Pricing Contractor Delay Costs Construction
Pricing Contractor Delay Costs Construction
Pricing Contractor Delay Costs Construction
Introduction
Virtually all construction contracts provide for changes to the Time of Performance of the work
of the contract. Each contract provides for a number of types of delay which may or may not
qualify for a time extension. Some of these delay types provide for time only whereas others
1
The opinions and information provided herein are provided with the understanding that the opinions and
information are general in nature, do not relate to any specific project or matter and do not necessarily reflect the
official policy or position of Navigant Consulting, Inc. Because each project and matter is unique and professionals
can differ in their opinions, the information presented herein should not be construed as being relevant or true for
any individual project or matter. Navigant Consulting, Inc. makes no representations or warranties, expressed or
implied, and is not responsible for the readers use of, or reliance upon, this paper, nor any decisions made based on
this paper.
2
Executive Director, Navigant Construction Disputes Forum, the industrys resource for thought leadership and best
practices on avoidance and resolution of construction project disputes globally, based in Irvine, CA.
3
Managing Director, West Coast Practice Area Leader in Navigant Consultings Global Construction Practice,
located in San Francisco, CA.
Page 1
mandate both a time extension was well as compensation to the contractor for delay damages.
When compensable delay arises, contractors look to the owner to compensate them for their
delay damages. There are, generally, two types of delay damages direct and indirect. Direct
delay damages include such costs as idled and extended labor and equipment costs, extended
storage costs, extended bond costs, material inflation costs, etc. Indirect delay costs include loss
of efficiency, extended or unabsorbed home office overhead costs and extended field office
overhead costs. Provided that the contractor has maintained reasonably good cost records during
the performance of the work, proving the direct delay costs should not be a monumental task.
Demonstrating their extended home office overhead, likewise, is not all that difficult once the
duration of the delay has been calculated as home office overhead recovery is generally done on
a formulaic basis; the Eichleay Formula in the U.S. and the Emden or Hudsons Formula in
Canada and the U.K., for example. Proving loss of efficiency is more difficult and is beyond the
scope of this paper.
This paper focuses on recovery of a contractors extended field office overhead. Proving
extended field office overhead costs used to be a relatively straight forward calculation. The
contractor would sum up the total field office overhead costs expended on the project, divide by
the number of days spent on the project and multiply times the number of days of compensable
delay documented through forensic schedule analysis. It was simple and straight forward. It
was, however, not always simple to recover such delay costs. Between 1942 and 1968
contractors on U.S. government contracts could not recover delay costs for government caused
delay to the work arising from changed work. This rule was known as the Rice Doctrine which
arose from a U.S. Supreme Court case, United States v. Rice.4 During this period a contractor
could only recover time but no delay damages.5
In 1968 this inequity was remedied by a rewording of the Changes clause mandated by the
Federal Acquisition Regulations (FAR).6 By insertion of only a few words the Federal
agencies drafting committees removed the ambiguous language the Supreme Court based their
ruling on and effectively reversed the Rice Doctrine.7 Contractors could now recover delay costs
for government caused delay. However, starting in the 1990s the Armed Services Board of
Contract Appeals, the U.S. Court of Appeals for the Federal Circuit and the U.S. Supreme Court
4
Page 2
began to shift back to the concept of limiting a contractors right to collect delay damages for
government caused delay.8 Courts now hold contractors to a higher standard of proof of
damages related to delay. Recent court decisions in the U.S. have required contractors prove
delay damages with actual costs.9 With this as a backdrop, this paper discusses eight potential
methods of calculating extended field office overhead costs.
Types of Delay
Most contracts deal specifically with three basic types of delay each type of delay yielding a
different recovery. The basic types of delay are the following.
Inexcusable Delay Inexcusable delay is delay caused by the contractor or any of their
subcontractors, suppliers or materialmen, at any tier. Examples of this type of delay are
failure to provide sufficient labor or late delivery of equipment or materials. As this is
self-imposed delay the contractor is typically entitled to recover no time and no delay
costs. Under most contracts, the contractor is exposed to potential liquidated damages or
may be directed to accelerate their work, at their own expense, to recover the lost time.
Excusable Delay Excusable delay is typically third party caused or a force majeure
delay. In essence, this is the type of delay which was not foreseeable, not under the
control of, nor caused by either the owner or the contractor or any party for whom they
are responsible, at any tier. Examples of this type of delay include abnormally severe
weather, earthquakes, tsunamis, labor actions or acts of terrorism. Under most contracts,
as neither the contractor nor the owner caused the delay, the contractor is entitled to
recover the time but no delay costs, while the owner is required to grant an extension of
time and forego late completion damages for this period of time.
