Eee-Viii-power System Operation and Control (06ee82) - Notes
Eee-Viii-power System Operation and Control (06ee82) - Notes
06EE82
SUBJECT: POWER SYSTEM OPERATION AND CONTROL SUBJECT CODE: 06EE82 PART - A UNIT - 1 CONTROL CENTER OPERATION OF POWER SYSTEMS: Introduction to SCADA, control center, digital computer configuration, automatic generation control, area control error, operation without central computers, expression for tie-line flow and frequency deviation, parallel operation of generators, area lumped dynamic model.8 Hours
UNIT - 2 & 3 AUTOMATIC GENERATION CONTROL: Automatic voltage regulator, automatic load frequency control, A VR control loops of generators, performance of A VR, ALFC of single area systems, concept of control area, multi-area systems, POOL operation-two area systems, tie-line bias control.10 Hours
UNIT - 4 CONTROL OF VOLTAGE AND REACTIVE POWER: Introduction, generation and absorption of reactive power, relation between voltage, power and reactive power at a node, single machine infinite bus systems, methods of voltage control, sub synchronous resonance, voltage stability, voltage collapse. 8 Hours PART - B UNIT - 5 POWER SYSTEM OPTIMIZATION: Optimal system operation with thermal plants, incremental production cost for steam power plants, analytical form of generating cost of thermal plants, constraints in economic operation, flow chart, transmission loss as a function of plant generation, the B-coefficients, examples. 8 Hours
Dept. of EEE, SJBIT Page 1
06EE82
UNIT COMMITMENT: Statement of the problem, need and importance of unit commitment, methods-priority lists method, dynamic programming method, constraints, spinning reserve, and examples.8 Hours
UNIT - 7 & 8 POWER SYSTEM SECURITY: Introduction, factors affecting power system security, power system contingency analysis, detection of network problems, network sensitivity methods, calculation of network sensitivity factor, contingency ranking.10 Hours
TEXT BOOKS: 1. Computer Aided Power System Analysis- G.L.Kusic, PHI. 2. Modern Power System Analysis- I J Nagarath and D P Kothari, TMH, 1993. 3. Power generation, operation and control- Wood & B A J F Woollenberg. John Wiley and Sons, 1984. 4. Electric Power Systems-B. M. Weedy
Page 2
Power System Operation and Control (PSOC) TABLE OF CONTENTS Sl. No. 1
06EE82
Topic UNIT 1: CONTROL CENTER OPERATION OF POWER SYSTEMS Introduction to POWER SYSTEM OPERATION AND CONTROL Introduction to Control center operation of power systems Introduction to SCADA Control center, digital computer configuration Automatic generation control, area control error Operation without central computers Expression for tie-line flow and frequency deviation Parallel operation of generators UNIT 2 & 3: AUTOMATIC GENERATION CONTROL Automatic generation control Automatic voltage regulator Automatic load frequency control performance of A VR ALFC of single area systems concept of control area multi-area systems tie-line bias control UNIT 4 : CONTROL OF VOLTAGE AND REACTIVE POWER Introduction to CONTROL OF VOLTAGE AND REACTIVE POWER generation and absorption of reactive power relation between voltage, power and reactive power at a node single machine infinite bus systems methods of voltage control sub synchronous resonance voltage stability, Voltage collapse
Page no.
6 11 15 15 22 24 26
31 33 33 34 37 38 39
41 55 57 57 57 61 63 63
OPTIMIZATION
AND
Page 3
UNIT
Power System Operation and Control (PSOC) POWER SYSTEM OPTIMIZATION Optimal system operation with thermal plants Incremental production cost for steam power plants constraints in economic operation, transmission loss as a function of plant generation the B-coefficients, Examples UNIT COMMITMENT: Introduction Statement of the problem of unit commitment need and importance of unit commitment methods-priority lists method dynamic programming method constraints, spinning reserve Examples on unit commitment Examples on unit commitment UNIT- 7 & 8 POWER SYSTEM SECURITY POWER SYSTEM SECURITY: Introduction Factors affecting power system security Power system contingency analysis Calculation of network sensitivity Factor Contingency Analysis Ranking of contingency
06EE82
Page 4
06EE82
SUBJECT: POWER SYSTEM OPERATION AND CONTROL SUBJECT CODE: 06EE82 PART - A
UNIT - 1 CONTROL CENTER OPERATION OF POWER SYSTEMS: Introduction to SCADA, control center, digital computer configuration, automatic generation control, area control error, operation without central computers, expression for tie-line flow and frequency deviation, parallel operation of generators, area lumped dynamic model.8 Hours General Electrical Technology was founded on the remarkable discovery by Faraday that a changing magnetic flux creates an electric field. Out of that discovery, grew the largest and most complex engineering achievement of man : the electric power system. Indeed, life without electricity is now unimaginable. Electric power systems form the basic infrastructure of a country. Even as we read this, electrical energy is being produced at rates in excess of hundreds of giga-watts (1 GW = 1,000,000,000 W). Giant rotors spinning at speeds up to 3000 rotations per minute bring us the energy stored in the potential energy of water, or in fossil fuels. Yet we notice electricity only when the lights go out! While the basic features of the electrical power system have remained practically unchanged in the past century, but there are some significant milestones in the evolution of electrical power systems.
Page 5
Power System Operation and Control (PSOC) Topics to be studied (i) Introduction to SCADA (ii) Control Centre (iii)Digital Computer Configuration (iv) Automatic Generation Control (v) Area Control Error (vi) Operation Without Central Computers (vii) (viii) Expression for Tie Line Flow Parallel Operation of Generators
06EE82
1.0 Introduction Electrical energy is an essential ingredient for the industrial and all round development of any country. It is generated centrally in bulk and transmitted economically over long distances. Electrical energy is conserved at every step in the process of Generation, Transmission, Distribution and utilization of electrical energy. The electrical utility industry is probably the largest and most complex industry in the world and hence very complex and challenging problems to be handled by power engineering particularly, in designing future power system to deliver increasing amounts of electrical energy. This calls for perfect understanding, analysis and decision making of the system. This power system operation and its control play a very important task in the world of Electrical Power Engineering.
Power Quality Power quality is characterized by = Stable AC voltages at near nominal values and at near rated frequency subject to acceptable minor variations, free from annoying voltage flicker, voltage sags and frequency fluctuations. = Near sinusoidal current and voltage wave forms free from higher order harmonics
Page 6
06EE82
All electrical equipments are rated to operate at near rated voltage and rated frequency.
Effects of Poor Power Quality = Maloperation of control devices, relays etc. = Extra losses in capacitors, transformers and rotating machines = Fast ageing of equipments = Loss of production due to service interruptions = Electro-magnetic interference due to transients = power fluctuation not tolerated by power electronic parts
Major causes of Poor Power Quality - Nonlinear Loads - Adjustable speed drives - Traction Drives - Start of large motor loads - Arc furnaces - Intermittent load transients - Lightning - Switching Operations - Fault Occurrences
Steps to address Power Quality issues Detailed field measurements Monitor electrical parameters at various places to assess the operating conditions in terms of power quality. Detailed studies using a computer model. The accuracy of computer model is first built to the degree where the observed simulation values matches with those of the field measurement values. This provides us with a reliable computer model using which we workout remedial measures.
Dept. of EEE, SJBIT Page 7
06EE82
For the purpose of the analysis we may use load flow studies, dynamic simulations, EMTP simulations, harmonic analysis depending on the objectives of the studies.
We also evaluate the effectiveness of harmonic filters through the computer model built, paying due attention to any reactive power compensation that these filters may provide at fundamental frequency for normal system operating conditions.
The equipment ratings will also be addressed to account for harmonic current flows and consequent overheating.
Power Quality Solutions : Poor power quality in the form of harmonic distortion or low power factor increases stress on a facilitys electrical system. Over time this increased electrical stress will shorten the life expectancy of electrical equipment. In addition to system degradation, poor power quality can cause nuisance tripping and unplanned shutdowns within electrical system. In an increasingly automated electrical world, it is important for a facility to evaluate power quality. Harmonic distortion, low power factor, and the presence of other transients can cause severe damage to electrical system equipment. PSE provides system analysis and evaluation of power quality issues and makes recommendations for system design solutions
1.1
Structure of Power Systems Generating Stations, transmission lines and the distribution systems are the main components of an electric power system. Generating stations and distribution systems are connected through transmission lines, which also connect one power system (grid, area) to another. A distribution system connects all the loads in a particular area to the transmission lines.
Page 8
06EE82
For economical technical reasons, individual power systems are organized in the form of electrically connected areas or regional grids. As power systems increased in size, so did the number of lines, substations, transformers, switchgear etc. Their operation and interactions became more complex and hence it is necessary to monitor this information simultaneously for the total system at a focal point called as Energy Control Centre. The fundamental design feature is increase in system reliability and economic feasibility.
Major Concerns of Power System Design and Operation Quality : Continuous at desired frequency and voltage level Reliability : Minimum failure rate of components and systems Security : Robustness - normal state even after disturbances Stability : Maintain synchronism under disturbances Economy : Minimize Capital, running and maintenance Costs
1.2 Need for Power System Management Demand for Power Increasing every day - No of transmission line, Sub-stations, Transformers, switchgear etc., Operation and Interaction is more and more complex Essential to monitor simultaneously for the total system at a focal point ENERGY LOAD CENTRE
Page 9
Power System Operation and Control (PSOC) Components of power system operation and control Information gathering and processing Decision and control System integration
06EE82
Energy Load Centre The function of energy load centre is to control the function of coordinating the response in both normal and emergency conditions. Digital Computers are very effectively used for the purpose. Their function is to process the data, detect abnormalities, alarm the human operator by lights, buzzers, screens etc., depending on the severity of the problem.
Control Centre of a Power System Human Machine Interface equipped with CRT presentations Keyboards change parameters Special function keyboards- alter transformer taps, switch line capacitors etc., Light-Pen cursor open or close circuit breakers Alarm lights, alarms, dedicated telephone communications with generating stations and transmission substations, neighboring power utilities
Control Features Control Centre System Commands Mode of control Units base / peak load AGC Automatic Generation Control Data Entry Alarms To find source of alarm and necessary action Plant/Substation selection Special Functions - To send/retrieve data etc., Readout control Output to CRT/printers etc., CPU control Selection for the computer
Page 10
Power System Operation and Control (PSOC) Functions of Control Centre Short, Medium and Long-term Load Forecasting System Planning Unit Commitment and maintenance Scheduling Security Monitoring State Estimation Economic Dispatch Load Frequency Control
06EE82
One of key processes of SCADA is the ability to monitor an entire system in real time. This is facilitated by data acquisitions including meter reading, checking statuses of sensors, etc that are communicated at regular intervals depending on the system. A well planned and implemented SCADA system not only helps utilities deliver power reliably and safely to their customers but it also helps to lower the costs and achieve higher customer satisfaction and retention. SCADA Why do we need it? If we did not have SCADA, we would have very inefficient use of human resources and this would cost us (Rs,Rs,Rs) In todays restructured environment SCADA is critical in handling the volume of data needed in a timely fashion Service restoration would involve travel time and would be significantly higher It is essential to maintain reliability
SCADA - Architecture Basic elements are sensors which measure the desired quantities Current Transformers CTs measure currents and Potential Transformers PTsmeasure voltages.
Page 11
06EE82
= Today there is a whole new breed of Intelligent electronic devices (IEDs) = This data is fed to a remote terminal unit (RTU) = The master computer or unit resides at the control center EMS
SCADA - Process Master unit scan RTUs for reports, if reports exist, RTU sends back the data and the master computer places it in memory In some new substation architectures there could be significant local processing of data which could then be sent to the control center. The data is then displayed on CRTs and printed
SCADA - Logging The SCADA provides a complete log of the system The log could be provided for the entire system or part of the system Type of information provided Time of event Circuit breaker status Current measurements, voltage measurements, calculated flows, energy, etc. Line and equipment ratings SCADA as a System There are many parts of a working SCADA system. A SCADA system usually includes signal hardware (input and output), controllers, networks, user interface (HMI), communications equipment and software. All together, the term SCADA refers to the entire central system. The central system usually monitors data from various sensors that are either in close proximity or off site (sometimes miles away). For the most part, the brains of a SCADA system are performed by the Remote Terminal Units (sometimes referred to as the RTU). The Remote Terminal Units consists
Page 12
06EE82
of a programmable logic converter. The RTU are usually set to specific requirements, however, most RTU allow human intervention, for instance, in a factory setting, the RTU might control the setting of a conveyer belt, and the speed can be changed or overridden at any time by human intervention. In addition, any changes or errors are usually automatically logged for and/or displayed. Most often, a SCADA system will monitor and make slight changes to function optimally; SCADA systems are considered closed loop systems and run with relatively little human intervention. SCADA can be seen as a system with many data elements called points. Usually each point is a monitor or sensor. Usually points can be either hard or soft. A hard data point can be an actual monitor; a soft point can be seen as an application or software calculation. Data elements from hard and soft points are usually always recorded and logged to create a time stamp or history User Interface Human Machine Interface (HMI) A SCADA system includes a user interface, usually called Human Machine Interface (HMI). The HMI of a SCADA system is where data is processed and presented to be viewed and monitored by a human operator. This interface usually includes controls where the individual can interface with the SCADA system. HMI's are an easy way to standardize the facilitation of monitoring multiple RTU's or PLC's (programmable logic controllers). Usually RTU's or PLC's will run a pre programmed process, but monitoring each of them individually can be difficult, usually because they are spread out over the system. Because RTU's and PLC's historically had no standardized method to display or present data to an operator, the SCADA system communicates with PLC's throughout the system network and processes information that is easily disseminated by the HMI. HMI's can also be linked to a database, which can use data gathered from PLC's or RTU's to provide graphs on trends, logistic info, schematics for a specific sensor or
Page 13
06EE82
machine or even make troubleshooting guides accessible. In the last decade, practically all SCADA systems include an integrated HMI and PLC device making it extremely easy to run and monitor a SCADA system. Todays SCADA systems, in response to changing business needs, have added new functionalities and are aiding strategic advancements towards interactive, self healing smart grids of the future. A modern SCADA system is also a strategic investment which is a must-have for utilities of all sizes facing the challenges of the competitive market and increased levels of real time data exchange that comes with it (Independent Market Operator, Regional Transmission Operator, Major C&I establishments etc). A well planned and implemented SCADA system not only helps utilities deliver power reliably and safely to their customers but it also helps to lower the costs and achieve higher customer satisfaction and retention. Modern SCADA systems are already contributing and playing a key role at many utilities towards achieving : New levels in electric grid reliability increased revenue. Proactive problem detection and resolution higher reliability. Meeting the mandated power quality requirements increased customer satisfaction. Real time strategic decision making cost reductions and increased revenue
Critical Functions of SCADA Following functions are carried out every 2 seconds : Switchgear Position, Transformer taps, Capacitor banks Tie line flows and interchange schedules Generator loads, voltage etc., Verification on links between computer and remote equipment
Modern SCADA systems are already contributing and playing a key role at many utilities towards achieving : - New levels in electric grid reliability increased revenue.
