Part 4C (Quantitative Methods For Decision Analysis) 354
Part 4C (Quantitative Methods For Decision Analysis) 354
B. .7354 inches.
C. .7746 inches.
C. Certainty.
D. Risk.
A. 70%.
B. Repetitive, nonprogrammed, and strategic.
B. 80%.
C. Repetitive, nonprogrammed, and nonstrategic.
C. 60%.
D. Nonrepetitive, nonprogrammed, and strategic.
D. 40%.
[3] Source: CMA 0683 5-17
CLT Company has three sales departments. Department A
processes about 50% of CLT's sales, Department B about
30%, and Department C about 20%. In the past,
Departments A, B, and C had error rates of about 2%,
5%, and 2.5%, respectively. A random audit of the sales
records yields a recording error of sufficient magnitude to
distort the company's results. The probability that
Department A is responsible for this error is
A. .50.
B. .33.
C. .02.
D. .25.
A. 300.
B. $320,000.
B. 100.
C. $240,000.
C. 160.
D. $360,000.
Model
--------P104
X104
A104
S104
Random Numbers
----------------0-1
2-6
7-8
9
B. 20%.
C. 50%.
D. Some percentage other than those given.
[16] Source: CMA 0688 5-26
(Refers to Fact Pattern #3)
In running a simulation of the computer demand, the
following numbers are drawn in sequence: 2, 8, and 6. The
simulation indicates that the third customer will purchase.
A. Model P104.
B. Model X104.
C. Model A104.
D. Model S104.
A. Maximax.
B. Minimax.
C. Minimum regret.
D. Expected monetary value.
[14] Source: CMA 0688 5-18
A decision maker is operating in an environment in which
all the facts surrounding a decision are known exactly, and
each alternative is associated with only one possible
outcome. The environment is known as
A. Certainty.
B. Risk.
A. 0.29.
C. Uncertainty.
B. 0.40.
D. Conflict.
C. 0.60.
D. 0.71.
n
_
S = X - X) P
e
e
e =1
X = individual cash flows.
e
_
X = expected value of all cash flows.
P = probabilities assigned to each cash flow.
e
[19] Source: CMA 1288 5-25
(Refers to Fact Pattern #4)
John Wills is using the standard deviation to assist in the
decision process because he is
A. Measuring the size of the constraints.
B. Determining the frequency of an event.
C. Measuring the dispersion of the probability for
each event.
D. Measuring the range of each event.
Probability
-----------0.4
0.3
0.2
0.1
D. $250,000.
[24] Source: CMA 0689 5-27
(Refers to Fact Pattern #5)
Using the expected value criterion,
A. The single purpose machine should be used
because of the low expected demand.
B. The automatic machine should be used because of
the high expected demand.
C. The semiautomatic machine should be used
because it has the lowest expected cost.
D. The automatic machine has the lowest expected
cost.
[Fact Pattern #6]
Refer to the profit payoff table below.
Supply
in Units
Demand in Units
--------------------------------------0
2
4
6
Probability of Demand
--------------------------------------0.1
0.3
0.4
0.2
-------0
2
4
6
----$0
(80)
(160)
(240)
--------$0
$0
40
40
(40)
80
(120)
0
----$0
40
80
120
operations.
[Fact Pattern #7]
The College Honor Society sells hot pretzels at the home
football games. The pretzels are sold for $1.00 each, and
the cost per pretzel is $.30. Any unsold pretzels are
discarded because they will be stale before the next home
game.
The frequency distribution of the demand for pretzels per
game is presented as follows.
B. $80.
C. $20.
D. $(10).
[26] Source: CMA 0689 5-29
(Refers to Fact Pattern #6)
The expected profit with perfect information is
A. $28.
B. $20.
A. 4,000 pretzels.
C. $(36).
B. 4,400 pretzels.
D. $68.
C. 5,000 pretzels.
[27] Source: CMA 0689 5-30
(Refers to Fact Pattern #6)
The price one is willing to pay for perfect information is
A. $68.
B. $40.
C. $48.
A. 4,000 pretzels.
D. $104.
B. 4,400 pretzels.
[28] Source: CMA 1289 5-13
Simple regression analysis may be used to approximate the
relationship between two variables, e.g., direct labor hours
and total product cost. This technique is
A. Most appropriate when the relationship between
the two variables is expressed by an exponential
(non-linear) graph.
C. 5,000 pretzels.
D. 6,000 pretzels.
[32] Source: CMA 1289 5-22
(Refers to Fact Pattern #7)
The conditional profit per game of having 4,000 pretzels
available but only selling 3,000 pretzels is
C. $2,800.
A. $1,200.
B. $2,100.
C. $2,800.
D. $800.
B. $(1,225).
C. $4,025.
D. $3,500.
B. 30.
C. 40.
D. 50.
A. $1,360.
[36] Source: CMA 0690 5-18
(Refers to Fact Pattern #8)
The maximum that Stan Berry should pay for perfect
information so that he could always stock the correct
number of bags of peanuts is
B. $2,200.
C. $3,900.
D. $1,960.
A. $.80.
B. $2.60.
C. $10.40.
D. $30.00.
C. $1,360.
D. $1,960.
[42] Source: CMA 1292 4-23
(Refers to Fact Pattern #9)
If the probability of hot weather given a hot weather
forecast is 50%, how much would the vendor be willing to
pay for the forecast?
A. $600.
B. $300.
C. $1,000.
D. $500.
A. 50%.
B. 1%.
C. 25%.
D. 33 1/3%.
D. The standard deviation of an event is greater than
zero.
[44] Source: CMA 1293 4-23
The Madison Company has decided to introduce a new
product. The company estimates that there is a 30%
probability that the product will contribute $700,000 to
profits, a 30% probability that it will contribute $200,000,
and a 40% probability that the contribution will be a
negative $400,000. The expected contribution of the new
product is
A. $500,000.
B. $110,000.
C. $270,000.
D. $430,000.
[45] Source: CMA 1293 4-26
The expected value of perfect information is the
A. Same as the expected profit under certainty.
A. Factor analysis.
C. Correlation analysis.
B. Normal analysis.
D. Regression analysis.
D. Difference between the expected profit under
certainty and the expected monetary value of the best
act under uncertainty.
[46] Source: CMA 1293 4-28
Regression analysis
A. Estimates the independent cost variable.
B. Dynamic programming.
C. Regression analysis.
C. $9.00.
A. Network analysis.
D. $8.60.
D. Queuing theory.
[58] Source: Publisher
Simple linear regression is a method applied when the
underlying relationship between two variables is believed to
be linear. The least squares process estimates this
hypothesized true relationship by minimizing the sum of
squared errors of the observations in a sample about a
fitted line. Which equation properly represents the
underlying true relationship between variables?
A. y = a + x.
B. y = a + bx.
C. y = a + bx + e.
D. y = a + bx + e.
D. x.
[60] Source: Publisher
(Refers to Fact Pattern #11)
The y-axis intercept is
D. e.
B. b.
C. x.
D. e.
D. All of the answers are correct.
[62] Source: Publisher
(Refers to Fact Pattern #11)
The independent variable is
A. a.
B. y.
A. Under risk.
C. b.
B. Under uncertainty.
D. x.
C. Under certainty.
D. Through satisficing.
B. 40%
D. 20%
C. 80%
B. Decision rules.
C. Input.
D. Outcome probabilities.
[71] Source: CIA 1195 II-14
In a large computer manufacturer, there has been much
concern about the consistency across departments in
adhering to new and unpopular purchasing guidelines. An
auditor has a list that rank-orders all departments according
to the percentage of purchases that are consistent with the
guidelines and indicates which division the department is
from. The auditor performs a t-test for differences in means
on the average rank of departments in divisions A and B to
see if there is any difference in compliance with the policy
and finds that division A (which has more departments) has
a significantly higher (i.e., better) average rank than division
B. Which one of the following conclusions should be drawn
from this analysis?
A. Division A is complying better with the new
policy.
B. A random sample of departments should be
drawn and the analysis recalculated.
D. Econometric modeling.
[Fact Pattern #12]
Total production costs of prior periods for a company are
listed. Assume that the same cost behavior patterns can be
extended linearly over the range of 3,000 to 35,000 units
and that the cost driver for each cost is the number of units
produced.
D. Nodes.
[73] Source: CMA 1294 4-30
Sweivel Company is preparing its budget and, taking into
consideration the recent pace of economic recovery, has
developed several sales forecasts and the estimated
probability associated with each sales forecast. To
determine the sales forecast to be used for budgeting
purposes, which one of the following techniques should
Sweivel use?
