Grid Code Testing
Grid Code Testing
Testing
Karl O’Keeffe
Karl O Keeffe, Colm MacManus, Oisin Goulding
Colm MacManus Oisin Goulding
Operational Services and Performance
November 19th 2012
November 19
1
Content
• Purpose of Grid Code Testing
• Roles of the Customer & TSO
• Testing Overview
• Testing timelines
Testing timelines
• Operational Certificate
p
• Testing Timelines
• Grid Code Testing Known Issues
2
Purpose of Grid Code Testing
• Ensure safe, secure and economic operation of the
, p
Power System
• Demonstrate compliance with the Grid Code
– Issue Operations Certificate
• Test true capabilities of the Generator unit at
Commissioning stage and throughout lifetime of unit
– Contract for Ancillary Services
– Address non‐compliance via remedy and/or derogation
• Assess the level of impact on other users
and the performance of the Power System
3
Customers
• Users connecting to the System must undergo
p g
Grid Code Compliance Testing.
• The following connections undergo this similar
process:
process:
• All Transmission Connected WFPS Generation
• DSO WFPS connections 5MW or more
• CDGU Generating Units testing review
completed.
4
Role - Customer
• Notify TSO Commissioning and Proposed
modifications to Installed Plant as early as possible
• Organise and Demonstration of Compliance as
applicable with Grid Code
• Development of necessary Test Procedures and
signoff at least 10 days in advance of testing.
• Submission
S b i i off the
th test
t t profile
fil & Outages
O t t
to
control@eirgrid.com & SEMO
• Request for ESBI Commissioner as applicable (TEM)
• Completion of Test Reports with Test data
5
Data Requirements - Customer
• Turbine Data Sheets & Models
• Commissioning Programme
• Completion Certificates (wiring / pre & post energisation
signals and control Check)
• Operational Readiness Confirmation
• Installed Plant confirmation
• Raw
R data
d t for
f completed
l t d tests
t t
• Test reports & respond to queries
• Registered Characteristics
• Operational Certificate
6
Agreeing a Test
• Standard list of tests to the Customer (available
(
online)
• Discussion of testing methodology
Discussion of testing methodology
• Alternatives are assessed and agreed
• Grid
Grid Code Tests conducted with normal generator
Code Tests conducted with normal generator
control settings applied.
• Compliance must be demonstrated while
Compliance m st be demonstrated hile
operating within EPA licence limits.
• Submit Test Request & agreed test procedure to
S b i T R & d d
Generator_testing@eirgrid.com with test date.
7
Role - TSO
• Developp Signal
g Lists
• Co‐ordination of testing (Dispatch and GCCT)
• Issue Operational Readiness Confirmation
• Agree Test Procedures for TSO Requirements
• O it Witnessing
Onsite Wit i off tests
t t
• Ensure Communications are clear between Responsible
O
Operators
t and d NCC
• Recommend for Operational Certificate
• Recommend for Ancillary Services with test report
• Handover to Per. Monitoring and Customer Relations
8
Wiring Completion
Testing Overview Certificate
g
Post Energisation
Signals and Controls Signoff
Energise Generator Transformer
g
Post Energisation
g g
Signals and Controls Signoff
Dispatch Testing
Operational Readiness Confirmation
Test Requests
Grid Code Testing
O
Operational Certificate
i l C ifi
9
Testing Timelines (indicative)
Dispatch Testing and
Capacity limits apply Ancillary Service
Agreement
Operational Operational
Energisation
Readiness Con Certificate
Testing Period
Testing Period
Energisation Day to Day Operations / Performance Monitoring
Instructions
DoFs
10
Operational Certificate
• Issued by TSO on successful completion of
y p
Grid Code Compliance testing.
