Geotechnical Report Draft
Geotechnical Report Draft
REPORT OF
GEOTECHNICAL EXPLORATION
NARBERTH COMMUNITY BUILDING TERRACE ADDITION
80 WINDSOR AVENUE
NARBERTH BOROUGH, MONTGOMERY COUNTY, PA
PREPARED FOR
BOROUGH OF NARBERTH
c/o CIRILLI ASSOCIATES
1489 BALTIMORE PIKE
SUITE 228
SPRINGFIELD, PA 19064
PROJECT 4545G1R1
April 7, 2015
____________________________
Mr. Brian D. McCree, PE
Vice President
__________________________
Matthew T. Uhrig, EIT
Geotechnical Engineer
TABLE OF CONTENTS
PAGE
EXECUTIVE SUMMARY
1. INTRODUCTION
2. PROPOSED CONSTRUCTION
3. GEOTECHNICAL EXPLORATION
4. GEOTECHNICAL BACKGROUND
4.2 GEOLOGY
4.3 SOILS
5. LABORATORY TESTING
6. SUBSURFACE CONDITIONS
10
12
13
14
15
16
16
17
8. QUALITY CONTROL
18
9. LIMITATIONS
19
APPENDIX
SOIL PARTICLE SIZE ANALYSIS RESULTS
SOIL PLASTIC AND LIQUID LIMIT TEST RESULTS
TEST BORING LOGS
BORING LOCATION PLAN
EXECUTIVE SUMMARY
Purpose
This exploration was completed to evaluate the subsurface conditions and their
effect upon the proposed site development. This exploration focused on the proposed
terrace addition to the existing Narberth Community Building located at 80 Windsor
Avenue in Narberth Borough, Montgomery County, PA.
Scope
A total of five (5) borings were completed at the subject site. The proposed borings
were drilled within the proposed terrace addition area to a maximum depth of 20
feet or auger refusal on schist bedrock. The test borings were located in the field by
DBA personnel using the Terrace Plan prepared by Brawer & Hauptman Architects
numbered A1 dated 02/28/2013.
Site design was underway during the
implementation of our exploration. Therefore, final site design may vary from the
preliminary design used to complete this exploration. A copy of the site plan used
for our exploration which has been annotated with our test boring locations is
included in the appendix of this report.
Findings
Preliminary finding include the following:
The results of our exploration indicate the presence of existing fill material (Stratum
IF) across the addition footprints to depths ranging from 4.3 feet to 8.8 feet below
existing grade. This existing fill material is considered to vary from loose to
moderately dense and consists of brown and orange brown fine sand and silt with
quartz and schist fragments and occasional roots. A 0.58 to 2.92 feet thick layer of
brown and gray organic silt (Stratum I) was encountered below this fill material.
Laboratory analysis of this material indicates an organic content (by weight) ranging
from 1.93% to 5.20%. Dense weathered rock (DWR), as determined by SPR data and
auger difficulty was encountered predominately at the north and west portions of
the site at depths ranging from 11 feet to 19 feet below existing grade in borings B1
through B3. Bedrock, as determined by auger refusal, was encountered in borings
B1 and B2 at depths of 13.8 feet and 16.3 feet below existing grade, respectively. See
Table IIA Approximate Rock and Fill Elevations for information regarding the
depths and relative elevations at which rock was encountered in each test boring
completed.
Groundwater was encountered in each test boring completed at depths ranging from
6.6 feet to 9.2 feet below existing grade. In general, the groundwater surface
elevation is shallowest at the southwest end of the site and becomes deeper in a
northern direction. See Table IIB Approximate Groundwater Elevations for depths
and elevations at which groundwater was encountered in each test boring.
Recommendations:
Comparing the existing topography with the proposed elevation of the proposed
terrace, an embankment of up to 4.2 feet of structural fill will be required to achieve
the proposed terrace elevation. Due to this fill placement and the variability in both
the content and strength of the existing fill material of Stratum IF, there is a risk of
settlement of the terrace slab. The complete removal and replacement of the existing
fill material of Stratum IF would resolve this problem. However this approach is
considered to be economically infeasible for a project of this size. Therefore, as an
alternative, DBA recommends the removal of 2 feet of the existing fill material.
