Em - 1110 2 1911
Em - 1110 2 1911
Em - 1110 2 1911
EM 1110-2-1911
Washington, DC 20314-1000
30 September 1995
EM 1110-2-1911
30 September 1995
US Army Corps
of Engineers
ENGINEERING AND DESIGN
ENGINEER MANUAL
AVAILABILITY
Copies of this and other U.S. Army Corps of Engineers
publications are available from National Technical Information
Service, 5285 Port Royal Road, Springfield, VA 22161. Phone
(703)487-4650.
Government agencies can order directlyu from the U.S. Army
Corps of Engineers Publications Depot, 2803 52nd Avenue,
Hyattsville, MD 20781-1102. Phone (301)436-2065. U.S.
Army Corps of Engineers personnel should use Engineer Form
0-1687.
UPDATES
For a list of all U.S. Army Corps of Engineers publications and
their most recent publication dates, refer to Engineer Pamphlet
25-1-1, Index of Publications, Forms and Reports.
CECW-ED
Manual
No. 1110-2-1911
EM 1110-2-1911
30 September 1995
1. Purpose. The purpose of this manual is to present principles and methods for construction
control of earth and rock-fill dams.
2. Applicability. This manual applies to all Corps of Engineers divisions and districts having
responsibility for construction of earth and rock-fill dams.
3. General. This manual is a guide to construction and inspection of earth and rock-fill dams in
those aspects that pertain to safe and satisfactory performance.
FOR THE COMMANDER:
ROBERT H. GRIFFIN
Colonel, Corps of Engineers
Chief of Staff
CECW-ED
Manual
No. 1110-2-1911
EM 1110-2-1911
30 September 1995
Paragraph
Chapter 1
Introduction
References . . . . . . . . . . . . . . . . . . . . . . 1-1
General Considerations . . . . . . . . . . . . . . 1-2
Chapter 2
Field Organization and
Responsibility
Resident Inspection Force . . .
Field Laboratory . . . . . . . . .
Assistance by Higher Echelon
Records and Reports . . . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Chapter 3
Foundation and Abutment
Treatment
General . . . . . . . . . . . . . . . . . . . . .
Clearing, Grubbing, Stripping, and
Cleaning . . . . . . . . . . . . . . . . .
Seepage Control . . . . . . . . . . . . . .
Treatment of Unfavorable Conditions
Dewatering and Drainage of
Excavated Areas . . . . . . . . . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
2-1
2-2
2-3
2-4
Page
Subject
Paragraph
2-1
2-3
2-4
2-4
. . . . 3-1
3-1
. . . . 3-2
. . . . 3-3
. . . . 3-4
3-1
3-3
3-6
. . . . 3-5
3-10
Section II
Quarries and Rock Excavation
General . . . . . . . . . . . . . . . . .
Equipment . . . . . . . . . . . . . .
Test Quarries . . . . . . . . . . . . .
Obtaining Specified Rock Fill .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Page
4-5
4-3
4-4
4-5
4-6
4-8
4-8
4-9
4-10
Section III
Final Condition of Borrow Areas,
Quarries, and Spoil Areas
Borrow Areas . . . . . . . . . . . . . . . . . . . . 4-7
Quarries . . . . . . . . . . . . . . . . . . . . . . . . 4-8
Spoil or Waste Areas . . . . . . . . . . . . . . . 4-9
4-11
4-11
4-11
Chapter 5
Earth-Fill and Rock-Fill
Construction
Chapter 4
Borrow Areas and Quarries
Section I
Fill Processing and Compaction
Equipment
Heavy Compaction Equipment . . . . . . . . 5-1
Hand-Operated Compaction Equipment . . 5-2
Spreading and Processing Equipment . . . . 5-3
5-1
5-1
5-1
Section I
Earth Fill
Excavation, Handling, and
Hauling Equipment . . . . . . . . . . . . . . 4-1
Section II
Test Fills
Rock Test Fills . . . . . . . . . . . . . . . . . . . 5-4
Earth Test Fills . . . . . . . . . . . . . . . . . . . 5-5
5-1
5-5
4-1
EM 1110-2-1911
30 Sep 95
Subject
Section III
Impervious and Semipervious Fill
Definitions . . . . . . . . . . . . . . . . .
Compaction Fundamentals . . . . . .
Compaction Specifications . . . . . .
Simple Control Procedures . . . . . .
Field Control Testing and Sampling
Operations in Adverse Weather . . .
Compaction in Confined Areas . . .
Paragraph
.
.
.
.
.
.
.
Section IV
Pervious Fill
Definition . . . . . . . . . . . . . . . . . . .
Compaction Equipment . . . . . . . . . .
Material Gradations . . . . . . . . . . . .
Water Content Control . . . . . . . . . .
Lift Thicknesses and Number of
Passes or Coverages . . . . . . . . .
Density Requirements . . . . . . . . . . .
Construction Control . . . . . . . . . . .
Test Results and Actions to be Taken
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-6
5-7
5-8
5-9
5-10
5-11
5-12
Page
5-5
5-6
5-6
5-7
5-8
5-15
5-16
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-13
5-14
5-15
5-16
5-17
5-17
5-18
5-18
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-17
5-18
5-19
5-20
5-18
5-19
5-19
5-20
Section V
Rock Fill
General . . . . . . . . . . . . . . . . . . . . . . . . . 5-21
Hard Rock . . . . . . . . . . . . . . . . . . . . . . 5-22
Soft Rock . . . . . . . . . . . . . . . . . . . . . . . 5-23
5-21
5-21
5-22
5-22
5-22
5-22
Section VII
Sequence of Placement and
Measurement of Quantities
Schedule of Construction . . . . . . . . . . . . 5-27
Placement Sequence . . . . . . . . . . . . . . . . 5-28
Measurement of Quantities . . . . . . . . . . . 5-29
5-22
5-22
5-23
ii
Paragraph
Chapter 6
Miscellaneous Construction
Features
River Diversion . . . . . . . . . . . .
Stage Construction . . . . . . . . . .
Surface Drainage Facilities . . . .
Service Bridge Pier Foundations
Instrumentation . . . . . . . . . . . .
Haul Roads, Maintenance Roads,
and Public Roads . . . . . . . .
Chapter 7
Records and Reports
Daily Reports . . . . . . . . . . . .
Compaction Control Reports . .
Instrumentation Observations . .
Construction Foundation Report
Final Construction Report . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
6-1
6-3
6-3
6-3
6-3
. . . . . . . 6-6
6-4
.
.
.
.
.
7-1
7-1
7-1
7-6
7-6
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Appendix A
References
Appendix B
Methods of Relating Field Density
Data to Desired or Specified
Values
Appendix D
Instructions for Preparing Periodic
Summaries of Field Compaction
Control Data on Earth and
Rock-Fill Dams
Appendix E
Description and Use of Instruments
During Earth and Rock-Fill Dam
Construction
Index
5-23
5-23
5-25
.
.
.
.
.
Page
6-1
6-2
6-3
6-4
6-5
.
.
.
.
.
.
.
.
.
.
Appendix C
Field Compaction Control Forms
and Supplemental Instructions
Section VI
Semicompacted Earth Fills
Uses . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-24
Specifications . . . . . . . . . . . . . . . . . . . . 5-25
Construction Control . . . . . . . . . . . . . . . 5-26
Section VIII
Slope Protection
Areas to be Protected . . . . . . . . . . . . . . . 5-30
Upstream Slope Protection . . . . . . . . . . . 5-31
Downstream Slope Protection . . . . . . . . . 5-32
Subject
.
.
.
.
.
7-1
7-2
7-3
7-4
7-5
EM 1110-2-1911
30 Sep 95
Chapter 1
Introduction
1-1.
References
General Considerations
The safety and satisfactory performance of earth and rockfill dams require competent and adequate supervision,
careful inspection, and control testing. It is the responsibility of the Resident Engineer to bring to the attention of
the Engineering Division any design or construction detail
not adequately covered by the plans and specifications. The
Resident Engineer must provide the field supervision and
control required to accomplish the intent of the plans and
specifications. The resident engineer must also coordinate
the work with design engineers and provide guidance to the
contractor if unexpected conditions are discovered during
construction.
a. Importance of construction control. Many earth and
rock-fill dams have shown signs of distress or experienced
partial failure (necessitating expensive remedial measures)
from causes traceable to poor construction practices or to
unexpected adverse conditions. Close observations by soils
engineers and geologists of foundation and abutment
preparation, excavation, fill operations, movements and
deformations of fill and foundation, and seepage can often
enable early detection and correction of undesirable
conditions. Construction control should ensure that:
(1) Necessary actions are taken to remedy or allow for
unexpected conditions. Frequent and careful observations
by inspectors, geologists, and field engineers, who are
familiar with conditions assumed for design, are essential
during stripping of the foundation, opening of borrow areas,
and excavating operations. Immediate reporting of unexpected conditions will enable the Resident Engineer to
1-1
EM 1110-2-1911
30 Sep 95
Chapter 2
Field Organization and
Responsibility
2-1.
2-1
EM 1110-2-1911
30 Sep 95
laboratory compaction, and in detecting inadequate construction procedures and unsafe conditions.
c. Number of personnel and skills required. Experienced construction engineers, inspectors, and technicians
are required for construction control operations on earth and
rock-fill dams. The Resident Engineer, the field engineer in
charge of supervision and inspection, chief inspector,
materials engineer or chief soil technician, and geologists
should have been associated with the project from the time
of any preliminary construction operations such as test fills,
quarry blasting and rock production tests, and excavations
of tunneling made to inspect subsurface conditions.
Augmentation of this cadre with less experienced inspectors
and technicians will provide a sufficiently capable inspection
force. An example of a resident inspection force organization for a large earth and rock-fill dam is shown in
Figure 2-1. Additional inspectors and technicians may be
required during certain phases when construction operations
are at their peak or when several major portions of the earth
or rock-fill dam are being constructed concurrently. An
example of a typical similar organization for a smaller earth
dam project is shown in Figure 2-2. It should be noted that
the organization for a small earth dam is very flexible, being
dependent on the magnitude and extent of the construction.
Small projects often require temporary assignment of
specialized personnel, such as soils engineers and geologists,
during certain construction phases.
d. Quality control.
(1) The contractor is responsible for quality control, and
the contract specifications give requirements for the
contractor quality-control organization, personnel qualifications, facilities and types of tests, and reporting of test
data and inspections. The Government field inspection force
has the responsibility of accepting completed work and must
have a staff large enough to accomplish the following:
(a) Check the effectiveness and adequacy of the contractors quality-control system and take action to have
deficiencies corrected.
(b) Inspect construction operations to prevent defective
work and placement of unsatisfactory materials.
(c) Monitor progress.
(d) Perform check tests and acceptance tests.
(e) Resolve or report field problems and conflicts with
contract documents to higher authority.
(f) Make acceptance inspections.
(2) Contractor quality-control operations will, if properly
implemented, assist in achieving adequate construction,
Figure 2-1. Example of resident engineers staff organization for large earth dam project
2-2
EM 1110-2-1911
30 Sep 95
Figure 2-2. Example of resident engineers staff for small earth dam project
2-2.
Field Laboratory
2-3
EM 1110-2-1911
30 Sep 95
Discrepancies resulting from variations in testing equipment
and techniques should be carefully avoided. Water content,
compaction, relative density gradation, and Atterberg limits
tests are the most common tests conducted. Water content
and compaction tests are used for control of cohesive soils
in impervious and random fills. Atterberg limits tests may
be used for control of fills of fine-grained cohesive soils
where good correlations of optimum water content and
maximum dry density with the Atterberg limits have been
established. Gradation and relative density tests are used for
control of pervious fills. Gradation tests are also used for
control of rock fill. Field density tests are performed on the
fill, but compaction tests on the material and water content
determinations may be made either in the central laboratory
or in the field. The central laboratory must have equipment
for these tests, but supplemental portable units may be
advisable for gradation, compaction, and water content
testing at remote locations. Panel pickup trucks are often
used to transport equipment for field density testing,
undisturbed (record) sampling in the fill, and sampling in
borrow areas. Specially equipped pickup trucks with a
small hoist may be required where large-scale field density
tests are to be performed on material such as rock fill or
soils with a high percentage of large gravel sizes.
2-3.
2-4
EM 1110-2-1911
30 Sep 95
specifications, construction procedures, sequence of operations, and the location and as-built dimensions of important
features. These are necessary to evaluate claims made by
the contractor based on changed conditions, or claims by the
Contracting Officer that work performed does not meet
contract requirements. Progress reports are also needed for
the district office and to provide a basis for payments to the
contractor for work accomplished. Inspectors must maintain
a daily inspection report (or log), and a master diary must
be kept by the Resident Engineer. The required content of
these documents is outlined in EM 415-1-302, Inspection
and Work Records. Details of specific construction control
records and reports are described in Chapter 7.
a. Construction records. These records provide useful
data for designing future alterations and additions to the
structure, determining causes of later undesirable movement
or seepage, or interpreting piezometric data. As-built
drawings, construction photographs, descriptions of foundation conditions encountered and various treatments,
compaction data, and test data on record samples should be
included in the records.
b. Construction reports. The construction foundation
report should include details such as dip and strike of rock,
2-5
EM 1110-2-1911
30 Sep 95
Chapter 3
Foundation and Abutment
Treatment
3-1.
General
EM 1110-2-1911
30 Sep 95
be done for foundation areas under the embankment unless
specifically permitted by the plans and specifications or
approved by the design office, as the effects of a lightly
compacted layer at the base of the dam could adversely
affect stability.
3-2
Figure 3-1. Final foundation cleaning using compressed air, DeGray Dam, Arkansas
EM 1110-2-1911
30 Sep 95
(5) Where rough and irregular surfaces remain after hand
excavation, troughs, pits, and other depressions are filled
with concrete to provide a more even surface on which the
first layer of the embankment may be compacted. As
previously noted, this procedure is termed dental treatment
and is discussed further in paragraph 3-4b(3). If foundation
grouting has been performed, cleanup operations should
include removal of any spilled or washed grout that might
otherwise conceal surface imperfections and pockets of
undesirable material.
(6) Before placing the first layer of embankment
material, the cleaned and prepared rock surface should be
moistened, but no standing water should be permitted.
Moistening the rock surface is recommended instead of
using overly wet soil in the first lift to obtain good contact.
Use of heavy pneumatic equipment (preferably a rubbertired roller) is recommended for compacting the first lift on
rock surfaces. This will enable the rock surface to be kept
intact, especially where the rock surface is irregular or
composed of thin beds of alternating hard and soft rock.
(7) Foundations consisting of compaction-type shales and
slaking tuffs should be protected from disintegration caused
by drying due to exposure to air. The handling of clay
shales is discussed in paragraph 3-4a(2).
3-3.
Seepage Control
3-3
EM 1110-2-1911
30 Sep 95
hydraulic systems. A dragline excavating a slurry trench is
shown in Figure 3-2.
(d) The specific gravity of the slurry must be high
enough to ensure that hydrostatic pressure exerted by the
slurry will prevent caving of the sides of the trench and yet
not be so high as to limit the depth to which the excavating
bucket will operate. Typical values of specific gravity of
slurries used in past jobs range from 1.05 to 1.2, with some
values as high as 1.5. The slurry level is generally
maintained 2 to 3 ft above the groundwater level.
(e) Procedures for cleaning the bottom of the trench,
removing sand which settles out of the slurry, continuous
control of viscosity and specific gravity of the slurry, and
mixing and placing the backfill are critical in achieving
successful results. An example of successful slurry trench
construction is that at West Point Dam, Chattahoochee
River, Alabama and Georgia, in which the bottom of the
trench was cleaned with a modified dragline bucket (Jones
3-4
EM 1110-2-1911
30 Sep 95
(3) Grout curtains.
(a) Grouting is the injection by pressure of grout (a
mixture of water, cement, and other chemical compounds)
into openings (voids, cracks, or joints) in a rock mass. The
grout is designed to be injected as a fluid and to stiffen or
solidify after injection.
(b) The rock foundation and abutments of most large
dams require grouting to reduce seepage and to reduce
hydrostatic uplift pressures in dam foundations. Grout
curtains are frequently tied into the bottom of cutoff
trenches which extend through soil overburden to the rock
foundation. Grouting procedures must be tailored to the
formation characteristics of the foundation being grouted,
and close supervision and inspection are required to obtain
satisfactory and economical results. The resident geologist
should direct and supervise the inspection of grouting work;
he should be experienced in this type of work since many
decisions must be made as the work progresses based on
judgment and evaluation of results. Successful and economical grouting requires a complete and reliable subsurface
investigation to allow determination of the volume which
must be grouted. Items which must be determined by the
grouting inspector are grout hole location, geometry, length
and inclination; injection pressure and rate; grout properties
(liquid, transition, set); and necessary degree of improvement in soil properties.
b. Blankets, relief wells, galleries, and toe drains.
(1) Upstream impervious blankets.
A horizontal
upstream impervious blanket controls underseepage by
lengthening the path of underseepage. The effectiveness of
the blanket depends on its length, thickness, continuity, and
the permeability of the material/soil from which it is
Figure 3-3. Progressive excavation and backfilling scheme for slurry trench construction
3-5
EM 1110-2-1911
30 Sep 95
installation of rock bolts and other structural support
features by plans and specifications. Drainage galleries at
the base of a dam or in an abutment of soil or weathered
rock are usually concrete-lined tunnels. Inspection of
concrete-lined tunnels requires knowledge of concrete
placement and backfill practices around concrete structures
in addition to knowledge of grouting and seepage control in
pervious soils. Inspection of concrete, including proper
placement techniques, is thoroughly discussed in the ACI
Manual of Concrete Inspection (1967). EM 1110-2-2000
also contains information related to the inspection of
concrete placement.