Production
in units
per month 3,000
9,000 16,000 35,000
Cost X
$23,700 $ 52,680 $ 86,490 $178,260
Cost Y
47,280 141,840 252,160 551,600
[77] Source: CIA 0594 III-99
(Refers to Fact Pattern #12)
What is the average cost per unit at a production level of
8,000 units for cost X?
A. $5.98
B. $5.85
C. $7.90
D. Sensitivity analysis.
D. $4.83
B. .0612
[78] Source: CMA 1287 5-21
(Refers to Fact Pattern #13)
The value (1 - P) must be
C. .0316
D. .00375
Ho: = 1
Ha: is not equal to 1
B.
A. I/(L - C) - 1.
Ho: 1
Ha: > 1
B. (I + C)/L.
C.
C. 1 - I/(L - C).
Ho: = 1
Ha: > 1
Ho: = 0
Ha: < 1
[84] Source: Publisher
(Refers to Fact Pattern #14)
The appropriate means for testing this hypothesis is
A. A z-statistic.
A. C chart.
B. A t-statistic.
B. P chart.
C. An F-statistic.
C. R chart.
D. A Q-statistic.
D. X-bar chart.
[81] Source: CIA 0595 II-48
Many firms are beginning to use the statistical processing
control techniques as part of their total quality management
approach. Which of the following would not constitute a
part of statistical processing control techniques?
A. Acceptance sampling.
C. 2.45
B. Dollar-unit sampling.
D. 4.65
C. Quality control charts.
D. Continuous monitoring and feedback.
[Fact Pattern #14]
The ABC Company has specified that the mean number of
calories in a can of its diet soda is 1 or less. A consumer
testing service examined nine cans with the following
amounts of calories: .9, .95, 1.0, 1.05, .85, 1.0, .95, .95,
and .9. The mean of these observations is .95. The sum of
the squared deviations from the mean is .03. Assume the
underlying population is approximately normal.
[82] Source: Publisher
(Refers to Fact Pattern #14)
What is the sample standard deviation?
A. .0577
A. 2.306
D. .333
B. 1.86
C. 1.833
D. 2.262
[88] Source: Publisher
(Refers to Fact Pattern #14)
What conclusion can be drawn with 95% confidence?
A. The manufacturer's claim can be rejected.
B. The manufacturer's claim cannot be rejected.
C. No decision is possible based on current
information.
D. All sodas have at most 1 calorie.
[89] Source: CMA 0697 4-22
Philip Enterprises, distributor of compact disks (CDs), is
developing its budgeted cost of goods sold for 1998. Philip
has developed the following range of sales estimates and
associated probabilities for the year:
D. $7,200
[Fact Pattern #15]
The probabilities shown in the table below represent the
estimate of sales for a new product.
Sales (Units)
-----------0-200
201-400
401-600
601-800
Probability
----------15%
45%
25%
15%
A. Queuing theory.
C. 70%
B. Dynamic programming.
D. 25%
C. The critical path method.
D. Decision tree analysis.
[91] Source: Publisher
Under favorable weather conditions, the management of
Flesher Farms expects its raspberry crop to have a
$120,000 market value. An unprotected crop subject to
B. 380
C. 400
D. 800
[Fact Pattern #16]
The table below shows the estimated probabilities of the
proportions of defective units resulting from a production
run. Each defective unit costs the company $100, and each
production run consists of 100 units.
Percentage Defective Probability
-------------------- ----------1%
20%
2%
20%
3%
30%
4%
20%
5%
10%
[95] Source: Publisher
(Refers to Fact Pattern #16)
The expected percentage of defective units is
A. 2.80%
B. 3.00%
C. 0.90%
D. 3.45%
[96] Source: Publisher
(Refers to Fact Pattern #16)
The variance of the percentage of defective units is
A. 0.00%
C. .17
B. 3.16%
D. .11
C. 10.20%
D. 1.56%
[97] Source: Publisher
(Refers to Fact Pattern #16)
The company hires a worker to oversee the machinery and
assure that no defective units are produced. What is the
breakeven amount per production run to be paid to the
worker?
A. $100
B. $200
A. .40
C. $280
B. .30
D. $295
C. .70
D. .20
D. $366.67
D. 0.95
[102] Source: Publisher
Pongo Company's managers are attempting to value a
piece of land that they own. One potential occurrence is
that the old road that borders the land gets paved. Another
possibility is that the road does not get paved. A third
outcome is that the road might be destroyed and
completely replaced by a new road. Based on the following
future states of nature, their probabilities, and subsequent
values of the land, what is the expected value of the land?
Future States of Nature (SN)
Probability
--------------------------------- ----------SN 1: Current road gets paved
.5
SN 2: Road does not get paved
.4
SN 3: Current road destroyed and
replaced with new road
.1
Estimates of land value under each possible future state of
nature:
Value if SN 1: $200,000
Value if SN 2: $100,000
Value if SN 3: $550,000
A. $133,333
B. $195,000
C. $225,000
D. $283,333
C. $576,272,000,000
D. $730,611,000,000
[107] Source: CMA Samp Q1-3
A U.S. company currently has domestic operations only. It
is considering an equal-size investment in either Canada or
Britain. The data on expected rate of return and the risk
associated with each of these proposed investments are
given below.
Mean
Standard
Proposed Investment Return Deviation
------------------- ------ --------British Investment
22%
10%
Canadian Investment
28%
15%
The mean return on the company's current (domestic only)
business is 20%, with a standard deviation of 15%. Using
the above data and the correlation coefficients, the
company calculated the following portfolio risk and return
(based on a ratio of 50% U.S. domestic operations and
50% international operations).
Mean
Standard
Investments
Return Deviation
---------------- ------ --------U.S. and Britain
21%
3%
U.S. and Canada
24%
15%
The company plans to select the optimal combination of
countries based on risk and return for the domestic and
international investments taken together. Based on the
above data, which one of the following alternatives
provides the best risk adjusted return to the firm?
A. $2,720.00
B. $1,400.00
C. $767.00
Yes
Yes
No
B.
C.
No
Yes
No
No
B. $8 + $0.01x.
D.
C. $8 + $0.02x.
D. $8 $0.02x.
[109] Source: CIA 1190 III-15
(Refer to Figure 6.) A health insurance company uses a
computer application to monitor physician bill amounts for
various surgical procedures. This program allows the
company to better control reimbursement rates. The X-bar
chart is an example of the output from this application.
Select the interpretation that best explains the data plotted
on the chart.
A. Random variation.
C. 160,000 gallons.
B. Abnormal variation.
D. 150,000 gallons.
C. Normal variation.
D. Cyclic variation.
[110] Source: CMA 1280 5-13
A manufacturing company allocates the cost of its service
departments to the producing departments. The service
departments provide services to each other as well as to
the producing departments. The allocation technique that
will charge each service department with the cost of the
service received from other service departments as well as
charge the producing departments for the total incurred
costs of all service departments is
A. Matrix algebra.
B. Boolean algebra.
C. Simulation techniques.
D. Dynamic programming.
B. $(50,000).
C. $(3,350,000).
D. $(150,000).
[116] Source: CMA 0683 5-5
The personnel manager has just completed a survey on
employee attitudes, working conditions, and productivity.
He would like to analyze data subject to the constraints of
his company (i.e., salary structure, capital equipment, etc.).
The stated objectives of this company are to (1) maximize
profits, (2) maximize safety, and (3) promote positive
employee attitudes. The decision analysis technique that
could accomplish this analysis is
t
b
t
R
m
t
(R), then
A. Linear programming.
C.
B. Statistical analysis.
C. Goal programming.
m would be negative.
t
D. Investments and/or stock of money would decline.
D. Dynamic programming.
[117] Source: CMA 1283 5-20
One limitation of the linear programming technique is that it
is effective only for
A. Two-product situations.
B. Unused capacity.
b >b
t t-1
C.
Pc < Py
t t
D. Negative saving occurs.
C. Simulation.
D. Matrix algebra.
[Fact Pattern #20]
The equality between a household's total sources and uses
of funds can be represented in the form of the budget
constraint model presented as follows.
Py + b (1 + R) + m = Pc + b + m
t t-1
t-1
t t t
If
Py = earned income during time period t.
t
Pc = consumption spending during time period t.
