Project Control
Project Control
PROJECT CONTROL-
REASONS FOR INEFFECTIVE PROJECT
CONTROL,
TECHNIQUE OF PROJECT CONTROL
FMS@BHU Page 1
INDEX
1-PROJECT
CONTROL-------------------------------------------------------------------------------3
CONTROL--------------------------------------------4
3-PROJECT CONTROL
VARIABLE------------------------------------------------------------------6
4-PROJECT CONTROL
TECHNIQUE----------------------------------------------------------------7
FMS@BHU Page 2
Project management
Project Control
FMS@BHU Page 3
Time—
Technical difficulties require more time to solve Technical solve
Scope of work increases Scope increases--Unexpected utilities needing
relocation
Task sequencing not done right Task right--Required material,
labor/equipment unavailable when needed.
Key preceding tasks were not completed on time.
Reference- GENERAL CLUES (Meredith and
Mantel, 2006)
Elements of Project
Control
Manpower related control
Machinery related control
Money related control
Material related control
Effective control is critical for the realization of project objective. Yet, control
of projects in practice tends to be ineffective. Why? There seems to be three
reasons for poor control of projects.
FMS@BHU Page 4
Coordination and communication problem multiply when several org.
are involved in the project.
(Reff.-Projects by Prasanna
Chandra)
People problems
One of the factors which inhibit effective control is the poor quality of control
and information system. Some of the weaknesses observed in the control and
the information system are:
Unreliable information
FMS@BHU Page 5
One of the major problems in project control is unreliable and inaccurate data
and information. Often project managers receive reports which suggest that
“everything is okay” when the reality is otherwise. Further, for months after
the project is completed, cost dribble in to change a favorable variance into
an unfavorable one or to aggravate an unfavorable variance.
Reff-projects by Prasanna
Chandra
Cost - Calculated from the time variable. Cost to develop an internal project
is time multiplied by the cost of the team members involved. When hiring an
independent consultant for a project, cost will typically be determined by the
consultant or firm's hourly rate multiplied by an estimated time to complete.
Quality - The amount of time put into individual tasks determines the overall
quality of the project. Some tasks may require a given amount of time to
complete adequately, but given more time could be completed exceptionally.
Over the course of a large project, quality can have a significant impact on
time and cost (or vice versa).
FMS@BHU Page 6
Scope - Requirements specified for the end result. The overall definition of
what the project is supposed to accomplish, and a specific description of
what the end result should be or accomplish.
To keep control over the project from the beginning of the project all the way
to its natural conclusion, a project manager uses a number of techniques:
project planning, earned value, risk management, scheduling and process
improvement.
Has the cost of the project as a whole been as per budget estimates, less
than the budget estimates?
What is the trend of per formation? What would be the likely final cost and
completion date for the project and its individual parts?
Method analysis
FMS@BHU Page 7
For analyzing the performance at cost account and higher levels of the work
breakdown structure, we employee a method of analysis which takes into
account the value of work that has been done. In the traditional method of
analysis, the project manager measured the actual Progress against the
predetermined schedule and the actual cost against the budget estimate.
Performance analysis sees to remove this subjectivity by employing an
analytical frame work based on the following terms.
(Reff-Projects by Prasanna
Chandra)
FMS@BHU Page 8
Steps in CPM Project Planning
1. Specify the individual activities.
2. Determine the sequence of those activities.
3. Draw a network diagram.
4. Estimate the completion time for each activity.
5. Identify the critical path (longest path through the network)
6. Update the CPM diagram as the project progresses.
1. Specify the individual activities
All the activities in the project are listed. This list can be used as the basis for
adding sequence and duration information in later steps.
2. Determine the sequence of the activities
Some activities are dependent on the completion of other activities. A list of
the immediate predecessors of each activity is useful for constructing the
CPM network diagram.
3. Draw the Network Diagram
Once the activities and their sequences have been defined, the CPM diagram
can be drawn. CPM originally was developed as an activity on node network.
4. Estimate activity completion time
The time required to complete each activity can be estimated using past
experience. CPM does not take into account variation in the completion time.
5. Identify the Critical Path
The critical path is the longest-duration path through the network. The
significance of the critical path is that the activities that lie on it cannot be
delayed without delaying the project. Because of its impact on the entire
project, critical path analysis is an important aspect of project planning.
The critical path can be identified by determining the following four
parameters for each activity:
ES - Earliest start time: the earliest time at which the activity can start
given that its precedent activities must be completed first.
EF - Earliest finish time, equal to the earliest start time for the activity
plus the time required to complete the activity.
LF - Latest finish time: the latest time at which the activity can be
completed without delaying the project.
LS - Latest start time, equal to the latest finish time minus the time
required to complete the activity.
The slack time for an activity is the time between its earliest and latest start
time, or between its earliest and latest finish time. Slack is the amount of
time that an activity can be delayed past its earliest start or earliest finish
without delaying the project.
The critical path is the path through the project network in which none of the
activities have slack, that is, the path for which ES=LS and EF=LF for all
activities in the path. A delay in the critical path delays the project. Similarly,
FMS@BHU Page 9
to accelerate the project it is necessary to reduce the total time required for
the activities in the critical path.
CPM Benefits
Provides a graphical view of the project.
Predicts the time required to complete the project.
Shows which activities are critical to maintaining the schedule and
which are not.
CPM Limitations
While CPM is easy to understand and use, it does not consider the time
variations that can have a great impact on the completion time of a complex
project. CPM was developed for complex but fairly routine projects with
minimum uncertainty in the project completion times. For less routine
projects there is more uncertainty in the completion times, and this
uncertainty limits its usefulness.
PERT
The Program Evaluation and Review Technique (PERT) is a network model
that allows for randomness in activity completion times. PERT was developed
in the late 1950's for the U.S. Navy's Polaris project having thousands of
contractors. It has the potential to reduce both the time and cost required to
complete a project.
FMS@BHU Page 10
The activities are the tasks required to complete the project. The milestones
are the events marking the beginning and end of one or more activities.
FMS@BHU Page 11
If the critical path is not immediately obvious, it may be helpful to determine
the following four quantities for each activity:
These times are calculated using the expected time for the relevant
activities. The ES and EF of each activity are determined by working forward
through the network and determining the earliest time at which an activity
can start and finish considering its predecessor activities.The latest start and
finish times are the latest times that an activity can start and finish without
delaying the project. LS and LF are found by working backward through the
network. The difference in the latest and earliest finish of each activity is that
activity's slack. The critical path then is the path through the network in
which none of the activities have slack.
Benefits of PERT
Limitations of PERT
FMS@BHU Page 12
The following are some of PERT's limitations:
• The activity time estimates are somewhat subjective and depend on
judgment. In cases where there is little experience in performing an activity,
the numbers may be only a guess. In other cases, if the person or group
performing the activity estimates the time there may be bias in the estimate.
Reff: www.wikkipedia.com
FMS@BHU Page 13