(4) Toe drains.
(a) Toe drains collect and facilitate removal of seepage
water at the downstream toe of the dam to prevent formation of soft boggy areas and/or boils. Toe drains are
generally connected to the horizontal drainage blanket and
sometimes to the relief well system to collect and remove
seepage water in thin pervious strata in the upper foundation
that the deeper relief wells cannot drain.
(b) Toe drains generally consist of a trench containing a
perforated collector pipe surrounded by filter gravel with the
remainder of the trench backfilled with sand. Particular care
must be exercised in placement of the backfill. Unless the
sides of the trench are approximately sloped at the angle of
repose of the filter material, a wood or steel form must be
used to keep the filter layers separated as the backfill is
brought up. Additionally, filter materials must be protected
from contamination which could result from inwash during
a rainstorm. Construction (backfilling) of toe drains in short
sections could minimize contamination.
(c) The same control procedures are used for toe drains
as those that are used in construction of impervious fill in
the main embankment; these are described in Section IV of
Chapter 5. Gradation tests on filter materials should be run
at least twice each day during placement operations. Stockpiled as well as in-place filter material should be tested.
Handling and compaction of the filter material must be
closely controlled to avoid segregation and particle
breakage.
3-4.
3-6
EM 1110-2-1911
30 Sep 95
that is released with time after overlying materials are
removed. Therefore, excavating in clay shales should be
completed and backfilled without delay. The last foot or so
of excavation into a slaking clay shale should be deferred
until just prior to backfill operations in order to minimize
the time of exposure of the final clay shale surface. During
winter, the depth of cover should be no less than the frost
penetration depth; operating in this manner will provide a
fresh surface to compact the fill against and eliminate the
chance of a soft stratum between the unweathered shale and
the fill. This is generally a costly procedure for steep
slopes, but becomes more economical for slopes flat enough
for equipment to work on.
(c) Only rubber-tired equipment should be used in final
excavation, cleanup, and initial fill placement on clay shales
to minimize disturbance. Final clay shale surfaces should
not be scarified prior to covering with fill. If pressure
cleaning is required, only air pressure (i.e, no water) should
be used.
(d) Various types of coatings have been applied to
protect exposed clay-shale surfaces; they include gunite,
sprayed asphalt, and other bituminous materials and resin
emulsions. Gunite is reliable when reinforced and anchored
to the shale, but particular care must be exercised to avoid
a drummy condition. This type of protection was successfully used at Waco and Proctor Dams in Texas. Although
bituminous coatings and resins have been used successfully,
they do not always provide adequate protection for the clay
shale. At Waco Dam, an asphalt emulsion membrane used
on near-vertical cuts was not always adequate, even with
multiple application. Evidence of its inadequacy was that
the shale surfaces spalled and slaked. Concrete slabs,
whether placed specifically for protective purposes or as
slabs for an overlying structure, provide good protection.
Exposed surfaces may also be protected by wet mats.
Burlap has proven to be an unsatisfactory mat because it is
too porous to retain water for any length of time. Maximum allowable exposure time can vary from a few minutes
to several hours depending on the characteristics of the shale
and the prevailing weather conditions.
(3) Collapsible soils.
(a) Collapsible soils are generally soils of low density
and plasticity which are susceptible to large decreases in
bulk volume when they are exposed to water. Collapsible
soils are characterized by bulky grains (in the silt-to-finesand grain size) along with some clay. Collapse results from
softening of clay binder between larger particles or the loss
of particle-to-particle cementation due to wetting. Volume
change from collapse occurs rapidly (relative to consolidation) and can be very significant especially if the soil is
EM 1110-2-1911
30 Sep 95
encountered unexpectedly during construction. As mentioned earlier, the extent of these deposits is often
impossible to establish accurately during the exploratory
stages, and in some cases an entire deposit may be missed.
Old river channels beneath a dam foundation, filled with
course-grained pervious material, would constitute a
dangerous open path of seepage. Channel fillings of soft
fine-grained materials can cause differential settlements and
cracking of the embankment if not removed and replaced
with properly compacted material. Where the existence of
such deposits has been revealed, additional exploration by
borings, test pits, etc., to establish their extent may be
necessary. The design engineer can then decide what
measures will have to be taken to modify the design or to
remove the deposit. An old river channel found during
foundation excavation for the core trench at Fall Creek
Dam, Fall Creek, Oregon is shown in Figure 3-4.
EM 1110-2-1911
30 Sep 95
EM 1110-2-1911
30 Sep 95
3-10
EM 1110-2-1911
30 Sep 95
taken. Wells or wellpoints from which fines are being
discharged must be sealed and replaced with wells having
adequate filters. Piezometers should be installed with
dewatering systems to monitor drawdown levels in the
excavated area. Piezometers should be read daily and the
readings plotted to enable continuous evaluation. Daily
pumping records should also be kept and evaluated to
determine the quantity of water removed by dewatering
systems and sump systems. These records are valuable for
detecting inadequate seepage control and for evaluating
claims by the contractor of changed conditions with respect
to the plans and specifications. A detailed description of
various types of dewatering systems, installation procedures,
and performance evaluation is given in TM 5-818-5. A
sketch of a single-stage wellpoint dewatering system is
shown in Figure 3-11a, and a sketch of a multistage
dewatering system with provisions for drainage of surface
water is shown in Figure 3-11b. The two-stage wellpoint
system used to dewater the core trench at Carlyle Dam,
Illinois, in the St. Louis district is shown in Figure 3-12.
(2) Failure of the dewatering system can result in
extremely serious problems, often requiring extensive and
expensive remedial work. In excavations bottoming in
impervious material, unchecked artesian pressure in underlying pervious strata can cause heaving of the excavation
3-11
EM 1110-2-1911
30 Sep 95
wet spots in the bottom of the excavation, even with deep
wells or wellpoint systems in operation. Water seeping into
the excavation from the upstream and downstream slopes of
a long cutoff trench can usually be captured by excavating
narrow longitudinal ditches or drainage trenches at the
intersection of the slopes and the bottom of the excavation
(see Figure 3-11b), or by forming such trenches with sandbags, with sumps located as necessary for pumping the
water out. If the bottom of the excavation will still not dry
out, smaller ditches can be cut through the problem areas
and sloped to drain to the side trenches.
(2) To keep the bottom of the cutoff trench dry while
placing backfill, the drainage ditch system can be filled with
gravel so that the system can continue to function even after
being covered with soil. These gravel-filled ditches should
constitute only a very small portion of the overall area being
drained to preclude the necessity of later grouting large
portions of the bottom of the cutoff trench containing gravel.
The surface of the gravel can be covered with a layer of
heavy felt paper, burlap, or plastic sheeting, or by a layer of
stiff concrete to prevent migration of fines from the fill
material. The ditches are blocked at the ends of the excavation by means of concrete plugs. Riser pipes are brought up
from each sump (low point in the ditch) with the result that
water can be pumped from one or more of the riser pipes as
necessary, with the remaining riser pipes serving as vent
pipes.
(3) After the backfill is brought to a height that will
counteract the hydraulic head, the gravel-filled ditches are
grouted. Cement grout is introduced under gravity through
one riser pipe with the vent pipes serving as an escape for
air and water in the gravel. When grout issues from the
vent pipes, the vent pipes are shut off and a slight pressure
is maintained in the system until the grout has set. After
grouting, normal fill placement operations are continued. If
only one sump is used in the drainage system, a vent pipe
will have to be installed at an appropriate location before
backfilling starts.
(4) Figures 3-14a and 3-14b show the drainage system
successfully used at Laurel Dam, Kentucky, to remove
localized flow cracks in the shale. The system provided a
dry foundation for impervious material. Figure 3-14a shows
a trench dug along a water-producing crack in the shale. A
perforated collector pipe was placed in the trench with a
vent hose and grout pipe attached. The collector pipe was
surrounded with stone and the remaining portion of the
trench filled with concrete. Water volume from various
collector pipes discharged into a collection box from which
a single pipe carried the water to a pump located in a 60-in.
corrugated metal pipe (CMP) sump (see Figure 3-14b). The
vent hoses, grout, pipes, and CMP were extended as the fill
was brought up. After 20 to 30 ft of embankment fill had
3-12
been placed, the collector pipes were grouted and the CMP
was filled with -3-in. stone and grouted.
(5) In many cases where a dewatering system is being
used, a 4- to 5-ft-high impervious blanket placed at the toe
of the slope will prevent the minor seepage flow that
otherwise might occur and will therefore provide a dry
bottom.
c. Surface erosion. Surface erosion may present
problems on slopes cut in silts, fine sands, and lean clays.
EM 1110-2-1911
30 Sep 95
Eroded material will wash down and fill in the excavation
below the slope. The slope itself will be left deeply scoured
and rutted, making it necessary for costly smoothing
operations to be performed before the fill can be placed
against it. Figure 3-15 shows surface erosion on an
unprotected excavation at Kaskaskia Dam, Illinois. The best
way to combat surface erosion of temporary excavation
slopes is to backfill as soon as possible, thus cutting down
on exposure time. This often cannot be done, however, and
it becomes necessary to take other measures. Grass cover
on the slopes is a good means of preventing surface erosion
if it can be readily established and if the slopes are to
remain open for a season or two. Other slope protection
measures such as rip-rap or asphaltic treatment are rarely
justified for construction slopes. Thus, it is necessary to
keep as much water off the slope as possible. Most slopes
can withstand rain falling directly on them with only minor
sloughing.
Perimeter ditches and/or dikes (see Figure 3-11b) at the top of the slope are needed to carry other
surface waters away from the excavation if surface waters
outside the excavation would otherwise run into it. Ditches
may be needed at several elevations along the excavation
slopes to catch surface waters, as shown in Figure 3-11b.
3-13
EM 1110-2-1911
30 Sep 95
Chapter 4
Borrow Areas and Quarries
Section I
Earth Fill
4-1. Excavation, Handling, and Hauling
Equipment
Over the past several decades, significant improvements in
earth-moving equipment have been made at an increasing
rate, and there is no indication that this trend will slow.
While the basic types of equipment have remained virtually
the same, speed, power, and capacity have continuously
increased. Some of the basic principles of the more
common units are discussed in the following paragraphs.
a. Excavation equipment.
(1) Power shovels, draglines, elevating graders, wheel
excavators, and scrapers. Excavation is usually accomplished with power shovels, draglines, scrapers, wheel
excavators, or side-delivery loaders. Each offers certain
advantages and has certain disadvantages; therefore, several
types are often used on the same job. Discussion of the
four major types of excavation units is given in Figures 4-1
through 4-3.
(2) Dredges. Dredging is sometimes employed to move
material from borrow areas to the damsite. Dredges are
particularly suitable for use when large quantities of material
are to be obtained from borrow areas submerged in rivers,
lakes, etc. The two basic types of dredges are the bucket
dredge and the hydraulic dredge.
(a) Bucket dredge. A limiting disadvantage of bucket
dredges is that the discharge is alongside the place of
excavation. They can best be used for localized dredging or
where the borrow area is located so that the material can be
economically transported by trucks or barges to the site.
There are three types of bucket dredges: grab dredges,
dipper dredges, and ladder dredges. The grab dredge is
essentially a grab bucket operated from a derrick mounted
on a flat-topped barge. The dipper dredge is simply a
power shovel operating from a barge. The ladder dredge
excavates with a continuous chain of buckets supported on
an inclined ladder. Bucket dredges have the advantage that
they can excavate in most any material. Dredging depths
greater than 100 ft are not uncommon for grab dredges.
Digging depths of the dipper dredge are limited by the
length of the boom (65 ft is about the maximum, although
greater lengths are available for special projects) while the
digging depth of the ladder dredge is limited by the length
Primary Use:
Advantages :
Disadvantages:
Capacities:
DRAG LINE
Primary Use :
Advantages :
Disadvantages:
Capacities:
EM 1110-2-1911
30 Sep 95
4-2
POWER SHOVEL
ELEVATING GRADER
Primary Use:
Advantages :
When the borrow areas are large with flat topography and uniform soil
conditions, side delivery loaders generally provide the most economical
and rapid means of excavation
Disadvantages:
Capacities:
WHEEL EXCAVATOR
4-3
Advantages:
Disadvantages:
Borrow areas must have reasonably flat and uniform topography; slow
travel speed to other areas; if unit breaks down, all borrow operations
cease
Capacities:
Face cut up to 10ft wide and 13ft deep; 1,750 nominal bank ydlhr
capacity
EM 1110-2-1911
30 Sep 95
Primary Use:
Primary Use :
Advantages :
Serve as both excavating and hauling units ; larger and faster units can
compete with trucks as hauling units; deposit borrow material in even
layers, sometimes eliminating use of additional spreading equipment;
borrow material is broken up when excavated, making compaction
easier.
Disadvantages :
Capacities:
Note : Self-propelled rubber-tired scrapers are rapid-moving type ; scrapers towed by slower moving crawler tractors may be preferred where better traction is needed in
the pit and the haul is relatively short.
EM 1110-2-1911
30 Sep 95
4-4
SCRAPER
EM 1110-2-1911
30 Sep 95
blending operations, water additions, etc. Transfer points
(where the material is transferred from one belt to another)
are usually required. Automatic facilities for loading trucks
at the terminal points can be easily provided, or sometimes
the material can be dumped directly from the belt onto the
embankment, spread with bulldozers or grader, and
compacted.
(3) Separation plants. Separation or screening plants
(Figure 4-5) are employed where it is desired to separate
different particle sizes of a granular material. Generally, the
purpose is to remove oversize rocks or cobbles to facilitate
compaction or to remove fines from filter material. There
are four principal types of screening plants:
(a) Horizontal or sloping stationary screens. With this
equipment, material is directed through a stack of stationary
screens/sieves with screen opening sizes decreasing toward
the bottom of the stack. Larger soil particles are retained on
the upper screens while smaller particles fall through to be
retained on a lower screen.
(b) Vibrating screens. This equipment is basically like
the stationary system described above except that soil
separation through the screens is facilitated and expedited by
vibrating the screens.
(c) Rotating trommels. This equipment consists of an
inclined rotating cylinder with screens or holes of different
sizes around the periphery. Separation is accomplished
when soil particles of different sizes fall through the appropriate hole size as the mixed material rolls around inside the
rotating cylinder.
(d) Wobblers (or rotating cams). In wobblers, rotating
cams produce vibrations which cause fines to fall through
4-5
EM 1110-2-1911
30 Sep 95
compaction. During excavation and processing, the inspector observes all adjustments made to the water content
of the material. If separation or blending is required, the
inspector performs tests to ensure that the soil type and/or
gradation of the processed material meets the specifications.
4-6
EM 1110-2-1911
30 Sep 95
material to absorb additional water. Excavating with power
shovels on a vertical face is an example of this strategy.
d. Blending soil layers with excavating equipment.
(1) Blending two or more soil types may be required
where different soil strata are present in borrow areas or
required excavation. Reasons for blending soils are to
obtain borrow materials having acceptable characteristics for
a particular embankment zone and to utilize borrow
materials so stratified in situ that it would not be feasible to
load and place material from individual soil strata.
(2) Where materials to be blended occur as horizontal
strata, shovels, draglines, wheel excavators, or in some
cases, scrapers have been used to blend them during
excavation. Excavation with a power shovel on a vertical
cut will blend the materials. Where more extensive mixing
is required, it can be achieved by running the open bucket
through the mixture several times before loading. Construction control in this case will require maintaining the
height of cut necessary to obtain the desired proportions of
each type of material and to ensure that the materials are
blended thoroughly.
(3) Blending different materials from different sources
can be accomplished by stockpiling one layer on the other
so that excavation can be made through the two materials as
in a stratified natural deposit. However, this procedure is
expensive and is seldom used.
(4) Scrapers have been used to mix stratified deposits by
developing the excavation in such a way that the scraper is
loaded on an incline, cutting across several horizontal strata
of different materials; however, this procedure is generally
not as effective in mixing as the use of a shovel, dragline,
or wheel excavator.
e. Selection of materials intended for different embankment zones.
(1) The borrow pit inspector must assure that materials
intended for a certain embankment zone are within specification limits. Selection of materials will, to a large extent,
have been accomplished on the basis of design studies; that
is, borrow areas for the various zones will have been
designated. Design studies should have disclosed the nature
of the materials and the expected ranges of variation.
Therefore, field personnel should review the results of all
investigations and know what materials are acceptable; the
inspector must be able to identify these materials visually as
far as possible, and with a minimum of index tests.
(2) The use of proper equipment by the contractor will
EM 1110-2-1911
30 Sep 95
be kept at a minimum; the filter material stockpile should be
located well away from other types of material, the area
should be sloped so that water drains away from filter
stockpiles, and heavy equipment should not be operated over
filter materials. Gradation tests should be performed on
samples of filter material from a number of locations around
the stockpile before and after it is placed to ensure that
specifications have been met.
The
advantages of
maintaining stockpile quality should be well understood and
appreciated by site personnel, especially if many contractors
will use the stockpile.
h. Cold weather operations. Borrow area operations
can often continue into freezing weather without loss of
embankment fill quality. Frost penetration progresses slowly in undisturbed (in situ) fine-grained soils except in
extremely cold weather, and soils will generally remain
unfrozen if borrow operations are conducted continuously.
Material satisfactory for fill placement can be obtained if the
in situ water contents do not require adjustment on the fill.
Sands and gravel can generally be excavated and handled
effectively under very low temperatures, but the addition of
water on the fill for compaction may present problems.
Borrow excavation in cold weather is usually limited by fill
placement requirements; it should be limited to use only in
special situations and should be practiced with considerable
caution.
