BIS - Programme Management
BIS - Programme Management
PROGRAMMES
Understanding programmes
and Programme
Management
NOVEMBER 2010
CONTENTS
TM
MSP is a Trade Mark owned by the Office of Government Commerce (OGC).
2
What is a programme, and how does a programme differ from
a project?
The term Portfolio is used to describe the total set of programmes and stand-
alone projects undertaken by an organisation.
3
When is it appropriate to treat an initiative as a programme?
· Cross-cutting
· Multi-disciplinary
· Risky
· Uncertain, with unpredictable outcomes
· Long duration (spanning years rather than months)
· Influenced by a wide range of interested parties with differing degrees of
commitment
· Impacting on a wide range of stakeholders some of whom may suffer ‘dis-
benefits’
· Liable to change direction in the light of experience and external events.
Early in the life of a new initiative you might like to consider it in the light of the
seven Principles of programmes (as per MSP ™) to determine which
programme management approach is appropriate:
4
Leading change
Should this initiative be led at a senior level in order to take a range of
stakeholders on what might be a challenging journey involving many changes
to such things as working practices, attitudes and behaviours?
Envisioning and Communicating a Better Future
Is there a compelling vision of a better future that the initiative must achieve?
Focus on Benefits and the Threats to them
Will the outcomes arising from the programme result in tangible advantage (or
disadvantage) to one or more stakeholders within or beyond your organisation
(including the general public and society as a whole)? Will benefits be
realised during the life of the initiative?
Designing and Delivering Coherent Capability
Will the required outcomes and benefits be dependent on the creation of
many different but related project outputs which must be integrated and
implemented successfully?
Learning from experience
Has your organisation undertaken similar initiatives? Is there anything you
could learn from the experience? Is your management culture such that you
will continue to identify lessons during this programme?
Adding value
Will the cost of the additional resources required to manage the initiative as a
programme be justified in terms of the increase in likelihood of success?
5
The Government approach to Programme Management -
Managing Successful Programmes (MSP TM)
MSP comprises:
· Principles
· Governance Themes
· Transformational Flow processes
Each bullet above is expanded on in the following pages, but for full details
you should refer to the published MSP guidance.
6
Principles
These are proven, universal principles that apply to all types of programme
and when applied help achieve success. The seven principles are:
7
Governance themes
The MSP Governance Themes are used to help you design and implement
the control framework through which you deliver changes, achieve outcomes
and realise benefits. The nine themes are:
· Organisation
· Vision
· Leadership and Stakeholder Engagement
· Benefits Realisation Management
· Blueprint Design and Delivery
· Planning and Control
· Business Case
· Risk Management and Issue Resolution
· Quality Management
The following pages give more information on the above headings but for full
details you should refer to the published MSP guidance.
8
Organisation
9
Vision
This governance theme describes how to establish a picture of the end goal
the programme must achieve by producing a Vision Statement that:
This governance theme describes how to identify, define, track and optimise
the realisation of benefits (and dis-benefits).
The most easily managed benefits will be tangible, measurable and, ideally,
definable in financial terms. However some benefits might be intangible
(sometimes referred to as ‘soft’ benefits) in that they are difficult to
substantiate – proxy measures might be necessary to provide some evidence
of realisation (e.g. a reduction in the number/type of calls to a Help Line might
be used as a proxy indicator for the improved customer appeal or usability of
a website).
The Blueprint is a model of the operational capability that will need to be put in
place to enable the required outcomes and benefits. The Blueprint comprises
the current, intermediate and target end state of the key aspects of the
business operations of not only the parent organisation but also any partner,
customer and supplier organisations that must change for benefits to be
realised. The ‘POTI’ model is used to define the key elements of future
business operations that should be defined in a Blueprint:
· Processes and functions and their operational costs and performance
levels
· Organisation, staffing levels, skills and culture
· Technology, tools, IT, equipment, buildings and accommodation.
