Api 653 Faq
Api 653 Faq
653 2nd - Dec. 1995 General Does API 653 specify the time frame for leak detection
between internal inspections?
653 2nd - Dec. 1995 General Does API 653 include requirements for abandonment of
tanks?
653 2nd - Dec. 1995 General Do aboveground storage tanks with capacity of 10,000
barrels or less require an API 653 inspection?
653 2nd - Dec. 1995 1.1 653-I-10/98 What API 653 rules apply to repairs of riveted tanks?
653 2nd - Dec. 1995 1.5 653-I-04/99 Does API 653 require contractors performing repairs to
have a API 653 certified inspector employed with them,
and if so, where can this be found in the standard?
653 2nd - Dec. 1995 4.2.4 653-I-10/00 Shall the design requirements of the latest edition of
API 650 be considered for tanks that will have their
operating temperature increased above 200°F.
653 2nd - Dec. 1995 4.2.4 653-I-03/01 Question 1: An existing tank greater than 100 ft. in
diameter with a lap-welded bottom is currently in heated
service (>200ºF). This tank is removed from service for
a routine internal inspection. Does this tank have to be
retrofitted with an annular ring per API 650, Section
M.4?
653 1st - Jan. 1991 4.3 What information is required to determine the fill height
according to API 653?
653 1st - Jan. 1991 4.3.3 Will the evaluation of the calculations require a certified
API 653 inspector?
653 2nd - Dec. 1995 4.3.2.1 How do you classify "corroded areas of considerable
size" -- Section 4.3.2.1? Is there a size limit for this
corroded area? If so, what are these limits? If not, why
not?
653 2nd - Dec. 1995 4.3.3 Does the criteria to settle the minimum thickness (tmin --
Section 4.3.3) calculation for welded tank shell apply
only for a local corroded area? If so, what are the limits
for this local area? Can that criteria be applied when
there is a uniform corroded area along all the tank
course? In this particular case, would t1 be equal to t2?
653 2nd - Dec. 1995 4.3.3 653-I-09/00 Question 1: When evaluating the retirement thickness
in a corroded plate away from welds at a distance of at
least the greater of one inch or twice the plate
thickness, is the value of E=1.0 to be used?
653 2nd - Dec. 1995 4.3.3.1 653-I-22/98 Did API intend to reduce the operating height of tanks
when the formula in 4.3.3.1 was changed to eliminate
the term "H-1" and replace it with the term "H"?
653 1st - Jan. 1991 4.4.1 Does API 653 permit the use of leak detection
procedures to justify extending inspection intervals
beyond that determined by corrosion rates?
653 1st - Jan. 1991 4.4.1 What are the applicable requirements in API 653
pertaining to tank bottom settlement limits?
653 2nd - Dec. 1995 4.4.5 653-I-07/97 Does the definition of RPB (see API 653, Section 4.4.5,
or API 650, Appendix I, Section 1.1, Note 1) include a
thin or reinforced thick film lining applied to the topside
of a tank bottom in conformance to API RP 652?
653 2nd - Dec. 1995 4.4.7.1 653-I-04/00 Does API 653 require that tank bottom expected service
life calculations for a bottom, that has been repaired
with patch plates fillet-welded over areas of underside
pitting, be based on the corrosion rate (UPr) of the
repaired areas or the unrepaired areas?
653 2nd - Dec. 1995 General-6 Does API 653 require that the authorized inspector be
physically present at the inspection site and have 1st-
hand knowledge of all aspects of the tank inspection?
653 2nd - Dec. 1995 6.2.4.3 653-I-12/01 Section 6.2.4.3 is clear on the requirements for
changing a tank to operate at a temperature above
200ºF. How should Section 4.3.3.1 be applied to tanks
that are and have been for some time operating at
temperatures above 200ºF?
653 2nd - Dec. 1995 6.3 If ultrasonic thickness measurements are not required,
how would the 1/4 corrosion rate of the shell be
determined for the formal visual external inspection?
653 2nd - Dec. 1995 6.3.2 653-I-24/98 Does API 653 require the insulation covering flanges to
be removed for periodic inspections?
653 2nd - Dec. 1995 6.3.2 653-I-12/99 Does API 653, Section 6.3.2, indicate when the 5-year
external inspection interval is to be measured from, e.g.
the date last inspected, the date on the last inspection
report, or the date put back in service?
653 1st - Jan. 1991 6.3.3 Does API 653, Section 6.3.3 require ultrasonic thickness
readings on the tank shell?
653 2nd - Dec. 1995 6.3.3 653-I-08/97 Referring to API 653, Section 6.3, does this Section,
including Section 6.3.3, ever require an internal
ultrasonic examination of the tank bottom?
