Appendix C1 - Geotech Assessment Report
Appendix C1 - Geotech Assessment Report
SITE INVESTGATION
FINAL REPORT
14 March 2023
Report Ref.: 1281
Prepared for:
ENERGY SYSTEMS PLANNING (PTY) LTD
Parkwood, Johannesburg
GEOTECH
(SWAZILAND) (PTY) LTD
CONSULTING ENGINEERING GEOLOGISTS AND GEOLOGISTS
Tel and Fax: (+268) 404 6775; cell (+268) 607 5825
E-mail: [email protected]
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
CONTENTS Page
1 INTRODUCTION ……….................................... 1
1.1 Appointment. ................................................. 1
1.2 Scope of Works . ................................................. 1
1.3 General Methodology. ................................................. 1
1.4 Site Location. ………………………………. 1
1.5 Climate. .................................................. 2
1.6 Limitations of Assessment. .................................................. 3
Geotech (Swaziland) (Pty) Ltd Report Ref: 1181 (February 2023) Page i
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
LIST OF FIGURES
Figure 1.1: Google Earth image showing the location of Solar 1 and 2 sites.
Figure 2.1: Google Earth image showing the Solar 1 site.
Figure 2.2: Geological map of the Solar 1 and 2 sites.
Figure 2.3: Google Earth image showing the Solar 2 site.
Figure 2.4: Google Earth image (2014) showing the location of the water delivery canal.
Figure 4.1: Solar 1 site test pit locations and numbering.
Figure 5.1: Solar 2 site test pit locations and numbering.
Figure 6.1: Solar 1 schematic presentation of the soil profiles.
LIST OF TABLES
Table 2.1: Geology of the Solar 1 and Solar 2 sites.
Table 3.1: Various classification and geotechnical soil parameters captured from previous reports.
Table 4.1: Solar 1 site test pit co-o-ordinated positions.
Table 4.2: Solar 1 site brief generalised layer descriptions of the soil and rock horizons encountered.
Table 4.3: Solar 1 site summary of the soil horizons encountered and their depths.
Table 4.4: Solar 1 site summary of the soil classification test results.
Table 4.5: Solar 1 site summary of the laboratory soil compaction and CBR test results.
Table 5.1: Solar 2 sire test pit co-o-ordinated positions.
Table 5.2: Solar 2 site brief generalised layer descriptions of the soil and rock horizons encountered.
Table 5.3: Solar 2 site summary of the soil horizons encountered and their depths.
Table 5.4: Solar 2 site summary of the soil classification test results.
Table 5.5: Solar 2 sire summary of the laboratory soil compaction and CBR test results.
Table 6.1: Solar Site 1 potential hazards and associated risks.
Table 6.2: Solar Site 2 potential hazards and associated risks.
Table 7.1: Comparison of the Solar 1 and Solar 2 sites.
LIST OF PLATES
Plate 2.1: Photograph of the water delivery canal looking east.
Plate 2.2: Photograph of the water delivery canal looking west
LIST OF APPENDICIES
Appendix 1: Test pit profile sheets and photographs of the excavated test pits.
Appendix 2: Laboratory soil classification test results.
Appendix 3: Site photographs.
Appendix 4: Schematic presentation of geological and geotechnical soil profiles.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1181 (February 2023) Page ii
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
1 INTRODUCTION
1.1 Appointment
Royal Eswatini Sugar Corporation (RES) proposes to construct a 10MW solar PV plant at Mhlume
Sugar Mill. They have appointed Energy System Planning (ESP) to undertake consulting services
relating to the Project.
ESP has appointed Geotech (Swaziland) (Pty) Ltd as a sub-consultant to provide Sub-Consultancy
Services relating to the geotechnical input requirement. The effective date of the Contract being 13
February 2023.
• Undertake a comprehensive desk study and site walkover with limited fieldwork and laboratory
testing to evaluate the risks and benefits of both sites.
• To compile a feasibility report on the geotechnical aspects of each site.
• Desk study. To capture and review available geological and geomorphological data to
formulate an initial geotechnical site plan and to identify potential problematic areas and sites
for limited field investigation.
• Field investigation. To undertake an intrusive investigation by the excavation of test pits at key
points identified from the desk study. To determine the prevailing subsoil conditions and soil
profile characteristics by visual inspection and profiling, and to take representative samples for
laboratory soil testing.
• Reporting. To compile a comprehensive factual interpretative report (geotechnical evaluation)
of each solar plant site. The report will contain all information gathered from the desk study
and all data collected from the fieldwork and laboratory testing and any associated photography.
Two sites were investigated, these being referred to as RES Solar 1 and RES Solar 2. Their general
locations are shown on Figure 1.1.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 1
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
Figure 1.1: Google Earth image showing the location of Solar 1 and 2 sites.
1.5 Climate
The sites lie within the Lowveld climatic zone. The climate is characterised by hot summers and mild
dry winters with annual temperatures varying from 17 to 32°C.
Most rainfall occurs from October to April with a mean annual precipitation of about 550mm.
Climate generally determines the mode of weathering. The effect of climate on the weathering process
with respect to soil formation is determined by the climatic N-value defined by Weinert.
The N-value for the site area is approximately 2. A climatic N-value of <5 is associated with humid
warm areas where chemical decomposition is the predominant rock weathering process.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 2
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
1.6 Limitations of Assessment
The information contained within this factual report relates to the positions at which the test pits were
excavated, insitu test conducted and to the associated recorded visual observations as they existed at
the time of the investigation.