Page 14
06EE82
- Proactive problem detection and resolution higher reliability. - Meeting the mandated power quality requirements increased customer satisfaction. - Real time strategic decision making cost reductions and increased revenue.
1.4 Digital Computer Configuration Major functions - Data acquisition control - Energy Management - System Security For best/secured operation 100% redundancy is used Dual Digital Computers i) on-line computer monitors and controls the system ii) Backup computer load forecasting or hydro thermal allocations
The digital computers are usually employed in a fixed-cycle operating mode with priority interrupts wherein the computer periodically performs a list of operation. The most critical functions have the fastest scan cycle. Typically the following categoties are scanned every 2 seconds : All status points such as switchgear position (open or closed), substation loads and voltages, transformer tap positions, and capacitor banks etc., Tie line flows and interchange schedules Generator loads, voltage, operating limits and boiler capacity Telemetry verificationto detect failures and errors in the bilateral communication links between the digital computer and the remote equipment. 1.5 Important Areas of Concern in power System Automatic Generation Control (AGC)
Page 15
06EE82
On-line Computer Control that maintains overall system frequency and net tie-line load exchange through interconnection Economic Load Dispatch On-line computer control to supply load demand using all interconnected systems power in the most economical manner
AGC is the name given to a control system having three major objectives : a. To hold system frequency at or very close to a specified nominal value (50 or 60Hz) b. To maintain the correct value of interchange power between control areas c. To maintain each units generation at the most economic value.
To implement an AGC system, the following information is required : Unit megawatt output of each committed unit Megawatt flow over each tie line to neighboring systems System frequency
Usually, neighboring power companies are interconnected by one or more transmission lines called Tie Lines. The objective is to buy or sell power with neighboring systems whose operating costs make such transactions profitable. Also, even if no power is being transmitted over ties to neighboring system, if one system has a sudden loss of a generating unit, the units throught all the interconnection will experience a frequency change and can help in restoring frequency.
Advantages of interconnected system Reduces Reserve Capacity thus reduces installed capacity Capital Cost/kW is less for larger Unit - in India single unit can support >500MW because of Effective Use of Generators Optimization of Generation installed capacity is reduced Reliability
Page 16
interconnection
06EE82
Disadvantages of interconnected system Fault get Propagated calls for fast switchgear CB rating increases Proper management required EMS and it must be automated Economic load dispatch - Base load and Peak Load National Regional Electricity Boards Northern Regional Electricity Board Western Regional Electricity Board Southern Regional Electricity Board Eastern Regional Electricity Board North-east Regional Electricity Board
Goal To have National Grid to improve efficiency of the whole National Power Grid Control Area Concept All generators are tightly coupled together to form Coherent Group - all generators respond to changes in load or speed changer setting Control Area frequency is assumed to be constant throughout in static and dynamic conditions For the purpose of analysis, a control area can be reduced to a single speed governor, turbo generator and load system
Page 17
06EE82
Functions Exchange or sale of power Disturbed areas taking other areas help Long distance sale and transfer of power
1.6 Area Control Error ACE To maintain a net interchange of power with its area neighbors, an AGC uses real power flow measurements of all tie linesa emanating from the area and subtracts the scheduled interchange to calculate an error value. The net power interchange, together with a gain, B (MW/0.1Hz), called the frequency bias, as a multiplier on the frequency deviation is called the Area Control Error (ACE) given by,
Pk = Power in Tie lIne - +ve out of the area Ps Scheduled Power Interchange f0 Base frequency, fact Actual frequency +ve ACE indicates flow out of the area.
Page 18
06EE82
Page 19
06EE82
The real power summation of ACE loses information as to the flow of individual tie lines but is concerned with area net generation. The tie lines transfer power through the area from one neighbor to the next, called Wheeling Power. The wheeling power cancels algebraically in the ACE. Thus one area purchases or sells blocks of power (MWh) with non-neighbor utilities. Power Sale from A to C
Page 20
06EE82
Power export starts until its AGC forces ACE to become zero Area C introduces -p into its ACE Power flows in to area C until its ACE becomes zero Areas B & C must be aware of the power exchange as they are also interconnected
The minimum requirements of AGC on controlling the interchange of power and frequency have been established by NERC North American Electric Reliability Council, which is comprised of representatives of the major operating power pools. This committee specifies the following criteria as minimum performance expected by AGC. A. Normal System Conditions - ACE = 0 at least once in 10 min period - Deviation of ACE from zero must be within allowable limits B. Disturbances Conditions - ACE must return to zero within 10 min - Corrective action from AGC must be within a minimum disturbance
The allowable limit, Ld of the average deviation on power systems (averaged over 10 minutes) is : Ld = 0.025L + 5.0 MW
Page 21
06EE82
The value of L is determined annually and is taken from the daily load cycle. A power system is said to be in a disturbance condition if the ACE signal exceeds 3Ld.
Power Systems are capable of functioning even without Central Computer and/or AGC - Due to a result of Turbine Generator speed controls in the generating station and natural load regulation - Thus generators within an area are forced to share load and cause interconnected areas to share load
Let there be two independent areas A and B without tie line flow as the circuit breaker is open. Let there be a sudden change in load occurs in the area D. Area A is considered as a single operating area representing the remainder of the interconnection. It is further assumed that the areas share the disturbance in proportion to their generating capacity and operating characteristics. Let the area generation-frequency characteristics be represented by the curve GG which is a composite response curve from all the generators in area A. The characteristic curve has a negative slope with frequency.
Page 22
06EE82
The area connected load is defined by the curve LL as shown. As there is increase in load the rotating machinery in the area is forced to increase the speed.
Basic Equations GA = G0 +10 1 (fact f0) GA = Total Generation, MW LA = L0 +102 (fact f0) MW
LA = Total Load, L 0 = Base load, fact = System frequency, 1 = Cotangent of generation-frequency characteristic, MW/0.1 Hz < 0 2 = Cotangent of load-frequency characteristic, MW/0.1 Hz > 0 1.7.2 Isolated Operation in A response to load change
Page 23
06EE82
For Steady State Frequency Total generation = Total effective load This is defined by the intersection of GG and LL curves as shown Io. Combined characteristic of GG and LL is CC. The composite generation load frequency characteristics is given by, GA = G0 +101 (fact f0), LA = L0 +102 (fact f0) GA - LA = G0 +101 (fact f0) - L0 -102 (fact f0) Increase in load in A moves the load frequency curve to position LL. The new system frequency will now be defined by the intersection labeled as I 1 at 49.9Hz.Then it is desired to return the system frequency to 50.0Hz i.e., point I2. Setting AGC in A- shifting of GG to GG takes place to meet frequency demand of 50.0Hz I2 Resulting combined characteristic is CC In terms of increments, A = GA - G0 + L0 - LA = 101 (fact f0) -102 (fact f0) = 10BA XA f A = GA = 10BA XA f XA Generating Capacity of Frequency deviation = f = MW - G0 + L0 - LA = 101 (fact f0) -102 (fact f0) MW
10BA XA Hz
Hz
TL
TL = GA - LA
Page 24
06EE82
Let two areas A and B are interconnected through a Tie Line. Thus both Generation and Load frequency are equal to 50.0 Hz. There is no initial Tie Line Power Flow.
Disturbance occur at B causing frequency to drop to 49.9Hz Area generation does not match with effective load in A Difference between I1 and I2 difference between generation and load net excess power in the area flows out of A towards B Contributory effects in A are decrease in load power L and increase in generation G Tie Line Flow from A to B = TL = (GA - LA ) MW If area A has AGC, tie line flows increases TL and TL representing increased amounts of bias due to AGC.
Frequency change due to disturbance B for a tie line power flow from A to B is f = B TL / (10BB XB) Hz TL = (10BA XA)
AB
Net power change in B is = AB - TL = (10BB XB) AB / (10BA XA +10BB XB) AB = (10BA XA+ 10BB XB )f Hence, f / AB = 1/(10BA XA+ 10BB XB )
Page 25
06EE82
Two areas A and B are interconnected. Generating capacity of A is 36,000Mw with regulating characteristic of 1.5%/0.1Hz. B has 4000MW with 1%/0.1Hz. Find each areas share of +400MW disturbance (load increase) occurring in B and resulting tie line flow. f = AB / (10 BAXA + 10 BBXB = 400 / -10(0.015)(36,000) 10(0.01)(4000) = 0.06896 Hz Tie Line flow = TL = (10BA XA) AB / (10BA XA +10BB XB) = 5400*400/4800 = 372.4MW Smaller system need only 27.6 MW Frequency regulation is much better
1.8 Parallel Operation of Generators Tie line flows and frequency droop described for interconnected power areas are composite characteristics based on parallel operation of generators. Each area could maintain its speed w = 2 f, then aload common to both areas, by superposition have the terminal voltage, Vload = V1sinw1t + V2sinw2t, Where, 1&2 represents areas and t time in secs. Generator speed versus load characteristics is a function of the type of the governor used on the prime movertype 0 for a speed droop system and type 1 for constant speed system. Parallel operation of generator with infinite bus
Page 26
06EE82
The generator characteristic is such that it is loaded to 50% of its capacity when paralleled to the bus. Therefore, Unit speed regulation = R = f(pu)/P(pu) = If it is desired to increase the load on the generator, the prime mover torque is increased, which results in a shift of the speed-droop curve as shown below. The real power flow is given by, P = V1V2 sin(1 - 2) / X , where X = synchronous reactance
Load
Page 27
06EE82
Two generators paralleled have different governor-speed-droop characteristics. Because they are in parallel, power exchange between them forces them to synchronize at a common frequency. Since the two units are of equal capacity having equal regulation are initially operating at 1.0 base speed as shown above. If unit is operated at point A1 satisfies 25% of the total load and unit 2 at point A2 supplies 75%. If the total load is increased to 150%, the frequency decreases to f1. Since the droop curves are linear, unit 1 will increase its load to 50% of rating and unit 2 to be overloaded. Parallel operation of two units with different capacity and regulation The case when two units of different frequency and regulation characteristics are operated in parallel is as shown below. The regulation characteristics are R1 = f(pu) / P1 (pu), R2 = (pu) / P2 (pu)
Page 28
Power System Operation and Control (PSOC) 1.9 Area Lumped Dynamic Model
06EE82
The model discussed so far is one macroscopic behavior because there is no effort made to indicate instantaneous power flow within the system due to a tie line disturbance, magnitudes of the internal line flows, the time history of generator phase angles and so on. The power system macro model may be described by means of a block diagram as shown in the block diagram.
Page 29
Power System Operation and Control (PSOC) HA = Effective Inertia of rotating machinery loads 2 = Load frequency characteristics, MW/0.1Hz Pirate = Rated power output of Gen i Pi = Power Increment for gen i 1/Ri = Droop characteristic of gen i, Hz/MW Analysis Isolated Power Area without Tie Lines
06EE82
Steady State value of Frequency deviation f for a load change L = A/S Hence, f/ A = 1/(101 - 10 2) Combining droop characteristics of M gen,
Page 30
06EE82
AUTOMATIC GENERATION CONTROL: Automatic voltage regulator, automatic load frequency control, A VR control loops of generators, performance of A VR, ALFC of single area systems, concept of control area, multi-area systems, POOL operation-two area systems, tie-line bias control.
2.1 Introduction
The main objective of power system operation and control is to maintain continuous supply of power with an acceptable quality, to all the consumers in the system. The system will be in equilibrium, when there is a balance between the power demand and the power generated. As the power in AC form has real and reactive components: the real power balance; as well as the reactive power balance is to be achieved.
There are two basic control mechanisms used to achieve reactive power balance (acceptable voltage profile) and real power balance (acceptable frequency values). The former is called the automatic voltage regulator (AVR) and the latter is called the automatic load frequency control (ALFC) or automatic generation control (AGC).
2.2 Generator Voltage Control System The voltage of the generator is proportional to the speed and excitation (flux) of the generator. The speed being constant, the excitation is used to control the voltage. Therefore, the voltage control system is also called as excitation control system or automatic voltage regulator (AVR). For the alternators, the excitation is provided by a device (another machine or a static device) called exciter. For a large alternator the exciter may be required to supply a field current of as large as 6500A at 500V and hence the exciter is a fairly large machine. Depending on the way the dc supply is given to the field winding of the alternator (which is on the rotor), the exciters are classified as: i) DC Exciters; ii) AC Exciters; and iii) Static Exciters. Accordingly, several standard block diagrams are developed by the IEEE
Dept. of EEE, SJBIT Page 31
06EE82
working group to represent the excitation system. A schematic of an excitation control system is shown in Fig2.1.
Fig2.1: A schematic of Excitation (Voltage) Control System. A simplified block diagram of the generator voltage control system is shown in Fig2.2. The generator terminal voltage Vt is compared with a voltage reference Vref to obtain a voltage error signal V. This signal is applied to the voltage regulator shown as a block with transfer function KA/(1+TAs). The output of the regulator is then applied to exciter shown with a block of transfer function Ke/(1+Tes). The output of the exciter E fd is then applied to the field winding which adjusts the generator terminal voltage. The generator field can be represented by a block with a transfer function K F/(1+sTF). The total transfer V function is
V
KAKeKF
ref 1 + G(s) (1 + sTA )(1 + sTe )(1 + sTF ) The stabilizing compensator shown in the diagram is used to improve the dynamic response of the exciter. The input to this block is the exciter voltage and the output is a stabilizing feedback signal to reduce the excessive overshoot.
Page 32
06EE82
Fig2.2: A simplified block diagram of Voltage (Excitation) Control System. Performance of AVR Loop The purpose of the AVR loop is to maintain the generator terminal voltage with in acceptable values. A static accuracy limit in percentage is specified for the AVR, so that the terminal voltage is maintained within that value. For example, if the accuracy limit is 4%, then the terminal voltage must be maintained with in 4% of the base voltage.
The performance of the AVR loop is measured by its ability to regulate the terminal voltage of the generator within prescribed static accuracy limit with an acceptable speed of response. Suppose the static accuracy limit is denoted by A c in percentage with reference to the nominal value. The error voltage is to be less than (A c/100)|V|ref. From the block diagram, for a steady state error voltage e;
Example1: Find the open loop gain of an AVR loop if the static accuracy required is 3%. Solution: if the Given Ac = 3%. K > { 100 - 1}= K > { 100 - 1} = 32.33. Thus, Ac 3
open loop gain of the AVR loop is greater than 32.33, then the terminal voltage will be within 3% of the base voltage.
