Module 003: Construction Contract Management and Administration
Module 003: Construction Contract Management and Administration
Learning outcomes
Module Overview
Contract Management and administration involves making decisions and the timely flow of
information and decisions to enable completion of the project as required by the contract
documents including review and observation of the construction project. This is important to
the client, contractor and Consultant not only to determine that the work is proceeding in
conformity with the contract documents, but also because it allows a final opportunity to
detect any inaccuracies, ambiguities or inconsistencies in the design.
This module will take the individual beyond the “business as usual” approach followed in the
construction industry. Although some of the same topics may overlap with other modules, the
depth of understanding and explanation as applicable to each module will provided needed
skills to enhance improved construction performance.
This basic course includes, Construction Industry participants, Bidding Requirements and
Process, alternatives and Substitutions, standards and Regulatory Influences, Site Activities,
Execution of the Work, Certificate of Payment, Changes in the Work, Dispute Resolution,
Construction Insurance, Construction Surety Bonds, Guaranties and Warranties, Project
Submittal, Contract Close-Out, Commissioning, Definitions and Resources.
Designed for: The course is designed for those individuals involved in construction
administration, including contractors, site engineers, General foremen, Contract
Administrators, Property Managers, Architects, Engineers, Quantity surveyors, bonding and
Insurance Agencies
Page | ii
National Council for Construction
Training Manual Introduction to Contract Management and Administration
National Council for Construction
Training Manual Introduction to Contract Management and Administration
1.0 A CONTRACT..............................................................................................................1
1.1 What is Contract Management?.................................................................................1
1.2 Management of Civil Works Contracts .....................................................................2
1.3 Different Types of Construction Contracts................................................................3
1.3.1 Lump Sum or Fixed Price Contract....................................................................3
1.3.2 Cost Plus Contracts.............................................................................................5
1.3.3 Unit Price Contracts ...........................................................................................6
1.3.4 Time and Material Contracts ..............................................................................6
1.4 Construction Condition of contracts ..........................................................................6
1.4.1 Communications.................................................................................................7
1.5 Managing time ...........................................................................................................7
1.5.1 Programme .........................................................................................................8
1.5.2 Extensions of time ..............................................................................................8
1.5.3 Completion .........................................................................................................8
1.5.4 Early completion ................................................................................................9
1.5.5 Penalties for late completion ..............................................................................9
1.5.6 Changes to the prices for the works ...................................................................9
1.6. Construction process................................................................................................10
1.6.1 Allowable rates .................................................................................................10
1.6.2 Resourcing the project ......................................................................................11
2.0 What is administration? ...............................................................................................12
2.1 Record keeping ........................................................................................................13
2.1.1 General..............................................................................................................13
2.1.2 Site diary...........................................................................................................13
2.1.3 Drawing register ...............................................................................................14
2.1.4 Written notices, correspondence and site instructions......................................15
2.1.5 Site photographs ...............................................................................................15
2.2 Contractual documents ............................................................................................16
2.2.1 Understanding the Contract Documents...........................................................16
2.2.2 Various documents constitute the contract documents that are the basis of the
contract. 16
2.2.3 Construction Contract Documents....................................................................17
3.0 Essentials Quality Control ...........................................................................................24
Page | v
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Page | vi
National Council for Construction
Training Manual Introduction to Contract Management and Administration
1.0 A CONTRACT
A construction contract is a legally binding agreement between two parties on the details and
cost of a construction project. This type of contract covers very expensive, complex projects
and simple renovations. There are two types of clients that use construction contracts:
residential and commercial. Each client has different requirements that determine what is
included in the contract.
A residential construction contract includes three basic elements: project scope, schedule of
work and payment details. The project scope is a statement of exactly what construction
work is included in the contract. Both parties must agree that this section provides an exact
representation of the required work.
The payment details section includes the total project cost and payment dates. All
construction projects are paid on a percentage of completion basis. A deposit of no more
than five percent of the total costs is provided at the start of the project. The next payment is
made when the predefined section of work is completed.
Page | 1
National Council for Construction
Training Manual Introduction to Contract Management and Administration
The main purpose of contract management is to make sure that the objectives of the contract
(supply of goods, delivery of services or execution of works) are met in a timely fashion and
value for money is achieved. In practice this means optimizing the efficiency of the
processes, balancing costs and risks against returns and ideally aiming for a continuous
improvement in performance over the life of the contract.
The first and foremost condition of successful contract management is getting the job done.
This translates in the fact that the ultimate scope/objective of the contract is accomplished,
i.e.:
(i) Goods are delivered/installed;
(ii) Services are performed;
(iii)Civil works are completed.
Just getting the job done is not enough for a successful contract management. We should
also be concerned about how the job is getting done. The aim should always be to get the job
done in the best possible way. This means that the scope/objective of the contract is
accomplished within the agreed:
(i) Costs (budget);
(ii) Time (duration);
(iii)Quality (functional parameters).
(Note: Achieving efficiency should not be mistaken for an unrealistic chase for cost savings,
or unreasonable pressure to squeeze more output from the contractors for less money or less
time. These practices frequently backfire and may result in more time and resources being
misdirected towards a false objective).
To begin with, there is a very large variety of types of civil works with various degrees of
complexity and risks and even more various types of expertise required for their
management.
Type of civil works – large infrastructure projects (highways, bridges, roads, irrigation
systems, dams etc.), smaller scale municipal infrastructure projects (rehabilitation of
buildings, roads, sewage, water or power utilities), environmental rehabilitation projects
(earthworks, planting, seeding, water management etc.).