Section II
Quarries and Rock Excavation
4-3.
General
Equipment
a. Loading.
(1) Power shovels and front-end loaders are used almost
exclusively today for loading trucks or other vehicles in
rock excavations or quarries. Power shovels have been used
for many years; large front-end loaders have recently come
into prominence with the advent of more powerful units
4-8
EM 1110-2-1911
30 Sep 95
processing plants, each with its own advantages and disadvantages; the use and end product desired will dictate the
choice of plant. Some of the more common plants are
briefly discussed below.
(1) Grizzlies. The grizzly is perhaps the most common
separating device; it is used only for removing oversize rock
from the material which, in some cases, is all that is needed
to obtain the gradation specified. A grizzly consists of a
sloped grate made of heavy bars which are wider at the top
than at the bottom to ensure that particles do not bind
partway through the gratings and clog the openings between
the bars. Grizzlies are often constructed with sloped vibrating screens or with rotating cams (grizzly wobblers) so that
oversize material passes over the grate and falls off the end
while the desired material falls through the grate. Grizzlies
may be constructed in many ways, but they always involve
the use of a grate or lattice of heavy bars. Figure 4-6 shows
a sloping grizzly in operation at Gathright Dam, Virginia.
A grizzly wobbler used at Stockton Lake Dam, Missouri, is
shown in Figure 4-7.
(2) Trommel. A trommel is a separating device which
consists of a rotating cylinder of perforated sheet metal or
wire screen. Like the grizzly, it is used for eliminating
oversize particles, but it can also separate the remaining
material into various size fractions. A trommel can be open
at either one end or both ends with the axis of the cylinder
horizontal or slightly inclined so that the material is
advanced by rotation of the cylinder. Size of the perforations in the sheet metal or of the openings in the screen
can be varied to obtain more than one size fraction. As
material is fed into the rotating cylinder, the oversize
material passes through and is discharged at the other end,
while each of the fractional sizes falls through a properly
Test Quarries
4-9
EM 1110-2-1911
30 Sep 95
quarry in operation at Foster Dam, Oregon, is shown in
Figure 4-8.
4-10
EM 1110-2-1911
30 Sep 95
required will depend on the results of the blasting unless
special processing is expressly called for in the specifications. Different types of separation equipment and their
utilization have been described above.
in them. All slopes should be scales and trimmed to eliminate the probability of falling rocks and debris. All areas
that can support vegetation should be seeded. In some
cases, fencing may be needed to restrict free access.
Section III
Final Condition of Borrow Areas, Quarries, and Spoil Areas
4-9.
4-7.
Borrow Areas
Quarries
4-11
EM 1110-2-1911
30 Sep 95
Chapter 5
Earth-Fill and Rock-Fill Construction
Section II
Test Fills
5-4.
Section I
Fill Processing and Compaction Equipment
5-1.
5-1
EM 1110-2-1911
30 Sep 95
TAMPING ROLLER (SHEEPSFOOT)
Specifications:
Towed:
Double-drum unit:
Water or sand and water ballasted. Towed by crawler or rubber-tired tractor at not more than
5 mph.
Drum:
Weight:
Weighted: at least 4,000 lb/ft of drum length. Empty: not more than 2,500 lb/ft of drum length.
Feet:
Uniformly spaced. Approximately three feet per each 2 sq ft of drum surface. Foot length: 9
to 11 in. Face area: 7 to 10 sq in.
Cleaning fingers:
Self-propelled:
Use:
Advantages:
Kneading, churning, and tamping action mixes soil and water better than other compaction
equipment (this does not preclude proper processing of material prior to compaction, however);
produces good bond between lifts; and breaks down weak rock or cemented soils.
Disadvantages:
Leaves surface rough and loose, and therefore susceptible to wetting by rains or surface
waters. Compacts to shallower depth than other equipment. Effectiveness diminished in
compacting soils containing cobbles or large rock fragments. Self-propelled rollers sometimes
cause shearing of or laminations in fill.
5-2
EM 1110-2-1911
30 Sep 95
RUBBER-TIRED ROLLER
Specifications:
Unit with pneumatic-tired wheels towed at speeds not exceeding 5 mph.
Wheels:
Minimum of 4 wheels abreast, each carrying equal load in traversing uneven surfaces.
Wheel spacing:
Distance between nearest edges of adjacent tires not to exceed one-half of tire width under
25,000-lb wheel load. Tire pressure 80 to 100 psi.
Weight:
Use:
Advantages:
Compacts to greater depths than sheepsfoot roller. Produces relatively smooth compacted
surface which is rain-resistant. Effective in compacting in closer quarters than sheepsfoot (i.e.,
against rock abutments and concrete structures). More effective than sheepsfoot in
compacting cohesive soils containing large particle sizes. Wet areas of fill can be determined
by observation of roller rutting.
Disadvantages:
Compacted surfaces must be scarified before placing next lift. Not as effective as sheepsfoot
roller in breaking down soft rock or in mixing fill material.
5-3
EM 1110-2-1911
30 Sep 95
VIBRATORY STEEL-WHEEL ROLLER
Specifications:
Single drum unit. Towed by crawler tractor with minimum drawbar horsepower of 50 at speed not to exceed 1.5 mph (when
compacting rock fill or sands and gravels), or self-propelled at speed not to exceed 1.5 mph (when compacting sands and
gravels only).
Weight:
Minimum total weight, 20,000 lb; 90 percent transmitted to ground by smooth drum with roller
in level position attached to towing vehicle. Unsprung weight of drum shaft and internal
mechanism not less than 12,000 lb. (Note: while guide specification CW 02212 specifies a
roller with a minimum static weight of 20,000 lb, lighter rollers (7,000 to 10,000 lb) have been
effectively used to compact pervious sand and/or gravel, and to compact soft rock that would
be broken down too much by heavier rollers.)
Vibration:
Frequency: between 1,100 and 1,500 vpm. Dynamic force: not less than 40,000 lb at
1,400 vpm.
Use:
Advantages:
Greater densities can be obtained in cohesionless soils than with tamping or rubber-tired
equipment. Fill may be flooded with water to improve compaction.
Disadvantages:
May cause degradation of soil or rock-fill particles and create layers of fines.
5-4
EM 1110-2-1911
30 Sep 95
Definitions
Impervious materials include clays of high and low plasticity (CH and CL), clayey sand or gravel (SC and GC), and
5-5
EM 1110-2-1911
30 Sep 95
the laboratory by compacting five or more specimens of a
soil at different water contents using a test procedure which
utilizes a standard amount of energy called standard
compactive effort. A detailed description of the laboratory
compaction procedure to establish maximum dry density and
optimum water content is contained in EM 1110-2-1906.
b. In the field as in the laboratory, the two variables
that control fill density are placement water content and
field compactive effort applied by the passage of a piece of
equipment a certain number of times over a lift of a specific
thickness. When the water content of a soil being compacted with a certain compactive effort deviates from the
optimum water content for that effort, a dry density less
than maximum will result; the greater the water content
deviation from optimum, the lower the resulting density will
be. For soil with a water content on the dry side of
optimum or at optimum, an increase in compactive effort
will generally increase the density. For soil with water
content considerably greater than optimum, an increase in
compactive effort will tend to shear the soil but not further
compact it.
c. Compactive effort can be increased by increasing
contact pressure of the roller on the soil, increasing the
number of passes, or decreasing the lift thickness. Combinations of these procedures to increase and control
compaction on a job will depend on difficulty of compaction, degree of compaction required, and economic factors.
Figure 5-6. Test fill data from Canyon Dam, Texas
Compaction Fundamentals
5-6
5-8.
Compaction Specifications
EM 1110-2-1911
30 Sep 95
c. Uncompacted or loose lift thickness will be specified.
Lift thickness specified will be based on type of material
and compacting equipment used. Impervious or semipervious materials are commonly placed in 6-to-8-in. loose
lift thicknesses and compacted with six to eight passes of a
sheepsfoot roller or in 9-to-12-in. loose lift thicknesses and
compacted with four coverages or a 50-ton rubber-tired
roller. When using a rubber-tired roller or any roller that
leaves a smooth surface after compaction, scarification of
the compacted lift prior to placing the next lift is specified
to ensure a good bond between the lifts. In confined areas
where hand-operated power tampers must be used, fill is
commonly place in 4-in. loose lifts and compacted to
densities achieved with sheepsfoot or pneumatic-tired
equipment under the above-mentioned conditions.
d. In-place water content and density must be related to
optimum water content and to maximum dry density to
judge whether a compacted soil is suitable or unsuitable.
Minimum acceptable field density is normally established in
design as a percent (usually 95 or above) of maximum dry
density1, and an allowable range of placement water
contents is given in the specifications relative to optimum
water content of the soil being compacted. Each soil type
has a different maximum dry density and optimum water
content for a given compactive effort, and it is necessary
that in-place field densities and water contents be compared
with laboratory-determined optimum water contents and
maximum densities of the same soil. Because mixing
different soil strata in borrow areas can result in materials
with unexpected compaction characteristics, if a material
being compacted in the field cannot be related to available
laboratory compaction data, a laboratory compaction test
should be performed on that material. Check companion
tests should be performed by field personnel before fill
placement to ensure consistency with target values for a
given soil.
e. Assumptions are made in design regarding shear
strength, permeability, and deformation characteristics of the
embankment fill. These properties vary with density and
water content of the compacted soil. Therefore, soil must
be placed as specified; otherwise, design assumptions are
not met and problems may occur in the completed structure.
Thus, desired density and placement water content range are
not arbitrarily established but are specified for very definite
reasons, and both requirements must be satisfied. If the
water content is outside its specified range, even though the
desired density is obtained, the soil must be reworked and
When the compaction procedures are set forth in the specifications, the
percentage of maximum dry density is not specified, but the desired value
is given to field inspection forces by the design office.
5-7
EM 1110-2-1911
30 Sep 95
spade. Many inspectors, in fact, have had success in
judging density by noticing the resistance of the compacted
soil to penetration by a spade.
e. Proper lift thickness is fairly easy to estimate when
the inspectors judgement has been calibrated by actual
thickness measurements. However, many contractors are
interested in placing lifts as thick as they can get by with,
and conflict often arises on this point. Therefore, control of
lift thickness by visual observation alone is not sufficient
and must be supplemented with measurements. Contractor
behavior dictates the level of force that must be exercised to
maintain proper lift thicknesses. As a minimum practice by
the inspector, it is necessary to make measurements on the
same point on the construction surface after every few
layers.
f. Much useful information can be gained by observing
the action of compacting and heavy hauling equipment on
the construction surface. If the water content of the fill
material is uniform and the lift thickness is not too great,
the action of the roller will indicate whether water content
of the material is satisfactory and good compaction is being
obtained. For example, it is likely that soil-water content is
too high if on the first pass of a rubber-tired roller the tires
sink to a depth greater than or equal to half the tire width,
after several passes, excessive rutting of the soil surface is
observed, the surface ahead of the roller shows signs of
weaving or undulating (as opposed to springing). It
should be noted that the characteristics just described may
sometimes be caused by tire pressure which is too high, but
in most instances they are caused by water content which is
too great. On the other hand, if the roller tracks only vary
slightly or not at all and leave the surface hard and stiff
after several passes, the soil is probably too dry. For most
soils with the proper water content, the roller will track
nicely on the first pass and wheels will embed 3 to 4 in.;
there should always be some penetration into soil at its
proper water content, although penetration will decrease as
the number of passes increases. After several passes of a
sheepsfoot roller, the roller should start walking out of the
fill if adequate and efficient compaction is being obtained.
Walking out means that the roller begins bearing on the soil
through its feet with the drum riding a few inches above the
soil surface. If the roller walks out after only a few passes,
the soil is likely too dry. If the roller does not walk out but
continues churning up the material after the desired number
of passes, either the soil is too wet or foot contact pressure
is too high.
Another significant observation during
compaction by sheepsfoot roller is whether or not the feet
are coming out clean. Soil is generally too wet when large
amounts of material are being picked up by the feet and
knocked off by the cleaning teeth. If soil is at the proper
water content, only a small amount of sticking should occur.
5-8
EM 1110-2-1911
30 Sep 95
ensure that proper construction is attained in this important
area. The locations of record samples should be at the
discretion of the design engineer and should also be stated
on a predetermined plan of testing. A rough guide for
taking record samples is one for every 30,000 cu yd of core
fill and every 30,000 to 50,000 cu yd of compacted material
outside the core. Since the record samples are taken primarily to determine the shear strength of the fill, it may be
more important in many dams to concentrate more tests in
the material outside the core because this is where a major
portion of the resistance to sliding is developed. For dams
with narrow central plastic clay cores placed wet of
optimum water content for impermeability and flexibility,
flanked by large lean clay zones, record samples should be
taken mainly in the clay shells.
(3) In addition to routine control tests, tests should be
made in the following areas: where the inspector has reason
to doubt the adequacy of the compaction, where the
contractor is concentrating fill operations over relatively
small areas, where special compaction procedures are being
used (power tampers in confined areas, etc.), where
instruments are located, and adjacent to abutments.
c. Record samples. Undisturbed record samples may be
obtained by carefully carving out about a cubic foot block
of the compacted fill. The sample is then sealed in wax and
encased in a wooden box or protected by other methods of
packaging against disturbance or water loss. Undisturbed
record samples are also taken by trimming around a large
steel cylinder as it is pushed into the fill (e.g., the Fort
Worth district has used a sampler 7-1/2 in. in diam by 10 in.
high). Details for obtaining and preserving record samples
are described in EM 1110-2-1907. Undisturbed record
samples are subjected to shear and perhaps consolidation
testing by the division laboratory, and the material from
trimmings and unused portions of the record samples or of
the companion bag samples are used for laboratory
compaction, gradation, specific gravity, Atterberg limits, and
other laboratory tests. Undisturbed record samples and bag
samples must be tested promptly if the results are to be
useful in construction control.
d. Field density tests. Field density determination
consists of volume and weight measurements to determine
wet density of in-place fill and water content measurement
to determine fill water content and dry density. Volume and
weight measurement can be determined by direct or indirect
methods. In direct measurements, weight of the material
removed from a hole in the fill and hole volume are used to
determine wet density. Direct water content determination
involves drying the soil in an oven at 110 5 C, then
weighing the dry soil to determine water loss. Determining
density and water content by indirect methods involves
5-9
EM 1110-2-1911
30 Sep 95
2-1906. The hot plate method utilizes a small tin pan and
a hot plate, oil burner, gas burner, or some other device to
apply high temperature quickly; the test is performed by
weighing a sample of wet soil, drying the soil on a tin pan
over high heat, and weighing again to determine how much
water was lost. Hot plate drying is fast but can result in
inaccuracy in water content because high uncontrolled
temperature applied to the soil can drive off adsorbed water
and burn or drive off volatile organic matter, neither of
which should be removed in a normal water content test. In
5-10
(c) Microwave oven. A Computer Controlled Microwave Oven System (CCMOS) has been developed at WES
and demonstrated to be an acceptable and useful piece of
equipment for rapid determination of water content for
compaction control. The principal of operation of the
system is that water content specimens are weighed
continuously while being heated by microwave energy; a
small computer monitors change in water content with time
and terminates drying when all free water has been
removed. CCMOS is essentially automatic; after the
operator has placed a specimen in the oven system, the
controlling computer performs all required tasks (including
calculations) through software, and returns the final water
content with no additional input required from the operator.
A water content test in the CCMOS typically requires 10 to
EM 1110-2-1911
30 Sep 95
15 min; the system has been field-tested at the Yatesville
Lake and Gallipolis Lock projects in the Ohio River
division. At the projects, companion tests were performed
in a conventional oven at 110 5 C and in CCMOS. Data
returned from the projects are shown in Figure 5-9;
statistical analysis of the data shows that CCMOS produces
water contents that are within 0.5 percent of the conventional oven water content. Special procedures must be used
when drying materials which burst from internal steam
pressure during microwave drying (which includes some
gravel particles and shales) and highly organic material,
which requires a special drying cycle. CCMOS will not
produce correct water contents in soils with high gypsum
content; therefore, no attempt should be made to use the
system to dry such materials. (However, it must be noted
that a special drying procedure is required to dry gypsum
rich soils in the conventional constant temperature oven).
CCMOS and its operation and use are described by Gilbert
(1990).
Components of the system are shown in
Figure 5-10.
(d) Pressure tester methods. The pressure tester method
for water content determination involves combining moist
soil in a sealed chamber with calcium carbide (these react
with water in the soil to release gas) and relating the
resulting gas pressure to soil water content. Accuracy can
be a problem when using this technique since soils and
especially fine grained clays bind and hold water at different
energy levels. Consequently, there is no assurance that
calcium carbide will react correctly with bound or adsorbed
water; calibration tests must be performed to correlate
pressure tester water content with conventional oven water
5-11
EM 1110-2-1911
30 Sep 95
careful calibration using soils of known density and water
content and considerable operating experience. Even then
the results may be questionable due to the significant
influence of nonuniform water content or variation due to
the influence a small piece of gravel can have on the
penetration resistance.
The Proctor penetrometer is,
therefore, not recommended for general use in compaction
control; it can be a very useful tool in supplementing the
inspectors visual observations and providing a general
guide for detecting areas of doubtful compaction. The
procedure for determining the relation between wet unit
weight, penetration resistance, and water content is
described in the ASTM Standards, Designation D 1558-63.