It has been assumed that the assembled data including the laboratory soil test results are generally
representative of the whole site, and this report has been compiled based on this assumption. However,
soils are rarely homogeneous and conditions at variance with those described in this report may arise.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 3
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
2 DESKTOP STUDY AND SITE WALKOVER
Contours were draw on the site map using ground levels taken from Google Earth imagery see Figure
2.1. The site topography falls to the east at rates varying from about 1 in 35 to 1 in 59.
There are no natural water courses, wetlands or springs on the site, however irrigation associated with
the cultivation of sugar cane is likely to lead to fluctuating subsoil soil moisture conditions. It is
considered to be quite likely that occurrences of a man-made / induced shallow perched water conditions
will exist.
The site is covered by sugar cane which is usually an indication of the presence of a rich dark brown to
black clay topsoil.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 4
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
2.1.2 Geology
The geological map of the area at a scale of 1:50,000 (sheet 8) produced by the Government of Eswatini
and published in 1980, is reproduced as Figure 2.2.
The geological map suggests that the Solar 1 site area is likely to be underlain rocks belonging to the
Ecca Group which is part of the Karoo Super Group, and in particular geological unit K2.
The Ecca Group unit K2 comprises of sandstone and claystone with some thin coal horizons. The
sandstones are commonly feldspathic and micaceous.
Dolerite dykes and sills are present throughout the Karoo sedimentary sequence. These have been
mostly intruded post Karoo and belong to a N-S striking swarm. The intensity of the dolerite intrusions
is not well known due to a general lack of rock outcrops.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 5
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
The geological map suggests that the Solar 1 site will be predominately underlain by sandstone and
claystone with subordinate occurrences of dolerite.
According to the latest 2023 Google Earth imagery, the Solar 2 site is greenfield and is covered by
dense natural lowveld vegetation. However, it was noticed during the site walkover that a water
conveyance canal crosses the site, refer to Section 2.2.3 below.
Contours were draw on the site map using ground levels taken from Google Earth imagery see Figure
2.2. The site topography generally falls the SSE, but transitions to the E along the eastern site boundary
at rates varying of generally about 1 in 40 to 1 in 65. Some areas are steeper with falls of about 1 in 19.
There was no evidence of rock outcrop on the site, although the bush is dense limiting visibility. The
presence of some rock outcrop occurring should not be ruled out.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 6
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
2.2.2 Geology
The geological conditions at the Solar 2 site are considered to be very similar to those at the Solar 1
site. Refer to section 2.1.2 above and replace test references to Solar 1 with Solar 2.
During the site walkover it was noticed that there is a water conveyance canal running through the site.
This is not visible on the latest Feb 2023 Google Earth image. Photographs of the canal were taken to
show its general appearance see Plate 2.1 and Plate 2.2 taken from the same location looking east and
west.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 7
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
The canal has an access road running immediately adjacent to it on its southern side.
The position of the canal is visible on the 2014 Google Earth image, see Figure 2.4.
Figure 2.4: Google Earth image (2014) showing the location of the water delivery canal.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 8
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
3 REVEIW OF EXISTING GEOTECHNICAL REPORTS
Existing geotechnical reports in the Mhlume area that have been carried out in the K2 geological domain
suggest that:
• Tractor-Loader-Backhoe (TLB) excavated test pits usually refuse at depths of less than 3.0m.
• Typical soil profiles consist in descending order of occurrence of topsoil, colluvial soil and
various insitu soils derived from the weathering of sandstone, claystone and dolerite.
• Dolerite may be more prevalent than shown on the geological map of the area.
Various classification and geotechnical soil parameters have been captured from the previous reports
and are presented in Table 3.1.
Parameter Colluvial Soil Soil Derived from Soil Derived from Soil Derived from
Claystone Sandstone Dolerite
Clay content (%) Range: 4-45 Range: 6-47 Range: 9-34 Range: 13-40
Average: 26.6 Average: 20.9 Average: 16.1 Average: 29.0
Dry density (kg/m³) Range: 1268-1745 Range: 1447-1684 Range: 1549-1638 Range: 1537-1588
Average: 1556 Average: 1536 Average:1590 Average: 1563
AASHTO A-6 and A-7-5/A-7-6 A-6 and A-7-5/A-7-6 A-6 and A-7-6 A-7-5/A-7-6 and A6
classification
TRH14 classification G10, <G10 and G6 G8, G10 and <G10 G10, G9 and G7 <G10
Potential 50% Low 38% Low 33% Low 31% Low
expansiveness. 50% Medium 53% Medium 67% Medium 63% Medium
9% High 6% High
Void Ratio Range: 0.490-1.136 0.649 No data No data
Average: 0.702
Free swell (%) Range 0.2-5.1 1.4 No data No data
Average: 1.35
Swell pressure (kPa) Range: 12-106 Range: 52-97 38 20
Average: 37.1 Average: 75
Table 3.1: Various classification and geotechnical soil parameters captured from previous reports.
These test results indicate that the K2 soils derived from the weathering of claystone, sandstone and
dolerite can be expected top be problematic. They are generally:
The K2 soils are further expected to be problematic with regards to foundations and special precautions
may be necessary, and with respect to shallow piled foundations which are typically driven to 2 to 3m
depth.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 9
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
4 SOLAR 1 FIELD INVESTIGATION
The site investigation was conducted on the 24th February 2023.Test pits were excavated using a TLB
(JCB 3DX) hired from Dyson and Lincoln (Pty) Ltd, Siteki. Each test pit was profiled by a professional
engineering geologist in accordance with the methods stipulated by Williams, Jennings & Brink, 1973
and by referring to “Guidelines for Soil and Rock Logging in SA”: AEG – SA Section Geoterminology
Workshop 1990.
A total of six test pits were excavated, these being spread over the site to give a representative coverage,
see Figure 4.1 for test pit locations.