In the form of an equation with a multitude of variables this would translate as:
Page | 2
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Figure1: Managing a Civil Works contract means managing relationships with many more
parties than just the Contractor
The choice of which construction contract to use oftentimes comes down to the owner’s risk
tolerance.
Under a Lump Sum or Fixed Price Contract, the contractor agrees to perform the work
specified and described in the contract for a fixed price. The price of a fixed contract can
only be changed upon the execution of a change order, under which the owner and the
contractor either (1) agree for the contractor to perform additional work that falls outside the
scope of the original work for an agreed upon extra compensation or (2) agree to remove
certain work from the original scope of work and reduce the price of the contract in
proportion to the work that the contractor no longer has to perform. These types of contracts
are appropriate when a clear scope and a defined schedule have been reviewed and agreed
upon.
The benefit of using Lump Sum or Fixed Price Contracts is that the owner’s construction
costs are more predictable. The owner’s cost will be capped by the contract price, so long as
no change orders are issued and no disputes arise on the project.
There are not many drawbacks with the use of the Lump Sum or Fixed Price Contract. To
ensure that the Lump Sum or Fixed Price Contract fulfills this function, i.e., provides a
predictable and accurate cost of construction for the owner, it is very important for the scope
of work under the contract to be clearly defined. This will eliminate the owner’s risk of the
contractor attempting to increase the contract price through the issuance of change orders for
the performance of additional work that is arguably not part of the original scope of work
but should be. Additionally, the schedule should clearly define the work and the deadlines
that must be met. This could perhaps be a drawback to the use of the Lump Sum or Fixed
Price Contract because it would require additional time and money to clearly define the
scope of work and create a detailed schedule (though this is something that should be done
on every construction project to protect the owner).
Page | 3
National Council for Construction
Training Manual Introduction to Contract Management and Administration
In addition, other types of contracts, such as Cost Plus Fee or Time and Materials Contracts,
could arguably be cheaper if the actual cost of construction were less than the contractor’s
estimated cost of construction on which the fixed price is based. But these types of
construction contracts could also be more expensive if the actual cost of construction were to
exceed the contractor’s estimated costs.
Therefore, the Lump Sum or Fixed Price Contract is a relatively safe and predictable
contract type that could be used on a construction project.
Page | 4
National Council for Construction
Training Manual Introduction to Contract Management and Administration
The Cost Plus Contract is a type of a construction contract under which the owner agrees to
pay the complete cost of the materials and labor needed to needed to build the project along
with a fee for the contractor’s overhead and profit. This contract type is favored where the
scope of work is highly uncertain or indeterminate and the type of labor, material, and
equipment needed to build the project is also uncertain in nature.
This type of contract involves payment of the actual costs, purchases or other expenses
generated directly from the construction activity. Under this arrangement, complete records
of all time and materials spent by the contractor on the work must be maintained. Cost Plus
Contracts must contain specific information about certain pre-negotiated amount (some
percentage of the material and labor cost) covering contractor’s overhead and profit. Costs
must be detailed and should be classified as direct or indirect costs.
There are multiple variations for Cost plus contracts, and the most common are:
1. Cost plus Fixed Percentage Contract – Compensation is based on a percentage of
the cost;
2. Cost plus Fixed Fee Contract – Compensation is based on a fixed sum independent
the final project cost. The owner agrees to reimburse the contractor’s actual costs,
regardless of amount, and in addition pay a negotiated fee independent of the
amount of the actual costs;
3. Cost plus Fixed Fee with Guaranteed Maximum Price Contract – Compensation is
based on a fixed sum of money. The total project cost will not exceed an agreed
upper limit;
4. Cost plus Fixed Fee with Bonus Contract – Compensation is based on a fixed sum of
money. A bonus is given if the project is finished below budget, ahead of schedule,
etc.;
5. Cost plus Fixed Fee with Guaranteed Maximum Price with Bonus Contract –
Compensation is based on a fixed sum of money. The total project cost will not
exceed an agreed upper limit and a bonus is given if the project is finished below
budget, ahead of schedule, etc.; and
6. Cost plus Fixed Fee with Arrangement for Sharing Any Cost Savings Contract –
Compensation is based on a fixed sum of money. Any cost savings are shared with
the buyer and the contractor.
The Cost Plus Fixed Fee construction contract is more predictable than Cost Plus Fixed Fee
Percentage Construction Contract because the contractor’s fee for overhead and profit is, as
its name suggests, predetermined. Regardless of what the cost of construction ultimately
amounts to, the contractor’s fee remains the same. Conversely, the Cost Plus Fixed
Percentage Construction Contract provides more variability with respect to the amount of
the contractor’s fee because it is directly linked to the cost of construction, which in these
types of arrangements is inherently unpredictable. In fact, the Cost Plus Fixed Percentage
Construction Contract arguably incentivizes the contractor to not keep the costs low because
its fee increases with the cost of construction.
Page | 5
National Council for Construction
Training Manual Introduction to Contract Management and Administration
The Cost Plus with Guaranteed Maximum Price Contract seeks to eliminate some of the
risks associated with Cost Plus Contracts in that it caps the owner’s overall financial
exposure. Thus, while the contract price is to be determined based on the cost of
construction and the contractor’s fee, owner’s costs are capped at a certain amount.
These types of Cost Plus Construction Contracts are oftentimes grouped with bonus
contracts, built-in contingencies, or cost savings contracts which incentivize the contractor
to complete the project with agreed targets regarding schedule, quality, and budget in
exchange for additional compensation on the project.
