Precast Cladding PDF
Precast Cladding PDF
SEPTEMBER 1998
ACA
SEPTEMBER 1998
ISBN: 0 9500347 6 2
No part of this publication may be reproduced in a retrieval system or transmitted in any form
or by any means, electronic, mechanical, photocopying or otherwise without prior written
permission from the Secretary, Architectural Cladding Association
60 Charles Street, Leicester LE1 1FB
Every effort has been made to ensure that the statements made and advice given provide a safe
and accurate guide; however, no liability or responsibility of any kind (including liability for
negligence) can be accepted in this respect by the publishers or the authors.
ACA
SEPTEMBER 1998
CODE OF PRACTICE DRAFTING COMMITTEE
P. A. King
(Chairman)
C. J. Budge
(Secretary)
M. Padkin
P. F. Thomas
P. Dorkings
D. Vittle
B. Ayres
C. Wright
D. Reid
D. Gray
C. Clark
P Cope
G. Stark
Techrete Ltd
ACA
SEPTEMBER 1998
ACA
SEPTEMBER 1998
FOREWORD
Safety is a state of mind and it is the responsibility of all parties concerned with a construction
project to encourage a positive attitude and contribute to the overall success of that project.
This Code of Practice sets forth the guidelines which should be observed in order to carry out
the safe and efficient erection of precast cladding and is aimed at the building designer and
contractor in addition to the precast designer and erector.
The Code will form a base manual for the training and updating of personnel involved in the
planning, management and execution of the erection of precast cladding.
This review of the Code incorporates the numerous revisions and additions introduced by
changes in legislation and working practice since the drafting of the original document in 1992
and maintains a practical approach to site safety.
Whilst the Code has been prepared by the experienced members of the committee invaluable
assistance has been received from the Health and Safety Executive and the Precast Flooring
Federation.
P A King
Chairman
July 1998
ACA
SEPTEMBER 1998
ACA
SEPTEMBER 1998
CONTENTS
DEFINITIONS
Page No.
11
REFERENCES
13
SECTION 1:
1.1.
1.1.1.
SECTION 2:
2.1
2.2
2.3
2.4
2.5
2.6
SECTION 3:
3.1
3.2
3.3.
3.4
Introduction
Content of Safe Working Method Statements
Communication of the Safe Working Method Statement
Additions to the Safe Working Method Statement
SECTION 4:
4.1
4.2
4.3
Attendances
Protection of the Cladding
Contractor Installed Fixings
SECTION 5:
5.1
5.2
5.3
5.4
5.5
15
15
19
19
20
20
20
20
21
21
22
23
25
25
25
27
27
28
28
29
ACA
SEPTEMBER 1998
Page No.
SECTION 6:
FOREMANS ROLE
6.1
6.2
6.3
SECTION 7:
7.1
7.2
Training
Certification
SECTION 8:
8.1
8.2
8.3
8.4
8.5
SECTION 9:
9.1
9.2
9.3
9.4
9.5
9.6
9.7
SECTION 10:
TRANSPORTATION OF COMPONENTS
10.1
10.2
10.3
10.4
SECTION 11:
11.1
11.2
31
31
31
33
33
35
35
36
37
38
39
39
40
47
47
48
50
51
51
51
52
55
56
ACA
SEPTEMBER 1998
Page No.
SECTION 12:
ACCESS
12.1
12.2
12.3
12.4.
General
Scaffolding
Edge Protection
Work at Roof Level
SECTION 13:
13.1
13.2
13.3
13.4
13.5
13.6
Barring
Jacking
Chain Block, Tirfors etc.
Tilting Tables and Pitching Frames
Bogies
Manual Handling
SECTION 14:
14.1
14.2
14.3
14.4
14.5
14.6
14.7
14.8
14.9
Temporary Propping
Insitu Concrete
Dry Packing and Grouting
Jointing
Insulation and Fire-stops
Final Finishing and Clean Down
Drilling and Cutting
Welding and Cutting of Steel
Cartridge Operated Tools
SECTION 15:
15.1
15.2
57
61
62
63
67
67
68
68
69
69
73
73
74
74
74
75
75
76
77
79
79
81
ACA
SEPTEMBER 1998
10
ACA
SEPTEMBER 1998
DEFINITIONS
Most of the terms used in this document are in common use. However, the following definitions
are intended to remove any ambiguity:
AS BUILT DRAWING: The layout drawings confirming as built positions of precast
cladding and/or component positions, issued at the completion of the contract.
APPOINTED PERSON: A competent and certificated person appointed to supervise
prescribed lifting operations, to ensure compliance with relevant legislation.
ATTENDANCE: The standard ACA Health, Safety & Welfare Attendances, a copy of which
is included as an Appendix to this Code.
BUILDING DESIGNER: The person or persons appointed to design the building or structure
upon which the cladding is installed.
CERTIFICATED: Having been trained and qualified to fulfil a particular role. Holding a
valid licence/certificate of training gained by attending a recognised course of instruction for
the task in question.
CLADDING: The precast concrete units forming part of the architectural envelope and taking
support from the frame of a building or structure.
COMPANY: The precast concrete company engaged in the design, manufacture and erection
of the Cladding.
COMPANY REPRESENTATIVE: A visiting Supervisor/Contracts Manager in the Erection
Companys employ who shall be competent to assess all health, safety and welfare
arrangements in relation to company operations.
COMPONENTS: Any member, article, or item which is essential to the erection of the
cladding whether such item is of precast concrete or not.
CONTRACTOR:
11
ACA
SEPTEMBER 1998
ERECTOR: A competent and trained person able to carry out all functions of Slinger and
Signaller, as well as to hoist, place and secure precast concrete sections, including all
plumbing, levelling and lining up, with the ability and training to work safely at heights.
FOREMAN: A competent and trained person responsible for the precast erection team.
JOINTING: Generally a flexible gun-applied or preformed material acting as a seal to the
Cladding joints.
SIGNALLER (BANKSMAN): A competent and trained person responsible for directing the
safe movement of a load attached to a crane, and for the movement of the crane on site.
SLINGER: A competent and trained person responsible for the proper selection of lifting
tackle, the slinging of loads to the crane attachment and who can also direct the safe movement
of the crane, taking into account the capabilities of the crane with which he is working.
SUB CONTRACTOR: A specialist appointed by the Company or the Contractor to undertake
work on their behalf.
SUPPORTING STRUCTURE: The background structure from which the cladding is to be
permanently supported and restrained, normally being constructed from steelwork, insitu or
precast concrete, or masonry.
WORK AREA: The area on a site or building where precast cladding units/components are
being erected. This includes the area covered by the radius of a crane from lifting off a lorry
(or stack) to the final position.
WORKING DRAWINGS: The layout drawings, section and details, produced by the
Designer approved by the client and issued for production and erection purposes.
12
ACA
SEPTEMBER 1998
REFERENCES
Factories Act.
Health & Safety at Work etc. Act
1961
1974
1992
1961
1970
1972
1974
1981
1989
1989
1989
1992
1992
1992
1994
1994
1994
1995
1996
1996
The following Health and Safety Executive Guidance Notes are also relevant:
GS 6 (Rev 1997)Avoidance of Danger from Overhead Electrical Lines
GS 28/2
GS 28/3
HS (G) 141
HS (G) 150
13
ACA
SEPTEMBER 1998
Guidance notes are issued on a continuing basis and users of this Code of Practice should
acquaint themselves with the latest updates and revisions.
