Pulchowk Campus Department of Civil Engineering
Pulchowk Campus Department of Civil Engineering
(CESS-NEPAL)
INSTITUTE OF ENGINEERING
PULCHOWK
. CAMPUS
.
DEPARTMENT OF CIVIL
. ENGINEERING
Introduction
Project report in this manual refers to a documented report of the process followed and
the results of final year project conducted by a student in fulfillment of the requirements
in bachelor degree. This report will outline the report format for Final Year Project.
1. ARRANGEMENT OF CONTENTS:
The sequence in which the project report material should be arranged and bound should
be as follows:
1. Cover Page (Specimen copy-1)
2. Title Page (Specimen copy-2)
3. Certificate of Approval (Specimen copy-3)
4. Acknowledgment (Specimen copy-4)
5. Abstract (Specimen copy-5)
6. Table of Contents (Appendix 1)
7. List of Figures (if any) (Appendix 2 )
8. List of Tables (if any) (Appendix 3 )
9. List of Symbols (if any) (Appendix 4 )
10. Abbreviations (if any) (Appendix 5 )
11. Main body
11.1Chapter 1 Introduction (Appendix 6 )
11.2Chapter 2……………….
11.3Chapter 3……………….
…………………………………..
…………………………………..
11.… Conclusion and Recommendation
12. Appendices (if any)
13. References (Appendix 7)
3. PREPARATION FORMAT:
Abstract –Abstract should be one page synopsis of the project report and it must
clearly give the overview of the
(Specimen copy-5).
Table of Contents – The table of contents should list all material following it as well
as any material which precedes it. Appendix 1.
List of Figures – The list should use exactly the same captions as they appear below
the figures in the text. (Appendix 2).
List of Symbols - The list should provide the detail of the symbols used in the report.
(Appendix 4).
Abbreviations – Abbreviation list should provide the details of the abbreviations used
in the report in alphabetical order. (Appendix 5).
Chapters – The main text will be divided into several chapters and each chapter may
be further divided into several divisions and sub-divisions.
List of References –The reference material should include the author name, title, year
in details as shown in Appendix 7. Do not mention the references of the websites in
the report.
TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
PULCHOWK CAMPUS
DEPARTMENT OF CIVIL ENGINEERING
Pulchowk, Lalitpur
Submitted by
Submitted to
Department of Civil Engineering
March 2020
Project Title
[Code No.:]
Submitted by
Submitted to
Institute of Engineering
Pulchowk Campus
Pulchowk, Lalitpur
Nepal
March 2020
Project Title
[Code No.:]
Submitted by
Uttam Pal (PUL073BCE189 or Exam Roll No.)
…
Project Supervisor
Supervisor Name
Full Designation
Organization Name with Full Details
Submitted to
March 2020
Body here…
…………………………..
(Supervisor Name)
Supervisor
Full designation
Organization
……………………………..
(External Examiner Name)
External Examiner
Full designation
Organization
……………………………..
(HOD Name)
Head of Department
Full designation
Organization
ACKNOWLEDGEMENT
Please do it yourself.
10 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
SPECIMEN-5 (Abstract Sample)
ABSTRACT
Please do it yourself.
11 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
Appendix – 1: Table of Contents
TABLE OF CONTENTS
Acknowledgement i
Abstract ii
List of figures iii
List of tables iv
List of symbols v
Abbreviation vi
Chapter 1: Introduction 1
1.1 ………….. 1
1.2 …………. 2
1.2.1 ………. 5
1.2.2 ........... 12
1.2.2.1 ………. 19
1.2.2.2 . . . . . . . . . . 25
1.2.3 ............ 30
1.3 . . . . . . . . . . .. . . . . . . 45
1.4 .................. 58
……………………………….. 60
………………………………...
(Make other chapters in the same format)
References 100
Appendices 102
12 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
Appendix – 2: List of figures
LIST OF FIGURES
Figure Number Figure Page No.
13 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
Appendix – 3: List of tables
LIST OF TABLES
Table Number Table Page No.
………………………………………………………………………………….
………………………………………………………………………………….
………………………………………………………………………………….
14 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
Appendix – 4: List of symbols
LIST OF SYMBOLS
15 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
Appendix – 5: Abbreviations
ABBREVIATIONS
16 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
Appendix – 6: Format of Body Text
Chapter 1: INTRODUCTION
1.1 Background
Soil nailing evolved from the New Austrian Tunneling method which is a system for
underground excavations in rock.
This method consists of passive steel reinforcement in the rock followed by the
application of reinforced concrete. This concept of combining passive steel
reinforcement and concrete has also been applied to the stabilization of rock slopes
since the early 1960s.
The first application of soil nailing was implemented in 1972 for a railroad widening
project near Versailles, France.
Soil nails were used to stabilize an 18 meter (59 ft) high slope consisting of sandy
soil. This method proved to be more cost-effective, while at the same time cutting
down the construction time when compared to other conventional support methods.
The United States first used soil nailing in 1976 for the support of a 13.7 meter deep
foundation excavation in dense sands that contain a significant amount of silt.
Soil nailing was implemented in the expansion of The Good Samaritan Hospital in
Portland, Oregon. This retaining system was produced in approximately half the time
at about 85% of the cost of conventional retaining systems.
In short, the major advantage of soil nail walls is their cost-effectiveness over other
alternatives. When conventional soil nailing construction procedures are used, soil
nail walls are much more affordable than concrete gravity walls and similarly as well
as more cost-effective than ground anchor walls.
17 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
At Maloney Construction, we put our knowledge, experience and commitment to
work for you. Client goals and expectations are never compromised when you hire
Maloney Construction. We offer years of practical field experience and engineering
background to make your vision a reality. From our closely monitored projects, both
big and small, all the way to our first-class equipment and outstanding crew, no detail
ever goes unnoticed at Maloney Construction.
1.2 Objective
2. …..
6. ……………………………………………………………………………….
18 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l
References
[1] S.N Sinha, “Reinforced Concrete design”, Second revised edition, McGraw-Hill,
Boston, 2002
[2] A.K. Jain, “Reinforced Concrete Limit State Design”, Third Edition, Nem Chand
Bros, Roorkee, 1989.
[3] …………………………………………………………….
19 | F i n a l Y e a r P r o j e c t R e p o r t G u i d e l i n e s | | C E S S - N e p a l