In this article, you will be knowing the general steps involved in any Conversion/Data Migration of Oracle Projects module.
Stages in Oracle Projects Conversion
How to setup the Oracle Projects module for the conversion/Data Migration
Options for the Load (Flat file, csv, or Direct Load)
Oracle Projects AMG APIs needed to perform the Data Conversion
Testing the Conversion Process
AGIS (1)
Alerts (1)
AOL (7)
Now the question arises: What data to migrate from the legacy system to Oracle Projects?. Well, it depends upon the type
Concurrent Program (3)
of projects.
If the Projects are used for Internal Administration and tracking of costs, you may want to migrate the existing projects, tasks(the
work break down structure), Cost Budgets, Cost (Timecards, Employee Expenses, Miscellaneous Expenses) etc.
Discoverer (3)
FAQs (1)
If the Projects are used for billing the Clients for the work done (Typical Contract Projects), then you may want to Revenue,
Agreements(Contracts), Revenue budgets and Invoices in addition to the above data.
Flexfields (1)
Once the decision is made to which data to migrate, then the next step would be setting up the Oracle Projects for the
FNDLOAD (1)
conversion purpose, which we will see in detail sooner. Once the System has been setup, the technical elements(programs,
concurrent processes etc) have to be created in order to migrate the data from Legacy System to Oracle Projects.
Stages in Oracle Projects Conversion:
Forms (31)
Forms FAQs (2)
General (2)
1. The First Stage is to obtain the data from the Legacy System which needs to be migrated to Oracle Projects.
2. The Second Stage will be most crucial step in the process which is to massage the data according to the Oracle Projects
Conversion Interface(Programs built using AMG APIs). This Step is indeed time consuming, manual labor intensive to massage
and rectify the errors etc. But completing this step successfully pays dividends in the consecutive processes / Stages.
iExpenses (5)
3. The Third Stage is uploading the data obtained from legacy systems into the Staging Area(Staging Tables created to hold
Messages (1)
the data temporarily till it gets migrated into Oracle Projects). Once the data is uploaded to the Staging tables, the programs
built for migration(We will see how to build these programs in detail) will validate the Staging Table data to confirm that it is in
compliance with the Projects Conversion Program( The AMG APIs used in the programs indeed needs data in certain format,
also the data should be validated against the Oracle Projects Setup. For instance, when migrating the cost or hours from legacy
to Projects, we might need to validate if the expenditure type is already setup in Oracle Projects, if the expenditure type is not
setup, the program/APIs will throw an error. So it is always better to capture these kind of scenarios in the Validation Step of the
Migration.
4. The Fourth Stage is the actual migration process which will migrate the data from the Staging Tables to the Oracle Projects
Base tables. Once this step is done, the projects, tasks and other data are available in Oracle Projects for use.
OA Framework (6)
OA Framework FAQs (1)
OBIEE (1)
Oracle BoM (3)
Oracle Inventory (6)
Before going through the stages, we will look at some of the basic setups that needs to be done in Oracle Projects.
Oracle Order Management (9)
Oracle Projects Setup For Conversion
Oracle Projects (5)
Product Code:
Oracle Purchasing (4)
The Product Code needs to be setup in Oracle Projects in the AMG Gateway Source Products Form in the Oracle
Projects Implementation Super User Responsibility. This setup is mandatory since this product code needs to be
passed when using the Oracle Projects AMG APIs.
Project Types and Project Templates:
The project types and project templates for conversion projects need to be setup up. This is a mandatory setup since
while migrating projects we need to tell the APIs which project template/type the projects use.
For Contract Projects, setup the Contract Project Type Template. For administrative or internal projects, setup the
Indirect Project Type templates.
If you are migrating Cost and Revenue Budgets, then the Plan Types need to be attached to the templates in order
1 of 5
Receivables (7)
23/05/2015 11:59 PM
Steps for Conversion of Oracle Projects Data into Oracle EBS | Oracle...
http://ebscircle.com/steps-for-conversion-of-oracle-projects-data-into-...
