Ms Project Help
Ms Project Help
View the schedule Adjust the schedule Save the plan Track and manage Communicate
Tip You can change your project information at any time by clicking Project Information on the Project menu.
Tip To look for a menu command that doesn't appear, click the arrows at the bottom of the menu. The menu expands to show more commands. You can also expand a menu by double-clicking it.
To change one day of the week for the entire calendar, for example, to have Fridays end at 4:00 P.M., click the abbreviation for that day at the top of the calendar. To change all working days, for example, to begin working days Tuesday through Friday at 9:00 A.M., click the abbreviation (such as T for Tuesday) for the first working day of the week. Hold down SHIFT, and then click the abbreviation for the last working day of the week (such as F for Friday).
4 5
Click Nonworking time for days off, or Nondefault working time to change the hours worked. If you clicked Non-default working time in step 3, type the times you want work to start in the From boxes, and the times you want work to end in the To boxes.
Click OK.
In the Task Name field, type a task name, and then press TAB. Microsoft Project enters an estimated duration of one day for the task followed by a question mark.
In the Duration field, type the amount of time each task will take in months, weeks, days, hours, or minutes, not counting nonworking time. You can use the following abbreviations: months = mo weeks = w days = d hours = h minutes = m Note To show an estimated duration, type a question mark after the duration.
Press ENTER.
Tip You can also add a note about a task. In the Task Name field, select the task, and then click Task Notes. Type your information in the Notes box, and then click OK. Note The toolbar button you want may be temporarily hidden. It may not appear because there is not enough room to display all the buttons. Click More Buttons, and then click Task Notes
Create a milestone
A milestone is a task you use to identify significant events in your schedule, such as the completion of a major phase. When you enter a duration of zero days for a task, Microsoft Project displays the milestone symbol on the Gantt Chart at the start of that day. 1 In the Duration field, click the duration of the task you want to make a milestone, and then type 0d.
Press ENTER.
Note Although a task with a duration of 0 is automatically marked as a milestone, you can make any task a milestone. To mark a task as a milestone, click the task in the Task Name field. Click Task Information, click the Advanced tab, and then select the Mark task as milestone check box. Tip To see all milestones, click Milestones in the Filter list. To see the entire project again, click All Tasks in the Filter list.
If you selected End after, type the number of occurrences for the task.
If you selected End by, type the date you want the recurring task to end.
Click OK.
Tip To view all instances of a recurring task, click the plus sign next to the main recurring task.
1 2 3 4 5 6
On the View menu, click Gantt Chart. Click the first task you want to make into a subtask. On the Insert menu, click New Task. In the inserted row, type the name of the new summary task in the Task Name field. In the Task Name field, select the tasks you want to make into subtasks. Click Indent to indent these tasks.
Tip You can indent or outdent a task quickly with the mouse. Select the task, and then position the pointer over the first letter of the task name. When the pointer changes to a two-way arrow, drag right to indent the task or drag left to outdent the task.
You can also easily rearrange project phases in an outlined schedule. When you move or delete a summary task, the subtasks associated are moved or deleted as well.
1 In the ID field (the leftmost field), select the task you want to copy, move, or delete.
To select a row, click the task ID number. To select a group of adjacent rows, hold down SHIFT, and then click the first and last ID numbers of the group. To select several nonadjacent rows, hold down CTRL, and then click the task ID numbers.
To copy the task, click Copy. To move the task, click Cut. To delete the task, press DELETE.
To move the selection you cut or repeat the selection you copied, select the rows where you want to paste it. Be sure to select entire rows. Click Paste. If there is information in the destination row, the new rows will be inserted above the destination row.
Note The toolbar button you want may be temporarily hidden. It may not appear because there is not enough room to display all the buttons. Click More Buttons, and then click the button you want. Tip To add a new task between existing tasks, click a task ID number and then press the INSERT key. Tasks renumber automatically after you insert a new task.
After the tasks are linked, changes to the predecessor's dates affect the successor's dates. Microsoft Project creates a finish-to-start task dependency by default. Because a finish-to-start dependency does not work in every situation, you can change the task link to start-to-start, finish-to-finish, or start-to-finish to model your project realistically.