After this material is removed, the exposed subgrade shall be densified in-place and
evaluated through a proofroll via a heavy (minimum 15-ton) smooth drum roller to
detect the presence of any soft conditions. Any soft conditions encountered shall be
repaired to the satisfaction of the Geotechnical Engineer. In order to minimize the
potential for differential settlement within the terrace footprint, a geosynthetic
reinforced rigid stone layer shall be installed on the exposed subgrade prior to fill
placement to construct the terrace embankment.
Our settlement analysis indicates that the total settlement of the terrace addition is
estimated to be on the order of 1 inch. Settlements of this magnitude are typically
considered to be within normal construction tolerances, the differential settlement
between the terrace and the existing Community Building may create a tripping
hazard. The partial soil exchange procedure will mitigate this condition to some
extent. In an effort to further reduce the total settlement of the proposed terrace,
the use of a lightweight fill alternative for the construction of the terrace
embankment can be considered. The use of this material in lieu of traditional fill
material would reduce the stress imposed on the loose underlying soils and
consequently reduce the magnitude of settlement. For additional information
regarding these alternatives, see Section 7.2 Soil Replacement.
1. INTRODUCTION
David Blackmore and Associates, Inc. (DBA) has completed the geotechnical
exploration of the subject site in accordance with our Proposal 4545G1P1, dated May
14, 2014.
conditions and their effect upon the proposed site development. Specifically, DBA
has provided recommendations regarding the following:
- Foundation support of the structure and slabs, including soil bearing
pressures, bearing elevations, foundation design recommendations and
anticipated settlement for shallow foundations,
- Depth to material requiring rock excavation methods for removal, if
encountered,
- Depth to and management of groundwater for design of structures and
pavements, if encountered
- Relative elevations of surface and subsurface features,
- Fill and compaction criteria,
- Pavements and floor slabs,
- Lateral earth pressures for retaining walls, and
- General geotechnical related construction procedures.
The following section (2. PROPOSED CONSTRUCTION) summarizes the
information available to DBA regarding the proposed site development. This report
has been prepared based on the proposed construction. Changes to the proposed
construction may require alterations to this report or additional investigative work.
DBA should be notified of significant changes to the proposed construction.
2. PROPOSED CONSTRUCTION
The proposed construction consists of a terrace to the existing Narberth
Community
Building,
including
steps,
railings,
lighting,
receptacles,
and
underground rainwater piping. The terrace is to cover a footprint area of +/- 2,000
square feet, spanning the west side of the existing structure and wrapping around
the southwest corner. The terrace will consist of slab on grade construction with a
finished elevation that will match the Community Building finished floor elevation.
3. GEOTECHNICAL EXPLORATION
A total of five (5) borings were completed at the subject site.
The proposed
borings were drilled within the proposed terrace addition area to a maximum depth
of 20 feet or auger refusal on schist bedrock.
The test borings were located in the field by DBA personnel using the Terrace
Plan prepared by Brawer & Hauptman Architects numbered A1 dated 02/28/2013.
The test borings were drilled by our subcontractor, The Corcoran Drilling
Company, under the direction of DBA personnel.
All test boring logs and a test boring location plan are included in the appendix
of this report.
4. GEOTECHNICAL BACKGROUND
4.1 SITE DESCRIPTION
The subject site is located at the west and south portions of the property of
the Narberth Community Building located at 80 Windsor Avenue in Narberth
Borough, Montgomery County, PA. These portions of the site consist of
landscaped lawn area with medium to large sized trees scattered throughout the
area. The southeast corner of the proposed terrace addition is located within an
existing paved parking/driveway area. At the time of preparing this report, there
was no topographic survey data available; therefore an elevation of 100 feet was
arbitrarily assigned to the finished floor of the existing Community Building in
order to provide more specific recommendations for the proposed construction.
The terrace elevation will match this finished floor elevation to provide access to
the terrace from the Community Building. Using the surface elevations of the
borings determined in the field, the low point of the site is 95.8 feet (relative to
the assigned finished floor elevation of 100 feet) at the southwest corner of the
site, at boring B3. The grade then gently slopes to the north and east to an
elevation of 96.5 feet at both boring B1 and B5.
5. LABORATORY TESTING
Representative soil samples taken during the field exploration were tested in
DBA's laboratory for basic engineering properties. The laboratory testing consisted
of classification of soil samples for engineering purposes. The laboratory testing
included Particle Size Analysis (ASTM D442), Plastic and Liquid Limits (ASTM
D4318), and Natural Moisture Content (ASTM D2216).
