REVIEW ORDER
The Design, Manufacture, Supply, Delivery,
Testing & Commissioning and Warranty of Additional
Nine (9) Sets of New 4-Car Trains
and Other Related Works for Monorail Line
August 2003 Monorail Trains in Kuala Lumpur.
6 sets 2-car and 5 sets 4-car
monorail
Existing Train will
be Supplemented
9 Sets 4-Cars Monorail
Tender with dateline:
December 4th 2017
PROJECT OVERVIEW
Object Remarks
Length 8.6 km
Number of 11 stations (existing)
Stations + 1 station (future)
Sultan Sulaiman
(Future)
GENERAL TECHNICAL SPECIFICATION
Object Remarks
The Design, Manufacture, Supply, Delivery, Testing & Commissioning
Project and Warranty of Additional Nine (9) Sets of New 4-Car Trains and
Other Related Works for Monorail Line
Amount 9 trainset with 4-cars
Seats 80 seats per train ~ 20 seats per car
Trainset
Capacity 430 Passenger, Seated and Standing (6 p/m2)
Performance 6450 passenger per hour per direction
Services 18 hours/day
Operational Round trip rime 50 minutes
Scenarios
Max. speed 55 km/h
Guideway beam 800 mm wide x 1600 to 2200 mm high
Mainline: 70 m radius
Horizontal Track
Alignment Depot : 50 m radius
Characteristics
Vertical Track Mainline: 1000 m radius
Mainline: max. 4,6%
Gradient
Depot. : max. 6%
FINANCIAL
Object Remarks
The Design, Manufacture, Supply, Delivery, Testing & Commissioning
Project and Warranty of Additional Nine (9) Sets of New 4-Car Trains and
Other Related Works for Monorail Line
Trainset 9 trainset with 4-cars
Tender Bond MYR 1 Million or ~ IDR 3,5 Billion
Total Offering Tender Price USD$ 50 Million or ~ IDR 700 Billion
Cash Flow 1st Year USD$ 12 Million or ~ IDR 168 Billion
Dateline December 4th, 2017
Scope for LEN/LRS Financial Partnership
1. Using Thales for Signaling System
Remarks 2. No issues for tender preparation except financing
3. Propose consortium scheme
SUMMARY
Consortium
PT LEN RAILWAY
RSC Sdn Bhd
SYSTEMS
Financial Partnership
- Tender Bond ~IDR 3.5 Billion
- Total tender ~IDR 700 Billion
(cash flow estimate 1st year ~ 168 Billion)