Compensable Delay Compensable delay is generally described as owner caused delay
but also includes delay caused by events or circumstances for which the owner has
assumed liability under the terms of the contract. Examples of owner caused delay
include suspensions of work; delays caused by owner issued changes to the work or
8
Kelleher, Thomas J. Jr., Eric L. Nelson and Garrett E. Miller, The Resurrection of Rice? The Evolution (and DeEvolution) of the Ability of Contractors to Recover Delay Damages on Federal Government Construction Contracts,
Public Contract Law Journal, Winter, 2010, American Bar Association, Washington, D.C.
9
Lee, James M., Prove Your Damages with Actual Costs: The United States District Court for the District of New
Jersey Rejects Both the Cumulative Impact theory of Causation and the Total Cost Method to Prove Delay Damages
in a Tort Action, www.GibbonsLaw.com/news_publications/articles, 2011.
Page 3
See Josh M. Leavitt and Joseph C. Wylie, Recent Trends in Exceptions to Enforceability of No Damages for
Delay Clauses, Real Estate Law and Practice Course Handbook, Practising Law Institute, New York, 2005. See
also Carl S. Beattie, Apportioning the Risk of Delay in Construction Projects: A Proposed Alternative to the
Inadequate No Damages for Delay Clause, William and Mary Law Review, March, 2005.
11
Bruner, Philip L. and Patrick J. OConnor, Jr., Risks of Construction Time: Delay, Suspension, Acceleration and
Disruption, Bruner and OConnor on Construction Law, October, 2010.
12
Lankenau, Matthew James, Owner Caused Delay Field Overhead Damages, Cost Engineering, Vol. 45, No. 9,
September 2003.
Page 4
Page 5
Field Supervision
Project manager
Assistant project manager(s)
Project engineer(s)
Project scheduler(s)
Superintendent(s)
General foremen
Field office clerical
Document control personnel
Cost engineer(s) and/or timekeeper(s)
Payroll and social taxes
13
Construction Dictionary, 8th Edition, The National Association of Women in Construction, 1991.
Cost Accounting Standard 401 Consistency in Estimating, Accumulating and Reporting Costs, DCAA Contract
Audit Manual, DCAAM 7640.1, January 1997, Department of Defense Defense Contract Audit Agency,
Washington, D.C.
14
Page 6
Fringe benefits
Workers compensation insurance
Subsistence costs for travelers
Field Office Labor
Safety teams (e.g., safety engineer(s),
flaggers, cone and K-rail and
fence maintenance)
Security personnel
Site and street cleanup personnel
Survey and staking crews
Equipment maintenance personnel
Storage yard/laydown area personnel
Payroll and social taxes
Fringe benefits
Workers compensation insurance
Subsistence costs for travelers
Miscellaneous Field Office Costs
First aid, fall protection, hard hats, safety
glasses, etc.
Travel
Entertainment
Mobilization
Demobilization and final clean up
Scaffolding
Project insurance
Permits and licenses
Project legal costs
Small tools and consumables
There may be other costs included in project field office overhead accounts but all of the above
costs fit the general definition as they are costs incurred at the jobsite in support of just one
project and cannot be allocated to any specific pay item on the projects Schedule of Values.
Page 7
Page 8
project is complete. These accounts will have to be disaggregated to sort out the
purchase and/or installation cost from the operating costs.
Office furniture, copiers, scanners, fax machines and computer costs If these items are
purchased for the project then they too are non-time related costs and should be removed
from a delay calculation. However, the operating costs (such as paper, toner, printer ink
cartridges, etc.) are time related since the longer the field office is in operation the more
of these materials the project will consume.
Once the non-time related costs are removed the calculation of extended field office overhead
costs can begin in earnest. Experience with preparing or analyzing delay damage claims has
taught the authors that there are at least eight different methods of calculating extended field
office overhead costs. Each method is described below followed by a discussion of the apparent
strengths and issues related to each method.
Average Field Office Overhead Cost For The Project This is one of the more common
techniques used when calculating field office overhead costs. The contractor using this
technique adds up all field office overhead costs expended on the entire project. They should
then remove the non-time related portions of the field office overhead cost account as
discussed above. The contractor then divides the remaining time related costs by the
duration of the project to arrive at a daily field office cost. The contractor then multiplies this
daily rate by the number of days of compensable delay determined from their forensic
schedule analysis to determine the extended field office overhead costs owed as a result of
the owner caused delay.