5-12
EM 1110-2-1911
30 Sep 95
5-13
EM 1110-2-1911
30 Sep 95
5-14
Reclamation
(USBR)
rapid
EM 1110-2-1911
30 Sep 95
rapid method, a wet density compaction curve is developed
from three wet density compaction points, and the percent
of maximum dry density and deviation from optimum water
content are computed without having to perform water
content tests. The visual method consists of establishing by
visual examination that the field density material is the same
as one of the materials on which laboratory compaction
curves were developed. It is a frequently used method, but
is the least desirable because materials that look very much
alike and have the same soil classification can have widely
varying compaction characteristics.
g. Procedures for gravelly soils. Results of the fivepoint, two-point, one-point, and visual methods are usually
correlated directly with field density test results if
appropriately sized compaction molds are used (see
EM 1110-2-1906). However, the Atterberg limits correlations and USBR rapid methods are based on the minus
No. 4 sieve fraction; consequently, the field density test
results must be corrected to obtain the water content and
density of the minus No. 4 fraction. Corrections must also
be applied to the field results if the laboratory compaction
curve is based on a scalped material (corrections would not
be made if particles larger than 2 in. are replaced with an
equal weight of particles from 2 in. to the No. 4 sieve and
tested in the laboratory in a 12-in. compaction mold). The
equations necessary to make these corrections and procedures for applying them are given in Appendix B.
h. Evaluation of test results and subsequent actions to
be taken. As soon as field test results are obtained, they
must be compared to appropriate values of maximum dry
density and optimum water content to determine if specification requirements have been met. If measured values
match or exceed specification requirements, the next lift can
be added. If test results show that specifications have not
been met, corrective measures must be taken immediately.
A lift must be rejected if the material is too wet or too dry.
If density is too low but water content is acceptable, additional rolling is all that is required. If, however, water
content is outside specifications, the entire lift should be
reworked and rerolled. A lift that is too wet should be
worked by disking until the water content is lowered to an
acceptable value and then recompacted. A lift that is too
dry should be disked, sprinkled, and redisked until the
additional water is uniformly distributed, then recompacted.
It is important when reworking a rejected lift that the full
lift depth be reworked, not just the upper portion. All
reworked lifts should be retested for density and water
content. It is desirable to determine the reason(s) for an
unsatisfactory lift in either borrow or fill operations, so that
conditions causing the problem may be corrected on future
lifts.
5-15
EM 1110-2-1911
30 Sep 95
successfully between rains. Water content of material
spread on embankments can be reduced somewhat during
periods between rains by plowing or disking before rolling.
(2) It is desirable to compact fill material as soon as
possible after spreading to minimize the time loose fill is
exposed to precipitation. Rubber-tired rollers are superior
to sheepsfoot rollers when rains are frequent because they
leave a relatively smooth compacted surface, whereas the
sheepsfoot roller leaves a loose rough surface that readily
soaks up rain water. If a sheepsfoot roller is used for
general compaction, smooth-wheel rollers (steel or rubber)
can be employed to seal the surface when rain is imminent.
In any event, the construction surface should be kept sloped
to allow the water to run off instead of standing in puddles
and soaking in. After a rain, if some ponding does occur,
it is usually easy for the contractor to install a few small
ditches to drain these areas.
(3) It is often necessary after a rain to scarify and work
the construction surface to a depth below that of excessive
moisture penetration until it is dried to a satisfactory water
content or, to remove and waste all affected material. If
procedures to facilitate runoff are followed (sloping the
surface, sealing the surface with smooth rollers, etc.), the
depth of moisture penetration will be kept to a minimum.
c. Dry weather.
(1) If material being dumped on the fill is too dry for
proper compaction, water must be added by sprinkling after
it is spread and before it is rolled. The amount of water
added and the blending required will depend on grain size
and plasticity of the soil, fine-grained soils of high plasticity
requiring the greatest amount of blending. Soil must be
worked with disks to thoroughly blend and homogenize
added water into the soil. The importance of uniform
moisture distribution cannot be overemphasized; if pockets
of wet and dry soil are allowed in uncompacted material,
very poor compaction will result.
(2) Sprinkling the soil can be accomplished by hosing
from a pipeline, located along either the embankment toe or
the crest, or by the use of water trucks. The latter method
is the most effective and the most commonly used today.
Pressure sprinkling systems on trucks are superior to gravity
systems and should be employed if at all possible. Water
sprays must not be directed on the soil with such force as to
cause fines to be washed out. Until the inspectors and
contractor personnel have gained a feel for the amount of
water needed, rough computations of the number of gallons
to add for a given area should be made, and water applied
accordingly. After a few trials, a feel for the proper amount
will develop. The coarser and less plastic the soil, the more
easily water can be added and worked uniformly into it. It
5-16
EM 1110-2-1911
30 Sep 95
sieve.1 Standard impact compaction tests on such materials
do not yield well-defined values of optimum water content
and maximum dry density, and field densities are related to
maximum and minimum density determinations made
according to the relative density procedures in EM 11102-1906 rather than to maximum dry density as determined
in the standard compaction test.
5-14. Compaction Equipment
inspector should carefully check to ensure that the manufacturers recommended air pressure is being developed.
Experience has shown two-by-four wood rammers, or
single-foot compressed air tampers (commonly referred to
as powder puffs or pogo sticks) do not produce
adequate compaction. It is important that zones of hand
compaction and compaction by heavy equipment overlap so
that no uncompacted material exists between them.
b. Where impervious material is to be placed adjacent
to abutments or concrete structures, it should be as finegrained as practicable. Soil must be plastic enough to
penetrate all irregularities in the abutments and to form a
well bonded seal.
c. Close compaction control must be exercised in these
areas since they are generally more critical with respect to
seepage and damaging settlements causing cracking and
piping than the main embankment. A special sampling
program should be established, and an inspector must watch
operations involving the use of power tampers at all times.
Section IV
Pervious Fill
5-13. Definition
Pervious fill material as used in this manual is defined as
free-draining cohesionless sand and/or gravel, containing
less than approximately 5 percent passing the No. 200
5-17
EM 1110-2-1911
30 Sep 95
EM 1110-2-1911
30 Sep 95
5-18. Density Requirements
Compaction equipment and procedures are normally specified without field densities being specified. The expectation
is that the prescribed field compaction methods will produce
the desired densities. If these are not achieved in the field,
then the contractor is paid for additional rolling. Requirements established by the Office of Chief of Engineers are
that the average in-place relative density of pervious fill
zones should be at least 85 percent and that no portion of
the fill should have a relative density less than 80 percent.
5-19. Construction Control
a. Simple control procedures.
(1) Checking lift thicknesses of pervious fill can be
accomplished by the simple procedures described for
impervious and semipervious materials, except that in using
a shovel or rod it is often difficult to determine when the
top of the underlying compacted layer is reached. This
procedure is also not practical in fills containing large gravel
particles. In some cases, it is possible to excavate a small
hole in the loose material to the top of the underlying layer,
which is identified by a relatively higher resistance to
digging.
(2) The inspector must make certain that the
embankment is always graded so that surface waters will not
wash fines from impervious or semipervious fill materials
into the pervious fill. During construction of earth dams,
placement of filter materials for drainage layers should be
kept higher than adjacent fill containing fines in order to
prevent spillage of fine-grained soil onto the pervious
material or to reduce the washing of fine-grained soils into
the materials by surface runoff. The inspector should be
trained to recognize the appearance of pervious material
meeting specifications so that he can more easily detect,
without the delay of testing, the presence of excess fines.
A good indication of excessive fines is when the hauling
and compacting equipment sinks in and causes ruts in the
fill surface. This usually indicates that water applied during
compaction is not draining through the material as it should
because of clogging by excess fines.
(3) In general, a vibratory roller should push only a
small amount of material ahead of it and leave a smooth
surface behind on the first pass. If the roller sinks in and
pushes a large amount of material in front of it, either the
frequency of vibration is not correct for the particular soil
being compacted or the material contains too many fines.
(4) It is more difficult to judge the compacted density of
pervious material than that of fine-grained material.
testing
and
relative
density
5-19
EM 1110-2-1911
30 Sep 95
free-draining pervious fills and filter materials cannot be
related to standard impact compaction test results since
water content/density relations are not valid for such
materials, as they are for materials having varying degrees
of plasticity. Field densities must be expressed in terms of
maximum-minimum densities as determined by laboratory
tests described in EM 1110-2-1906. Field densities are
expressed in terms of their relation to these laboratory
values, i.e., in terms of relative density. The percent
relative density, Dd, of the in-place material can be
computed by the equation:
Dd
d
max
min
min
max
d
100
where
d = dry unit weight of the pervious fill in place (the inplace density), pcf
min = minimum density, pcf, from laboratory tests
max = maximum density, pcf, from laboratory tests
(2) Field density determinations using the water balloon
or sand volume procedures should be made for every
1,000 cu yd of pervious fill placed at the beginning of the
job and for every 3,000 cu yd thereafter, with more frequent
determinations desirable for testing in drainage layers.
These tests generally should be taken one lift thickness
deep, especially in sands. Although the performance of
maximum and minimum density determinations on material
from each field density test would give the most accurate
determination of the relative density of the in-place material,
this is frequently not feasible because of time and manpower
restrictions. Therefore, it is often advisable to attempt to
develop correlations between the gradation data and the
maximum-minimum density values on materials representing
the range of gradations to be expected from the sources of
supply. Figure 5-15 is an example of a correlation between
the percent finer than the No. 16 sieve and the maximumminimum density values. Where a good correlation like this
is developed, a simple determination of the percent finer
than the No. 16 sieve is all that is needed to obtain the
appropriate maximum-minimum density values in the inplace material. In other instances, good correlations may be
developed between maximum-minimum density values and
the percent of material passing other sieve sizes or the
coefficient of uniformity. Correlations developed between
minimum and maximum density values can be used to
obtain minimum density after the performance of a
maximum density test alone. Caution should be exercised
in using such correlations for uniform sands, since the
5-20
EM 1110-2-1911
30 Sep 95
Section V
Rock Fill
5-21. General
a. Embankments with large rock-fill zones are
becoming more common. This is primarily due to the
necessity of using sites where rock foundation conditions are
unsuitable for concrete dams, the suitability of modern
construction equipment to handle rock, the increasingly
higher dams being constructed, and the economic benefit
obtained by the maximum use of rock from required
excavation.
b. Rock for construction purposes falls into two
categories, soft rock and hard rock. Soft rocks such as
shales, mudstones, siltstones, claystones, chalk, earthy
limestones, weakly cemented sandstones, and badly
weathered igneous and metamorphic rocks break down in
varying degrees during compaction, some into tight compact
masses similar to impervious soils. Soft rocks are generally
susceptible to further softening by exposure to air and water.
Conversely, hard rocks do not readily break down during
handling and compaction, and their use results in a pervious
to very pervious fill depending on the amount of fines
present.
c. There are no well-established criteria for construction
methods best suited to either type of rock. The breakdown
of most types of rock is very unpredictable, and this fact has
led to the widespread use of test quarries and test fills for
large rock-fill dams.
5-22. Hard Rock
a. Specifications. The specifications for pervious rockfill sections generally require that the rock be sound, well
graded, and free draining. Gradation is not usually
specified, but the maximum permissible size is normally
specified together with lift thickness. Rock fill is usually
required to be placed by dumping from trucks, with
bulldozers spreading the material to the desired lift
thickness. The required placement and spreading operations
should be that segregation of rock sizes is avoided. This is
discussed in more detail in the following paragraphs. The
type of roller, lift thickness, and number of passes will be
specified, preferably based on results of test fills.
b. Placement operations.
(1) When rock is dumped on the fill surface and pushed
into place by a bulldozer, the fines are moved into the upper
part of the lift, thereby creating a smoother working surface
5-21
EM 1110-2-1911
30 Sep 95
5-23. Soft Rock
a. The use of soft rocks in the past has been dictated by
their availability in large quantities from required
excavations. The main concern about these materials is
their tendency to weather and soften with time when
exposed to air and water. However, cases in which large
portions of embankments were composed of soft rocks have
shown that they can be used satisfactorily in random and
semipervious zones, attaining adequate shear strength and
experiencing no appreciable softening after placement.
Where soft rocks will constitute a significant structural
portion of a fill, their properties and the best methods of
compaction should be determined by means of a test
embankment constructed during the design studies.
b. Some types of soft rock have been compacted by
first rolling over the loose lift with a heavy tamping roller
equipped with long spike or chisel-type teeth (shell
breaker), and then compacting the lift with conventional
tamping or rubber-tired rollers. A summary of this
technique is given by Bennett (1958).
Section VI
Semicompacted Earth Fills
5-24. Uses
Spoil berms, channel fillings, and low levees to protect
farmlands are often constructed of semicompacted fills.
5-25. Specifications
Semicompacted fills are those specified to be compacted by
the routing of hauling and spreading equipment over the
spread layer. Lift thickness is specified, but the range of
placement water contents is either not specified or permitted
to vary widely.
5-26. Construction Control
Inspection of semicompacted fill is usually entirely visual,
although a few density tests may be made for record
purposes. The primary concern of the inspector is to ensure
that the specified lift thickness is not exceeded, suitable
materials are being used, and hauling and spreading
equipment covers the fill uniformly.
Section VII
Sequence of Placement and Measurement of Quantities
5-27. Schedule of Construction
The schedule for construction of an earth or rock-fill dam
5-22
EM 1110-2-1911
30 Sep 95
5-29. Measurement of Quantities
Measurement of excavated materials is usually based on
cross-section surveys of the area before and after
excavation, using the average end area method for
computing quantities. For embankment fill, a cross-section
survey of the outer boundaries and average end area method
are used in computing quantities. For separate zones within
an embankment, the theoretical quantities are computed
from the lines and grades shown in the construction
drawings. Inspection personnel should be completely
familiar with provisions of the specifications and lines and
grades shown on construction drawings so that instances of
overexcavation or fill placement outside contract lines and
grades are recorded. This will assist in preventing possible
errors in measurement and certification of payment for
quantities in excess of contract provisions.
Section VIII
Slope Protection
5-30. Areas to be Protected
Slope protection is required to protect upstream slopes
against damage from wave erosion, weathering, ice damage,
and damage from floating debris. Upstream slope protection
of earth dams usually consists of riprap, although soil
cement, concrete paving, and asphalt paving have been
occasionally used when riprap was not economically
justified. Dams with outer shells of sound, durable, large
rock may not require further protection. Downstream slope
protection is required to protect against damage from surface
erosion by wind and rain. Downstream slope protection
includes gravel for dry climates, turf in humid climates,
riprap where tailwater may create wave action, and waste
rock. Proper field construction procedures and enforcement
of specifications are particularly important in obtaining slope
protection that will remain in place and in minimizing
maintenance during the life of the dam.
5-31. Upstream Slope Protection
Placement of upstream slope protection may be accomplished either as the embankment is being built or after the
embankment is completed. This depends on the elevation
limits of slope protection, the schedule for impounding
reservoir water, and the type of slope protection. The best
procedure is to require that the slope protection construction
not lag behind earth-fill construction more than 10 ft in
elevation.
a. Riprap. Riprap is the most commonly specified type
of upstream slope protection. Properly graded riprap, placed
to provide a well-integrated mass with minimum void spaces
5-23
EM 1110-2-1911
30 Sep 95
stable base for riprap. Placement is shown in Figure 5-16c.
Many riprap failures have occurred because the bedding
material was not large enough to preclude being washed out
by wave action through interstices of the riprap. Removal
of the bedding causes settling and dislodging of overlying
riprap, further exposing bedding and embankment material
to direct wave action. It is, therefore, necessary that
bedding material meet specifications relating to gradation
and layer thickness. It is good practice to place rock spalls
or crushed stones of like size between the bedding and
riprap if they are available from quarry or required
excavation. The term spalls refers to the finer materials
resulting from rock excavation for materials such as riprap.
Spalls must be durable fragments of rock, free of clay, silt,
sand, or other debris. The gradation of spalls will vary and
must be specified for each particular job. The use and
minimum and maximum size of spalls or equivalent crushed
stone should be established in the design memo and should
be specified if it is appropriate. In some cases, spalls may
replace graded bedding material.
5-24
EM 1110-2-1911
30 Sep 95
asphalt paving are other methods of protection for upstream
slopes. These methods have been used infrequently, if at
all, for Corps of Engineers dams in the past.
5-32. Downstream Slope Protection
a. Grass turf. Grass turf for protection of downstream
slopes is usually specified in humid climates for earth
embankments. Where the downstream embankment zone is
composed of pervious material, sufficient fine-grained soil
or topsoil must be placed to support vegetation growth. The
method usually specified consists of clearing the slope of
any roots and stones, tilling to a depth of at least 4 in.,
fertilizing, seeding or sprigging, compacting, watering, and
maintaining as required to establish the turf. Temporary or
permanent protection should be established on completed
portions of the embankment as soon as possible. The usual
practice of waiting until near the end of construction and
trimming slopes by filling erosion channels with loose
material and then fertilizing and seeding has resulted in
continuing maintenance problems at several projects.
Specifications usually provide detailed instructions with
which inspection personnel should be familiar. Frequent
inspection should be made to ensure the following:
(1) That the soil is properly tilled and not allowed to
migrate down the slope during tilling, which might create
depressions or undulations.
5-25
EM 1110-2-1911
30 Sep 95
Chapter 6
Miscellaneous Construction Features
6-1.
River Diversion
6-1
EM 1110-2-1911
30 Sep 95
significant delays would occur from a failure. Compaction
procedures as well as other pertinent construction aspects,
including construction and surveillance requirements, would
be covered in the contract plans and specifications. Inspection and control testing, as outlined in Chapter 5, are
required especially for cofferdams which will become part
of the dam to ensure compliance with specifications or to
determine when specified procedures need to be modified.