· Information and data
11
· Influence/Interest Matrix: used to map the potential interest of each
stakeholder against their areas of interest and hence work out approaches
and priorities for stakeholder engagement and communication
· Stakeholder Profiles: used to record stakeholder information such as
current and target positions in terms of levels of interest, impact, influence
and support
· Stakeholder Engagement Strategy: the framework that enables effective
stakeholder engagement and communication in the programme
· Programme Communications Plan: the timetable and arrangements for
implementing the Stakeholder Engagement Strategy. This includes the
messages, audiences, timing responsibilities, communication channels
and feedback processes.
This governance theme is concerned with the approach to risk and issues
management and how the processes will be applied across the programme,
its projects, its transition activities and operational areas that will undergo
change. The theme advises how to establish a framework for managing risks
and issues and on the tools that should be used to capture and use
information about them:
· Risk Management Strategy: the programme’s approach to the
management of risk, derived as far as is possible from the corporate
approach
· Risk Register: used to capture and actively manage risks to the
programme
· Issue Resolution Strategy: the programme’s procedures and
mechanisms for resolution of issues such as change requests, requests
for information, technical problems, stakeholders’ concerns and
suggestions. Again the programme should take into account any relevant
corporate approach
· Issues Log: used to capture and actively manage programme issues.
Quality Management
The scope of quality management theme covers all aspects of the programme
(including its projects and transformation activities) to ensure they are
appropriate and fit for purpose. This will enable stakeholders to be assured
that the planned benefits have the best chance of being realised. The theme
recommends the production of:
· Quality Management Strategy: to define the approach to managing
quality across the programme e.g. what will be subject to quality
assurance/audit/review/control, responsibilities for quality management,
standards and regulations, interfaces with corporate and other relevant
quality management systems.
· Quality Management Plan: the timetable and arrangements for
implementing the quality management strategy
13
Transformational Flow processes
Programme
Identifying Completion
a of
Program
me Sponsoring
Defining a Group
programme Closing a
programme
Programme
definition,
governance Managing the Tranches
arrangements
and plans
Delivering Realising
the the
Outputs Outcomes
and and
The ‘Identifying the Programme’ process is used to appoint the SRO who
will then define in outline the programme vision, objectives and benefits and
record them in a Programme Brief which contains an outline business case.
This leads to the first key decision by the Sponsoring Group whether or not to
commit resources to defining the programme and its management approach
in detail i.e. whether or not it is sensible and worthwhile to start the Defining a
Programme process.
14
If the SRO is given the go-ahead then work commences on ‘Managing the
Tranches’ which is the process where day to day governance of the
programme is applied by the SRO and Programme Board with involvement of
the Sponsoring Group at key points (e.g. Tranche Boundaries).
Eventually there will come a point when the Closing the Programme process
is required. This is usually when the whole ‘Blueprint’ for change has been
delivered and benefits are materialising to a sufficient degree to satisfy the
programme’s Business Case. Sometimes premature closure will be
appropriate if the programme’s business case is no longer viable or if
programme management no longer adds value. Either way this leads to the
final decision by the Sponsoring Group to close and disband the programme
but also to ensure that benefits realisation and measurement continues after
the programme has closed. The main activities at programme closure are:
15
What is the lifecycle of a typical Programme?
Programme
Mandate
G H G B E H B G B E BE
• Programme Brief
• Programme Preparation Plan Project .A
• SRO and Sponsoring Group
appointments Project .B
Project .C T
• Vision Statement Transition
• Programme Definition Doc
Project .D
• Business Case T
• Benefit Profiles/Map/Realisation Plan Transition
• Blueprint
• Governance arrangements
• Programme Plan Project E
• Projects Dossier
Project F Project H
• Communications Plan
• Risk Register/Issues Register
• Programme Manager/Business Project G
T Project I
Change Manager appointments Step change
Transition T
in capability
Transition
Realisation of
Benefits
Step change
KEY to Reviews/ Approvals: in capability Step change
= Sponsoring Group decision point Realisation of in capability
B = Benefit Review Benefits Realisation of
E = End of Tranche Review Benefits
• In MSP: Tranche governance by the SRO/Programme Board
T = Approval to enact transition (e.g. to ‘Go live with a new service)’ is via the ‘Managing the Tranches’ processes.