Strength of Method This is a simple and straight forward cost engineering or cost
accounting exercise which does not typically require spending a lot of money on outside
legal counsel or forensic accountants. Ordinarily, this can be done by the onsite project staff.
Issues There are two general issues related to this method. First, this is an end of the job
calculation requiring the owner and the contractor to wait until the project is completed
because the total cost of the field office overhead and the total duration of the project are not
known until the project is completed. For owners and contractors striving to settle delay
claims as they arise on the project, this technique doesnt work. The second issue is that this
method calculates an average daily field office overhead rate, pricing each day on the
project the same as every other day. But, this is not accurate in the strict cost accounting
Page 9
sense. Field office overhead costs are typically like a bell shaped curve low at the outset of
the work, climbing fairly rapidly and leveling off at the high rate for a lengthy period of time,
later dropping off with a long but low tail off while the project is being closed out. But by
dividing the total field office cost expended by every day spent on the project an average cost
is created with each day costing the same as all others. If a delay occurs on the project
during one of the periods which are below the average cost line, the contractor may be
overcompensated when the average field office daily rate is applied. Conversely, if the delay
occurs when the field office cost is above the average cost line, the contractor may be
undercompensated.
Example 1 Average Total Project Field Office Overhead Cost/Month
Average Field Office Overhead Cost For The Period Of The Delay This method is
employed when owners and contractors are attempting to resolve delay issues as they arise
on the project. This method is not an end of the project method. Instead, this method is a
contemporaneous field office overhead rate calculation that determines the field office
overhead rate only during the period of the delay. The method starts with the forensic
Page 10
schedule analysis. This analysis identifies the total amount of compensable delay owed and,
more specifically, identifies the start and completion dates of the delay. Once these dates are
known the cost engineer or cost accountant will determine what period(s) the delay fell in.
For example, if the delay started on January 13, 2011 and ended on March 22, 2011 the
periods for calculating the field office overhead would be January, February and March
2011. The contractor then sums up the total amount of field office overhead cost incurred in
this three month period and divides by the total number of days during this period.
Assuming each accounting period starts on the first of the month and ends on the last day of
the month, this period equals 89 calendar days. The contractor divides the field office cost
for this three month period by 89 days to derive a daily rate. The contractor then multiplies
the daily rate by 68 days (the number of days of delay identified earlier by the forensic
schedule analysis) to determine the delay damage owed.
Strength of Method The strengths of the method are twofold. First, this method can be used
at any time during the project thus allowing the contractor and the owner to resolve delay
claims as they arise. Second, this method avoids the issue of over or under compensation
common to the average project cost method discussed above.
Issues The issues related to this method lie in the difference between the actual delay
period (in this case the 68 days between January 13 and March 22, 2011) and the time
extension period (68 days added to the end of the project). That is, the project is delayed 68
days in the early part of 2011. But the extended period of time will take place for 68 days at
the end of the project which may be September of 2013. If the cost during the delay period
was very high but the field office overhead cost at the end of the project is very low, some
argue that the contractor is being over compensated. (See Example 2 below.) Conversely, if
the delay period occurred when the field office cost was very low and the extended period
takes place when the field office cost is very high, contractors will surely argue that they are
being under compensated. (See Example 3 below.)
Page 11
Original
completion date
Actual
completion date
Delay
Event
Time
Extension
Original
completion date
Actual
completion date
Delay
Event
Navigant Consulting, Inc. - 2011
Time
Extension
Page 12
Page 13
1. Prove that the self-imposed events the contractor has admitted to are the only selfimposed impacts on the project;
2. Calculate the damages to be deducted from the total cost calculation and prove that
these damages are a fair and reasonable cost to be deducted.
Jury Verdict Methods
A jury verdict requires that the arbitration panel or court arrive at a reasonable equitable
adjustment after receiving sufficient evidence to reach such a decision. This method may be
used where
1. There is clear proof of injury;
2. There is no more reliable method for computing damages;
3. And, the evidence presented is sufficient for the court or arbitration panel to make a
fair and reasonable approximation of the damages.16
A contractor seeking a jury verdict award for delay damages, as the claimant, is required to
present a calculation of the damages to the court or the panel in order from them to reach a
decision as to how much is owed. One method for calculating field office overhead and seeking
a jury verdict decision is set forth below.
Comparative Field Office Overhead Cost Method In situations where the contractor
cannot prove the delay damages (extended field office overhead) by an actual damage
method, it may be possible to present a comparison of the field office overhead cost incurred
on this project with the field office overhead cost incurred on another, very similar project.