653 2nd - Dec. 1995 6.3.3.3 If the internal inspection is used as a substitute for the
external ultrasonic thickness measurements (per
6.3.3.3), are ultrasonic thickness readings required
during the internal inspection?
653 2nd - Dec. 1995 6.4.1.2 653-I-05/02 Background: Robotic inspection, which does not
require an internal entry into the tank to collect data, is
being promoted as a way to comply with the internal
inspection requirements of API 653, Section 6.4.
Furthermore, claims are being made that no internal
inspection is required for periods exceeding 20 years if
the provisions of 6.4.3 are invoked. This essentially
would allow a covered tank to operate for a period
exceeding 20 years without an internal inspection.
653 3rd - Dec. 2001 6.4.2 Referring to API 653, Sections 6.4.2.2 (last sentence)
and 6.4.3 (5th sentence), do they mean together that the
inspection interval shall not exceed 20 years unless an
RBI assessment is performed to support an extension?
653 2nd - Dec. 1995 6.4.2.2 653-I-08/97 Referring to API 653, Section 6.4.2.2, when corrosion
rates are not known, (a) must an inspection be
performed within ten years after a tank has been put
into service?, and (b) is it acceptable to perform the
inspection in the ninth year of operation?
653 2nd - Dec. 1995 Table 6-1 Referring to API 653, Table 6-1, what is the meaning of
the term "tank bottom/foundation design?"
653 2nd - Dec. 1995 Table 6-1 Does the term "means to provide . . . containment of a
bottom leak" imply undertank liner systems?
653 2nd - Dec. 1995 7.3.1 653-I-14/98 Does API 653 permit the welding of electrical conduit
supports (unistruts) to be welded onto the projection of
bottom plates outside the shell of tanks built to API
650?
653 2nd - Dec. 1995 8.2 Referring to API 653, Section 8.2 and 8.3, when inserting
a new shell course into an existing tank shell, is the
weld joining the new course to the course above
considered as a "new weld joint" or an "existing weld
joint?"
653 2nd - Dec. 1995 8.4.2 653-I-06/99 Background: Section 6.4.2 requires the use of
hydrostatic stresses (St) from API 650, Table 3-2. Prior
to the issuance of Addendum 2 of API 653, the formulas
in API 650 and 653 were the same except for the joint
factor (E) contained in the API 653 formula.
2 . 6 D ( H −1 ) G
td = + CA
Sd E
with an “E”, added for the joint efficiency, be used when
a
reconstructed tank is involved? Background: API 653,
Section 8.4.2
requires the use of hydrostatic stresses (St) from API
650,
Table 3-2. Prior to the issuance of Addendum 2 to the
second
edition of API 653, the formulas in API 650 and 653 were
the same
except for the joint factor (E) contained in the API 653
formula. A
reconstructed tank with its original weld (or riveted)
joints must
maintain the joint efficiency of its original construction.
API 653
requires the design and hydrostatic stresses from API
653 2nd - Dec. 1995 8.4.2 653-I-06/99 650
Is it be
theused
intent of API 653 that the following API 650
for reconstructed
formula tanks. This
for the hydrostatic testindicates
height bethat thewhen a
used
formulas from tank
reconstructed API is involved?
650 should also be used for design and hydrostatic
testing of a Sd E t min
reconstructed Htank.
t = The addition +of1 a joint factor is
required if 2.6 D
original joints remain in the tank. If all old joints are
removed, the
current API 650 design formula may be used. Since API
650 and 653
formulae were the same before Addendum 2, this posed
no
problem.
653 2nd - Dec. 1995 9.1 653-I-03/00 Question 1: Does an authorized inspector have to be on
site during reconstruction, repairs and alterations?
653 2nd - Dec. 1995 9.2 653-I-02/98 Referring to API 653, Section 12.1.2.5, does the weld
between the insert plate and the shell plate have to be
fully or partially radiographed if a new nozzle has been
installed in a new insert plate that complies with Section
9.2. and 12.2?
653 2nd - Dec. 1995 9.2.2 653-I-14/98 Do the welding requirements for the critical zone of
Section 9.2.2 of API 653 apply to the welds made for
attaching supports, such as unistrut supports welded to
the projection of bottom plates?
653 2nd - Dec. 1995 9.2.3 Question 1: Does API 653 permit the above new weld
joint to be a lap-welded design, assuming the existing
tank welds are lap-welded?