2.3 Automatic Load Frequency Control The ALFC is to control the frequency deviation by maintaining the real power balance in the system. The main functions of the ALFC are to i) to maintain the steady frequency; ii) control the tie-line flows; and iii) distribute the load among the participating generating units. The control (input) signals are the tie-line deviation Ptie (measured from the tieline flows), and the frequency deviation f (obtained by measuring the angle deviation ). These error signals f and Ptie are amplified, mixed and transformed to a real power signal, which then controls the valve position. Depending on the valve position, the turbine (prime mover) changes its output power to establish the real power balance. The complete control schematic is shown in Fig2.3
Page 33
06EE82
Fig2.3: The Schematic representation of ALFC system For the analysis, the models for each of the blocks in Fig2 are required. The generator and the electrical load constitute the power system. The valve and the hydraulic amplifier represent the speed governing system. Using the swing equation, the generator can be
Fig2.4. The block diagram representation of the Generator The load on the system is composite consisting of a frequency independent component and a frequency dependent component. The load can be written as Pe = P0 + Pf where, Pe is the change in the load; P0 is the frequency independent load component; Pf is the frequency dependent load component. Pf = where, D is called frequency characteristic of the load (also called as damping constant) expressed in percent change in load for 1% change in frequency. If D=1.5%, then a 1% change in frequency causes 1.5% change in load. The combined generator and the load (constituting the power system) can then be represented as shown in Fig2.5
Page 34
06EE82
The turbine can be modeled as a first order lag as shown in the Fig2.6
Fig2.6. The turbine model. Gt(s) is the TF of the turbine; PV(s) is the change in valve output (due to action). Pm(s) is the change in the turbine output The governor can similarly modeled as shown in Fig2.7. The output of the governor is by where Pref is the reference set power, and /R is the power given R by governor speed characteristic. The hydraulic amplifier transforms this signal Pg into valve/gate position corresponding to a power PV. Thus PV(s) = ( Kg/(1+sTg)) Pg(s).
Page 35
06EE82
Fig2.7: The block diagram representation of the Governor All the individual blocks can now be connected to represent the complete ALFC loop as shown in Fig2.8
In the steady state, the ALFC is in open state, and the output is obtained by substituting s0 in the TF. With s0, Gg(s) and Gt(s) become unity, then, (note that Pm = PT = PG = Pe = PD ; That is turbine output = generator/electrical output = load demand) P m = Pref (1/R) or Pm = Pref (1/R) f Pref . When the generator is connected to infinite bus (f = 0, and V = 0), then Pm = If the network is finite, for a fixed speed changer setting ( Pref = 0), then Pm = (1/R) f or If the frequency dependent load is present, then Pm = Pref (1/R +D) f Pm or = D 1/ R
Dept. of EEE, SJBIT Page 36
f = -R Pm.
Power System Operation and Control (PSOC) If there are more than one generator present in the system, then Pm. eq = Pref.eq (D + 1/Req) f where, Pm. eq = Pm1 + Pm2 + Pm.3 +. Pref. eq = VPref1 + Pref2 + VPref3 +.. 1/Req = (1/R1 +1/R2 +1/R2 +.)
06EE82
The quantity = (D + 1/Req) is called the area frequency (bias) characteristic (response) or simply the stiffness of the system.
2.5 Concept of AGC (Supplementary ALFC Loop) The ALFC loop shown in Fig2.8, is called the primary ALFC loop. It achieves the primary goal of real power balance by adjusting the turbine output Pm to match the change in load demand PD. All the participating generating units contribute to the change in generation. But a change in load results in a steady state frequency deviation f. The restoration of the frequency to the nominal value requires an additional control loop called the supplementary loop. This objective is met by using integral controller which makes the frequency deviation zero. The ALFC with the supplementary loop is generally called the AGC. The block diagram of an AGC is shown in Fig2.9. The main objectives of AGC are i) to regulate the frequency (using both primary and supplementary controls); ii) and to maintain the scheduled tie-line flows. A secondary objective of the AGC is to distribute the required change in generation among the connected generating units economically (to obtain least operating costs).
Page 37
Power System Operation and Control (PSOC) 2.6 AGC in a Single Area System
06EE82
In a single area system, there is no tie-line schedule to be maintained. Thus the function of the AGC is only to bring the frequency to the nominal value. This will be achieved using the supplementary loop (as shown in Fig.2.9) which uses the integral controller to change the reference power setting so as to change the speed set point. The integral controller gain KI needs to be adjusted for satisfactory response (in terms of overshoot, settling time) of the system. Although each generator will be having a separate speed governor, all the generators in the control area are replaced by a single equivalent generator, and the ALFC for the area corresponds to this equivalent generator.
2.7 AGC in a Multi Area System In an interconnected (multi area) system, there will be one ALFC loop for each control area (located at the ECC of that area). They are combined as shown in Fig2.10 for the interconnected system operation. For a total change in load of PD, the steady state
Fig.2.10.
Page 38
06EE82
2.8 Expression for tie-line flow in a two-area interconnected system Consider a change in load PD1 in area1. The steady state frequency deviation f is the same for both the areas. That is f = f1 = f2. Thus, for area1, we have where, 1 and 2 are the composite frequency response characteristic of Area1 and Area 2 respectively. An increase of load in area1 by PD1 results in a frequency reduction in both areas and a tie-line flow of P12. A positive P12 is indicative of flow from Area1 to Area 2 while a negative P12 means flow from Area 2 to Area1. Similarly, for a change in Area Frequency bias tie line control The tie line deviation reflects the contribution of regulation characteristic of one area to another. The basic objective of supplementary control is to restore balance between each area load generation. This objective is met when the control action maintains Frequency at the scheduled value
Net interchange power (tie line flow) with neighboring areas at the scheduled values The supplementary control should ideally correct only for changes in that area. In other words, if there is a change in Area1 load, there should be supplementary control only in Area1 and not in Area 2. For this purpose the area control error (ACE) is used (Fig2.9). The ACE of the two areas are given by For area 1: For area 2: ACE1 = P12 + 1 f ACE2 = P21 + 2 f
2.9 Economic Allocation of Generation An important secondary function of the AGC is to allocate generation so that each generating unit is loaded economically. That is, each generating unit is to generate that
Page 39
06EE82
amount to meet the present demand in such a way that the operating cost is the minimum. This function is called Economic Load Dispatch (ELD).
2.10 Systems with more that two areas The method described for the frequency bias control for two area system is applicable to multi-area system also.
Examples: Ex 1. A 500 MVA, 50 Hz, generating unit has a regulation constant R of 0.05 p.u. on its own rating. If the frequency of the system increases by 0.01 Hz in the steady state, what is the decrease in the turbine output? Assume fixed reference power setting. Solution: In p.u. f = 0.01/50 = 0.0002 p.u. With pref = 0, pm = -1/R( f) = - 0.004 p.u. Hence, pm = -0.004 Sbase = - 2 MW. Ex. 2. An interconnected 60 Hz power system consists of one area with three generating units rated 500, 750, and 1000 MVA respectively. The regulation constant of each unit is R= 0.05 per unit on its own rating. Each unit is initially operating at one half of its rating, when the system load suddenly increases by 200MW. Determine (i) the area frequency response characteristic on a 1000 MVA system base, (ii) the steady state frequency deviation of the area, and (iii) the increase in turbine power output. Regulation constants on common system base are (Rpu new = R pu old ( Sbase new/Sbase old): R1 = 0.1; R2 = 0.0667; and R3 = 0.05. Hence = (1/R1 + 1/R2 + 1/R3) = 45 per unit.
Neglecting losses and frequency dependence of the load, the steady state frequency deviation is f = (-1/) pm = -4.444 x10 -3 per unit = (-4.444 x10 -3 )60 = - 0.2667 Hz.
pm1 = (-1/R1)( f) = 0.04444 per unit = 44.44 MW pm2 = (-1/R2)( f) = 0.06666 per unit = 66.66 MW pm3 = (-1/R3)( f) = 0.08888 per unit = 88.88 MW
Page 40
06EE82
UNIT - 4 CONTROL OF VOLTAGE AND REACTIVE POWER: Introduction, generation and absorption of reactive power, relation between voltage, power and reactive power at a node, single machine infinite bus systems, methods of voltage control, sub synchronous resonance, voltage stability, voltage collapse. 8 Hours Control of Voltage and Reactive Power
Reactive power is an odd topic in AC (Alternating Current) power systems, and it's usually explained with vector mathematics or phase-shift sine wave graphs. However, a non-math verbal explanation is possible.
Note that Reactive power only becomes important when an "electrical load" or a home appliance contains coils or capacitors. If the electrical load behaves purely as a resistor, (such as a heater or incandescent bulb for example,) then the device consumes "real power" only. Reactive power and "power factor" can be ignored, and it can be analysed using an AC version of Ohm's law.
Reactive power is simply this: when a coil or capacitor is connected to an AC power supply, the coil or capacitor stores electrical energy during one-fourth of an AC cycle. But then during the next quarter-cycle, the coil or capacitor dumps all the stored energy back into the distant AC power supply. Ideal coils and capacitors consume no electrical energy, yet they create a significant electric current. This is very different from a resistor which genuinely consumes electrical energy, and where the electrical energy flows continuously in one direction; moving from source to load.
In other words, if your electrical appliance contains inductance or capacitance, then electrical energy will periodically return to the power plant, and it will flow back and forth across the power lines. This leads to an extra current in the power lines, a current which heats the power lines, but which
Dept. of EEE, SJBIT Page 41
06EE82
isn't used to provide energy to the appliance. The coil or capacitor causes electrical energy to begin "sloshing" back and forth between the appliance and the distant AC generator. Electric companies must install heavier wires to tolerate the excess current, and they will charge extra for this "unused" energy.
This undesired "energy sloshing" effect can be eliminated. If an electrical load contains both a coil and capacitor, and if their resonant frequency is adjusted to exactly 60Hz, then the coil and capacitor like magic will begin to behave like a pure resistor. The "energy sloshing" still occurs, but now it's all happening between the coil and capacitor, and not in the AC power lines. So, if your appliance contains a large coil induction motor, you can make the motor behave as a pure resistor, and reduce the current in the power lines by connecting the right value of capacitance across the motor coil.
Why is reactive power so confusing? Well, the math is daunting if not entirely obscure. And the concept of "imaginary power" puts many people off. But this is not the only problem. Unfortunately most of us are taught in grade school that an electric current is a flow of energy, and that energy flows back and forth in AC power lines. This is completely wrong. In fact the energy flows constantly forward, going from source to load. It's only the charges of the metal wires which flow back and forth.
Imagine that we connect a battery to a light bulb. Electric charges already present inside the wires will begin to flow in the circle, and then electrical energy moves almost instantly to the light bulb. The charge flow is circular like a belt, but the energy flow is one-way. Now imagine that we suddenly reverse the connections to the battery. The voltage and current will reverse... but the energy still flows in the same direction as before. It still goes from battery to bulb. If we keep reversing the battery connections over and over, we'd have an AC system. So, in an AC system, only the voltage and current are "alternating," while the electrical energy flows one-way, going from source to load. Where AC resistive loads are concerned, electrical energy does not "alternate." To understand energy flow in AC systems, it's critically important that we understand the difference between charge flow (current, amperes) and energy flow (power, watts.)
Dept. of EEE, SJBIT Page 42
06EE82
What is imaginary power? Simple: it's the unused power which flows backwards and forwards in the power lines, going back and forth between the load's coil or capacitor and the distant AC generator. If your appliance was a pure capacitor or inductor, then it would consume no electrical energy at all, but instead all the flowing energy would take the form of "sloshing energy," and we'd call it "imaginary power." Of course it's not actually imaginary. Instead it's reflected by the load.
Page 43
06EE82
Page 44
06EE82
What is real power? Even more simple: it's the energy flow which goes continuously from the AC generator and into the appliance, without any of it returning back to the distant generator.
Finally, what is "reactive" power? It's just the combination of the above two ideas: it is the continuous-forward-moving or "real" energy flow, combined with the sloshing or "imaginary" energy flow. Power in A.C. Networks Active Power Reactive Power Apparent Power Power Factor (p.f.) Power Factor Correction Instantaneous power, p(t) = v(t)i(t) Power, p(t) value positive power transmit/dissipate by load negative power return from the load Since p(t) is power transmits by load, then it is the average power, P at load Sometimes P is also known as active power, real power Watts. or true power measured in unit of
Page 45
06EE82
Page 46
06EE82
P = VI = I R = V /R (Watt) REACTIVE POWER Z = jX L (inductive) Instantaneous power p(t) = v(t)i(t) = VI sin 2t Average power is zero The product of VI is called reactive power Reactive (VAR) Reactive power (inductive) QL = VI = I2 XL = V2/XL (QL) with unit Volt-Amp
Page 47
06EE82
(VAR)
Note: To distinguish between inductive reactive power ( QL) and capacitive reactive power (QC), we use two different signs (+ or ) depending on our reference (i or v), for example jQL and jQC or otherwise.
Note that Reactive power only becomes important when an "electrical load" or a home appliance contains coils or capacitors. If the electrical load behaves purely as a resistor, (such as a heater or incandescent bulb for example,) then the device consumes "real power" only. Reactive power and "power factor" can be ignored,
Reactive power is simply this: when a coil or capacitor is connected to an AC power supply, the coil or capacitor stores electrical energy during one-fourth of an AC cycle. But then during the next quarter-cycle, the coil or capacitor dumps all the stored energy back into the distant AC power supply. Ideal coils and capacitors consume no electrical energy, yet they create a significant electric current. This is very different from a resistor which genuinely consumes electrical energy, and where the electrical energy flows continuously in one
Page 48
Power System Operation and Control (PSOC) direction; moving from source to load. ACTIVE/REACTIVE POWER Example
06EE82
I = 100 V/25 = 4 A, P = VI = (100 V)(4 A) = 400 W, = 0 VAR I = 100 V/20 = 5 A, P = 0, QL = VI = (100 V)(5 A) = 500 VAR (inductive) I = 100 V/40 = 2.5 A, P = 0, QC = VI = (100 V)(2.5) = VAR (capacitive) = 250 VAR Note: use the magnitude of I and V
Determine the total PT and QT for the circuit. Sketch the series equivalent circuit.
Page 49
06EE82
Page 50
06EE82
For load consisting of series resistance and reactance, Z = R + j X = Z / , the power produced is called Apparent Power or Complex Power), S or PS with unit Volt-Amp (VA)
S = V *I S = V *I
S = P + jQ L positive, inductive load negative, capacitive load S = VI (VA) P = VI cos = I R = VR /R (W) = S cos (W) Q = VI sin = I X = Vx /X (VAR) = S sin S = (P + Q ) = V I Power Triangle
S = P jQ
Page 51
Power System Operation and Control (PSOC) POWER TRIANGLE Example Sketch the power triangle.
06EE82
Note that Reactive power only becomes important when an "electrical load" or a home appliance contains coils or capacitors. If the electrical load behaves purely as a resistor, (such as a heater or incandescent bulb for example,) then the device consumes "real power" only. Reactive power and "power factor" can be ignored,
Reactive power is simply this: when a coil or capacitor is connected to an AC power supply, the coil or capacitor stores electrical energy during one-fourth of an AC cycle. But then during the next quarter-cycle, the coil or capacitor dumps all the stored energy
Page 52
06EE82
back into the distant AC power supply. Ideal coils and capacitors consume no electrical energy, yet they create a significant electric current. This is very different from a resistor which genuinely consumes electrical energy, and where the electrical energy flows continuously in one direction; moving from source to load.
Page 53
06EE82
Power factor, p.f. = cos = P/S = R/Z p.f. depends on the load type: o Most of the loads are inductive (lagging p.f.) and must be corrected until p.f. o approximately become unity (p.f. = 1) using capacitor.