1 2 On the View menu, click Gantt Chart. In the Task Name field, select two or more tasks to link in the order you want them linked. To select adjacent tasks, hold down SHIFT, and then click the first and last task you want to link. To select nonadjacent tasks, hold down CTRL, and then click the tasks you want to link, in order. 3 4 Click Link Tasks. To change the task link, double-click the link line between the tasks you want to change. The Task Dependency dialog box appears. If the Bar Styles dialog box appears, you didn't click precisely on the task link and need to close this dialog box and click on the task link again. 5 In the Type box, select the task link you want, and then click OK.
Note To unlink tasks, select the tasks you want to unlink in the Task Name field, and then click Unlink Tasks. The tasks are rescheduled based on existing links to other tasks, or constraints.
2 3
Type lead time as a negative number (for example, 2d for two days lead time) or as a percentage. Type lag time as a positive number or as a percentage.
Click OK.
Tip To quickly add lead or lag time to a successor task, double-click the link line on the Gantt Chart, and then type the amount of lead or lag time in the Lag box of the Task Dependency dialog box.
2 3 4
Note If you select a start date for a task in the Start field of the Gantt Chart, or if you drag a Gantt bar to change the start date, Microsoft Project sets a Start No Earlier Than (SNET) constraint based on the new start date. If you select a finish date for a task, Microsoft Project automatically assigns a Finish No Earlier Than (FNET) constraint.
Tip You can drag the deadline symbol on the Gantt Chart to change the deadline date.
Tip You can remove the split by dragging a portion of a split task so that it touches another portion.
Track the amount of work done by people and equipment assigned to tasks or monitor materials used. Have more flexibility in scheduling tasks. Monitor resources with too little or too much work assigned. Keep track of resource costs.
If you don't enter resource information, Microsoft Project calculates your schedule using only task duration and dependencies.
For a work resource (people or equipment), set the resource type to Work. For a material resource (consumed throughout the project) set the resource type to Material.
For each work resource (people or equipment), type the number of resource units available for this resource in the Max. Units field, as a percentage. For example, type 300% to indicate three full-time units of a particular resource. For each material resource (supplies consumed throughout the project), in the Material Label field, type a measurement unit for the material resource, such as ton.
Notes
Resource groups can be used for sorting, filtering, or grouping tasks by resources belonging to a particular group. You can use groups to indicate the department a human resource belongs to or to specify accounting codes for billing purposes. You cannot assign resource groups to tasks. If you want to specify consolidated resources, such as "Carpenters" or "Editors" or "Engineers," enter that as the resource name, and then assign the consolidated resource name to tasks.
Tip As you work in the Gantt Chart or other task views, you can enter additional resource names. To assign additional resources, click Assign Resources, and then type a resource name in the Name field. You can also click Address and select a resource from your e-mail address book.
Tip If a group of resources has the same special working hours and days off, you can create a new base calendar for them. On the Tools menu, click Change Working Time. Click New, and type a name for the new base calendar. Click Create new base calendar to begin with a default calendar. Or to base the new calendar on an existing calendar, click Make a copy of, and then click the calendar name of the existing calendar in the Calendar box. Click OK, and then modify the days and hours on the calendar. On the View menu, click Resource Sheet, and select the new base calendar in the Base Calendar field for each resource that you want to assign the calendar to.
To assign several different resources, hold down CTRL and click the names of the resources. To assign more than one of the same resource (such as two carpenters), type or select a percentage greater than 100 in the Units column. If necessary, type the name of a new resource in the Name column.
Click Assign. A check mark to the left of the Name column indicates that the resource is assigned to the selected task.
Click Close.
Tip You can replace one resource with another. Select the task whose resource you want to replace. In the Assign Resources dialog box, select the assigned resource and click Replace. Select one or more resources to assign, and then click OK.
Tip You can turn off effort-driven scheduling for all new tasks you create. Existing tasks will not be affected. On the Tools menu, click Options, click the Schedule tab, and then clear the New tasks are effort driven check box.
Notes
You can change the timescale to another scale, such as weeks, if that is more appropriate for your project. On the Format menu, click Timescale, and change the values in the Units boxes under Major scale and Minor scale. Changing the view or table does not add information to or remove information from your project; it only changes the project information that is displayed.