The safety of cofferdams depends to a large extent on
competent construction. Intensive inspection is required to
ensure compliance with design requirements and safe
construction practices. A contract requirement for quality
control by the contractor does not relieve resident inspection
forces from performing necessary and adequate inspection
and surveillance.
(b) Slopes of temporary cofferdams depend on the type
of material used, degree of compaction, and their height.
Cofferdams are often designed on the basis of past experience. If the contractor is permitted to design a cofferdam,
it should be required that an analysis of slope stability with
plans for construction be furnished. Slopes of cofferdams
designed by the Government are specified in the contract
drawings.
(c) Seepage under cofferdams and through uncompacted
rock-fill cofferdams can be a serious problem unless seepage
control provisions such as a cutoff and/or an upstream
impervious zone are included. For cofferdams designed by
the Government the plans provide necessary measures for
controlling underseepage and through-seepage. However,
particular attention should be given to any contractors plans
for temporary cofferdams to ensure that adequate seepage
control measures are included. It is also important that
where thin upstream blankets are placed against rock-fill or
coarse gravel, careful attention be given to providing
properly graded transitions between the impervious and
coarser materials.
(3) Slope protection. Slope protection against wave
action is usually not required for cofferdams. However,
where a river is restricted to a channel by temporary
cofferdams prior to diversion, slope protection against
current action may be required. EM 1110-2-1601 should be
referred to for guidance on rock weights required to resist
various current velocities.
b. Closure sections. After portions of the dam have
been constructed with the river confined to a natural or
constructed channel, cofferdams are constructed to divert the
river through the outlet works so that the closure section can
be constructed in the dry. This may cause flooding of
upstream borrow areas, in which case alternate borrow areas
6-2
EM 1110-2-1911
30 Sep 95
fill, flattening slopes, addition of stability berms, or
installation of drains.
6-2.
Stage Construction
6-3.
Instrumentation
6-3
EM 1110-2-1911
30 Sep 95
given in Appendix E. A comprehensive reference on geotechnical instrumentation for monitoring field performance
including calibration, use, installation, and maintenance is
given in EM 1110-2-1908.
a. Installation. Installation of instrumentation devices,
particularly electronic types, should be supervised, if not
actually done, by experienced personnel from within the
Corps of Engineers or by firms specializing in instrumentation installation. The Resident Engineer staff must be
familiar with the planned locations of all instruments and
appurtenant apparatus or structures (such as trenches for
piezometer lines and terminal house, etc.) so that necessary
arrangements and a schedule for installation can be made
with the contractor and/or with the office or firm that will
install the devices. Inspectors should inspect settlement
gauges furnished and installed by the contractor. Records
must be made of exact locations and procedures used for
installation and initial observations. Riser pipes, tubes, or
leads extending above the embankment surface must be
protected from damage by earth mounds, guard posts, or
other means. Inspectors should ensure that necessary extensions are added as the fill is constructed to higher
elevations. This feature of construction generally occurs at
a time when the contractor is anxious to begin or accelerate
embankment construction. Therefore, patience, cooperation,
and understanding must be exercised by the contractor and
the Resident Staff.
b. Observations. Schedules for observations during
construction are generally established by the design office.
Pore pressure piezometers are observed frequently during
construction to provide data for use in slope stability checks
and to control, if necessary, the rate of fill construction on
soft foundations. Initial observations should be checked to
ensure their validity and accuracy, since these readings
usually form the basis to which subsequent observations are
related. Observations should be plotted immediately after
each set of readings is taken and evaluated for reasonableness against the previous set of readings. In this way,
it is often possible to detect errors in readings and to obtain
check readings before significant changes in field conditions
occur. On large projects all records should immediately be
processed by computers. This will generally result in the
quickest results with a minimum amount of effort. Possible
sources of errors other than erroneous readings are discussed
in EM 1110-2-1908. ER 1110-2-1925 prescribes the forms
6-4
EM 1110-2-1911
30 Sep 95
Chapter 7
Records and Reports
7-1.
Daily Reports
c. Date.
7-3.
d. Weather.
a. Records of instrumentation observations are important in determining changes in pore water pressure,
deformations, and settlements. The data, when summarized
and evaluated, are useful in substantiating design assumptions and thus in verifying stability during construction,
designing modifications, and additions to structures, or
determining causes of operating difficulties. Standard forms
and instructions for recording the following types of
instrumentation readings are contained in Appendix E.
Instrumentation Observations
7-1
EM 1110-2-1911
30 Sep 95
...,.,CT
(ER 1110-1-4)
"""'
""""""" .......
''''"'""'
CQC COnltal , . _ ~ MdlnltniciiCin ......:
HAS ANYTHING t:le"llt:L.OPf.O ON lliE 'MJRK 'hHICH MIGHT \.LI<DTOA CKP\HGE ORDER OR fiNO!NG OF f/C.TI
7-2
(MiliTARY}
EOI~
QNo
QvEs
~:CMP.c1'J
EM 1110-2-1911
30 Sep 95
lnfomwtion on proan of ..-ork. c:.~ fCH" clel-v .net extent of delays, ..-. .ttrer, plant, ma~.n... ecc.
tnfo,.tlon.
lnt~uctlon~
S"FETY: Onclu<h Ml' /tlf,..:riotl~ of .ppr<>Wid uln-t pJMo. :tain-t IMftll.t f>f
REMARKS:
(l~~b~Mrdmi:Doe~.r,.~~niiO'II'Offt)
QA REPRESENTATMS SIGNATVRE
DATE
SUPERVISOR"S INITIALS
Page 2 of 2 Pagecs
DATE
* U.S.G.P.O.: 1!i"90-718-S<tlft0302
7-3
EM 1110-2-1911
30 Sep 95
_,
........
IER 1110-1-61
DATE
'"
W~n<
%1'
%~~
HAS .
OEVElOf'ED ON THE WOfU: WHICH MIQHT
lEAO TO A OiANOE OROEA OR fNOINO OF FAcn
.~~'
F
1..., .....
I'
ITOTAL
0""
!'"""
n~-
'
o,....-
FEET
I"""'~ ITO
.I
I'"'
.I
""'WOK<'
.ro
FROM
o f.........,g: (al M.P. ll...,o ol oqlllptMnt .m- IAI Dl" ~. eM Ill) Nunober end d.l1dfic.lllon of oontl'lctor penoiiMI
~ P,.port \O.CRI ......talns U... ~ ll..W coot lae NIM~
..
..
..
..
I.
I
n~e;
I""""'
rOYAL
...
~.
'
d.
'
..'
by'-tfwt!
T~
abow.)
... - .........
""'"
ENG Fonn"
- ......... '"'"'
, May 94 (C'V"l
7-4
-~. ~
"'""'"' .......
'
EM 1110-2-1911
30 Sep 95
RESULTS OF QA INSPECTIONS AND TfST6, DEFICIENCIES OBSERVED, ACTIONS TAKEN AND CORRECTIVE ACllON OF CONTRACTOR.
INC\.UOE COMMENT PER'TA\HtHG 'TO CONl'f\ACTORS CQC ACTIVITIES
REMARKS:
~ wfslll:n lo
S-"'FE11 : (l~ .,., ~ ol ~ cal<liy plan, ufel)' tnar>u.l ex ~.strvcebn.s from Go\o'lm1711flll ~l Sprf OCIITKM acflfotl tMen.J
Qo\.REPRESE.HTATIVES SIGNATVRE
DATE
SUPERVISOR'S INITIALS
J"""'
Page 2 of 2 pages.
7-5
EM 1110-2-1911
30 Sep 95
c. Observations of seepage quantities from relief wells,
toe drains, seepage galleries, and other seepage control
installations should be recorded on appropriate locally
developed forms for evaluation at the project and district
levels. Unusual seepage conditions should be reported
immediately to the district office along with available
observational data for evaluation of the effect of existing
conditions on the safety of the dam.
7-4.
7-6
7-5.
EM 1110-2-1911
30 Sep 95
Appendix A
References
A-1. Required Publications
TM 5-818-5
Dewatering and Ground Water Control
TM 5-820-4
Drainage for Areas Other Than Airfields
ER 1110-1-1801
Construction Foundation Report
ER 1110-2-103
Strong Motion Instrument for Recording Earthquake
Motions on Dams
ER 1110-2-1925
Field Control Data for Earth and Rockfill Dams
ER 1110-2-8152
Planning and Design of Temporary Cofferdams and Braced
Excavations
ER 1180-1-6
Construction Quality Management
EM 1110-2-1601
Hydraulic Design of Flood Control Channels
EM 1110-2-1602
Hydraulic Design of Reservoir Outlet Works
EM 1110-2-1901
Seepage Analysis and Control for Dams
EM 1110-2-1906
Laboratory Soils Testing
EM 1110-2-1907
Soil Sampling
EM 1110-2-1908
Instrumentation of Earth and Rock-Fill Dams
EM 1110-2-1914
Design, Construction and Maintenance of Relief Wells
EM 1110-2-3800
Systematic Drilling and Blasting for Surface Excavations
A-1
EM 1110-2-1911
30 Sep 95
Gordon 1966
Gordon, B. B., and Miller, R. K. 1966 (May). Control of
Earth and Rock-Fill for Oroville Dam, Journal, Soil
Mechanics and Foundations Division American Society of
Civil Engineers, Vol 92, No SM3, pp 1-23.
Hammer 1973
Hammer, D. P., and Torrey, V. H., III. 1973. Test Fills
for Rock Fill Dams, Miscellaneous Paper S-73-7, U.S.
Army Engineer Waterways Experiment Station, Vicksburg,
MS.
Layman 1942
Layman, A. K. B. 1942. Compaction of Cohesionless
Foundation Soils by Explosives, Transactions, American
Society of Civil Engineers, New York, Vol 107, Paper No.
2160, pp 1330-1341.
Rosser 1969
Rosser, T. B., III, and Webster, S. L. 1969. Evaluation of
Nuclear Methods of Determining Surface in Situ Soil Water
Content and Density, Miscellaneous Paper S-69-15, U.S.
Army Engineer Waterways Experiment Station, Vicksburg,
MS.
Sherards 1963
Sherards, J. L., et al. 1963. Earth and Earth-Rock Dams,
Wiley, New York.
Smith 1968
Smith, P. C. 1968. The Use of Nuclear Meters in Soils
Investigations: A Summary of Worldwide Research and
Practice, Special Technical Publication No. 412, American
Society for Testing and Materials, Philadelphia, PA.
Torrey 1970
Torrey, V. H., III. 1970. Analysis of Field Compaction
Control Data; Perry Dam, Delaware River, Kansas, Miscellaneous Paper S-70-13, Report 1, U.S. Army Engineer
Waterways Experiment Station, Vicksburg, MS.
Torrey 1991
Torrey, V. H., III, and Donaghe, R. T. 1991. Compaction
Control of Earth-Rock Mixtures, Technical Report GL-9116, U.S. Army Engineer Waterways Experiment Station,
Vicksburg, MS.
Tokue 1976
Tokue, T. 1976. Characteristics and Mechanisms of Vibratory Densification of Sand and the Role of Acceleration,
Soil and Foundations, Vol 16, No. 3.
A-2
EM 1110-2-1911
30 Sep 95
EM 1110-2-2000
Standard Practice for Concrete for Civil Works Structures
EM 1110-2-2300
Earth and Rock-Fill Dams, General Design and Construction
Considerations
CE-1201
Subsurface Drilling, Sampling and Testing
CE-1305.01
Foundation Drilling and Grouting
CE-1306
Embankment (for Earth Dams)
CE-1307
Relief Wells
CE-1308
Stone Protection (Slopes and Channels)
Bertram 1963
Bertram, G. E. 1963. Rock-Fill Compaction by Vibratory
Rollers, Proceedings, Second Panamerican Conference on
Soil Mechanics and Foundation Engineering, Brazil, Vol 1,
pp 441-455.
Cedergren 1967
Cedergren, H. R. 1967. Seepage, Drains and Flow Nets,
Wiley, New York.
Fang 1991
Fang, Hsai-Yang, ed. 1991. Foundation Engineering
Handbook, Van Nostrand Reinhold, New York.
Huston 1970
Huston, J. 1970. Hydraulic Dredging: Theoretical and
Applied, Cornell Maritime Press, Cambridge, MD.
Leonards 1962
Leonards, G. A., ed. 1962.
McGraw-Hill, New York.
Foundation Engineering,
Robeson 1966
Robeson, F. A., and Crisp, R. L., Jr. 1966 (Sept).
Rockfill DesignCarters Dam, Journal of the Construction Division, Proceedings of the American Society of
Civil Engineers, Vol 92, CO3, pp 51-74.
Terzaghi 1967
Terzaghi, K., and Peck, R. B. 1967. Soil Mechanics in
Engineering Practice, 2d ed., Wiley, New York.
Tschebotarioff 1951
Tschebotarioff, G. 1951. Soil Mechanics, Foundations, and
Earth Structures, McGraw-Hill, New York.
Turnbull 1958 and 1959
Turnbull, W. J., and Shockley, W. G. 1958 and 1959.
Compaction of Earth Dams in the Corps of Engineers, U.S.
Army, Transactions, Sixth International Congress on Large
Dams, New York, Paris, Vol. 3, pp. 317-331.
U.S. Bureau of Reclamation 1973
U.S. Bureau of Reclamation. 1973. Design of Small Dams,
2d ed., U. S. Government Printing Office, Washington, DC.
U.S. Army Engineer District, Rock Island 1965
U.S. Army Engineer District, Rock Island.
1965.
Engineering Investigation and Design Studies for Underseepage Control (Slurry Trench Cutoff) for Taylorville Dam,
Des Moines River, Iowa, Design Memorandum, Harza
Engineering Co., Rock Island, IL.
Wilson 1969
Wilson, D. S., and Squier, R. 1969. Earth and Rockfill
Dams, State-of-the-Art Volume, Seventh International
Conference on Soil Mechanics and Foundation Engineering,
Mexico, pp 137-223.
Jones 1967
Jones, J. C. 1967. Deep Cut-offs in Pervious Alluvium,
Combining Slurry Trenches and Grouting, Transactions,
Ninth International Congress on Large Dams, Istanbul, Vol
I, pp 509-524.
A-3
EM 1110-2-1911
30 Sep 95
Appendix B
Methods of Relating Field Density Data
to Desired or Specified Values
B-1. General
Compaction control of soils requires the comparison of fill
water content and/or dry density values obtained in field
density tests with optimum water content and/or maximum
dry density or determination of relative density if the fill
materials are cohesionless. For fine-grained soils or coarsegrained with appreciable fines, field results are compared
with results of laboratory standard effort (or in special cases
15-blow or modified effort) compaction tests performed in
accordance with procedures given in EM 1110-2-1906
(Appendices VI and VIA). For free-draining cohesionless
soils, relative density of the fill material is determined using
test procedures described in EM 1110-2-1906 (Appendices XII and XIIA). However, see Control Using Relative
Density under paragraph B-4a below.
B-2. Fine-Grained Soils
a. Standard compaction test. The performance of a
standard laboratory compaction test on material from each
field density test would give the most accurate relation of
the in-place material to optimum water content and
maximum density, but it is not generally feasible to do this
because testing could not keep pace with the rate of fill
Figure B-2. Illustration of possible error using oneand two-point compaction methods
B-1
EM 1110-2-1911
30 Sep 95
one-point method, consider the field density and water content shown by point B in Figure B-2. Point B is close to
three compaction curves. Consequently, the correct curve
cannot be determined from the one point. The estimated
maximum dry density and optimum water content could
vary from about 92.8 pcf and 26 percent, respectively, to
95.0 pcf and 24 percent, respectively, depending on which
curve was used. Therefore, the one-point method should be
used only when the data define a relatively good line of
optimums.
c. Two-point compaction test results.
(1) In the two-point test, using the same equipment and
procedures used in the five-point compaction test, one
sample of material from the location of the field density test
is compacted at the fill water content, if thought to be at or
on the dry side of optimum water content (otherwise, reduce
the water content by drying to this condition). A second
sample of material is allowed to dry back about 2 to 3 percentage points dry of the water content of the first sample
and then compacted in the same manner. After compaction,
the water contents of the two samples are determined by
oven drying or other more rapid means, and the dry
densities are computed. The results are used to identify the
appropriate compaction curve for the material tested as
shown in Figure B-3.
(2) The data shown in Figure B-3 warrant the use of the
two-point compaction test since the five-point compaction
B-2
curves are not parallel. Using point A only, as in the onepoint test method, would result in appreciable error as the
shape of the curve would not be defined. The established
compaction curve can be more accurately defined by two
compaction points as shown. Although the two-point method is more accurate than the one-point method, neither
method would have acceptable accuracy when applied to the
set of compaction curves shown in Figure B-2. There are
materials and instances when the two-point compaction test
fails to identify the proper compaction curve. Experienced
embankment construction engineers suggest that when this
occurs, a third compaction point is necessary, and is performed for proper definition of the soil compaction curve.
d. Visual comparison. In the visual comparison method, selection of an appropriate compaction curve is based on
visual identification of the type of material from the field
density test with material (usually jar samples) on which
five-point compaction tests have been run. Unfortunately,
materials that appear similar can have widely varying
compaction characteristics, and this method is not considered reliable.
e. Atterberg limits correlations. To develop Atterberg
limits correlations, liquid limit, and plastic limit determinations and five-point compaction tests are made and plots
are prepared of optimum water content versus liquid limit,
versus plastic limit, and versus plasticity index. Similar
plots are made of the limits values versus maximum densities. The plots are then analyzed to determine if adequate
correlations exist (exhibited by plotted points falling in a
narrow band across the plot). Figures B-4 and B-5 are
examples of such plots. If a good correlation exists, appropriate limits tests are performed on the field density test
material and the plots used to estimate optimum water
contents and maximum densities of the in-place material.