The test pit positions were co-ordinated using a hand-held Garmin GPSmap 62SC, see Table 4.1.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 10
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
4.2 Soil profile Encountered
The soil profile encountered within the test pits was found to be reasonably uniform and in broad terms
comprised, in descending order of occurrence, of the following horizons:
• Fill. Used on the farm roads to increase trafficability around the sugar cane fields.
• Topsoil and colluvial soil.
• Completely weathered soil derived from claystone or completely weathered soil derived from
sandstone.
• Claystone rock or sandstone rock.
A summary of the occurrence of the horizons encountered within each test pit is given in Table 4.3.
Test Pit Soil and Rock Horizons and Depths (m) Remarks
Fill. Topsoil Colluvium CW CW Claystone Sandstone
claystone sandstone
RES 1.1 0.0-0.2 0.2-0.6 - - 0.6-1.3 - 1.3 Refusal 1.3m on sandstone.
RES 1.2 0.0-0.2 - 0.2-0.9 0.9-2.8 - 2.8-3.0 - End at 3.0m.
RES 1.3 0.0-0.2 0.2-0.4 - 0.4-1.2 1.2-2.5 - 2.5-3.0 End at 3.0m.
RES 1.4 0.0-0.3 0.3-0.5 - 0.5-1.5 - 1.5-3.0 - End at 3.0m.
RES 1.5 0.0-0.2 0.2-0.4 - - 0.4-1.1 - 1.1 Refusal 1.1m on sandstone.
RES 1.6 0.0-0.2 0.2-0.4 - 0.4-2.2 - 2.2-3.0 - End at 3.0m.
CWGd: Completely weathered granodiorite soil. HWGd: Highly weathered granodiorite soil.
Table 4.3: Solar 1 site summary of the soil horizons encountered and their depths.
See also the test pit location plan and profile sheets Figures A1.1 to A1.7 in Appendix 1.
Representative disturbed soil samples were taken from the various soil horizons encountered. This was
limited to a total of 3 samples for this feasibility study. The soil tests conducted on each sample were:
• Grading analysis.
• Hydrometer analysis.
• Atterberg Limit determination.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 11
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
• Modified AASHTO compaction (maximum dry density and optimum moisture content).
• California Bearing Capacity (CBR).
Table 4.4: Solar 1 site summary of the soil classification test results.
A summary of the compaction and CBR test results is presented in Table 4.5 below.
4.4 Groundwater
Groundwater was encountered within test pits 1.3 and 1.6. This occurred as sporadic, discrete seepage
zones within the soil profile. These seepage zones occurred between 0.4 to 1.2 and 2.5 to 3.0m in test
Pit 1.3; and between 0.4 to 1.5 and 2.1 to 2.2m in test pit 1.6.
Rock joint surfaces in test pits 1.3 and 1.6 were found to be wet below 2.5m (sandstone) and 2.2 m
depth (claystone) in these test pits respectively.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 12
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
5 SOLAR 2 SITE INVESTIGATION
The site investigation was conducted on the 24th February 2023.Test pits were excavated using a TLB
(JCB 3DX) hired from Dyson and Lincoln (Pty) Ltd, Siteki. Each test pit was profiled by a professional
engineering geologist in accordance with the methods stipulated by Williams, Jennings & Brink, 1973
and by referring to “Guidelines for Soil and Rock Logging in SA”: AEG – SA Section Geoterminology
Workshop 1990.
A total of six test pits were excavated, these being spread over the site to give a representative coverage,
see Figure 5.1 for test pit locations.
The test pit positions were co-ordinated using a hand-held Garmin GPSmap 62SC, see Table 5.1.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 13
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
5.2 Soil profile Encountered
The soil profile encountered within the test pits was found to be derived from three different parent
rocks, namely sandstone, dolerite and shale, and in broad terms comprised, in descending order of
occurrence, of the following horizons:
A summary of the occurrence of the horizons encountered within each test pit is given in Table 5.3.
Test Pit Soil and Rock Horizons and Depths (m) Remarks
Fill. Topsoil CW CW -HW CW Shale Sand- Dolerite
Shale Sandstone dolerite stone
RES 2.1 - 0.0-0.4 0.4-2.4 - - 2.4-3.0 - - End at 3.0m.
RES 2.2 - 0.0-0.2 - - 0.2-0.8 - - 0.8-2.3 Refusal 2.3m on dolerite.
RES 2.3 - 0.0-0.4 - - 0.4-1.5 - - 1.5-2.1 Refusal 2.1m on dolerite.
RES 2.4 0.0-0.2 0.2-0.5 - 0.5-3.3 - - - - End at 3.0m.
RES 2.5 - 0.0-0.3 - 0.3-1.5 - - 1.5-2.0 - Refusal 2.0m on sandstone.
RES 2.6 - 0.0-0.3 - 0.3-1.1 - - 1.1-1.3 - Refusal 1.3m on sandstone.
CW: Completely weathered. HW: Highly weathered.
Table 5.3: Solar 2 site summary of the soil horizons encountered and their depths.
See also the test pit location plan and the profile sheets Figures A1.8 to A1.14 in Appendix 1.
Representative disturbed soil samples were taken for the various soil horizons encountered. This was
limited to a total of 3 samples for this feasibility study. The soil tests conducted on each sample were:
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 14
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
• Grading analysis.
• Hydrometer analysis.
• Atterberg Limit determination.
• Modified AASHTO compaction (maximum dry density and optimum moisture content).
• California Bearing Capacity (CBR).
Table 5.4: Solar 2 site summary of the soil classification test results.
A summary of the compaction and CBR test results is presented in Table 4.5 below.
