August 2017 STPP 2x600MW Performance Review
August 2017 STPP 2x600MW Performance Review
STPP 2x600MW
r 2015
11/06/2020 August-2017 1
OR#1
INDEX
S.No. Particulars
1 Highlights
2 Station Performance
4 Chemistry
10 OR#1 2
Highlights and Lowlights
Highlights
• Highest Station PLF for the Month -98.43% since inception. Earlier best was 95.15%
in the month of Feb,17.
• Highest Station generation in the month since inception -878.81 MU. Earlier best was
776.5MU in the Month of March,2017.
• Highest Availability Factor ( Running Hour) in the month since inception 99.54%.
Previous best was 98.9% in the month of March,17
• Station Auxiliary Power consumed 5.82% in the month of August,2017 lowest since
inception. Previous best was 6.2% in the month of July,2017.
11/06/2020 3
OR#1
Highlights and Lowlights
Highlights
• Lowest Specific Oil consumption for the month - 0.09 ml/kwh, previous best achieved
0.44 ml/kwh in the month of June,2017.
• Lowest Station DM water (cycle) consumption for the month 0.72%, previous best
achieved 0.82% in the month of May,2017
• Lowest specific oil consumption in any unit -0.01ml/kwh of Unit#1 in the month since
inception. Earlier best was 0.18 ml/Kwh by Unit#1 in April,17
11/06/2020 4
OR#1
2. STATION PERFORMANCE
DC-SG-AG % (Station)
110.0
100.0
90.0
80.0
70.0
Axis Title
60.0
50.0
40.0
30.0
20.0
July,17 Aug,17 Target Sep,17 FY 2017-18
11/06/2020 OR#1 5
2. STATION PERFORMANCE
PLF-%- U1/U2/Station
120.0
100.0
80.0
40.0
20.0
0.0
July,17 Aug,17 Target Sep,17 FY 2017-18
11/06/2020 OR#1 6
2. STATION PERFORMANCE
Availability Factor %
120
100
80
Axis Title 60
40
20
0
July,17 Aug,17 Target Sep,17 FY 2017-18
11/06/2020 OR#1 7
2. STATION PERFORMANCE
APC-%
7
6.5
5.5
Axis Title 5
4.5
3.5
3
July,17 Aug,17 Target Sep,17 FY 2017-18
11/06/2020 OR#1 8
2. STATION PERFORMANCE
0.6
0.5
0.4
Axis Title
0.3
0.2
0.1
0
July,17 Aug,17 Target Sep,17 FY 2017-18
11/06/2020 OR#1 9
2. STATION PERFORMANCE
DM Cycle Make Up %
1.4
1.2
0.8
Axis Title
0.6
0.4
0.2
0
July,17 Aug,17 Target Sep,17 FY 2017-18
11/06/2020 OR#1 10
2. STATION PERFORMANCE
STATION
PERFORMANCE INDICES UNIT – 1 UNIT – 2
(2X600MW)
Generation (MU)
Actual for the Month 443.08 435.73 878.81
432.02 448.54 776.49
Previous Best
Apr’ 17 May’ 17 Mar’17
YTD 1810.26 1992.15 3802.41
STATION
PERFORMANCE INDICES UNIT – 1 UNIT – 2
2X600MW
PLF (%)
Actual for the Month 99.26 97.61 98.43
100 100.11 95.1
Previous Best
Apr’ 17 Feb’ 17 Feb’ 17
YTD 82.17 90.42 86.29
Deemed PLF For the Month 100.53 99.29 99.91
100 100.2 97.9
Previous Best(Deemed)
Apr’ 16 Feb’ 17 Mar’17
Deemed PLF-YTD 87.18
11/06/2020 OR#1 11
2. STATION PERFORMANCE
AUX POWER CONSUMPTION (%)
STATION
PERFORMANCE INDICES UNIT – 1 UNIT – 2
(2X600MW)
APC (%)
11/06/2020 OR#1 12
2. STATION PERFORMANCE
STATION
PERFORMANCE INDICES UNIT – 1 UNIT – 2
(2X600MW)
SCC (gms/kwh)
11/06/2020 OR#1 13
2. STATION PERFORMANCE
SPECIFIC OIL CONSUMPTION
STATION
PERFORMANCE INDICES UNIT – 1 UNIT – 2
(2X600MW)
SOC (ml/kwh)
Actual for the Month 0.01 0.18 0.09
11/06/2020 OR#1 14
2. STATION PERFORMANCE
DM WATER
STATION
PERFORMANCE INDICES UNIT – 1 UNIT – 2
(2X600MW)
DM MAKE UP (%)
11/06/2020 OR#1 15
3. STATION PERFORMANCE ANALYSIS
OUTAGE STATISTICS – (NO. OF SHUTDOWN)
Station
Performance Indices Unit-1 Unit-2 (2X600 MW)
During Month
a) Planned 0 0
Tripping 0 03