Tip You can set the default standard and overtime rates for any new resources you enter. On the Tools menu, click Options, and then click the General tab. In the Default standard rate and Default overtime rate boxes, type the new rates. If you want to set this default for all future projects, click Set as Default. Note If the rate for a resource will change over the course of the project or if the resource will be paid at different rates for different assignments, or if you work with different grades of material, click Resource Sheet on the View menu. In the Resource Name field, select a resource and then click Resource Information. Then, enter the information on the Costs tab.
3 4
In the Fixed Cost field for the task, type the cost. Press ENTER.
Tip In the Cost table, you can also change when the fixed cost is accrued by selecting an accrual method in the Fixed Cost Accrual field.
Notes
When you enter time phased rate changes for a resource and use the prorated cost accrual method, your costs will be calculated using the rates for the appropriate time periods and may change during the completion of the task.
You cannot prorate per-use resource costs or accrue them at the end of a task assignment. They always accrue at the start of the assignment.
To see task costs, on the View menu, click More Views, and then click Task Sheet. To see resource costs, on the View menu, click Resource Sheet.
Tips
You can also view how costs are distributed over a task's duration in the Task Usage view by displaying its cost details. On the View menu, click Task Usage. On the Format menu, point to Details, and then click Cost.
You can view resource costs in more detail by clicking Resource Usage on the View menu, pointing to Details on the Format menu, and then clicking Cost. You can also see resource cost totals displayed graphically by clicking Resource Graph on the View menu, pointing to Details on the Format menu, and then clicking Cost or Cumulative Cost.
Tips
After you set a baseline and begin to track actual costs, you can compare the Baseline and Actual fields to see if total project costs are progressing as expected. As actual work progresses, you can also compare the variance between the Current and Remaining fields to see if you will have enough money to complete the project.
Tips
To see the Gantt bars on a larger or smaller timescale, click Zoom In or Zoom Out. If you have to scroll down to see the project's finish date, and you have outlined tasks in a hierarchy, you can look at just the top-level summary tasks. Click the ID field heading (the left uppermost cell in the Gantt Chart) and then click Hide Subtasks. To see tasks to a specific outline level, click the ID column heading (the left uppermost field in the Gantt Chart). Click Show, and then click the outline level you want.
Tips
You can filter your schedule so that only the critical tasks are displayed. On the Project menu, point to Filtered for, and then click Critical. Click All Tasks in the Filter list to display all the tasks again. After filtering critical tasks, you can sort them by duration so that the critical tasks will be in order, from the longest to the shortest. Sorting the critical tasks helps you see where to put your efforts in shortening tasks.
On the View menu, click the task or resource view you want.
If the view you want to see isn't on the View menu, click More Views for more choices. Click a view in the Views list, and then click Apply. Note Changing the view neither adds information to nor removes information from your project; it only changes what is displayed.
To use a view that is not on the View menu, click More Views, click the view you want in the Views list, and then click Apply.
2 On the View menu, point to Table, and then click the table you want to apply.
To apply a table that isn't on the Table submenu, click More Tables, click the task or resource table you want, and then click Apply. Note that the field headings change as you switch between tables.
Note You cannot apply task filters to resource views or apply resource filters to task views. Tip You can set an AutoFilter in many views to quickly find a subset of data in a field. On the Project menu, point to Filtered for, and then click AutoFilter. Click the arrow in the column that contains the information you want to display, and then click a value you want to use to filter the table. To turn off AutoFilters, point to Filtered for on the Project menu, and then click AutoFilter again.
1 2 3 4
On the View menu, click Gantt Chart. On the Project menu, point to Sort, and then click the sorting option you want. To customize a sort, on the Project menu, point to Sort, and then click Sort by. In the Sort by box, click the field you want to sort by, and then click Ascending or Descending to specify the sort order. Specify sorting options.
To sort by an additional field, click the field in the first Then by box, and then click Ascending or Descending to specify the sort order. To permanently renumber your tasks, select the Permanently renumber tasks check box. To sort tasks within their outline structure so that subtasks remain with their summary tasks, select the Keep outline structure check box. To reset the sort order back to the default sort order, click Reset.
Note Clicking Reset only resets the sort options in the Sort dialog box to their default order. If your tasks were permanently reordered by using the Permanently renumber tasks check box, then clicking Reset will not reset the numbered order of the tasks.
When you've completed this lesson, you'll have adjusted your schedule to meet the finish date.
The Task Dependency dialog box appears. If the Bar Styles dialog box appears, you didn't click precisely on the task link and need to close this dialog box and double-click the task link again.