C = Compliance Audit • Projects are initiated and controlled by the Programme
G= Gateway Review Manager under the ‘Delivering the Capability’ process
H = Healthcheck • Transition Management is done by Business Change
Managers in the ‘Realising the Benefits’ process
16
The importance of Benefits Management in Programmes
Ideally it will be possible to establish the ‘baseline’ current value for a benefit
before any changes are introduced via the programme.
17
What is the role of a Benefit Owner?
Define
and
quantify Help
h plan
the
Manage
any
Prepare
business
for
Measure
ongoing
achievement
of the
Implement
measurem
Establish
baseline
measures
19
been produced. In these circumstances indicate the triggers/enablers and
any lead times for achievement of the target
· Benefit start date: Anticipated date is either a defined business
requirement or derived from the Programme Plan (e.g. MM/YY for benefits
commencing in a particular Tranche).
20
What Programme Management support is available?
21
Glossary of key Programme Management terms
This is a subset of those in MSP manual plus other PPM terminology used in
this guidance but not commonly used in BIS. See http://www.best-
management-practice.com/officialsite.asp?DI=575004&FO=1230366 for more
a more comprehensive glossary of MSP terms.
Change Team
A group of specialists appointed to support a Business Change Manager in
the change management aspects of benefits realisation.
Dis-Benefit
Outcomes perceived as negative by one or more stakeholders. Dis-benefits
are actual consequences of an activity whereas, by definition, a risk has some
uncertainty about whether it will materialise.
Emergent programme
A programme that subsumes one or more pre-existing projects into a
coherent alignment with corporate policy and strategy.
Gateway Review
The OGC Gateway Review Process examines programmes and projects at
key decision points in their lifecycle. It looks ahead to provide assurance that
they can progress successfully to the next stage. The process is best practice
in central Civil Government, the Health sector, Local Government and
Defence and is applicable to a wide range of programmes and projects
including:
Outcome
The result of change, normally affecting real-world behaviour and/or
circumstances. Outcomes are desired when a change is conceived.
Outcomes are achieved as a result of the activities undertaken to effect the
change. In a programme, the outcome is the manifestation of part or all of the
new state conceived in the blueprint.
22
Output
The tangible or intangible product resulting from a planned activity.
Portfolio
The totality of the change initiatives within an organization; it may comprise a
number of programmes, stand-alone projects and other initiatives that achieve
congruence of change.
Programme
A temporary flexible organization structure created to coordinate, direct and
oversee the implementation of a set of related projects and activities in order
to deliver outcomes and benefits related to the organisation’s strategic
objectives. A programme is likely to have a life that spans several years.
Programme Assurance
Independent assessment and confirmation that the programme as a whole or
any of its aspects are on track, applying relevant practices and procedures,
and that the projects, activities and business rationale remain aligned to the
programme’s objectives. See also Gateway Review.
Programme Board
A group that supports the senior responsible owner to deliver the programme
Programme Management
The coordinated organisation, direction and implementation of a dossier of
projects and activities that together achieve outcomes and realise benefits
that are of strategic importance.
Programme Manager
The role responsible for the set-up, management and delivery of the
programme, typically allocated to a single individual.
Programme Office
The function providing the information hub for the programme and its delivery
objectives; could provide support for more than one programme.
Programme Organisation
How the programme will be managed throughout its lifecycle, the roles and
responsibilities of individuals involved in the programme, and personnel
management or human resources arrangements.
Project
A temporary organization that is created for the purpose of delivering one or
more business products/outputs according to a specified Business Case.
Projects Dossier
The group of projects designed to deliver the outputs required by the
programme.
23
Senior Responsible Owner (SRO)
The single individual with overall responsibility for ensuring that a project or
programme meets its objectives and delivers the projected benefits.
Sponsoring Group
The main driving force behind a programme who provide the investment
decision and top-level endorsement of the rationale and objectives of the
programme.
Tranche
A group of projects, transition activities and governance structured around
distinct step changes in capability and benefit delivery.
24
Programme Management Documentation Templates
You can access and view those example templates that are available by
clicking here, which will take you to the BIS website.
URN 10/1256
25