A. Objective functions.
B. Inequalities.
C. Deterministic functions.
D. Max Z = A + B + C.
D. Constraints.
[126] Source: CMA 1288 5-11
(Refers to Fact Pattern #21)
A feasible solution for Merlin Company is
A. D = 2 and F = 8.
B. Min Z = 2A + 2B + 3C.
B. D = 6 and F = 4.
C. Max Z = 2A + 2B + 3C - 150.
C. D = 12 and F = 0.
D. 2A + 2B + 3C 150.
D. D = 8 and F = 3.
[127] Source: CMA 1288 5-4
Variables that are important to the decision-making
process but are out of the control of the decision maker,
e.g., economic conditions, are considered to be
A. Exogenous variables.
B. A + 2B + 2.5C 100.
B. Decision variables.
C. Indeterminable from the data given.
C. Performance criteria.
D. A + B + C 190.
D. Constraints.
[128] Source: CMA 0689 5-13
Sensitivity analysis in linear programming is used to
B. Responsibility accounting.
C. Simple regression analysis.
D. Linear programming.
[Fact Pattern #23]
Keego Enterprises manufactures two products, boat wax
and car wax, in two departments, the Mixing Department
and the Packaging Department. The Mixing Department
has 800 hours per month available, and the Packaging
Department has 1,200 hours per month available.
Production of the two products cannot exceed 36,000
pounds. Data on the two products follow:
A. Z = 150B + 200C.
A. 2,400 Regular models.
B. 2B + 1.5C 36,000.
B. 3,000 Deluxe models.
C. 2B + 1.5C 36,000.
C. 1,091 Regular models and 2,182 Deluxe models.
D. Z = 200B + 150C.
D. 4,000 Deluxe models.
[134] Source: CMA 1290 4-26
(Refers to Fact Pattern #23)
The mixing constraint for the Keego linear program would
be
A. 2.4M + 6P 36,000.
B. 5B + 2.4C 800.
A. Gross margin.
C. 5B + 2.4C 800.
B. Segment margin.
D. 5B + 2.4C = 800.
C. Contribution margin.
[135] Source: CMA 1291 4-24
A small company makes only two products with the
following production constraints representing two machines
and their maximum availability:
2X + 3Y 18
2X + Y 10
X 0; Y 0
If
D. $24.
A. Cost-volume-profit analysis.
B. Transportation algorithms.
C. MAX Z = 12S + 24G.
C. Discounted cash flow techniques.
D. MAX Z = 7S + 15G.
D. PERT/CPM analysis.
A. 1A + 1.5B 200,000.
B. 8A + 12B 600,000.
C. 8A + 12B 200,000.
D. 1A + 1.5B 600,000.
[143] Source: CMA 1283 5-18
(Refers to Fact Pattern #24)
The constraint function for the machine capacity is
A. 6A + 24B 200,000.
B. S, G < 0.
B. 1/.5A + 1.5/2.0B 800,000.
C. S, G 0.
C. .5A + 2B 200,000.
D. S, G 0.
D. (.5 + .5)A + (2 + 2)B 200,000.
[144] Source: Publisher
The product of a matrix and its inverse matrix is
A. The matrix.
A. Regression analysis.
C. An identity matrix.
B. Markov analysis.
D. A nonconforming matrix.
D. Objective function.
C. Conditions.
D. Shadow prices.
A. Variable function.
B. Be a feasible point.
B. Constraint function.
C. Lie in a corner.
C. Linear function.
D. Minimize cost.
D. Objective function.
[Fact Pattern #27]
Pleasant Valley Company makes two products, ceramic
vases (V) and ceramic bowls (B). Each vase requires 2
pounds of material and 3 hours of labor. Each bowl
requires 2 pounds of material and 1 hour of labor. During
the next production week, there will be 100 pounds of
material and 60 hours of labor available to make vases and
bowls. Each pound of material costs $4 and each hour of
labor costs $10. All factory overhead is fixed and is
estimated to be $200 for this production process for a
week. Pleasant Valley sells vases for $50 each and bowls
for $35 each.
[151] Source: CMA 0687 5-19
(Refers to Fact Pattern #27)
One of the constraints on Pleasant Valley's objective
function would be
A. 2V + 2B 60.
B. Constraints.
B. 3V + B 60.
C. Shadow prices.
C. V + 3B 100.
D. The objective function.
D. $8V + $8B $600.
A. Parametric model.
B. Present value model.
C. Economic order quantity model.
D. Linear programming model.
C. D = 12 and F = 0.
D. D = 8 and F = 3.
A. Constraints.
B. Objectives.
A. Multiple regression.
A. Gross margin.
B. Linear programming.
B. Segment margin.
Product Y
----------
A.
146 units and
B.
0 units.
40 units.
C. Conditions.
D. Constraints.
[162] Source: CMA 0694 4-12
(Refers to Fact Pattern #29)
The point at which M = 2 and S = 3 would
A. Minimize cost.
C. Queuing theory.
B. Lie in a corner.
C. Be a feasible point.
D. Be an infeasible point.
B. +B2 x 1.2
A.
C. +C2 + (.2 x B2)
D. +B2 + (.2 x B2)
[168] Source: CMA 0696 4-9
(Refers to Fact Pattern #30)
Which one of the cells listed below contains an incorrect
formula?
A. D4
B. D8
C. E6
D. C1
[169] Source: CMA 0696 4-10
(Refers to Fact Pattern #30)
If all of the errors in the formulas in the spreadsheet were
corrected, the correct projected net income for year 4
would be
A. $21,858
B. $37,410
C. $90,978
D. $88,074
[170] Source: CMA 1296 4-10
A large retail chain has 10 warehouses and 50 retail
locations. The quantitative technique it would likely use to
determine the minimum cost of moving its goods from the
warehouses to the retail stores is
A. A transportation model.
B. Markov analysis.
C. Calculus-based optimization.
D. A queuing model.
x 6 3 49
1
x 12 2 17
2
B.
6 3 x 49
1
12 2 x 17
2
C.
6 3 49 x
1
12 2 17 x
2
D.
x 6 3 49
1
x 12 2 17
2
[173] Source: CIA 0581 IV-25
The Apex Fertilizer Company is planning a new formulation
to appeal to the increasing market of herb growers. Each
unit of the product will require 3 pounds of chemical A, 1
pound of chemical B, and 4 pounds of chemical C. The
per-pound costs of chemical A are $7.95; chemical B,
$3.28; and chemical C, $6.14. Which of the following
matrix algebra formulations will lead to the cost of one unit
of the new fertilizer?
A.
0 1 0
0 0 4
B.
7.95 3, 1, 4
3.28
6.14
C.
7.95 3
3.28 1
6.14 4
D.
3 1 4 7.95
3.29
6.14
D. Integral calculus.
[179] Source: CIA 1194 III-58
An investment company is attempting to allocate its
available funds between two investment alternatives, stocks
and bonds, which differ in terms of expected return and
risk. The company would like to minimize its risk while
earning an expected return of at least 10% and investing no
more than 70% in either of the investment alternatives. An
appropriate technique for allocating its funds between
stocks and bonds is
A. Linear programming.
B. Capital budgeting.
C. Differential analysis.
D. Queuing theory.
[180] Source: CIA 0593 IV-21
Shadow prices in linear programming solutions are
ordinarily considered to be the same as
A. Relevant costs.
B. Differential cost.
C. Alternative costs.
D. Opportunity costs.
[Fact Pattern #31]
Polar Bear Inc. has three service departments. The
relationship between the three departments, maintenance,
cleaning, and food prep, and the total costs incurred by
each are expressed below:
Maintenance = $40,000 + .25C
Cleaning = $60,000 + .2M
Food Service = $50,000 + .1M + .45C
In addition, there are two production departments:
Assembly and Finishing. Maintenance workers spend
A. $14,000
B. $20,000
C. $20,264
D. $28,948
[182] Source: Publisher
(Refers to Fact Pattern #31)
Using the reciprocal method, what is the total cleaning
department cost to be allocated to all other departments?
A. $57,895
B. $71,579
C. $68,000
D. $60,000
[183] Source: Publisher
(Refers to Fact Pattern #31)
Using the reciprocal method, what is the total food service
department cost to be allocated to all other departments?