5.4 Groundwater
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 15
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
6 GEOTECHNICAL EVALUATIONS OF THE TWO SITES
A summary of the geological and Geotechnical conditions encountered is shown on the schematic
presentation Figure 6.1.
The following observations regarding the soil profile encountered are made:
• Soil derived from the weathering of the claystone and sandstone are considered to be potentially
expansive. Historical data suggests that some 50 to 67% of these soils are likely to be of medium
to high potential expansiveness.
• Limited soil testing (3 tests) from the site suggests that the soils are likely to be of A-6 / CL
classification, and be of Low (33% of samples) to Medium (66% of samples) potential
expansiveness.
• Soil derived from the weathering of the claystone and sandstone in terms of subgrade strength
is generally considered to be poor. Historical data suggests that these soils are likely to of
mainly G10 to unclassified classification (TRH14).
• Limited soil testing (2 tests) from the site suggests that the soils are likely to be unclassified in
relation to the TRH14 specification.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 16
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
• Rock was encountered in all test pits at depths ranging from 1.1 to 2.8m depth. The sandstone
encountered was mainly soft to medium hard rock, while the claystone was very soft to soft
rock.
Appraisal of the site in terms of potential hazards / risks is presented in Table 6.1.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 17
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
A summary of the geological and Geotechnical conditions encountered is shown on the schematic
presentation Figure 6.2.
The following observations regarding the soil profile encountered are made:
• Soil derived from the weathering of the claystone (or shale), sandstone and dolerite is
considered to be potentially expansive. Historical data suggests that some 50 to 67% of these
soils are of medium to high potential expansiveness.
• Limited soil testing (3 tests) from the site suggests that the soils are likely to be quite variable
and be of A-6 /CL, A-2-6/SC and A-1-b /SCL classification, and be of Low potential
expansiveness.
• Soil derived from the weathering of the claystone (and shale), sandstone and dolerite in terms
of subgrade strength is generally considered to be poor. Historical data suggests that these soils
are likely to be of mainly G10 to <G10 classification (TRH14).
• Limited soil testing (2 tests) from the site suggests that the soils are likely to vary from G9 to
unclassified in relation to the TRH14 specification.
• Rock was encountered in five of the six test pits test pits at depths ranging from 0.8 to 2.4m
depth. The shale encountered was soft rock, the sandstone was mainly medium hard rock, while
the dolerite was mainly hard rock.
• Excavation of the hard rock dolerite was possible due to it being closely jointed.
• TLB refusal during excavation occurred at depths ranging from 1.3 to 2.8m, while two test pits
were terminated at 3.0 and 3.3m without refusal occurring.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 18
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
Appraisal of the site in terms of potential hazards / risks is presented in Table 6.2.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 19
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
7 CONCLUSIONS AND RECOMMENDATIONS
A comparison of the two sites for various parameters based on data collected from this investigation is
presented in Table 7.1.
Both the Solar 1 and Solar 2 sites are very similar in terms of geology and geotechnical considerations
based on the parameters presented in Table 7.1.
Solar site 1 is more favourable in terms of site orientation, site steepness and environmental
considerations.
Site 1 appears to be more at risk from the presence of potentially expansive soils, however site 2 is
considerably more variable in terms of the soil profile physical characteristics. Other than this both sites
are remarkably similar.
A significant disadvantage of the Solar 2 site is the presence of the canal and its wide servitude which
splits the site into two elongated sections.
The canal access road running along the south side of the canal and the unvegetated servitude are likely
to present a dust hazard to the solar panels.
Based solely on the observations and data collected in compiling this report, and the objectives of the
report itself, it is concluded that SOLAR SITE 1 be the recommended site.
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 20
Feasibility Study for the Proposed RES 10MW Solar PV Plant
Shallow Geotechnical Investigation
_________________________________________________________________________________
Geotech (Swaziland) (Pty) Ltd Report Ref: 1163 (September 2019) Page 21
APPENDIX 1
TEST PIT PROFILE SHEETS AND ASSOCIATED PHOTOGRAPHS
Figure A1.1: Solar 1 site showing test pit locations and numbering.
DCP Penetration (blow/10cm)
Location: See Figure A1.1. TEST PIT No.: RES 1.1
Soil Depth
0 10 20 sample
Lith-ology
(m)
Soil / Rock Description Remarks
0
Loose, intact, clayey gravel. Contains numerous small plant roots.
0.2 Slightly moist, light yellowish orange, gravel roadbed.
Firm, intact, silty sand. Contains numerous small plant roots.
Moist, dark brown, topsoil.
0.6
Medium dense, intact, clayey gravel. Contains occasional small plant roots.
Moist, dark reddish orange mottled dark red,
highly weathered sandstone.
-1
1.3
Refusal on sandstone rock.
Depth (m)
-2
-3
-4
Machine: JCB 3DX super. Final test pit depth: End at 1.3m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: Slightly weathered, dark yellow, medium jointed, Groundwater: No.
Condition: Excellent. medium grained, medium hard rock SANDSTONE. Seepage: None.
Hired from: Dyson and Lincoln, Siteki DCP testing from: Not undertaken. Inflow: None
0.9
Firm to stiff, intact, clay silt. Pocket pennetrometer190-220 kPa.
-1
Moist, dark olive, completely weathered claystone.
1.2.1
1.7
Stiff, intact, gravely clayey silt. Gravel comprised of mudstone fragments.
Depth (m)
Moist, light grey mottled dark reddish orange, Pocket penetrometer 260-300kpa
completely weathered claystone.
-2
1.2.2
2.8
Moderately weathered, light grey, closely jointed, Fractures iron stained and clay filled.
