This document contains 6 questions related to project management techniques including:
1) Differences between CPM and PERT, definitions of float types, and crashing procedures.
2) Fulkerson's rules for network diagrams, critical path significance, and identifying critical activities.
3) Drawing network diagrams, calculating time estimates, floats, critical path, and project duration.
4) Determining probability of project completion given activity information in PERT format.
5) Calculating project completion time distribution from a given PERT table.
6) Developing a crashing scheme to reduce a project's duration by 3 weeks given normal and crash times and costs.
This document contains 6 questions related to project management techniques including:
1) Differences between CPM and PERT, definitions of float types, and crashing procedures.
2) Fulkerson's rules for network diagrams, critical path significance, and identifying critical activities.
3) Drawing network diagrams, calculating time estimates, floats, critical path, and project duration.
4) Determining probability of project completion given activity information in PERT format.
5) Calculating project completion time distribution from a given PERT table.
6) Developing a crashing scheme to reduce a project's duration by 3 weeks given normal and crash times and costs.
PERT (2M) b) Define Total float, Independent float, Free float and Head Slack of an activity. (2M) c) What do you mean by crashing of the project and explain crashing procedure for a project
2) a) State Fulkerson?s rules for drawing a network diagram.
b) What do you mean by critical path and give the significance of total float. (2M) c) The following details are available regarding a project. Determine the critical path, the critical activities and the project completion time. (6M)
Activi Predecessor Duration
ty Activity (Weeks) A --- 3 B A 5 C A 7 D B 10 E C 5 F D,E 4
3) Estimate the following for the activities in a project shown
below. a) Draw the network diagram neatly. b) EST, LST, EFT, LFT (2M) c) Total float, Free float, Independent float d) Critical path, Project duration (3M) Activit 1 1 1 2 3 3 3 4 5 6 7 y - - - - - - - - - - - 2 3 4 5 5 6 7 6 7 8 8 Durati 2 7 8 3 6 1 4 6 2 5 6 on 0
4) The owner of a chain of fast food restaurant is considering
a new computer system for accounting an inventory control. A computer company sends the following information about the system installation. Determine the probability of completing the project in 55 days. (10M) Activity A B C D E F G H I Predecess -- A A B B C E D, G, or F H T0, Tm, TP 4,6 5,7, 4,8, 15,20, 10,18, 8,9, 4,8, 1,2 6,7 ,8 15 12 25 26 16 12 ,3 ,8
5) The data for a PERT is given below. Determine the
completion of duration of entire project and find the probability of completing the project between 45 and 54 days. (10M) Activity 1- 1- 1-4 2- 2-5 3-4 3- 4-6 5-6 2 3 3 6 T0, Tm, TP 2,4 6,6 6,12, 2,5 11,14, 15,24, 3,6 9,15, 4,10, ,6 ,6 24 ,8 23 45 ,9 27 16
6) A project has activities with the following normal and crash
times and cost. Determine a crashing scheme for the above project so that the total project time is reduced by 3 weeks.(7 M) Activi Predecess Norm Crash Normal Crash ty or al Time Cost Cost Activity Time (Wee (Rs.) (Rs.) (Wee ks) ks) A --- 4 3 8,000 9,000 B A 5 3 16,000 20,000 C A 4 3 12,000 13,000 D B 6 5 34,000 35,000 E C 6 4 42,000 44,000 F D 5 4 16,000 16,500 G E 7 4 66,000 72,000 H G 4 3 2,000 5,000