A. $88,001
B. $55,790
C. $82,211
D. $83,211
C. 2, 4, 5, 6, and 8.
D. 3, 5, 6, and 7.
[188] Source: CIA 1192 III-42
(Refers to Fact Pattern #33)
(Refer to Figure 8.) If a series of profit lines for X and Y
are drawn on the graph, the mix of X and Y that will result
in the maximum profit can be determined from
A. The last point in the feasible solution region
B. Funz-N-Oonz Inc.
C. Moonsammy and Associates.
D. Step-N-Wolf Intl.
[193] Source: CPA 0591 I-44
On January 1, 2001, Hooks Oil Co. sold equipment with a
carrying amount of $100,000 and a remaining useful life of
10 years to Maco Drilling for $150,000. Hooks
immediately leased the equipment back under a 10-year
capital lease with a present value of $150,000. It will
depreciate the equipment using the straight-line method.
Hooks made the first annual lease payment of $24,412 in
December 2001. In Hooks's December 31, 2001 balance
sheet, the unearned gain on the equipment sale should be
A. $50,000
B. $45,000
C. $25,588
D. $0
[194] Source: CPA 0588 I-32
On December 31, 2001, Ruhl Corp. sold equipment to
Dorr and simultaneously leased it back for 3 years. The
following data pertain to the transaction at this date:
Sales price
$220,000
Carrying amount
150,000
Present value of lease rentals
($2,000 for 36 months at 12%)
60,800
Estimated remaining useful life
10 years
At December 31, 2001, what amount should Ruhl report
as deferred revenue from the sale of the equipment?
A. $0
B. $9,200
C. $60,800
A. Redler Company.
D. $70,000
B. Funz-N-Oonz Inc.
C. Moonsammy and Associates.
D. Step-N-Wolf Intl.
[191] Source: Publisher
(Refers to Fact Pattern #34)
Which company has the largest quantity of cleaning fluid
that should be produced to maximize profit?
A. Redler Company.
B. Funz-N-Oonz Inc.
A. $34,100
B. $30,000
D. Step-N-Wolf Intl.
C. $4,100
D. $0
Plane #1 Plane #2
-------- ---------Sales price
$600,000 $1,000,000
Carrying amount, 12/31/01 $100,000 $550,000
Remaining useful life,
12/31/01
10 years 35 years
Lease term
8 years 3 years
Annual lease payments
$100,000 $200,000
In its December 31, 2001 balance sheet, what amount
should Dirk report as deferred gain on these transactions?
A. $950,000
B. $500,000
C. $450,000
PRODUCT
------A B C
-- -- -Selling price per unit $7 $6 $5
Variable cost per unit 5 3 1
Fixed cost per unit
1 1 2
Management used linear programming to generate the
following solution:
PRODUCT VALUE REDUCED VALUE
------- ----- ------------A
100
8
B
?
2
C
150
0
CONSTRAINT VALUE SHADOW PRICE
---------- ----- ------------
D. $0
[197] Source: CPA 0592 T-32
Rig Co. sold its factory at a gain, and simultaneously leased
it back for 10 years. The factory's remaining economic life
is 20 years. The lease was reported as an operating lease.
At the time of sale, Rig should report the gain as a(n)
A. Extraordinary item, net of income tax.
Machine X
Machine Y
Machine Z
Demand A
Demand C
0
400
500
100
150
?
0
0
0
0
D. 1,400 hours.
[200] Source: Publisher
(Refers to Fact Pattern #35)
What is the maximum number of units of B that can be
produced by machine Y?
A. 1,400 units.
A. $35,000
B. 800 units.
B. $20,000
C. 700 units.
C. $15,000
D. 400 units.
D. $0
[Fact Pattern #35]
A company produces three products, A, B, and C, using
three different machines, X, Y, and Z. Management has
decided that at least 100 units of product A must be
manufactured. Marketing research indicates that the
company's maximum market share for product C is 150
units.
Each product uses different amounts of machine time
(hours per unit), and each machine has different capacities
(hours per year), as summarized below.
MACHINE TIME (HOURS)
-------------------PRODUCT
X
Y
Z
------- ----- ----- ----A
2
4
3
B
3
2
5
C
4
3
2
CAPACITY 1,400 1,650 2,100
Each product also has a different selling price per unit and
different costs per unit.
B. $608,640.
C. $885,800.
D. $708,640.
[208] Source: CMA 0688 5-9
(Refers to Fact Pattern #36)
In order to ensure that the company would not lose money
on the project, LCB's minimum bid for the 40 units would
be
A. $760,800.
B. $608,640.
C. $885,800.
D. $708,640.
[209] Source: CMA 0688 5-14
When using PERT, the expected time for an activity, given
an optimistic time (A), a pessimistic time (B), and a most
likely time (m), is calculated by which of the following
formulas?
A. Queuing theory.
A. (4a + m + 4b)/6.
B. Expected value analysis.
B. (a + 4m + b)/6.
C. The Markov process.
C. (a + b)/2.
D. Contribution margin analysis.
D. (b - a)/2.
[Fact Pattern #36]
LCB, Inc. is preparing a bid to the Department of the Navy
to produce engines for rescue boats. The company has
manufactured these engines for the Navy for the past 3
years, on an exclusive contract, and has experienced the
following costs:
Cumulative
Total Cumulative Costs
Units Produced
Materials
Labor
---------------------- -------10
$ 60,000 $120,000
20
120,000
192,000
40
240,000
307,200
At LCB, variable overhead is applied on the basis of $1.00
per direct labor dollar. Based on historical costs, LCB
knows that the production of 40 engines will incur
B. Differential calculus.
D. Linear programming.
A. Regression analysis.
C. Is based on the most likely times for each activity.
B. Simulation analysis.
C. Markov chain analysis.
D. Gantt charting.
[214] Source: CMA 0690 5-20
Pallis Enterprises has a warehouse with a loading dock that
is used to unload railroad freight cars. Pallis maintains
records of daily incoming cars that are delivered to the
warehouse during the night. On any given night, zero to six
freight cars could be delivered. It takes the dock workers 4
hours to unload each car. The company would like to
analyze the wait time (delay) involved when more than two
freight cars are delivered. The appropriate technique to
analyze the arrival of the freight cars is
A. Monte Carlo simulation.
B. Regression analysis.
C. Sensitivity analysis.
Optimistic
2 months
Most likely 4 months
Pessimistic 9 months
Using the Program Evaluation Review Technique (PERT),
the expected completion time for this particular phase
would be
A. 4 months.
B. 4 months.
D. Matrix analysis.
[220] Source: CMA 1284 5-9
Which one of the following statements best describes a
difference between basic PERT and the Critical Path
Method (CPM) of network analysis?
A. PERT considers only activity cost while CPM
considers only activity time.
C. 5 months.
D. 7 months.
B. Regression analysis.
C. Program Evaluation Review Technique (PERT).
A. A GANTT chart.
B. The critical path method (CPM).
C. Queuing theory.
D. Sensitivity analysis.
Immediate
Duration
Predecessor
(Days)
------------------------A
4
B
3
C
A
9
D
A
6
E
B, D
5
For this project, the critical path is
A. A-C.
B. B-E.
C. A-D-E.
D. B-D-C.
D. Linear programming.
A. Is not essential to the overall project.
[232] Source: CMA 1287 5-26
PERT is widely used to plan and measure progress toward
scheduled events. PERT is combined with cost data to
produce a PERT-Cost analysis to
A. Calculate the total project cost inclusive of the
additional slack time.
B. Evaluate and optimize trade-offs between time of
an event's completion and its cost to complete.
C. Implement computer-integrated manufacturing
concepts.
D. Calculate expected activity times.
[233] Source: CIA 0594 III-61
Which of the following terms is not used in project
management?
A. Dummy activity.
B. Latest finish.
C. Optimistic time.
A. 7.29 minutes.
D. Lumpy demand.
B. 8.1 minutes.
[234] Source: CIA 1195 III-100
A bank is designing an on-the-job training program for its
branch managers. The bank would like to design the
program so that participants can complete it as quickly as
possible. The training program requires that certain
activities be completed before others. For example, a
participant cannot make credit loan decisions without first
having obtained experience in the loan department. An
C. 6.56 minutes.
D. 5.90 minutes.
[238] Source: CMA 0688 5-16
When making a cost/time trade-off in PERT analysis, the
first activity that should be crashed is the activity
B. Activity EF 2 weeks.
C. Regression analysis.
D. Activity DE 2 weeks.
[240] Source: CMA 1291 4-17
A company is planning a multi-phase construction project.