Purely resistive load, R , p.f. = 1 Inductive load, RL, p.f. <1 (lagging) and Capacitive load, RC, p.f. < 1 (leading)
Page 54
06EE82 P
POWER FACTOR Example Find the complex power for the circuit. Correct the circuit power factor to p.f. = 1 using parallel reactance.
Page 55
06EE82
Reactive Power is a Byproduct of Alternating Current (AC) Systems Transformers, transmission lines, and motors require reactive power Transformers and transmission lines introduce inductance as well as resistance (Both oppose the flow of current) Must raise the voltage higher to push the power through the inductance of the lines (Unless capacitance is introduced to offset inductance) The farther the transmission of power, the higher the voltage needs to be raised Electric motors need reactive power to produce magnetic fields for their operation Generation and Absorption of Reactive Power Synchronous Generators - Synchronous machines can be made to generate or absorb reactive power depending upon the excitation (a form of generator control) applied. The ability to supply reactive power is determined by the short circuit ratio.
Synchronous Compensators - Certain smaller generators, once run up to speed and synchronized to the system, can be declutched from their turbine and provide reactive power without producing real power. Capacitive and Inductive Compensators - These are devices that can be connected to the system to adjust voltage levels. A capacitive compensator produces an electric field thereby generating reactive power An inductive compensator produces a magnetic field to absorb reactive power. Compensation devices are available as either capacitive or inductive alone or as a hybrid to provide both generation and absorption of reactive power.
Overhead Liines,, Underground Cablles and Transformers.. Overhead lines and underground cables, when operating at the normal system voltage, both produce strong electric fields and so generate reactive power. When current flows through a line or cable it produces a magnetic field which absorbs reactive power. A lightly loaded overhead line is a net generator of reactive power while a heavily loaded line is a net absorber of reactive power. In the case of cables designed for use at 275 or 400kV the reactive power generated by the electric field is always greater than the
Dept. of EEE, SJBIT Page 56
06EE82
reactive power absorbed by the magnetic field and so cables are always net generators of reactive power. Transformers always absorb reactive power.
The phase voltage V at a node is a function of P and Q at that node. i. e V = f (P,Q) The voltage is also independent of adjacent nodes and assume that these are infinite busses. the total differential of V, dV = ( v/ p) . dp + ( v/ Q) . dQ and using the relation ( p/ v) . ( v/ p) = 1 and ( Q/ v) . ( v/ Q) = 1 dv = dp /( p/ v) + dQ / ( Q/ v) ---------(1) From the above equation it is seen that the change in voltage at a node is defined by two quantities, ( p/ v) and ( Q/ v) Normally ( Q/ v ) is the quantity of greater interest and can be experimentally
determined using Network Analyser by injecting known quantity of VARs at the node in question and measuring the difference in voltage produced.
Methods of voltage control By Reactive Power Injection By Tap Changing Transformers Combined use of Tap Changing Transformers and Reactive Power Injection Booster Transformers.
Reactive Power Injection This is the most fundamental method and is used only in places where the transformer alone is not sufficient to control the voltage. since many years we use capacitors to
Dept. of EEE, SJBIT Page 57
06EE82
improve the power factors of industrial loads. The injection of reactive power required for the power factor improvement is determined like this. A load of P 1 kw at a lagging power factor of cos_ 1 has a KVA of P 1 / cos 1. If this power factor is improved to cos 2, the new KVA is P 1 / cos 2. The reactive power required from the capacitors is (P 1 tan 1 P 1 tan 2 ) KVAr Now the question is why the power factor is to be improved. What if the power is transmitted at non unity power factor. We all know very well that the voltage drop depends on reactive power (Q) while the load angle (or) power transmission angle () depends on real power (P) At non unity power factors if the power is transmitted then it results in higher line currents which increases the I
2
thermal capability. one of the ideal place for the injection of reactive power is at the loads itself.
Generally reactive power injections are of the following types. Static shunt capacitors Static series capacitors Synchronous compensators Shunt capacitors and Reactors: shunt capacitors are used for lagging power factor circuits whereas shunt reactors are used for leading power factors that are created by lightly loaded cables. In both the cases the effect is to supply the required amount of reactive power to maintain the voltage. Capacitors are connected either directly to the bus bar or to the tertiary winding of the main transformer and are distributed along the line to minimise the losses and the voltage drops. Now when the voltage drops, the vars produced by shunt capacitor or reactor falls, so when required most, the effectiveness of these capacitors or the reactors also falls. On the other hand, on light loads when the voltage is high, the capacitor output is large and the voltage tends to rise to excessive level, so some of the capacitors or reactors are to be switched out by over voltage relays. For fast control of voltages in power systems, switched capacitors in parallel with semiconductor controlled reactors are generally used to provide var compensation.
Dept. of EEE, SJBIT Page 58
06EE82
Series capacitors:
Here the capacitors are connected in series with the line. The main aim is to reduce the inductive reactance between supply point and the load. The major disadvantage of the method is, whenever a short circuit current flows through the capacitor, protective devices like spark gaps and non linear resistors are to be incorporated. Phasor diagram for a line with series capacitor is shown in the figure (b).
Relative merits between shunt and series capacitors. If the load var requirement is small, series capacitors are of little help. If the voltage drop is the limiting factor, series capacitors are effective, also to some extent the voltage fluctuations can be evened. If the total line reactance is high, series capacitors are very effective and stability is improved. With series capacitors the reduction in line current is small, hence if the thermal considerations limits the current, little advantage is from this, so shunt compensation is to be used.
Dept. of EEE, SJBIT Page 59
06EE82
A synchronous compensator is a synchronous motor running without a mechanical load and depending on the excitation level, it can either absorb or generate reactive power. when used with a voltage regulator the compensator can automatically run overexcited at times of high loads and under excited at light loads. A typical connection of a compensator is shown in the figure along with the associated voltage var output characteristics.
Fig: Typical Installation with synchronous compensator connected to tertiary (delta) winding of main transformer
Page 60
06EE82
A great advantage of the method is the flexible operation for all load conditions. Being a rotating machine, its stored energy is useful for riding through transient disturbances, including voltage drops.
Sub Synchronous Resonance Series capacitors are installed in series with long lines for providing compensation of reactive power and giving higher power transfer ability. Series compensated lines have a tendency to produce series resonance at frequencies lower than power frequencies. This is called Sub Synchronous Resonance (SSR) The sub synchronous resonance currents produce mechanical resonance in Turbo generator shafts, which causes the following in the generator shaft(i)Induction generator effect (ii) torsional torques and (iii) transient torques. These problems have resulted in damage to rotor shafts of turbine generators. Therefore the sub synchronous resonance is analysed in the design of series compensated lines. Now let us derive a relationship between the normal frequency and the sub synchronous resonance frequency.
Dept. of EEE, SJBIT Page 61
06EE82
Let fn be the normal frequency (synchronous) let fr be the sub synchronous frequency of series compensated line. 2_fn L be the series inductive reactance of EHV line at normal frequency. 1/2_fn C be the series capacitive reactance of series compensation at normal frequency.
K = Xc/X L be the degree of compensation. X = (XL Xc) = XL(1 K) is the equivalent reactance of the compensated line. Let the SSR occur at a frequency fr. Then f2= (1/ 2_L ) * (1/ 2_C) (OR) (fr/ fn)2= Xc/XL=Kor fr= fn*sqrt(K) Thus SSR occurs at a frequency fr which is the product of normal frequency and the root of the degree of compensation K. The condition of SSR can occur during the faults on the power system, during switching operations and changing system configurations. Solution to SSR problems 1. Use of filters: For eliminating/damping the harmonics. The various filters include: static blocking filters, bypass damping filters, dynamic filters. 2. Bypassing the series capacitor bank under resonance condition 3. Tripping of generator units under conditions of SSR
Reactive Power and Voltage Collapse Voltage collapse is a system instability and it involves many power system components and their variables at once. Indeed, voltage collapse involves an entire power system although it usually has a relatively larger involvement in one particular section of the power system. Voltage collapse occurs in power systems which are usually Heavily loaded, faulted and/or have reactive power shortages. Voltage collapses can occur in a transient time scale or in a long term time scale. Voltage collapse in a long term time scale can include effects from the transient time scale; for example, a slow voltage collapse taking several minutes may end in a fast voltage collapse in the transient time scale.
06EE82
There are several power system disturbances which contribute to the voltage collapse. i. increase in inductive loading ii. Reactive power limits attained by reactive power compensators and generators. iii. On Load Tap Changing operation iv. Load recovery dynamics. v. Generator outage vi. Line tripping. most of these factors have significant effects on reactive power production, transmission and consumption. Switching of shunt capacitors, blocking of OLTC operation, generation rescheduling, bus voltage control, strategic load shedding and allowing temporary reactive power over loading of generators may be used as some of the effective countermeasures against voltage collapse.
Voltage Stability The voltage stability may be defined as the ability of a power system to maintain steady acceptable voltage at all busses in the system at normal operating conditions and after being subjected to disturbances/ perturbations. OR Voltage stability is the ability of a system to maintain voltage so that when load admittance is increased, load power will increase, and so that both power and voltage are controllable. Power system is Voltage Stable if voltages at respective busses after a disturbance are close to the voltages at normal operating conditions. So voltage instability is that appears when the attempt of load dynamics to restore power consumption is just beyond the capability of the combined transmission and generator system. Though voltage instability may be a local problem, its consequences may have a widespread effect. Voltage collapse is the catastrophic result of a sequence of events leading to a sudden low-voltage profile in a major part of the system, i.e. in a significant part of the system. Voltage Stability can also be called Load Stability. A Power system
Dept. of EEE, SJBIT Page 63
06EE82
lacks the capability to transfer an infinite amount of electrical power to the loads. The main factor causing voltage instability is the inability of the power system to meet the demands for reactive power in the heavily stressed system keeping desired voltages. Other factors contributing to voltage instability are the generator reactive power limits. Transfer of reactive power is difficult due to extremely high reactive power losses, which is why the reactive power required for voltage control is generated and consumed at the control area. A classification of power system stability is shown in the table below. The driving forces for instability are named generator driven and load-driven. It is to be noted that these terms do not exclude the effect of other components to the mechanism. The time scale is divided into short and long-term time scale. Now let us analyse voltage stability using Q-V curves. Consider a simple system as shown below and its P-V curves.
Page 64
06EE82
Fig: Normalised P-V curves for fixed (infinite) source Now map the normalised P-V curves onto V-Q curves. for constant value of P, note the values of Q and V and then re plot to get Q-V curves as shown below. from P-V curves it is observed that the critical voltage is very high for high loadings. V is above 1.0p.u for P = 1.0p.u The right side represents normal conditions where applying a capacitor bank raises voltage.
Page 65
06EE82
Fig
Curves
Page 66
06EE82
Figure shows the Q-V diagram of a bus in a particular power system at four different loads: P1, P2, P3, P4 . the Q axis shows the amount of additional reactive power that must be injected into the bus to operate at a given voltage. The operating point is the intersection of the power curve with the voltage axis, where no reactive power is required to be injected or absorbed. If the slope of the curve at the intersection point is positive, the system is stable, because any additional reactive power will raise the voltage and vice-versa. Hence for P 1 load, there is a reserve of reactive power that can be used to maintain stability even if the load increases. For load P 2 the system is marginally stable. For higher load P3 and P4 the system is not stable (Since a certain amount of reactive power must be injected into the bus to cause an intersection with the voltage axis.) Thus the measure of Q reserve gives an indication of the margin between stability and instability. The slope of the Q-V curve represents the stiffness of the test bus. when nearby generators reach their Var limits, the slope of the Q-V curve becomes less steep and the bottom of the curve is approached. V-Q curves are presently the workhorse method of voltage stability analysis at many utilities. Since the method artificially stresses a single bus, conclusions should be confirmed by more realistic methods.
Page 67
06EE82
Page 68
06EE82
PART - B
UNIT 5 & 6 POWER SYSTEM OPTIMIZATION: Optimal system operation with thermal plants, incremental production cost for steam power plants, analytical form of generating cost of thermal plants, constraints in economic operation, flow chart, transmission loss as a function of plant generation, the B-coefficients, examples.
UNIT COMMITMENT: Statement of the problem, need and importance of unit commitment, methods-priority lists method, dynamic programming method, constraints, spinning reserve, and examples.
(x) Introduction (xi) Problem of economic load scheduling (xii) Performance curves (xiii) (xiv) Constraints in economic operation of power systems Spinning reserve
(xv) Solution to economic load dispatch Solution to ELD without inequality constraints Solution to ELD with capacity constraints
Solution
to
ELD
with
Transmission
losses
considered-
LOSS
06EE82
INTRODUCTION
In EPS, the first step is to properly assess the load requirement of a given area where electrical power is to be supplied. This power is to be supplied using the available units such as thermal, hydroelectric, nuclear, etc. Many factors are required to be considered while choosing a type of generation such as: kind of fuel available, fuel cost, availability of suitable sites for major station, nature of load to be supplied, etc.
Variable load: The load is not constant due to the varying demands at the different times of the day. The EPS is expected to supply reliable and quality power. It should ensure the continuity of power supply at all times.
{Qn.: write a note on the choice of the number and size of the generating units at a power station from economic operation point of view}
Single unit Vs. multiple units: the use of a single unit to supply the complete load demand is not practical since, it would not be a reliable one. Alternately, a large number of smaller units can be used to fit the load curve as closely as possible. Again, with a large number of units, the operation and maintenance costs will increase. Further, the capital cost of large number of units of smaller size is more as compared to a small number of units of larger size. Thus, there has to be compromise in the selection of size and number of generating units within a power plant or a station.
Electric energy is generated at large power stations that are far away from the load
Dept. of EEE, SJBIT Page 70
06EE82
centers. Large and long transmission lines (grid lines) wheel the generated power to the substations at load centers. Many electrical equipment are used for proper transmission and distribution of the generated power. The grid lines are such that:
Each grid operates independently, although power can be exchanged between various grids.
Optimum economic efficiency is achieved when all the generators which are running in parallel are loaded in such a way that the fuel cost of their power generation is the minimum. The units then share the load to minimize the overall cost of generation. This economical approach of catering to the load requirement is called as economic dispatch. The main factor in economic operation of power sy stems is the cost of generating the real power. In any EPS, the cost has two components as under:
The Fixed Costs: Capital investment, interest charged on the money borrowed, tax paid, labour, salary, etc. which are independent of the load variations.
The Variable Costs: which are dependant on the load on the generating units, the losses, daily load requirements, purchase or sale of power, etc.
The current discussion on economic operation of power systems is concerned about minimizing the variable costs only.
Page 71
06EE82
Further, the factors affecting the operating cost of the generating units are: generator efficiency, transmission losses, fuel cost, etc. Of these, the fuel cost is the most important factor.
Since a given power system is a mix of various types of generating units, such as hydel, thermal, nuclear, hydro-thermal, wind, etc., each type of unit contributes its share for the total operating cost. Since fuel cost is a predominating factor in thermal (coal fired) plants, economic load dispatch (ELD) is considered usually for a given set of thermal plants in the foregoing discussion.
There are two problem areas of operation strategy to obtain the economic operation of power systems. They are: problem of economic scheduling and the problem of optimal power flow.