3 4 In the Type box, check the task dependency. To change the dependency, in the Type box, click the task link you want to use.
Tips
If you have tasks that can be worked on at the same time, you can shorten the critical path most by changing the task dependency. For example, if two tasks can be started at the same time, you can change the task dependency to start-to-start. If two tasks should finish at the same time, you can change the task dependency to finish-to-finish. You can add lead or lag time to tasks to make their start or finish dates overlap each other or to delay a predecessor task. To quickly add lead or lag time to a successor task, double-click the link line on the Gantt Chart, and then type the amount of lead or lag time in the Lag box of the Task Dependency dialog box. Type lead time as a negative number (for example, 2d for two days of lead time) or as a percentage. Type lag time as a positive number or as a percentage
Overlap tasks
If you have tasks that can begin earlier than shown in your schedule, you can overlap (add lead time) to more accurately model how the work will be done. For example, if the electricians can begin wiring outlets before the walls are all finished, you can use time more efficiently by starting the "Wire outlets" task after half of the walls have been roughed in. To do this, you set up a lead time between the finish of the "Rough-in walls" task and the start of the "Wire outlets" task. In Microsoft Project, you type lead time as a negative number or as a negative percentage, such as 50 or 30%.
1 2 3
In the Task Name field, click the task you want, and then click Task Information. Click the Predecessors tab. In the Lag field, type the lead time you want, as a negative number or as a percentage.
Tips
You can quickly add lead time to a successor task by double-clicking the link on the Gantt Chart, and then typing the amount of lead time in the Task Dependency dialog box. You can also delay tasks by adding lag time. For example, if you need a 2-day delay between the finish of one task and the start of another, double-click the link line on the Gantt Chart, and then type 2d in the Lag field of the Task Dependency dialog box.
You may need to drag the divider bar to the right to view the Constraint Type and Constraint Date fields. The Constraint Dates table shows the task name, duration, constraint type for all constraints, and the constraint date, as applicable. If the field you want to see isn't visible, press TAB to move to it.
4 For each task with a constraint other than the default, As Soon As Possible, look at the predecessor tasks and successor tasks on the Gantt Chart to determine if you really need the constraint. Change a constraint if necessary.
To change a constraint type, in the Constraint Type field, click the arrow, and then click the appropriate constraint. To change a constraint date, type or select the date in the Constraint Date field.
Notes
If you type a start date for a task or drag a Gantt bar to change the start date, Microsoft Project sets a Start No Earlier Than (SNET) constraint based on the new start date. If you type a finish date for a task, Microsoft Project automatically assigns a Finish No Earlier Than (FNET) constraint.
If you're scheduling your project from a finish date, typing a start date for a task or dragging a Gantt bar to change the start date sets a Start No Later Than (SNLT) constraint. If you type a finish date for a task, Microsoft Project automatically assigns a Finish No Later Than (FNLT) constraint.
Note If the task duration isn't affected by adding resources, ensure the scheduling options are set to effort-driven scheduling. Click Task Information, and then click the Advanced tab. Be sure the Effort driven check box is selected and the task type is Fixed Units or Fixed Work. Tips
If you don't know which resources are available to take on more work, you can see current resource allocations by clicking Resource Usage on the View menu. To assign a resource part-time, type a value less than 100 in the Units field to represent the percentage of working time you want the resource to spend on the task. To assign more than one of the same resource (such as two carpenters), type a percentage amount greater than 100 in the Units field. To assign several different resources, hold down CTRL as you click nonadjacent resources or hold down SHIFT as you click adjacent resources.
Splitting tasks is useful when you need to stop work on a task temporarily to work on another task. You can split a task as many times as necessary. Splitting a task into parts is not the same as entering a recurring task scheduled to occur at regular intervals, such as a staff meeting.
1 2 3
On the View menu, click Gantt Chart. Click Split Task. Move the pointer over the taskbar you want to split, and then click the taskbar where you want the split to occur.
Note The toolbar button you want may be temporarily hidden. It may not appear because there is not enough room to display all the buttons. Click More Buttons, and then click Split Task. Tips
You can create a longer split by clicking and dragging the taskbar to the right. You can remove the split by dragging a portion of a split task so that it touches another portion.
Click Selected tasks to add new tasks to an existing baseline. 3 Click OK.