3.0 very fine grained, very soft to soft rock, CLAYSTONE.
-3 END. Required depth reached.
-4
Machine: JCB 3DX super. Final test pit depth: End at 3.0m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: No refusal. Groundwater: No.
Condition: Excellent. Seepage: None.
Hired from: Dyson and Lincoln, Siteki DCP testing from: Not undertaken. Inflow: None
-1
1.2
Firm, intact, sand silt clay with some gravel.
Wet, dark reddish orange, completely weathered sandstone.
Depth (m)
1.3.1
-2
2.5
Moderately weathered, dark olive, very closely jointed, Joint surfaces oxide stained, joints clay
fine to medium grained, soft rock SANDSTONE. filled and wet.
Some discrete seepage pockets.
3.0
-3
End. Required depth reached.
-4
Machine: JCB 3DX super. Final test pit depth: End at 3.0m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: No refusal. Groundwater: Yes.
Condition: Excellent. Seepage: Between 0.4 and 1.2m and 2.5 to 3.0m depth.
Hired from: Dyson and Lincoln, Siteki DCP testing from: Not undertaken. Inflow: None
0.9
Firm, intact, clayey silt.
-1
Moist, dark olive streaked dark grey, completely weathered
claystone.
1.5
Moderately weathered, light grey and dark grey, closely jointed, Joint surfaces oxide stained and clay filled.
very fine grained, very soft to soft rock, CLAYSTONE.
Depth (m)
-2
3.0
-3
End. Required depth reached.
-4
Machine: JCB 3DX super. Final test pit depth: End at 3.0m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: No refusal. Groundwater: No.
Condition: Excellent. Seepage: None.
Hired from: Dyson and Lincoln, Siteki DCP testing from: Not undertaken. Inflow: None
-2
-3
-4
Machine: JCB 3DX super. Final test pit depth: End at 1.1m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: Slightly weathered, light brown and light yellowish orange, Groundwater: No.
Condition: Excellent. medium jointed, medium to coarse grained, hard rock SANDSTONE. Seepage: None.
Hired from: Dyson and Lincoln, Siteki DCP testing from: Not undertaken. Inflow: None
-1
1.5
Stiff, intact, gravelly silty clay. Seepage at base 2.1 to 2.2m depth.
Moist, dark grey blotched dark yellowish orange,
completely weathered claystone.
Depth (m)
-2
2.2
Moderate to slightly weathered, dark grey and olive, Joint surfaces oxide stained and clay filled.
closely jointed, very fine grained, soft rock CLAYSTONE. Some joints wet.
3.0
-3
End. Required depth reached.
-4
Machine: JCB 3DX super. Final test pit depth: End at 3.0m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: No refusal. Groundwater: No.
Condition: Excellent. Seepage: Between 0.4 and 1.5m and 2.1 to 2.2m depth.
Hired from: Dyson and Lincoln, Siteki DCP testing from: Not undertaken. Inflow: None
0.4
Firm, intact, clay silt. Contains some plant roots and threads.
Moist, dark yellowish orange mottled dark olive,
completely weathered shale.
-1
1.2
Medium dense, very closely jointed, silty gravel.
Slightly moist, dark yellowish orange layered light grey,
highly weathered shale.
2.1.1
Depth (m)
-2
2.4
Moderately weathered, light grey laminated dark yellowish Joint surfaces oxide stained and coated
orange and dusky red, closely jointed, fine grained, laminated, with silty clay.
soft rock SHALE.
3.0
-3
End. Required depth reached.
-4
Machine: JCB 3DX super. Final test pit depth: End at 3.0m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: No refusal. Groundwater: No.
Condition: Excellent. Seepage: None.
Hired from: PSK plant hire, Siteki DCP testing from: Not undertaken. Inflow: None
0.8
Slightly weathered, dusky blue, closely jointed, medium grained, Joint surfaces oxide stained with some
hard rock DOLERITE. clay film on joints and some joint infill.
-1
Depth (m)
-2
2.3
Refusal on dolerite rock.
-3
-4
Machine: JCB 3DX super. Final test pit depth: End at 2.3m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: Slightly weathered, dusky blue, closely jointed, medium Groundwater: No.
Condition: Excellent. grained, hard rock dolerite. Seepage: None.
Hired from: PSK plant hire, Siteki DCP testing from: Not undertaken. Inflow: None
0.4
Firm, intact, clayey gravel. Contains some plant roots.
Moist, dark reddish orange, completely weathered dolerite.
-1
1.5
Slightly weathered, dusky blue, closely jointed, Joint surfaces oxide stained with some
medium grained, hard rock DOLERITE. clay film.
Depth (m)
-2
2.1
Resusal on dolerite rock.
-3
-4
Machine: JCB 3DX super. Final test pit depth: End at 2.1m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: Slightly weathered, dusky blue, closely jointed, medium Groundwater: No.
Condition: Excellent. grained, hard rock DOLERITE. Seepage: None.
Hired from: PSK plant hire, Siteki DCP testing from: Not undertaken. Inflow: None
1.4
Medium dense, intact, sandy gravel. Contains some irregular calcrete nodules.
Slightly moist, dark yellowish orange, highly weathered
sandstone.
Depth (m)
-2
2.4.1
-3
3.3
End. Required depth reached.
-4
Machine: JCB 3DX super. Final test pit depth: End at 3.3m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: No refusal. Groundwater: No.
Condition: Excellent. Seepage: None.
Hired from: PSK plant hire, Siteki DCP testing from: Not undertaken. Inflow: None
0.7
Stiff, intact, sand silt clay.
Slightly moist, dark olive, completely weathered sandstone.