* The problem of economic scheduling: This is again divided into two categories:
The unit commitment problem (UCP): Here, the objective is to determine the various generators to be in operation among the available ones in the system, satisfying the constraints, so that the total operating cost is the minimum. This problem is solved for specified time duration, usually a day in advance, based on the forecasted load for that time duration.
The economic load dispatch (ELD): Here, the objective is to determine the generation (MW power output) of each presently operating (committed or put on) units to meet the specified load demand (including the losses), such hat the total fuel cost s minimized.
* The problem of optimal power flow: Here, it deals with delivering the real power to the load points with minimum loss. For this, the power flow in each line is to be optimized
Dept. of EEE, SJBIT Page 72
Power System Operation and Control (PSOC) to minimize the system losses.
06EE82
{Qn.: compare ELD and UCP and hence bring out their importance and objectives.}
PERFORMANCE CURVES:
The Performance Curves useful for economic load dispatch studies include many different types of input-output curves as under:
1. Input Output Curve: A plot of fuel input in Btu/Hr. as a function of the MW output of the unit.
2. Heat Rate Curve: A plot of heat rate in Btu/kWH, as a function of the MW output of the unit. Thus, it is the slope of the I-O curve at any point. The reciprocal of heat rate is termed as the Fuel Efficiency.
3. Incremental Fuel Rate Curve: A plot of incremental fuel rate (IFC) in Btu/kWH as a function of the MW output of the unit, where, IFC=
input/ output
4. Incremental Fuel Cost Curve: A plot of incremental fuel cost (IFC) in Rs./kWH as a function of the MW output of the unit, where, IFC in Rs./kWH = (Incremental fuel rate in Btu/kWH) (Fuel cost in Rs./Btu) (2)
The IFC is a measure of how costlier it will be to produce an increment of power output by that unit.
The Cost Curve can be approximated by: * Quadratic Curve by the function: C i(Pi) = ai+biPi+ciPi2 Rs./Hr.
Page 73
(3)
Power System Operation and Control (PSOC) * Linear curve by the function: d(Ci)/dPi =bi+2ciPi Rs./MWHr.
06EE82 (4)
Generally, the quadratic curve is used widely to represent the cost curve, with the IC curve given by the linear curve as above.
Various constraints are imposed on the problem of economic operation of power systems as listed below: 1. Primary constraints (equality constraints):
Power balance equations: Pi - PDi - Pl =0; Qi - QDi - Ql =0; i=buses of the system where, Pl= ViVjYij cos (ij-ij); Ql= ViVjYij sin (ij-ij); j = 1,2,.n, are the power flow to the neighboring system. (6) (5)
The above constraints arise due to the need for the system to balance the generation and load demand of the system.
Page 74
Power System Operation and Control (PSOC) 2. Secondary constraints (inequality constraints):
06EE82
These arise due to physical and operational limitations of the units and components. Pimin Pi Pimax Qimin Qi Qimax i = 1,2,.n, the number of generating units in the system. (7)
These are used to account for the errors in load prediction, any sudden or fast
change in load demand, inadvertent loss of scheduled generation, etc. Here, the total generation available at any time should be in excess of the total anticipated load demand and any system loss by an amount not less than a specified minimum spare capacity, PSP (called the Spinning Reserve) given by: PlG (Generation) Pl (Losses) + PSP + PDj (Load) 4. Thermal Constraints: (8)
For transmission lines of the given system: - Simin Sbi Simax i = 1,2,.nb, the number of branches, where, Sbi is the branch transfer MVA. (9)
Bus voltage and Bus angle Constraints are needed to maintain a flat bus voltage
Dept. of EEE, SJBIT Page 75
Power System Operation and Control (PSOC) profile and to limit the overloading respectively. - Vimin Vi Vimax - ijmin ij ijmax i = 1,2,.n i = 1,2,.n; j = 1,2,.m
06EE82
(10)
where, n is the number of nodes and m is the number of nodes neighboring each node with interconnecting branches.
6. Other Constraints:
In case of transformer taps, during optimization, it is required to satisfy the constraint: Timin Ti Timax where Ti is the percentage tap setting of the tap changing transformer used. In case of phase shifting transformers, it is required to satisfy the constraint: PSimin PSi PSimax where PSi is the phase shift obtained from the phase shifting transformer used. (12) (11)
SPINNING RESERVE
Spinning reserve (SR) is the term used to describe the total amount of generation available from all the synchronized (spinning) units of the system minus the present load plus the losses being supplied. i.e., Sp.Res., PSP = {Total generation, PlG} - { PDj(load) + Pl (losses)} (13)
Page 76
06EE82
The SR must be made available in the system so that the loss of one or more units does not cause a large drop in system frequency. SR must be allocated to different units based on typical Council rules. One such rule is as follows: SR must be capable of making up for the loss of the most heavily loaded unit in the system Reserves must be spread around the system to avoid the problem of bottling of reserves and to allow for the various parts of the system to run as islands, whenever they become electrically disconnected.
{Qn.: Write a brief note on the following: Spinning Reserve, constraints in economic operation, performance curves}
{Qn.: Derive the EIC criterion for economic operation of power systems with transmission losses neglected, MW limits considered/ not considered}
The solution to economic load dispatch problem is obtained as per the equal incremental cost criterion (EIC), which states that: All the units must operate at the same incremental fuel cost for economic operation
This EIC criterion can be derived as per LaGrangian multiplier method for different cases as under.
Page 77
06EE82
Consider a system with N generating units supplying a load P D MW. Let the unit MW limits and the transmission losses are negligible. Suppose the fuel cost of unit i is given by: Ci(Pi) = ai+ biPi+ ciPi2 Rs./Hr. so that
The ELD problem can thus be stated mathematically as follows: CT = Ci(Pi) i = 1,2, N Pi = PD (15)
where, CT is the total fuel cost of the system in Rs./Hr., P D is the total demand in MW and Pi is the MW power output of unit i. The above optimization problem can be solved by LaGranjes method as follows.
The LaGranje function L is given by: L = CT + (PD Pi) The minimum cost value is obtained when: L/Pi = 0; and L/ = 0 (17) (16)
Page 78
06EE82
Further, since the cost of a given unit depends only on its own power output, we have, CT/Pi = Ci/Pi = dCi/dPi Thus, dCi/dPi = 0 i = 1,2, N or (19) i= 1,2, N (18)
The equation above is stated in words as under: For the optimum generation (power output) of the generating units, all the units must operate at equal incremental cost (EIC) Expression for System Lambda, :
Solving, we get,
(20)
Consider a system with N generating units supplying a load P D MW. Let the unit MW limits be considerable and the transmission losses be negligible. Suppose the fuel cost of unit i is given by: Ci(Pi) = ai+ biPi+ ciPi2 CT = Ci(Pi)
Dept. of EEE, SJBIT
Rs./Hr. i= 1,2, N
Page 79
Power System Operation and Control (PSOC) The ELD problem can now be stated mathematically as follows: CT = Ci(Pi) i = 1,2, N Pi = PD and ma Pimin Pi Pi x (21)
06EE82
where, CT is the total fuel cost of the system in Rs./Hr., P D is the total demand in MW, Pi is the MW power output of unit i, Pimin is the minimum MW power output and Pimax is the maximum power output by the unit i. The necessary conditions for the solution of the above optimization problem can be obtained as follows: i = dCi/dPi = i = Rs./MWHr. for Pimin Pi Pimax for Pi = Pimax for Pi = Pimin (22) Rs./MWHr. dCi/dPi i Rs./MWHr. = dCi/dPi
Page 80
06EE82
From the above equations, if the outputs of the unit, according to optimality rule, is: * Less than its minimum value, then it is set to Pimin, the corresponding IC will be greater than the system , * More than its maximum value, then it is set to Pimax, the corresponding IC will be less than the system ,
* With in its maximum and minimum values, then the corresponding IC will be equal to the system .
1. First, find the power output according to the optimality rule (EIC Criterion)
2. If the power output of any unit is less than its minimum value, then set the value to be equal to its Pimin,
3. Similarly, if the power output of any unit is more than its maximum value, then set the value to be equal to its Pimax,
4. Adjust the demand for the remaining units after accounting for the settings made for the above units (those units which have violated the limits)
5. Finally, apply the EIC criterion, for the remaining units. Here, the system lambda is determined by only those units whose power output values are with in the specified MW limits.
Page 81
06EE82
CASE (iii) Solution to ELD with Transmission losses consideredPENALTY FACTOR METHOD
{Qn.: Derive the EIC criterion for economic operation of power systems with transmission losses considered. Use penalty factor method}
Consider a system with N generating units supplying a load P D MW. Let the transmission losses be considerable. Suppose the fuel cost of unit i is given by: Ci(Pi) = ai+ biPi+ ciPi2 CT = Ci(Pi) Rs./Hr. i= 1,2, N so that the total cost,
Let PL be the total transmission losses in the system. The ELD problem can now be stated mathematically as follows:
where, CT is the total fuel cost of the system in Rs./Hr., P D is the total demand in MW, Pi is the MW power output of unit i, PL is the transmission losses in the system. This above optimization problem can be solved by LaGranjes method as follows.
(24)
Page 82
Power System Operation and Control (PSOC) The minimum cost value is obtained when: L/Pi = 0; and L/ = 0 (25)
06EE82
CT/Pi (1-PL/Pi)=0 and Pi-PDPL=0 (which is same as the constraint given) Further, since the cost of a given unit depends only on its own power output, we have, CT/Pi = Ci/Pi = dC i/dPi Thus, dCi/dPi (1- dPL/dPi) = 0 dCi/dPi = ICi = (1- dPL/dPi) So that we have for optimal operation, = ICi /(1- dPL/dPi) = ICi (1- dPL/dPi)-1 = Pni ICi Where, Pni is the penalty factor of unit i = (1- dPL/dPi)-1 = (1-ITLi)-1 ; ITLi = dPL/dPi is the Incremental Transmission Loss of unit i, and is in Rs./MWHr. (26) i = 1,2, N or i= 1,2, N
The equation above is stated in words as under: For the optimum generation (power output) of the generating units, when the transmission losses are considered, all the units must operate such that the product of the incremental fuel cost and their penalty factor must be the same for all units
Note: in equation (26), if losses are negligible as in case (i) above, then, ITLi = dPL/dPi = 0, Pni=1.0 so that = ICi i = 1,2, N, as before.
CASE (iv) Solution to ELD with Transmission losses consideredLOSS COEFFICIENTS METHOD
Page 83
Power System Operation and Control (PSOC) {Qn.: Derive the EIC criterion for economic operation
06EE82 of power
systems with
Derive an expression for the transmission loss as a function of the plant generations.}
Consider a system with two generating units supplying currents I 1 and I2 respectively to the load current IL. Let Ik1 and Ik2 be the respective currents flowing through a general transmission branch element k of resistance R k, with current Ik as shown in figure 1 below.
Page 84
06EE82
Figure 1.
(27)
Where, Nk1 and Nk2 (assumed to be real values) are the current distribution factors of units 1 and 2 respectively.
It is assumed that the currents Ik1 and IL as well as Ik2 and IL have the same phase angle or they have a zero phase shift. Thus, they can be added as real numbers as under. I1 = I1 1 = I1cos 1+ jI1sin 1 I2 = I2 2 = I2cos 2+ jI2sin 2 (28)
Let
Where 1 and 2 are the phase angles of currents. Consider now, the magnitude of current Ik, in branch k, given by Ik = {Nk1I1cos 1+ j Nk1I1sin 1} + {Nk2I2cos 2+ j Nk2I2sin 2} = {Nk1I1cos 1+ Nk2I2cos 2} + j{Nk1I1sin 1 + Nk2I2sin 2} Thus,
Dept. of EEE, SJBIT Page 85
Power System Operation and Control (PSOC) Ik2 = Nk1I12 + Nk2I22 + 2 Nk1Nk2I1I2 cos(1-2) However, we have, P1 = 3V1I1cos1; P2 = 3V2I2cos2; PL = 3Ik2Rk
06EE82 (29)
(30)
where, P1 and P2 are the MW power output values by the units 1 and 2 respectively, V1 and V2 are the respective line voltages and 1, 2 are the respective power factor angles and PL is the transmission loss in the system. From equations (29) and (30),
Page 86
06EE82
after simplification, an expression for the transmission loss as a function of plant generation can be obtained as: PL = Nk12RkP12/(V12cos21) + Nk22RkP22/(V22cos22) + 2 Nk1Nk2RkP1P2 cos(1-2)/ (V1V2cos1cos2) = B11P12 + B22P22 + 2 B12P1P2 (31)
Where, the B coefficients are called as the loss coefficients. Thus, in general, for a system of n units we have, PL = PiBijPj Where, i j (32) Bij = {cos(i-j)/ (ViVjcosicosj) NkiNkjRk
Note: 1. The B coefficients are represented in units of reciprocal MW, (MW-1) 2. For a three unit system , equation (32) takes the form: PL = B11P12 + B22P22 + B33P32 + 2 B12P1P2+2 B13P1P3+ 2 B23P2P3 = PTBP (33)
Where, P = [P 1 P2 P3], the vector of unit power output values and B = [B11 B33] the loss coefficient matrix for the 3 unit system. B12 B13; B21 B22 B23; B31 B32
3. The B coefficient matrix is a square, symmetric matrix of order n, n being the number of generating units present in the system. 4. The following are the assumptions made during the above analysis: All load currents maintain a constant ratio to load current
06EE82
The power factor of each bus source is constant (i=constant). The voltage phase angle at load buses is constant (i=constant).
5. The Incremental Transmission loss, ITLi of a given unit can be expressed in terms of its MW power output values as under:
Page 88
06EE82
Example-1:
The I-O characteristics of two steam plants can be expressed analytically as under (with P1 and P2 in MW): F1 =(2.3P1+0.0062 P12 + 25)106
The calorific value of coal at plant#1 and plant#2 are respectively equal to 4000 kCals/kg. and 5000 kCals/kg. The corresponding cost of coal is Rs.55/- and Rs.65/-per Ton. Find the following: (i)Incremental Fuel Rate in kCals/MWHr (ii)Incremental Fuel Cost in Rs./MWHr and (iii)Incremental Production Cost in Rs./MWHr if the cost of other items can be taken as 10% of the incremental fuel cost/plant.
Solution:
(i)Incremental Fuel Rate in kCals/MWHr IFR1=dF1/dP1 = (2.3+0.0124P1)106 kCals/MWHr IFR2=dF2/dP2 = (1.5+0.02P2)106 kCals/MWHr (ii)Incremental Fuel Cost in Rs./MWHr
Page 89
06EE82
IC1= [dF1/dP1 in kCals/MWHr] [cost of coal in Rs./ton] [calorific value -1 = (2.3+0.0124P1)106 (55) (1/4000) (10-3) = 31.625 + 0.1705 P1 Rs./MWHr. IC2= [dF2/dP2 in kCals/MWHr] [cost of coal in Rs./ton] [calorific value-1 = (1.5+0.02P2)106 (65) (1/5000) (10-3)
= 19.9 + 0.26 P2 Rs./MWHr. (iii)Incremental Production Cost in Rs./MWHr if the cost of other items can be taken as 10% of the incremental fuel cost/plant.
