Power Supply Guidelines For Major Projects: Power & Water Planning Division Power Transmission Planning Department
Power Supply Guidelines For Major Projects: Power & Water Planning Division Power Transmission Planning Department
Our Mission
رسالتنا
We are committed to the happiness of our stakeholders and promoting
Dubai’s vision through the delivery of sustainable electricity and water
services at a world-class level of reliability, efficiency and, safety in an
environment that nurtures innovation with a competent workforce and
effective partnerships; supporting resources sustainability
نلتزم بتحقيق السعادة لكافة المعنيين وتعزيز رؤية دبي من خالل تقديم خدمات مستدامة
للكھرباء والمياه بمستوى عالمي من االعتمادية والكفاءة والسالمة ضمن بيئة محفزة
داعمين لديمومة الموارد،لالبتكار بكادر مؤھّل وشراكات فعّالة
Our Motto
شعارنا
For Generations to come
ألجيالنا القادمة
Contents
Contents
1. Introduction ………………………………………………….. 1
2. Requirements
2.1 Technical Requirement …………………………………. 2
2.1.1 Location and layout of the project………………………………… 2
2.1.2 Nature of the project ………………………………………………….. 2
2.1.3 TCL of the project ………………………………………………………. 2
2.1.4 Distribution Renewable Resources Generation (DRRG)…….. 3
2.1.5 Power Factor ………………………………………………………………. 3
2.1.6 Load Characteristics ……………………………………………………. 3
2.1.7 Supply Voltage …………………………………………………………… 4
2.1.8 Substation plot sizes ………………………………………………….. 4
2.1.9 Location of substation plot …………………………………………… 4
2.1.10 Site plan for 400kV & 132kV substation………………………… 5
2.1.11 Undertaking to clear services within the substation plot 5
2.1.12 Corridors ……………………………………………………………………. 5
2.1.13 Policy on construction of 400kV and 132kV substations …… 7
2.1.14 Requirement for 11kV Network/Design approval ………….... 7
2.2 General Requirements ……………………………………. 8
3. Annexures
3.1 List of documents to be submitted …………..………. 11
3.2 Distribution network design requirements and
guidelines for 11/0.4kV supply ……………………….. 12
3.3 Main developer’s load confirmation format, NOC
approval ……………………………………………………… 15
3.4 II&P Department requirements for updating Major
Project Landbase in DEWA GIS ………………………... 16
1 Introduction
2 Requirements
In order to avail the power supply for any project / development on time, it is
necessary to submit and get approved the technical pre-requisites on time as
DEWA require lead-time as indicated in Item No. 2.1.11.
• Details of the District Cooling Plant loads (size, location and the
expected phasing of its commissioning).
For project with DRRG, the submittal shall include DRRG plan (PV
Rooftop Solar) which consists of ;
• Planned DRRG capacity (kW) per plot and for entire project.
• The 132/11kV substation plot shall have access from two major
roads or one major road and Sikka (min 7m wide). The longer
side to face the road.
2.1.12 Corridors
11 kV underground cable
400/132kV substation
132/11kV substation
• Latest planning of the development (with both hard & soft copy).
• 11kV corridors details for all the roads within the project
boundary.
Addressed to:
Dr. Nasser Tleis
Vice President – Power Transmission Planning
Dubai Electricity and Water Authority
P O Box – 564, Dubai
Fax: 04 - 3249206
4. The listed documents shall be submitted in three sets of hard copies and
1 set of soft copy (drawings in AutoCad/Microstation & PDF and load
details in Ms Excel format).
6. Once approved, DEWA expects that the developer will adhere to the plan
and any minor changes in the project plan, changes in phasing, etc. shall
be informed to DEWA in time and got approved. Changes on works during
the execution stage shall not be entertained.
7. Any power supply requirement for the project shall be from the 132/11kV
substation built for the project. The developer shall phase the
developments and accordingly the power requirements matching the
commissioning schedule of the source 132/11kV substation for the
project.
9. DEWA will not be responsible for any delay in commissioning due to any
change/ revision of loads, which might result in re-design of 11kV cable
circuits.
10. After approval of power supply Master Plan, the developer / consultant to
submit 6 sets of final / approved power supply Master Plan (hard & soft
copy) of the project, for DEWA records.
11. The 11kV substations, connected loads, demand loads / diversity factors,
locations, networks etc. related to the LV design approval, the relevant
drawings, load schedules, single line diagrams etc. shall be uploaded
through on-line Getting Electricity application system (www.dewa.gov.ae).
12. On approval of power supply Master Plan, the plot owners / consultant
may apply for power supply NOC for their plot, through E-Services for
“Getting Electricity” on DEWA Website (as per normal practice), along
with the main developer’s letter confirming the load figures indicated in
NOC application are same as that in the approved project Master Plan
(Refer Annexure-3, for sample format).
13. On finalization of power supply Master Plan for entire or portion (Phase) of
any Major Development, the project developer / consultant to approach
concerned Zoning Authority as well as DEWA Infrastructure Information &
Permits (II&P) Department (at Al Warsan Office) to upload the project
landbase in GIS. II&P department’s requirements are listed in Annexure-4.
3 Annexures
3.1 Annexure – 1
List of documents to be submitted
3 Phasing
4 Nature of Load
3.2 Annexure – 2
Design Requirements & Guidelines for 11kV Supply
In line with DEWA’s power distribution network design, the following guidelines
shall be followed strictly:
3. DEWA standard 11 kV cable sizes are 3/C 300mm2 Copper XLPE, 3/C
240mm2 Copper XLPE, and 3/C 240mm2 Aluminum XLPE.
