XY0001 PAC-1 XY0001 PAC-1: XY0001.1 Undergr XY0001.1 Underground Floor

This document provides a 2 week lookahead schedule for the PAC-1 construction project. The schedule outlines activities and timelines for underground floor, first floor, and second floor construction over 477 days. Current work includes excavation of the underground floor through April 19th and brick wall construction for the first floor through mid-June. Future work includes electrical, plumbing, and finishing activities for both the first and second floors to be completed by October 6th.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
Download as pdf or txt
0% found this document useful (0 votes)
78 views4 pages

XY0001 PAC-1 XY0001 PAC-1: XY0001.1 Undergr XY0001.1 Underground Floor

This document provides a 2 week lookahead schedule for the PAC-1 construction project. The schedule outlines activities and timelines for underground floor, first floor, and second floor construction over 477 days. Current work includes excavation of the underground floor through April 19th and brick wall construction for the first floor through mid-June. Future work includes electrical, plumbing, and finishing activities for both the first and second floors to be completed by October 6th.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 4

PAC-1

2 Week Lookahead

Activity ID

Activity Name

XY0001 PAC-1
XY0001.1 Underground
Undergr
Floor

Original Early Start


Duration

25-Mar-15 22:49

Early Finish

Late Start

Late Finish

Total Float Remaining


Duration

477 30-Mar-15

06-Oct-16

30-Mar-15

06-Oct-16

477

74 06-Apr-15

24-Jun-15

30-May-16

16-Aug-16

360

63

UG1010

Excavation

12 06-Apr-15

19-Apr-15

30-May-16

12-Jun-16

352

10

UG1020

P.C. For Footing

16 13-Apr-15

23-Apr-15

06-Jun-16

16-Jun-16

300

16

UG1030

R.C. For Footing

22 23-Apr-15

25-May-15

16-Jun-16

18-Jul-16

300

22

UG1040

Brick wall

15 25-May-15

04-Jun-15

18-Jul-16

27-Jul-16

300

15

UG1050

Insulation for Footing

8 04-Jun-15

16-Jun-15

28-Jul-16

08-Aug-16

300

UG1060

Back Fill

6 16-Jun-15

24-Jun-15

09-Aug-16

16-Aug-16

300

UG1000

Site Preparation

8
193 30-Mar-15

30-Oct-15

30-Mar-15

06-Oct-16

293

214

162 30-Mar-15

30-Oct-15

30-Mar-15

06-Oct-16

244

155

XY0001.2 First Floor


Flo

FF.2020

Brick Walls-1

FF.2030

Electrical Works-1

18 30-Mar-15

22-Apr-15

30-Mar-15

22-Apr-15

18

FF.2040

Plumbing Works-1

12 23-Apr-15

08-May-15

23-Apr-15

08-May-15

12

FF.2050

Erect Doors&Windows-1

10 11-May-15

22-May-15

11-May-15

22-May-15

10

FF.2060

Plastering Works-1

32 25-May-15

07-Jul-15

25-May-15

07-Jul-15

32

FF.2000

R.C . Colums-1

12 24-Jun-15

10-Jul-15

17-Aug-16

01-Sep-16

300

12

FF.2070

Flooring-1

25 08-Jul-15

11-Aug-15

08-Jul-15

11-Aug-15

25

FF.2010

R.C. Slabs-1

24 13-Jul-15

14-Aug-15

05-Sep-16

06-Oct-16

300

24

FF.2080

Paints-1

45 12-Aug-15

13-Oct-15

12-Aug-15

13-Oct-15

45

FF.2090

Lighting Fixtures-1

3 14-Oct-15

16-Oct-15

14-Oct-15

16-Oct-15

FF.2100

Plumbing Fixtures-1

5 19-Oct-15

23-Oct-15

19-Oct-15

23-Oct-15

FF.2110

Finishes

5 26-Oct-15

