Project Final Report Template
Project Final Report Template
Project Successes
Name Description
Best Location The site selected for Dam was a rocky land surrounded by
mountains, making a small valley. So just 1 big wall was needed at
front, and a steel grid at enterance to avoid garbage.
Clean Water Due to mountain region, no water purification was needed. We got
clean natural water.
Easy Supply Dam was at height as compared to village, so water supply become
much easier and economical.
Unexpected Events
Description Impact Actions Taken
Summer Rain Schedule extended by Speeded up work after
20 days rain by extra resourses
Technical Fault in Machinary Schedule extended by Brought new
one week Equipments
Project Final Report
Lessons Learned
Description Recommendation
Unexpected Weather Conditions Weather Conditions must be taken into
account when planning.
Technical Faults Must avail an alternative and trained staff
Project Performance(Flow)
Time Frame
Started on 5 April 2018 with survey and construction plan.
On 10 April, installed machinery and practically started the job.
Local labour force hired for speeding up work.
On July 15 summer rain started, have to stop work for 20 days.
This delay was compensated by more labour and long shifts of job.
The loading crane was shut due to some fault, so a weak wasted in maintenance.
Finally almost after 10 months, on 10 February 2019 project was finished and
functional.
We remained 20 days behind schedule.
BudgetFrame
Approved budget was 30,00,000/- PKR.
To manage time delay spent 50,000/- extra on labour.
40,000/- maintenance expendetures
Water filteration plant was not in schedule/plan, but at the end it costed
1,10,000/- extra.
Finally almost 200,000/- rupees gone over budget, that was managed by fund
raising by locals.
On Schedule
Start Date Planned Finish Actual Finish Variance On Schedule Ahead of Behind
Date Date (in days) Schedule Schedule
05-04-2018 20-01-2019 10-02-2019 20 days ☐ ☐ ☒
On Budget
Approved Spent Budget Variance On Under Budget Over Budget
Budget (in PKR) Budget
30,00,000/- 32,00,000/- 200,000/- ☐ ☐ ☒
Goals Achievement