PROJECT MANAGEMENT
PROJECT SCHEDULING
Definition of terms
ACTIVITY - An activity always consumes time and may also consume resources. Examples include
paperwork, labour, negotiations, machinery operations, and lead times for purchased parts or
equipment.
CRITICAL - A critical activity or event is one that must be achieved by a certain time, having no
latitude (slack or float) whatsoever.
CRITICAL PATH - The critical path is the longest path through a network and determines the
earliest completion of project work.
EVENTS - Beginning and ending points of activities are known as events. An event is a specific
point in time. Events are commonly denoted graphically by a circle and may carry identity
nomenclature (e.g., words, numbers, alphanumeric codes).
MILESTONE - Milestones are events that represent a point in a project of special significance.
Usually, it is the completion of a major phase of the work. Project reviews are often conducted at
milestones.
NETWORK - Networks are called “arrow diagrams.” They provide a graphical representation of a
project plan showing the relationships of the activities.
Intro
One of the primary features that distinguishes project management from general
management is the special attention to scheduling
A project is a problem scheduled for solution. [1]
Project scheduling is a project management process that consists of creating and
managing a schedule to organize the tasks, deliverables and milestones of a project on a
timeline.
Until around 1958, the only tool for scheduling projects was the bar chart developed by
Henry Gantt. Often termed Gantt charts.
They are simple to construct and read and remain the best tool to use for communicating to
team members what they need to do within given time frames.
However, it is often helpful to show an arrow diagram to the people doing the work so that
they understand interdependencies and why it is important that they complete certain tasks
on time. Bar graphs didn’t show these interdependencies until contemporary software.
…
To overcome this problem, two methods of scheduling were developed in the late 1950s
and early 1960s, both of which use arrow diagrams to capture the sequential and parallel
relationships among project activities
One of the methods, developed by Du Pont, is called Critical Path Method (CPM), and
the other, developed by the U.S. Navy and the Booz Allen Hamilton consulting group, is
called Program Evaluation and Review Technique (PERT).
With PERT it is possible to calculate the probability that an activity will be completed by a
certain time, whereas that is not possible with CPM.
Network diagrams
A network diagram is a graphical representation
of the logical relationships among the project
schedule activities
They show the sequence in which work is
performed.
In diagram A, the network uses activity-on-
node notation which shows the work as a box
or node and the arrows shows the sequence in
which the work is performed.
Task A is done before B, while Task C is done
in parallel with them.
In B, the network uses activity-on-arrow
notation, in which the arrow represents the
work being done and the circle represents an
event. An event is binary; that is, it has either
occurred or it has not. An activity, on the other
hand, can be partially complete
…
Events are not shown in activity-on-node networks unless they are milestones—points in the project
at which major portions of the work are completed.
Both diagrams are still used and both get the same results in figuring out when work is supposed to
be completed.
The activity-on-node is used a bit more than the other, simply because much of today’s computer
software is programmed to use node notation.
The main advantage of using the two is that you can tell whether it is possible to meet an important
project completion date, and you can also tell exactly when various tasks must be finished in order to
meet that deadline.
Furthermore, you can tell which tasks have some leeway and which do not.
Both CPM and PERT determine the critical path, which is defined as the longest series of activities
(that can’t be done in parallel) and which therefore governs how early the project can be completed.
The critical path is the longest path through a project network. Because it has no slack, all activities
on the critical path must be completed as scheduled, or the end date will begin to slip—one day for
each day a critical activity is delayed.
Why schedule?
The primary reason for scheduling a project is to ensure that the deadline can be met- most
projects have a deadline imposed.
Furthermore, since the critical path method helps identify which activities will determine
the end date, it also helps guide how the project should be managed.
Unless resource allocation is handled properly, schedules are next to useless
Knowing where the critical path is in a project allows you to determine the impact on the
project of a scope or priority change. You know which activities will be impacted most
heavily and what might need to be done to regain lost time.
In addition, managers can make informed decisions when you can tell them the impact of
changes to the project. Thus, CPM can be an invaluable tool when used properly.
Constructing an Arrow diagram
A work breakdown structure (WBS) should be developed before work on the project is scheduled.
You should never plan (or schedule) in more detail than you can manage
A good rule of thumb to follow is that no task should have a duration much greater than four to six
weeks
The first step in developing a schedule is to decide what can be done first. Sometimes, several tasks can
start at the same time. In that case, you simply draw them side by side and start working from there
Schedules should be developed according to what is logically possible, and resource allocation should
be done later. This will yield the optimum schedule
It is hard to tell whether a network is absolutely correct, but it can be said to be wrong if logic is
violated.
Another rule is to keep all times in the same increments
Remember that there is usually no single solution to a network problem
Time estimates for each task are made by using history, taking into account how long each activity has
taken in the past. Remember, though, that the estimate is valid only for the individual who is going to do
the task.
Schedule computations
Once a suitable network has been drawn, with durations assigned to all activities, it is necessary to
determine where the longest path is in the network and to see whether it will meet the target completion
date.
Since the longest path through the project determines minimum project duration, any activity on that path
that takes longer than planned will cause the end date to slip accordingly, so that path is called the critical
path.