Classification System (USCS) was used to assign group symbols and group names to
the soils tested.
A summary of the test results is provided on Table I. A photocopy of the particle
size analysis results and the plastic and liquid limit analysis results are included in
the appendix of this report.
6. SUBSURFACE CONDITIONS
The results of the drilling program revealed a fairly consistent subsurface profile.
The following strata, beneath 4 to 6 of topsoil in landscaped lawn or 3 of asphalt
and 11 of modified stone in paved areas, can describe a typical soil profile.
Stratum IF:
Stratum I:
0.58 to 2.92 thick; Brown and gray organic silt with roots.
This stratum is considered to be relatively loose to loose
with SPR1 values ranging from 1 blow per foot (B/F) to 7
B/F. The average SPR value for this stratum is 5 B/F.
Laboratory testing of representative soil samples retrieved
from this stratum indicates organic contents (by weight)
ranging from 1.93% to 5.20%. This stratum was
encountered in each of the test borings completed.
Stratum II:
3.0 to 5.17 thick; Orange brown and gray mottled fine sand
with some silt, occasional rock fragments. This stratum is
considered to be loose to moderately dense with SPR values
ranging from 6 B/F to 17 B/F. The average SPR value is
1 SPR = is the Standard Penetration Resistance or number of blows required of a 140 pound hammer
dropping 30", to drive a 2" OD split spoon sampler one foot.
Bedrock:
The groundwater information provided is based on conditions encountered during the drilling
program. Seasonal fluctuations in the groundwater table are to be expected.
brown and gray mottled fine sand and silt with occasional schist fragments (Stratum
II) was encountered which transitions into gray, brown, and orange brown
weathered schist (Stratum III). Dense weathered rock (DWR), as determined by SPR
data and auger difficulty was encountered predominately at the north and west
portions of the site at depths ranging from 11 feet to 19 feet below existing grade in
borings B1 through B3. Bedrock, as determined by auger refusal, was encountered
in borings B1 and B2 at depths of 13.8 feet and 16.3 feet below existing grade,
respectively. See Table IIA Approximate Rock and Fill Elevations for information
regarding the depths and relative elevations at which rock was encountered in each
test boring completed.
Groundwater was encountered in each test boring completed at depths ranging
from 6.6 feet to 9.2 feet below existing grade. In general, the groundwater surface
elevation is shallowest at the southwest end of the site and becomes deeper in a
northern direction. See Table IIB Approximate Groundwater Elevations for depths
and elevations at which groundwater was encountered in each test boring.
Comparing the existing topography with the proposed elevation of the proposed
terrace, an embankment of up to 4.2 feet of structural fill will be required to achieve
the proposed terrace elevation. Due to this fill placement and the variability in both
the content and strength of the existing fill material of Stratum IF, there is a risk of
differential settlement of the terrace slab. In order eliminate this risk, the complete
removal and replacement of the existing fill material of Stratum IF and underlying
organic silt of Stratum I from beneath the proposed terrace addition and
replacement with structural fill would be required. However, the removal and
replacement alternative is considered to be economically infeasible for a project of
this size.
As an alternative to the complete removal of the existing fill within the proposed
terrace footprint, DBA recommends the removal of 2 feet of the existing fill material.
After this material is removed, the exposed subgrade shall be densified in-place and
evaluated through a proofroll via a heavy (minimum 15-ton) smooth drum roller to
detect the presence of any soft conditions. Due to the loose nature of the existing fill
material of Stratum IF, localized subgrade repair consisting of removal of unsuitable
material and replacement with structural fill shall be anticipated. In order to
minimize the potential differential settlement within the terrace footprint, a
geosynthetic reinforced rigid stone layer shall be installed on the exposed subgrade
prior to fill placement to construct the terrace embankment. The subgrade
evaluation and stabilization is to be completed under the direction of the
Geotechnical Engineer.
Our settlement analysis indicates that the total settlement of the terrace
addition is estimated to be on the order of 1 inch. Settlements of this magnitude are
typically considered to be within normal construction tolerances, the differential
settlement between the terrace and the existing Community Building may create a
tripping hazard. The partial soil exchange procedure will mitigate this condition to
some extent. In an effort to further reduce the total settlement of the proposed
terrace, the use of a lightweight fill alternative for the construction of the terrace
embankment can be considered. The use of this material in lieu of traditional fill
material would reduce the stress imposed on the loose underlying soils and
consequently reduce the magnitude of settlement. For additional information
regarding these alternatives, see Section 7.2 Soil Replacement.