653 2nd - Dec. 1995 9.2.3 653-I-20/98 Can a complete (360º) doubler plate be installed on the
inside of the tank shell and fillet welded to the ID of the
tanks shell and tank bottom for the purpose of
reinforcing a corroded lower tank shell when the
thickness of the tanks shell does not comply with the
minimum thickness requirements of API 653 due to
external corrosion?
653 2nd - Dec. 1995 9.3.1 653-I-06/97 Question 1: Does API 653 permit installing a lap-welded
patch plate on the inside of a shell plate, as well as the
outside?
653 2nd - Dec. 1995 9.3.1.6 Is it acceptable to repair an externally corroded shell
plate at the shell-to-bottom joint using an internal patch
plate extending to the corner weld?
653 2nd - Dec. 1995 9.3.2 653-I-06/97 Referring to API 653, Section 9.3.2, does this section
mean that it is acceptable to repair a small corroded
area by cutting a 2" diameter hole and then applying a
patch plate?
653 2nd - Dec. 1995 9.3.2.1 653-I-06/97 Referring to API 653, Section 9.3.2.1, does the "inner
perimeter" refer to the perimeter of the hole in the shell
plate?
653 2nd - Dec. 1995 9.7 653-I-11/01 Does API 653 allow nozzle-type clean out fittings that
are half above floor level and half below floor level to be
replaced in an old tank or installed in a new tank? If so,
what section permits them to be replaced?
653 2nd - Dec. 1995 9.8 653-I-17/98 When adding a new nozzle to an existing shell plate > ½
inches that does not meet the current design metal
temperature criteria, which of the [alleged] conflicting
rules are to be satisfied: Section 9.8.2b of API 653,
Section 3.7.3.1a of API 650, or Section 3.7.3.1b of API
650?
653 2nd - Dec. 1995 9.8 653-I-07/99 In the case of a new clean-out fitting being installed in
an old tank, does API 653 or 650 allow the waiving of the
requirement on API 650, Section 3.7.7.3 calling for
stress-relieving after completely pre-assembling into a
shell plate and prior to installation in the tank shell?
653 1st - Jan. 1991 9.9 Are the requirements of Section 9.9.2 applicable only if
the tank bottom has failed?
653 2nd - Dec. 1995 9.9 653-I-18/98 When making a “tombstone" modification to an existing
penetration, extending the reinforcing down to the shell-
to-bottom weld, does API 653 permit increasing the
thickness of nozzle reinforcing plates and
proportionally decreasing the vertical dimension from
the nozzle centerline to the tank bottom?
653 2nd - Dec. 1995 9.9 Does API 653 allow nozzle-type clean out fittings that
are half above floor level and half below floor level to be
replaced in an old tank or installed in a new tank? If so,
what section permits them to be replaced?
653 2nd - Dec. 1995 9.9.1 653-I-06/00 Background: Refer to Sections 9.9.1 and 9.9.2.2 of API
653. Given the following proposed tank modification: 1)
A second bottom is to be installed by slotting the shell.
2) The existing diamond shape reinforcing plate is
required to be replaced with a tombstone type
reinforcing plate as shown in Fig. 9-3b to meet weld
spacing. 3) The modification will satisfy the reinforcing
area required. 4) This modification would violate the
minimum elevation shown in Fig. 3-4A of API 650.
653 2nd - Dec. 1995 9.9.2.1.2 Is the requirement for a projection of a new bottom
beyond the shell specified by the Section 9.9.2.1.2
dependent upon whether the bottom replacement is due
to failure or due to some other reason?
653 2nd - Dec. 1995 9.1 Does API 653 permit the use of lap-welded narrow plate
strips, approximately 6 inches wide, to be used to repair
tank bottoms that have shrunk due to other weld repairs
to the tank bottom? The strips would be installed with
one edge below the adjacent bottom plate and the
opposite edge riding on the adjacent plate.
653 2nd - Dec. 1995 9.1 Is there ever a condition when the new bottom would
not extend beyond the shell plates?
653 2nd - Dec. 1995 9.1 Does API 653 permit the installation of single-
corrugation bell-shaped bottom plates that would serve
as expansion joints? The corrugation size would be
approximately 4 inches high by 14 inches wide.
653 2nd - Dec. 1995 9.1 Is it better to replace a floating roof tank bottom by
cutting a slot in the bottom course or by bringing the
new plates over the top of the shell?
653 2nd - Dec. 1995 9.1 653-I-01/00 Referring to API 653, Figure 9-5 and Section 9.10, Can a
patch be placed near a three-point seam as shown
below?
3-point lap
Weld seam
653 2nd - Dec. 1995 9.10.1.1 Regarding 653, Section 9.10.1.1, if a tank has an annular
ring, is the critical zone limited to the region within 12"
of the shell?