This method is applicable to fine-grained cohesive soils
classified as CL and CH. Statistical analyses of the data
shown in Figures B-4 and B-5 indicate relatively good
correlations. Least square linear regressions were performed
on the data shown in Figures B-4 and B-5 to determine the
best fit linear equations to correlate optimum water
content and maximum dry density with liquid limit and
plasticity index. Using properties of statistical parameters,
it can be shown that about 68 percent of the data points (of
true optimum water content) on Figure B-4a will lie within
plus or minus 1.4 percentage points of the indicated line of
best fit; similarly, about 65 percent of the maximum dry
density data points will lie within plus or minus 2.7 pcf of
the indicated line. (Conversely, 32 percent of the data
points will fall outside of these limits around the respective
lines). Optimum water content and maximum dry density
did not correlate as well with plasticity index. Approximately 68 percent of the actual optimum water contents and
EM 1110-2-1911
30 Sep 95
.....
30
..,(' /
'1-._ z
~0
1-
.....
...1-z
z
~"
-15
.Po.f!"K
0
20
_,OS
1--- ..... --
1-wo.PT
=0. ZlO
y/
/0
..P
,.-<?
~~
foiV
~::.c
~
g-0
_,.<1
__ 0
8
..."'1-
()'/ ~
00
L1.4
L L t 1.5.fg
10
20
eo
70
110
LIQUID LIMIT LL
30
00
100
' 1).
>u:_o
~
'u '
'0
110
' ' ~c
._u
K
,..o
10
~
"',
0
>
1-
...0
>
~
~
~
roo
'bii'
MAX-::::.-0.41-tLL -1125.704
' 'BQ
f~
00
'~;
..
b,
'-0
'o..
',
""
', ',
'a..,~
0
20
30
50
LIQUID
60
LlJ..~IT
'
p.tz.7
~b
'
'
'
70
',,"'~--,
eo
'"'
00
100
Ll
Figure B-4. Examples of plots of optimum water content and maximum dry density versus liquid limit
B-3
EM 1110-2-1911
30 Sep 95
30
00
~
~
0
0
1-
"'
1-
.."'
u
~-
0/0
20
,.'Y ~~
fO 8""''J~- -
::i
. --...-<
15
1-
~~
, . ....
~
}d'
~-0/
/
~
v~
v
.12.1
~:t
~
v WOPT=O.Z63 P/112.262
/
10
zo
10
30
""
50
PLASTIC! TV INDEX PI
CJ.
70
115
'--o
'~ ",s
I
I
'0 MAX= -O. .t.t9 PI
f l/l.J72
110
'
O'o~
" t-,
0
0"
"'z
"'0
10 0
""
"
''
>
"'0
"'
b.
p;
'
'--B.
..
"
n,
'
'<J
"
~
',
0
10
"-,
' "-,
"',
"K
1:-- .tJ.6
"'
"'
0
10
zo
JO
AO
PLASTICITY IND(X PI
00
70
Figure B-5. Examples of plots of optimum water content and maximum dry density versus plasticity index
B-4
EM 1110-2-1911
30 Sep 95
dry densities will be within 2.1 percent and 3.6 pcf,
respectively, of those indicated by the lines of best fit.
Therefore, when this method is used, it is very important
that additional five-point compaction tests and Atterberg
limits tests be performed to check the correlation and to
extend the correlation for new borrow material for mixtures
not previously tested. The Atterberg limits correlation
method includes more variables than the two-point method
and thus can be less accurate, depending on how carefully
the particular method is used. However, the limits
correlation method has the advantage of providing the exact
classification of the soil, and of providing data that can be
correlated with design strength studies.
f. Analysis of Atterberg limits correlations. A discussion of Atterberg limits correlations and comparison of
results with the one-point method are given in by Torrey
(1970). However, additional discussion of the method is
deemed appropriate here to point out mathematical weaknesses in the procedure. In order to determine a mathematical relationship between the variables of interest (that is
liquid limit, plastic limit, optimum water content, maximum
dry density) using the methods of statistics, it is necessary
to assume a frequency distribution between the variables.
It was assumed that there is a normal or Gaussian distribution between the variables. A normal distribution has a
very specific mathematical definition and, although the
assumption of normal distribution is reasonable, it must be
pointed out that there is no insurance that the assumption is
valid. Additionally, it was assumed that the relationship
between the variables of interest is linear; again, there is no
evidence to support such an assumption; in fact, it is very
likely that there is a curvilinear relationship between the
variables of interest. Analysis of the data presented in Figures B-4 and B-5. showed that the linear correlations between optimum water content and liquid limit (shown in
Figure B-4a) and maximum density and liquid limit (shown
in Figure B-4b) explain only 77.6 percent and 76.3 percent,
respectively, of variation between the regression line and the
data points. This means that unidentified mechanisms
explain about one quarter of the variation between the
regression line and the points. Similarly, the linear correlations between optimum water content and plasticity index
(shown in Figure B-5a) and maximum dry density and
plasticity index (shown in Figure B-5b) explain only
57.8 percent and 55.7 percent of the variation, respectively;
about 43 percent of the observed variation is unexplained by
the mathematical model chosen. In this light, the correlation
between the variables appears less sound, especially considering that there is no mathematical assurance that a
relationship exists between these variables; the mathematical
curve-fit procedure used in the analysis ensures only that the
mathematical expressions given are the best possible linear
fits. The numbers defining the error bands of the regression
lines of Figures B-4 and B-5 are called the standard error of
the estimate. Again, if the data are normally distributed
about this line, theory predicts that about 68 percent of the
points lie between the (error band) lines. However, this also
indicates that 32 percent (about one-third) of the points will
statistically lie outside the band. For example, since the
standard error between maximum dry density and liquid
limit is 2.7 pcf, if maximum dry density were estimated
based on a determination of liquid limit of a soil sample
taken from the area, chances are about one in three that the
error in maximum density would be greater than 2.7 pcf. In
this light, the use of this procedure to estimate either
maximum dry density or optimum water content appears to
be unsound and inappropriate. The use of one- and twopoint compaction test results appears to be much more
sound, especially considering that the results of a one-point
compaction test may be obtained in about 40 min using
microwave drying techniques outlined in paragraph 5-10d
(1)(c). Conversely, the time required to obtain the results of
a liquid and/or plastic limit test may be prohibitive in a
construction environment where large volume rates of earth
are being placed.
g. USBR rapid compaction control method. Details of
this method are described in the U.S. Bureau of Reclamation
Earth Manual (1963). The test is applicable to fine-grained
(100 percent minus No. 4 sieve) cohesive soils with liquid
limits less than 50. The method, however, is applicable to
soils containing oversize particles providing the proper
corrections, as stated in Torrey (1970) or in the Earth
Manual (1963), are applied. It is a faster method than the
standard compaction test, and is often more accurate than
other methods. The method usually requires adding water
to or drying back sampled fill material, and thorough mixing
is required to obtain uniform drying or distribution of added
water. Otherwise, the results may be erroneous, especially
for highly plastic clays. In highly plastic (and probably
difficult) clays, it is likely to be inaccurate because of the
lack of sufficient curing time of the specimens.
B-3. Cohesive Soils
a. Oversize particles. The term oversize particles as
used in this work refers to those particles larger than the
maximum size allowed when using a given mold (i.e., No. 4
for a 4-in. mold, 3/4-in. for a 6-in. mold, 2-in. for a 12-in.
mold). The term fine fraction refers to that part of the
soil composed of particles equal to and smaller than the
maximum size allowed for a given mold. Results of field
density tests made in fill material containing oversize
particles must sometimes be related to results of compaction
tests made on materials from which oversize particles have
been scalped, if the USBR rapid compaction control method
is used, or if it has not been possible to perform compaction
B-5
EM 1110-2-1911
30 Sep 95
tests using molds of sufficient size to accommodate the
large particles.
c. Modified Ziegler equation to estimate maximum density. A procedure to compute dry density of earth-rock mixtures has been determined as an extension of the Ziegler
procedure and is discussed by Torrey and Donaghe (1991);
the procedure is a modification of the development which
resulted in Equation B-1. The modified equation accounts
for the actual percent compaction of the gravel fraction
when the total material (gravel and fines) is at its maximum
density. This is done by incorporating the effect of a factor
called the density interference coefficient, which is defined
as
ftwGm
wG m
(B-1)
ct
where
f = dry density of fine fraction, pcf
f = proportion of fine fraction by weight expressed
as a decimal fraction
t = dry density of total field sample, pcf
w = unit weight of water, 62.4 pcf
Gm = bulk specific gravity of oversize particles (dry
method), dimensionless
c = proportion of oversize particles by weight
expressed as a decimal fraction
The water content of the fine fraction can be calculated
from the following equation:
wf
wt
cwc
f
100
(B-2)
where
wf = water content of fine fraction, percent
wt = water content of the total field density sample,
expressed as a decimal fraction
wc = water content of oversize fraction, expressed as a
decimal fraction
At the beginning of construction, charts can be prepared for
materials having oversize particles relating dry densities and
water contents of total samples to dry densities and water
contents of fine fractions (Figures B-6a and B-6b) if it is
desired to use the original Ziegler equation. Different charts
are required for materials having oversize particles with
significantly different bulk specific gravity and/or absorption
values. In field density testing, the appropriate chart is
entered using the percent oversize particles and the water
content or dry density determined on the total sample to
obtain the water content, dry density, and wet density of the
fine fraction. Corrections for oversize particles will be subject to large errors if the percent of oversize particles is
greater than about 35; in such cases, compaction control
B-6
Ic
Rc
(B-3)
PgGm
where
Rc = decimal fraction of the percent compaction of
the minus No. 4 or -3/4-in. fraction
Pg = decimal fraction of percent gravel in the total
material
Gm = bulk specific gravity of the gravel
To determine the maximum dry density corresponding to the
gradation of the total fill sample, use the equation
tmax
PgIcfmaxwGm
fw
PgcIcfmax
(B-4)
where
tmax = maximum dry density of the gradation of the
total fill
fmax = maximum dry density of the finer fraction
determined at its optimum water content, Wfopt,
by the one- or two-point compaction method
It should be noted that fmax may be determined based on
gravel content defined as either the -3/4-in. or the minus
No. 4 sieve fraction of the total material to be placed in the
fill. However, it is more efficient to use the minus No. 4
fraction because percent oversize particles (c) and percent
gravel in the total material (Pg) are the same number. This
will eliminate an extra sieving operation which would be
required if fmax and Wfopt are used for the -3/4-in. fraction,
since both the percent oversize (+3/4-in. material) and the
percent gravel in the total material would have to be
determined.
To facilitate its numerical evaluation,
Equation B-4 may be rewritten in the form
90r---------r-------~---------r--------,---------~-------,
180r---------r--------,--------r---------,---------,---------.
eo
,.
'...
,...
z
!:?
1v
9
,..
~
120
...
w
2
;;:
"'z
i:
..
0
lo.
,..
1-
110
v
cr
,.."'
>-
40
1-
"'2w
cr
50
:!:
II:
0
>-
eo
130
"-
"
100
c..,= 2
30
5
A= 3%
A ::::10%
20
90
NOT
or
UNIT WEIGHTS
Or
~ATERIALS
10
70L-------~-------L------~L-------~-------L_______J
90
100
110
120
!30
140
'YT' Per
B-7
oL-------J--------L------~--------~-------L-------J
'o
20
30
~o
eo
t,.
EM 1110-2-1911
30 Sep 95
1~0
EM 1110-2-1911
30 Sep 95
PgIcwGm
tmax
f
w
fmax
Pg Ic
wfopt
(B-5)
Fopt
wtopt
(B-7)
Pg
wtopt fwfopt
cwc
(B-6)
where
wfopt = optimum water content of the fine fraction
The optimum water content of the fine fraction, wfopt, can be
directly related to that of the total material, wtopt, and the
gravel content of the total material, Pg, by an optimum
water content factor, Fopt, defined as
B-8
EM 1110-2-1911
30 Sep 95
a. Control using relative density. Where materials
available for cohesionless fill vary significantly in gradation,
maximum-minimum density tests should be performed on
material from each field density test at least in the initial
construction stages. Where cohesionless materials can be
grouped into categories with relatively constant gradations,
relative density tests and gradation tests can be performed
on each different material. Gradation tests on material from
field density tests can then make it possible to match field
densities with appropriate relative density test results.
However, it is necessary to point out that relative density is
computed from maximum and minimum densities determined on the material in question, using the procedure
outlined in EM 1110-2-1906. It was concluded by ASTM
(1973) that the maximum density of cohesionless materials
as determined on the vibratory table (as described in
EM 1110-2-1906) is subject to considerable uncertainty.
Further, the conclusions are that vibratory tables cannot, in
general, be successfully calibrated for repeatable energy
application to the soil specimen, large local density
variations exist throughout the vibrated soil specimen, and
density results obtained with the vibratory table are
generally not repeatable from laboratory to laboratory.
Therefore, control of the gradation and density of
cohesionless fill using the method of relative density may be
unacceptable, especially if the procedure involves
coordinated effort and testing between two laboratories. An
example is given by ASTM (1973) in which the standard
deviation in maximum density of one sand tested by
14 laboratories is greater than 6 pcf. It is specified in
EM 1110-2-1906 that minimum density tests be repeated
until densities from two successive runs agree within
1 percent. Maximum density is then obtained by placing
a minimum density specimen on the vibratory table; only
one maximum density test is required. Variation and uncertainty in laboratory-measured values of maximum density
can cause serious problems in the construction of cohesionless fill and graded filters. Basic laboratory research is
needed to resolve difficulties with the shaking table test for
maximum density. Until research is performed and the
B-9
EM 1110-2-1911
30 Sep 95
Appendix C
Field Compaction Control Forms and
Supplemental Instructions
C-1. General
ENG Form 4080 (Figure C-1) is for use where water content control is required to obtain adequate compaction; the
title of this form is Summary of Field Compaction Control
of Impervious or Semipervious Soils for Civil Works
Projects. ENG Form 4081 (Figure C-2) is for use when
water content control (other than complete saturation) is not
required; the title of this form is Summary of Field Compaction Control of Pervious Soils and Rockfill for Civil
Works Projects. Use of these forms is described in
ER 1110-2-1925.
a. A database package utilizing the commercially
available software routine dBase III Plus (Trademark of
Ashton-Tate) was developed around the information required
for ENG Forms 4080 and 4081; the system uses the microcomputer to analyze data for use in the quality assurance
(QA) program. Specially prepared Computer Applications
in Geotechnical Engineering (CAGE) software interacts with
the database to reduce data, perform statistical analysis, and
generate ENG Forms 4080 and 4081 with the information
required for reporting. Data from field notes is entered into
a microcomputer in a dBase III-driven format; for data
manipulation, the system is menu driven and user interactive. CAGE is designed to store, retrieve, and display
earthwork construction control data as well as provide
summaries of required construction parameters. Hard copies
of any of the summaries, reports, and graphs generated may
be printed by the system along with computer-generated
copies of ENG Forms 4080 and 4081 if they are required in
hard copy form. The use and operation of the CAGE
system is described by Edris, Strohm, and Woo (1991).
b. If construction control data are recorded manually on
ENG Forms 4080 and 4081, information at the top of each
form could be placed on a master sheet from which reproducible copies could be made for recording data and for
making subsequent copies for submission.
c. Explanation of any abbreviations used which are not
explained in the forms, should be furnished with the first
report submitted on a project.
d. Lower lines of the forms may be used for necessary
remarks.
C-1
~M"'"a""i_n_E=-m-:b:-a-n"'k_m_e_n_t-
am
Closure Section
,_,
EM 1110-2-1911
30 Sep 95
C-2
"-.clJf.CT
$U""-4 ... RY Oft Ft[LC COMPJ.CTION CONTROL OF tMPERVIOIJS OR Sl:NtPERVIOUS !"<>tLS ~"OR Ct\'IL WQRI(S Pllt0JE"CT5
"'
CO-'"'" o
:~:::
(nearest)
TO"'"
o" o o'
C0.'"'0'00
l1oo'..,
73
(date tran!llmitted
from field)
'
.. L.
IOliliCC .. '
OAT(
\
0111
t(lM(
.... Clt
114. 8
9. 8
II 0.
16.
I 07. 2 17. I
II I.
14.
116.
,,,,I
+ _1_1 _l.
II 3,
~am
76
26,2 j. .. CC.6
<I'
D
~'""~to"'
oo.LI,. ~P
c~~.,OI" '~'
C>'V;;;
<>"
0:.
Afi(A C U'LI."~' t~C.0."o'Afo0 .. , (TC
1
0
\"H
ToOOo "l0ufOOIOot, uU '"'I Sv""' (oo(,ToL '01100 o.O"O ,.,,,. ~I '0""' V~"ll tMt t>.ool
...
~c
- - I
82.
34.
68.4
j 44.4
37
74
32
91.
27' 4
8!. 0
' .. _..
~~~~o~o.o
,.,T .. o:l t .~ ..
o~"'
.. o~o.
ee
84. 0
'AI
>-
'"
,.,,Joo ...o"'
o~o
....