7.1 SITE PREPARATION
All deleterious materials including topsoil, root mass, trees and vegetation,
asphalt and other materials determined in the field by the Geotechnical
Engineer to be unsuitable shall be removed from all structural areas (buildings,
pavements and walkways) prior to placement of structural fill. Recycling of the
asphalt and underlying stone can be accomplished on site if the asphalt is milled
to a maximum 1 inch particle size and the material is used in the upper fill zones
of pavement areas only. This fill is not suitable for other structural areas.
7.2 SOIL REPLACEMENT
Comparing the existing topography with the proposed elevation of the
proposed terrace, it is anticipated that an embankment of up to 4.2 feet of
structural fill will be required to achieve the proposed terrace elevation. Due to
this fill placement and the variability in both the content and strength of the
existing fill material of Stratum IF, there is a risk of settlement of the terrace
slab. In order eliminate this risk, the complete removal and replacement of the
existing fill material of Stratum IF and underlying organic silt of Stratum I from
beneath the proposed terrace addition and replacement with structural fill would
be required. In addition this removal shall extend beyond the building footprint
for a minimum lateral distance equal to the removal depth to ensure adequate
lateral stability. However, the removal and replacement alternative is considered
to be economically infeasible for a project of this size.
As an alternative to the complete removal of the existing fill within the
proposed terrace footprint, DBA recommends the removal of 2 feet of the existing
fill material.
densified in-place and evaluated through a proofroll via a heavy (minimum 15ton) smooth drum roller to detect the presence of any soft conditions. Due to the
loose nature of the existing fill material of Stratum IF, localized subgrade repair
consisting of removal of unsuitable material and replacement with structural fill
shall be anticipated. In order to minimize the potential differential settlement
within the terrace footprint, geosynthetic reinforcement via a layer of Tensar BX
Type 1 (or approved equal) geogrid shall be placed on the exposed subgrade prior
to placing fill to build the terrace embankment. The geosynthetic reinforcement
shall be covered with a 12 to 18 of dense graded aggregate meeting the
A smooth drum roller shall be made available to seal the subgrade in the
event of predicted precipitation.
7.4 BACKFILL OF FOUNDATION AND UTILITY TRENCHES
All foundation and utility trenches shall be backfilled with structural fill,
under the supervision of a Geotechnical Engineer (Refer to Section 7.7, Fill and
Compaction Criteria).
7.5 PAVEMENTS AND WALKWAYS
Pavement and sidewalk areas shall be prepared in a manner similar to the
slab on-grade areas. A minimum of 8 inches of crushed aggregate base shall be
used beneath exterior pavements due to the frost heave potential of the subgrade
soils. The pavement subgrade shall be graded to drain water from beneath the
pavement system to prevent ponding and subsequent pumping of silty subgrade
soils.
For pavement design a preliminary estimated California Bearing Ratio (CBR)
Value of 5.0 may be used for stabilized subgrade areas consisting of stabilized
portions of on-site existing fill consisting of silty sand (Stratum IF) or structural
fill selected and placed in accordance with the Section 7.7 of this report. Should
anticipated heavy duty pavement requirements or other project conditions
require final site specific CBR values DBA can complete field and/or laboratory
CBR testing of proposed subgrade soils at the clients request.
7.6 FILL AND COMPACTION CRITERIA
Fill supporting slabs, pavements, and foundations is considered herein to be
structural fill.
submitted to the Geotechnical Engineer for testing at least 1 week before use on
site. A minimum of 65 lbs. or two (2) five-gallon buckets is required for testing.
7.7 LATERAL EARTH PRESSURES - RETAINING WALLS
The retaining/loading dock walls of the structure, if proposed, should be
designed for an at rest condition (Ko). The foundations and walls must be fully
drained to relieve potential hydrostatic pressure. A foundation/wall drainage
system is recommended. Soil backfill around the basement walls shall be well
compacted and should consist of granular soils to prevent the trapping of water.
Retaining walls outside the structure which are free to rotate should be
similarly designed except with an active earth pressure as opposed to Ko
condition.