Tip To create a budget, first assign resources and enter rate information or any fixed costs, and then save a baseline. The cost information in the baseline plan can serve as a budget. You cannot save this information in an interim plan. Note If you haven't yet entered all your basic project information when you first save your file, you can choose to save it without a baseline.
Note An interim plan saves the tasks' start and finish dates into Start and Finish fields. You can display these interim plan dates by adding the Start and Finish fields to a table.
As you enter actuals, the top bar may move to show a departure from plan. For example, if the start date of "Inventory artifacts" moves by two days and is over half complete at 55%, the red scheduled bar extends two days beyond the lower baseline bar.
1 2 3 4 5
On the View menu, click Tracking Gantt. To view the variance fields, on the View menu, point to Table, and then click Variance. If necessary, press TAB to see the variance fields. On the View menu, point to Toolbars, and then click Tracking. Update the progress of the tasks in your project.
If the task has started as scheduled, click the task, and then click Update as Scheduled
If the task is not progressing as scheduled, in the next lessons you'll learn how to enter actual start and finish dates, enter the actual duration of the task, or update a task's progress as a percentage.
Note You must have saved a baseline in order to have variance information.
In the Task Name field, select the tasks you want to update. To select nonadjacent tasks, hold down CTRL, and then click the tasks. To select adjacent tasks, hold down SHIFT, and then click the first and last task to update.
4 5
Click Update Tasks. Under Actual, type or select a date in the Start or Finish box. If you enter a finish date, make sure that the task is 100% complete; Microsoft Project will assume the date is correct and reschedule tasks accordingly.
Click OK.
Note Entering an actual start date or actual finish date for a task changes the corresponding scheduled date for that task. Baseline dates, however, are not affected.
Tip If you think the task is going to be finished sooner or later than originally scheduled, you can enter a new value in the Remaining dur box. Note If you enter an actual duration longer than or equal to the scheduled duration, the task becomes 100% complete, and the scheduled duration then equals the actual duration.
1 2 3 4 5
On the View menu, click Gantt Chart In the Task Name field, click the task for which you want to update progress. Click Task Information, and then click the General tab. In the Percent complete box, type a whole number between 0 and 100. Click OK.
Notes
Microsoft Project calculates the summary task's percentage of completion based on the progress of its subtasks. You can also manually enter the summary task's percentage of completion, which Microsoft Project will use to calculate the percentage of completion for its subtasks.
By default, Microsoft Project indicates the task's percentage of completion as a thin, black line drawn horizontally through the middle of each Gantt bar on the Gantt Chart.
When you mark a task as 100% complete, Microsoft Project displays a check mark in the Indicators field.
Tip You can use the buttons on the Tracking toolbar to update progress on a task and to perform other tracking activities. To view the Tracking toolbar, point to Toolbars on the View menu, and then click Tracking.
Tips
If it makes no difference which of the resources assigned to a task performs the work, in the Actual Work field for the task, type a value for the combined work done on the task by all the resources. Microsoft Project divides the actual and remaining work among the resources based on when they are scheduled on the task and the remaining work for each assignment. You can also type actual work for a week at a time. On the View menu, click Zoom, and click 1 month to display the timescale in weekly increments. Then, type actual work for the week in the Actual Work field.
Note You must update tasks' actual start and finish dates, actual work values, or actual durations before variances will appear. Microsoft Project calculates the other task information based on the information you enter.
comparison can help you keep track of your resources' performance and plan workloads for future projects.
Tip If it makes no difference which resource assigned to a task performs the work, then type a value for the combined work done on the task by all the resources in the Actual field for the task. Microsoft Project divides the actual and remaining work among the resources based on when they are scheduled on the task and the remaining work for each assignment.
5 6 7
On the View menu, point to Table, and then click Tracking. If necessary, press TAB to view the Act. Cost field. In the Act. Cost field, type the actual cost for the assignment whose costs you are updating.
Tips
You can set the fixed cost for a task to accrue at the beginning or the completion of a task or to be prorated for the length of the task. Click Gantt Chart on the View menu. On the View menu, point to Table, and then click Cost. In the Fixed Cost Accrual field, type or select the accrual method you want. In addition to a standard rate, sometimes assignment costs include a fixed amount charged for a resource each time the resource is assigned to a task, such as equipment costs, setup charges, delivery, or rental fees. You can enter this per-use cost by clicking Resource Sheet on the View menu, and then typing a new cost in the Cost/Use field for the resource whose per-use cost you want to change.