Project Numbering: This implementation option is by default set to Automatic which means when creating projects
Reports (16)
in Oracle Projects, the project number is automatically derived and users are not required to provide any project
SQL*Loader (2)
numbers. This option is best suitable when creating projects in Oracle Projects. But when migrating the projects from
the third party systems, there is an option to migrate the projects with the same project number as in the legacy
system. This is not mandatory but is recommended since it will be easy to refer back the projects in the source
SQL-PL/SQL (69)
System Administrator (1)
The Transaction Source needs to be setup in Oracle Projects in the Transaction Sources form in Oracle Projects
Valuesets (1)
Implementation Super User Responsibility. This is a mandatory setup for the Costs/hours migration from the legacy
system to Oracle Projects. We need to tell the migration APIs what is the source system and how the data is
But if you are migrating the costs directly from the legacy instead of hours then this step is not needed. But ideally
the cost rates are required in a general production scenario wherein the employees/contractors enter their
timecards.
You can setup job rate schedule, employee level rate schedule or employee level overrides. Alternatively, the costing
client extension can be setup to calculate the cost according to the business scenario.
*Refer to the Oracle Projects User Guide for how to setup the employee cost rates.
First Stage: Obtain Data from Legacy System
The first stage deals with obtaining the data from the legacy system in the desired format. The data can be obtained in the form
of flat text file or comma separated file csv, tab delimited file or file with any delimiters. Generally tab delimited files are
recommended since comma separated files behave strange when there is a comma in the data itself.
FAQs
If there is a database link created between the Source Legacy database and the Oracle Projects Database then the data can be
obtained directly using the select statements against the Source DB from within the Oracle Projects DB. But this method is not
SQL Functions
preferred as it is more performance intensive when it comes to selecting large data over the network.
For Projects Migration, generally 2 files are obtained. One file for Projects Data and the other file for Tasks Data.
For Transaction Migration, single file is enough with all the cost/hours data.
For Cost/Revenue Budget migration, single file is enough with all the Budgets Data.
Create SQL Loader concurrent program which will upload the obtained data into the Oracle Staging Tables.
Also it is always the best practice to create a control table in the Staging area, which will control the data migration. For example
your control table might look like the one below:
Parameter Type
Parameter
Parameter Value
Template
Template
Expenditure Type
Expenditure Type
Transaction
Product Code
Project
Project
Cost Budget
Revenue Budget
Contract
Indirect
Hours
Expenses
Transaction Source
Product code
Publish Workplan
Baseline Workplan
Baseline
Baseline
Contract_Template
Indirect_Template
Labor
Employee_Expense
Legacy1
LEGACY1
Yes
Yes
Yes
Yes
R12
R12
SQL
Suppliers WFLOAD
Workflow
This control table is looked upon by the migration program. So whenever there is a change in the templates, expenditure types
it is easy to change this control table instead of the code. So the advise is never hard code any values in the code, always
handle it using the control table.
Also it will be better to have a form based on this table, so that this table data can be changed from the front end.
Second Stage & Third Stage: Validate and Format the Data
Iam coupling the second and third stage because both are interdependent. Validating data is very important and it prevents
some of the time consuming tasks in actual migration such as trouble shooting the errors due to the invalid data.
Below are some of the key validations that need to be done before doing the actual migration.
Projects/Tasks Migration:
Though the projects and tasks are in different staging tables, the migration of projects/tasks are doing using a single program.
We can always migrate projects and tasks separately, but the issue is with the performance when adding task by task to each
project. So it always better to create projects and tasks together because of the bulk loading of tasks.
2 of 5
23/05/2015 11:59 PM
Steps for Conversion of Oracle Projects Data into Oracle EBS | Oracle...
http://ebscircle.com/steps-for-conversion-of-oracle-projects-data-into-...
Validateif the project name is unique. Project with the same name should not exist in Oracle Projects.
Validate if the project number is unique. Project with the same number should not exist in Oracle Projects.
Validate if the project long name is unique. Project with the same long name should not exist in Oracle.
Validate the project reference(this field is mandatory in the projects file, it can be the projects identifier of the source project or
project number of the source project, but it has to be unique in the source system as well. This field needs to be populated in all
the converted projects in order to track back and identify the project in the source system)
Project name and project number should be 30 chars in length. Project long name should be 240 chars in length. Project
Description should be 250 chars in length. Project description is not a mandatory field when creating project.
Check if the project has a project manager and the project manager is active in Oracle HR and has an assignment and a Job
assigned. Also the project manager has to be active from the project start date, else you cannot create a project with that
project manager.
In case of contract projects, check if the customer of the project is a valid customer defined and with a valid Bill To site
assigned.
Check if the Tasks in the Task file has a project in the Projects file.
Apart from the above necessary validations, you may have to validate the additional data such as Projects DFF Data you may
want to populate with your custom field values. For example you may want to populate the Project cost center value in the
Segment1 of the Project DFF. In such case you have to validate if the cost center value is a valid value for that
Segment1(sometimes you may have attached an LOV to that segment1, so in that case, the cost center has to be validated
against that LOV Values).