The time estimates for a particular phase of the project are
Optimistic
2 months
Most likely 4 months
Pessimistic 9 months
Using the Program Evaluation Review Technique (PERT),
the expected completion time for this particular phase is
A. 2 months.
C. 61-100.
B. 4 months.
D. 11-60.
C. 4 months.
D. 5 months.
[241] Source: CMA 1284 5-3
An assumption often made with queuing models is that
A. Arrival time follows a Poisson distribution and
service times are exponentially distributed.
C. 9.
D. 12.
[246] Source: CMA 0688 5-17
A PERT network has only two activities on its critical path.
These activities have standard deviations of 6 and 8,
respectively. The standard deviation of the project
completion time is
A. 7.
time of Job #181 and, at the same time, report the highest
possible income for the year. California Building should
crash
B. 10.
A. Activity BC 1 week and activity EF 1 week.
C. 14.
B. Activity BC 2 weeks.
D. 48.
C. Activity EF 2 weeks.
[Fact Pattern #37]
Moss Point Manufacturing recently completed and sold an
order of 50 units that had costs as follows.
The company has now been requested to prepare a bid for
150 units of the same product.
Direct materials
$ 1,500
Direct labor (1,000 hours x $8.50)
8,500
Variable overhead (1,000 hours x $4.00)*
4,000
Fixed overhead**
1,400
------$15,400
=======
*Applied on the basis of direct labor hours.
**Applied at the rate of 10% of variable cost.
[247] Source: CMA 1288 5-19
(Refers to Fact Pattern #37)
If an 80% learning curve is applicable, Moss Point's total
cost on this order would be estimated at
A. $26,400.
B. $32,000.
C. $38,000.
D. $41,800.
[252] Source: CMA 0689 5-25
A Gantt chart
[248] Source: CMA 1288 5-20
(Refers to Fact Pattern #37)
If Moss Point had experienced a 70% learning curve, the
bid for the 150 units would
D. $17,280.
[259] Source: CMA 0694 4-1
When using PERT (Program Evaluation Review
Technique), the expected time for an activity when given an
optimistic time (A), a pessimistic time (B), and a most likely
time (m), is calculated by which one of the following
formulas?
C. (a + 4m + b) 6.
D. (4abm) 6.
[260] Source: CMA 0694 4-2
In a PERT (Program Evaluation Review Technique) or
CPM (Critical Path Method) network, the critical path is
the
B. Cost-volume-profit analysis.
A. Least costly path through the network.
C. PERT-Cost analysis.
B. Most costly path through the network.
D. Queuing theory.
C. Shortest path through the network.
[256] Source: CMA 1291 4-23
Manning Corporation is preparing a proposal for the
government to produce a steam generator to be used in
nuclear submarines. Manning has three factories that can
initiate and complete the generator; however, completion
times vary due to different technologies and older
equipment within each of the three factories. The decision
tool that would best assist Manning in its factory selection is
A. Queuing theory.
C. PERT-Cost analysis.
D. Linear programming.
D. On the critical path with the lowest unit crash cost.
[257] Source: CMA 0692 4-7
The Markov process
A. Assumes that the probabilities of an event depend
only on the current state.
B. Assumes that the probabilities of an event are
dependent on all previous events.
C. Is useful if sequencing of related decisions is
necessary.
D. Is used to assess the implications of decisions in a
competitive environment based on trend analysis.
[258] Source: CMA 1293 4-24
The average labor cost per unit for the first batch produced
by a new process is $120. The cumulative average labor
cost after the second batch is $72 per product. Using a
batch size of 100 and assuming the learning curve
continues, the total labor cost of four batches will be
A. $4,320.
D. Regression analysis.
B. $10,368.
C. $2,592.
slack is the
A. Uncertainty associated with time estimates.
B. Difference between the latest starting time and
earliest finishing time.
C. Path that has the largest amount of time associated
with it.
D. Number of days an activity can be delayed
without forcing a delay for the entire project.
C. Statistical sampling.
A. Simulation techniques.
D. Time series analysis.
B. Correlation and regression analysis.
[265] Source: CMA 1293 4-25
The four components of time series data are secular trend,
cyclical variation, seasonality, and random variation. The
seasonality in the data can be removed by
A. Multiplying the data by a seasonality factor.
B. Ignoring it.
C. Taking the weighted average over four time
periods.
D. Subtracting a seasonality factor from the data.
[266] Source: CMA 0695 4-12
In PERT, slack is the
C. Statistical sampling.
D. Time series analysis.
[270] Source: CIA 0593 III-64
What coefficient of correlation results from the following
data?
X Y
- -1 10
2
8
3
6
4
4
5
2
A. 0
B. -1
C. +1
D. Cannot be determined from the data given.
A. -0.73
C. -.89
B. -0.11
D. .75
C. 0.12
D. 0.35
C. Constant coefficient.
D. Variable coefficient.
[274] Source: CMA 1290 4-28
(Refers to Fact Pattern #38)
The letter x in the standard regression equation is best
described as a(n)
A. Independent variable.
B. Dependent variable.
C. Constant coefficient.
D. Coefficient of determination.
[275] Source: CMA 1290 4-29
(Refers to Fact Pattern #38)
Based upon the data derived from the regression analysis,
420 maintenance hours in a month would mean the
maintenance costs (rounded to the nearest dollar) would be
budgeted at
A. $3,780.
B. $3,600.
C. $3,790.
D. $3,746.
[276] Source: CMA 1290 4-30
(Refers to Fact Pattern #38)
The percentage of the total variance that can be explained
by the regression equation is
A. 99.724%.
B. 69.613%.
C. 80.982%.
D. 99.862%.
[277] Source: Publisher
(Refers to Fact Pattern #38)
If Wilkens Company uses the high/low method of analysis,
the equation for the relationship between hours of activity
and maintenance cost would be
A. Y = 400 + 9.0X
B. Y = 570 + 7.5X
C. Y = 3,600 + 400X
D. Y = 570 + 9.0X
[278] Source: Publisher
(Refers to Fact Pattern #38)
What is the range of values for the marginal maintenance
cost such that Wilkens can be 95% confident that the true
value of the marginal maintenance cost will be within this
range?
A. $7.02 - $7.56
A. Independent variable.
B. $7.17 - $7.41
B. Dependent variable.
C. $7.07 - $7.51
D. $6.29 - $8.29
C. $3,568.18 - $3,613.93
A. A transportation model.
D. $3,565.54 - $3,634.48
B. Markov analysis.
[280] Source: CIA 0595 II-47
An internal auditor for a large automotive parts retailer
wishes to perform a risk analysis and wants to use an
appropriate statistical tool to help identify stores that would
be out of line compared to the majority of stores. The most
appropriate statistical tool to use is
A. Linear time series analysis.
C. Calculus-based optimization.
D. The critical path method.
[285] Source: CMA 0696 4-20
A widely used approach that managers use to recognize
uncertainty about individual items and to obtain an
immediate financial estimate of the consequences of
possible prediction errors is
C. Longest path.
island.
B. Exponential smoothing.
C. Queuing theory.
D. Linear regression analysis.
[289] Source: CIA 0586 III-15
A bank has changed from a system in which lines are
formed in front of each teller to a one-line, multiple-server
system. When a teller is free, the person at the head of the
line goes to that teller. Implementing the new system will
A. Decrease the bank's wage expenses because the
new system uses fewer tellers.
B. Decrease time customers spend in the line.
C. Increase accuracy in teller reconciliations at the
end of the day because fewer customers are served
by each teller.
D. Improve on-the-job training for tellers because
each will perform different duties.
B. Chi-square.
C. Poisson.
D. Exponential.
[293] Source: CIA 1192 III-99
(Refers to Fact Pattern #39)
The time that car 3 will have to wait to be serviced (not
including its own service time) is
C. 4 minutes.
D. 5+ minutes.
[294] Source: CIA 1192 III-100
(Refers to Fact Pattern #39)
The time that car 4 will have to wait to be serviced (not
including its own service time) is
A. 0-2 minutes.
D. 30.0 hours.
[301] Source: CIA 1189 III-50
What are the four components of a time series?