2 3 4 5 6 7 8
To enter actual values for a resource, select a day or other time period in the timescale portion of the view, and then type a value into the Act. cost field for the resource. Tip You can enter actuals in other time increments, such as weeks. On the View menu, click Zoom, and click the increment you want.
Tips
To see the total cost, baseline, and variance information for the entire project, you can display the project summary task. On the Tools menu, click Options, and then click the View tab. Under Outline options, select the Project summary task check box, and then click OK. You can view the resources assigned to a task and the resource costs related to that task. On the View menu, click Task Usage. On the View menu, point to Table, and then click Cost. Drag the divider bar to the right and compare the values in the Total Cost, Baseline, Actual, and Remaining fields for the resources assigned to that task.
baseline (or budgeted) cost. The VAC field displays the variance at completion between baseline cost and scheduled cost for a task.
1 2 3 4 On the View menu, click Gantt Chart. On the View menu, point to Table, and then click More Tables. In the Tables list, click Earned Value, and then click Apply. Drag the divider bar to the right to display all of the Earned Value table fields. The values are calculated based on the actual work and costs up through and including the current date.
To change the calculation date, on the Project menu, click Project Information. In the Status date box, type the date you want to use, and then click OK. Tips
Move the mouse pointer over a field name to get a description of the field; for example, position the pointer over the VAC field and click Help on VAC for a description of the field. In the Task Usage view, you can view earned value data over time periods such as daily, weekly, monthly, quarterly, or yearly. On the Format menu, click Detail Styles, and then click the Usage Details tab. In the Available fields list, hold down CTRL, click the earned value fields you want to display (such as ACWP, BCWP, CV, or SV), and then click Show. Double-click the timescale to change the time periods that you see. To see cost variances for the entire project, you can display the project summary task. On the Tools menu, click Options. Click the View tab and under Outline options, select the Project summary task check box.
The Resource Usage view shows the total hours the resource is working, the total hours the resource is working on each task, and the hours worked per time period on the timescale.
Resources with no tasks yet assigned do not have tasks listed under their names. Tasks with no resources assigned are listed under Unassigned in the Resource Name field.
On the Project menu, point to Filtered for and then click Overallocated Resources. Any work resources that are overallocated are displayed and highlighted.
Tips
If you see number signs (##) in the timescale portion of the Resource Usage view, the columns in the timescale are not wide enough to display the information. To change the width of the columns, click Timescale on the Format menu, and then increase the value in the Size box. You can see how much of a resource's work is allocated to particular tasks and per time period. On the Format menu, click Detail Styles. Click the Usage Details tab and in the Available fields list, click Percent Allocation, and then click Show.
Tip You can also use the Resource Usage view to see and edit work values for tasks grouped under the resources are assigned to them. On the View menu, click Resource Usage. Note You can also change the individual work values (or hours) for the assigned resources on the timescale portion of the view.
Drag the task to the resource that you want to reassign it to.
Delay a task
A simple way to resolve a resource overallocation is to delay a task assigned to the resource until the resource has time to work on it. You can add delay to a task, check the effect on the resource's allocation, and then adjust the delay further if necessary. Delaying a task also delays the start dates of its successors and can affect the finish date of your schedule. To avoid this, delay tasks with free slack first (noncritical tasks) and only delay them up to the amount of slack that is available for each task. Experiment with adding delay to different tasks to see the effect on your schedule.
1 2 On the View menu, click More Views. In the Views list, click Resource Allocation, and then click Apply.
In the timephased portion on the top right, overallocation for a resource is displayed in red. In the bar chart below, slack for tasks to which the resource is assigned appears graphically as a thin slack bar adjoining the regular Gantt bar.
In the Resource Name field in the top left portion of the view, click the resource name for the overallocated resource with a task you want to delay. In the Leveling Delay field (bottom left portion of the view) for the task you want to delay, type the amount of time that you want the task to be delayed.
To ensure that successor tasks are not affected, do not enter more lag than the amount of free slack for that task.
5 To return to a single view, on the Window menu, click Remove Split.
To change a day of the week for the entire calendar, select the day at the top of the calendar.