(excluding hydrostatic loads) and some additional parameters which may be used
in the design of a retaining wall system are summarized in the following table:
SOIL PROPERTIES FOR DETERMINATION OF LATERAL LOADS
Parameter
Stratum II
Stratum III
28 degrees
30 degrees
125 pcf
120 pcf
0.36
0.33
2.77
3.03
0.53
0.50
22 degrees
24 degrees
8. QUALITY CONTROL
This report was prepared to provide design criteria for the design team. DBA
assumes that Geotechnical and Construction Quality Control Services will be
provided in order to implement the recommendations provided herein and to identify
unanticipated or changed conditions. The Geotechnical Engineers representative
should review the consistency and texture of the exposed soils with the conditions
encountered by this exploration as described herein.
subgrade soils was not reviewed as part of this evaluation. All materials generated
FIGURES
AND
TABLES
SITE
Project 4545G1
Figure I
SITE LOCATION & TOPOGRAPHY
U.S.G.S. 7.5 Minute Topographic Quadrangle
Norristown Quadrangle
SITE
KEY
Xw - Wissahickon Formation
GEOTECHNICAL & ENVIRONMENTAL ENGINEERS
Project 4429G3
Figure II
SITE GEOLOGY
USGS Geologic Quadrangle Maps of PA
Norristown Quadrangle
SITE
KEY
UrmB - Urban land - Glenelg complex, 0 to 8 percent slopes
Project 4545G1
Figure III
Soils
Soil Mappig via
USDA Natural Resources Conservation Service
TABLE I
LABORATORY TEST RESULTS
B1
B4
S-2
S-3
4-6
6-8
S-7
S-8
14-16
16-18
B4
B5
S-6
S-5
12-14
13-15
STRATUM
II
III
III
NMC* (%)
18.7
21.4
51.3
44.7
50.8
54.4
BORING #
SAMPLE #
DEPTH
3/4"
100.0
100.0
100.0
3/8
96.1
100.0
100.0
93.9
100.0
100.0
10
90.3
99.2
99.8
40
75.6
94.3
97.5
100
53.0
71.9
67.4
200
37.0
57.6
37.5
N/A
N/A
N/A
PL*
N/A
N/A
N/A
PI*
N/A
N/A
N/A
SM
ML
SM
Descr.
Orange brown
and gray silty
sand
TABLE I (CONTD)
LABORATORY TEST RESULTS
BORING #
B3
B4
B5
SAMPLE #
S-2
S-3
S-3
DEPTH
4-6
6-8
6-8
STRATUM
NMC* (%)
38.92
26.52
20.11
ORG** (%)
5.20
2.76
1.93
TABLE IIA
APPROXIMATE ROCK ELEVATIONS
Boring
Number
Surface
Elevation
Depth to
Stratum
II
Stratum II
Surface
Elevation
Depth to Dense
Weathered
Rock1
Dense
Weathered
Rock Elevation
Depth to
Bedrock2
Bedrock
Elevation
B1
96.5 feet
4.3 feet
92.2 feet
11 feet
85.5 feet
13.8 feet
82.7 feet
B2
96.5 feet
6.3 feet
90.2 feet
13.8 feet
82.7 feet
16.3 feet
80.2 feet
B3
95.8 feet
6.8 feet
89.0 feet
19.0 feet
76.8 feet
>20.3 feet
<75.5 feet
B4
96.1 feet
7.0 feet
89.1 feet
>20.0 feet
<76.1 feet
>20.0 feet
<76.1 feet
B5
96.5 feet
8.8 feet
87.7 feet
>21.0 feet
<75.5 feet
>21.0 feet
<75.5 feet
NOTES:
Surface elevations at each boring location were determined using an arbitrary finished floor elevation of 100.0 for the existing
Narberth Community Building.
1
2
TABLE IIB
APPROXIMATE GROUNDWATER ELEVATIONS
Boring Number
Surface Elevation
Depth to Groundwater
Groundwater Elevation3
B1
96.5 feet
9.2 feet
87.3 feet
B2
96.5 feet
8.5 feet
88.0 feet
B3
95.8 feet
6.7 feet
89.1 feet
B4
96.1 feet
6.6 feet
89.5 feet
B5
96.5 feet
6.8 feet
89.7 feet
NOTES:
Surface elevations at each boring location were determined using an arbitrary finished floor elevation of 100.0 for the existing
Narberth Community Building.