30-Oct-15

26-Oct-15

30-Oct-15

291 02-Nov-15

06-Oct-16

02-Nov-15

06-Oct-16

291

XY0001.3 Second Floor


SF3000

R.C . Colums-1

12 02-Nov-15

17-Nov-15

02-Nov-15

17-Nov-15

12

SF3020

R.C. Slabs-1

24 19-Nov-15

22-Dec-15

19-Nov-15

22-Dec-15

24

SF3010

Brick Walls-1

35 13-Jan-16

01-Mar-16

13-Jan-16

01-Mar-16

35

SF3030

Electrical Works-1

18 04-Mar-16

29-Mar-16

04-Mar-16

29-Mar-16

18

SF3040

Plumbing Works-1

12 30-Mar-16

14-Apr-16

30-Mar-16

14-Apr-16

12

SF3050

Erect Doors&Windows-1

10 15-Apr-16

28-Apr-16

15-Apr-16

28-Apr-16

10

SF3060

Plastering Works-1

32 29-Apr-16

13-Jun-16

29-Apr-16

13-Jun-16

32

SF3070

Flooring-1

25 14-Jun-16

18-Jul-16

14-Jun-16

18-Jul-16

25

SF3080

Paints-1

45 19-Jul-16

19-Sep-16

19-Jul-16

19-Sep-16

45

Baseline

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Summary

Page 1 of 4

TASK filter: All Activities

Primavera Systems, Inc

PAC-1
ining
ation

2 Week Lookahead
Schedule % Start
Complete

Finish

Free Float

Apr 12
Sun

477

0% 30-Mar-15 A

06-Oct-16

63

0% 30-Mar-15 A

24-Jun-15

10

15.63% 11-Apr-15 A

23-Apr-15

16

0% 30-Apr-15

21-May-15

22

0% 29-Apr-15

28-May-15

15

0% 29-May-15

18-Jun-15

0% 04-Jun-15

16-Jun-15

0% 16-Jun-15

24-Jun-15

100% 30-Mar-15 A

214

0% 23-Apr-15 A

04-Dec-15

155

0% 11-Nov-15 A

30-Oct-15

244

18

0% 11-Nov-15

04-Dec-15

12

0% 23-Apr-15

08-May-15

10

0% 11-May-15

22-May-15

32

0% 25-May-15

07-Jul-15

12

0% 24-Jun-15

10-Jul-15

25

0% 08-Jul-15

11-Aug-15

24

0% 13-Jul-15

14-Aug-15

300

45

0% 12-Aug-15

13-Oct-15

0% 14-Oct-15

16-Oct-15

0% 19-Oct-15

23-Oct-15

0% 26-Oct-15

30-Oct-15

291

0% 02-Nov-15

06-Oct-16

12

0% 02-Nov-15

17-Nov-15

24

0% 19-Nov-15

22-Dec-15

35

0% 13-Jan-16

01-Mar-16

18

0% 04-Mar-16

29-Mar-16

12

0% 30-Mar-16

14-Apr-16

10

0% 15-Apr-16

28-Apr-16

32

0% 29-Apr-16

13-Jun-16

25

0% 14-Jun-16

18-Jul-16

45

0% 19-Jul-16

19-Sep-16

25-Mar-15 22:49

Mon

Tue

Wed

Apr 19
Thr

Fri

Sat

Sun

Mon

Tue

Wed

Apr 26
Thr

Fri

Sat

Sun

Excavation

08-Apr-15 A

Baseline

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Summary

Page 2 of 4

TASK filter: All Activities

Primavera Systems, Inc

PAC-1

2 Week Lookahead

Activity ID

Activity Name

Original Early Start


Duration

25-Mar-15 22:49

Early Finish

Late Start

Late Finish

Total Float Remaining


Duration

SF3090

Lighting Fixtures-1

3 20-Sep-16

22-Sep-16

20-Sep-16

22-Sep-16

SF3100

Plumbing Fixtures-1

5 23-Sep-16

29-Sep-16

23-Sep-16

29-Sep-16

SF3110

Finishes

5 30-Sep-16

06-Oct-16

30-Sep-16

06-Oct-16

Baseline

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Summary

Page 3 of 4

TASK filter: All Activities

Primavera Systems, Inc

PAC-1
ining
ation

2 Week Lookahead
Schedule % Start
Complete

Finish

Free Float

Apr 12
Sun

0% 20-Sep-16

22-Sep-16

0% 23-Sep-16

29-Sep-16

0% 30-Sep-16

06-Oct-16

25-Mar-15 22:49

Mon

Baseline

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Summary

Tue

Wed

Apr 19
Thr

Fri

Page 4 of 4

Sat

Sun

Mon

Tue

Wed

Apr 26
Thr

Fri

Sat

Sun

TASK filter: All Activities