Example-2:
The incremental costs of a two unit system are given by: IC1 = (0.008 PG1 + 8.0); IC2 = (0.0096 PG2 + 6.4) Find the incremental cost and the distribution of loads between the two units for optimal operation for a total load of 1000 MW. What is
Dept. of EEE, SJBIT Page 90
06EE82
this value if the same total load is equally shared among the two units?
Solution:
For the total load values of PT = 1000 MW, if the load is shared equally among the two units then:
PG1 = 500 MW; PG2 = 500 MW with 1 = 12 Rs./MWHr and 2 = 11.2 Rs./MWHr. (unequal lambda values)
Now, for optimal operation, we have as per EIC principle, the ICs to be equal.
i.e.,
IC1=IC2;
PT = P1+P2 = 1000
are the equations to be solved for the output power values. Thus,
IC1 =0.008 PG1 + 8.0= IC2 = 0.0096 PG2 + 6.4 = 0.0096 (1000 - PG1) + 6.4
Solving, we get,
Further, system is calculated using any one of the IC equations as: system = 1 = 2 = 11.64 Rs./MWHr. Thus, with system = 1 = 2 = 11.64 Rs./MWHr, the total load is optimally shared between the two units and the operating cost would be at its minimum.
Dept. of EEE, SJBIT Page 91
06EE82
The fuel costs in Rs./Hr. for a plant of three units are given by: C1=(0.1P12+40P1+100); C2=(0.125P22+30P2+80); C3=(0.15P32+20P3+150); Find the incremental cost and the distribution of loads between the three units for optimal operation for a total load of 400 MW, given that the max. and min. capacity limits for each of the units as 150 MW and 20 MW respectively.
Solution:
Consider the incremental cost curves given by: ICi= dCi/dPi = (2ciPi+bi) Rs./MWHr IC1=dC1/dP1 = (0.20P1+40) Rs./MWHr IC2=dC2/dP2 = (0.25P2+30) Rs./MWHr and
For the total load values of PT = 400 MW, for optimal operation, as per EIC principle, the ICs are equal. i.e., IC1=IC2=IC3; and PT = P1+P2+P3 = 400 MW. Also, the system lambda is given by: = {PD+(bi/2ci)}/ {(1/2ci)}
i= 1,2,3
Substituting
the
values,
we
get
after
Using this value of common system lambda, the MW output values of all the 3 units are obtained from their IC curves as: P1= 118.9 MW, P2= 135.12 MW and P3=91.90 MW.
Page 92
06EE82
(All the MW output values are found to be within their capacity limits specified) Thus, with system = 1 = 2 = 3 =63.78 Rs./MWHr, the total load is optimally shared between the three units and the operating cost would be at its minimum.
Example-4:
The incremental costs of a two unit system are given by: IC1 =0.008 PG1 + 8.0 ; IC2 =0.0096 PG2 + 6.4 Find the incremental cost and the distribution of loads between the two units for optimal operation for a total load of 900 MW. Also determine the annual saving in cost in optimal operation as compared to equal sharing of the same total load.
Solution:
For a total load of PT = 900 MW, if the load is shared equally among the two units then: PG1 = PG2 = 450 MW. Now, for optimal operation, we have as per EIC principle, the ICs to be equal. i.e., IC1=IC2; PT = P1+P2 = 900 are the equations to be solved for the output power values.
=0.008 PG1
Page 93
Power System Operation and Control (PSOC) instead of 400 MW (optimal sharing) is given by:
06EE82
sharing) instead of 500 MW (optimal sharing) is given by: C2= IC2 dPG2 = (0.0096PG2+6.4) dPG2 = |(0.0096PG22+6.4PG2)|500450 = Rs. 548/hr.
Thus, the net saving in cost in optimal operation is given by: Rs. 570 548 = Rs. 22/- per hour or it is equivalent to an annual saving in cost of (assuming continuous operation): Rs.(22)(24)(365) = Rs. 1,92, 720/- PA.
Example-5:
The fuel costs of a two generator system are given by: C1 =1 + 1P1+ 1P12; C2 =2 + 2P2+ 2P22 Where, 1=40, 2=30, 1=0.1, 2=0.125, and 1,2 are constants. How will the load of
150 MW be shared optimally between the two units? Also determine the saving in cost in Rs./Hr. in optimal operation as compared to equal sharing of the same total load.
Page 94
06EE82
Consider the incremental cost curves given by: IC1=dC1/dP1 = 1+ 1P1 = 40+0.2P1 Rs./MWHr IC2=dC2/dP2 = 2+ 2P2 = 30+0.25P2 Rs./MWHr
For a total load of PT = 150 MW, if the load is shared equally among the two units then: PG1 = PG2 = 75 MW. Now, for optimal operation, we have as per EIC principle, the ICs to be equal. i.e., IC1=IC2; PT = P1+P2 = 150 are the equations to be solved for the output power values.
Thus,
IC1
=40+0.2P1
IC2
30+0.25P2
30+0.25 Solving,
(150-P1) we
The increase in cost of operation by Unit 1 if it supplies 75 MW (equal sharing) instead of 61.11 MW (optimal sharing) is given by: C1= IC1 dPG1 = (40+0.2P1) dP1 = |(40P1+0.1P12)|61.1175 = Rs.737.344/hr. Similarly, the decrease in cost of operation by Unit 2 if it supplies 75 MW (equal sharing) instead of 88.89 MW (optimal sharing) is given by: C2= IC2 dPG2 = (30+0.25P2) dPG2 = |(30P2+0.125P22)|88.8975 = Rs. - 707/hr. Thus, the net saving in cost in optimal operation is given
Dept. of EEE, SJBIT Page 95
Power System Operation and Control (PSOC) by: Rs. 737.344 707 = Rs. 30.344/- per hour
06EE82
(or it is equivalent to an annual saving in cost of (assuming continuous operation): Rs.(30.3)(24)(365) = Rs. 2,62,800/- PA)
Example-6:
The fuel cost function in Rs./Hr. for three thermal plants is given by the following (with Ps in MW): F1 = 350 + 7.20 P1 + 0.0040 P 1 2 F2 = 500 + 7.30 P2 + 0.0025 P 2 2 F3 = 600 + 6.74 P3 + 0.0030 P 3 2
Find the optimal schedule for a total load of 450 MW. Also compute the costs of operation for this schedule. Compare the same when the three generators share the same total load equally among them.
Solution:
IC1=dF 1/dP1 = 7.2+0.008P1 Rs./MWHr IC2=dF 2/dP2 = 7.3 + 0.005P 2 Rs./MWHr and = 6.74 + Rs./MWHr
For optimal operation, we have as per EIC, the common lambda of the system given
Dept. of EEE, SJBIT Page 96
06EE82
by:
Using this value of common system lambda, the MW output values of all the 3 units are obtained from their IC curves as: P1= 100 MW, P2= 140 MW and P3=210 MW.
The operating costs for this schedule are found by using the cost curves as: FT(Optimal operation) = F1+F2+F3 = 1110+1571+2147.7 = 4828 Rs./Hr.
Similarly, the operating costs for the equal sharing of total load are also found by using the cost curves as: (with P1= P2= P3=150 MW.
FT(Equal sharing) = F1+F2+F3 = 1520+1621.25+1078.5 = 4849.5 Rs./Hr. Thus, saving in cost in optimal operation is: 4849.5 4828 = Rs.21.75/- per hour.
Example-7:
Given that IC1=(40+0.2P1) ; IC2 =(30+0.25P2) Calculate and tabulate the load shared by each unit for optimal operation if the total load varies from 50 to 250MW, in steps of 50MW, given that max.MW is 125 and min. MW is 20 for both the units.
Page 97
Power System Operation and Control (PSOC) IC1|P1=P1min = 20MW = 40+0.2(20) = 44 Rs./MWHr IC2|P2=P2min = 20MW = 30+0.25(20) = 35 Rs./MWHr
06EE82
Thus, IC2 < IC1 ; i.e., the EIC holds good only from the stage where, the system lambda is equal to 44 Rs./MWHr. Now find P2 corresponding to this Lambda: P2|2=44 = (44 30)/0.25 = 56 MW so that then PTotal = 20 + 56 = 76 MW
Thus, until PT=76 MW, EIC will not be feasible, Unit 1 will work at its minimum load 20 MW and all the additional load is shared by unit 2 alone till =44 Rs./MWHr.
Stage 2:
IC2|P2=P2max
125MW
= 30+0.25(125) = 61.25
Rs./MWHr P1|1=61.25 = (61.25 40)/0.2 = 106.25 MW so that then PTotal = 106.25+125= 231.25 MW
Thus, after PT=231.25MW, EIC ceases to hold good; Unit 2 will work at its maximum load sharing of 125 MW only and all the additional load variations are shared by unit 1 alone untill P1 also reaches 125 MW.
Page 98
06EE82
limits:
and
For the total load values of PT = 100, 150 and 200 MW, the equations to be solved for the output power values are: IC1=IC2; PT = P1+P2 and system is calculated using any one of the IC equations. The values so obtained for the said range of load values are tabulated as under.
Sl. No. 1. 2. 3. 4. 5. 6. 7.
P1 20 (fixed) 20
P2 30 56
syste m 44
Unit 1 and Unit 2 share the total load as per 33.33 66.67 46.67 EIC 61.11 88.99 52.22 Criterion. The system 88.88 111.11 57.78 works with a common system lambda 106.25 125 61.25 125 125 61.25 Unit 1 only shares (fixed (fixed) the additional load )
Example-8: Given thatF1 =110 + 30P1+ 0.09P12 F2 =135 + 12P 2+ 0.1P 2 2 12 P1 125 MW 25 P2 125 MW
Calculate and tabulate the load shared by each unit for optimal sharing of the total load in the range 50-250 MW in steps of 100 MW. Also find system in each case.
Page 99
06EE82
Solution:
IC1|P1=P1min Rs./MWHr
12MW
32.16
Rs./MWHr IC2|P2=P2min = 25 MW = 17
Thus, IC2 < IC1 ; i.e., the EIC holds good only from the stage where, the system lambda is equal to 32.16 Rs./MWHr. Now find P2 corresponding to this Lambda: P2|2=32.16 = 100.8 MW so that then PTotal = 112.8 MW
Thus, until PT=112.8 MW, EIC will not be feasible, Unit 1 will work at its minimum load, 12 MW and the additional load is shared by unit 2 alone till =32.16 Rs./MWHr.
Stage 2: Consider the ICs at Pmax: since the Unit 2 is expected to reach its max. limit earlier, find:
Page 100
06EE82
Thus, after PT= 163.88 MW, EIC ceases to hold good; Unit 2 will work at its maximum load sharing of 125 MW only and all the additional load variations are shared by unit 1 alone untill P1 also reaches 125 MW.
Stage 3: In summary, EIC holds good only for PT and system values which satisfy the limits: 112.8 PT 163.88 MW and 32.16 system 37 Rs./MWHr
For the total load value of PT = 150 MW, where the EIC holds good, the equations to be solved for the output power values are: IC1=IC2; PT = P1+P2 and system is calculated using any one of the IC equations. The values so obtained for the said range of load values are tabulated as under.
Sl. No. 1. 50
PT
P1 12 (fixed)
P2 38
2.
112.8
12
3. 4. 5.
150
31.58
(fixed) the additional load Unit 1 and Unit 2 share 100.8 32.16 the total load as per EIC Criterion. The system 118.42 35.67 works with a common 125 37 system lambda Unit 1 only shares 125 37 (fixed) (fixed) the additional load
Page 101
06EE82
The maximum and minimum loads on the units are 100 MW and 10 MW respectively. Determine the minimum cost of generation for supplying a load as follows based on the EIC criterion: Load 12 Midnight 6 am 12 noon 2-6 pm 120 6-9 9pm 12 pm Midnight 50
12 noon -2 pm 100 80
175
MW
Thus, IC2 < IC1 ; i.e., the EIC holds good only from the stage where, the system lambda is equal to 29.6 Rs./MWHr. Now find P2 corresponding to this Lambda: P2|2=29.6 = 38.4 MW so that then PTotal = 48.4 MW However all the required loads to be supplied are above this total load of 48.4 MW!
Stage 2:
06EE82
IC2|P2=P2max = 100MW = 45 Rs./MWHr P2|1=44 = 96 MW so that then PTotal = 196 MW Again, it is observed that all the required loads to be supplied are below this total load of 196 MW!
In summary, EIC holds good for all the load values specified. Now for the total load value of PT = P1+P2, where EIC is shown to holds good, the equations to be solved for the output power values are: IC1=IC2; PT = P1+P2 and system is calculated using any one of the IC equations. The values so obtained for the said range of load values are tabulated as under.
Example-10:
Assume that the fuel input in Btu/Hr. for unit 1 and unit 2 of a plant are given by: F1 = {P1+ 0. 024P12+80}106; F2={6P2+ 0.04P22 +120)106
The maximum and minimum loads on the units are 100 MW and 10 MW respectively. Determine the minimum cost of generation for supplying a load as follows with the fuel cost at Rs.2 per MBtu. 12 Midnight 6 am 6 pm 12 Duration 6 am 6 pm Midnight Load 50 MW 150 MW 50 MW Load
Page 103
06EE82
MW
Thus, IC2 >IC1; i.e., the EIC holds good only from the stage where, the system lambda is equal to 13.6 Rs./MWHr. Now find P1 corresponding to this Lambda: P1|1=13.6 = 120.833 MW (>P1max) (so that then PTotal = 130.833 MW)
Thus, until PT=130.833 MW, EIC will not be feasible, Unit 2 will work at its minimum load of 10 MW and the additional load is shared by unit 2 alone till =13.6
Rs./MWHr. However, this is not further feasible since the unit 1 reaches its max. value of 100 MW within this range!!! Hence, EIC ceases to exist for any given range of load. The load sharing is thus constrained by the MW limits for the various loads specified: 50 MW and 150 MW, as shown by the table below:
Page 104
Power System Operation and Control (PSOC) Solution: Consider the IC curves in Rs./MWHr for the 3 units as under: IC1=dH1/dP1 = (1.1) (7.2+0.000284P1) Rs./MWHr IC2=dH2/dP2 = (1.0) (7.85 + 0.00388P2) Rs./MWHr and IC3=dH3/dP3 = (1.0) (7.97 + 0.00964P3) Rs./MWHr
06EE82
For optimal operation, we have as per EIC, the common lambda of the system given by: = {PD+(bi/2ci)}/ {(1/2ci)} i= 1,2,3
Substituting the values, we get after simplification, = 9.148 Rs./MWHr. Using this value of common system lambda, the MW output values of all the 3 units are obtained from their IC curves as: P1= 393.2 MW, P2= 334.6 MW and P3=122.2 MW. (All the MW output values are within their capacity limits specified) Example-12: Three plants of total capacity 500 MW are scheduled for operation to supply a total load of 310 MW. Find the optimal load schedule if the IC curves and limitations are: : 30 P1 IFC1 = 30+ 0.12P1 150 MW 20 P2 100 IFC2 = 40+ 0.20P2 MW 50 P3 IFC3 = 10+ 0.16P3 250 MW Solution: For optimal operation, we have as per EIC, the system given by: system = {PD+(bi/2ci)}/ {(1/2ci)} i= 1,2,3 Substituting the values, we get after simplification, system = 42 Rs./MWHr.