'" o..
o
~.-~to
OT"I:"
roT
11
Ol"'"'
uno'"'""
L.O. CO .... A~ Tl(l,. Tfp ... QT( At "'I V"Oil. COL. Ho AIOQ tOT OIT"-1'-t 0 ' P .. OCfOUIU
I 0 .. 1"01>< T COM .. A~ TIQIO OAT A 0 .. 110.0 IAfO,.kll (0" "'ICOO(Q '" CO~ II 4100 U. W.O.KI"G
....... 0""'" I ( (,..0'<<)(~ "' ( 01 """ Ml A(IIMtll
'0" uH " " ' " '""~ Ofdlf """ 0'"11"u'" "Af(tlt C:Ooof("T (ITI .. Af(O ITAl~ "0" UTUOAT(O
"~ C '""' '" ' .. ~, ( C, h,.OI>I f \1 A .. QAfiO t T "I)Q, "~ I'IP CO'"""~''"" CO" I OOQ~; ' IQ\,1! 0 ~'""
COJfiOOhAliQ", ~''"~~ C:Q"'"""'l0 .. , (YC
CO' 1' 0 .. <-Oc 1 "''"'"''COL H 000 COL H
!"OI(,Alf 0f."!vAfl0". ( <;; '0" COL 1a ~ COL ll 0" CO~ U. UoO!(Af( A 0" . "ll"ICTov{>.T
'0" CO-. II~
~I 0" COL II, ... OICOt( ... C 0 .. D. "'11"(Cfi~IL>
I~ TI.Sl tU.o. f t llO ~Ot .. (fT U"((.O,.(;ATOO .. t, 0(.,01( .... LCTfl"' OWl U<(l HQlt .. (W(O:OOAL ' " 1 ' 1
"'"1." "'"\' ,., "'- '0"' ""t:" os co><f.o:o ""0 oOf c o. oc. .. orr ,.,,
r7~/,o,h .4080
Figure c-1. Specimen sheet showing data actually reported from several projects
2 -0.
9i.:_l E
' ' '""''"'"~ '""'" ,...,._ ~'nc,_l loll <Hitr '""" 1. '"
Cliock !eot
on NM
97' 7
- f--- +--
J7' 0
81' 0
...
"
OL 20
.. Of(
J4
'
'
98.
126. 3
75
..
'--
>--
27
96.
"
11!2~~~:::.:
--i--+--"Dci.~~.:..!
Ciao
103
I Pt. Std.
Di.'!tict
-.2 t
ol 12. 9 t!.
Vi sua
COI!ol
I'IIC:1oQirl
..
...
7'
--
81
100
'
I -
---
Main l:mbankment
Dam
Daily
co"-""""
~"'C
(QI,l"'
,_, . .....L---l__
' - ..
--
... ,.
if desirerl1 or di~trict or
dtvleton use)
,r 1[()
"
1.,1
'"1..
OfN
.:-
'"'-"'5-S
(LfVA
Typ(
...... oe:
!10 ..
rts
~(1
........
T("
51Z(
(h
wv
I 0+ 70
I 0 US
338
(h
wv
1 5; 00
2 5 DS
143
1-1/
]"
~~
GP
1/4
10
fu!TOW
c GP
. Potvb.>!. :Born;.;;~.
'c:F:i5
1!1GC:W-E~IUIH)
Of IIIEPOAT
r date transmitted
from field)
~ Of"~t ~ro.:_'--,.---,---,--~
~ [l~
tt
9-10_
"
; 011
I Data_ 'n
c._---
.._ "
f'co"""'o
(0ption~l _e~try
(nearest)
'0~
,.r;:$:
!5-UMMJI.~V OF f"I(LO COMP.IICTIQN CONT~OL OF PEAVIOUS SOILS o\NO l'tOCWFILL FOI't CIVIL WORM.$ PROJECTS
nq
100
~6
zs)
100
40 ....
<.0 U
u,,.,,
c~~"'
"'""'""''
.. '
Sfi>(C'C
"""'"''' ~
~:Ol. II COl. U
""
...... o
~.,., ..
II!CtMo
00
III'CFI
.. ,. ........ 11111
III'C,I
,.., ...........
III'CI'I
COL 11 COL M
0, 7 1'1:5144._2 %.9
t.6 ~2.
-- t-0, 6 67.1 418 J.\4 1.4 46.7
~M~I
"f-:...:.:C-"f---+-"=--- - - -
. - -- 1- --
--r .... ..
I- 2Q_26
2176
-t--
Class u
1962
BPpr DT 21; 00
f:.~-
DT 21; 20
-
24U US
1400
I 00 DS
1461
....
___R~~=,
~l~ dta f+=o~m~~P::-"!'t~~c"t?~-~a~m~,
aT am e :;;:j::;;;:jp~\~st~rfct:_~~-i-t-t--~~~--'f2cc
I ..
r~~-T~;
__:_
. -------~
....
lA
so 6_4_1--~4_ _1_6_
I()_D_
llfl_1QQ~Yr"8
--
_1_01_6, 4 1:}
.
I
l"_....,i
--'--I
--
--+--+--
---+---t~~
__
)M IIJJ - - -
~- 2J,4t---t~--t-J"-'-'4+-'---i''t---+ll_?~-clt--V-t-'l-'0~2'-,7-t-'9"'4"-'-'-4+_ _-+-------25
J.lt---
4,7
118.6
104
114.1100,8 M. - -
--1---- - - r--
t-- --.
rr-
0
20
.:1 .....
1 :...!!_
I
1--
-----
_1_0
--f---1-j-
--
f- . . .....
t- -
-111---t--1----+-t---- -t-----t----1---t---t-----j
!----+- t--- .. -I-t-- - - - -
1----t----t-~--t-~-J
- --.-+--+-+-+--!---+--
Info mati n no
Riven
n fi!!'ld
....
Hf'mar s:
C 1
- Densiiy Tt>st
anTr rptn n~
Ap aratrs
(Job~
:ate ,
......
(.lt)
;~:;,;,o:;
-+- -
-+---1
~ 1-----------+--t---+---
_.L__.L__L_-l_-L._.J.._ ..L_.l_-l,---L-.L--,..,.,_,-,,_.,f---'-----1
,. ',,. .. ' 1
lj
...... ---l--+--+----jf--
tO "'"'' ._, g
v,
Distric-t,
c.
''''-
0, oc ,,,
1>0 ..
~ .. o ..
leO>~
Dt~S,f>
lU'
~0!
~ '<I
"l'~h
<1011
C-3
Figure C-2. Specimen sheet showing both pervious fill and rock-fill data actually reported from two districts
EM 1110-2-1911
30 Sep 95
EM 1110-2-1911
30 Sep 95
(d) Weight empty and as used, type of ballast, tire
pressure, and load per tire as used.
C-4
EM 1110-2-1911
30 Sep 95
Appendix D
Instructions for Preparing Periodic
Summaries of Field Compaction Control
Data on Earth and Rock-Fill Dams
D-1. Compaction Control Data Summary Forms
Summaries of compaction control data are prepared at least
monthly, using tabular summary form, ENG Form 4287, and
one or both of two summary plots: ENG Form 4287A for
soils requiring control of both water content and density and
ENG Form 4287B for soils requiring only density control.
D-2. Separate Summary Forms and Plots
Separate summary forms and plots should be prepared for
(a) significantly different materials (impervious, random,
pervious, etc.) used in different zones of the embankment
and (b) materials compacted by different equipment (e.g.,
impervious fill compacted by towed rollers and impervious
backfill compacted by hand-operated power tampers).
D-3. Example Summary Forms and Plots
Examples of prepared summary forms and plots are shown
in Figures D-1 through D-4. Examples of appropriate entries for tabular summaries are given in Table D-1.
lines are first drawn on the plot to show the limiting values
of water content in percentage points wet or dry of standard
optimum. A horizontal line is drawn to show the desired or
specified minimum percent of maximum standard and dry
density. The top margin and right side margin of the plot
are marked to show the limiting values illustrated in
Figure D-2. The data are then plotted using symbols shown
on the legend. Should an area be reworked more than once
or reworked and tested more than once, only the last test
result or last set of test results should be plotted. The test
results are summarized in the tabulation form on the right
side of the plot in Figure D-2. Total number of tests is the
total number of plotted data points excluding retests and
check tests. Check tests should not be included in the
number retested.
D-5. Summary Plot for Materials Requiring Only
Density Control
Use of the summary plot for material requiring only density
control is illustrated in Figure D-4. Inappropriate labels at
the top and bottom of the plot are lined out. If control is
based on maximum density determined using a vibratory
procedure, STD should also be lined out. Suitable scales
are added to the plot, and a vertical line is drawn to indicate
the minimum value of relative density, minimum percent of
maximum standard dry density, or minimum percent of
maximum dry density by a vibratory procedure, whichever
applies.
D-1
EM 1110-2-1911
30 Sep 95
Project
Resident Engr
Distri_ct
(Rtver)
Location of Projec-t
Report No
12
Perlod
5 N g v 68
TYPE OF FILL
S. J. Smith
IMPERVIOUS (CORE)
Soil Classification
CH, CL
(USCS Symbols)
stationing of Areas Tested
~levation of Areas
Tested
Fompaction Equipment
Number of Passes
~ncomp.
~oiler
Lift Thick.
Speed, MPH
14+75 to 46+50
832 to 840
Method of Relating
Field w to Std Opt w,
and Field Density to
Max. Dry Density, or
Relative Density
8 in.
3 to 5
Sand Volume (90%)
Nuclear ( 1 Oo/oP
Oven Drying
Field results compared to laboratory
compaction curve for similar soil. Appropriate laboratory curve selected by I - or
2-point Std compaction test at field w or
drier, supplemented "':ith liquid 1imit test
correlation
9 5%
21
3
2
I
Remarks
Only the two 11 1nthal 11 tests shown on the summary plot were by nuclear method;
check tests and remainder of tests were by ;and volume method
**Strike out inapplicable words.
(ER lll0-2-1925)
Summary Prepared by
Summary Checked by
ARC
JSJ
Date
Date
6 Dec 68
7 Dec bB
Figure D-1. Example of a prepared summary form, field compaction control data, impervious (core)
D-2
PROJECT: - - - - - - - - - - - Dam
DISTRICT: ------........_-__,,..._
REPORT PERIOD :
5 Nov - 5 Dec 68
REPORT NO, :
12
TYPE OF
aM TERIAL : ---!:
l~:.:.
MPE R:.:.
V.::.:
IO:..:U:.:::S:....Jo.:
(C
::.:O:.:.
RE
::::.L.
)_
CUKJLATIVE
TO THIS
REPORT
THIS
REPORT
270
21
roTAL
57
42
___..1_
DENSITY
12
___2_
_ _1_
w " DENSITY
NO, REWORKED
50
__2_
44
__
4
LEGEND :
X 111
)1.1' )1.
e,,
NOTE :
7
e . g.,",- e,,
A, -
D-3
Figure 0-2. Example of a prepared summary plot for materials requiring water content and .density control
A1
(ER 1110-2-1925)
EM 1110-2-1911
30 Sep 95
ENG For m 4 28 7A
JUN 69
EM 1110-2-1911
30 Sep 95
Dam
Distrtct
Insp. or Tech ~J~~S~-~~J~o~n~e~s~Loc~tion of Project -=--~~----~~(~R~iv~e~r~l--------~----~~(un~e~a~r~e~s~t~to~vv~nu_~s~ta~tu.e)
12
Report No
Period
Soi 1 Classification
of Areas Tested
Compaction Equipment
Number of Passes
~ncomp.
to
5 D ~~ 68
':<
15+50 to 37+50
830 to 839
Vibratory Roller, Tampo Model vcso
(static wt. = 3. 5 tons, ,)entrifugal force
of 7 5 tons at 1600 rom
4
Lift Thick.
~oller Speed,
6 in.
2
MPH
Specified Range
~oints Above
0{
w (Percentage
(Desired)
(1. Comp. or
Min.
(Specified)
Rei. Density)+
"o. Areas Tested
th W Outside
Acceptable Limits
~o. with Density
Below M1 n.
~o. With w and Density
Outside Acceptable Limits
fNo.
N6S
OV
sw
(USCS Symbols)
Stationing of Areas Tested
~levation
TYPE OF FILL
80o/o
25
Wl
Not Applicable
6
Not applicable
Remarks
,.,.,
JUN 69
(ER 1110-2-1925)
Summary Prepared by
Summary Checked by
ARG
JSJ
Date
Date
6 Dec 68
7 Dec 68
Figure D-3. Example of a prepared summary form, field compaction control data, pervious
(sand drain)
D-4
I(DESI RED)(fil
I .. u II)
liMN)
PROJECT:
Dam
DIS11tiCT : - - - - - - - - - -
REPORT PERIOD:
!""; _
"
130
. i.
~ ::- L :
. .
: -<:1.;.:
I,
CUIIULA TI VI
T0111IS
REPORT
"I
:i-
.J
68
5 Nov - 5 Dec
::: ..:;:
'IBIS
REPORT
112
26
NO, REW<EIED
2J
6
__5_
NO, RETESTED
AP"''ER RnORIONG
18
_.1_
LBGEND :
)(
x..
e,,
N<Jm:
(RELATIVE DENSITY, Dd , PERCENT)
(Bml :IN I
JUN 69
D-5
Figure 0-4. Example of a summary plot for material requiring only density control
EM 1110-2-1911
30 Sep 95
EM 1110-2-1911
30 Sep 95
Table D-1
Samples of Appropriate Entries on Tabular Summary
Compaction Equipment
Method of Relating Field w to Standard Optimum w and Field Density to Maximum Dry
Density or Relative Density
Field results compared with results of complete standard compaction test on material
from field test.
Field results compared with results of rapid compaction (USBR) tests on fill material.
Field results compared with laboratory standard compaction results for minus 1-in.
material, corrected for percent plus 1-in. material. Appropriate laboratory results
selected by Atterberg limits correlations.
Compared visually with materials on which laboratory standard compaction tests were
performed.
Maximum (vibratory table)1 and minimum density determined for each field density test.
Note: if more than one method is used, show percentage use of each method.
1
Use care to confirm reliability of maximum density as determined on the vibratory table. See the caution in Appendix B,
paragraph B-4a.
D-6
EM 1110-2-1911
30 Sep 95
Appendix E
Description and Use of Instruments
During Earth and Rock-Fill Dam
Construction
E-1.
General
Stability of an earth and rock-fill dam is often more uncertain during construction than upon completion. Unfavorable conditions produced, for example, by inclement weather
during construction may result in transient conditions of
marginal stability, which may be the most dangerous over
the life of an embankment. For that reason, it is important
to carefully and continuously monitor the state of a
compacted earth structure during construction. Instruments
to monitor displacement, slope (change), pore water pressure, soil stress, and water flow are necessary to monitor
changes in an embankment that may signify the onset of
instability and indicate the need of a change in construction
technique or procedure. The basic instruments, their function and basic operating principal will be described here.
However, EM-1110-2-1908 is under preparation at this
writing and will clarify the philosophy, policy, use, and
installation of instrumentation with respect to earth and
rock-fill dams.
E-2. Displacement Measuring Techniques
and Instruments
a. Slope indicators (inclinometers). Slope indicators are
used primarily to monitor earth movement in undisturbed
soil masses as well as compacted embankments by detecting
changes in slope within the soil structures. A specially
designed plastic or aluminum casing with an alignment
groove along one edge may be installed in a bore hole up to
900 ft deep. Slope indicator instruments are lowered into
the casings on spring-loaded rollers which ride into the
grooves to maintain alignment. Deviation from the vertical
is detected by monitoring an electronic signal from either a
Wheatstone Bridge circuit or piezoelectric crystals within
the sensor, which is generated by a change in stress in a
mechanical system such as a pendulum or cantilever arm.
Slope versus electronic signal from a slope indicator
instrument is established by calibration; therefore the slope
of the bore hole with depth is determined from the output
signal of the sensor as it is lowered into the bore hole.
Change in slope with time is an indication of embankment
movement. Plots of slope versus depth at various locations
over the site of the embankment will indicate patterns of
movement and will therefore index the stability of the
embankment. Manufacturers of slope indicator instruments
claim that some models have the sensitivity to detect a
deviation in slope of one part in 10,000. A careful calibration is recommended before installation of this or any
instrument to confirm that devices are operational, and that
they deliver the measurement accuracy required for proper
monitoring.
b. Settlement/heave measurement devices. Settlement
devices are sometimes used in the same casings as slope
indicators. Settlement meter casings are designed to telescope in order to follow settlement or heave within the soil
structure. Special couplings in the casing may allow from 6
to 12 in. of movement per casing section. A probe which
hooks to the bottom lip of a casing section is lowered into
the bore hole. After hooking onto the bottom lip of a casing
section, distance from the top of the casing is measured with
a surveyors chain. The elevation of the casing top may be
determined by standard level survey techniques based on
bench marks outside the settlement zone. Calibration required for this procedure is accomplished with a surveyors
chain. A slight variation to this procedure is to measure
settlement in emplaced structures by placing ferrous metal
washers around the casings. The vertical position of the
washers may be monitored using magnetic or inductive
pickup sensors.
E-3.
Stress Measurement
E-1
EM 1110-2-1911
30 Sep 95
structure in which they are installed and, as a result, the
stress measured may be in error. Calibration of these devices can be difficult, and installation must be performed by
an experienced technician.
E-4.
E-2
Flow Measurement
EM 1110-2-1911
30 Sep 95
calibration. Impeller flow transducers are generally used to
measure relatively small rates of flow which must be
obtained precisely. However, impeller flow transducers do
not work well when used with water containing sediment, as
particles of grit tend to jam the mechanism, causing it to
seize.
E-6.