-1
1.5
Slightly weathered, light brown, closely jointed, medium Joint surfaces oxide stained.
grained, medium hard rock SANDSTONE.
Depth (m)
2.0
-2
Refusal on sandstone rock.
-3
-4
Machine: JCB 3DX super. Final test pit depth: End at 2.0m Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: Slightly weathered, light brown, closely jointed, Groundwater: No.
Condition: Excellent. medium grained, medium hard rock SANDSTONE. Seepage: None.
Hired from: PSK plant hire, Siteki DCP testing from: Not undertaken. Inflow: None
-1
1.1
Slightly weathered, dark red, closely jointed, laminated to thinly
1.3 bedded, medium grained, medium hard rock SANDSTONE.
Refusal on sandstone rock.
Depth (m)
-2
-3
-4
Machine: JCB 3DX super. Final test pit depth: End at 1.3m. Test pit stability: Side walls stable during excavation.
Bucket width: 0.6 m. Refusal on: Slightly weathered, dark red, closely jointed, laminated to Groundwater: No.
Condition: Excellent. thinly bedded, medium grained, medium hard rock SANDSTONE. Seepage: None.
Hired from: PSK plant hire, Siteki DCP testing from: Not undertaken. Inflow: None
FOUNDATION INDICATOR AND CBR TEST RESULTS TEST PIT No.: RES 1.2
Client: Energy System Planning (Pty) Ltd. Sample No.: 1.2.1 Date: March 2023
Project: Royal Eswatini Sugar - Solar 1 and 2 Sites. Sample Depth: 0.9-1.7m. Job No.: 1281
Percentage Passing
53
37.5 60
26.5
19 40
13.2 100
4.75 98
20
2.00 96
0.425 83
0.075 54 0
0.001 0.01 0.1 1 10 100
Particle Size (mm)
60 60
Very High CV
50 50
PI of Whole Sample
CH
40 40
Plasticity Index
High
MV
30 Medium 30 CI
MH
20 20
CL MI
10 Low
10
S
ML
0 0
0 20 40 60 80 0 20 40 60 80
FOUNDATION INDICATOR AND CBR TEST RESULTS TEST PIT No.: RES 1.2
Client: Energy System Planning (Pty) Ltd. Sample No.: 1.2.2 Date: March 2023
Project: Royal Eswatini Sugar - Solar 1 and 2 Sites. Sample Depth: 1.7-2.8m. Job No.: 1281
Percentage Passing
53
37.5 60
26.5
19 40
13.2
4.75
20
2.00 100
0.425 98
0.075 88 0
0.001 0.01 0.1 1 10 100
Particle Size (mm)
60 60
Very High CV
50 50
PI of Whole Sample
CH
40 40
Plasticity Index
High
MV
30 Medium 30 CI
MH
20 20
CL MI
10 Low
10
S ML
0 0
0 20 40 60 80 0 20 40 60 80
FOUNDATION INDICATOR AND CBR TEST RESULTS TEST PIT No.: RES 1.3
Client: Energy System Planning (Pty) Ltd. Sample No.: 1.3.1 Date: March 2023
Project: Royal Eswatini Sugar - Solar 1 and 2 Sites. Sample Depth: 1.2-2.5m. Job No.: 1281
Percentage Passing
53
37.5 60
26.5
19 40
13.2 100
4.75 98
20
2.00 93
0.425 85
0.075 61 0
0.001 0.01 0.1 1 10 100
Particle Size (mm)
60 60
Very High CV
50 50
PI of Whole Sample
CH
40 40
Plasticity Index
High
MV
30 Medium 30 CI
MH
20 20
CL MI
10 Low
10
S ML
0 0
0 20 40 60 80 0 20 40 60 80
MDD (kg/m³)
OMC (%)
CBR %
CBR
1
90 92 94 96 98 100
% Compaction
THR14 Specification: No data.
COLTO Specification: No data.. Figure: A2.3
P.O. Box 1376, Mbabane, Swaziland Cell: +268 76075825
Geotech ( Swaziland) (Pty) Ltd Landline: +268 24046775 e mail: [email protected]
FOUNDATION INDICATOR AND CBR TEST RESULTS TEST PIT No.: RES 2.1
Client: Energy System Planning (Pty) Ltd. Sample No.: 2.1.1 Date: March 2023
Project: Royal Eswatini Sugar - Solar 1 and 2 Sites. Sample Depth: 1.2-2.4m Job No.: 1281
Percentage Passing
53
37.5 100 60
26.5 93
19 74 40
13.2 71
4.75 59
20
2.00 51
0.425 40
0.075 26 0
0.001 0.01 0.1 1 10 100
Particle Size (mm)
60 60
Very High CV
50 50
PI of Whole Sample
CH
40 40
Plasticity Index
High
MV
30 Medium 30 CI
MH
20 20
CL MI
10 Low
10
S ML
0 0
0 20 40 60 80 0 20 40 60 80
FOUNDATION INDICATOR AND CBR TEST RESULTS TEST PIT No.: RES 2.4
Client: Energy System Planning (Pty) Ltd. Sample No.: 2.4.1 Date: March 2023
Project: Royal Eswatini Sugar - Solar 1 and 2 Sites. Sample Depth: 1.4-3.3m Job No.: 1281
Percentage Passing
53
37.5 60
26.5
19 100 40
13.2 99
4.75 98
20
2.00 96
0.425 84
0.075 50 0
0.001 0.01 0.1 1 10 100
Particle Size (mm)
60 60
Very High CV
50 50
PI of Whole Sample
CH
40 40
Plasticity Index
High
MV
30 Medium 30 CI
MH
20 20
CL MI
10 Low
10
S ML
0 0
0 20 40 60 80 0 20 40 60 80
FOUNDATION INDICATOR AND CBR TEST RESULTS TEST PIT No.: RES 2.4
Client: Energy System Planning (Pty) Ltd. Sample No.: 2.4.2 Date: March 2023
Project: Royal Eswatini Sugar - Solar 1 and 2 Sites. Sample Depth: 0.7-1.4m Job No.: 1281
Percentage Passing
53
37.5 60
26.5
19 40
13.2 100
4.75 96
20
2.00 88
0.425 46
0.075 18 0
0.001 0.01 0.1 1 10 100
Particle Size (mm)
60 60
Very High CV
50 50
PI of Whole Sample
CH
40 40
Plasticity Index
High
MV
30 Medium 30 CI
MH
20 20
CL MI
10 Low
10
S ML
0 0
0 20 40 60 80 0 20 40 60 80
MDD (kg/m³)
OMC (%)
CBR %
CBR
1
90 92 94 96 98 100
% Compaction
THR14 Specification: No data.