Unit Price Contracts are based on anticipated quantities of items which are counted in the
project in addition to their unit prices. The final price of the project depends upon the
quantities required to carry out the work. Generally, these types of contracts are suitable
only for construction and supplier projects which involve accurate identification of different
types of items, but not their numbers, in the contract documents. These types of contracts are
oftentimes used on excavation projects.
Time and Material Contracts are usually preferred if the project scope is not clear, or has not
been defined. The owner and the contractor must establish an agreed hourly or daily rate,
including additional expenses that could arise in the construction process. The costs must be
classified as direct, indirect, mark-up, and overhead. Sometimes the owner might want to
establish a cap or specific project duration to the contractor that must be met, in order to
have the owner’s risk minimized.
a) The parties’ main responsibilities e.g., the employer provides the site and the right of
access thereto while the contractor provides the works in accordance with the
requirements established in the contract.
b) The timing of the works, e.g. start date, time for completion, period for defects
liability, etc.
c) Testing and remedying of defects.
d) Payment, e.g. manner in which the works are to be assessed and certified, time for
payment and interest on overdue amounts.
e) Variations and claims, e.g. the manner in which variations to the contract are to be
evaluated and paid for and how the costs which result from employer liabilities are
assessed and paid for.
f) Title (ownership) to objects, materials within the site, etc.
g) Risks and insurances, e.g. what are the employer’s and contractor’s risk and what
insurances each party will take out.
Page | 6
National Council for Construction
Training Manual Introduction to Contract Management and Administration
h) Termination, e.g. the reasons for termination, the procedures for termination and the
payment to be made upon termination.
i) The resolution of disputes, e.g. by adjudication, mediation, arbitration, litigation
(court of law) or a combination thereof.
Conditions of contract can be standardized so that the same conditions of contract can be
used on different projects, in which case they are referred to as standard forms of contract.
The public sector generally uses one of the following standard forms of contract when
engaging main contractors for construction works contracts:
1.4.1 Communications
The construction sector has a wide range of standard forms of contract which are intended to
balance the risk of the parties but more importantly, through extensive and repeated use,
give rise to a certainty of meaning. The single most important task in administering a
contract is to ensure effective communications with the employer and his representatives e.g.
principal agent (JBCC Series 2000), engineer (FIDIC and GCC 2004) or project manager
(NEC3). Each form of contract stipulates requirements for communications between the
parties of the contract. These usually need to be communicated in a form which can be read,
copied and recorded. The contract data associated with a contract also state to whom
communications are to be addressed and where certain communications are to be sent.
Each of these events requires different types of communications between the parties.
Effective communications can mean the difference between a problematic contract and a
smoothly run one. It is also important for a contractor to communicate effectively with its
suppliers, service providers and subcontractors.
Page | 7
National Council for Construction
Training Manual Introduction to Contract Management and Administration
1.5.1 Programme
Construction works are unique in that each activity needs to be sequenced in order for the
project to be completed. For example, it is not possible to erect the roof until the
foundations and walls have been constructed. This type of logic is used to determine how
long a project will take to complete. Efficient programming can mean significant time and
cost savings to both the contractor and the employer.
At the start of each contract, the contractor is required to prepare a programme and have it
agreed to by the employer or his representative. This programme indicates the duration and
logic of the sequencing of activities for the project. The employer or his representative will
evaluate whether the logic is sound and whether the estimated time frames for completion of
the works are reasonable.
The programme is an important tool for managing time to ensure that the works are
completed in accordance with contractual requirements. It also allows the employer’s
representative to establish the reasonableness of any claims for an extension of time.
Where the contractor is instructed by the employer or his representative to add, change or
remove activities from the project or to change the scope of work, there may be grounds for
a change to the time for completion. If the change to the project causes the project to be
completed later than planned, then there is reason to change the completion date. If it does
not, there is no reason to do so.
Some forms of contract require that the contractor submit a claim for an extension of time to
the employer within a specified time period of becoming aware of an event that may give
rise to such an extension, e.g. abnormal rainfall, failure by the employer to provide access to
the site, etc. Failure to do so might result in the forfeiting of the right to an extension of
time.
1.5.3 Completion
The contractor is responsible for the works from the date that possession of the site is given
by the employer or his representative until such time that the works are completed or are
capable of being used by the client. The different forms of contract have different processes
for declaring a contract complete. Some require the employer’s representative to issue a
single completion certificate while others require a practical completion certificate and a
completion certificate to be issued.
At this point (depending on the form of contract) retention moneys are reduced, performance
bonds are released and the defects liability period commences. This is a great financial
relief for a contractor.
Where the contract allows for it, the contractor is entitled to or required to hand over
sections of the project before the whole project is completed. Handing over these sections
means that the employer is able to utilise that portion of the works before the whole project
is completed and the contractor is thereafter not liable for that portion of the works.
Page | 8
National Council for Construction
Training Manual Introduction to Contract Management and Administration
The risk of damage to the works also passes to the employer upon completion. It is
therefore important to manage and complete the work in such a manner that completion is
achieved as soon as possible.
If the contractor is very efficient, and there are no problems experienced on site, then the
contractor will be free to start a new project much earlier. The contractor needs to ascertain
that by completing a contract earlier does not cost him more. In some contracts, the
employer may encourage early completion by offering a bonus for early completion.
Provisions for penalties or delay damages (a monetary value representing the damage caused
by the delay) are contained in most construction contracts. These are imposed where the
employer has specific deadlines or other requirements and will experience a loss of revenue,
loss of use of the premises if the project is delivered late or have to pay additional
supervision and administration costs relating to the late completion.