03
b) Forced BTL 0 0
Withdrawl
b) Forced YTD 09 15 24
11/06/2020 OR#1 16
3. STATION PERFORMANCE ANALYSIS
Tripping Synchronization
Outage
Gen Loss
Unit duration Reason of Tripping
Date Time Date Time (MU)
(hr)
Both FD Fans off 3.3
1 01.08.17 01:59 01.08.17 03:45 01:46 1.62
KV Bus 2CA got dead
Both FD Fans off 3.3
1 01.08.17 16:05 01.08.17 19:28 03:23 3.1
KV Bus 2CA got dead
Furnace Pressure
1 04.08.17 04:24 04.08.17 06:04 01:40 0.9
High
Total Outage(6.81 Hrs) 06:49 5.62
11/06/2020 17
OR#1
3. STATION PERFORMANCE ANALYSIS
11/06/2020 18
OR#1
3. STATION PERFORMANCE ANALYSIS
Generation Loss % For The Month Aug,2017
Electrical; 4.72; 0.53% AHP; 0.9; 0.10% Grid Restriction; 13.17; 1.47%
Gen
Electrical
AHP
Grid Restriction
Gen
878.81
97.91%
11/06/2020 19
OR#1
3. STATION PERFORMANCE ANALYSIS
Electrical
AHP
1.67
5.15
0.69%
0.22%
Availability
Electrical
AHP
Availability
737.18
99.08%
11/06/2020 20
OR#1
3. STATION PERFORMANCE ANALYSIS
Area wise % of Availability loss during Financial Year 2017-18
11/06/2020 21
OR#1
3. STATION PERFORMANCE ANALYSIS
Area wise % of Availability loss during Financial Year 2017-18
Electrical &AHP
COperation
I
62.7 9.5 1.66
10.35
6.99% 0.18%
1.15%
1.06%
BTL
Electrical
C&I
Operation
AHP
BTL
813.32
90.62%
11/06/2020 22
OR#1
3. STATION PERFORMANCE ANALYSIS
GENERATION VARIANCE
Planned 0 0 0
Outage
Forced 0 5.62 5.62
11/06/2020
OR#1 23
2. STATION PERFORMANCE
UNBURNT CARBON IN ASH
Unit-1 Unit-2
ITEM LIMIT
Max Min Avg Max Min Avg
11/06/2020 OR#1 24
3. STATION PERFORMANCE ANALYSIS
U#1 APH PERFORMANCE FOR THE MONTH OF AUG
ONLINE OFFLINE
SI.No. Parameter Unit Design
APH-A APH-B APH-A APH-B
1 FG I/L temperature °C 335 345 351 332 345
2 FG O/L temperature °C 138 143 130 142 129
3 APH FG I/L O2 % 3.53 3.74 3.67 3.81 4.07
4 APH FG O/L O2 % 5.03 5.63 4.90 5.33 5.66
5 APH Leakage % 9 12.27 7.68 9.70 10.37
6 Corrected FG O/L temp °C 150 158 139 154 141
11/06/2020
OR#1 28
3. STATION PERFORMANCE ANALYSIS
GENERATOR OPERATING PARAMETER
11/06/2020
OR#1 29
3. STATION PERFORMANCE ANALYSIS
GENERATOR OPERATING PARAMETER
11/06/2020
OR#1 30
3. STATION PERFORMANCE ANALYSIS
CT PERFORMANCE FOR THE MONTH
PARAMETERS DESIGN
Average 4.49
Min 4.1
11/06/2020 OR#1 31
3. STATION PERFORMANCE ANALYSIS
ESP PERFORMANCE & STATUS
Unit-1 Unit-2
11/06/2020 OR#1 32
3. STATION PERFORMANCE ANALYSIS
SOOT BLOWERS AVAILABILITY
Unit-1 Unit-2
11/06/2020 OR#1 33
3. STATION PERFORMANCE ANALYSIS
Auto Loops Status
Description Reason for not
UNIT-1 Reason for not in UNIT-2 in Auto
Auto
PA Fan controller Manual Hdr. Pr. fluctuation Manual Hdr. Pr. fluctuation
No clearance from
Feeder Controller Auto Manual
BHEL
11/06/2020 35
3. STATION PERFORMANCE ANALYSIS
Auto loops status
Reason
Reason for
Description UNIT-1 for not in UNIT-2
Auto not in Auto
11/06/2020 36
3. STATION PERFORMANCE ANALYSIS
Auto loops status
Reason
for Reason for
Description UNIT-1 UNIT-2
not in not in Auto
Auto
Primary water temp controller Auto Auto
11/06/2020 37
3. STATION PERFORMANCE ANALYSIS
CRITICAL PROTECTION CHECKS
Turbine- TP 25/07/2017
Turbine ATT
Generator 13.03.2016
Turbine- TP 30/07/2017
UNIT-2
Turbine- Over Speed (Oil injection test) 28/01/2017
Turbine ATT
Generator 28.05.2016
11/06/2020 OR#1 38
3.STATION PERFORMANCE ANALYSIS
SWITCHYARD EQUIPMENT AVAILABILITY:
S.No. Description SWYD (bays)