COLTO Specification: No data.. Figure: A2.6
APPENDIX 3
SITE PHOTOGRAPHS
Plate A3.1: Central site road looking west. Plate A3.2: Central site road looking east from
same location as Plate A3.1.
See Plates 2.1 and 2.2 on page 7 of the report text for photographs of the Solar 2 site area.
APPENDIX 4
GENERAL PROCEDURES AND DESCRIPTIVE TERMINOLOGY
TEST PIT PROFILING PROCEEDURES AND GEOTERMINOLOGY
The procedures and methods used in the profiling of test pits generally adhered to the following:
* Jennings et al: "Soil profiling for civil engineering purposes in Southern Africa". Transactions
of the SAICE Jan 1973.
* Geological Society of London: " Working party report. The logging of rock cores for engineering
purposes:. QJEG, V3
* "A guide to core logging for rock engineering": Proceedings of the Symposium for Rock
Engineering, Nov. 1976.
* "Guideline for soil and rock logging in South Africa". 2 nd Impression. A.B.A Brink and
R.M.H. Bruin, Proceedings, Geoterminology Workshop organised by AEG, SAICE and
SAIEG, 1990.
Page A4.i
SOIL STRUCTURE
INTACT No structure present.
FISSURED Presence of discontinuity planes open or closed, stained or unstained.
SLICKENSIDED Very smooth or glossy often stained discontinuity planes.
SHATTERED Presence of open fissures. Soil breaks into gravel sized blocks.
MICRO-SHATTERED Small scale shattering, very closely spaced open fissures. Soil breaks into sand sized crumbs.
RESIDUAL STRUCTURES Relict bedding, lamination, foliation etc.
PINHOLED Voids or pores (<2mm), hand lens may be needed.
HONEYCOMBED Similar to pin-holed but >2mm (specify size).
Matrix: Clasts supported by matrix.
SUPPORTED
Clast: Clasts touching (with or without matrix).
SOIL ORIGIN
TRANSPORTED Alluvium, hill wash, talus, etc.
RESIDUAL Weathered directly from parent rock with no subsequent transportation.
PEDOCRETES Ferricrete, laterite, silcrete, calcrete, etc.
DESCRIPTIONS OF PEDOCRETES
CALCRETE FERRICRETE SILCRETE DESCRIPTION
A soil which exhibits little to no nodule development or massive
cementation, but which contains some pedogenic mineralisation,
Calcareous Ferruginous -
but not sufficient to have indurated the soil significantly, or
affected soil consistencies.
Massive to platy soil which has been indurated by cementation
Calcified Ferruginised Silicified
to at least firm to stiff consistency.
Generally loose silt and fine sand consisting of cemented or
Powder Calcrete Powder Ferricrete -
aggregated particles of nearly pure pedogenic minerals.
Nodular Calcrete Nodular Ferricrete Noduar Silcrete Mixture of gravel sized nodules of cemented particles.
Partly amalgamated (fused) nodular pedocrete representing and
Honeycomb Calcrete Honeycomb Ferricrete Honeycomb Silcrete intergrade between nodular and hardpan variety. It may still contain
loose/soft pockets, but usually requires ripping for excavation.
Indurated and strongly cemented, massive, rock-like material.
Hardpan Calcrete Hardpan Ferricrete Hardpan Silcrete
Consistencies vary, but usually at least medium hard rock.
Page A4.ii
SIGNIFICANCE OF SOIL COLOUR
Black or dark colours Generally indicates high organic matter content.
Red colours Indicates good drainage and aeration, and results from the presence of iron oxide.
Reflects a moist soil climate. Is believed to be related to the crystalline state and not the amount of
Yellow colours
iron oxide present.
Usually indicates conditions of poor drainage or periodic saturation. The colour is believed to be that
Grey and light colours of the individual uncoated soil particles. Under such conditions the iron oxide has been leached away
or the percentage of silica and lime is high.
Dark grey, pale blue, and
Usually indicates the presence of wetland soils.
pale green colours
Reflects the accumulation of iron and manganese oxide in either poorly drained horizons or in zones
where the water table fluctuates. For example, under wet conditions the clay compound in the soil
Mottling
breaks up but the iron oxide remains and gives rise to red, yellow and brown mottles. Black centres
are usually manganese.
