Alternating Current: Unit 1 When You Complete This Objective You Will Be Able To
Alternating Current: Unit 1 When You Complete This Objective You Will Be Able To
=
N
N
F
For example the highest load factor for N = 6 will be 80%. Bus-tie circuit-breakers are
often used for maintenance purposes. During normal plant operation all bus-tie circuit-
breakers are normally closed. Short-circuit calculations should always take operation
with N generators into account since it is normal to connect standby sets prior to
switching off sets for maintenance.
A power supply using local generation is generally much weaker than a utility supply
and therefore it is probable that load shedding will be required to maintain system
stability during fault conditions.
Determination of how much load must be shed requires dynamic simulation of the network
for different fault conditions such as a loss of a generator or a short-circuit. Prior to the
study it is necessary to determine which operating configurations are to be considered.
Operating conditions with the bus-tie circuit-breaker both in the open and the closed
positions will greatly increase the complexity of the load shedding system since each busbar
can be operated independently and will require specific load shedding criteria. For most
plants it is recommended that only the standard operating configuration be used for the
dynamic simulations and definition of the load shedding strategy.
Integrated Training Program / Phase B Generator Page 64 of 69
Copyright 2004 International Human Resources Development Corporation
Figure 52 shows each generator having its own transformer. The use of generator
transformers has several advantages:
- provides flexibility in the choice of generator voltage,
- reduces peak short-circuit current at main board,
- allows use of high impedance generator grounding (reduces possible damage to
generator).
Starting and stopping of generator sets
Since Diesel generator sets are often used for emergency power, it is necessary that
steps be taken to ensure that the set will start correctly and quickly when required.
An example of measures to be taken is lubrication, and heating of the cooling water
when the set is not operating. The Diesel generator set manufacturer should list all such
measures and the design should take into account the availability of all auxiliary
supplies necessary during times when set is not operating.
A starting time of 15 seconds from the start order to the closing of the generator circuit-
breaker can be guaranteed by manufacturers. Specifying shorter starting times should be
avoided since the decrease in starting time will be small and could increase the cost of
the set. Critical equipment must be supplied by an UPS in any case.
Two techniques are commonly used for starting.
These are compressed air and battery, compressed air generally being used for larger
sets. The starting equipment should be designed for a minimum of 3 consecutive starts.
It should be carefully monitored in order to enable preventive maintenance to be carried
out prior to a failure during an attempted start. Failure to start is most often due to a
problem with the starting battery. Where reliable starting is essential, consideration
should be given to using compressed air.
When a generator is operating in parallel with another source, it will be synchronized,
and gradually loaded.
When a generator set is operating alone, the load will be applied in one or more steps.
The variation in frequency and voltage will depend upon the size of the step loads. As
an example, step loads of 90% can be applied to a Diesel generator set without the
frequency varying more than 10% and the voltage more than 15%.
Should specific limits on frequency and voltage variations be required, they should be
specified together with the type of load which is to be connected. This information
should include motor starting characteristics such as the starting current, and the type of
starting (direct-on-line, wye-delta). Several steps may be required should the frequency
and voltage tolerance be small.
Integrated Training Program / Phase B Generator Page 65 of 69
Copyright 2004 International Human Resources Development Corporation
When stopping a generator set, the power output should be reduced to zero by
transferring the load to other sources, and the circuit-breaker then tripped. The generator
set should be run for several minutes to allow it to cool down prior to shutdown. In
some cases the cooling system should continue to operate after shutdown in order to
remove latent heat from the machine.
Manufacturers recommendations for shutdown should be followed.
Generator set start and stop sequences should be handled by the generator set control
equipment.
Generator sets should be operated periodically.
For installations where short power outages are not critical, opening the normal
incoming circuit breaker will cause the set to start and automatically pick up the
emergency load.
After the required minimum operating time, the generator circuit-breaker can be tripped
and the normal source circuit-breaker closed.
For plants where power outages mean unacceptable production losses, it must be
possible to test generator sets without first switching off the supply. This is normally
done by using a maintenance transfer. The generator set is started, and after it is ready to
take load, it is synchronized to the incoming supply.
The generator circuit-breaker (or bus-tie circuit breaker depending on the scheme) will
then be closed and the generator will thus be paralleled with the incoming supply. The
closing of the circuit-breaker will cause tripping of the incoming supply and the loads
will be supplied by the generator. The transfer to the normal incoming supply is done in
the same manner without power interruption. Since the supplies are paralleled only for a
few hundred milliseconds, it is not necessary to dimension the switchboard for the
combined short-circuit power of both the normal incoming supply and the generator.
Where equipment has been designed to operate in parallel on a permanent basis, it is not
necessary to trip the incoming supply after connection the generator to the load. For this
case, however, the switchboard must be designed for the combined short-circuit power
of the incoming supply and the generator.
Generator General Protection Philosophy
Since generators are a source of electrical power, the overcurrent protection relays
should be connected to current transformers on the neutral side of the stator windings in
order to cover faults occurring in the windings.