BS 1129
BS 1139
BS 2037
BS 2482
BS 2830
BS 4592
BS 5323
BS 5628
BS 5950
BS 5973
BS 5974
BS 5975
BS 6180
BS 7121
BS 7212
BS 8110
BS 8297
BSEN 354
BSEN 355
BSEN 358
BSEN 361
BSEN362
BSEN 363
BSEN 364
BSEN365
BSEN 795
14
ACA
SEPTEMBER 1998
1.
1.1
The Management of Health and Safety at Work Regulations 1992 and Approved
Code of Practice
These Regulations require an employer to make a suitable assessment of the risks to the
health and safety of employees and others who may be exposed to those risks. This
includes contractors and temporary staff engaged for special work.
Most employers will be capable of making the risk assessment themselves using
expertise within their own organisations, however, where there are complex hazards or
equipment, it may need to be done in conjunction with the help of external Health and
Safety Advisors appointed under Regulation 6 of the Management of Health and Safety
at Work Regulations 1992.
In addition employees have certain duties under the Regulations:l
To make full and proper use of anything provided by the employer in accordance
with the training given. This includes safety equipment, machinery, substances,
means of transport etc.
Employees must also inform the Employer (or nominated persons) of any
dangerous work situation or any matter relating to the Employers Health and
Safety arrangements.
b)
c)
d)
e)
f)
15
ACA
SEPTEMBER 1998
g)
h)
Reducing Risks
a)
b)
c)
d)
e)
Ensure all personnel involved are competent to carry out the operation
f)
g)
Remember
a)
b)
Risk expresses the likelihood that the harm is realised and the consequential
extent, to persons and/or property
c)
Risk therefore reflects both the likelihood that harm will occur and its severity.
b)
Risk Assessments should be regularly reviewed and altered if they are no longer
valid or circumstances/conditions have changed significantly
c)
d)
16
ACA
SEPTEMBER 1998
e)
f)
Training must be provided to the employees in respect of the duties placed upon
them by the Regulations, at induction when first employed, when transferred or if
the job changes. This training should be updated and repeated periodically to
take account of any changes.
17
ACA
SEPTEMBER 1998
18
ACA
SEPTEMBER 1998
2.
DESIGN STAGE
2.1
2.2
19
ACA
2.3
SEPTEMBER 1998
Stability of Cladding
Cladding components should be designed such that stability is maintained at all times
during and after erection.
The sequence of erection should be clearly stated and implemented to ensure stability of
the cladding and supporting structure at all stages during construction and communicated
to all relevant parties.
Means of access to connections, particularly to bearing points, jointing positions,
insulation, fire stops etc. should be carefully considered by the Designer.
2.4
2.5
2.6
Tolerances
The issue of tolerances must be clearly identified and addressed at the design stage to
ensure that the specified aesthetic and structural requirements of the contract can be
achieved. This will involve careful consideration of the relevant manufacturing and
erection tolerances for the supporting structure, the cladding components and any
adjacent works i.e windows, ceilings, floors etc., to ensure compatibility between the
different systems.
Failure to achieve compatible tolerances will invariably result in a lack of fit situation
which in extreme cases may lead to an unstable condition of the cladding component or
supporting structure.
Connections at support and restraint positions between cladding and structure must be
designed to accommodate the necessary three dimensional tolerances for movement
purposes and still retain full structural integrity of the connection.
20
ACA
SEPTEMBER 1998
3.
3.1
Introduction
Safe Working Method Statements form part of the overall Safety Management System,
covering hazardous activities, such as the erection of precast cladding and associated
components. They provide the information on the arrangements and, where required, the
actual sequence of work necessary to manage health and safety during the erection of the
Cladding and associated components. Basic information should be provided and
communicated to all concerned parties at the planning stage, thus allowing time for
approval or modification of the Safe Working Method Statement prior to site erection.
Cladding erection is similar in nature on many sites and therefore a Safe Working
Method Statement will contain common elements and activities. However the Safe
Working Method Statements should take account of specific site
conditions/requirements, health and safety information from the Health and Safety
Plan/Design Risk Assessment and/or contractors requirements.
3.2
21
ACA
SEPTEMBER 1998
Working at Heights
Welfare Facilities
3.3
22
ACA
3.4
SEPTEMBER 1998
Additions to the Safe Working Method Statement
The Safe Working Method Statement may be added to by attaching and/or referring to
other documents, for example;
Company Site Safety Booklets
Company Procedures (e.g. Handling and Storage)
Craneage Supplier site visit/Craneage Reports
Company Representative Reports
Risk, COSHH Noise and Manual Handling Assessments
Addendums to the Safe Working Method Statement
Specifications and Certification of plant and equipment etc.
Architectural Cladding Association Code of Practice/Attendances
The Health and Safety Plan
This list is not exhaustive and the level of information/inclusion will vary and depends
on the nature of the contract.
23
ACA
SEPTEMBER 1998
24
ACA
SEPTEMBER 1998
4.
4.1
Attendances
The Attendances, specified in the ACA Attendances Appendix, attached to the cladding
sub-contractors quotation, together with any additional specific requirements
necessitated by the nature of the site or contract works, are to be provided by the
Contractor.
The Contractor should also maintain and up-grade these attendance items to compensate
for deterioration through usage and weather.
4.2
4.3
25
ACA
SEPTEMBER 1998
26
ACA
SEPTEMBER 1998
5.
5.1
Should it be necessary for the erection sequence to be varied after commencement, for
whatever reason, this should only be implemented after reference to the Company and
after all safety requirements have been satisfied. The Safe Working Method Statement
should be amended by an addendum to cover any revisions which should be
documented, signed, agreed and discussed with all relevant parties.
5.2
Method of Lifting
Based upon experience, and if necessary in liaison with crane hire representatives, the
Company Representative should decide upon the type of lifting, plant and equipment to
be employed in the erection of each specific component, taking into account the weight
of components to be lifted, the radius of lifting, and any special handling requirements.
The Company Representative should liaise with the Contractors Representative to
ensure the suitability of any lifting equipment provided by the Contractor.
As a guide to the Contractor, the Company should discuss and advise upon the type and
size of delivery lorries and craneage, in order that the Contractor may provide adequate
access and hardstandings or other facilities which may be required to accommodate
delivery and lifting equipment.
The Company should also bring to the attention of the Contractor any visible
obstructions likely to hinder the safe working of lifting equipment e.g. aerial
obstructions, stacked materials, earthworks, in order that these may be removed or made
safe prior to the commencement of the cladding erection. The Company should monitor
this aspect of site safety as the works proceed.
After reaching a decision upon the lifting arrangements, unloading points, site access,
crane standing areas etc. the Company should provide a marked up record, prior to work
commencing, showing the areas agreed with the Contractor, as part of the Safe Working
Method Statement.
27
ACA
SEPTEMBER 1998
During the routine pre-contract site visit the Company Representative should satisfy
himself that the site conditions, observed or anticipated at the time when the crane or
lifting equipment was selected, have not changed, or will not change. If change has
occurred or can be anticipated, the Company Representative should again ensure that the
crane or lifting equipment is adequate.