Schedule computations are usually done by the computer
Network computations are made for the network on the assumption that activity durations are exactly as
specified.
However, activity durations are a function of the level of resources applied to the work, and, if that level is
unavailable when it comes time to do the work, then the scheduled dates for the task cannot be met.
It is for this reason that network computations must ultimately be made with resource limitations in mind.
Another way to say this is that resource allocation is necessary to determine what kind of schedule is
actually achievable
The first step in network computations is to determine where the critical path is in the schedule and what
kind of latitude is available for noncritical work, under ideal conditions
Network rules
In order to compute network start and finish times, only two rules apply to all networks.
Rule 1. Before a task can begin, all tasks preceding it must be completed.
Rule 2. Arrows denote the logical order of work.
Node boxes in the schedule have notations which denote -:
ES – Early Start , LS – Late Start , EF – Early Finish , LF – Late Finish and DU - Duration
.
Forward-Pass Computations
Consider the picking up trash activity, it has a duration of
15mins. Assuming that it starts at time = zero, it can finish
as early as fifteen minutes later. Thus, we can enter 15 in
the cell labelled EF.
Putting gas in the mower and the weed whacker takes only
five minutes
The clean up task takes fifteen minutes, whereas the gas
activity takes only five minutes. How soon can the
following activities start? Not until the clean-up has been
finished, since it is the longest of the preceding activities.
The Early Finish for clean up becomes the Early Start for
the next three tasks. It is always true that the latest Early
Finish for preceding tasks becomes the Early Start for
subsequent tasks. That is, the longest path determines how
early subsequent tasks can start.
This shows that the project will take a total of 165 minutes
to complete, if all work is conducted exactly as shown. We
have just performed what are called forward-pass
computations
RULE-When two or more activities precede another activity, the earliest time when that activity can
preceding it.
be started is the longer ofto
the determine Earliest Finish times for all
durations of the activities
activities
Backward-pass computations
A backward pass is made through the network to compute the latest start and latest finish
times for each activity in the network. To do that, we must decide how late the project can
finish.
If Hauling Away Trash has a Late Finish of 165 minutes and has a duration of 45 minutes,
what is the latest that it could start? Clearly, if we subtract 45 from 165, we have 120
minutes, which is the Latest Start for the task. Proceeding in this manner, we get LS times
for Bagging Grass and Bundling Clippings of 90 and 105 minutes, respectively. One of
these two numbers must be the LF time for each of the preceding activities. Which one?
Well, assume we try 105 minutes. If we do that, the schedule would say that Bagging Grass
could start as late as 105 minutes, since subsequent tasks can begin as soon as preceding
tasks are finished. But if we add 30 minutes for Bagging to the 105-minute ES time, we will
finish at 135 minutes, which is later than the 120 minutes previously determined, and we
will miss the 165-minute end time for the project.
Therefore, when we are doing backward-pass calculations, the Latest Finish for a preceding
task will always be the smallest of the Late Start times for the subsequent tasks.
RULE - When two or more activities follow another, the latest time that the preceding activity can be achieved is the smaller of the times
…
Examine the path includes activities highlighted by bold lines.
Each activity has the same ES/LS and EF/LF times. There is
no float (or latitude for slippage) on this path.
By convention, an activity with no float is called critical, and a
total path with no float is called the critical path, which means
that if any of the work on this path falls behind schedule, then
the end date will slip accordingly.
All of the activities that have ES/LS or EF/LF times that differ
are said to have float. For example, Trim Weeds has an ES
time of fifteen minutes and an LS time of sixty minutes, giving
it forty-five minutes of float.
Note that some tasks have the same EF and LF times, as well
as the same ES and LS times. These tasks are on the critical
path
The critical path activities have no latitude. They must be
completed as scheduled or the entire project will take longer
than 165 minutes. Knowing where the critical path is tells a
manager where his attention must be applied
Using the Network
The point of developing a CPM diagram is to use it to manage the project. If this is not
done, scheduling is simply a worthless exercise. So
- Try to stay on schedule. It is always harder to catch up than to stay on target to begin with.
- Keep float in reserve in case of unexpected problems or bad estimates.
- Apply whatever effort is needed to keep critical tasks on schedule. If a task on the critical
path can be finished ahead of schedule, do it! Then start the next task.
- Avoid the temptation to perfect everything—that’s what the next-generation product or
service is all about. By definition, you will never reach perfection.
-Estimates of task durations are made on the assumption that certain people will work on those
tasks. If someone else is actually used, you may have to adjust durations accordingly.
-No task should be scheduled with a duration much greater than four to six weeks
-Scheduling is done initially on the assumption that you will have the resources you planned
on having
Resource allocation
The first step in developing a schedule is to assume that you have unlimited resources,
because this is the best situation you can ever assume
A major factor in dealing with resource allocation is the availability of each person to do
project work
Resource overloads like having people double or triple scheduled can be resolved only by
using computer software, except for very simple schedules. This is where the software
really excels
Most software programs allow you to specify the number of working hours needed for a
task and the percentage of a day that a person will work on the task; the software then
translates those estimates into calendar time.