The contractor, as claimant, bears the burden of proving that the projects are, in fact, similar
in scope, cost, duration, location and time. If the contractor can demonstrate this then they
may be able to compare the difference in cost incurred on each and use the calculated cost
difference as the measure of damages.
Strength of Method Once the similarity of projects is demonstrated, the calculation of the
delay damages is simple.
16
1 Construction Contracts Deskbook 6.3, Contractors Rights and Responsibilities as a Result of Delays
Contractors Right to Recover for Excusable Delay, May, 2010.
Page 14
Issues It appears that proving the similarity of the projects is the biggest problem facing a
contractor seeking to use this method. There are so many variables with every construction
project (other than, perhaps, track housing) that to argue that any two projects are virtually
identical will be difficult at best.
Stipulated Contract Methods
There are various methods to calculate field office overhead that may be included in the contract
documents prior to bidding. By including a specific method in the contract documents the owner
has mandated the method to be used to calculate extended field office overhead costs in the event
of an owner caused delay.
As-Bid Field Office Overhead Rate The California Department of Transportation
(Caltrans) has employed a unique mechanism on some of their larger projects (the San
Francisco Oakland Bay Bridge replacement project, for example). They use a Time
Related Overhead (TRO) bid item and specification to implement the approach.17 One of
the line items in the Caltrans bid form requires the contractor to fill in their daily time related
cost and multiply this daily rate times the number of working days in the Time of
Performance clause.18 The cost is stipulated to include both the field office overhead costs as
well as the home office overhead cost.19 The contractor is paid monthly as the project
progresses based upon the number of work days consumed each month. If delays arise
during the performance of the work, the TRO number is used to price the delay once
agreement is reached on delay causation and liability. The TRO number is only subject to
unit price adjustment if delay exceeds 149% of the original number of work days stipulated
in the contract.
Strength of Method This specification avoids the need for an audit concerning delay costs
and makes settlement of delay claims easier both during and at the end of the project.
Further, Caltrans has tied this requirement to their Escrow Bid Documents requirement such
that the work sheets used to calculate and bid the daily delay costs are preserved in a secure
17
Caltrans Program Procedure Bulletin CPB 00-8, Contract Administration - Time-Related Overhead (TRO),
December 15, 2000.
18
California Department of Transportation contracts are all work day contracts. Should an owner want to employ
this method but stay with a calendar day contract they need only change the wording of the specification to calendar
days.
19
An owner can choose to use the same procedure or modify it to include only the field office overhead cost.
Page 15
neutral location for examination in the event the owner has a need to review the calculation
in order to settle a delay claim.
Issues The only perceived issue with this method is that there is nothing to prevent a
contractor from unbalancing their bid and making their daily delay cost artificially high,
counting on the owner to cause a lot of delay on the project. If this happens, the TRO
specification would prevent the owner from modifying the daily rate until the total delay
exceeds 149% of the original number of days stipulated in the contract documents.
Specified Mark Up Rates Stipulated In The Contract Documents Owners may include a
fixed markup rate in the contract documents which specifically covers field office overhead
rates. Should an owner decide to do this, they will have to specify clearly in the contract
documents that this fixed rate includes extended field office overhead costs and/or
unabsorbed or extended home office overhead costs. In the U.S. the General Services
Administration, the Veterans Administration and the U.S. Postal Service have all adopted
contractually fixed overhead rates which have, to date, withstood court challenges.20 To see
the Veterans Administration overhead limitation clause see FAR 8-7.650-21, Contract
Changes.21 The General Services Administration overhead limitation clause may be found at
FAR 552.243-71, Equitable Adjustments.22 Numerous State highway agencies and
professional associations in the U.S. also specify change order markups that include field
office overhead costs. The table below summarizes 8 State agencies, 2 regional
transportation agencies and 3 professional associations.23
Organization
Alabama
Georgia
Kentucky
Mississippi
Labor
20%
15%
25%
15%
20
Santa Fe Engineers v. United States, 801 F.2d 379 (C.A.F.C. 1986); West Land Builders, VABCA 1664, 83-1
B.C.A. 16325.
21
34 FR 15470, October 4, 1969, as amended at 38 FR 5478, March 1, 1973; 39 FR 13263, April 12, 1974; 41 FR
48519, November 4, 1976; 45 FR 15930, March 12, 1980.
22
48 CFR 552.243-71.
23
Saunders, Herbert, Survey of Change Order Markups, Practice Periodical on Structural Design and Construction,
American Society of Civil Engineers, February, 1996.