5.3
Site Access
In addition to the access required for the method of lifting (see Section 5.2) the Company
must agree with the Contractor access from the public highway onto site, unloading
points, the type and location of hard roads and hard standing areas for delivery vehicles
and the need for temporary or long term removal of any fences, walls or other
obstructions. Consideration should be given to the sizes of vehicles to be used including
the possibility of abnormal loads and the effect parked vehicles may have on the site
entrance. It may be necessary for the Contractor to involve the police and statutory
authorities and others before arriving at a satisfactory solution.
The condition of the agreed access roads should at all times be maintained by the
Contractor to an acceptable standard. The need for vehicles to leave the site in a clean
condition, free from mud, dust and other materials, should be considered and the
Contractor may need to consider providing vehicle and/or automatic wheel washing
facilities at the exit. These additional points should form part of any agreement.
Whilst making these arrangements, locations of and access to stacking areas, stores,
temporary buildings and lorry/trailer holding areas should be agreed.
The agreed access and other arrangements should then be incorporated into the Safe
Working Method Statement, in order that all parties should have the information readily
available and to avoid misunderstandings or confusion when the cladding erection
commences.
Access into the building(s) as erection progresses should be agreed together with
protection on and around the cladding. Particular attention should be paid to barriers,
guardrails/handrails, toeboards, access lighting and similar. The Company should
monitor the provision of these Attendances during the period of the site works.
5.4
Attendances Liaison
The Contractor will be aware of the precast concrete sub-contractors general
requirements with regard to Attendances, having received the ACA Attendances as
specified in the Appendix to this Code.
The Company Representative should discuss the general requirements with the
Contractor in order to agree more specific Attendances, which reflect the nature of the
site and the contract works.
28
ACA
SEPTEMBER 1998
All Agreements reached between the Company Representative and the Contractors Site
Representative should be confirmed either in writing or by inclusion on a marked up
record, copies being held by both parties to the agreement.
Before commencing erection of cladding the Company Representative should satisfy
himself that the Attendances described in the Safe Working Method Statement are in fact
available and of a satisfactory standard. Where possible such a check should be
conducted together with the Foreman.
If any item is found to be inadequate or missing, the Company Representative should
highlight the problem and if necessary delay commencement of erection until the
Attendances are satisfactory. In such circumstances the Company Representative must
fully acquaint the Contractors Site Representative with the situation.
5.5
Supervision of Erection
Prior to commencement of the cladding erection the Company Representative should
visit the site to visually examine the suitability of the supporting structure provided by
the Contractor. This inspection should be conducted, wherever possible, together with
the Contractors Site Representative. However, in all cases where defects or
irregularities are found these should be brought to the Contractors attention, so that
corrective measures may be executed before cladding erection commences to that area.
The Company Representative should visit site on the first day of any site visit by an
erection team to acquaint the Foreman and erection team fully with any special problems
or conditions relative to the Safe Working Method Statement.
Whilst on site the Company Representative should satisfy himself that the Contractors
Attendance items have been satisfactorily provided and ensure that the Foreman is fully
aware of the Contractors and sub-contractors obligations.
On contracts of a complex nature a Company Representative should spend a greater
length of time with the erection team. In certain cases, where there is a complex
erection, the Company Representative should oversee the complete erection.
It is essential for the Company Representative to call on site at intermediate points
throughout the contract, to ensure that erection is proceeding in a safe and proper manner
and that all Attendances continue to be provided.
29
ACA
SEPTEMBER 1998
30
ACA
SEPTEMBER 1998
6.
FOREMANS ROLE
6.1
6.2
6.3
Supervision of Erection
In all cases the Foreman is responsible for the actual erection of the cladding and its
components in accordance with the Safe Working Method Statement. On contracts
where the Company Representative oversees erection, the overall responsibility for the
erection team and their actions still remains with the Foreman, through whom all
instructions from the Company Representative should be given.
The delegation of specific tasks within the team is the responsibility of the Foreman,
who should be satisfied that the person to whom the task is assigned is competent to
carry out that work safely.
Before placing any components the Foreman should satisfy himself that the lifting
appliances, plant and equipment are operating in a safe and proper manner, and that all
operators are fully aware of the nature of the work and can identify and understand the
Signaller (Banksman).
31
ACA
SEPTEMBER 1998
Prior to the commencement of erection, the Foreman should visually inspect and satisfy
himself that the supporting structure provided for the cladding and its components
appear satisfactory. If any item is found to be inadequate or missing the Foreman should
highlight the problem and if necessary delay commencement of erection until the matter
is resolved.
During the actual erection and placement of the cladding and its components, the
Foreman should ensure that correct handling and placing procedures are being adhered
to, and that all aspects of the work are being executed in a safe and proper manner, in
accordance with the Working Drawings and Safe Working Method Statement.
The Foreman should also check the accuracy of the cladding and its components,
ensuring that erection tolerances correspond with the Working Drawings and
Specification.
Any variations which occur should be referred back to the Company by the Foreman for
instructions, so that remedial measures may be safely and properly executed to ensure
the overall structural integrity and stability of the cladding, which may necessitate a
revision of the Safe Working Method Statement.
When erection of all or agreed sections of the cladding is complete the Foreman will
inspect the work and a handover certificate will be issued to the Contractors Site
Representative identifying any outstanding items of work.
32
ACA
SEPTEMBER 1998
7.
7.1
Training
Employers have a responsibility under the Health and Safety at Work etc. Act 1974 and
the Management of Health and Safety at Work Regulations 1992 to provide appropriate
training for their employees and ensure that their sub-contractors have received
appropriate training. The personnel designated to carry out specific tasks on site should
therefore have received training and should hold appropriate certification. Personnel
employed on the site who require specific training appropriate to their functions include:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
11.
12.
7.2
Erectors
Crane Operators
Signallers/Banksmen
Slingers
Lift Truck Operators
Dumper Truck Drivers
Operators of Work-Access Platforms
Operators of Concrete Pumping Equipment
Abrasive Wheel Operators
Welders
Operators of Hoists
First Aiders
Certification
ACA Approved Training Providers run courses on all aspects of the Safe Erection of
Precast Concrete components.
Employers also have an obligation to provide training to all personnel and ensure their
sub-contractors have been trained. The training should include the following aspects.
(i)
(ii)
(iii)
(iv)
(v)
(vi)
33
ACA
SEPTEMBER 1998
34
ACA
SEPTEMBER 1998
8.
8.1
8.2
35
ACA
SEPTEMBER 1998
All operatives involved in the use of these materials, e.g. cement, ready-mixed concrete,
etc., will be reminded of the hazards of the particular material about to be used and all
necessary precautions and any protective equipment or clothing will be made available
and put into use before any substance is utilised on site.
All substances received on site will be stored in accordance with the instructions
contained in the Assessment Sheets, and in the event of any spillage, appropriate action
should be taken to retrieve the material in accordance with instructions contained in the
Assessment Sheet. The Company Representative should monitor these procedures.
Empty containers and waste material must be disposed of in accordance with the
approved procedures, as noted on the Assessment Sheet for the product or products
concerned.
The materials used in the erection of precast concrete cladding are generally of low
toxicity but all operatives must be reminded of the hazards at all times by the Foreman.
Checks that control measures are being adhered to should be made at periodic intervals
by the Company Representative.
Copies of COSHH Assessment sheets may form part of the Companys Work Method
Statement.
The Company Representative should request the Main Contractor to supply details of
any other substances on site that could affect employees of the Company or their subcontractors.
8.3
Noise at Work
The Noise at Work Regulations 1989 place certain duties on employers, employees and
manufacturers. The noise created by drilling, cutting etc., may be excessive and could
cause a health hazard, which requires to be assessed and controlled.
Action Levels
First Action Level
85 dB (A)
90 dB (A)
140 dB (A)
(200 Pascals)
Where employees are exposed between the first and second Action levels the employer
is required to provide protectors to employees who so request.
Where employees are exposed above the second Action level the wearing of ear
protection is mandatory. The employer should provide hearing protection and ensure
that the protectors are used and the employee has been trained in their correct use. At no
time should the Peak Action Level be reached.
36
ACA
8.4
SEPTEMBER 1998
Personal Protective Equipment at Work
37
ACA
8.5
SEPTEMBER 1998
The Construction (Health Safety and Welfare) Regulations 1996
38
ACA
9.
SEPTEMBER 1998
SAFE USE OF CRANES, FORK LIFTS AND OTHER LIFTING EQUIPMENT
It is in the interest of all parties involved in lifting operations to ensure that they are
carried out efficiently and safely. BS7121 Part 1: Safe Use of Cranes ensures that
everyone involved in a lifting operation is aware of their responsibilities.
9.1
The lifting operation should be taken to include any necessary preparation of, as well as
erection and dismantling of the crane(s).
The Safe Working Method Statement should be effectively communicated to all parties
concerned.
9.2
39
ACA
e)
SEPTEMBER 1998
Ramps, slopes or uneven ground can seriously affect the stability of a crane and should,
therefore, be avoided, made safe or approached with extreme caution.
Following the visit of the Company Representative the Contractor should ensure that
suitable levelled hardstanding/hardcore areas are provided for the safe passage and
working of the crane, but if there is any doubt as to the suitability of any aspect of the
site, it should be brought to the attention of the Contractors Site Representative in order
that remedial measures may be implemented. The Foreman and Crane Operator should
continue to monitor ground conditions during the whole operation, paying particular
attention to deterioration as a result of usage and adverse weather.
The crane should only operate from the position(s) agreed between the Company
Representative and the Contractors Site Representative or such other position as may
be agreed at the time by the Foreman and the Contractors Site Representative, provided
that the level of safety is not reduced as a result.
9.3
40
ACA
SEPTEMBER 1998
When travelling with a suspended load, great care must be taken and full liaison
maintained between Crane Operator, Foreman and Contractors Site Representative.
The crane must operate on level ground and proceed at a crawl pace and be guided by a
competent Signaller/Banksman, who should watch for obstructions at ground level and
overhead as well as uneven ground or slopes which should be avoided.
Before allowing the crane to travel the Foreman should ensure that the Crane Operator
and Signaller/Banksman are aware of the route to be taken and that the Crane Operator
is confident that the operation can be undertaken safely.
The suspended load should be carried as close to the ground as possible and hand lines
should be attached to the load during transit to prevent excessive swinging.
41
ACA
SEPTEMBER 1998
The structure of a tower crane, together with all metal cases of electrical equipment,
should be effectively and directly connected to earth. This recommendation also
applies to rail mounted tower cranes, in which case it is further advised that at least one
rail should be electrically bonded at each joint and the track itself should be effectively
earthed. The reliance on the use of crane wheels for earthing is not recommended.
In the case of rail-mounted tower cranes, all rails must be constructed and laid by
competent persons in strict accordance with the provisions of the Construction (Lifting
Operations) Regulations, 1961.
Whenever a tower crane is left unattended, irrespective of the duration, the jib should be
left free slewing with the hook as close to the trolley as possible, and the trolley close
into the mast of the crane. When unattended for longer periods of time e.g. the end of a
working day, weekend, or holiday period, the cranes power feed should be shut off at
the isolator.
Special consideration should be given when two or more tower cranes are being
operated in close proximity, to avoid contact between jibs or ropes etc.
42
ACA
SEPTEMBER 1998
When handling precast components on the forks of a lift truck, it will be necessary to
ensure that the forks of the vehicle are spaced such that the load is maintained in a stable
condition and padded so that no damage is caused to the component being handled.
43
ACA
SEPTEMBER 1998
Prior to use, the Foreman should ensure that he is in possession of the relevant
certificates and that he or the slinger carries out a visual inspection of all items to be
used in the lifting operation. He should also identify the SWL of each item to ensure that
adequate capacity is selected for the loading condition to be applied.
The use of Patent Lifting Devices (see 9.3.6) automatically selects the appropriate
shackle capacity which in turn greatly simplifies the selection of chains or ropes.
Where it is not possible or practicable to use cast-in patent devices, the component
weight should always be available on site to enable the Foreman to select the correct
lifting equipment. This information should be conveyed in the form of a component
schedule, or the weight of the component may be painted on, or otherwise indicated on
the component itself.
All chains, ropes and lifting gear must be securely attached to the lifting appliance e.g
crane hook, in such a manner that damage is not caused to the chain, rope, lifting gear or
the lifting appliance.
Any hook used for lifting purposes must, under the Construction Regulations, be fitted
with either a safety catch or be of such a shape (e.g `C hook) to prevent the
displacement of the sling or load from the hook.
Any hook which has been damaged or has had the safety catch damaged, or removed if
originally fitted, must not be used. Safety catches must not be tampered with or removed
at any time.
two leg
three leg
four leg
SWL @ 90
SWL @ 45
SWL @ 90
There are two options for the consideration of SWL of multi leg slings, under known
working conditions. These are the uniform load method and the trigonometric method.
The uniform load method rates slings for all angles between legs from 0 to 90 (0-45
from vertical to each leg). The sling may be additionally rated from 90 to 120 (45-60
from vertical to each leg). This method is to be preferred where slingers do not have
either the time or the inclination to consult tables on SWLs at varying angles.
44
ACA
SEPTEMBER 1998
The trigonometric method rates a multi leg sling at a SWL which relates to the angle
between the legs when the sling is in use, reference being made to the manufacturers
table of safe working loads.
Although marked with a SWL at 90, multiple leg slings of two or four legs can be used
at angles of 30, 60, 90 and 120, similarly three leg slings at 15, 30, 45 and 60
angles.
It is recommended that the Slinger should be aware of these methods of rating, further
guidance being given in Table 2.
When carrying out near capacity lifts, with three or four leg slings, the Foreman should
refer back for technical advice on the choice of lifting slings, as multiple leg slings are
rated on equal loading in each leg.
In the case of a four leg sling, two legs may take majority loading, whilst two act as a
balance with minimal loading.
Many chain manufacturers produce illustrated tables, which clearly identify the SWL at
different angles. Where such tables are available from manufacturers, a copy should be
issued to the Foreman for his reference on site.
Table 2
Chain Slings
Dia
in mm
7
8
10
11
13
14
16
19
1.5
2
3.2
3.8
5.4
6.4
8.2
11.5
0o
3
4
6.4
7.6
10.8
30o
2.9
3.9
6.1
7.3
10.4
60o
2.6
3.5
5.5
6.6
9.3
11
90o
2.1
2.8
4.5
5.3
7.6
8.9
11.6
120o
1.5
2
3.2
3.8
5.4
6.4
8.2
11.5
Endless
Slings
2.4
3
4.8
5.7
8.1
9.6
12.3
SPECIAL NOTE
The loads listed for four-leg slings are based upon the traditional method of
calculation which assumes that the load is equally shared by the four-legs. The latest
ISO and BSI specification recommend that a general purpose four-leg sling should be
rated at the same working load limit as a three-leg sling of the same size and grade,
on the assumption that one leg of a four-leg sling may be taking a disproportionately
small share of the total load. Users may wish to consider the adoption of these latest
recommendations.
45
ACA
SEPTEMBER 1998
In extreme cases where a component length or building headroom causes the angle between
chain legs to become excessive, the use of a lifting beam should be considered.
46
ACA
9.4
SEPTEMBER 1998
Documentation - Certificates, Records and Registers
The person delegated to be in charge of the lifting operation will be responsible for
checking all documentation.
Crane:
Operator:
Lifting
Equipment:
for cranes less than 14 months old or within 14 months of Test and
Thorough Examination - not required.
For many years there has been a requirement within the Construction (Lifting
Operations) Regulations 1961 to have cranes and lifting equipment tested and thoroughly
examined with the results recorded on prescribed forms.
Prior to 1992 there were standard prescribed forms, as noted in brackets above.
With the exception of F91 Section C, from 1992 these forms are no longer required to be
used, providing the form used shows the prescribed particulars, as required by the 1992
regulations.
9.5
47
ACA
SEPTEMBER 1998
On certain types of contract it will be necessary for additional Signallers to be used,
primarily to guide units through roof structures or around obstructions.
In instances where more than one Signaller is used, the general requirements for
Signallers apply but only one person should give signals direct to the operator.
9.6
Ensure that all personnel involved are familiar with the Safe Working Method
Statement/Safe System of Work and fully briefed on their roles and
responsibilities.
2.
Discuss with all personnel involved the intended lifting operation and weight of
loads being lifted including the heaviest load and maximum radius of operation.
3.
Before allowing the crane to enter the work area, the Foreman and the Crane
Operator should ensure by joint inspection that the access, working and adjacent
areas are safe and suitable, particular attention being paid to overhead
obstructions and trenches, cellars, basements, ramps and slopes. Recently
compacted fill of trenches or excavations should be avoided. All proximity
hazards should be identified and appropriate action taken.
4.
Ensure that the Crane Operator can identify and understand those who are to give
signals and that all are aware of the code of signals that are to be used. See
table of recommended Crane Signals.(page 49)
48
ACA
SEPTEMBER 1998
RECOMMENDED CRANE SIGNALS
49
ACA
9.7
SEPTEMBER 1998
Control of the Lifting Operation
Lifting operations should be controlled by the authorised Slinger/Signaller/Banksman
who will be in attendance at all times and whose duties will include:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Supervise the manoeuvring of the crane onto and across site and into the
required position ensuring that the public and other site personnel are not being
put at risk.
Discuss with the Crane Operator, ground conditions and ensure that the outrigger
jacks are adequately supported on the ground.
Ensure that the lifting tackle is of adequate SWL, of suitable sling leg length for
sling angle and that a hand line is available for use if required.
Ensure that before lifting, site personnel have been warned of the lifting
operation and are clear of the working area of the crane.
Ensure that during lifting and placing loads the crane is lifting within safe
working load, radius and capacity.
When lifting from transport off site or with the crane positioned offsite,
particular attention must be given to pedestrians and traffic management.
Ensure that the jib load and slings are clear of obstruction at all times.
Ensure adequate clearance for slewing of the tail-weight.
Monitor the lifting operation continuously to ensure that it progresses safely.
Be prepared to stop the operation if personnel or the crane are working unsafely,
or for any other reasons.
50
ACA
SEPTEMBER 1998
10.
TRANSPORTATION OF COMPONENTS
10.1
10.2
Loading Sequence
In order to ensure safe, evenly distributed loads it is not always possible to load
vehicles in the exact erection sequence. What should be achieved, however, is vehicle
sequences corresponding with the general fixing sequence agreed between the Company
and the Contractor.
10.3
Site Access
Before a vehicle arrives on site, the access from the highway onto and around the site
should have been agreed between the Company Representative and the Contractor. The
Foreman should have checked access suitability with the Contractors Site
Representative upon site commencement.
51
ACA
SEPTEMBER 1998
Notwithstanding the above, the final acceptance of the access and the unloading area
should remain with the vehicle driver, and in these circumstances the driver should
satisfy himself before entering site that his vehicle can travel safely on the access
provided and if deemed necessary, seek assistance.
In all cases the driver should not remove any securing ropes, chains or tarpaulins until
his vehicle is at rest in the area agreed for unloading.
10.4
Unloading
The Foreman should ensure that the correct lifting equipment, and where applicable,
special lifting equipment, is available on site to offload components. As smaller
components are generally delivered on pallets, it is important to ensure therefore that the
correct lifting appliances are available for off-loading, e.g. forks.
The Slinger should ensure that the delivery vehicle is positioned on a level
hardstanding, clear of site debris and within the radius capacity of the site craneage.
The Slinger should also visually inspect all cast in lifting devices to ensure that no
damage has occurred during loading or deliveries.
Components should be unloaded in such a manner that the stability of the delivery
vehicle is not adversely affected. The Slinger should (when necessary) liaise with the
delivery vehicle driver to ascertain the most suitable unloading sequence, particularly
when A frames, or other special delivery frames or racks are being used. When
special frames are used it is important to ensure that the frames are properly anchored to
the delivery vehicle and each unit is independently attached to the frame.
52
ACA
SEPTEMBER 1998
When components are taken straight from the vehicle to their fixing position, care must
be taken to ensure that any loose packings or protective materials have been removed
and that any nuts, bolts or fittings are secure.
Cladding components which require to be pitched to facilitate erection, should be
lowered to the ground and pitched from there.
When considering large panels, purpose made tilting or turning equipment should be
used to pitch such units (refer to 13.4).
In circumstances where components may have to be lifted or passed over the cab of the
delivery vehicle, the driver should remove himself to a place of safety, until advised by
the Slinger that the lifting operations have ended. Delivery drivers must always wear
the appropriate PPE for the site in question. Where vehicles are off-loaded off site, the
vehicle and surrounding area will be deemed part of the construction site for the
purposes of the PPE Regulations. There should, under no circumstances, be any person
under or adjacent to a load being lifted during unloading operations. All persons not
directly concerned with the lifting operation should be excluded from the unloading
area.
53
ACA
SEPTEMBER 1998
54
ACA
SEPTEMBER 1998
11.
11.1
55
ACA
SEPTEMBER 1998
Whenever A frames or racks are used in connection with the site storage of
components, ensure:
(i)
(ii)
(iii)
(iv)
Access to the components for the purpose of affixing or removing restraints or lifting
tackle should be by way of ladders, to deter men from climbing the frame, rack or
component.
In instances where doubt exists concerning any aspect of site stacking, the Foreman or
Companys Representative should refer back to the Company before allowing units to be
stacked.
11.2
56
ACA
SEPTEMBER 1998
12.
ACCESS
12.1
General
Access onto and about the structure is normally provided by the contractor, by means of
stairs or scaffolding. However temporary access to fixings etc. in the form of ladders,
tower scaffolds, stagings and power operated mobile platforms is usually provided by
the Company.
The Foreman should visually inspect all means of access provided for use during the
erection process, and any defects noted should be brought to the attention of the
Company, or where appropriate the Contractors Site Representative, so that the
particular item can be replaced, before it is used.
Type of access and working places are summarised in Table 3, pages 64 to 66.
57
ACA
SEPTEMBER 1998
The painting of ladders is prohibited under the Construction (Health, Safety and
Welfare) Regulations 1996.
It is recommended that alternative means or methods be provided to prevent work being
carried out from ladders, wherever reasonably practicable to do so. The use of
lightweight mobile scaffold towers and other alternative working platforms should be
fully explored.
Properly secured ladders combined with the use of harnesses, safety belts, static lines,
or anchorage points may also be practicable in certain conditions where the working
height precludes mobile towers.
58
ACA
SEPTEMBER 1998
12.1.3 Stagings
When stagings e.g. Youngman type boards, are provided to form temporary access or
working areas, these should be lashed to the structure, or otherwise secured, to prevent
excessive movement or dislodgement. Should it become necessary to move stagings
during the course of the erection process, the Company Representative should designate
a competent person(s) to carry out this work, and he should satisfy himself of the
stability of the staging (s) before recommencing work.
59
ACA
SEPTEMBER 1998
ii.
iii.
iv.
the capacity.
v.
the terrain.
vi.
working environment.
Working platforms can be self propelled, static, or vehicle mounted. If the working
platform is self propelled, the route across site should be chosen with care, avoiding
uneven surfaces, obstructions (similar procedure to that for cranes - 9.2 refers) and
wherever necessary additional hard-core or similar measures should be implemented to
minimise the unevenness of the site.
Power operated mobile work platforms should be operated and maintained in
accordance with BS 7171.
Only persons appointed by the Company, who are trained and Certificated in the safe
operation and maintenance of this equipment, should be allowed to operate it.
The following precautions should be observed when operating a working platform.
a)
b)
c)
d)
e)
f)
60
ACA
SEPTEMBER 1998
g)
h)
i)
carry out daily and periodic checks as per the manufacturers instructions.
do not use the working platform in wind conditions likely to affect stability
(The maximum height/wind speed data are available from the supplier).
A full body harness must be worn by the operator(s) and attached to a suitable
anchorage.
A six monthly inspection should be carried out by a competent person, who will issue a
certificate to state that the working platform is safe for use.
12.2
Scaffolding
The provision of scaffolds etc. is subject to the construction (Health, Safety and
Welfare) Regulations 1996 and BS 5973 : Code of Practice for Access and Working
Scaffolds.
The Company Representative will consult with Contractors Site Representative to
agree the basic details of the scaffolding, the area affected, the implications and any
special arrangements to be made.
The Company Representative will give a clear instruction to the scaffold designer,
preferably in writing, with basic information regarding:
i.
ii.
iii.
iv.
v.
vi.
Protection required.
There should also be a clear instruction that the scaffold will comply with the
Construction (Health, Safety and Welfare) Regulations 1996.
Where the Company Representative is responsible for appointing the scaffold company,
he shall satisfy himself as to the competence of that company to carry out the work.
The erection Company will provide a competent person who will oversee the erection,
check the suitability of materials and ensure compliance with the Regulations and the
companys requirements.
The Company Representative will obtain a handover certificate signed by the competent
person, stating the scaffolds compliance with the Regulations.
61
ACA
SEPTEMBER 1998
The Company Representative/Foreman will inspect any scaffold before his men work
on it, to satisfy himself that it complies with the regulations, in particular he should
check that:
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
12.3
Edge Protection
The responsibility for providing protective measures at the edges and openings should
be clearly defined and recorded before work commences.
It is usual for edge protection to be provided by way of an Attendance by the Contractor,
and in such circumstances the Foreman and Supervisor should liaise with Contractors
Site Representative so that precise requirements and timing can be agreed.
In all cases the Foreman must ensure that his operatives are not subjected to an
unacceptable level of risk, and if necessary cladding erection should be suspended until
protective measures have been installed. Whenever work is suspended the Foreman
must advise the Company of the situation.
62
ACA
SEPTEMBER 1998
The operatives engaged in the erection of the precast cladding must not remove or in any
way interfere with any protective measures provided by the Contractor or others,
without prior consultation.
Should protective measures require maintenance, removal, or adaptation the Foreman
must liaise with the Contractors Site Representative for the latter to assign an
experienced competent person to execute such works. Should it be necessary for
operatives to work beyond the safety of edge protection then full body harnesses must be
used, attached to a suitable anchorage.
In circumstances where the company provide their own protective measures at edges or
openings, the role of the Foreman and Company Representative are unaffected, other
than they will liaise with scaffolding sub-contractors, or the Companys plant or stores
department.
All measures provided, irrespective of their origins, must comply with the requirements
of the Construction (Health, Safety and Welfare) Regulations 1996.
12.4
63
Table3
Method
Examples of use
References
Comment
A Temporary
Ladders
Vertical
Access up columns
BS1129
BS2037
Fix to column prior to erection, preferably on faces within building line. Ladders
and stepladders should be of good construction without defects; space to be
allowed for toes behind ladder.
Where possible, max length without resting place 9m
Inclined
BS1129
BS2037
Step ladder
Good base
positions only
BS1129
BS2037
BS5323
(Scissor lifts
only)
Manufacturers
instructions
Erection should be planned so that , for instance, previously erected pieces will
not hinder the operation.
Ground conditions for both use and access to the point of use should be
satisfactory;
Gives increased speed of access;
Can enable some connections to be made in poor weather, that may not
otherwise be possible.
Scissor Lifts
Other mobile platforms
Manriding skips
BS2830
Tower scaffolds
Making connections
(particularly lower level and
roof)
Firm foundation;
Sound, even surface;
Erected by competent persons only;
Height to base with ration can be critical and
should be checked for stability;
Safe means of access to working places.
BS1139
BS5973
Suspended
cradles
Remedial work on
completed structure
BS5974
Maximum load clearly indicated. Fall arrest device, on secondary safety rope,
to be provided where possible.
BS2830
Table3 cont
Method
References
Comment
Non-mobile platforms
Common or
proprietary
scaffolds
Construction of ladder
access towers.
BS1139
BS5973
Purpose built
platform (i.e.
fabricated)
At connections where a
large number of fasteners
require fixing;
At eaves level in timber
house construction;
Circular steel tank
construction
BS5950
General access;
Working place;
More than one unit may be
required to provide sufficient
width for intended use
BS1129
BS2037
Scaffold boards
As above
BS2482
Edge protection
Securely fixed;
Adequate to take loads
BS5950
BS6180
Clips which could open up under load should not be used; Proprietary systems
are available; Types which can be fitted before erection are recommended.
Table3 cont
Method
References
Comment
BS8093
BSEN1263-2
BS3913
BSEN1263-1
1977
Safety harnesses
and belts
BSEN354
BSEN355
BSEN358
BSEN361-365
Manufacturers
instructions
The use of harnesses is preferred as this reduces injuries should a fall occur;
Harnesses or belts, which incorporate tool frogs and pouches encourage their
use:
Competent person to check and maintain.
Safety lines
BSEN353
BSEN355
BSEN362-365
BS5062
Safety eyebolt
BSEN795
Walkways and
Stairways
General access
BS4592
BS6180
Ladders
BS4211
B Permanen
ACA
SEPTEMBER 1998
13.
13.1
Barring
Cladding components should be positioned as near as possible to their finally fixed
position upon the structure to minimise the operation of secondary movement. However,
the use of pinch or crow bars to move components into their final position is common to
all types of cladding.
When moving components, care must be taken to ensure that the units are not damaged.
In addition, care must be taken to avoid any damage or movement in the bearing on
which the components are seated.
Components should be positioned or moved by a succession of small movements. No
attempt should be made to slide or lift units for distances which would cause the
person(s) involved in the operation to lose their balance, or to hold excessive weight on
a bar.
In whatever situation bars are used, there are basic precautions which must be observed.
The bar itself should be of sound construction and of adequate strength. The end of the
bar should be shaped such that it can gain maximum purchase onto the component to be
moved, and the heel of the bar should be able to fully bear onto the component or surface
being barred against.
Brickwork, blockwork or other masonry should not be used to provide a surface to bar
against, and where a possibility of damage to other surfaces exists, protective measures
should be employed to prevent spalling or fracture.
13.2
Jacking
Jacks are sometimes used in a number of situations during cladding erection. It is
important to ensure that jacking is carried out in a safe and proper manner, using correct
equipment.
Whenever jacks are used, they should be of adequate strength and capacity to safely
raise and hold the load. Steel or hardwood wedges should be used to provide an
additional safeguard when a component is required to remain raised for some time.
When jacking up a component, the Foreman should ensure that the jack is sited on a firm
level base. If jacking from a floor, he should ensure by reference to the Contractors
Representative, that the floor is capable of safely supporting the jack and the weight of
any load being raised.
Components should only be raised a few millimetres by this means, greater lifts or
movement should be undertaken by lifting appliances.
67
ACA
SEPTEMBER 1998
Where jacks are employed to apply side thrust to components, purpose-made jacks
should be used and the Foreman must ensure that the component is capable of
withstanding the load imposed by the jack, by reference to the Company if necessary.
In all cases, jacks must be used in compliance with the instructions and
recommendations of the manufacturer. The Foreman should conduct regular visual
examinations of jacking equipment. Any defective items should not be used.
13.3
13.4
68
ACA
SEPTEMBER 1998
pitching operation. There should be provided suitable adequate measures to lock the
table or frame in position during the transfer (if necessary) of lifting equipment from
table or frame to the precast component, or at any other time during the lifting operation.
Suitable locations should be agreed between the Company and Contractors
Representatives for the operation of the tilting table/pitching frame during the course of
the works, with due regard to crane access.
Tilting tables or pitching frames should be so designed and constructed that there is no
need for an operative to pass or work under the component whilst it is elevated on the
table or frame.
The Company Representative must ensure that all operatives engaged in the use of such
equipment are competent and familiar with their operation.
The Foreman should also conduct regular inspections of the table or frame whilst in use
to ensure that its safe operation is not impaired as a result of damage or defect.
Although not classified as a lifting device, it is recommended that the safe working load
of the table or frame is indicated on the equipment.
13.5
Bogies
In situations where units cannot be transported directly to the lifting facility by the
delivery vehicle i.e. within or through the structure, bogies are often used as the
secondary form of transport.
The construction of bogies will vary according to their requirements, but the basics will
remain the same. They must be designed and constructed to be of sufficient size, strength
and stability to safely support the weight of the component during loading, transportation
and unloading.
During transportation the precast component should be suitably positioned upon and, if
necessary, secured to the bogie to create a stable load. Care should be taken to avoid
damage to the component or the structure from impact due to a direct collision or from
excessive unevenness of the floor surface.
The route across a floor should be planned in advance by the Company Representative
and Foreman and agreed with the Contractor to ensure that the floor is of sufficient load
bearing capacity and will be clear and free of obstructions and debris etc.
13.6
Manual Handling
69
ACA
SEPTEMBER 1998
Definition
Manual Handling means the transporting or supporting of a load, lifting, putting down,
pushing, pulling carrying or moving of a load by hand.
General Provisions
General Provisions - employers must take appropriate measures to avoid the need for
manual handling by using mechanical equipment, and where manual handling cannot be
avoided, then the risks must be reduced.
Organisation - where manual handling cannot be avoided, the employer must organise
the workstations to make handling as safe as possible and assess the conditions of the
type of work involved, the environment and the activity.
Information and Training - employers must ensure that workers receive, where possible,
precise information on the weight of the load and its centre of gravity (where necessary).
Workers must also receive proper training on how to handle loads correctly.
Consultation - employers must have consultation and participation of workers.
The Duties of Employers:
1.
a)
b)
c)
d)
i.
ii.
2.
a)
b)
70
ACA
SEPTEMBER 1998
Regulation 5
The duties of employees:
1.
a)
Take reasonable care for their own health and safety and that of others who may
be affected by their activities.
Co-operate with their employer to enable him to comply with his health and
safety duties; and
Make full and proper use of equipment or system of work provided.
b)
c)
71
ACA
SEPTEMBER 1998
72
ACA
14.
SEPTEMBER 1998
ADDITIONAL ON SITE WORKS
Elements of this section will involve the use or production of substances hazardous to
health. Due consideration should be given to the relevant manufacturers health and
safety data sheets and in particular the following statutory regulations:
Management of Health and Safety at Work Regs. 1992.
Provision and Use of Work Equipment Regs. 1992
P.P.E. Regs 1992
C.O.S.H.H. Regs 1994
The Construction (Health, Safety and Welfare) Regs. 1996.
Electricity at Work Regs. 1989.
Noise at Work Regs. 1989.
14.1
Temporary Propping
Where fixing details dictate that precast units rely upon other panels for their restraint it
is often the case that temporary restraint is required until further units have been erected.
An example of this would be the top restraint to a mullion unit which is fixed to the
bottom of a spandrel unit, which sits above and is positively restrained and supported
by the structure.
This temporary restraint is normally provided in the form of push/pull props which are
attached to the rear of the unit via cast in sockets and bolts and to the floor slab via
drilled in fixings. The propping height in the precast panel must always be above mid
height and preferably as close to the top of the unit as is practicable. The fixings into the
slab should be positioned to achieve a propping angle of between 45 and 60 to the
horizontal.
The precise detail of propping angles and number of props should be determined by the
Designer, together with the sequence of installing and dismantling temporary propping
which should also be included in the Safe Working Method Statement for the work.
14.2
Insitu Concrete
Insitu concrete work must be executed in accordance with the Working Drawings and
Safe Working Method Statement.
Insitu concrete used in connection with precast cladding is usually a means of providing
a permanent connection to the supporting structure or adjacent precast component
incorporating the use of formwork and temporary support from propping, until the insitu
concrete achieves the required strength.
When formwork is used, this must be of sufficient strength to support its own weight, and
that of the concrete, together with reinforcement and the weight of any operatives or
plant engaged in the work. Formwork should be designed, constructed and erected by
competent persons and should be closely examined before, during and after the placing
of concrete, in accordance with the requirements of current recommendations and
legislation (see BS5975 1996 - Code of Practice for Falsework).
73
ACA
SEPTEMBER 1998
Where props are used to support the formwork these should be designed by a competent
person with due regard to number and position and installed as directed by the Designer.
Formwork and temporary props should only be removed after the concrete has achieved
sufficient strength, and the curing time allowed should be as stated by the Designer.
Whilst insitu work is in progress, the Foreman should ensure that the area beneath the
work being executed is kept clear of all personnel.
14.3
14.4
Jointing
The procedure for jointing works should again be carried out in accordance with the
Working Drawings and Safe Working Method Statement which determines the material
specification and joint details. Although open drained and filled joint systems are
available, it is the latter which is most commonly used. This system involves an
external filler of sealant (polysulphide or silicone) normally gun applied onto primed
surfaces and invariably requires a safe means of external access, e.g scaffolding,
cradles, etc. Additionally internal seals of proprietary preformed strip material are
commonly used, which are installed as cladding erection proceeds from within the
supporting structure.
In all instances the seal material must be handled and used in accordance with the
manufacturers recommendations.
14.5
74
ACA
14.6
SEPTEMBER 1998
Final Finishing and Cleaning Down
Upon completion of an area of cladding and prior to handover to the Contractor, final
finishing and cleaning down are carried out. These works should be carried out in
accordance with the Safe Working Method Statement, which determines the material
specification and safe means of external access which should be provided for these
operations.
14.7
75
ACA
SEPTEMBER 1998
The Company has a legal responsibility to ensure that any person who uses a concrete
saw including the changing of abrasive wheels or discs has attended a course of
instruction and has a current certificate in the safe handling and usage of abrasive
wheels as prescribed in The Provision and Use of Work Equipment Regs 1992 and the
Abrasive Wheel Regulations Regs 1970 and is appointed by the Company.
Where possible, drilling and cutting should be carried out in the open air and away from
other people. Attention should be given to the area around the operation to avoid
inconvenience and danger to other work people and the public and great care should be
taken to prevent hazards from falling debris.
Precast concrete components should not be cut by persons other than the Companys
employees, qualified as previously described, without reference to and authority from
the Company. In all cases care must be taken to avoid damage to other components or
work near to the component being cut.
14.8
All
Health and Safety Executive Guidance Note EH55 gives information on the health risks
associated with welding processes.
76
ACA
SEPTEMBER 1998
Other information on welding safety is available from suppliers booklets, e.g. BOC
Safe Under Pressure - Guidelines for all who work with Cylinder Gases.
Site welding and cutting is a specialised operation, which should be undertaken only by
operatives who have undergone a course of training, are in the opinion of the Company
competent to carry out welding operations and are Certificated if necessary in the
appropriate classes. The Company Representative must ensure that welding is carried
out only by trained operatives.
77
ACA
SEPTEMBER 1998
78
ACA
SEPTEMBER 1998
15.6
15.1
15.2
79
ACA
SEPTEMBER 1998
During the course of the lifting operation the Signaller/Banksman must ensure that
members of the public are not in the vicinity of the suspended load or lifting equipment.
On sites where the building operations are in close proximity to public places or
highways, additional care must be taken to prevent materials or debris falling from the
works. Where the Contractor has provided measures to prevent such falls, or to protect
the public, the operatives engaged in the erection of the cladding must not remove or
interfere with these measures in any way whatsoever.
When the installation involves the operation of a crane in third parties air space, the
contractor should obtain the necessary permissions and ensure that the appropriate steps
are taken to protect third parties and the public in these areas.
Any debris or material which falls from delivery vehicles must be removed from the
public highway, or public areas, and the area left clean and hazard free.
The Foreman should liaise and co-operate in all respects with the Contractors Site
Representative, to ensure compliance with any measures, provisions or rules previously
agreed with the Contractor, or with any statutory provisions for the protection of the
public.
80
ACA
SEPTEMBER 1998
1.1
The Contractor shall provide and maintain hard access roads, onto and around the site
and also hardstandings, entirely suitable for the operations and for the safe passage and
working of cranes and delivery vehicles. Maintenance of the same should take into
account deterioration due to adverse weather, continued use, etc.
For the guidance of the Contractor, the precast cladding sub-contractor shall provide
information regarding the delivery vehicles and cranes on which their Quotations are
based.
1.2
Should road signs, bollards, etc., or police permission be required in connection with
such access, then the provision of, or application for them, as the case may be, shall be
the responsibility of the Contractor.
1.3
Where erection operations are to be carried out from the public highway, all road signs,
traffic control and the like, and necessary permissions, shall be the responsibility of the
Contractor.
1.4
1.5
Where craneage is working the Contractor must consider the work area to be a
prohibited area and ensure that adequate precautions are taken to protect other trades
and members of the public.
2.
AERIAL OBSTRUCTIONS
2.1
The Contractor shall be responsible for the re-routing, removal and/or making safe prior
to the arrival on site of the precast cladding sub-contractor of any aerial obstructions
which are likely to foul or hinder a crane boom or suspended load, and also for their
subsequent replacement. He shall be responsible also for the protection of power lines
or other services and, where applicable, the issue of notifications to third parties.
2.2
Where permission is required to operate within the air space of third parties,
appropriate authority shall be obtained by the Contractor.
81
ACA
3.
SEPTEMBER 1998
GENERAL
The Contractor shall provide the following:
3.1
Level and grid datums at each floor level adjacent to fixing positions
3.2
Clearance of debris etc. to facilitate movement of equipment and access to fixing points.
3.4
Accurate and properly prepared fixing positions, marking out, forming, drilling of all
holes, mortices, pockets etc., for bolts, dowels or similar type fixing, casting-in sockets
in insitu concrete and/or steelwork.
3.3
A cradle or alternative for sealant works, cleaning down and any minor finishing items
3.5
Any necessary protection and cleaning once agreed sectional completion/phased areas
or the whole of the works have been handed over for acceptance.
4.
SCAFFOLDING
4.1
4.2
Access to working areas shall be provided by the Contractor and should be by way of
stairways, ramps, ladders, mobile towers or the like, properly constructed, maintained,
secured and illuminated.
WELFARE
5.1
All welfare facilities shall be afforded to the precast cladding sub-contractor by way of
an attendance by the Contractor, including:
a)
b)
c)
Water supply
d)
Space for offices with provision for temporary lighting supply and storage.
e)
f)
If the Contractor shall fail to make available any of the facilities above stipulated to be
provided by him, the precast cladding sub-contractor may at his sole option suspend
work on the contract until the required facility has been made available.
Any delay in the performance of the works arising from such suspension shall not be
deemed a failure on the precast cladding sub-contractors part to proceed with the
works in accordance with the provisions of his sub-contract, and he shall be entitled to
claim against the Contractor in respect of any loss, damage or expense he may have
suffered by reason of the Contractors default or the delay caused thereby.
82