653 2nd - Dec. 1995 9.10.1.1 If the tank does not have an annular ring, does it still
have a critical zone, and is the critical zone defined as
the region within 12" of the shell?
653 2nd - Dec. 1995 9.10.2 653-I-05/98 Does the API allow variations in the installation of tank
bottoms that do not comply with API 653, Section
9.10.2, such as the fillet welding of the new bottom to
the inside of the tank shell instead of slotting the tank
shell?
653 2nd - Dec. 1995 9.10.2 653-I-03/01 If a new bottom is being installed in an existing tank by
means of a slot in the shell, can the bottom be installed
through an existing low-type repad if the weld spacing
is acceptable and the remaining repad has adequate
reinforcement? If the bottom can be installed through
the repad, which weld detail should be used?
653 2nd - Dec. 1995 9.10.2.1.1 Does API 653 permit repairing a tank bottom by welding
a completely new floor directly on top of the old bottom
plates, which would serve as a back-up for the new
welds?
653 2nd - Dec. 1995 9.10.2.1.2 653-I-01/99 Question 1: In API 653, Section 9.10.2.1.2, is “cutting a
slot" intended to mean a complete severing of the tank
wall?
653 2nd - Dec. 1995 9.10.2.4 653-I-19/98 When a new raised bottom is installed in an existing
tank, what criteria apply to the spacing between the
existing shell nozzles and the new bottom-to-shell
weld?
653 3rd - Dec. 2001 9.11.1.2 When installing girders and rafters in an existing tank,
do they need to be installed in accordance with the
latest edition of API Standard 650?
653 2nd - Dec. 1995 9.14.1 653-I-09/01 Background: API 653 specifies a minimum shell plate
thickness of ¼ in. is required to install a 2-inch hot tap.
We must install hot taps on some tanks in which the
shell thickness is less than ¼ in. The tanks are
approximately 50 years old.
653 2nd - Dec. 1995 9.14.1 653-I-12/97 Referring to API 653, Sections 9.14.1.3 and 9.14.5.1, is
the use of E-6010 electrode permitted for welding the
1st pass of the weld attaching the hot-tap nozzle to the
shell? Subsequent passes would be the specified low-
hydrogen electrode (E-7018).
653 2nd - Dec. 1995 Figure 9-1 Do the rules of API 653, Figure 9-1 apply to weld
spacing if bottom plates only are being replaced?
653 2nd - Dec. 1995 10.5 653-I-06/98 Would it be correct to assess planar tilt and calculate
limits via use of the plumbness rules in API 653, Section
10.5.2?
653 2nd - Dec. 1995 10.5.5 653-I-08/99 Question 1: In API 653, Section 10.5.5, does the term
"banding" apply to the fillet-welded joint between the
bottom of the tank shell and the annular plates, i.e. the
bottom corner weld?
653 2nd - Dec. 1995 10.5.6 653-I-14/99 Question 1: Are the foundation tolerances in API 653,
Section 10.5.6, applicable only to reconstructed tanks or
repairs on tank foundations originally constructed to
the tolerances of API 650, Section 5.5.5, and Appendix
B?
653 2nd - Dec. 1995 12 653-I-09/99 Consider a tank built in the 1950’s to API 12C rules, but
having vertical and horizontal welds that will not pass
the API 12C radiography criteria. If only the vertical
welds were repaired, can the tank be put back in service
meeting the API 653 requirements?
653 2nd - Dec. 1995 12 653-I-03/99 Referring to API 653, Section 10, is NDE required after
roof repairs are made?
653 3rd - Dec. 2001 12.1.1 Does API 653 require radiographic tracer shots on
repairs of new shell plate to new shell plate welds and
new shell plate to old shell plate as is required in new
construction repairs with API 650.
653 2nd - Dec. 1995 12.1.2.2 653-I-03/98 Question 1: Referring to API 653, does Section 12.1.2.2
require that cavities created during the removal of
attachment welds of existing reinforcement plates be
examined?
653 2nd - Dec. 1995 12.1.4.2 653-I-08/98 Does API 653, Section 12.1.4.2, in its entirety, apply only
to attachments welded to Groups IV through VI
material?
653 2nd - Dec. 1995 12.2.1 653-I-05/00 With justifiable cause and at the request of the owner, is
it allowable to substitute the RT in Section 12.2.1 of API
653 with UT?
653 2nd - Dec. 1995 12.2.1.1 Regarding API 653, Section 12.2.1.1., if during a major
tank repair new vertical welds are introduced which
both intersect new horizontal welds and old horizontal
welds, does the intersection of the new vertical weld
with the old horizontal weld have to be radiographed?