TABLE III
COMPACTION CRITERIA
LOCATION
Foundations
98%
Floor Slabs
98%
Pavements
95%
Berms(non
structural)
93%
APPENDIX
SOIL PARTICLE
SIZE ANALYSIS
RESULTS
TEST BORING
LOGS
Boring Number : B1
1.0
2.0
96.04
3.66
92.88
4.25
92.29
5.0
6.0
SPT DATA
510 20 30 40 50
SPT GRAPH
100
Strattum IF
FILL consisting of orange
brown and brown micaceous
finesand and silt with some
quartz fragments.
3.0
4.0
Water Content
SPT Value
0.50
NUMBER
ELEVATION
Topsoil (6")
SAMPLING DATA
DEPTH (FT)
LITHOLOGIC
SYMBOL
WATER LEVEL
DEPTH BELOW
LITHOLOGY
GEOLOGIC DESCRIPTION OF
SOIL AND ROCK STRATA
Sheet 1 of 1
Topsoil
Strattum II
Orange brown and gray
mottled finesand with some
silt, occassional rock
fragments
7.0
8.0
Strattum III
Gray weathered schist
9.0
Multi-colored weathered
schist
S-1*
4-6-4-4
10
S-2*
2-3-3-4
3-4-8-10
12
6-10-19-18
29
7.25
89.29 S-3**
8.33
88.21
S-4**
10.0
11.0
12.0
S-5
13.0
50/2"
N.R.
100
13.83 82.71
14.0
Auger Refusal
15.0
Notes:
16.0
*Very moist
**Moist
-Hard Augering from 11'
17.0
18.0
The boring results represent subsurface conditions at the boring locations only and are not necessarily representative of conditions at other locations. Water levels are taken at the time of drilling and are not
indicative of seasonal variations in the ground water level. NR = No Recovery, S =Split Spoon sample(2" O.D.), C=Rock Coring Run.
Boring Number : B2
Water Content
SPT DATA
510 20 30 40 50
SPT Value
NUMBER
ELEVATION
SAMPLING DATA
DEPTH (FT)
LITHOLOGIC
SYMBOL
WATER LEVEL
DEPTH BELOW
LITHOLOGY
GEOLOGIC DESCRIPTION OF
SOIL AND ROCK STRATA
Sheet 1 of 1
SPT GRAPH
100
Topsoil (4")
1.0
2.0
3.0
Strattum IF
FILL consisting of orange
brown and brown micaceous
finesand and silt with
occasional schist fragments
and roots.
S-1*
2-2-3-3
S-2*
3-3-4-6
S-3**
6-3-5-8
S-4*
5-6-7-8
13
S-5**
44-50/3"
100
4.0
5.0
6.0
7.0
8.0
9.0
Strattum I
Brown and gray organic silt
with roots.
Strattum II
Orange brown and brown
gray slightly micaceous
finesand, some silt,
occassional schist fragments,
and traces of pebbles.
5.25
91.25
6.33
90.17
10.0
11.0
12.0
13.0
11.50 85.00
Strattum III
Multi-colored weathered
schist
14.0
15.0
16.0
16.25 80.25
Auger Refusal
17.0
Notes:
18.0
19.0
*Very moist
**Moist
-Fairly hard to hard augering from
12'
-Hard augering from 13.75'
20.0
The boring results represent subsurface conditions at the boring locations only and are not necessarily representative of conditions at other locations. Water levels are taken at the time of drilling and are not
indicative of seasonal variations in the ground water level. NR = No Recovery, S =Split Spoon sample(2" O.D.), C=Rock Coring Run.
Boring Number : B3
Water Content
SPT DATA
510 20 30 40 50
SPT Value
NUMBER
ELEVATION
SAMPLING DATA
DEPTH (FT)
LITHOLOGIC
SYMBOL
WATER LEVEL
DEPTH BELOW
LITHOLOGY
GEOLOGIC DESCRIPTION OF
SOIL AND ROCK STRATA
Sheet 1 of 1
SPT GRAPH
100
Topsoil (5")
1.0
2.0
3.0
Strattum IF
FILL consisting of orange
brown and brown micaceous
finesand and silt with
occasional quartz fragments
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
4.25
14.0
15.0
Notes:
12.0
13.0
16.0
17.0
6.75
8.00
S-1*
2-2-1-2
S-2**
2-1-1-2
S-3*
3-9-18-7
27***
S-4**
7-7-9-9
16
S-5*
5-12-19-26
31
S-6*
24-38-50/5"
100
50/3"
100
91.57
89.07
87.82
11.00 84.82
*Moist
**Very Moist
***High blow due to quartz fragments
-Fairly hard augering from 16.5' to
19'
-Hard augering from 19'
18.0
19.0
20.0
20.25 75.57
S-7*
Boring Terminated
21.0
22.0
The boring results represent subsurface conditions at the boring locations only and are not necessarily representative of conditions at other locations. Water levels are taken at the time of drilling and are not
indicative of seasonal variations in the ground water level. NR = No Recovery, S =Split Spoon sample(2" O.D.), C=Rock Coring Run.