A. Trend, cyclical, seasonal, and irregular.
B. Alpha, cyclical, seasonal, and irregular.
C. Alpha, cyclical, seasonal, and repetitive.
A. Game theory.
B. Probability theory.
C. Queuing theory.
A. Game theory.
D. Sensitivity analysis.
B. Probability theory.
C. Linear programming.
D. Sensitivity analysis.
[303] Source: CIA 0593 III-69
Only two companies manufacture Product A. The finished
product is identical regardless of which company
manufactures it. The cost to manufacture Product A is $1
and the selling price is $2. One company considers
reducing the price to achieve 100% market share but fears
the other company will respond by further reducing the
price. Such a scenario would involve a
A. No-win strategy.
B. Dual-win strategy.
C. One win-one lose strategy.
D. Neutral strategy.
[304] Source: CIA 0592 III-70
One of your firm's trucks was involved in an accident with
a car, both parties claiming the other was at fault. A court
ruled that your firm was solely responsible for all damage.
From a game theory perspective, this dispute can be
described as a
C. Regression analysis.
A. Prisoner's dilemma.
D. Game theory.
B. Zero-sum game.
[300] Source: CMA 0696 4-7
It is estimated that a particular manufacturing job is subject
to an 80% learning curve. The first unit required 50 labor
hours to complete. What is the cumulative average time per
unit after completing four units?
A. 50.0 hours.
B. 40.0 hours.
C. 32.0 hours.
C. Saddle point.
D. Minimax regret.
[Fact Pattern #40]
A bank plans to open a branch in one of five locations
(labeled L1, L2, L3, L4, L5). Demand for bank services
may be high, medium, or low at each of these locations.
Profits for each location-demand combination are
presented in the following payoff matrix.
Payoff Matrix
------------Location L1 L2 L3 L4 L5
-------- -- -- -- -- -Demand:
High 15 21 17 26 29
Medium 12 8 14 10 4
Low
7 -2 4 -3 -6
D. A time-series study.
[310] Source: CIA 1190 III-46
A firm is attempting to estimate the reserves for doubtful
accounts. The probabilities of these doubtful accounts
follow a transition process over time. They evolve from
their starting value to a changed value. As such, the most
effective technique to analyze the problem is
A. Markov chain analysis.
B. Econometric theory.
A. L2
B. L3
C. L4
D. L5
[307] Source: CIA 1191 III-98
(Refers to Fact Pattern #40)
If, in addition to the estimated profits, management of the
bank assesses the probabilities of high, medium, and low
demands to be 0.3, 0.4, and 0.3, respectively, what is the
expected opportunity loss from selecting location L4?
Path
Time in Days
-----------------A-B-C
27
A-D-E-C
33
A-F-C
34
A-F-G-C
36
[311] Source: Publisher
(Refers to Fact Pattern #41)
Which is the critical path?
A. 5.50
A. A-B-C
B. 10.90
B. A-D-E-C
C. 5.67
C. A-F-C
D. 7.00
D. A-F-G-C
[308] Source: CIA 0592 IV-21
Following is a table of probabilities for two separate
product lines, X and Y:
Probability
X profit
Y profit
------------------------.20
$500
$ 50
.70
300
400
.10
600
800
The product line to obtain maximum utility for a risk-averse
decision maker is
B. 27 days.
C. 32 days.
D. 38 days.
[314] Source: Publisher
A particular manufacturing job is subject to an estimated
80% learning curve. The first unit required 50 labor hours
to complete. What is the cumulative average time per unit
after eight units are completed?
A. 20.0 hours.
B. 25.6 hours.
C. 32.0 hours.
D. Average number of units in the system.
D. 40.0 hours.
[315] Source: Publisher
A particular manufacturing job is subject to an estimated
80% learning curve. The first unit required 50 labor hours
to complete. If the learning curve is based on a cumulative
average time per unit assumption, what is the time required
to complete the second unit?
A. 30.0 hours.
B. 40.0 hours.
C. 45.0 hours.
D. 50.0 hours.
[316] Source: Publisher
A particular manufacturing job is subject to an estimated
90% learning curve. The first unit required 50 labor hours
to complete. What is the cumulative average time per unit
after four units are completed?
A. 50.0 hours.
B. 45.0 hours.
C. 40.5 hours.
D. 40.0 hours.
A. Risk.
[317] Source: CIA 0596 III-100
A shortest-route algorithm is used in network models to
B. Uncertainty.
C. Subjective likelihoods.
D. Objective likelihoods.
[322] Source: CMA 1288 5-6
The procedure for choosing the smallest maximum
alternative loss is
A. Deterministic decision making.
B. Queuing theory.
C. Maximax.
D. Minimax.
[323] Source: Publisher
The least exact method for separating fixed and variable
costs is
B. Game theory.
A. 12.0 days.
C. Sensitivity analysis.
B. 13.0 days.
D. Queuing theory.
C. 11.5 days.
[325] Source: Publisher
In a simple linear regression, the standard error of the
estimate represents
A. A measure of variability of the actual observations
from the least squares line.
B. A variability about the least squares line that is
uniform for all values of the independent variable in
the sample.
C. The proportion of the variance explained by
independent variable.
D. 11.0 days.
[329] Source: CMA 1290 4-8
(Refers to Fact Pattern #42)
(Refer to Figure 9.) In order to keep costs at a minimum
and decrease the completion time by 1 days, Networks,
Inc. should crash activity(ies)
A. AD and AB.
B. DE.
C. AD.
D. AB and CE.
[330] Source: CIA 1196 III-96
(Refer to Figure 10.) The network in Figure 10 describes
the interrelationships of several activities necessary to
complete a project. The arrows represent the activities.
The numbers between the arrows indicate the number of
months to complete each activity. The shortest time to
complete the project is
A. 6 weeks.
A. 5 months.
B. 7 weeks.
B. 6 months.
C. 12.5 weeks.
C. 8 months.
D. 13 weeks.
D. 14 months.
[327] Source: CMA Samp Q4-7
When simulating with the Monte Carlo technique, the
average simulated demand over the long run should
approximate the
A. Actual demand.
B. Real demand.
C. Sampled demand.
D. Expected demand.
[Fact Pattern #42]
The PERT network diagram and corresponding activity
B. 2 customers.
total cost for the month of May using the high-low method?
C. 3 customers.
A. $560
D. 4 customers.
B. $650
C. $720
D. $760
[337] Source: Publisher
Rusty, the night manager at a local fast food restaurant, has
had problems with his employees not arriving on time. After
doing some research, he discovered that, if his employees
were on time the night before, the probability that they
would arrive on time again is .7. On the other hand, if they
were late the night before, the probability that they would
arrive on time the following day is .4. What is the
probability that an employee will arrive on time the fourth
day if they arrived on time the first day?
A. .575
B. .583
A. .25 minutes.
C. .61
B. .33 minutes.
D. .7
C. .50 minutes.
D. .67 minutes.
[Fact Pattern #44]
Jackson Co. has the following information for the first
quarter of its year:
Machine Cleaning
Hours Expense
------- -------January
2,100
$ 900
February 2,600
1,200
March
1,600
800
April
2,000
1,000
[334] Source: Publisher
(Refers to Fact Pattern #44)
Using the high-low method, what is Jackson's variable cost
of cleaning per machine hour?
A. $.40
B. $1.20
C. $2.00
D. $2.50
A. 47,000
[335] Source: Publisher
(Refers to Fact Pattern #44)
Using the high-low method, what is Jackson's fixed cost?
A. $160
B. 47,500
C. 48,000
D. 50,000
B. $320
[Fact Pattern #46]
C. $640
D. $1,040
[336] Source: Publisher
(Refers to Fact Pattern #44)
Jackson's management expects machine hours for the
month of May to be 1,400 hours. What is their expected
service 10 in a minute.
[340] Source: Publisher
(Refers to Fact Pattern #46)
If the yearly bonus is given to the operator with the lowest
average number of cars waiting in line, which operator
would receive the bonus?
A. Linus.
B. Schroeder.
C. Snoopy.
D. Pigpen.
[341] Source: Publisher
(Refers to Fact Pattern #46)
If the yearly bonus is given to the operator with the lowest
average number of cars in line not being serviced, which
operator would receive the bonus?
A. Linus.
B. Schroeder.
C. Snoopy.
D. Pigpen.
[342] Source: Publisher
(Refers to Fact Pattern #46)
If the yearly bonus is given to the operator with the lowest
average waiting time, which operator would receive the
bonus?
A. Linus.
to
Donehart will be the hourly rate in effect at the time the
work is performed. Midland is currently negotiating its
labor
contract which includes a 4% increase in direct labor cost
and
should be applicable when Donehart signs the contract.
A learning curve factor of 75% will be applied through the
first 640 units produced, and all benefits derived from the
learning factor will accrue to Donehart.