The contract document will specify the value of the penalties per day, per week or per
month, or the extent of the penalties should specific requirements not be achieved.
Penalties are deducted from interim payment certificates as soon as they occur and can be
objectively quantified. They are based on the difference between the time that the works
were actually completed and the time according to the contract when they were supposed to
be completed.
Instructions given by the employer or his representative that change the scope of the work or
the timing of the works (i.e. the construction programme), can impact on the cost of the
works. Each of the different forms of contract assesses the impact on the contract price
differently. The contractor is required to carry out any instruction received in writing to
change the scope of work or the timing of the works unless it is impossible or illegal to do
so.
Changes in the scope of work most often arise through changes in the details on the
construction drawings or specifications, the employer increasing or decreasing the size of
the work, and new information regarding the site becoming available which necessitates that
the design be amended. The contractor should always check the changes that are made to the
drawings and identify how the changes affect the programme, materials ordering and
utilisation of resources.
Changes in the completion date for the works frequently arise from access being denied to
the site or a portion thereof for whatever reasons, the employer requiring the contractor to
stop the works or an earlier completion being required.
Page | 9
National Council for Construction
Training Manual Introduction to Contract Management and Administration
The contract also identifies which risks are carried by the contractor and which are carried
by the employer. Accordingly should an event occur on the site and the contract states that it
is the employer’s risk, then the contractor is entitled to have the contract price adjusted to
compensate for the additional costs incurred. An extension to the time for completion may
also be due to the contractor.
At the start of any contract, the contractor needs to deliver certain items that are required in
terms of the contract. These items can include:
a) Proof of the insurances that the contractor is required to have.
b) Provision of a performance bond.
c) Provision of the preliminary contractual programme.
These contractual requirements are needed by the employer to justify providing the
contractor with access to the site. The contractor must comply with these requirements
timeously; otherwise he will be in breach of contract and may have the contract terminated
due to lack of performance.
Before the work on site can start, the contractor should make certain preparations. These
preparations include careful planning of resources and methods of work in order to ensure
that the manner in which the work is performed on site is in line with the thinking at tender
stage.
This process is known as the pre-contract planning stage of the contract, and will result in a
set of allowable rates or lump sum amounts for activities that have been calculated, in order
to guide the productivity requirements on site. The contractor uses productivity rates from
past projects of a similar nature to determine productivity hours.
“Allowable rates or lump sums” are the costs or time period that a contractor can allow for
the task at hand, covering labour, equipment, transport, supervision and planned profit.
These allowable can help the contractor to plan the work more efficiently and make the most
of cutting costs of production and thereby maximizing profits.
Page | 10
National Council for Construction
Training Manual Introduction to Contract Management and Administration
When putting the price together for the tender submission, the contractor was required to
make certain assumptions regarding the manner in which the work would be done. This
includes how many people of what category are to be used for the work, how long they will
take to perform a task, and how much work they will be able to complete in a day.
The difference between the estimates and the allowable is that the allowable are calculated
backwards from the tendered rates submitted in the tender. The cost allowable are calculated
by dividing the direct project cost for the item of work by the total quantity of work to be
done on that item. Each item of work will contain at least one of the following components:
a) Labour
b) Equipment
c) Materials
d) Transport
The drawback of not planning is that FAILURE comes as a complete surprise without the
worry and stress that normally precedes it.
From the quantities identified in the contract or taken off the drawings, the contractor can
identify the gross quantities of each type of material that will be required to construct the
works, how many people will be required to finish the works in time, the plant required to
carry out each activity and also have a good idea of the profit that might be made on the
project. This will provide good indicators as to how many people are required on site, and
how much equipment is needed (e.g. does the contractor need to provide his own batching
plant or can he make use of ready - mixed concrete).
Work programmes are essential for the efficient performance of any job. They are an
essential tool for job planning and cost control and may be used to demonstrate claims for
delays and extra payments.
The programme is the tool that is used to determine the sequence in which the work needs to
be done in order to be completed on time. In construction, there is a logical sequence to the
activities. It is not possible to construct the roof until the walls have been built, and the
walls cannot be built until the foundations have been constructed. This logical sequencing
of activities is an essential tool for managing any construction project (see section 3.6).
By carefully sequencing the work that has to be done, the contractor can work more
efficiently with equipment, personnel and tools and are informed at the start of the project
more or less when the required materials need to be purchased. By moving activities around
and carefully changing the sequence of the works, the contractor can optimise each
resource’s input and complete the works as soon as possible.
Page | 11
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Different options can be explored and the one that will yield the greatest profit or the least
risk can be chosen. At tender stage the methodology for the works is prepared in a hurried
and broad - brush manner. When the contract is awarded, the contractor owes it to himself to
ensure that the most profitable and least risky options are chosen to maximise the profits for
the shareholders
Site administration and site management is often under - resourced and neglected in favour
of production pressures. Site administration and site management is the ‘nerve centre’ of
operations and if these functions are not functioning effectively, they will hamper
production output and quality will suffer.
A building project, has to undergo three specific stages namely, design, tender and
construction. In all three stages, good contract administration is required to manage design
specification, contractual agreement, competitive tendering, evaluation, cost control,
variations, final accounts, claims and even disputes. Poor management in any of these
aspects would lead to unnecessary claims and disputes and eventually higher construction
costs.
A schedule of tender adjustments or clarifications negotiated and agreed after the receipt of
tenders and prior to the signing of the contract should be included into the pack of
documents.
The requirement for the contractor to provide a performance bond and to obtain collateral
warranties from any specialist sub-contractors or suppliers should form part of the
conditions of contracts.