Boring Number : B4
Water Content
SPT DATA
510 20 30 40 50
SPT Value
NUMBER
ELEVATION
SAMPLING DATA
DEPTH (FT)
LITHOLOGIC
SYMBOL
WATER LEVEL
DEPTH BELOW
LITHOLOGY
GEOLOGIC DESCRIPTION OF
SOIL AND ROCK STRATA
Sheet 1 of 1
SPT GRAPH
100
Topsoil (4")
1.0
2.0
3.0
Strattum IF
FILL consisting of orange
brown and brown micaceous
finesand and silt with some
rock fragments.
S-1*
4-2-2-2
S-2*
3-3-2-2
S-3*
3-6-7-7
13
S-4*
4-3-3-3
S-5**
3-3-3-4
S-6*
1-1-1-1
S-7*
1-2-3-4
S-8*
4-5-9-9
14
S-9*
6-10-12-13
22
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
Strattum I
Gray and brown organic silt
with roots.
Strattum II
Orange brown, brown, and
orange brown micaceous
finesand with some schist
fragments, traces of silt, and
occassional pebbles.
5.66
90.45
7.00
89.11
11.00 85.11
Strattum III
Multi-colored weathered
schist
13.0
14.0
15.0
16.0
17.0
18.0
19.0
20.0
20.00 76.11
Boring Terminated
21.0
22.0
Notes:
23.0
*Very moist
**Moist'
24.0
25.0
The boring results represent subsurface conditions at the boring locations only and are not necessarily representative of conditions at other locations. Water levels are taken at the time of drilling and are not
indicative of seasonal variations in the ground water level. NR = No Recovery, S =Split Spoon sample(2" O.D.), C=Rock Coring Run.
Boring Number : B5
2.0
Strattum IF
FILL consisting of orange
brown and brown micaceous
finesand, some silt with some
rock fragments.
3.0
4.0
95.54
5.0
5.83
6.0
7.0
Water Content
SPT DATA
510 20 30 40 50
SPT Value
0.92
NUMBER
ELEVATION
Asphalt (3")
1.0
SAMPLING DATA
DEPTH (FT)
LITHOLOGIC
SYMBOL
WATER LEVEL
DEPTH BELOW
LITHOLOGY
GEOLOGIC DESCRIPTION OF
SOIL AND ROCK STRATA
Sheet 1 of 1
S-1*
2-1-3-5
S-2*
2-2-2-2
S-3**
2-2-5-8
S-4**
8-8-9-9
17
S-5**
1-1-1-1
S-6**
2-5-6-8
11
S-7**
5-6-9-9
15
S-8***
6-7-10-12
17
SPT GRAPH
100
90.63
Strattum I
Gray and brown organic silt
with roots.
8.0
8.75
9.0
10.0
11.0
12.0
13.0
Strattum II
Orange brown, brown and
gray micaceous finesand with
schist fragments, traces of
silt.
87.71
12.00 84.46
Strattum III
Multi-colored weathered
schist
14.0
15.0
16.0
17.0
18.0
19.0
20.0
21.0
21.00 75.46
Boring Terminated
22.0
Notes:
23.0
24.0
*Very moist
**Moist
***Wet
25.0
The boring results represent subsurface conditions at the boring locations only and are not necessarily representative of conditions at other locations. Water levels are taken at the time of drilling and are not
indicative of seasonal variations in the ground water level. NR = No Recovery, S =Split Spoon sample(2" O.D.), C=Rock Coring Run.
TEST BORING
LOCATION PLAN
B5
B4
B1
B3
B2
KEY
Project 4545G1
TEST BORING PLAN
Narberth Community Building
Terrace Addition
Narberth Borough, Montgomery County, PA