For tasks, values for task types, work type, task manager has to be validated. Task types and work types have to be defined in
Oracle Projects before the task with those values are migrated, else the task will not be created.
Cost/hours validation
Setup Validations:
Setup Validations:
Validate the project template has the required financial plan type attached. Financial plans are the project management
versions of the Budget types in the Forms applications.
Budget amount has to be greater than zero.
There is no need to create revenue budgets if the Baseline funding without budget option is checked at the project or project
type level. Whenever the funding is created for the contract project and is baselined, the revenue budget is automatically
created and baselined. If that option is not checked, it is necessary that a revenue budget with the same amount as the funding
amount needs to be created and baselined in order to baseline the funding.
Data Validations:
The cost budget for the project can be from the source systems budgeting system. If there is no budgeting in the source
system, a cost budget with the total cost of the project can be created in Oracle Projects.
For revenue budgets, it has to be equal to the funding amount of the project. If there is no funding amount in the source system,
the sum of the revenue amount can be the funding amount and it is the revenue budget amount as well.
Agreements and Funding Validation
Data Validations:
3 of 5
23/05/2015 11:59 PM
Steps for Conversion of Oracle Projects Data into Oracle EBS | Oracle...
http://ebscircle.com/steps-for-conversion-of-oracle-projects-data-into-...
Data Validations:
Once the data is validated, the program for conversion is executed to migrate the data into oracle projects base tables. There
might be still errors due to AMG APIs which has to analyzed and resolved. But the chances of such AMG API issues is just
below 10% in any migration(based on my experience in Oracle Projects Conversion).
Below is a table with Conversion and which AMG APIs are used for that conversion:
Conversion
AMG APIs
Projects/Tasks Conversion
Budgets Conversion
PA_PROJECT_PUB.CREATE_PROJECT
PA_BUDGET_PU B.CREATE_DRAFT_BUDGET,
PA_BUDGET_PUB.BASELINE_BUDGET
PA_AGREEMENT_PUB.CREATE_AGREEMENT
PA_AGREEMENT_PUB.ADD_FUNDING
PA_EVENT_PUB.CREATE_BILLING_EVENT
PA_PROJECT_PUB.LOAD_EXTENSIBLE_ATTRIBUTE
Agreements
Funding
Revenue/Invoice
User Defined Attributes (UDA)
For Transactions(cost/hours) migration, there is no APIs to create the expenditures in Oracle. The pa_transaction_interface_all
table needs to be populated with the migration data and once it is populated, the PRC:Transaction Import process with the
Transaction source as parameter needs to be run in Oracle Projects. All invalid records needto be rectified in order to migrate
all the transactions.
The rejected records can be found in the same interface table with the transfer_status_code as R.
Conversion Tips:
Make sure the templates are defined properly and exactly the way it is needed. Once the projects are created using the
templates and the template was wrongly defined, then it takes ages to rectify the converted projects.
Create the conversion program to operate in two modes: Validate, Run. A concurrent process with a parameter called mode
accepting Validate/Run can be created. So the same concurrent program can be used to validate as well as run the actual
migration.
It is a good practice to have source Project id / Project Number as parameter to the projects conversion program. This will
allow us to test the conversion for a single project and validate the data for that project.
The validation process can write the invalid records to the output file. So once validation process completes, the output will
have all the invalid records which needs to be rectified.
Create a separate concurrent program to know the status of the already running migration process. If you want to know where
the migration process is in terms of the number of records migrated, number of records rejected etc. If the volume of the
migration data is huge, then it is likely possible that the conversion programs may run for hours. So in this scenarios this
concurrent program can be helpful in finding the status of that migration process.
For Transactions migration, the custom program written to populate the interface table can kick off the PRC:Transaction
Import process and wait for its completion. Once the transaction import completes, the custom process can print the invalid
records from the interface table to the output file.
There are APIs to publish and baseline the workplans created as a part of projects migration. But these APIs need to be used
with care. There are lot of performance issues and bugs when using these APIs.
Tweet
4 of 5
Like
Share
Mailto
23/05/2015 11:59 PM
Steps for Conversion of Oracle Projects Data into Oracle EBS | Oracle...
0 Comments
http://ebscircle.com/steps-for-conversion-of-oracle-projects-data-into-...
Home
5 of 5
About us
Training
Contact Us
23/05/2015 11:59 PM