6. For bulk loads such as furnaces or district cooling requiring direct 11kV
supply (private equipment's), space for metering units at party’s
premises/substation shall be considered. Necessary documents,
drawings, SLD shall be submitted for DEWA’s comments/approval at
design stage.
7. Single unit load demand shall not exceed the maximum sustained
current of DEWA’s 11kV cable/feeder, which is maximum 175A/3MW for
11kV feeder.
10. The planning levels of voltage flicker shall be in compliance with IEC
61000-3-7: ED.2.0-2008. Accordingly, voltage dip calculations during
motor starting shall be submitted along with the motor specification,
starting characteristics, number of motor starts per day, SLD drawings
etc. for approval at design stage.
11. For loads that injects harmonics currents into DEWA’s network,
harmonic study shall be prepared by the party and approved by DEWA
at the design stage. The party to comply with the planning limits of
Harmonic Emissions for voltage and current based on IEC 61000-3-6:
ED.2.0-2008 and IEC 61000–3-12: ED.2.0-2011 respectively.
13. Maximum allowable number of cables per trench for 11kV cables is 20
arranged in maximum two layers. (2.5 to 3-meter trench width on both
sides of the road, close to 132/11kV S/S and 2.0/1.5 meters elsewhere
depending on load distribution).
15. Horizontal spacing between 11kV cables is 150mm (edge to edge for
11kV cables) and vertical spacing between layers is 100mm (edge to
edge applicable for 11kV cables).
16. Separate corridor shall be allocated for 11kV cable laying within party’s
premises along the road to ensure avoiding crossing between 132kV
and 11kV cables.
17. Backfilling to be used for 11kV cables with soil resistivity below 1.6oC-
m/W with the following conditions:
b. At 90% of compaction.
18. Single line diagram illustrating the protection schemes along with relay
setting calculation shall be submitted for DEWA’s comments and
approval at design stage.
3.3 Annexure – 3
Ref: Date :
To,
Reference to the NOC --------------, we hereby confirm that the total connected load
requirement of ------ MW for the plot No. ----------- by (power requirement date) ----------
-------- is complying with the data mentioned in our latest / approved project Master Plan
for ----------------------------------------- Project.
Further, we confirm the type of development on the above indicated plot is -----------------
---------------------------- (industrial / commercial / residential etc.).
With Regards,
For and On behalf of ---------------------- (developer name)
3.4 Annexure – 4
II&P Department requires below listed in order to update Major Project Landbase in
DEWA GIS ;
1. Project Layout
2. Parcels / plots along with parcel / plot IDs.
3. DEWA ESS plots with plot IDs.
4. Road Facilities ;
• Road Centre Line
• Right Of Way
• Dividers (Road medians / roundabouts)
• Road Cross-sections
• Approved corridors with clear indications of width from ROW.
Data formats : The format of the data may be any common GIS format such as Shape
file, ESRI Geodatabase or a common CAD format such as AutoCAD Drawing File (DWG)
or MicroStation Design File (DGN). However, road cross0-sections must be provided in
CAD / DGN formats only.
If the Data is unable to provide in ESRI shape file format, below are few guidelines should
be followed when preparing CAD / DGN data for submission to DEWA.
Each Feature class (Layer) and / or its sub-types need to be in a separate layer/level in
the CAD / DGN file.
o Each CAD layer / level must represent only one class of feature.
o Each text representing information about plot/road/etc and should fit well inside it.
o All data attributes (tabular data) for a corresponding CAD ID will be also be found
and documented in an associated MS Excel spreadsheet. A worksheet for each
CAD layer will be created. The worksheet should contain the CAD ID (ex: handle
which must be unique) and one or more fields that contain the associated attribute
data.
Topological Rules :
o Where two polylines logically join, intersecting features within the same layer these
shall be snapped at the point of intersection.
o Lines should run continuously from Point object to Point object. All line features
shall be of a continuous line-type, such that each individual line feature (i.e each
segment) is only broken at the ends where a node/structure is located.
o Lines should not be broken for the purpose of annotations. Annotation for each
layer shall be placed in annotation layers as specified in the template file.
o Straight lines must be represented by only the beginning and ending x- and y-
coordinate points. The exception to this is a line where the coordinates differ only
in the z values (ex: developed from multiple traverses on the same bearing). Lines
stings must not cross back on themselves or have a zero length (i.e points).
o Polyline features that logically join shall be snapped to each other at the joining
ends. This is, no dangles (overshoots and undershoots) are allowed.
o All edges on polygon features must be snapped together at the vertices. Gap in
polygon boundaries will not be accepted.
o The completed CAD drawing file should contain text in standard fonts that can be
read without third-party software.
Projection :
Transverse Mercator
Parameters :
Longitude of Origin 55:20:00:00 d:m:s
Latitude of Origin 0:00:00:000 d:m:s
False Easting 500,000.000 m
False Northing 0.000 m
Scale Factor along Longitude of Origin 1.0000
Geodetic Datum: WGS84
Ellipsoid WGS84 (standard parameters)
Equatorial Radius: 6378137.000 m
Polar Radius: 6356752.314 m
Eccentricity: 0.0818191908426215
Flattening: 0.00335281066474746
Flattening Inverse: 298.257223563002