1 Primary Equipments All 14 bays are in service.
2 Protection Panels All are in healthy condition
11/06/2020 OR#1 39
STATION PERFORMANCE ANALYSIS
BATTERY BANK STATUS
Sp. Electrolyt
Equipment Nos Volts(DC) Gravity e Level Remarks
Normal •
CHP Battery Battery Charger –A&B both are in service condition and
Two 220 1220
Bank healthy condition.
11/06/2020 OR#1
STATION PERFORMANCE ANALYSIS
BATTERY BANK STATUS
Volts Sp. Electrolyt
Equipment Nos (DC) Gravity e Level Remarks
Normal •
AHP Battery Battery Charger –A&B both are in service
Two 220
Bank 1220 condition and healthy condition
48
SWYD Banks One Dry cell N/A • All Battery are in healthy condition.
Diesel Fire
Hydrant One 24 1230 Normal • Battery Charger is in service condition
Pump
Diesel Fire
Spray Pump One 24 1220 N/A • Yet To be commissioned
11/06/2020 OR#1
3. STATION PERFORMANCE ANALYSIS
PLC AVALABILITY
11/06/2020 OR#1 42
3. STATION PERFORMANCE ANALYSIS
UPS AVALABILITY
LOCATION CAPACITY BATTERY REMARK
STATION DCS UNIT#1 2X150 KVA From Main DC bank Working normal
STATION DCS UNIT#2 2X150 KVA From Main DC bank Working normal
11/06/2020 OR#1 43
Concern
Description
Poor effectiveness of Cooling tower & Frequent failure of CT fans. (Structure stability) .
Inlet & outlet Isolation valves are passing on DMCW-PHE coolers, ACW A,B & C
Boiler different elevation, the furnace cladding skin temperature are on higher side due to lack of insulation.
When ever the safety valve floats the entire insulation get dislodged from the pipes
44
11/06/2020 OR#1
Concern
Description
Emergency Light to be commissioned in Track Hopper and Tunnels, Switch Gear Room, stair case
Data concentrator is not properly through , many relays are not communicating properly.
Recommended relay setting to be implemented for BOP area to avoid spurious tripping of transformer &
board.