Both client and contractor should engross the contract by witnessed signatures prior to
commencement of work. In practice the administrative effort of collating all necessary
paperwork can be overtaken by the desire to begin construction. In such circumstances it
becomes harder to sort out any disputes as to the content. There have been cases where the
courts have had to interpret an implied contract when the contract has remained unsigned at
the time of the dispute.
Page | 12
National Council for Construction
Training Manual Introduction to Contract Management and Administration
2.1.1 General
Construction is a complex business to operate and there are many different activities that
need to be managed at any one time. It is not possible to remember what happened at what
time, and who did it, and why. Record keeping is essential to ensure that events can be
recalled at a later stage.
There are several main types of records that need to be kept including:
1) Site diary.
2) Drawing register.
3) Written notices, correspondence and site instructions.
4) Site photographs.
5) Contractual documents.
6) Occupational health and safety documents.
It is essential to also ensure that these records are properly filed so that they can be easily
found when needed. By implementing a standard way of keeping and filing records, the
contractor will save time and effort when starting new projects. It will also improve the
contractor’s ability to monitor and improve on production, quality and cost controls.
The site diary should be kept by the contractor’s site agent or site manager responsible for
the site. This site diary should keep specific information relating to the work that is done
each day, what problems were encountered, what instructions were issued by the employer’s
representative (principal agent, project manager, supervisor, engineer), what drawings were
received, and production and milestones achieved. Each project is different and the site diary
for each contract will change depending on the type of work to be done.
There are standard records that need to be kept which are needed for contractual reasons.
Information kept for all projects should include:
a) Day.
b) Date.
c) Rainfall measured.
d) Personnel schedule.
e) Equipment schedule.
f) Record of any reportable accidents that occur.
g) Production targets and achievements.
h) Site instructions received.
i) Drawings received.
j) Issues that are causing delays.
k) Work that is to be rectified.
l) Site meetings held and the date for the next one.
The contractor can decide how they wish to implement the site diary and there are different
approaches that are commonly used. Some contractors produce a customised printed book
Page | 13
National Council for Construction
Training Manual Introduction to Contract Management and Administration
with carbonated copies for use on site. This is useful for specific sites where the site agent
will write in the diary what the records are for the day and issue a copy to the employer’s
representative. Another approach is to develop a spreadsheet with the required information
on it. Each day this spreadsheet is filled in and e - mailed to the employer’s representative
who can then store it electronically or print it out for their files or pass it on for information
to the employer or other parties.
A drawing register must be kept and is essential in identifying changes and dates when these
changes are notified. The drawing register must identify each drawing issued to the
contractor for the contract with a revision number and the date it was received. This record
is essential in determining when changes were implemented in the drawings and how it may
have affected the works.
Changes to drawings may result in a variation if the work that is required for the change has
already started. On the other hand, if the work has not yet started and materials have not
been purchased for the original design the change may not result in a claim.
Page | 14
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Correspondence is used to convey messages and confirm verbal discussions held between
the parties on site. They place the discussion on record and expand on the circumstances or
approach to be followed.
Written notices are similar to correspondence but differ in the fact that they are written in
accordance with a specific requirement in terms of the general conditions of contract and
usually make reference to a particular clause.
Site instructions are often given verbally on site in order not to delay the work. These must
be confirmed in writing as soon as practically possible, so that they are placed on record and
become binding in terms of the contract. Some contractors print standard site instruction
booklets similar to the site diary, with carbonated pages which can be filled in by the
employer’s representative and handed to the contractor.
It is important to keep copies of outgoing mail as well as incoming mail. This should also be
added to the filing system. Where there is a likelihood of a large quantity of mail to be
processed, it would be a good idea to implement a document management system.
Site photographs are invaluable in recording conditions at a particular date and time. A
picture tells the whole story; however, it is important to capture additional information about
the picture as well. The additional information is needed to place the image in time and
place so that it can be utilised.
Digital cameras now provide a means of recording actual events cheaply and effectively.
The camera records the date and time of an image within the resulting image file.
The best “diary” of a project is a regular completed site diary coupled with a series of
regularly taken photographs. These photographs do not have to be taken daily but could be
taken on a weekly basis or at times when specific important occurrences take place.
It is important that the photographs are correctly coded and filed with the appropriate
description relating to each photograph. Electronic storage is fine as long as there is a clear
way of finding a particular picture when needed.
Page | 15
National Council for Construction
Training Manual Introduction to Contract Management and Administration
The most important document for any construction project is the contract. This details all
the rights, responsibilities and obligations of the parties to the contract. There should always
be a copy of this document available for site personnel to refer to. Other contractual
documents are also important and should be stored carefully. Documents that have
contractual reference include:
a) The main contract.
b) Subcontracts.
c) Labour contracts
d) Plant - hire agreements.
e) Delivery notes.
f) Programmes and bar charts.
g) Site - meeting minutes.
h) Notifications for inspections.
i) Correspondence with the employer/employer’s representative.
j) Payment certificates.
k) Completion certificates.
l) Daily labour sheets and materials and equipment usage where work is performed on
a cost reimbursable basis.
m) Health and safety file containing relevant health and safety documents.
2.2.2 Various documents constitute the contract documents that are the basis of the
contract.
Other documents are for reference, such as geotechnical data and surveys, and others are
generated to carry out the requirements, such as shop drawings and test reports. Certain
requirements used in the procurement of the construction contract may no longer apply once
the agreement is signed and the contract is formed. These documents include procurement
solicitations, instructions for procurement, bid security, and procurement forms.
