This factory acceptance test procedure outlines inspections and tests to be performed on switchgear panels prior to delivery. It includes checks of the appearance and wiring against drawings, mechanical and interlocking operation tests, resistance and voltage withstand tests on main circuits, and timing estimates for each test. The goal is to verify components and wiring are correct and the panels can withstand the rated voltage.

Uploaded by

wado11
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
Download as xls, pdf, or txt
0% found this document useful (0 votes)
169 views2 pages

FAT Procedure (En)

This factory acceptance test procedure outlines inspections and tests to be performed on switchgear panels prior to delivery. It includes checks of the appearance and wiring against drawings, mechanical and interlocking operation tests, resistance and voltage withstand tests on main circuits, and timing estimates for each test. The goal is to verify components and wiring are correct and the panels can withstand the rated voltage.

Uploaded by

wado11
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1/ 2

FACTORY ACCEPTANCE TEST PROCEDURE

Name of project

Project No.

SWG Model

Quantity

Normative document

Panel No.

IEC 62271-200 Alternating-current metal-enclosed switchgear and controlgear for rated voltages above 1kV and up to and including
52kV
IEC 60298 A.C metal-enclosed switchgear and controlgear for rated voltages. Above 1kV and up to and including 52kV
Date
No.

Inspection Item

Description

Time/each panel

Appearance and structure


check

According to project drawing and diagram,the primary


scheme and all components are in compliance with
requirement

15 Munites

Mechanical Operating and


Interlocking Test

All switchgears of main circuits such as main switch,truck or


disconnector and earthing switch operate properly,the wiring
is correct.All interlock are in compliance with requirement.

0.5 hours

Verification of correct wiring

Checking the wiring conforms to the diagram,all components


& all contacts operate properly,all meters indicate properly

1.5 hours

Measurement of Resistance on
Main Circuits

Carry out the measuring of the resistance of the switchgear's


main circuits, applying a current of range 100A DC on each
phase in succession. All the circuit breakers are inserted in
service position and closed.

15 Munites

Power Frequency Voltage


There must be no flashover and discharge when phase to
Withstand Test on Main Circuits phase and phase-to-earth withstand 28kV,50Hz,60s.

15 Munites

Remark

Other

Edited by/Date

Checked by/Date: