NJDCA Eplan App User Manual
NJDCA Eplan App User Manual
NJDCA Eplan App User Manual
By
Avolve Software
http://dcaplanreview.nj.gov
Applicant User Guide V.2.8 In addition to this user manual, please refer to
June 23, 2016 the instructions provided in the ProjectDox
system.
Applicant Users Guide Electronic Review 2 New Jersey Department of Community Affairs
Contents
NJDCA ePlans ................................................................................................................................................ 5
Getting Started.......................................................................................................................................... 5
Technical Support ..................................................................................................................................... 5
System Requirements ............................................................................................................................... 5
Security Timeout ....................................................................................................................................... 5
File Standards ............................................................................................................................................ 5
Required Files........................................................................................................................................ 5
Layout Standards .................................................................................................................................. 6
Signatures and Seals ............................................................................................................................. 7
File Naming Standards Building Plans ................................................................................................ 7
File Type Standards ............................................................................................................................... 7
Folder Structure ........................................................................................................................................ 7
Drawing & Specifications Folder ........................................................................................................... 8
Documents Folder ................................................................................................................................. 8
Released Folder..................................................................................................................................... 8
DOs and DONTs ........................................................................................................................................ 9
Logging into DCAs ePlans System .............................................................................................................. 10
Navigating the Home Screen/Dashboard ............................................................................................... 10
Starting a new application .................................................................................................................. 10
Initial Plan Submission ................................................................................................................................ 14
Uploading Files ........................................................................................................................................ 14
Prescreen Review ........................................................................................................................................ 18
Prescreen Correction Request ................................................................................................................ 18
Plan Review ................................................................................................................................................. 23
Applicant Resubmit ................................................................................................................................. 23
Review Cycles .............................................................................................................................................. 28
Reviewing Changemarks (Markups) ....................................................................................................... 28
File Versions ........................................................................................................................................ 29
Printing Changemarks ............................................................................................................................. 29
Option One (Pasting into a Word document) ..................................................................................... 29
Option Two (Creating a PDF file)......................................................................................................... 30
Plan Release ................................................................................................................................................ 31
Print Released Plans ............................................................................................................................ 31
Amendments............................................................................................................................................... 32
Amending Final Releases ........................................................................................................................ 32
Amending Partial Releases...................................................................................................................... 32
Questions or Problems............................................................................................................................ 32
Adding New* Files....................................................................................................................................... 33
Applicant Users Guide Electronic Review 3 New Jersey Department of Community Affairs
Reports ........................................................................................................................................................ 34
Site Wide Reports ................................................................................................................................... 34
Project Reports ....................................................................................................................................... 34
Vista and Windows 7 Install Instruction ..................................................................................................... 36
Uninstall-reinstall DCA Electronic Plan Review components.............................................................. 36
Turning Off UAC in Windows Vista and Windows 7 ........................................................................... 36
Turning off Protected mode in IE8 ...................................................................................................... 36
Applicant Users Guide Electronic Review 4 New Jersey Department of Community Affairs
NJDCA ePlans
NJDCA ePlans (ProjectDox) is a web-based solution that will allow building plans to be submitted and
reviewed electronically.
See DOs and DONTs on page 9.
Getting Started
Review the standards for how to name your drawing and documents files, border spacing, acceptable
file formats, etc. (See File Standards, below.)
Technical Support
NJDCA Help Desk: (609) 292-8134 or [email protected]
Please be as specific as possible describing your question in your phone message or the Subject line and
text of your email.
System Requirements
You may use Internet Explorer v10.0 or higher, Google Chrome, or Firefox to access the ePlans
system.
Prior to logging into ePlans, the following actions must be completed:
If your computer has pop-up blockers installed, disable pop-up blocking for the ePlans systems
web address (http://dcaplanreview.nj.gov). If pop-up blockers are still active, when you type in
your login and password and hit the Login button, the page will immediately disappear. You
might have more than one pop-up blocker installed (Internet Explorer, Google Task Bar, etc.).
Once the dcaplanreview.nj.gov site is allowed, you will be able to run the application.
If you are using Internet Explorer, a link to a Microsoft Silent Install (MSI) component (required
to install all the necessary ProjectDox ActiveX controls) is available on the login page. This
installation will only need to be done once per computer. If use a different computer to access
ePlans, you will need to install the ProjectDox ActiveX controls on that computer, too. Please
refer to the Vista and Windows 7 Install Instructions on page 36 if you are running Windows 7 or
Vista on your computer.
Security Timeout
Due to security and resource concerns, the system will automatically sign you out after 60 minutes of
inactivity. When you are ready to resume working with the system, click any button on the screen. The
system will automatically load the login page. You can also close the web browser window and reload
the login page manually in a new browser window.
File Standards
Required Files
Scope of Work a brief narrative describing the work to be performed.
For renovations or additions to existing structures, the Scope of Work will fully describe any current
existing conditions (i.e., building Use Group(s), Construction Type, Height & Area, extent of demolition,
etc.), the new intended use of the structure or spaces within the structure, Project construction phasing
(if applicable), and all proposed new work.
For new structures, the Scope of Work will fully describe the intended building (i.e., building Use
Group(s), Construction Type, Height & Area, etc.), the intended use of the structure or spaces within the
structure, Project construction phasing (if applicable), and all work to be done.
Applicant Users Guide Electronic Review 5 New Jersey Department of Community Affairs
Confirmation of Professional Certifications Design professionals must send a signed and sealed letter
attesting that the electronic documents submitted were developed under their supervision. A hard copy
of this letter must be submitted to the DCA Plan Review Unit. The applicants must also scan and upload
a PDF of the letter into the Documents folder when submitting their plans.
Mailing Address: New Jersey Department of Community Affairs
Bureau of Construction Project Review
Intake and Admissions
101 South Broad Street, 4th Floor
PO Box 817
Trenton, NJ 08625-0817
Drawing and Specification Files All required drawings following State standards for submission (along
with other information required by the Plan Submission Checklist found in the Plan Review Instructions,
available on the Bureau of Construction Project Review site
http://www.nj.gov/dca/divisions/codes/offices/bcpr.html).
Index A listing of all project drawings that must be uploaded into the Index sub-folder under
Drawings. The index may be appended through the course of the project, but existing files on the index
must not be renamed.
! Narratives Provide a narrative every time files are submitted (or resubmitted) for a particular subcode,
including amended drawings. Upload the narratives into the proper subcode Documents folder.
Supporting Document Files All other required files that are part of the plan submission but are not
drawing files (i.e. Drainage Calculations, Easement letter, certifications, etc.) and will not require a DCA
Release stamp.
Layout Standards
! Drawings
All uploaded drawings must be configured in LANDSCAPE orientation.
The top right corner of all drawings must be reserved for NJDCAs electronic release stamps. Please
leave the top right corner completely blank on all drawings (with the exception of the border). Stamp
location box dimensions should be 3 width x 3 height (3/4 from edge of paper in both directions).
! Specifications
The top right corner of the first page must be reserved for NJDCAs electronic release stamps. Please
leave the top right corner completely blank (with exception of the border). Stamp location box
dimensions should be 3 width x 3 height (3/4 from edge of paper in both directions).
Applicant Users Guide Electronic Review 6 New Jersey Department of Community Affairs
Signatures and Seals
! Final Plans
An embossed seal and wet signature are required only on the printed, released plans that will reside on
the work site and that are needed for permits to be issued.
IMPORTANT: For state building projects, it is not necessary to submit printed plans to the NJ
Department of Community Affairs.
! Filenames
The file name of any uploaded drawing must match the drawing name/number.
Folder Structure
The Project folder structure is separated into three main folders: Drawings & Specifications,
Documents, and Released.
The Drawings & Specifications and Documents folders each contain subcode folders. Plus (+) and minus
(-) signs to the left of the folder icons allow you to expand or contract the list of subcode folders.
Applicant Users Guide Electronic Review 7 New Jersey Department of Community Affairs
Drawing & Specifications Folder
! Drawings
Each drawing must be uploaded as a separate file to the appropriate subcode folder within the
Drawings & Specifications folder for the Project.
The index of the drawing files is uploaded into the Index sub-folder.
Corrected files are uploaded into the SAME folders as the original files with
the SAME FILE NAMES as the original files. The ePlans system will assign
versions to each file.
! Specifications
Specifications must be saved as one full and complete document.
Individual copies of this document must be uploaded into each of the
appropriate subcode folders within the Drawings & Specifications
folder for the Project.
The associated subcode must be incorporated into each file name. This
will allow each copy of the specifications to be stamped by the
appropriate reviewer.
NOTE: The Elevator Layouts folder should only contain elevator layout
drawings and elevator subcode technical sections.
Documents Folder
Each document (for example, truss calculations, geotechnical reports,
etc.) is uploaded as a separate file into the appropriate sub-folder
within the Documents folder for the Project.
Released Folder
When all corrections are complete and the plans are released by NJDCA,
they will be located in the Released folder. Released plans may be downloaded and printed.
Applicant Users Guide Electronic Review 8 New Jersey Department of Community Affairs
DOs and DONTs
DO accept a Task (by clicking on the name of the Task) before you upload
new plans or files.
DO click the appropriate button to complete a task when you have finished
it, like Upload Complete. If the Task is not completed, DCA will be unable to
move forward with the review.
DO upload a narrative into the proper subcode folder whenever files are
submitted for that particular subcode. For example: if you are submitting (or
re-submitting) files for electrical and plumbing subcodes, include a narrative
for those two subcodes and save them in the corresponding documents
folders.
DONT upload files to a specific subcode review unless you have a Task for
that subcode.
For example, if you recently re-submitted your Electrical drawings for
subcode review; do not upload any additional Electrical drawings until a Task
has been assigned to you for Electrical. Files may be uploaded for other
subcodes (like Plumbing, Mechanical, etc.), as long as a Task has been
assigned for the subcode. If additional drawings or files are uploaded to a sub
code that is currently with DCA for review it causes confusion and may delay
DCAs ability to complete a review.
DONT leave Applicant Response fields blank when returning corrections. Use
the Applicant Response boxes to address each changemark individually. If
you have no response or if no response appears necessary please enter
something like no response, acknowledged, or N/A so the reviewer knows
that you saw the comment.
Applicant Users Guide Electronic Review 9 New Jersey Department of Community Affairs
Logging into DCAs ePlans System
How to get to the login screen
Go to http://dcaplanreview.nj.gov the Welcome screen will be displayed
or
Applicant Users Guide Electronic Review 10 New Jersey Department of Community Affairs
Agree to the Terms And Conditions.
Scroll down to the bottom of the Terms
And Conditions page.
Click the I have read check box.
Click on the Accept & Start My
Application button.
This will take you to the application form.
Applicant Users Guide Electronic Review 11 New Jersey Department of Community Affairs
At the Billing Information screen
Update the billing information, if necessary.
Select your preferred method of payment
from the Payment Options.
eCheck*
Credit Card**
Interstate Agency Wire Transfer
(OPTIONAL for state owned
properties only)***
**If you selected Credit Card, you will be redirected to the NIC USA Payment Service Screen, where you
will enter your credit card information.
***If you selected Interstate Agency Wire Transfer Payment (UAT), you will be brought to the
Interstate Agency Wire Transfer Payment Info screen, where you will enter the appropriate UA
Number.
The Interstate Agency Wire Transfer Payment process may be used to pay application
fees when an architectural/engineering firm is submitting an ePlan application for a
state-owned property. It is not required. The ePlan applicant may prefer to use either
the eCheck or Credit Card payment option.
If wire transfer is used, the funds will be automatically transferred from the property
owner DIRECTLY to the Department of Community Affairs through the NJ Treasury
system.
To use the wire transfer option, the architectural/engineering firm needs to work with
the property owner to obtain a UA Number. To process the wire transfer, the applicant
enters this UA Number in the Interstate Agency Wire Transfer Payment Info screen.
Applicant Users Guide Electronic Review 12 New Jersey Department of Community Affairs
Click the Pay or Pay Now button to submit your payment.
After submitting the payment, a short delay may occur while the system processes the payment.
Applicant Users Guide Electronic Review 13 New Jersey Department of Community Affairs
Initial Plan Submission
Uploading Files
When you have successfully logged into ePlans, a screen with a listing of your assigned Projects will
display.
Applicant Users Guide Electronic Review 14 New Jersey Department of Community Affairs
Click on the Workflow
Portals button.
The upload screen will display two buttons, View Folders and
Upload Files.
Click on the Upload Files button.
Applicant Users Guide Electronic Review 15 New Jersey Department of Community Affairs
Navigate to the file location on your computer
and select or highlight the files you want to
upload. Select multiple files by using the Shift
or Ctrl keys while clicking with your mouse.
Click the Open button and the files selected
will be copied to the upload window.
At this point, you can either Upload the files you have selected
or Add more files. (If you want to add more files to the upload
window, click Add more files.)
To upload the files, click the Upload button.
Applicant Users Guide Electronic Review 16 New Jersey Department of Community Affairs
Click the Upload Process
Complete button.
A popup box will ask, Completing this task will finish your
participation in this step and cannot be undone. Continue?
Click OK.
You have successfully finished the Initial Plan Submission step of
submitting your plans electronically.
Applicant Users Guide Electronic Review 17 New Jersey Department of Community Affairs
Prescreen Review
Prescreening is a cursory review by BCPR of your uploaded documents in preparation for formal review.
Allow a minimum of three (3) working days after you have uploaded your documents for the
Prescreening process to begin.
Applicant Users Guide Electronic Review 18 New Jersey Department of Community Affairs
The eForm is displayed.
Read the information in the text
field.
Click on the View Intake Checklist
link.
After you have made the checklist corrections, log back into ePlans and upload the corrected files.
Remember that corrected files must have the SAME NAMES as the original files.
Applicant Users Guide Electronic Review 19 New Jersey Department of Community Affairs
You will be uploading drawings into the appropriate subcode folder.
You will be uploading supporting Project documents into the
appropriate subcode folder under the Documents folder.
Click the plus sign [+] next to the Drawings folder. This will
expand to display a list of subcode folders.
Click on a subcode folder to display the upload function.
When you open the folder, you will see two buttons, View Folders
and Upload Files.
Click the Upload Files button.
Applicant Users Guide Electronic Review 20 New Jersey Department of Community Affairs
At this point, you can either Upload the files you have selected
or Add more files. (If you want to add more files to the upload
window, click Add more files.)
To upload the files, click the Upload button.
When the eForm opens, place a checkmark in the I have uploaded the corrected and the
Corrections Complete button will display.
Click the Corrections Complete button.
Applicant Users Guide Electronic Review 21 New Jersey Department of Community Affairs
Click OK at the confirmation box.
NJDCA will be notified that the files have been completed or corrected and the Prescreen Review
process will continue.
Once the Prescreen Review process is complete, the Plan Review process will begin.
Applicant Users Guide Electronic Review 22 New Jersey Department of Community Affairs
Plan Review
Applicant Resubmit
If corrections are required following the formal
review cycle(s) of your drawings, you will receive an
email notification from BCPR requesting revised
drawings and/or documents.
To login into ePlans, click the Online Plan
Review System link in the email.
Login to the ePlans system.
Applicant Users Guide Electronic Review 23 New Jersey Department of Community Affairs
The eForm is displayed and should list changemarks.
NOTE: If changemarks are not displayed, click on the Click Here to Load Changemarks link.
Read the text in the Review Comments field at the bottom of the screen.
Review the changemarks.
If you click a link in the Markup column, the full drawing with changemarks will display.
The Details column displays only the changemarks.
Please enter explanatory text in the Applicant Response box.
If no response is necessary, enter N/A. This helps expedite the review process.
If you make any comments, make sure to Save.
Click the Save & Close button.
NOTE: Make the necessary changes to the drawings in whatever software application was used to
create them, for example, AutoCAD. Please circle your changes, comments, or modifications in RED, to
make it easier for reviewers to find them.
Once the drawings have been modified/corrected, upload them into the ePlans system.
Applicant Users Guide Electronic Review 24 New Jersey Department of Community Affairs
At the Main Project screen, click the plus sign [+] next to the
Drawings folder. This will expand to display a list of subcode
folders.
You will be uploading drawings into the appropriate
subcode folder.
If necessary, you may upload an updated Index.
You will be uploading supporting Project documents into
the appropriate subcode folder under the Documents
folder.
Click on a subcode folder to display the upload function.
When you open the folder, you will see two buttons,
View Folders and Upload Files.
Click on the Upload Files button.
Applicant Users Guide Electronic Review 25 New Jersey Department of Community Affairs
Navigate to the file location on your computer
and select or highlight files you want to
upload. Select multiple files by using the Shift
or Ctrl keys while clicking with your mouse.
Click the Open button and the files selected
will then be copied to the upload window.
Applicant Users Guide Electronic Review 26 New Jersey Department of Community Affairs
When the eForm opens, place a checkmark in each of the three check boxes at the bottom of the
screen.
Click the Complete button.
NOTE: the Complete button will not display until all three checkboxes have been checked.
Once the Complete button has been clicked, the Project has been sent back to NJDCA to continue the
Plan Review process.
Applicant Users Guide Electronic Review 27 New Jersey Department of Community Affairs
Review Cycles
The review process will continue until all corrections/modifications have been made and accepted by
NJDCA.
Applicant Users Guide Electronic Review 28 New Jersey Department of Community Affairs
All changemarks will display in the right hand pane.
As you review, click on each changemark and you will
zoom directly into the red line from the reviewer.
File Versions
The file will display the must current version number of
the file, for example, the drawing to the right is version 2
(i.e., V2). Versions can only be managed when corrections
are uploaded with the SAME FILE NAME as the original
file name.
To see previous versions of the file, click the magnifying
glass icon.
Printing Changemarks
Option One (Pasting into a Word document)
Select the Copy Changemarks button.
Check all boxes and change Image Size for larger thumbnails of markups.
Click OK.
Create a new Word document and paste the changemarks into the
document.
Applicant Users Guide Electronic Review 29 New Jersey Department of Community Affairs
Option Two (Creating a PDF file)
Click Publish to create a PDF of the changemarks overlaid on the drawing.
Select Publish to PDF.
Select OK.
In the Publish option screen
Check Burn in Changemarks.
Check Append Changemarks Notes.
Click Publish.
Then choose Save to File.
Click OK.
Select the location to save the file on your computer and click Save.
Applicant Users Guide Electronic Review 30 New Jersey Department of Community Affairs
Plan Release
When plans are released by NJDCA, you will be notified by email. All released plans will be located in the
Released folder.
Applicant Users Guide Electronic Review 31 New Jersey Department of Community Affairs
Amendments
STOP! Amendments are only applicable if either a Partial Release for a specific subcode or Final
Release for the entire project has already been issued. If you are providing new files for subcodes that
have not been released, please follow the Adding New Files process below.
Questions or Problems
Call Plan Review at 609-633-0800 or email [email protected].
NOTE: Currently, submitting Amendments is still a manual process. In the near future, submitting
Amendments will be automated like other tasks in the Plan Review process.
Applicant Users Guide Electronic Review 32 New Jersey Department of Community Affairs
Adding New* Files
If new files (that were not part of the original submission) are being submitted for review, please notify
the Team Supervisor and the Reviewer by using the Notes button. This will help to avoid delays in the
review process and avoid confusion.
After clicking on Notes, select Add Topic at the View Topics screen.
Then click on the Send and Prepare Email button and select the appropriate recipients.
New files are any files that have to be released and were not part of the original project submission.
This does not include revised/modified plans that are being resubmitted as a result of comments
and corrections made by a reviewer.
Applicant Users Guide Electronic Review 33 New Jersey Department of Community Affairs
Reports
ePlan has two levels of reports:
To run a report
Click on the icon next to the desired
report
List of Reports
Project Reports
display data for specific projects.
Menu
Applicant Users Guide Electronic Review 34 New Jersey Department of Community Affairs
Intake Checklist Report
Lists all Intake comments met/not met for Prescreen Review.
Routing Slip Report
Shows the detailed history of individual subcode reviews, including the task name, status, date
created, date updated, users (reviewer and applicant), review cycle, time to complete each.
Review Information
Summarizes the Routing Slip Report, including subcode, start date, cycle & status, reviewers
summary comments, reviewers email, and Intake Prescreen Comments.
Project Status Report
Illustrates the most recent activity for each subcode review, including subcode name, start date,
task name, task status, review status, date assigned, date updated, group name, user name, date
completed.
Schedule of Released Drawings
Lists every released drawing associated with a project organized by subcode.
Applicant Users Guide Electronic Review 35 New Jersey Department of Community Affairs
Vista and Windows 7 Install Instruction
Sometimes users will encounter errors or issues as a result of incomplete installation of the client
components. This is often caused by permissions issues. The instructions below have proved useful in
resolving the security/permissions issues and getting a successful installation. (The account executing