Dept. of EEE, SJBIT Page 105
06EE82
Using this value of system, the MW output values of all the 3 units are obtained from their IC curves as:
Page 106
06EE82
And hence the total load to be shared only between the unit 1 and unit 3 is: 310-10=290 MW;
Solution:
IC2=dH2/dP2 = (1.0) (7.85 + 0.00388P2) Rs./MWHr IC3=dH3/dP3 = (1.0) (7.97 + 0.00964P3) Rs./MWHr
and
For optimal operation, we have as per EIC, the common lambda of the system given by: = {PD+(bi/2ci)}/ {(1/2ci)} Substituting the values, we get
i= 1,2,3
after
Using this value of common system lambda, the MW output values of all the 3 units are obtained from their IC curves as: P1= 704.6 MW, P2= 111.8 MW and P3= 32.6 MW.
Thus, P1>P1max (of 600 MW) ; P3<P3min (of 50 MW) and P2 is within the limits.
In such cases, for optimal operation, we have: P1=P1 max = 600 so that
Dept. of EEE, SJBIT
1=8.016 Rs./MWHr;
Page 107
Power System Operation and Control (PSOC) P3=P3 min so that 3=8.458 Rs./MWHr and thus
06EE82
= 50
Thus between units 2 and 3, the optimal operation may be feasible since IC3<IC2. For this, we solve the equations:
7.85+0.00388P2=7.97+0.00964P3 The solution thus yields: 2= 3=8.576 Rs./MWHr.; P2= 187.13 MW; P3 = 62.82 MW with P1=P1max = 600 MW (fixed).
Example-14:
If the total load at a certain hour of the day is 400 MW for a 3 unit system, obtain the optimum generation schedule, if the IC curves of the three units are as under (with ICs in Rs./MWHr. and PGs in MW): PG1= -100 +50 (IC1)- 2 (IC1)2 PG2= -150 +60 (IC2)- 2.5 (IC2)2 PG3= -80 +40 (IC3)1.8 (IC3)2
Page 108
06EE82
Consider the EIC condition: IC1=IC2=IC3= system Thus, 400= [-100+50(IC)-2(IC)2]+ [-150+60(IC)-2.5(IC)2]+ [-80+40(IC)1.8(IC)2] i.e., 6.3(IC)2-150(IC)+730=0;
and PT=PG1+PG2+PG3=400
Solving we get two solutions: IC=6.82 and IC=16.989 Rs./MWHr., of which, the lower and economical value is considered for further analysis: With IC= 6.82 Rs./MWHr, we have, PG1= 148 MW, PG2= 142.9 MW and PG3= 109.1 MW.
In EPS, the first step is to properly assess the load requirement of a given area where electrical power is to be supplied. This power is to be supplied using the available units such as thermal, hydroelectric, nuclear, etc. Many factors are required to be considered while choosing a type of generation such as: kind of fuel available, fuel cost, availability of suitable sites for major station, nature of load to be supplied, etc.
Variable load: The load is not constant due to the varying demands at the different times of the day. The EPS is expected to supply reliable and quality power. It should ensure the continuity of power supply at all times. {Qn.: write a note on the choice of the number and size of the generating units at a power station from economic operation point of view}
Page 109
06EE82
Single unit Vs. multiple units: the use of a single unit to supply the complete load demand is not practical since, it would not be a reliable one. Alternately, a large number of smaller units can be used to fit the load curve as closely as possible. Again, with a large number of units, the operation and maintenance costs will increase. Further, the capital cost of large number of units of smaller size is more as compared to a small number of units of larger size. Thus, there has to be compromise in the selection of size and number of generating units within a power plant or a station.
Electric Power Systems (EPS): Operational Aspects: Electric energy is generated at large power stations that are far away from the load centers. Large and long transmission lines (grid lines) wheel the generated power to the substations at load centers. Many electrical equipment are used for proper transmission and distribution of the generated power. The grid lines are such that: GRID: The transmission system of a given area.2 Regional GRID: Different grids are interconnected through transmission lines. National GRID: Interconnection of several regional grids through tie lines. Each grid operates independently, although power can be exchanged between various grids.
Economic loading of generators and interconnected stations: Optimum economic efficiency is achieved when all the generators which are running in parallel are loaded in such a way that the fuel cost of their power generation is the minimum. The units then share the load to minimize the overall cost of generation. This economical approach of catering to the load requirement is called as economic dispatch. The main factor in economic operation of power systems is the cost of generating the real power. In any EPS, the cost has two components as under:
Page 110
06EE82
The Fixed Costs: Capital investment, interest charged on the money borrowed, tax paid, labour, salary, etc. which are independent of the load variations. The Variable Costs: which are dependant on the load on the generating units, the losses, daily load requirements, purchase or sale of power, etc. The current discussion on economic operation of power systems is concerned about minimizing the variable costs only. Further, the factors affecting the operating cost of the generating units are: generator efficiency, transmission losses, fuel cost, etc. Of these, the fuel cost is the most important factor. Since a given power system is a mix of various types of generating units, such as hydel, thermal, nuclear, hydro-thermal, wind, etc., each type of unit contributes its share for the total operating cost. Since fuel cost is a predominating factor in thermal (coal fired) plants, economic load dispatch (ELD) is considered usually for a given set of thermal plants in the foregoing discussion.
PROBLEM OF ECONOMIC LOAD SCHEDULING: There are two problem areas of operation strategy to obtain the economic operation of power systems. They are: problem of economic scheduling and the problem of optimal power flow.
* The problem of economic scheduling: This is again divided into two categories: The unit commitment problem (UCP): Here, the objective is to determine the various generators to be in operation among the available ones in the system, satisfying the constraints, so that the total operating cost is the minimum. This problem is solved for specified time duration, usually a day in advance, based on the forecasted load for that time duration. The economic load dispatch (ELD): Here, the objective is to determine the generation (MW power output) of each presently operating (committed or put on) units to meet the specified load demand (including the losses), such hat the total fuel cost s minimized
Page 111
06EE82
* The problem of optimal power flow: Here, it deals with delivering the real power to the load points with minimum loss. For this, the power flow in each line is to be optimized to minimize the system losses.
{Qn.: compare ELD and UCP and hence bring out their importance and objectives.}
PERFORMANCE CURVES:
The Performance Curves useful for economic load dispatch studies include many different types of input-output curves as under: 1. Input Output Curve: A plot of fuel input in Btu/Hr. as a function of the MW output of the unit. 2. Heat Rate Curve: A plot of heat rate in Btu/kWH, as a function of the MW output of the unit. Thus, it is the slope of the I-O curve at any point. The reciprocal of heat rate is termed as the Fuel Efficiency. 3. Incremental Fuel Rate Curve: A plot of incremental fuel rate (IFC) in Btu/kWH as a function of the MW output of the unit, where, IFC= input/ output = Incremental change in fuel input/ Incremental change in power output 4. Incremental Fuel Cost Curve: A plot of incremental fuel cost (IFC) in Rs./kWH as a function of the MW output of the unit, where, IFC in Rs./kWH = (Incremental fuel rate in Btu/kWH) (Fuel cost in Rs./Btu) The IFC is a measure of how costlier it will be to produce an increment of power output by that unit. The Cost Curve can be approximated by: * Quadratic Curve by the function: Ci(Pi) = ai+biPi+ciPi2 Rs./Hr. * Linear curve by the function: d(Ci)/dPi =bi+2ciPi Rs./MWHr. Generally, the quadratic curve is used widely to represent the cost curve, with the IC curve given by the linear curve as above.
Dept. of EEE, SJBIT Page 112
06EE82
CONSTRAINTS IN ECONOMIC OPERATION OF POWER SYSTEMS: Various constraints are imposed on the problem of economic operation of power systems as listed below:
1. Primary constraints (equality constraints): Power balance equations: Pi - PDi - Pl =0; Qi - QDi - Ql =0; i=buses of the system where, Pl= Ql= system. The above constraints arise due to the need for the system to balance the generation and load demand of the system. ViVjYijcos ( ij- ij);
ViVjYij sin ( ij- ij); j = 1,2,.n, are the power flow to the neighboring
2. Secondary constraints (inequality constraints): These arise due to physical and operational limitations of the units and components. Pi min Qi min Pi Qi Pimax Qimax
3. Spare Capacity Constraints: These are used to account for the errors in load prediction, any sudden or fast hange in load demand, inadvertent loss of scheduled generation, etc. Here, the total generation available at any time should be in excess of the total anticipated load demand and any system loss by an amount not less than a specified minimum spare capacity, PSP (called the Spinning Reserve) given by: PlG (Generation) _ _ Pl (Losses) + PSP + PDj (Load)
Page 113
06EE82
Spinning reserve (SR) is the term used to describe the total amount of generation available from all the synchronized (spinning) units of the system minus the present load plus the losses being supplied. i.e., Sp.Res., PSP = {Total generation, PlG}-{ PDj(load)+ Pl (losses)}
The SR must be made available in the system so that the loss of one or more units does not cause a large drop in system frequency. SR must be allocated to different units based on typical Council rules. One such rule is as follows: SR must be capable of making up for the loss of the most heavily loaded unit in the system Reserves must be spread around the system to avoid the problem of bottling of reserves and to allow for the various parts of the system to run as islands, whenever they become electrically disconnected.
{Qn.: Write a brief note on the following: Spinning Reserve, constraints in economic operation, performance curves}
SOLUTION TO ECONOMIC LOAD DISPATCH {Qn.: Derive the EIC criterion for economic operation of power systems with transmission losses neglected, MW limits considered/ not considered} The solution to economic load dispatch problem is obtained as per the equal incremental cost criterion (EIC), which states that: All the units must operate at the same incremental fuel cost for economic operation This EIC criterion can be derived as per LaGrangian multiplier method for different cases as under.
Page 114
Power System Operation and Control (PSOC) CASE (i) Solution to ELD without inequality constraints:
06EE82
Consider a system with N generating units supplying a load PD MW. Let the unit MW limits and the transmission losses are negligible. Suppose the fuel cost of unit i is given by:
where, CT is the total fuel cost of the system in Rs./Hr., PD is the total demand in MW and Pi is the MW power output of unit i. The above optimization problem can be solved by LaGranjes method as follows. The LaGranje function L is given by:
Page 115
06EE82
CASE (iv) Solution to ELD with Transmission losses considered- LOSS COEFFICIENTS METHOD
Page 116
06EE82
Where, Nk1 and Nk2 (assumed to be real values) are the current distribution factors of units 1 and 2 respectively. It is assumed that the currents Ik1 and IL as well as Ik2 and IL have the same phase angle or they have a zero phase shift. Thus, they can be added as real numbers as under. Let I1 = I1 1 = I1cos 1+ jI1sin 1 I2 = I2 2 = I2cos 2+ jI2sin 2 Where 1 and 2 are the phase angles of currents.
Consider now, the magnitude of current Ik, in branch k, given by Ik = {Nk1I1cos 1+ j Nk1I1sin 1} + {Nk2I2cos 2+ j Nk2I2sin 2} = {Nk1I1cos 1+ Nk2I2cos 2} + j{Nk1I1sin 1+ Nk2I2sin 2} Thus, Ik2 = Nk1I12 + Nk2I22 + 2 Nk1Nk2I1I2 cos( 1- 2) However, we have, P1 = 3V1I1cosq1; P2 = 3V2I2cosq2; PL = S3Ik2Rk where, p1 and p2 are the mw power output values by the units 1 and 2 respectively, v1 and v2 are the respective line voltages and 1, 2 are the respective power factor angles and PL is the transmission loss in the system. after simplification, an expression for the transmission loss as a function of plant generation can be obtained as: PL = SNk1 2RkP1 2/(V1 2cos2q1) + SNk2 2RkP2 2/(V2 2cos2q2) + 2 SNk1Nk2RkP1P2 cos(_1-_2)/ (V1V2cosq1cosq2) = B11P1 2 + B22P2 2 + 2 B12P1P2 Where, the B coefficients are called as the loss coefficients. Thus, in general, for a system of n units we have, PL = S S PiBijPj Where,
Dept. of EEE, SJBIT Page 117
Power System Operation and Control (PSOC) Bij = S {cos(i-j)/ (ViVjcosqicosqj) NkiNkjRk (32) Note:
06EE82
1. The B coefficients are represented in units of reciprocal MW, (MW-1) 2. For a three unit system , equation (32) takes the form: PL = B11P12 + B22P2 2 + B33P32 + 2 B12P1P2+2 B13P1P3+ 2 B23P2P3= PTBP Where, P = [P1 P2 P3], the vector of unit power output values and B = [B11 B12 B13; B21 B22 B23; B31 B32 B33] the loss coefficient matrix for the 3 unit system. 3. The B coefficient matrix is a square, symmetric matrix of order n, n being the number of generating units present in the system. 4. The following are the assumptions made during the above analysis:
All load currents maintain a constant ratio to load current (Nki=constant). he voltage at any bus remains constant. The power factor of each bus source is constant ( qi=constant). The voltage phase angle at load buses is constant ( i=constant). 5. The Incremental Transmission loss, ITLi of a given unit can be expressed in terms of its MW power output values as under:
Page 118
06EE82
--------------------------------------------------------------------------------------------------------------
Page 119
06EE82
Example-1:
The costs of two units at the busses connected through a transmission line are (with P1 and P2 in MW): IC1=15+0.125 P1; IC2=20+0.05 P2 If 125 MW is transmitted from unit-1 to the load at bus-2, at which the unit-2 is present, a line loss of 15.625 MW is incurred. Find the required generation for each of the units and the power received by the load when the system lambda is Rs.24.0 per MWHr. Use Penalty Factor method.
Solution:
With unit-2 not contributing to the line loss, it is due to the unit-1 alone, and hence, dPL/dP2 = ITL2 =0; where, PL=B11P12; Thus, PL=10-3P12 so that i.e., B11= PL/ P 12 = 15.625/1252 = 10-3 MW-1 dPL/dP1= ITL1 = 2(10-3)P1 MW
Hence we have, = 15+0.125 P1 = (1-ITL1) = 24 {1 - 2(10-3)P1 IC1 } = 20+0.05 P2 = (1-ITL2) = = IC2 24 Solving, we get, P1=52 MW and P2= 80 MW. Total loss = Total Generation Total Load = (P 1+P2) PLoad = (52+80) - 15.625 = 116.4 MW.
Dept. of EEE, SJBIT Page 120
and
06EE82
Example-2:
In a power system, bus-A is fed by generator-A and bus-B by generator-B. the two buses are connected by a line whose loss is given by: PL=0.0008 (PB-100)2; The load at bus-A is 400 MWand that at bus-B is 100 MW. The ICs of the two units are (with P1 and P2 in MW): A=4 + 0.006 PA; B=4+0.007 PB Rs./MWHr. Determine the optimal generation of each unit and the power loss in the line.