Temperature Measurement
E-3
EM 1110-2-1911
30 Sep 95
Subject
Index
Subject
Page
. . . . . . . . . . . . . 4-1
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
4-11
4-11
4-11
4-11
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
4-5
4-7
4-7
4-7
4-7
4-8
4-5
4-5
4-7
4-5
4-7
4-6
4-6
4-6
3-1
3-6
. . . . . . . . . . . . . 3-2
. . . . . . . . . . . . . 3-4
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. . . 5-6
. . . 5-15
. . . 5-16
5-6, 5-7
. . . 5-6
. . . 5-6
5-7, 5-8
. . . 5-8
. . . 5-7
5-6, 5-7
. . . 5-6
. . . 5-6
5-7, 5-8
Construction control
Fill . . . . . . . . . . . . . . . . . . . . . . .
Pervious . . . . . . . . . . . . . . . .
Semipervious earth . . . . . . . . .
Importance of . . . . . . . . . . . . . . .
Inspection . . . . . . . . . . . . . . . . . .
Personnel . . . . . . . . . . . . . . . . . . .
Procedures . . . . . . . . . . . . . . . . . .
Purpose of . . . . . . . . . . . . . . . . . .
Relation to design . . . . . . . . . . . . .
Test fill . . . . . . . . . . . . . . . . . . . .
Test quarries . . . . . . . . . . . . . . . .
Verification of requirements . . . . . .
Construction, earth-fill and rock-fill . . . .
Earth test fills (See Test fills,
earth.)
Equipment (See Equipment,
earth-fill and rock fill.)
Impervious fills (See Fill,
impervious and semipervious.)
Pervious fills (see Fill,
pervious.)
Placement sequence . . . . . . . . . . .
Quantity measurement . . . . . . . . . .
Rock fill (See Fill, rock.)
Rock test fills (See Test fills, rock.)
Semipervious fills (See Fill,
impervious and semipervious.)
Slope protection . . . . . . . . . . . . . .
Placement of protection . . . . . .
Reasons for . . . . . . . . . . . . . .
Types of damage . . . . . . . . . .
Types of protection . . . . . . . . .
Construction features, miscellaneous . . .
Drainage, surface . . . . . . . . . . . . .
Necessity . . . . . . . . . . . . . . . .
Methods . . . . . . . . . . . . . . . .
Instrumentation . . . . . . . . . . . . . .
River diversion . . . . . . . . . . . . . . .
Closure section . . . . . . . . . . . .
Cofferdams, embankment-type .
Roads . . . . . . . . . . . . . . . . . . . . .
Haul . . . . . . . . . . . . . . . . . . .
Maintenance . . . . . . . . . . . . . .
Public . . . . . . . . . . . . . . . . . .
Service bridge pier foundations . . .
Stage construction . . . . . . . . . . . .
Features . . . . . . . . . . . . . . . . .
Necessity . . . . . . . . . . . . . . . .
Construction records (See Records and
reports, construction.)
Contractor
Relations with resident engineer . . .
Page
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-19,
....
....
....
....
....
....
....
....
....
....
....
....
5-22
5-19
5-22
1-1
1-1
2-2
5-7
1-1
1-1
5-1
4-10
2-4
5-1
. . . . . . . . 5-22
. . . . . . . . 5-23
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.....
5-23,
.....
.....
5-23,
.....
.....
.....
.....
.....
.....
.....
.....
.....
.....
.....
.....
.....
.....
.....
.....
5-23
5-25
5-23
5-23
5-25
6-1
6-3
6-3
6-3
6-3
6-1
6-1
6-1
6-4
6-4
6-4
6-4
6-3
6-3
6-3
6-3
. . . . . . . . 2-3
Index-1
EM 1110-2-1911
30 Sep 95
Subject
Responsibilities
Borrow area operations . . . .
Dewatering systems . . . . . .
Quality control . . . . . . . . . .
Contract specifications (See Specifications, contract.)
Dental treatment . . . . . . . . . . . . . . .
Cavities . . . . . . . . . . . . . . . . . .
Overhangs . . . . . . . . . . . . . . . .
Rock foundations and abutments
Surface depressions . . . . . . . . .
Design . . . . . . . . . . . . . . . . . . . . . .
Evaluation of . . . . . . . . . . . . . .
Relation to construction . . . . . . .
Design engineers . . . . . . . . . . . . . . .
Preconstruction training . . . . . . .
Relation to construction . . . . . . .
Responsibilities . . . . . . . . . . . .
Dewatering of excavated areas . . . . .
Detection . . . . . . . . . . . . . . . . .
Evaluation . . . . . . . . . . . . . . . .
Failure of system . . . . . . . . . . .
Grouting . . . . . . . . . . . . . . . . .
Impervious blanket . . . . . . . . . .
Necessity . . . . . . . . . . . . . . . . .
Pumping of fines . . . . . . . . . . .
Responsibilities of . . . . . . . . . .
Sumps and ditches . . . . . . . . . .
Surface erosion . . . . . . . . . . . .
Types of systems . . . . . . . . . . .
Drainage of excavated areas (See
Dewatering of excavated areas.)
Equipment, earth-fill and rock-fill
Compaction . . . . . . . . . . . . . . .
Confined areas . . . . . . . . . . . . .
Excavating . . . . . . . . . . . . . . . .
Handling . . . . . . . . . . . . . . . . .
Hauling . . . . . . . . . . . . . . . . . .
Processing . . . . . . . . . . . . . . . .
Separating . . . . . . . . . . . . . . . .
Spreading . . . . . . . . . . . . . . . .
Equipment, rock excavation . . . . . . .
Hauling . . . . . . . . . . . . . . . . . .
Loading . . . . . . . . . . . . . . . . . .
Processing . . . . . . . . . . . . . . . .
Field control, testing and sampling . . .
Evaluation of results . . . . . . . . .
Field density and water content
related to maximum density
and optimum water content . .
Aspects of comparison . . . .
Gravely soils, methods for . .
Methods . . . . . . . . . . . . . .
Index-2
Page
. . . . . . . . . . 4-5
. . . . . . . . . . 3-10
. . . . . . . . . . 2-2
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. . 3-2
. . 3-8
. . 3-9
. . 3-2
. . 3-9
. . 1-1
. . 1-1
. . 1-1
1-1, 2-1
. . . 2-1
. . . 1-1
. . . 1-1
. . . 3-10
. . . 3-10
. . . 3-10
. . . 3-11
. . . 3-12
. . . 3-12
. . . 3-10
. . . 3-10
. . . 3-10
. . . 3-11
. . . 3-12
. . . 3-10
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-1,
...
...
...
...
...
...
...
...
...
...
...
...
...
5-17
5-16
4-1
4-1
4-1
5-1
4-1
5-1
4-8
4-8
4-8
4-8
5-8
5-15
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-14
5-14
5-15
5-14
.
.
.
.
.
.
.
.
Subject
Page
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-9
5-9
5-9
5-9
5-9
5-9
5-9
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-11
5-12
5-11
5-8
5-8
5-8
5-9
5-15
5-14
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
B-1
B-1
B-8
B-5
B-1
2-3
2-3
2-3
2-3
2-3
5-5
. . . . . . . . . . . 5-7
. . . . . . . . . . . 5-5
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-17
5-17
5-19
5-19
5-19
5-17
5-19
5-19
5-19
. . . . . . . . . . . 5-20
. . . . . . . . . . . 5-18
. . . . . . 5-18, 5-19
EM 1110-2-1911
30 Sep 95
Subject
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Page
Subject
5-18
5-21
5-21
5-21
5-21
5-21
5-21
5-22
5-22
5-22
5-22
5-22
5-22
5-22
3-1
3-1
3-1
3-1
3-1
3-1
3-1
Blasting . . . . . . . . . . . . . . . . . . .
Clearing . . . . . . . . . . . . . . . . . .
Compaction . . . . . . . . . . . . . . . .
Depressions . . . . . . . . . . . . . . . .
Final preparation . . . . . . . . . . . .
Grubbing . . . . . . . . . . . . . . . . . .
Slopes . . . . . . . . . . . . . . . . . . . .
Stripping . . . . . . . . . . . . . . . . . .
Government inspection force . . . . . . . .
Gradation
Pervious zones . . . . . . . . . . . . . .
Riprap . . . . . . . . . . . . . . . . . . . .
Rock test fills . . . . . . . . . . . . . .
Grout curtains . . . . . . . . . . . . . . . . . .
Inspection
Borrow pits . . . . . . . . . . . . . . . .
Closure . . . . . . . . . . . . . . . . . . .
Compaction . . . . . . . . . . . . . . . .
Construction control . . . . . . . . . .
Construction procedures, pervious
fill . . . . . . . . . . . . . . . . . . . . .
Dewatering systems . . . . . . . . . .
Excavation of weathered rock . . .
Field conditions . . . . . . . . . . . . .
Foundation and abutment treatment
Galleries, drainage . . . . . . . . . . .
Resident inspection force . . . . . . .
Rock fill . . . . . . . . . . . . . . . . . .
Shaping and cleaning operations . .
Stripping operations . . . . . . . . . .
Test trenches . . . . . . . . . . . . . . .
Instrumentation
Importance . . . . . . . . . . . . . . . .
Installation . . . . . . . . . . . . . . . . .
Observations . . . . . . . . . . . . . . .
Reports, observations . . . . . . . . .
Specialists . . . . . . . . . . . . . . . . .
Types . . . . . . . . . . . . . . . . . . . .
Materials, borrow area (See Borrow
area operations - Materials.)
Quality control . . . . . . . . . . . . . . . . .
Aspects of . . . . . . . . . . . . . . . . .
Compaction tests . . . . . . . . . . . .
Durability of materials . . . . . . . .
Fill placement procedures . . . . . .
Quality of materials . . . . . . . . . .
Responsibility of contractor . . . . .
Responsibility of Government
inspection force . . . . . . . . . . . .
Quarries (See Borrow areas and
quarries.)
Quarries, test . . . . . . . . . . . . . . . . . . .
Personnel . . . . . . . . . . . . . . . . . .
. . . . . . . . . . 3-1
. . . . . . . . . . 3-1
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. . . 3-2
. . . 3-2
. . . 3-6
3-2, 3-3
. . . 3-8
3-2, 3-3
. . . 3-2
. . . 3-2
3-2, 3-3
. . . 3-2
3-2, 3-3
. . . 3-2
. . . 3-3
. . . 3-3
. . . 3-2
Page
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. . . 3-1
. . . 3-1
. . . 3-1
3-1, 3-2
. . . 3-1
. . . 3-1
. . . 3-2
. . . 3-1
2-2, 2-3
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-18,
.....
.....
.....
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
4-5, 4-7
. . . 6-2
. . . 5-6
. . . 1-1
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-19
3-10
3-8
2-4
3-1
3-5
2-1
4-10
3-2
3-1
5-5
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
2-4
6-4
6-4
7-1
2-4
6-3
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
2-2
2-2
2-3
2-3
2-3
2-3
2-2
5-19
5-23
5-5
3-5
. . . . . . . . . 2-2
. . . . . . . . . 4-9
. . . . . . . . . 4-10
Index-3
EM 1110-2-1911
30 Sep 95
Subject
Procedures . . . . . . . . . . . . . . .
Purpose of . . . . . . . . . . . . . . .
Records . . . . . . . . . . . . . . . . .
Records and reports, construction
Additional information . . . . . .
Compaction control . . . . . . . .
Construction foundation . . . . .
Contents . . . . . . . . . . . . . . . .
Daily . . . . . . . . . . . . . . . . . .
Documentation of test results . .
Evaluation of claims . . . . . . . .
Final . . . . . . . . . . . . . . . . . . .
Forms, field compaction control
Inspection report . . . . . . . . . .
Instrumentation observations . .
Maintenance of . . . . . . . . . . .
Master diary . . . . . . . . . . . . .
Necessity of . . . . . . . . . . . . . .
Payments, basis for . . . . . . . . .
Photographs . . . . . . . . . . . . . .
Preparation instructions . . . . . .
Test fills . . . . . . . . . . . . . . . .
Test quarries . . . . . . . . . . . . .
Use of data . . . . . . . . . . . . . .
Reports (See Records and reports,
construction.)
Resident engineer . . . . . . . . . . . . . .
Assistants . . . . . . . . . . . . . . .
Relationship with contractor . . .
Responsibilities . . . . . . . . . . .
Technical responsibilities . . . . .
Resident inspection force . . . . . . . .
Composition . . . . . . . . . . . . .
Duties . . . . . . . . . . . . . . . . . .
Organization . . . . . . . . . . . . .
Preconstruction training . . . . . .
Relationship with contractor . . .
Size . . . . . . . . . . . . . . . . . . .
Riprap . . . . . . . . . . . . . . . . . . . . .
Removal . . . . . . . . . . . . . . . .
Stream protection . . . . . . . . . .
Rock conditions, unfavorable . . . . .
Cavities . . . . . . . . . . . . . . . . .
Causes . . . . . . . . . . . . . . .
Remedies . . . . . . . . . . . . .
Untreated . . . . . . . . . . . . .
Detrimental characteristics . . . .
Erosion and scour . . . . . . . . . .
Fill . . . . . . . . . . . . . . . . . . . .
Fractures . . . . . . . . . . . . . . . .
Inspection of excavations . . . . .
Open joints . . . . . . . . . . . . . .
Index-4
Page
. . . . . . . . . . . 4-9
. . . . . . . . . . . 4-9
. . . . . . . . . . . 4-10
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. . C-1
. . 7-1
. . 7-6
. . 2-5
. . 7-1
. . 2-4
. . 2-5
. . 7-6
. . C-1
. . 2-5
. . 7-1
. . 1-1
. . 2-5
. . 1-1
. . 2-5
1-1, 2-5
. . . D-1
. . . 5-1
. . . 4-10
. . . 2-4
1-1, 2-1
. . 2-1
. . 2-3
. . 1-1
. . 2-1
. . 2-1
. . 2-1
. . 2-1
2-1, 2-2
. . . 2-1
. . . 2-3
. . . 2-1
5-23, 6-2
. . . . 6-2
. . . . 5-23
. . . . 3-8
. . . . 3-8
. . . . 3-8
. . . . 3-8
. . . . 3-8
. . . . 3-8
. . . . 3-8
. . . . 3-8
. . . . 3-8
. . . . 3-8
. . . . 3-8
.
.
.
.
.
.
.
Subject
Overhangs . . . . . . . . . . . . . . . .
Dental treatment . . . . . . . . .
Removal . . . . . . . . . . . . . .
Tamping of soil . . . . . . . . .
Springs . . . . . . . . . . . . . . . . . .
Surface depressions . . . . . . . . .
Dental treatment . . . . . . . . .
Fill procedure . . . . . . . . . . .
Weathered rock . . . . . . . . . . . .
Rock fill, obtaining . . . . . . . . . . . . .
Blasting . . . . . . . . . . . . . . . . . .
Drilling . . . . . . . . . . . . . . . . . .
Processing . . . . . . . . . . . . . . . .
Seepage control . . . . . . . . . . . . . . . .
Blankets . . . . . . . . . . . . . . . . .
Core trenches (See Seepage
control - Cutoffs.)
Cutoffs . . . . . . . . . . . . . . . . . .
Compacted backfill trenches .
Grout curtains . . . . . . . . . .
Slurry trenches . . . . . . . . . .
Excavated areas . . . . . . . . . . . .
Galleries . . . . . . . . . . . . . . . . .
Relief wells . . . . . . . . . . . . . . .
Toe drains . . . . . . . . . . . . . . . .
Soil conditions, unfavorable . . . . . . .
Clay shales . . . . . . . . . . . . . . .
Collapsible soils . . . . . . . . . . . .
Highly compressible soils . . . . .
Loose granular soils . . . . . . . . .
Low-strength soils . . . . . . . . . .
Old river channels . . . . . . . . . .
Steep abutment slopes . . . . . . . .
Specialists . . . . . . . . . . . . . . . . . . . .
Design engineers . . . . . . . . . . .
Field instrumentation technicians
Geologists . . . . . . . . . . . . . . . .
Geotechnical engineers . . . . . . .
Specifications, contract
Changes . . . . . . . . . . . . . . . . .
Compaction . . . . . . . . . . . . . . .
Compliance with . . . . . . . . . . .
Rock fill . . . . . . . . . . . . . . . . .
Test fill . . . . . . . . . . . . . . . . . .
Understanding of . . . . . . . . . . .
Verification of requirements . . . .
Stockpiling (See Borrow area
operations - Stockpiling.)
Test fills, earth . . . . . . . . . . . . . . . .
Test fills, rock . . . . . . . . . . . . . . . . .
Construction control . . . . . . . . .
Gradation tests . . . . . . . . . . . . .
Page
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
3-9
3-9
3-9
3-9
3-9
3-9
3-9
3-9
3-8
4-10
4-10
4-10
4-10
3-3
3-5
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
3-3
3-3
3-5
3-3
3-13
3-5
3-5
3-6
3-6
3-6
3-7
3-6
3-7
3-6
3-7
3-7
2-4
2-4
2-4
2-4
2-4
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. . . . . 2-4
. . . . . 5-6
. . 1-1, 2-1
4-10, 5-21
. . . . . 5-1
. . 2-1, 2-3
. . . . . 2-4
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
5-5
5-1
5-1
5-5
EM 1110-2-1911
30 Sep 95
Subject
Page
Purposes . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1
Test quarries . . . . . . . . . . . . . . . . . . . . . . . . 5-1
Trenches, compacted backfill (See
Seepage control - Cutoffs.)
Trenches, slurry. (See Seepage
control - Cutoffs.)
Subject
Water content
Borrow area operations . . . . .
Compaction . . . . . . . . . . . . .
Measurements . . . . . . . . . . .
Microwave oven . . . . . . . . . .
Pervious materials . . . . . . . .
Related to maximum density
and optimum water content
Page
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
4-6
5-7
5-9
5-10
5-18
. . . . . . . . . . . . 5-14
Index-5