45
11/06/2020 OR#1
CHEMISTRY
DEVIATION IN WATER CHEMISTRY
A) RAW- CLARIFIED water Parameters
pH at 25 degree 8.0 7.45 8.14 7.68 7.5 – 8.0 7.72 7.98 7.90
Specific 350 2500
us/cm 771 859 830 3140 3670 3394
Conductivity
Turbidity NTU < 5.0 2.65 5.30 3.19 < 10 10.2 19.3 15
Total Hardness as 186 900
mg/L 190 210 204 846 1020 916
CaCO3
Chloride as Clˉ mg/L 75 102 120 113 < 600 472 568 513
Total Dissolved 231 1650
mg/L 501 834 549 2041 2385 2206
Solids
Alkalinity as 120
mg/L 112 136 123 100 ± 20 32 58 47
CaCo3
Cycle Of
5.0 4.10 5.01 4.49
Concentration
Free Residual
mg/L 0.6 1.0 0.9 0.2- 0.5 0.1 0.2 0.2
Chlorine
Langelier Index 0.5 +0.18 +0.69 +0.54
Silica as CaCo3
5 January 2015 Mg/L 16.58 17 21
OR#47 18 < 100 68 90 7847
CHEMISTRY
DEVIATION IN WATER CHEMISTRY
B) DM WATER
DM Water (m³)
Feed Water pH 8.8 - 9.3 9.37 8.91 9.16 9.29 8.99 9.14
Off line instrument not available
DO (ppb) < 7 ppb
S.Conductivity 15 5.41 8.87 19.78 4.66 8.46
< 50
(us/cm)
Boiler Water pH 9.0 - 9.5 9.44 9.06 9.25 9.41 9.04 9.23
1. NOV-16 NIL
2. DEC-16 NIL
3. JAN-17 NIL
5. MAR-17 NIL
7. MAY-17 NIL
8. JUNE-17 NIL
9. JULY-17 NIL
11/06/2020 OR#1 53
5. CHP
11/06/2020 OR#1 54
5. CHP
CONVEYOR PROTECTION
CONVEYOR PROTECTIONS BYPASSED: NIL
Protections Local PLC Remarks
EQUIPMENT AVALABILITY
Equipment Availability N/A Since Status
Paddle feeder A - A
Crusher A, Screen A A - A
Crusher B, Screen B A - A
Crusher C, Screen C A - A
Crusher D, Screen D A VSF-1 N/A 15-06-17 A
Stacker/Reclaimer 1 A - Initial Trial Taken
Stacker/Reclaimer 2 A - Under Erection
A - 10,11,12,13,14B
All Conveyors Under Erection
D-80NEW(10-08-17)
D-155 (20-05-2017)
Bull dozers A D-120(24-08-17)
D-120NEW(14-8-17)
11/06/2020 OR#1 55
5. CHP
INVENTORY
BELT STOCK :-
Type of Capacity
Location Installed Longest Current
Belt Type (TPH) Quantity belt in the No. of WIDTH Idle Stock at
(m) Group Ply (mm) Stock Store (m)
11/06/2020 OR#1 56
5. CHP
IDLER STOCK:-
11/06/2020 OR#1 59
Thank You
11/06/2020 OR#1 60
2. STATION PERFORMANCE
APC Deviation
11/06/2020 OR#1 61
STATION PERFORMANCE
Oil Consumption Detail
11/06/2020 OR#1 62
3. STATION PERFORMANCE ANALYSIS
Reason wise BTL Financial Year 2017-18
Shop Joint Failure Field Joint Failure Flue Gas erosion Blocking/Fish mouth
11/06/2020 65
OR#1
6. STATUTORY / REGULATORY
UPDATES
7 Portable gas detector Factories Act 1948 Half yearly April 06, 2017 (sent for
calibration)
9 Employee health checkup Factories Act 1948 Yearly Due in Sept 2017 (in final
stage)
Conducting of Mock drill in plant
10
11/06/2020
Factories Act 1948
OR#1
Six months Conducted on 31.08.17
66
area
6. STATUTORY / REGULATORY
UPDATES
STAT.
Sl. No. PARTICULARS AUTHORITY FREQUENCY VALIDITY/ STATUS
12 Storage of Petroleum Class - C PESO/ Dy. CCOE, Hyd. Once in Ten years December 31, 2024
16 Lifting Tools & Tackles Factories Act 1948 Yearly May 2018 & Jan 2018
17 Factories Drawing/ Plan Approval Director of Factories One Time Approved in February 2017
STAT.
Sl. No. PARTICULARS AUTHORITY FREQUENCY VALIDITY/ STATUS
21 Pressure Vessels examination Factories Act 1948 Half-yearly Awaited from SCCL
26 Drinking water analysis BIS - 3025 & CPCB Yearly Awaited from SCCL
28 Water Sample Analysis – CMB BIS - 3025 & CPCB Monthly Under construction
Water Sample Analysis – CW Blow
29 BIS - 3025 & CPCB Weekly Ongoing
Down
Sludge Sample Analysis- Storage
30 SPCB Under construction
sludge
11/06/2020 OR#1 68
6. STATUTORY / REGULATORY
UPDATES
Submission of Environmental
34 statement SPCB - TS Yearly September 2017
36 Consent for Operation (Air and SPCB - TS Once in Five years April 2022
Water Act) & HWA
Conducted in March
37 External Safety Audit Factories Act 1948 Yearly
2017
11/06/2020 OR#1 69









