CPM Report
CPM Report
1.4 Characteristics
1.8 Desventajas...................................................................................................................................5
IV. CONCLUSION.....................................................................................................................15
V. BIBLIOGRAPHY ...................................................................................................................16
I. CPM METHOD or CRITICAL PATH
1.1 Introduction
The CPM method or Critical Path is frequently used in development and control
projects. The main objective is to determine the duration of a project, understanding this
In this sense, the main assumption of CPM is that activities and their times of
durations are known, that is, there is no uncertainty. This simplifying assumption makes
that this methodology is easy to use and as much as one wants to see the impact of the
In this sense, the length of the critical path is equal to the longest trajectory of the project.
It is important to note that the duration of a project is equal to the critical path.
The CPM method was developed in the United States of America, as part of a
operational research program for the firm Dupont and Remington Rand, seeking
the control and optimization of operating costs through proper planning of the
all and each of the component activities of a project that must be developed
DECISION OPTIMIZATION 2
1.2 What is the CPM method?
adequate planning of the component activities of a project, that is, to plan the duration of a
project.
It is the sequence of the terminal elements of the project network with the longest duration.
among them.
1.4 Características
Establish relationships between activities. Decide which one should start first and which one should follow.
Identify the critical path and the float of the activities that make up the
project.
of precedence.
Use the diagram as a tool to plan, supervise, and control the project.
It is done in normal form. It is the maximum time to complete an activity with minimal use.
In resource, the normal time approaches the probable estimated time in PERT.
DECISION OPTIMIZATION 3
Crashing time: Time in the CPM that would be required if no cost is avoided with
such as reducing the project's time. Minimum possible time to complete an activity with
In CPM, only a time estimate is required. All calculations are done with the
assumption that the activity times are known. As the project progresses,
These estimates are used to control and monitor progress. If any delay occurs in
el proyecto, se hacen esfuerzos por lograr que el proyecto quede de nuevo en programa
The scope of application of this method is very broad and is suitable for large projects.
Dam construction.
Paving of roads.
Maintenance planning.
Computer programming.
Market research.
Expansion of factories.
Sales plans.
Population censuses.
DECISION OPTIMIZATION 4
1.7 Ventajas
It is easy to understand.
Cost saving.
1.8 Disadvantages
CPM
Consider that the times of the activities are known and can be varied.
DECISION OPTIMIZATION 5
Efforts are being made to ensure that the project is back on schedule.
Consider that the activities are continuous and interdependent, they follow a
chronological order and offers parameters for the right moment to start the
activity
PERT
independent, the variance of the project is the sum of the variances of the
pessimistic time.
DECISION OPTIMIZATION 6
II. REAL CASE
investment. A table of activities and the activity times that appear is presented.
continuation:
DECISION OPTIMIZATION 7
Network diagram with normal times and costs
Critical Path
DECISION OPTIMIZATION 8
Network diagram with accelerated times and costs
Critical Path
DECISION OPTIMIZATION 9
Comparative table of Normal costs vs Accelerated costs
COSTS
C. NORMALS C. ACCELERATED
100 140
80 120
120 150 Normal cost = $830
90 70 Costo acelerado = $1190
70 140
Diferencia en costos = $360
80 120
90 180
40 40
50 80
110 150
830 1190
EXERCISE 1:
Duration Activity
Activity
(sem) Predecessor
A 6 -
B 8 -
C 12 A,B
D 4 C
DECISION OPTIMIZATION
10
E 6 C
F 15 D,E
G 12 E
H 8 F,G
Considering the stages of the CPM method defined above, in this case it
You must develop steps 3 and 5. In this sense, it is necessary to build the diagram identifying
The relationships between the activities and to summarize the methodology will be incorporated.
Immediately the calculation of the Slack, IC, TC, IL, TL for each activity, along with the
identification of the critical path.
Then, the IC and TC indicators are identified for each activity. For example, for the
Activity C can start as soon as 8 (this is because C can only start once it is finished.
DECISION OPTIMIZATION
11
A and B, with B taking the longest and ending at 8) and the closest term being 20 (given
that activity C takes 12 weeks.
Subsequently, the IL and TL for each activity are obtained. With this information, the calculation
The slack of each activity is simple. To obtain the ES and LS of each activity we
We move from the end to the beginning. In this case, the activity that ends the latest is H.
(49 weeks) and therefore we wonder when is the latest that H could finish without delaying
the project (TL), this is clearly 49. Therefore, if the latest H can finish is 49,
The latest H can start to meet this time is 41 (since H lasts 8 weeks).
Then, the slack of H is zero. Note that the activities with slack equal to zero
correspond to the activities of the critical path. Additionally, a project may have
more than one critical path.
In our example, the critical path (the only one) is made up of the activities B-C-E-F.
With a total duration of 49 weeks.
EXERCISE 2:
DECISION OPTIMIZATION
12
SOLUTION:
DECISION OPTIMIZATION
13
EXERCISE 3:
Now that in example 2 the network diagram for the project was developed
RAMOV, analyze the trajectories through the network. Determine which of them is the critical route and
How long is the completion of the project expected to take.
SOLUTION:
Next, identify the trajectories and calculate the duration of each trajectory.
The longest duration is 64 days, and it is the critical path, which determines the duration.
for the entire project, therefore, the project is expected to take 63 days to complete.
DECISION OPTIMIZATION
14
IV. CONCLUSIÓN
control of each and every one of the component activities of a project that must
The CPM method is one of the systems that follow the principles of networks and is
DECISION OPTIMIZATION
15
V. BIBLIOGRAPHY
[Link]
[Link]
[Link]
DECISION OPTIMIZATION
16