Additional protection relays are required at the generator circuit-breaker only for
applications where generator sets will be operating in parallel with other generator sets
or with the utility, and will pick up faults on the line side of the generator. The current
transformers for these protection relays are installed at the generator circuit-breaker in
order to cover the whole connection to the generator.
Integrated Training Program / Phase B Generator Page 66 of 69
Copyright 2004 International Human Resources Development Corporation
Reverse active and reverse reactive power relays are normally connected to current
transformers on the neutral side of the generator as shown in figure 53. They can also be
connected to the current transformers associated with the circuit-breaker. The location
will depend on the split of works
Figure 53
Recommended Generator Protection
Integrated Training Program / Phase B Generator Page 67 of 69
Copyright 2004 International Human Resources Development Corporation
The recommended protection functions are shown in figure 35. Function reference
numbers are the following:
- protection functions connected to generator neutral current transformers:
o 32P : reverse active power
o 32Q : reverse reactive power serving as loss of field (for generators above 1
MVA)
o 46 : negative sequence (for generators above 1 MVA)
o 49 : thermal image
o 51 : overcurrent
o 51G : earth fault
o 51V : voltage restrained overcurrent
o 87G : generator differential protection (for generators above 2 MVA)
(Note: 46,49, 32P and 32Q can also be connected to the line-side current
transformers)
- Protection functions connected to voltage transformers:
o 25 : synchronism-check (for parallel operation only)
o 27 : undervoltage
o 59 : overvoltage
o 81 : overfrequency and underfrequency
- Protection functions connected to line-side current transformers (for parallel
operation only):
o 67 : directional overcurrent (not required if 87G is used)
o 67N : directional earth fault (on core balance CT for better sensitivity)
- Generator mechanical protection functions connected to sensors
o 49T : stator temperature (recommended for generators above 2 MVA)
o 49T : bearing temperature (recommended for generators above 8 MVA)
o 64F : rotor earth fault protection
The following table gives typical settings for each protection function, and what action
should be taken. This information should be verified with the generator set
manufacturer for each application. A general shutdown means tripping and locking out
the generator circuit breaker, switching off the excitation, and closing the fuel supply to
the engine.
Integrated Training Program / Phase B Generator Page 68 of 69
Copyright 2004 International Human Resources Development Corporation
Figure 54
Recommended Relay Settings and Action
Generator Installation And Maintenance
The installation of generator sets requires close cooperation among several disciplines
such as electrical, construction, process, and mechanical.
The following information should be considered when designing the installation of the
sets.
Location:
The location should be chosen close to the load center to reduce voltage drop and losses
in the connections. Due to the relatively large size of the equipment, adequate space
must be allowed for the transportation to and from the location.
The building housing the equipment must have adequate space to allow maintenance
including overhauling, and be provided with the necessary overhead cranes. The
generator set manufacturer should provide all information concerning space and access
requirements on civil works guide drawings.
Integrated Training Program / Phase B Generator Page 69 of 69
Copyright 2004 International Human Resources Development Corporation
In many locations noise emission will be a problem. The solution consists in sound
proofing the generator set, the building, or a combination of both. Sound proofing will
have a significant impact on cost and therefore must be defined prior to placing an order
for equipment.
Care must also be taken to avoid noise transmission via the generator set base.
Air Intake And Exhaust
In the definition of the rated power of generator sets, the length and configuration of the
air intake ducts and the exhaust piping is important.
In certain cases generator sets will be located in areas where long ducting and piping is
required, and this is to be taken into account in the definition of the rated power of the
engine.
Care must also be taken to ensure that the air intake is remote from the exhaust.
Generator sets used for emergency power must be able to operate in all site conditions.
In desert areas this can include sand storms. Special sand filters are required at the air
intake and can increase the foot print and cost of the generator set.
Compliance with Local Regulation
In many countries there are local regulations that must be met. In addition to
requirements related to emissions, environmental considerations often dictate the design
of the fuel system. This can include the maximum capacity of day tanks and the type of
buried storage tanks (double walled, etc.).
Local regulations must also be respected for the fire detection and protection equipment.
Fire detection should be installed in all locations where generator sets are located.
Automatic fire protection equipment should also be provided where possible.
Fire protection is normally achieved by flooding the building with inert gas. This type of
system requires automatic shutting of ventilation openings, air intake openings, and doors.
Local regulations cover many aspects such as the number and location of warning signs,
the location of the fire control panel, and the type of inert gas which can be used.
The assistance of a local company familiar with such regulations to get all required
approvals is very useful and often indispensable.
Special Tools and Spare Parts
Generator sets require periodic maintenance and also overhauls after a certain number
of years of operation. Special tools are normally required for periodic maintenance, and
additional special tools are required for overhauls. The definition and supply of tools
should be made with the generator set manufacturer based on the type of maintenance to
be performed. The list of special tools should be checked with the maintenance manuals
in order to ensure that all have been provided. Spare parts for the first overhaul should
be provided in addition to those required for normal operation.