‐ Statement on tests completed successfully
Statement on tests completed successfully
‐ Derogations which are required to address
g q
known non‐compliances
‐ Ongoing monitoring of unit
‐ Conditions for revocation of Ops Cert
11
Operational Certificate
• An Operational Certificate triggers:
p gg
– under the terms of the customer’s Connection
Agreement, the MEC Capacity Bond can be
Agreement, the MEC Capacity Bond can be
released and, if applicable, ‘Firm Access’
applied;
applied;
– under the terms of the Ancillary Service
Agreement receive Ancillary Service payments;
Agreement receive Ancillary Service payments;
– All relevant sections in TSO informed and PCA
parameters provided
t id d
12
Grid Code Testing - Known Issues
• Signalling and Controllability Issues
Signalling and Controllability Issues
• Reliable Forecasting and Scheduling of testing
• OEM travelling from abroad to carry out testing
OEM travelling from abroad to carry out testing
• Test Failures due to lack of Grid Code Knowledge
• p g p
Completion of testing within acceptable time lines
• Continued non‐compliance of legacy Wind Farm Power Stations
• g g
Notification to TSO of registered characteristic changes
• Meeting Reactive Power Requriements
• pp p p
Appreciation of TSOs role to test multiple units in parallel
• Retrospective application of new Grid Code Modifications
13
Dispatch Testing
Colm MacManus
Operational Services and Performance
Team
November 19th 2012
14
Dispatch Testing
• Testing Overview
• Commissioning Programme
• Post Energisation Signals and Controls signoff (3 party)
• Capacity Limits
Capacity Limits
• Dispatch Testing
• Controllability Requirements
• Examples of Pass / Fail
• Reporting
• Operational Readiness Confirmation
Operational Readiness Confirmation
• Categories of Controllability
• Moving Categories (iii) to (ii)
• Reference to Performance Monitoring
• Scheduling and Wind Forecasting
15
Testing Overview
Energise Generator Transformer
TEM
Post Energisation
Post Energisation
M
Signals and Controls Signoff
p g
Dispatch Testing
OSP
O
Operational Readiness Confirmation
Test Requests
Test Requests
Grid Code Testing
Operational Certificate
16
Sample Commissioning Program
17
Controllability Requirements
One key test
One key test
1. The WFPS Active Power Control
1. The WFPS Active Power Control
System is compliant during real time
operation and/or during ongoing
/
performance monitoring and testing of
performance monitoring and testing of
the WFPS.
18
Test 1
1- Active Power Control System
Turn the active power control on or off through SCADA with
acknowledgement from the WFPS;
Series of MW setpoints
p issued to the WFPS with
acknowledgement from the WFPS;
19
Sample Commissioning Program
20
Sample Commissioning Program
21
Controllability Requirements
Post installation of last turbine
Post installation of last turbine
Two key tests
Two key tests
1. The WFPS Active Power Control System is
compliant during real time operation
compliant during real time operation
and/or during ongoing performance
monitoring and testing of the WFPS
monitoring and testing of the WFPS.
2. The Available Active Power Signal of the
WFPS is correct and within the specified
WFPS is correct and within the specified
quality standard.
22
Test 1
1- Active Power Control System
Turn the active power control on or off through SCADA with
acknowledgement from the WFPS;
Series of MW setpoints
p issued to the WFPS with
acknowledgement from the WFPS;
23
Test 2 - Availability signal is within the TSOs
specified quality standard
This signal
Thi i l att a given
i titime iis th
the measure off th
the active
ti power a
WFPS is capable of delivering to the connection point.
This signal
Thi i l should
h ld account ffor unavailability
il bili off any off the
h turbines
bi
i.e. high and low wind speed shutdown scenarios, outages of a
wind turbine generator etc.
24
Successful Dispatch Test
25
Failed Dispatch Test
Availability Signal is not independent of Active Power Output
26
Dispatch Test Report
27
Dispatch Test Report
28
Dispatch Test Report
29
Dispatch Test Report
Successful dispatch test
• PASS means 10 MW increase in Export Limit
p
• PASS means Operational Readiness Confirmation
» If Operational Readiness is achieved, the unit may
now register as VPTG in the market
now register as VPTG in the market
» Units >10MW are required to register as a VPTG in
the SEM
30
Category (iii) Commissioning
• Operational Readiness deadline: 6 weeks from
installation of last turbine
• This group of WFPS will be dispatched in the
event that re dispatch of Category (i) and
event that re‐dispatch of Category (i) and
Category (ii) WFPS is not sufficient.