Page 16
15%
15%
15%
15%
10%
0%
0%
0%
0%
10%
1 10%
0%
0%
0%
5%
5%
5%
--
15%
15%
15%
0%
0%
15%
5%
5%
5%
Strength of Method The apparent strength of this method is its simplicity. Once the cost
elements of a change order have been agreed to between the owner and the contractor the
fixed markup rates from the contract are applied appropriately. No negotiations, no audits
are required.
Issues The method requires the owner to determine what changed costs they are willing to
mark up and then they must determine what the markup percentages are reasonable.
Additionally, the owner must craft the contract very carefully, with the assistance of
experienced legal counsel, to the effect that these markup rates include field office overhead
costs of any type. In order to make certain this contract requirement is enforceable the owner
may need to include a No Damages for Delay or a Limitation on Delay Damages clause in
order to make the method legally enforceable.
Activity Specific Field Office Overhead Allocation Process (ASAP Method) Each of the
methods present above calculate extended field office overhead at the project level and then
24
North Carolina provides a fixed 35% of labor cost for overhead, benefits and profit. Insurance and taxes are paid
at actual cost plus an additional 6% markup for administration.
25
Virginia allows 45% of labor cost for labor overhead, benefits and profit. A tax and insurance allowance of 25%
is paid separately.
26
AASHTO American Association of State Highway and Transportation Officials.
27
EJCDC Engineers Joint Contract Documents Committee.
28
CMAA Construction Management Association of America.
Page 17
allocate it to a daily, weekly or monthly cost. A theoretical alternative to these methods has
been identified at the Activity Specific Field Office Overhead Allocation Process Method.29
This method differs in approach, in that the time related overhead is allocated to each on site
activity in accordance with the activitys
Labor hours
Labor costs
Direct costs, or
Whatever cost driver the owner and contractor agree upon.
If compensable delay arises, an analysis of which activities were delayed and for how long is
performed. Field office cost is then allocated to each impacted activity in accordance with
the following formula.
Time Related Field Office Overhead for Activity i = Time Related Field Office Overhead x Cost Driver for Activity i
Cost Driver Value of Project
Strength of Method One obvious benefit of this method is that it can be applied both
prospectively and retroactively. That is, should the owner want to use this method to settle
change orders and delays as they arise, the can write a specification requiring that the
contractor has to calculate this cost for each on site activity on the basis of whatever cost
driver the owner wants to use, within 30 days after award of the contract and prior to
receiving a Notice to Proceed. Once this submittal is made, reviewed and approved, it would
be used for all future compensable delays.
Issues First, implementing this method may be difficult. While the contractor should be
able to perform such a calculation and submit it, the owner during review will have to agree
that each activitys proposed labor hours (if that is the cost driver the owner specifies for use)
are reasonable. This will be difficult for most owners to do. Second, while this method may
work for delays to base scope work, it adds an additional dimension of difficulty when
negotiating changes which add work not contained in the original scope of work.
29
Ibbs, William and Long D. Nguyen, Analysis of Delay Damages for Site Overhead, Cost Engineering, Vol. 50,
No. 3, March, 2008. The method is considered theoretical by the authors. In a recent exchange of e-mail between
the authors of this article and Dr. Ibbs and Mr. Nguyen it was learned that no project to date has employed this
method.
Page 18
Owen L. Schwam Construction Co., Inc., ASBCA No. 22407, 79-2 BCA 13919.
Bramble, Barry B. and Michael T. Callahan, Construction Delay Claims, 3rd Edition, Aspen Publishers, New
York, 2000.
31
Page 19
1. Whether the delay was of a reasonably known length to allow for planning for mitigation
activities;
2. Whether the contractor has other ongoing projects that could use the resources impacted
by the delay effectively;
3. What costs would be incurred by the contractor in redeploying these resources;
4. Would it be possible to partially or totally demobilize the project for the period of the
delay;
5. How would subcontractors and suppliers be affected by the delay;
6. How can the impact of the delay on the subcontractors and suppliers best be managed;
7. Can the remaining non-delayed work be resequenced to allow progress to be made on
other portions of the project; and,
8. What is the cost of demobilizing, remobilizing and/or resequencing the work?
Conclusion
Almost all projects encounter compensable delay at some point during the performance of the
work. Few contracts set forth any specific method for calculating the cost of a day of delay in
the contract documents. As has been discussed, there are at least eight different methods of
calculating extended field office overhead, a typical element of delay damages. It is
recommended that the owner, their design professionals and their legal counsel consider this
issue during the design period select a method and carefully craft and include the method in the
contract documents prior to bid.
Page 20