Understanding how they are prepared will provide a greater understanding of how to benefit
from their use. The following is an abbreviated description of typical documents used in
construction.
Page | 16
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Construction contract documents are listed and enumerated in the agreement and referred to
in the conditions of the contract for the work to be performed. They are the documents that
are a legal part of the contract and describe the work. The contract documents describe the
proposed construction (referred to as the Work) that results from performing services,
furnishing labor, and supplying and incorporating materials and equipment into the
construction.
Contract documents consist of both written and graphic elements and typically include the
following:
a) Contracting Requirements
These include contracting forms (agreement) and conditions of the contract (general and
supplementary conditions, or client furnished general or special conditions) as well as
various named attachments and forms. Revisions, clarifications, and modifications are
changes applicable to the contract documents such as addenda issued during the
procurement process or change orders issued during the course of the work.
b) Specifications
These include specific written requirements for the work. Specifications define the quality
requirements for products, materials, and workmanship upon which the contract is based and
establish requirements for administration and performance of the project. They are generally
written for each work result as sections and organized by divisions using Contract Drawings.
These include large graphic illustrations of the physical form of the work to be performed.
The drawings are graphic representations of the work upon which the contract is based. As
the graphic documents usually contain more than plan views, the preferred term is drawings
rather than plans.
Page | 17
National Council for Construction
Training Manual Introduction to Contract Management and Administration
They show the quantitative extent and relationships of elements to one another. The
contractor signing the agreement with the client has the responsibility of accomplishing the
work in accordance with the contract documents. Therefore, the contract documents are
addressed only to the contractor; however, client and designers responsibilities are also
included within these “contract documents.” Contracting requirements and specifications are
usually bound into the project manual. Contract drawings are generally bound separately
because of their larger size.
There are several types of drawings, reports, and specifications that may be utilized during
construction but may not be included with the contract documents. These may include
surveys, hazardous material reports, assessments, and geotechnical data.
c) Drawings
Various drawings represent information about the work to be performed. They illustrate
relationships between elements as well as quantities, locations, dimensions, sizes, shapes,
and forms of the elements and assemblies in the project. Paper drawings are two-
dimensional by their very nature. Certain types of specialized views can show elements in
isometric or perspective views, but one cannot see every view possible. The current
limitations of single views leave many portions of the work unseen. Communicating the
information accurately may require multiple views. Understanding how drawings are
prepared and the types of information shown is a major aspect of interpreting the
information.
Plan views are drawings that show the horizontal layout, as if one is looking down on the
subject. This view does not usually convey information about the vertical dimensions.
Other views such as elevations, sections, and profiles give a view looking perpendicular to
the horizontal plane. These basic types of views require the user to mentally compare the
two views to understand what is happening in the three dimensions of space. It is somewhat
difficult to understand how far an element extends if it does not appear at the plane in which
the view is drawn.
Fitting the various views together is like doing a jigsaw puzzle. To further explain various
conditions, details are drawn as if the element were sliced or viewed at a particular location.
These details indicate more specific information and may be considered representative of
unique conditions or typical of most conditions.
Understanding what exists in the space indicated by the drawings leads to a consideration of
the sequence necessary to carry out the work. The means, methods, and techniques are in the
contractor’s control and the efficiency is a result of ingenuity and timing of each activity.
Various types of views and drawings prepared by various professional disciplines are
associated with stages of the facility life cycle.
d) Resource Drawings
These are the drawings furnished during the procurement stage that generally show existing
conditions such as roads, buildings, and current construction circumstances. These may be
drawings that were prepared for the construction of existing facilities. Drawings of this
nature rarely show exact as-built conditions and may be record drawings from the previous
contractor. Resource drawings are generally furnished for reference only and are not
Page | 18
National Council for Construction
Training Manual Introduction to Contract Management and Administration
contract documents. Resource drawings may also include items such as client furnished and
-installed equipment that requires utility rough-in locations or attachment requirements.
e) Contract Drawings
Contract drawings are those named in the agreement and can be supplemented by various
forms of interpretations and modifications including small-size sketches. These drawings
document the work to be performed. They may show work to be removed and work to be
constructed. They help to establish the extent of the work and are complementary with the
specifications. The contract documents are interrelated and they provide different types of
information required to carry out the work.
f) Shop Drawings
These are drawings that are prepared by manufacturers, suppliers, subcontractors, and
contractors to illustrate a portion of the work. Only shop drawings required by the
specifications are normally reviewed and acted on by the designers. These drawings usually
illustrate proposed details and techniques to show compliance with the contract documents.
Shop drawings may include dimensions obtained at the project site showing how the
specialized work will be incorporated into the project. Shop drawings, regardless of
approvals, are not contract documents and do not waive requirements of the contract
documents.
g) Coordination Drawings
Information provided by various subcontractors and the contractor are brought together to
coordinate utilization of limited space. Information on the contract drawings may be
diagrammatic, with single lines indicating general locations. Coordination drawings are
drawn with actual (scale) dimensions of the elements. These drawings help determine how
elements will actually fit in the space available. Without coordination drawings, the
installation of each element may require that the next element fit in the remaining space.