• Currently 16 WFPS in this category (RoI)
31
Category (iii) Commissioning
Wind Farms Connected in Ireland
Installed
Associated 110kV Capacity
Wind Farm Name Station MW Hierarchy
Altagowlan Corderry 7.65 (iii) Controllability Works Outstanding
Black Banks 2 Corderry 6.8 (iii) Controllability Works Outstanding
Boggeragh Boggeragh 57 (iii) Controllability Works Outstanding
Carraigcannon Boggeragh 23 (iii) Controllability Works Outstanding
Carrowleagh Glenree 36.8 (iii) Commissioning
Coomatallin Dunmanway 6 (iii) Controllability Works Outstanding
Corkermore Binbane 10 (iii) Controllability Works Outstanding
Cronelea 1 Carlow 6.9 (iii) Controllability Works Outstanding
Cronelea 2 Carlow 6.9 (iii) Controllability Works Outstanding
Dromada
o ada Dromada
o ada 28.5
85 (iii) Controllability Works Outstanding
Gneeves Knockeragh 9.35 (iii) Controllability Works Outstanding
Kealkil Ballylickey 8.5 (iii) Controllability Works Outstanding
Lackan Moy 6.9 (iii) Controllability Works Outstanding
Mountain Lodge Ratrussan 31.5 (iii) Controllability Works Outstanding
Mullananalt Meath Hill 75
7.5 (iii) Controllability Works Outstanding
Taurbeg Glenlara 25.3 (iii) Controllability Works Outstanding
Total Hierarchy (iii) 278.6
32
Moving
M i From
F Category
C t (iii) to
t
Category (ii)
• Once Operational Readiness Confirmation is received.
33
Category (ii) - Controllable
34
Category (ii) - Controllable
Wind Farms Connected in Ireland
35
Category (ii) - Controllable
36
Scheduling GCCT
• Calendar system
• One unit per test day
• Mon – Fri (9am – 5pm)
• GCCT testing approx 1.5 days
37
Wind Forecasting
Forecasting Tool by EirGrid
38
Wind Forecasting
• Forecast 5/3/1 days in advance
• Confirmation 1 day in advance
39
Grid Code Testing
Oisín Goulding
Operational Services and Performance
Team
November 19th 2012
40
Grid Code Testing
1. Active Power Control
2. Frequency Response
3. Ramp Rate and Start up Test
Ramp Rate and Start up Test
4. Automatic Voltage Regulation
5
5. Reactive Power Capability
Reactive Power Capability
6. Capacity Test
7
7. Black Start Shutdown Test
Black Start Shutdown Test
41
Active Power Control
Active Power Control
42
Active Power Control
Active Power Control
Series of active power setpoints issued
43
Ramp Rate and Start up Test
Ramp Rate and Start up Test
• Tested with the Active Power Control system
y p
and by local stop/start
44
Frequency Response
Frequency Response
• Curve 1 and Curve 2
• Tested with Active Power Control On and OFF
Tested with Active Power Control On and OFF
45
Frequency Response
Frequency Response
46
Automatic Voltage Control
Automatic Voltage Control
47
Automatic Voltage Regulation
Automatic Voltage Regulation
48
Reactive Power Capability
Reactive Power Capability
49
Black Start Shutdown Test
Black Start Shutdown Test
• Operation of Blackstart Shutdown system
from NCC
• Confirmation of correct operation of
switchgear interlocking and signalling
switchgear, interlocking and signalling
50
Capacity Test
Capacity Test
51
Comments and Feedback welcome
Comments and Feedback welcome
Team Phone: +353 1 237 0583
Team Email: Generator_Testing@EirGrid.com
52