Page 121
Power System Operation and Control (PSOC) For optimal power dispatch, we have, i.e., PnAA = PnBB = New
06EE82
And PA + PB = PD + PLoss = 500 + 0.0008 (PB-100)2 Solving, we get, PA=227.7 MW, P B= 117.65 MW and P L = 4.58 MW Example-3: In a power system, the ICs of the two units are (with P 1 and P2 in MW): IC1=0.01 P1+20 ; IC2=0.015 P2 +22.5 Rs./ MWHr. The system is running under optimal scheduling with P1=P2=100 MW. If the incremental transmission loss of unit 2 is 0.2, find the penalty factors and the incremental transmission loss of unit 1. Solution: For optimal power dispatch, we have, PnAA = PnBB = System where, i.e., (0.01 P1+20) Pn1 = (0.015 P2 +22.5) Pn2
Pn2 = {1 ITL2}-1 = {1 0.2}-1 = 1.25 so that, [0.01 (100) +20] Pn1 = [0.015 (100) +22.5] 1.25 Solving, we Pn1 = 1.4286 and get, Since, Pn1 = {1 ITL1}-1 we get, ITL1 = 0.3.
Example-4: A hydro plant and a steel plant are to supply a common load of 90 MW for a week (168 Hrs.). the unit characteristics are as under: acre feet/ Hr. 0PH100 MW 125PS50 2 MW Steam Plant: HS=53.25+11.27P S+0.0213PS Hydro Plant: C1=300+15P H If the Hydro plant is limited to 10000 MWH of energy usage, find the sharing of load during the period as a means of economic operation schedule. Solution: Since load=90 MW, total energy=90(168) = 15128 MWH Energy to be supplied by steam plant, ES=15128 10000 = 5128 MWH. Now, the steam plant has the max. efficiency when
Dept. of EEE, SJBIT Page 122
Power System Operation and Control (PSOC) (HS=a+bPS+cPS2); Power, P= a/c = {53.25/0.0213} = 50 MW.
06EE82
Number of hours of operation of the steam plant at its maximum efficiency to supply
Hydro plant at 40 MW :
at 90 MW: Hrs./week.
Example-5:
Three plants A, B, C supply P1=100 MW, P2 =200 MW and P3=300 MW. Calculate the transmission loss in the network in p.u. and the incremental transmission losses in all the three units A, B and C, if the loss coefficient matrix of the system on 100 MVA
-0.001
0.02
-0.003;
-0.002
0.03]
-0.002; 0.003
Page 123
06EE82
= 0.308 pu = 30.8 MW ITLi = 2 PkBik i.e., ITL1 = 2[P1B11 + P2B12 + P3B13] = 0.004 pu = 0.4 MW i.e., ITL2 = 2[P1B21 + P3B22 + P3B23] = 0.06 pu = 6 MW i.e., ITL3 = 2[P1B31 + P2B32 + P3B33] = 0.082 pu = 8.2 MW.
Example-6:
Two units are at two busses connected through a transmission line. If 100 MW is transmitted from plant 1 at bus-1 to the load at bus-2, a line loss of 10 MW is incurred. The IC curves of the units are, IC1 =0.02P1+16; IC2=0.04P2 +20 Rs./MWHr. If system = 26 Rs./MWHr., the no-load fuel costs are Rs.250/- and Rs.350/- per hour for unit-1 and unit-2 respectively, determine the following:
(xvii) The values of P1, P2 and the received load for optimal operation?
(xviii) The optimum values of P1, P2 for the above received load, if the system losses are accounted for but not coordinated.
(xix)
Page 124
06EE82
Solution: Consider: IL = Ia + Ib; IL1 = Ia = 1- j0.15 and IL2 = Ib = 0.5 j0.1 IL1/IL= 0.6649 Na1 = Na2 = 0.6649 Nb1 = Nb2 = 0.3351 V1=1.0 00; V2 = 1 + Ic Zc = 1.0176
I
cos1 = 0.9923
Now, the loss coefficients are given by the expression: Bij = {cos(i-j)/ (ViVjcosicosj) NkiNkjRk So that
Dept. of EEE, SJBIT Page 125
06EE82
B11=Nk12Rk/(V12cos21)={1/(V12cos21)}{Na12Ra+Nb12Rb+Nc12Rc}= 0.01462
2 2
pu
2
B22
2
=
2
Nk22Rk/(V22cos22)
{1/(V2 cos 2)}{Na2 Ra+Nb2 Rb+Nc2 Rc}= 0.2175 pu and B12 = Nk1Nk2Rk cos(1-2)/ (V1V2cos1cos2) = {1/(V1V2cos1cos2)}{Na1Na2Ra+Nb1Nb2Rb+Nc1Nc2Rc}= 0.0079 pu
Page 126
06EE82
Example-8: Figure below shows a system with plant-1 and plant-2 connected to bus-1 and bus-2 respectively. There are two loads and 3 branches. The bus-1 is the reference bus with 1.0 00 pu voltage. Base MVA is 100. Calculate the loss formula coefficients in pu and in MW-1 units, if the branch currents and branch impedance values are as under: Ia = 2.0 j 0.50 pu Ib= 1.6 j 0.40 pu Ic = 1.8 j 0.45 pu Za = 0.06 + j 0.24 pu Zb = 0.03 + j 0.12 pu Zc = 0.03 + j 0.12 pu
Solution: Consider: Ic/(Ib+Ic) = 0.5294 Ib/(Ib+Ic) = (1-0.5294) = 0.4706 The current distribution factors are as follows: Na1 = -0.5294; Na2 = 0.4706; V1=1.0 00; V2 = 1 + Ia Za = 1.319 I1 = Ib Ia = -0.4+j0.1 = I1 1660 ; Thus, 1= 1660; 2= -140; 1= 1660 So that the PF values are: 0.829 Nb1 = Nb2 = 0.4706 Nc1 = Nc2 = 0.5294 200 I2 = Ia + Ic = I2 and cos1 = 0.97 and -140 cos2=
2= 20+14 = 340
Now, the loss coefficients are given by the expression: Bij = {cos(i-j)/ (ViVjcosicosj) NkiNkjRk So that B11 = Nk12Rk/(V12cos21) = 0.0338 pu = 0.3387(10-3) MW-1 B22 = Nk22Rk/(V22cos22) = 0.0237 pu = 0.237(10-3) MW-1
Dept. of EEE, SJBIT
and
Page 127
06EE82
Example-9: The following table gives the unit charges of a 3 unit system. Initially the unit 2 is ON for 4 hours. Min. up time is 3 hours for all the units. The priority schedule is 2-1-3. Find the unit commitment schedule. Unit Max. Incr. Cost No load Start up Load MW Rs./MW cost Rs./Hr. cost Rs. pattern Hrs. MW 1 200 75 100 100 # 1-2 200 3-4 500 5-6 200 3 100 100 100 200 7-8 200 Solution: Based on the priority schedule we have the UC combination and the load supplied worked out as per the table below: Unit combination A: 010 B: 110 C: 111 400 500
200
75
100
100
Consider the distribution of load in the given pattern: Stage a: 1-2 for 2 hours: 200 MW It is combination-a with unit 2 only ON. Thus Operating cost is = 75(200)2 + start up cost of unit 2 = 30000 + 100 = Rs. 30100.00 Stage b: 3-4 for 2 hours: 500 MW It is combination-c with unit all the units ON. Thus Operating cost is = 75(200)2 + 75(200)2+ start up cost of unit 1 + 100(100)2 +
Dept. of EEE, SJBIT Page 128
06EE82
start up cost of unit 3 = 30000 + 30000+ 100 + 20000 +200 = Rs. 80300.00 Stage c: 5-6 for 2 hours: 200 MW It is combination-d with the unit-2 ON at full load and units 1 & 3 ON at no load for one hour (due to min. up time of 3 hours for unit-1 and unit-3) and with only the unit-2 ON at full load for the next one hour. (Now,the unit-2 does not have any start up cost component). Thus,
Operating cost is = {75(200) + no load cost of unit 1 + no load cost of unit 3} + 75(200) = 15000 + 100+ 100 + 15000 = Rs. 30200.00 Stage d: 7-8 for 2 hours: 200 MW It is combination-a again with unit 2 only ON. Thus Operating cost is = 75(200)2 = 30000 = Rs. 30000.00 (there is no start up cost now) Thus, the total operating cost = Rs. 30100.00 + Rs. 80300.00 + Rs. 30200.00 + Rs. 30000.00 = Rs. 1,70,600/Example-10: The unit charges of a 3 unit system are as under. Initially the unit 1 is ON for 4 hours. Min. up time is 2 hours for all the units. The priority schedule is 1-2-3. Find the unit commitment schedule. Unit # 1 Max. MW 200 Incr. Cost Rs./MW 900 No load cost Rs./Hr. 200 Start up cost Rs. 400 Load pattern Hrs. MW 1-2 2 3 100 100 950 1000 150 150 100 100 7-8
Dept. of EEE, SJBIT
3-4 5-6
06EE82
Based on the priority schedule we have the UC combination and the load supplied worked out as per the table below: Unit combination A: 100 B: 110 C: 111 300 400
= {unit 1 for 2 hrs. (200 MW) + st up cost of unit-1} + {units 1 & 2 for 2 hours (200+100 MW) + st up cost of unit-2} + {units 1,2 3 for 2 hrs.(200+100+100 MW) + start up cost of unit-3} + {only unit 1 for the next 2 hrs. (200 MW)} = Rs. 360400.00 + Rs. 550100.00 + Rs. 750100.00 + Rs. 360000.00 = Rs. 20,20,600/-
Page 130
06EE82
POWER SYSTEM SECURITY: Introduction, factors affecting power system security, power system contingency analysis, detection of network problems, network sensitivity methods, calculation of network sensitivity factor, cotingency ranking. Introduction
The Power System needs to be operationally secure, i.e. with minimal probability of blackout and equipment damage. An important component of power system security is the systems ability to withstand the effects of contingencies. A contingency is basically an outage of a generator, transformer and or line, and its effects are monitored with specified security limits. The power system operation is said to be normal when the power flows and the bus voltages are within acceptable limits despite changes in load or available generation. From this perspective, security is the probability of a power systems operating point remaining in a viable state of operation. System security can be broken down into TWO major functions that are carried out in an operations control centre: (i) Security assessment and (ii) security control. The former gives the security level of the system operating state. The latterdetermines the appropriate security constrained scheduling required to optimally attaining the target security level. Before going into the static security level of a power system, let us analyse the different operating states of a power system. The states of power system are classified into FIVE states: Normal Alert Emergency Extreme Emergency and Restorative.
Fig below depicts these states and the ways in which transition can occur from one state to another.
Page 131
06EE82
The operation of a power system is usually in a normal state. Voltages and the frequency of the system are within the normal range and no equipment is overloaded in this state. The system can also maintain stability during disturbances considered in the power system planning. The security of the power system is described by Thermal, voltage and stability limits. The system can also withstand any single contingency without violating any of the limits. The system transits into the emergency state if a disturbance occurs when the system is in the alert state. Many system variables are out of normal range or equipment loading exceeds short-term ratings in this state. The system is still complete. Emergency control actions, more powerful than the control actions related to alert state, can restore the system to alert state. The emergency control actions include fault clearing, excitation control, fast valving, generation tripping, generation run back-up, HVDC modulation, load curtailment, blocking of on-load tap changer of distribution system transformers and rescheduling of line flows at critical lines. The extreme emergency state is a result of the occurrence of an extreme disturbance or action of incorrect of ineffective
Page 132
06EE82
emergency control actions. The power system is in a state where cascading outages and shutdown of a major part of power system might happen. The system is in unstable state. The control actions needed in this state must be really powerful. Usually load shedding of the most unimportant loads and separation of the system into small independent parts are required.
Factors Affecting Power System Security Contingency Analysis Illustrative Example Procedure Methods of of Security Analysis Study with fast but approximate algorithms Detailed analysis with AC power flow (Ex: NR Method) Contingency Selection and Detailed analysis Introduction System Security involves Procedures involved which ensure that the Power System can operate when components fail.
For Example: Maintaining Adequate Spinning Reserve ensures that when a generator fails, the remaining units can take up the deficit load without too much of a drop in frequency Taking care of Transmission Line Flows When generation is dispatched ensures that, when a Line is taken out, the remaining lines do not get overloaded The time at which failures occur are unpredictable Any initiating event should not result in Cascading Failures leading to Blackout Major Functions of System Security System Monitoring Contingency Analysis Security Constrained Optimal Power Flow (SCOPF) System Monitoring
Dept. of EEE, SJBIT Page 133
06EE82
Provides up-to-date information Telemetry Systems: Critical Quantities are measured and transmitted to a central location Measured Quantities V, I, Line Flows, f, Unit Outputs, C.B Status, Transformer Taps etc Measured data is very large Difficult for human operators to process Digital Computers at control centres Gathers Telemetered Data Process this Data Stores the Data in a Data Base Generate Alarms Operator can display this data Combines data with system models for on-line and offline analysis Telemetering is combined with Supervisory Control to provide operators with a capabality to control components such as switches etc (SCADA) Contingency Analysis Power System Problems due to events such as Transmission Line and Generator Outages etc, can cause serious damage within very short duration Contingency Analysis Programs Model the events before they occur Combined with standard analysis procedures such as Power Flow etc to study the system Generate Operator Alarms Other Features Fast Solution Methods
Dept. of EEE, SJBIT Page 134
06EE82
Automatic Initialization of Contingency Power Flows using Actual System Data and State Estimation Procedures
Security Constrained Optimal Power Flow (SCOPF) Third Major Security Function Contingency Analysis Combined with OPF Four States of Power System Optimal Dispatch (Figure A) State Prior to a Contingency Optimal w.r.t Economic Operation May not be secure Post Contingency (Figure B)
State after contingency has occurred A Security Violation may have occurred Ex: Tn Line Flow or Bus Voltage outside Limit Secure Dispatch (Figure C)
State with no contingency outages Corrections to dispatch parameters taking security violations into account Secure Post Contingency (Figure D)
State when contingency occurs at the base operating condition- with corrections
Summary of Contingency Analysis Line and Generator outages may result in line flow and Bus Voltage limit violations
Dept. of EEE, SJBIT Page 135
06EE82
The way in which lost generation is distributed among remaining units is important Contingency Analysis procedures are used to predict effects of outages Lost Generation is picked up by units in its own area as well as neighboring areas Contingency analysis procedures Model Single Event outages (Ex: 1 Line, 1 Generator out) Multiple Event Outages (2 Line, 2 Generators) All Credible Outages are Studied one after another The C.A procedure tests lines and voltages against their respective limits Difficulties Speed of Solution Selection of All Credible outages Changed system conditions over time
Page 136
06EE82
Overview of Security Analysis Thousands of outages may have to be studied before they occur
Dept. of EEE, SJBIT Page 137
06EE82
A Security Analysis procedure run at an Energy Control Centre must be very fast Three Techniques commonly used Study the Power System with Approximate but fast Algorithms (DC Power Flow Methods, Linear Sensitivity factors) Select only important cases for detailed analysis (Contingency Selection) Use Multiple Processors or Vector Processors: running cases in parallel (Still in research stage) ------------------------------------------------------------------------------------------------------------
Page 138