MS Project Basics: Presenter: R. Schmid
MS Project Basics: Presenter: R. Schmid
Presenter: R. Schmid
Lesson 4: Resources
A. Define a Resource Pool B. Assigning Resources
Online Resources
A. Microsoft
Standard toolbar Formatting toolbar Project Guide toolbar The entry bar Timescale
View bar
Table
Gantt Chart
The Standard toolbar- shortcut commands for opening, closing and printing a project plan The Formatting toolbar- frequently used formatting tools The Project Guide toolbar- links to navigate through a project plan The entry bar- enter and edit project tasks The Table- information about tasks, resources and assignments The Gantt Chart- displays graphic duration of tasks The Timescale- time period indicator at top of Gantt Chart The View bar- buttons for commonly used views
Project Views With the use of the View Bar, the views display information within different formats. 1. By default the View bar is not active. Click on View and select View Bar.
View/ observe tasks and durations in a bar graph format. This view appears by default.
Review, enter, and edit assignments by task. Each task is listed with the assigned resources beneath it. Appearance of the details in a more clear and effecitve view.
View tasks and information in a sheet, and a chart showing a baseline and scheduled Gantt bars for each task.
Contains a list of resources with associated task assignments. Review, enter, and edit assignments by resource.
2.
Timescale is a time period indicator at the top of the Gantt chart, Resource Graph, Task Usage, and Resource Usage.
Project Guide toolbar 1. To activate the Project Guide toolbar. a. From the menu bar, click on View and select Turn on Project Guide. 2. Within the Tasks side pane, click on Define the project link. From the screen it acts as a wizard to help you through the process of creating a new project file.
Creating a New Blank Project 1. Click on File and select New. On the New Project task pane, click on Blank Project.
Using Project Templates 1. Click on File and select New. On the New Project task pane, click On computer and click the Project Templates tab. Select a template and click on OK.
Project Information dialog box You can use the Project Information dialog box to create a new project. 1. Click on Project and select Project Information. a. Enter a start date in the Start Date text box, and click on OK. b. Save the file, click on File and select Save. Name the file and save to a preferred location.
Project Properties 1. Define the file properties. a. Click on File and select Properties. From the Summary tab and enter details of project. Click OK to close Properties dialog box.
Project Calendar A Project must base its schedule on a measure of time. Microsoft Project has three default base calendars that it uses to create a schedule for a project. Standard 24 Hours Night Shift 1. Monday through Friday 8am-5pm with 1 hr. break For projects that are worked on around the clock. Monday night through Saturday morning 11pm-8am with 1hr. break
Entering Tasks A task represents the work to be done to accomplish the goals of the project. 1. Enter Tasks: a. From the Entry table. Click in the desired row and enter a task name, press enter. Continue until all tasks for the project have been entered. 2. To enter Subtasks: a. Insert a new row in the Entry table. When inserting a new task, by default new rows are inserted above selected row. b. Click on Insert and select New Task. Or you can press the Insert key from your keyboard.
Editing Tasks Tasks within your project plan can change, editing tasks correctly will make it easier for you while working in Microsoft Project. 1. To Edit text: a. Select the task name, click in the entry bar to edit text, press enter or click on the green check mark. 2. To Move a task: a. Select the entire task by clicking on the ID number of the task. b. Right-click the ID number and select Cut Task. c. Click the row where you want the task to be placed. d. Right-click the ID number and select Paste. 3. To Copy a task: a. Select the entire task by clicking the ID number for the task. b. Right-click on the ID number and select Copy task. c. Click the row where you want the task to be placed. d. Right-click the ID number and select Paste. 4. To Insert a task: a. Select the task below the row where you want the new task inserted. b. Press the Insert key. c. Or. Click on Insert, select New Task. d. Or .Right-click on the ID number and select New Task. 5. To Delete a task: a. Select the entire task by clicking on the ID number and press the Delete Key. b. OrRight-click on the ID number and select Delete Task. Enter Task Duration Best practice is to enter duration estimates for tasks, allowing Project to schedule the task start and finish dates. 1. Duration can be displayed in minutes, hours, days, and weeks. a. Minutes are displayed as: m, mins, minute. b. Hours are displayed as: h, hr, hour. c. Days are displayed as: d, dy, day. d. Weeks are displayed as w, wk, week.
Linking Tasks Linking establishes a dependency between tasks. Task relationships by deault Project links tasks in a finish-to-start dependency. 1. Select the tasks that you want to link, and then click the Link Task button . 2. From the Gantt Chart double-click the link. The Task Dependency dialog box will appear, allowing you change the type of dependency.
Task Constraint Types Three types of constraints; Flexible, Semi-Flexible, and Inflexible.
