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
RICARDO COMOTA Initials and Date:
*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-31-Dec-2018 - Rev. 2018.12.00 (Standards Cutoff - Dec 31,2018) Rev.2018.12.00 31-Dec-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Low Voltage Power and Control Cable, Continuity and
SATR-P-3203 4-Mar-19 ELECT- 674
Megger Insulation Resistance Testing
Attachment - 1 (Pre-Com Form, SA-P-040)

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-31-Dec-2018 - Rev. 2018.12.00 (Standards Cutoff - Dec 31,2018) Rev.2018.12.00 31-Dec-18
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
Low Voltage Power and Control Cable, Continuity and
SATR-P-3203 4-Mar-19 ELECT- 674
Megger Insulation Resistance Testing

Saudi Aramco: Company General Use