Assignment 1
Assignment 1
ENGINEERING
ASSIGNMENT 1
Propane (FC3H8)
Propylene (FC3H6)
Propane (FC3H8)
Cumene (PC9H12)
Process
PDIPB (PC12H18)
Benzene (FC6H6)
1.5 Degree of Freedom
ṅi =ṅ0 + vi ξ 1
Unknown Variables 4
Independent reaction +2
Equation of extend of reactions -4
Composition of impurities -1
Total 1
50 000(1 x 106 )
Cumene production per hour = = 52000.99 mol/hr
120.19 x 8000
Rate Law:
r 1=k 1 C p C b
r 2=k 2 C p Cc
Mole balance :
dCp
=r p
dt
d Cb
=r b
dt
d Cc
=r c
dt
d C p dipb
=r p dipb
dt
Stoichiometry:
Cb=(ybo)(Cto)(Ꝋ-X)
Cc=(yc)Cto)(X)
Cc=(X)(Cpo)
conversion vs yield
1.2
0.8
0.6 1
1/2
yield
0.4 1/4
2
0.2
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
-0.2
-0.4
Conversion of propylene
56161.07−27768.53−8684.16
EP 2=
46800.89
= 0.35 USD/kmol Cumene
Appendix
Polymath calculation
#mole balance
#proppylene
d(Cp)/d(t) = rp
Cp(0) = 209.911 #mol/m3
# benzene
d(Cb)/d(t) = rb
Cb(0) = 419.822 #mol/m3
#cumene
d(Cc)/d(t) = rc
Cc(0) = 0 #kmol/m3
#PDIPB
d(Cpdib)/d(t) = rpdib
Cpdib(0) = 0 #kmol/m3
#rate law
r1=k1*Cp*Cb
r2=k2*Cp*Cc
rp=-r1-r2
rb=-r1
rc=r1-r2
rpdib=r2
t(0)=0
t(f)=3600
k1=3.5e4*exp(-1.04e5/R/T)
k2=2.9e5*exp(-1.47e5/R/T)
R=8.314
T=573.15 #K
Differential equations
1 d(Cp)/d(t) = rp
2 d(Cb)/d(t) = rb
3 d(Cc)/d(t) = rc
4 d(Cpdib)/d(t) = rpdib
Explicit equations
1 R = 8.314
2 T = 573.15
K
3 k1 = 3.5e4*exp(-1.04e5/R/T)
4 r1 = k1*Cp*Cb
5 rb = -r1
6 k2 = 2.9e5*exp(-1.47e5/R/T)
7 r2 = k2*Cp*Cc
8 rp = -r1-r2
9 rc = r1-r2
10 rpdib = r2
11 S = (r1-r2+0.00001)/(r2+0.00001)
12 Y = (r1-r2+0.00001)/(r1+r2+0.00001)
13 Cb0 = 419.822
14 P = (Cp+Cb+Cc+Cpdib)*R*T
15 V = 1
16 N = (Cp+Cb+Cc+Cpdib)*V
17 Cp0 = 209.911
18 P0 = (Cp0+Cb0)*R*T
19 N0 = (Cp0+Cb0)*V
20 Xp = 1-Cp*N*P0/(Cp0*N0*P)
21 delta = Cb0/Cp0
22 Xb = delta-Cb*N*P0/(Cp0*N0*P)
General
Total number of equations 26
Number of differential equations 4
Number of explicit equations 22
Elapsed time 0.000 sec
Solution method RKF_45
Step size guess. h 0.000001
Truncation error tolerance. eps 0.000001