Constraint type Flexible Constraint name As Late As Possible (ALAP) Description Schedules the task as late as possible with the task ending before the project ends and without delaying subsequent tasks. This is the default constraint for tasks when you schedule from the project finish date. Do not enter a task start or finish date with this constraint. Schedules the task to begin as early as possible. This is the default constraint for tasks when you schedule from the project start date. Do not enter a start or finish date with this constraint. Schedules the task to start on or after a specified date. Use this constraint to ensure that a task does not start before a specified date. Schedules the task to finish on or after a specified date. Use this constraint to ensure that a task does not finish before a certain date. Schedules the task to start on or before a specified date. Use this constraint to ensure that a task does not start after a specified date. Schedules the task to finish on or before a specified date. Use this constraint to ensure that a task does not finish after a certain date. Schedules the task to finish on a specified date. Sets the early, scheduled, and late finish dates to the date that you type and anchors the task in the schedule. Schedules the task to start on a specified date. Sets the early, scheduled, and late start dates to the date that you type and anchors the task in the schedule.
Flexible
As Soon As Possible (ASAP) Start No Earlier Than (SNET) Finish No Earlier Than (FNET) Start No Later Than (SNLT) Finish No Later Than (FNLT) Must Finish On (MFO)
Semi-Flexible
Semi-Flexible
Semi-Flexible
Semi-Flexible
Inflexible
Inflexible
To apply a constraint to a task: 1. Double-click on the task. 2. Within the Task Information dialog box, click on the Advanced tab. 3. Click the Constraint type drop-down arrow, select the desired type of constraint. 8
4. Click dropthe
the Constraint date down arrow and from calendar select the desired date.
Add Notes to a Task Task notes are additional or supporting information that is added to a task. 1. Double-click on the task, select the Notes tab and enter the information in the Notes section.
2. Notes
Resources People, equipment, material and other items used to complete a task are Resources. You can assign more than one resource to a task. 1. Click on View and select Resource Sheet. 2. In the Resource Name field, enter the names of the resources you will use for your project. 3. Work, material, cost,and budget are types of resources.
Assign Resources 1. Click on the Gantt Chart view, select a task which you want to assign a resource. 2. Click the Assign Resources button . 3. Within the Assign Resources dialog box, click the resource names, then click on Assign.
Display Critical Path 1. Click on Format and select Gantt Chart Wizard. 2. Within the Gantt Chart Wizard, click Next.
10
3. Verify that the Critical path option is selected and click Next.
4. Verify that the Resources and dates option is selected and click Next.
5. Verify that the Yes option is selected and click Next to indicate that the link must be shown between dependent tasks and to move to the next page.
6. Click on Format It to apply the custom Gantt Chart and click Exit Wizard to view the newly formatted chart.
11
Set a Baseline You have entered tasks, task durations, resources, assigned resources, and made necessary adjustment to your project. You can consider you project plan to be finalized. Before you begin tracking progress on the project, you want to preserve your original project estimates so that you will have some data to compare the actual project results with. Once your project begins, you will enter information about how things are actually progressing and the current information will be altered. To calculate variances between the original plan and the actual project progress for project, saving a project baseline is essential.
information in your project plan, you save a baseline plan, so that you can view the results in the task sheet view. In effect, this saves a copy of the current date information for future reference. To Set a Baseline: You can set up to 11 different baselines. The Set Baseline dialog box is used to set a baseline plan or interim plan. 1. Click on ToolsTrackingSet Baseline.
2. From within the Set Baseline dialog box, check Set baseline. a. In the For section, select the Entire project or Selected tasks option. b. Click OK to set the baseline.
12
To review the timing and sequence of tasks within a project against the actual information that shows what has actually occurred, the Project Statistics dialog box is used. This is accessed from the Project Information dialog box. 1. ProjectProject Information2
2. From the Project Information dialog box, click on Statistics. 3. The Project Statistics dialog box, will show the Current Start and Finish, plus the Baseline.
Print Project Summary Report 1. Click on the Report menu and select Reports. 2. Within the Reports dialog box, click the icon of the report category you want to print and click Select.
13
3. Within the Overview Reports dialog box, click on the icon of the report you want to print and click on Select to display a preview of the report. 4. Click on Print to print the report and within the Print dialog box, click OK to print out report.
Updating and Manage Updating the progress of your project is the only way to insure that your project stays on track as work is performed. 1. Select a task, click on Tools, select Tracking and click on Update Tasks. 2. Within the Update Tasks dialog box, enter the % Complete and click on OK.
3. Or Right-click on the ID number of a task and select Task Information. Within the General tab, enter % complete.
Other Online Resources Microsoft Get up to speed now with Project 2007 http://office.microsoft.com/en-us/project/FX100649011033.aspx?CTT=96&Origin=CL100627011033
14