Frequently, this creates a problem that is extremely difficult to rectify requiring elements to
be repositioned. Coordination drawings, regardless of submission or approval by the
designers, are not contract documents.
h) Record Drawings
The contract documents may require record drawings. Often the contractor marks up the
contract drawings to indicate changes and field conditions. The contract documents indicate
the type of information required to be included on the record drawings. Concealed
conditions and utility locations are the most common information required. These record
drawings are submitted through the designers to the client as a permanent record of the
actual conditions of the completed work.
i) Electronic Models
As technology continues to evolve, some traditional locations of facility information are
changing. Building Information Modeling (BIM) uses computer programs to document
facility design, to simulate construction, and to simulate facility operation. BIM is more than
3D modeling of facilities and components with the traditional information typically found in
contract drawings. A BIM database can be an intelligence-rich model that allows extraction
Page | 19
National Council for Construction
Training Manual Introduction to Contract Management and Administration
BIM allows design and construction team members to collaboratively embed intelligence
into the model in order for personnel to concentrate on design and problem- solving tasks
while allowing the computer to perform tasks such as quantity take-offs for cost estimating
or product ordering, clash detection, scheduling, and quality assurance.
j) Specifications
Specifications, in general, can include various types of data; however, the specifications
included as a part of the contract documents are the written description of the work to be
performed by the contractor and are prepared by the designers. The specifications may be
simple notes on a drawing or more detailed descriptions bound in the project manual. The
specifications are typically organized in accordance with the Standard Construction
Specifications which establishes the organizational structure for the documents and sections
within a project manual, each with its unique number and title. A section is further divided
into the three PARTs defined and organized into divisions. A good understanding of the
structure of specifications and the individual sections greatly aids in administrating the
work.
Other types of specifications and standards, not bound in the project manual, may include
those of organizations such as American Association of State Highway and Transportation
Officials (AASHTO). Specifications and standards by such organizations may be contract
documents if they are incorporated into the contract specifications by reference to specific
standards.
Manufacturers develop data sheets that give specifics about their products. These product
data sheets may be required as a submittal to provide evidence of the kind and quality of
products being furnished by the contractor. These data sheets are like shop drawings and are
not contract documents. Manufacturers may also develop guide specifications specifically
for their products to assist the designers in preparing project specifications.
Record specifications are similar to record drawings in that they utilize contract documents,
which are then marked by the contractor to indicate actual conditions such as the products
provided during the construction stage.
Clarifications and proposals include documents initiating changes or clarifications that have
not been incorporated into the contract by formal contract modifications. These documents
include requests and proposals.
Page | 20
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Contract modifications include modifications after the construction agreement has been
signed and may include additions to, deletions from, or modifications of the work to be
done. These are accomplished by change orders, change directives, and minor changes.
These can be issued at any time during the contract period.
Variations are therefore not only normal in a civil works contract, but also necessary
to correct shortcomings in the design, to improve the proposed technologies, to allow
for the use of newer or better materials etc. As long as they are carefully analyzed
and duly justified from a technical and economical perspective, variations should not
be regarded as attempts of the Contractor to get money in dubious ways.
The Engineer is again the most important player in this equation because it’s the
Engineer’s duty to make sure that the variations requested by the Contractor are (i)
necessary; and (ii) make technical and economical sense. The next step would be to
evaluate the financial impact of the respective variations and duly inform the
Employer about it. Depending on the limits of Engineer’s authority established in the
Particular Conditions, the Employer should approve the variations that exceed the
respective threshold.
Re-measurement of works
o Has notice been given by Engineer to Contractor about intention to carry out
measurement?
o Has Contractor sent qualified personnel to assist Engineer?
o Have all particulars requested by Engineer been provided by Contractor?
o Are certified laboratories/testing institutions hired for the tests?
Health and Safety
Schedule of works - A schedule of work should indicate the start date, milestones,
and project completion date. Review this section in detail to ensure that all the
primary requirements from the project scope are included. The process for
inspection and quality assurance should be provided here.
Managing Cash-flow projects
The Employer should supervise Contractor’s mobilization on site and use of the advance
payment, because usually this is a fairly good indication on Contractor’s later performance.
Any delays or deviations in site mobilization (in quantity but also in quantity – e.g.
unacceptable accommodation or sanitary facilities) should be promptly notified to and
remedied by the Contractor.
Page | 21
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Contractor’s mobilization should be seen as comprising at least the following key aspects:
(i) financial resources - if advance has been paid, than the Contractor should be able
to timely complete the appropriate mobilization arrangements;
(ii) manpower - both in terms of Contractor’s key staff and sufficient labor to ensure
proper and timely execution of the works;
(iii) plant, equipment, materials;
(iv) site facilities – check the contractual requirements
There may be cases where the Contractor receives the advance payment but fails to mobilize
up to the value of the advance payment or according to its own Mobilization Schedule
(which should have been part of its bid). If it is obvious that the Contractor does not have the
intention of making the adequate start up arrangements or uses the advance payment for
other purposes than the mobilization costs, than the Employer would be entitled and should
not hesitate to forfeit the advance payment guarantee, after due consultation with the
Engineer, who should be in the best position to determine Contractor’s capacity or
intentions.
Another important aspect would be the desk control of Engineer’s documents. The Engineer
should maintain very accurate records of everything that happens on the Site. The following
documents should be the minimum required:
Measurement logs
Activity reports – daily, weekly, monthly; showing in tabular format quantities of work
done, number of staff and equipment involved, consumption of materials, testing and
samples etc. The reports should also mention any specific events, incidents, weather
conditions etc.
Issues Log – a record of all issues that occurred during the execution of works, with
appropriate description and indication of the date, cause, remedial measures to be taken,
responsible party, status of remediation etc.
Variation Orders – critical documents that justify changes in quantities, prices and time
for completion.
Requests to Contractor.
Correspondence with the Contractor and third parties (Government agencies, local
authorities, controlling bodies, end users, beneficiaries etc.)