Donehart must pay the actual labor cost incurred plus a
5%
margin.
B. Schroeder.
C. Snoopy.
D. Pigpen.
[343] Source: Publisher
Red Baron Inc. is a new competitor in the production of
airplane propellers. Red Baron has to train its employees in
the process of making propellers. To increase the speed of
learning, Red Baron will give a bonus to the employee with
the lowest cumulative average time per unit after eight units
are completed. Lucy took 50 hours to complete the first
unit, and she is subject to an 80% learning curve. Sally
took 60 hours to complete the first unit, and she is subject
to a 70% learning curve. Marcy took 40 hours to complete
the first unit, and she is subject to a 90% learning curve.
Patty took 55 hours to complete the first unit, and she is
subject to a 75% learning curve. Which employee will
receive the bonus?
A. Lucy.
B. 19,660.8 hours.
B. Sally.
C. 24,330 hours.
C. Marcy.
D. 27,955.2 hours.
D. Patty.
[Fact Pattern #47]
Donehart Corporation produces agricultural vehicles. Most
of the component parts for these vehicles are
subcontracted to reliable vendors. The final assembly of all
vehicles is accomplished at Donehart's plant. Donehart's
B. $463,104
C. $503,193.60
D. $559,104
[347] Source: Publisher
(Refers to Fact Pattern #47)
Assuming Donehart subcontracts the order to Midland,
what is the total labor hours required to produce the 640
units on the learning curve?
A. 15,120 hours.
B. 18,350 hours.
C. 19,530 hours.
D. 35,840 hours.
A. 90.8%
[348] Source: Publisher
(Refers to Fact Pattern #47)
Assuming Donehart subcontracts the order to Midland,
how many hours will it take to complete a unit after the
initial 640 units on the learning curve are finished?
B. 42%
C. 48.8%
D. 95.3%
A. 11.81 hours.
B. 15.75 hours.
C. 21.50 hours.
D. 23.625 hours.
[349] Source: Publisher
(Refers to Fact Pattern #47)
Assuming Donehart subcontracts the order to Midland,
what is the total out-of-pocket cost?
A. $302,400
D. 22 degrees of freedom.
B. $330,220.80
C. $390,600
D. $426,535.20
[350] Source: Publisher
If PERT analysis were used to calculate revenue for
Oxford Industries, what would be the amount of that
revenue?
A. $21,600,000
D. (0.22, 3.97)
B. $22,516,587
C. $23,441,666
D. $42,875,000
[Fact Pattern #48]
Alpha Company produces several different products and is
making plans for the introduction of a new product which it
will sell for $6 a unit. The following estimates have been
made for manufacturing costs on 100,000 units to be
produced the first year:
PART 4C
Quantitative Methods for
Decision Analysis
ANSWERS
[1] Source: CMA 0683 5-14
Answer (A) is incorrect because .755 is the average
diameter.
Answer (B) is incorrect because .7354 inches equals
the mean minus 1.96 times the standard deviation.
Answer (C) is incorrect because .7746 inches equals
the mean plus 1.96 times the standard deviation.
Answer (D) is correct. Because a 95% confidence
interval equals 1.96 standard deviations in either
direction from the mean, the desired lower boundary
is found using the following formula:
_
x - z (s / (n) )
(x - mu)
i
Sigma = ------------
N
not probabilities.
Answer (D) is correct. The standard deviation
measures the range (dispersion) of observations
around the mean. For example, about 95.5% of all
observations fall within two standard deviations of the
mean of a normally distributed variable.
[20] Source: CMA 1288 5-26
_
_
_
X
X
(X - X)
P
(X - X) P
e
e
e
e
e
------ ------ ---------- ---- ----------$4,000 $5,500 $2,250,000 x .25 = $ 562,500
5,000
5,500
250,000 x .50 =
125,000
8,000
5,500
6,250,000 x .25 = 1,562,500
Variance
$2,250,000
The square root of $2,250,000 is $1,500.
Answer (C) is incorrect because $750 is the square
root of $562,500.
Answer (D) is incorrect because $353.55 is the
square root of $125,000.
[21] Source: CMA 1288 5-27
Answer (A) is correct. The standard deviation for
clocks ($1,500) is lower than the standard deviation
for calculators. Thus, the range of outcomes is less
dispersed and producing clocks is less risky.
Answer (B) is incorrect because the greatest
probability is for a lower rate of return.
Answer (C) is incorrect because both products are
profitable.
Answer (D) is incorrect because calculators have the
higher standard deviation and the greater risk.
$30.40).
Answer (D) is incorrect because the most Stan would
pay for perfect information is the difference between
expected profit with perfect information and expected
profit without perfect information, or $2.60 ($33 $30.40).
[37] Source: CMA 0690 5-19
prospective measure.
Answer (B) is incorrect because probability
assumptions are not used in regression analysis.
[50] Source: CMA 1286 5-5
Answer (C) is correct. Regression analysis finds an
equation for the linear relationship among variables.
The behavior of the dependent variable is explained
in terms of one or more independent variables.
Simple regression has one independent variable, and
multiple regression has more than one.
Answer (D) is incorrect because the coefficient of
determination may be interpreted as the proportion of
the total variation in the dependent variable that is
explained by the regression equation.
[47] Source: CMA 1293 4-29
Answer (A) is incorrect because network analysis is
a means of scheduling long term projects; PERT and
the critical path method (CPM) are examples.
Answer (B) is correct. Decision trees may be used to
describe complex decision situations. Each branch of
the tree represents a different decision, and each twig
extending from each branch represents several
possible outcomes of the decision.
Answer (C) is incorrect because Monte Carlo
simulation is a technique for experimenting with
mathematical models using a computer, which
generates random values for each variable.
Answer (D) is incorrect because linear programming
is a means of allocating scarce resources given a
specified objective and a variety of constraints.
[48] Source: CMA 1286 5-2
Answer (A) is incorrect because a probability less
than 1.0 would not be certainty.
Answer (B) is correct. An event is certain if there is
no doubt that it will occur. The probability is 1.0 if an
event is certain to occur, and 0 if it is certain not to
occur. Under conditions of certainty, consequences
are therefore deterministic, not probabilistic or
unknown.
Answer (C) is incorrect because certainty implies a
specific outcome.
Answer (D) is incorrect because it is a nonsense
answer.
S2
S3
Total
= 0.
= .16667
= .66667
= .75000
------1.58334
=======
The company can expect to have, on average,
1.58334 outages per month. At $800 per outage, the
expected cost is $1,266.67. Thus, paying $1,000 to
avoid an expense of $1,266.67 saves $266.67 per
month, or $3,200 per year.
Answer (D) is incorrect because $7,200 is the
amount the company will save if two outages occur
per month.
x
x
x
x
x
.20 = .20%
.20 = .40%
.30 = .90%
.20 = .80%
.10 = .50%
----Total 2.80%
=====
The expected rate of defective units is 2.80%.
Answer (B) is incorrect because 3.00% is the
unweighted average of the possible rates of defects.
Answer (C) is incorrect because .90% equals 30%
of 3%.
Answer (D) is incorrect because the expected rate of
defects must be less than 3.00%. The probability of a
rate less than 3.00% is 40%, whereas the probability
of a rate greater than 3.00% is 30%.
[96] Source: Publisher
Answer (A) is incorrect because a variance occurs
unless all data points are identical.
x .20 = .648
x .20 = .128
x .30 = .012
x .20 = .288
x .10 = .484
----Variance 1.56%
=====
.1x = 26
x = 260
Selling 260,000 gallons of cleaning fluid would
maximize revenues.
Answer (C) is incorrect because 260,000 gallons
maximizes revenue.
Answer (D) is incorrect because 150,000 gallons is
the profit-maximizing amount.
[114] Source: CMA 0681 5-12
Answer (A) is incorrect because 520,000 gallons is
the quantity that maximizes revenue if the first
derivative function is 26 - .05x.
Answer (B) is incorrect because 260,000 is the
quantity of product to be sold to maximize revenue.
Answer (C) is incorrect because 150,000 gallons is
the profit-maximizing production.
Answer (D) is correct. Profit is equal to the revenue
function minus the cost function
2
2
[(-$100 + $26x - $0.05x ) - ($50 + 8x + $0.01x )].
It is not necessary to combine terms. The profit
maximum is the first derivative of this profit function
(26 - .1x) - (8 + .02x), or 18 - .12x. Set this
derivative equal to zero and solve for x, or 150.