Page A4.iii
AASHTO CLASSIFICATION OF SOILS AND SOIL-AGGREGATE MIXTURES
Granular Materials Silt-Clay Materials
General Classification
(35% or less passing 0.075 mm) More that 35% passing 0.075 mm)
A-1 A-2 A-7-5
Group Classification A-3 A-4 A-5 A-6
A-1-a a-1-b A-2-4 A-2-5 A-2-6 A-2-7 A-7-6
Sieve Analysis Percent Passing
2.00 mm 50 max
0.425 mm 30 max 50 max 51 max
0.075 mm 15 max 25 max 10 max 35 max 35 max 35 max 35 max 36 min 36 min 36 min 36 min
Characteristic of Faction Passing
0.425 mm Liquid Limit 40 max 41 min 40 max 41 min 40 max 41 min 40 max 41 min
0.425 mm Plasticity Index 6 max NP 10 max 10 max 11 min 11 min 10 max 10 max 11 min 11 min
Usual Types of Significant Construction Stone fragments, Fine
Silty and clayey gravel sand soils Silty soils Clayey soils
Materials gravel and sand sand
Grading Rating as Sub-grade Excellent to good Fair to poor
Plasticity index of A-7-5 subgroup is equal to of less than LL minus 30.
Plasticity index of A-7-6 subgroup is greater than LL minus 30.
Page A4.iv
CLASSIFICATION OF NATURAL MATERIALS FOR PAVEMENT CONSTRUCTION (THR 14)
TRH14 Classification G4 G5 G6 G7 G8 G9 G10
Base Sub-base
Selected layer
Sub-grade
Liquid Limit (maximum). 25 30
Plasticity Index (maximum). 6 10 12 12
Linear shrinkage (%) (maximum). 3 5
Linear shrinkage x % passing 0.425 sieve.
Grading modulus. >1.5 >1.2 >0.75 none none none
Min. CBR (%) at 98% mod. AASTHO density. 80
Min. CBR (%) at 95% mod. AASTHO density. 45
Min. CBR (%) at 93% mod. AASTHO density. 25 15 10 7 3
Max. swell (%) at 100% mod. AASTHO density 1.0 1.5 1.5 1.5 1.5
GM+10
GM+10
GM+10
GM+10
Plasticity Index (maximum. 6 10
or 3x
or 3x
or 3x
or 3x
Linear shrinkage (%) (maximum). 3 5 5
Grading modulus 2.5-1.5 2.6-1.2 2.7-0.75 2.7-0.75 2.7-0.75
Min. CBR (%) at 98% mod. AASTHO density. 80
Min. CBR (%) at 95% mod. AASTHO density. 45
Min. CBR (%) at 93% mod. AASTHO density. 25 15 10 7
Max. swell (%) at 100% mod. AASTHO density 0.5 1.0 1.5 1.5 1.5
COLLAPSE POTENTIAL
Collapse Potential (%) Severity of Problem
0-1 No Problem.
1-5 Moderate trouble.
5-10 Trouble.
10-20 Severe trouble.
>20 Very severe trouble.
Rough guide by Jennings and Knight (1975).
Page A4.v
ROCK DESCRIPTIVE TERMS
ROCK TYPE
IGNEOUS: Granite, diorite, gabbro, dolerite, basalt rhyolite etc.
METAMORPHIC: Gneiss, quartzite, schist, slate, amphibolite, marble etc.
SEDIMENTARY: Sandstone, conglomerate, shale, claystone, mudstone, etc.
ROCK WEATHERING
Degree of Extent of Fracture (Joint) Surface Original
Grain Boundary Condition
Weathering Discolouration Condition Characteristics Fabric
UNWEATHERED None Closed to stained Unchanged Preserved Tight
Partial discolouration.
SLIGHTLY <20% of fracture spacing Discoloured may contain
Often unweathered rock Preserved. Tight.
WEATHERED on both sides of fracture. thin filling.
colour.
Partial / complete
MODERATELY 20% of fracture spacing on Discoloured may contain discolouration. Not friable
Preserved. Partial opening.
WEATHERED both sides of fracture. filling. except, poorly cemented
rocks.
COMPLETELY Partially
Throughout. Resembles a soil.
WEATHERED preserved. Complete separation. Easily indented
with knife. Slakes in water.
ROCK HARDNESS
Hardness Description UCS (MPa)
Material crumbles under firm blows of pick point. Can be peeled with a knife. Too hard to cut
VERY SOFT ROCK 1-3
triaxial sample by hand.
SOFT ROCK Firm blows with pick point produce 2 to 4mm indentations. Can just be scraped with a knife. 3-10
MEDIUM HARD ROCK Firm blows of pick head will break hand held specimen. Cannot be scraped or peeled with a knife. 10-25
GRAIN SIZE
Classification Size (mm) Recognition
VERY FINE GRAINED <0.2 Individual grains cannot be seen with a hand lens.
FINE GRAINED. 0.2-0.6 Just visible as individual grained under hand lens.
MEDIUM GRAINED 0.6-2 Grains clearly visible under hand lens, just visible to the naked eye.
COARSE GRAINED 06-Feb Grains clearly visible to the naked eye.
VERY COARSE GRAINED >6 Grains measurable.
DISCONTINUITY ORIENTATION
Discontinuity inclinations (i.e. of joints, bedding, faults) relative to down-axis of core (i.e. 90° = vertical and 0° = horizontal).
For orientated core, true azimuths are given.
Page A4.vi
DISCONTINUITY SPACING JOINT / DISCONTINUITY FILLING
Separation Spacing (foliation, Spacing (fractures, Infilling Definition (wall separation (mm)
(mm) cleavage, bedding) joints). CLEAN No fracture filling.
<6 Very intensely. Colouration on rock only. No recognisable filling
Extremely closely. STAINED
6-20 Intensely. material.
20-60 Very thinly Very closely. FILLED Filled with finite thickness of filling material.
60-200 Thinly Closely.
200-600 Medium Medium.
600-2000 Thickly. Widely.
>2000 Very thickly. Very widely.
Page A4.vii