Page | 22
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Inspection and Control Logbook – a record of all inspections, audits and controls
performed by any party starting with the Employer, but also any third party
(environmental agency, financial control, local authorities etc.)
Payment
Payment of the Interim Payment Certificates issued by the Engineer based on Contractor’s
monthly statements is one of Employer’s key responsibilities and also the moment with the
maximum involvement of its technical, procurement and financial staff.
Termination of Contract
Check the exact provisions of the Contract with regard to the Termination by the
Employer;
Assess Contractor’s claims and remedies;
Ensure that all Contractor’s reasonable claims have been properly addressed and all
due amounts have been paid;
Contingency planning.
Page | 23
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Check if the contract management team has consistently and correctly enforced the
conditions of contract;
Duly document any deviations from the specifications and conditions of contract.
A house built with face bricks will have a different outcome to one built with stock bricks.
The specifications for laying face bricks differ from that of laying stock bricks that will be
plastered afterward. Stock bricks do not need to be laid to the high level of tolerances that
face bricks are since they will anyway be covered with plaster. The bedding joints do not
have to be as regular or as neatly executed as those for face bricks. When the walls have
been built the result will be a quality job if they comply with the specifications, however,
there is a difference in the look, maintenance and performance of the finished product.
Quality control is an essential part of the construction process. By proper planning and
careful work any construction project can be completed correctly without having to re - do
any of the work that is required. This control over the work to prevent making mistakes is
known as quality control. The old adage that “prevention is better than cure” is most
definitely applicable in the construction industry.
By ensuring that quality work is being done from the start, the contractor ensures that when
the work is complete, it complies with the specifications and there will be no call to re - do
any of the sections he has completed.
A quality plan should indicate how the required activities will be carried out e.g. in the case
of excavations for a building to ensure that:
• The excavations have been done to the dimensions given on the drawings.
• The sides of trenches are vertical and the bottom of the trenches level.
• The inspections of footings by the local authority/building inspector/engineer (if
reinforced) are carried out before the concrete is cast.
The quality plan should also identify the individuals who will be responsible for carrying out
inspections. Accordingly, the quality plan should:
Page | 24
National Council for Construction
Training Manual Introduction to Contract Management and Administration
The following steps can be taken to ensure the continual improvement of the quality of
products and services offered by a contractor:
A team should be dedicated to run and monitor the quality improvement process. Without
consistent monitoring the improvements in quality cannot be measured and where there is no
visible outcome the quality improvement process will fail.
Page | 25
National Council for Construction
Training Manual Introduction to Contract Management and Administration
methods of approaching the work that they do in order to produce a consistent quality. To do
this the contractor might get the “good foreman” to come in and discuss the systems that he
uses to ensure that his work runs smoothly, document these systems and then instruct their
other foreman to comply with them.
If there is a standardised approach and systems in place, there is no excuse for anybody who
works within the contractor’s organisation to say that “I thought it was close (good)
enough”. Something is either right (conforms to the specifications), or it is wrong (does not
conform). However, this does not mean to say that everything must be perfect. Good
construction practice allows various tolerances and the contractor should ensure that the
work they perform is always within these tolerances. Conformance with specifications
means constructing the works within the specified tolerances.
Unless the contractor produces consistent quality work it will not be in business for very
long. There may be a quick profit on one job but there will be no repeat business if the
quality of work is poor.
The contractor would have made an allowance in the tender for time spent by the site agent
with the client to go through the project quality checks and hand over of the works. The
contractor should also have priced the cost of a finishing team in fixing up the snags as a
result of the final inspections. This amounts to the costs that were allowed and what
constitutes conformance to requirements. Any additional work done over this allowance is
due to the contractor’s non - conformance to the requirements.
All the re - work costs (PONC) must be added up on each project and the PONC for each
project should be noted. The PONC of all projects could be displayed on the contractor’s
notice board, website, in a marketing brochure, or discussed at company meetings to make
sure that everybody knows the seriousness of the pursuit for quality and that improvement
from each employee is expected on each of their subsequent projects. Monitoring can be
done on an ongoing basis and is not restricted to the end of a project.
The cost of quality is constituted by the cost of conformance (COC) (the cost of doing things
right) and the cost of non - conformance (CONC) (the cost of doing things wrong). The
CONC is useful as it can be related to an organisation’s monetary business volume and the
percentage contribution thereto can be computed. The cost related to the achievement of
quality is comprised of the cost of conformance and the cost of non - conformance. Non -
conformances result in rework. Each person within the contractor’s team needs to be made
aware of the price of non - conformance associated with the poor habits that they have
picked up. By ensuring that each person is aware of the cost that they are incurring to the
Page | 26
National Council for Construction
Training Manual Introduction to Contract Management and Administration
contracting organisation and incentivising them to improve, they will try to reduce the
PONC as much as possible.
Page | 27
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Date
Description of work
Engineer’s Signature
Page | 28
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Page | 29
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Week ending
Contract :
Week No
Description of work Bill Unit Quantity Quantity completed Total to date
Item executed up to during last week
Number the end of
previous week
A B A+B
Page | 30
SAMPLE ISSUES LOG (CIVIL WORKS CONTRACTS)
This checklist can assist in the audit of the Contractor and the Engineer, as well as with
regard to the interaction between contract parties
Name of Project:
Date of audit:
Name of audited party: Engineer
Contractor
33
National Council for Construction
Training Manual Introduction to Contract Management and Administration
Page | 34
National Council for Construction
Contract Management and Administration Training Manual
Auditor
35