STRUCTURE METHODS
Zoning Area -
Sequence Of Work -
Column, Beam & Slab Methods -
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Zoning Area
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Zoning Area
CLASSROOM BUILDING
ZONE 2 ZONE 1
ZONE 3
COMMON & OFFICE
BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
1. EXCAVATION WORK ZONE 1
ROOF
ROOF 3RD FLOOR
2ND FLOOR 2ND FLOOR
1ST FLOOR 1ST FLOOR
PIT LEVEL PIT LEVEL
ZONE 3 ZONE 2 ZONE 1
COMMON & OFFICE BUILDING CLASSROOM BUILDING CLASSROOM BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
2. SUB STRUCTURE ZONE 1
3. EXCAVATION WORK ZONE 2
ROOF
ROOF 3RD FLOOR
2ND FLOOR 2ND FLOOR
1ST FLOOR 1ST FLOOR
`
PIT LEVEL PIT LEVEL
ZONE 3 ZONE 2 ZONE 1
COMMON & OFFICE BUILDING CLASSROOM BUILDING CLASSROOM BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
3. UPPER STRUCTURE 1ST FLOOR ZONE 1
4. SUB STRUCTURE ZONE 2
5. EXCAVATION WORK ZONE 3
ROOF
ROOF 3RD FLOOR
2ND FLOOR 2ND FLOOR
`
1ST FLOOR 1ST FLOOR
`
`
`
PIT LEVEL PIT LEVEL
ZONE 3 ZONE 2 ZONE 1
COMMON & OFFICE BUILDING CLASSROOM BUILDING CLASSROOM BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
6. UPPER STRUCTURE 2ND FLOOR ZONE 1
7. UPPER STRUCTURE 1ST FLOOR ZONE 2
8. SUB STRUCTURE ZONE 3
ROOF
ROOF 3RD FLOOR
`
2ND FLOOR 2ND FLOOR
`
`
`
1ST FLOOR 1ST FLOOR
`
`
`
`
`
PIT LEVEL PIT LEVEL
ZONE 3 ZONE 2 ZONE 1
COMMON & OFFICE BUILDING CLASSROOM BUILDING CLASSROOM BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
9. UPPER STRUCTURE 3RD FLOOR ZONE 1
10. UPPER STRUCTURE 2ND FLOOR ZONE 2
11. STRUCTURE SLAB 1ST FLOOR ZONE 3
ROOF
`
ROOF 3RD FLOOR
`
2ND FLOOR 2ND FLOOR
`
`
`
1ST FLOOR 1ST FLOOR
`
`
`
`
`
PIT LEVEL PIT LEVEL
ZONE 3 ZONE 2 ZONE 1
COMMON & OFFICE BUILDING CLASSROOM BUILDING CLASSROOM BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
12. UPPER STRUCTURE ROOF FLOOR ZONE 1
13. UPPER STRUCTURE 3RD FLOOR ZONE 2
ROOF
`
`
`
`
ROOF 3RD FLOOR
`
2ND FLOOR 2ND FLOOR
`
`
`
1ST FLOOR 1ST FLOOR
`
`
`
`
`
PIT LEVEL PIT LEVEL
ZONE 3 ZONE 2 ZONE 1
COMMON & OFFICE BUILDING CLASSROOM BUILDING CLASSROOM BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
14. UPPER STRUCTURE ROOF FLOOR ZONE 2
15. UPPER STRUCTURE 2ND FLOOR ZONE 3
ROOF
`
`
`
`
ROOF 3RD FLOOR
`
`
`
2ND FLOOR 2ND FLOOR
`
`
`
`
`
1ST FLOOR 1ST FLOOR
`
`
`
`
`
PIT LEVEL PIT LEVEL
ZONE 3 ZONE 2 ZONE 1
COMMON & OFFICE BUILDING CLASSROOM BUILDING CLASSROOM BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Sequence Of Work
16. UPPER STRUCTURE ROOF FLOOR ZONE 3
ROOF
`
`
`
`
ROOF 3RD FLOOR
`
`
`
2ND FLOOR 2ND FLOOR
`
`
`
`
`
1ST FLOOR 1ST FLOOR
`
`
`
`
`
PIT LEVEL PIT LEVEL
ZONE 3 ZONE 2 ZONE 1
COMMON & OFFICE BUILDING CLASSROOM BUILDING CLASSROOM BUILDING
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Column, Beam & Slab Methods
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
Column, Beam & Slab Methods (VIDEO)
PREFAB FORMWORK
STRUCTURE COLUMN
METHODS PREFAB
FORMWORK FORMWORK
BEAM SLAB
PREFAB PREFAB
HOW TO
FORMWORK
REMOVE
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE
CONSTRUCTION WORK OF NEW BUILDING - NATIONAL UNIVERSITY OF TIMOR LESTE