4 Click Use default, Nonworking time, or Nondefault working time.
If you clicked Nondefault working time in step 4, type the times you want work to start in the From boxes and the times you want work to end in the To boxes. Click OK.
Tip If a group of resources will have the same special working hours and days off, you can create a new base calendar for them. Click New in the Change Working Time dialog box, and type a name for the new base calendar. Click Create new base calendar to begin with a default calendar. Or, to base it on an existing calendar, click Make a copy of, and then click the calendar name in the Calendar box. Click OK, and then modify the days and hours on the calendar. On the View menu, click Resource Sheet, and select the new base calendar in the Base Calendar field for each resource you want to assign it to.
Communicating results
To manage a project effectively, you need to communicate and distribute project information. You might prepare reports or presentations; publish information on a Web site; or use Microsoft Project Central to communicate with your workgroup on the Web. With Microsoft Project, you can format and publish views and print reports to meet the needs of a particular person or group. You can publish the information in Web format (HTML) or include it in a presentation using a program such as Microsoft PowerPoint.
Lesson: How do you format the schedule to look the way you want?
When you have a large task list, it can be difficult to focus on areas that concern you. To emphasize what you need to see, you can customize the format of the task list and the Gantt bars. You can format categories of information, such as all tasks that must end by a certain date. You can also make some tasks bold or use a different font for them.
Tip To undo the formatting you chose with the GanttChartWizard, click GanttChartWizard and reapply the default options by clicking Next for each step to return the Gantt Chart to its default settings.
6 7 8
Tip To change the formatting of an individual Gantt bar, select the task, and then click Bar on the Format menu. Click the Bar Shape tab, and format the Gantt bar.
In the Item to Change box, click the type of information you want to change, and then select formatting options for that information. To change the formatting of another type of information without closing the dialog box, click a new type in the Item to Change box, and then select formatting options for that information. Click OK.
Tips
To change the format of an individual task, select the task, click Font on the Format menu, and then select formatting options for that text. To quickly copy the text formatting of one task to another, select the task with formatting you want to copy, click Format Painter, and then select the task to which you want to apply that formatting.
Format text
If certain information in your view requires urgent attention, such as the completion date of a slipped task, you can call attention to that information by formatting it individually. In most views, you can change the font, font style, color, and size of the text.
To change the font, font style, color, and text size, select the text you want to change, click Font on the Format menu, and then select the formatting you want to apply. You can quickly apply character formatting such as bold, italic, or underlining by using the Formatting toolbar. Select the text you want to format, and then click Bold, Italic, or Underline. To change text alignment, click Align Left, Align Center, or Align Right.
Note This type of formatting won't change if you change the data later. You'll need to individually change the formatting you added.
2 3 4 5 6
Click the Header, Footer, or Legend tab. Click the Left, Center, or Right tab. In the text box, place the insertion point where you want to add the project information. In the General and Project fields boxes, click each type of information you want, and then click Add. Microsoft Project will use the information you typed into the Project Information and Properties dialog boxes to fill in each type of information.
Note To format project information, you need to select the ampersand (&) that precedes it, or select the entire line, and then click Format Text Font. Select the font, font style, size, and color you want; select the Underline check box if you want; and then click OK.
To see what a project view will look like when printed, click Print Preview.
Tips
To change options, such as printing notes or a specific number of columns, click Page Setup on the File menu, click the View tab, and then select the options you want. If you preview a view and then decide to change the appearance of the view pages, click Page Setup in the Print Preview window, and then make the changes you want. To return to the Print Preview window, click Print Preview in the Page Setup dialog box.
Note To change the default print settings, click Print on the File menu, and then specify the printer and printer properties, the print range, the number of copies, and the date range. To see the results of your changes immediately, click Preview in the Print dialog box.
each resource's task assignments, as well as the work, delay, and start and finish dates for each assignment.
1 2 3 4 On the View menu, click Reports. Click the report type you want, and then click Select. Click the specific report you want to print, and then click Select. Click Print.
Tips
You can change the appearance of your report pages and see the results before you print. Click Page Setup in the Print Preview window, make the changes you want, and then click Print Preview to return to the Print Preview window. You can switch between Print Preview and Page Setup as many times as necessary before printing your report. You can print any report without using Print Preview. On the View menu, click Reports, click Custom, and then click Select. In the Reports list, click the report you want to print, and then click Print. Make any necessary changes to the print options, and then click OK.