Thus, producing 150,000 gallons of cleaning fluid will
maximize profit.
[115] Source: CMA 0681 5-13
Answer (A) is incorrect because $3,200,000 equals
total revenues.
Answer (B) is incorrect because $(50,000) equals
fixed costs.
0.
[127] Source: CMA 1288 5-4
Answer (A) is correct. Exogenous or input variables
are outside the control of the decision maker.
Exogenous means "originating externally." These
influence the decision model (system) but are not
influenced by it.
Answer (B) is incorrect because at least one of the
decision variables in a model must be under the
decision maker's control; that is, at least one variable
cannot be exogenous.
Answer (C) is incorrect because performance criteria
are the means of measuring the results of a decision
after the fact.
Answer (D) is incorrect because constraints are
limitations (constants, not variables) that must be
considered as part of the decision process.
2X + 3Y = 18
-2X + -Y = -10
-------- --2Y = 8
Y = 4 and X = 3
This solution also results in a profit of $20 [($4 x 3) +
($2 x 4)].
Answer (B) is incorrect because the maximum profit
is $20.
Answer (C) is incorrect because the maximum profit
is $20.
Answer (D) is incorrect because the maximum profit
is $20.
[136] Source: CMA 1291 4-25
Answer (A) is incorrect because correlation and
regression analysis is a means of measuring the
relationships among two or more variables.
Answer (B) is incorrect because discounted cash
flow techniques are used to evaluate alternative
capital investment decisions.
Answer (C) is incorrect because transportation
algorithms are used to minimize transportation costs
when goods must be shipped from multiple factories
to multiple customers or warehouses.
Answer (D) is correct. Linear programming is a
technique used to optimize a revenue, profit, or cost
function subject to constraints. LP is often used for
planning resource allocations. Other business
applications include selecting a product mix, blending
chemical products, scheduling flight crews, assigning
jobs to machines, and determining transportation
routes.
[137] Source: CMA 0692 4-8
Answer (A) is incorrect because producing 2,400
Regular models will result in a profit of only
$264,000.
Answer (B) is correct. This linear programming
problem can be solved graphically or algebraically.
The objective function maximizes the contribution
margin: $110R + $175D. The constraint function for
assembly is: 3R + 4D 12,000. The constraint
equation for testing is: 2.5R + 1.5D 6,000.
Accordingly, at most 4,000 units of the Regular
model (12,000 hours 3) or 3,000 of the Deluxe
model (12,000 hours 4) can be assembled.
Moreover, at most, 2,400 units of the Regular model
(6,000 hours 2.5) or 4,000 units of the Deluxe
model (6,000 hours 1.5) can be tested. Hence,
two feasible solutions are to produce either 2,400
units of the Regular model and none of the Deluxe
model or 3,000 units of the Deluxe model and none
of the Regular. A third feasible solution is the
intersection of the constraint functions, adjusted to
state equalities and solved simultaneously.
Answer (C) is incorrect because producing 1,091
Regular models and 2,182 Deluxe models (the
solution at the intersection of the constraint functions)
will result in a profit of only $501,860.
Answer (D) is incorrect because producing 4,000
2x + 4y 100
6x + 4y 160
4x 60
x 15
profit is $1,050,000.
Answer (B) is incorrect because Funz-N-Oonz has a
profit of only $445,000.
Answer (C) is incorrect because Moonsammy has a
total loss of $430,000.
Answer (D) is incorrect because Step-N-Wolf has a
profit of only $20,000.
$220,000
(150,000)
-------$ 70,000
Variable cost
5
3
1
---- ---- ---Contribution margin
$ 2 $ 3 $ 4
Number of units
100 300 150
---- ---- ---Total contribution margin
$200 $900 $600
==== ==== ====
Combined contribution margin $200 + $900 + $600 =
$1,700.
Answer (D) is incorrect because $3,250 is the
combined amount of sales.
[202] Source: CMA 1291 4-18
network analysis.
Answer (D) is incorrect because linear programming
is a tool for optimizing a cost or profit function given
specified constraints.
y = a + bx
y = 684.65 + 7.2884(420)
y = $3,746
data.
[292] Source: CIA 1192 III-98
Answer (A) is incorrect because the binomial
distribution is a discrete distribution in which each trial
has just two outcomes.
Answer (B) is incorrect because the chi-square
distribution is a continuous distribution used to
measure the fit between actual data and the
theoretical distribution.
Answer (C) is correct. Queuing models assume that
arrivals follow a Poisson process: the events (arrivals)
are independent, any number of events must be
possible in the interval of time, the probability of an
event is proportional to the length of the interval, and
the probability of more than one event is negligible if
the interval is sufficiently small. If Y is the average
number of events in a given interval, k is the number
of events, and e is the natural logarithm (2.71828...),
the probability of k is
k -Y
Y e
f(k) = -----k!
Answer (D) is incorrect because service time has an
exponential distribution. This distribution gives the
probability of zero events in a given interval, i.e., the
probability of a specified time between arrivals.
------------------------------------------Maximum Regret 14 9 12 10 13
------------------------------------------The location with the minimum regret is L2. If
demand is low, L2 has a payoff of -2, whereas L1
has a payoff of 7.
Location
L1 L2 L3 L4 L5
--------------------------------------------Maximum Profit
15 21 17 26 29
--------------------------------------------The location with the greatest potential profit is L5.
[306] Source: CIA 1191 III-97
Answer (A) is correct. Under the minimax regret
criterion, the decision-maker selects the choice that
minimizes the maximum regret (opportunity loss). The
maximum regret for each location is determined from
the opportunity loss matrix (see Discussion of the
next question). The maximum regret for each location
is the highest number in each column as indicated
below:
Location
L1
L2 L3
L4
L5
16
16
16
-------- = ---- = -- = 1.33 customers waiting in line, not
6(6 - 4) 6(2) 12
being served
Answer (C) is incorrect because the average number
of customers waiting in line, not being served, is 1.33.
Answer (D) is incorrect because the average number
of customers waiting in line, not being served, is 1.33.
1.33
---- = .33
4
Answer (C) is incorrect because the average waiting
time is .33 minutes.
Answer (D) is incorrect because the average waiting
time is .33 minutes.
[334] Source: Publisher
Answer (A) is correct. The high-low method is used
to generate a regression line by basing the equation
on only the highest and lowest of a series of
observations. In this problem, March was the lowest
and February the highest.
To
----------------From
On Time
Late
---------------On time
.7
.3
Late
.4
.6
In Out
Pr
-------------------------------------------------------------Day 2 (1.0) x (.7)
= .7 (1-.7) = .3
Day 3 (.7) x (.7) + (.3) x (.4) = .61 (1-.61) = .39
Day 4 (.61) x (.7) + (.39) x (.4) = .583 (1-.58) = .417
=
=
=
=
$50D - $20(Q - D)
$50(950) - $20(1,000 - 950)
$47,500 - $1,000
$46,500
=
=
=
=
$50Q - $25(D - Q)
$50(1,000) - $25(1,100 - 1,000)
$50,000 - $2,500
$47,500
2
160
48
7,680
3
320
38.40
12,288
4
640
30.72
19,660.80
Therefore, the average labor hours per unit is 30.72
hours.
Answer (C) is incorrect because 23.63 hours is the
average labor hours per unit for Midland Inc.
Answer (D) is incorrect because 23.04 hours is
incremental hours per unit after 320 units have been
produced.
[345] Source: Publisher
Answer (A) is incorrect because 8,294.4 hours is the
time required to complete the remaining 360 units
after the learning curve.
Answer (B) is incorrect because 19,660.8 hours is
the time required to complete the 640 units on the
learning curve.
Answer (C) is incorrect because 24,330 hours is the
time required to complete 1,000 units if
subcontracted to Midland Inc.
Answer (D) is correct. The total hours required to
complete a project with a learning curve is found by
adding the total labor hours required to produce the
last set of units on the learning curve with the
remaining number of units times the final hours per
incremental unit. The following chart shows the final
hours per incremental unit:
Units in Run Hours in Run Hours per Unit
------------ ------------ -------------80
4,800
60
80
2,880
36
160
4,608
28.80
320
7,372.8
23.04
Therefore, 23.04 hours per unit times 360 remaining
units gives 8,294.40 hours. This number added to the
19,660.8 hours required to complete the 640 hours
on the learning curve equals 27,955.2 hours.
$426,535.20
===========
freedom.
[353] Source: Publisher