653 2nd - Dec. 1995 12.2.1.1 Can the examination of the [above] vertical weld
required by Section 12.2.1.1 of API 653 be done
concurrently with either the examination of the
intersection with the new horizontal weld or with the
examination of the intersection with the old horizontal
weld?
653 2nd - Dec. 1995 12.2.1.1 When replacing several shell rings on an existing tank,
is it acceptable, per API 653, to radiograph the joints
between existing plates per Section 12.2.1.1, 12.2.1.2,
and 12.2.1.3 of API 653 and joints between new plates
per API 650? Or must all joints be radiographed per API
653?
653 2nd - Dec. 1995 12.3 653-I-05/98 Does the hydrostatic test in Section 12 of API 653
specify a water test or can any liquid be used?
653 2nd - Dec. 1995 12.3 653-I-09/98 A tank has been repaired and hydrotested according to
the requirements of API 653. Following the hydrotest, a
condition not complying with API 653 is discovered, e.g.
a weld spacing being too small, that was not identified
prior to testing. Is this tank acceptable for service?
653 2nd - Dec. 1995 12.3 653-I-15/98 Question 1: Does API have any thoughts as to when it
is infeasible to get water for hydrotesting?
653 2nd - Dec. 1995 12.3 653-I-16/98 Question 1: What is the maximum nozzle size that can
be installed before a full hydrotest is required?
653 2nd - Dec. 1995 12.3.1 Referring to API 653, Section 12.3.1.2 (e) and Table 12-1
(3), do these apply to the cleaning of the weld necessary
prior to making a restoration of a corroded or otherwise
deficient weld?
653 2nd - Dec. 1995 12.3.2 653-I-23/98 Does API recommend the hydrostatic testing of major
repairs to tanks that store products with a specific
gravity greater than 1.0?
653 2nd - Dec. 1995 12.3.2.1 653-I-11/98 Referring to API 653, Second - Addendum 2, for the
case of a tank with a new bottom installed in an existing
tank that includes a new shell-to-bottom weld, is a
hydrotest required?
653 2nd - Dec. 1995 12.3.2.1 653-I-01/01 To meet the requirements of a hydrostatic test
exemption per API 653, Section 12.3.2.1(a), must all
repairs be reviewed, or just the items that are covered in
the scope of the major repair?
653 2nd - Dec. 1995 Figure 12- Referring to API 653, Table 12-1 and Figure 12-1, if the
1 conditions for a given tank fall above the Figure 12-1
curve, is a hydrostatic test required? Assume that the
other appropriate requirements in Table 12-1 have been
satisfied.
653 2nd - Dec. 1995 Figure 12- 653-I-04/97 Question 1: Referring to Table 12-1 and Figure 12-1, if
1 the location of the plot of shell metal temperature and
shell thickness is above the curve in Figure 12-1, are the
requirements of Table 12-1 (Basic Conditions) met?
653 2nd - Dec. 1995 Figure 12- 653-I-13/98 Is it possible to exempt from hydrotesting a tank that
1 requires a new shell-to-bottom weld or a new shell-to-
annular plate weld because of the replacement of the
annular plates or the installation of new bottom plates
under the tank shell using the basic conditions in Table
12-1?
653 2nd - Dec. 1995 13 653-I-10/98 Referring to API 653, Section 11, if the only work to be
done on a tank is floor repair, must the shell course,
allowable stress, and material be entered on the
nameplate?
653 2nd - Dec. 1995 13 653-I-10/01 How long does API 653 require inspection records to be
retained? Background: We are working with API 653-
certified inspectors to perform API 653 inspection
services for various clients. A question has arisen over
whether monthly "routine in-service inspection" records
are to be kept for the life of the tank, or whether some
shorter retention interval, such as 10 years, might be
considered adequate.
ration, and Reconstruction
Last update: March 10, 2004
Reply
No.
No.
No. API 653 applies to tanks built in accordance with API 650
and its predecessor 12C with no reduction in size. API 650 is
designed for tanks in oil storage services. API 650 can be
used for other applications as may be required by the tank
owner/operator or jurisdictional requirements. API 653 can be
used for inspection of tanks in other services. Jurisdictional
requirements may specify instruction per API 653.
Reply 1: Yes.
Reply 2: Yes.
No.
Reply 1: The committee currently has an agenda item to study
this question. Any changes resulting from this agenda item
will appear in a future addendum or edition to API 653.
Yes.
Yes.
Reply 1: No, but the authorized inspector is required to be on
the site for the external and internal inspections required by
Section 4 of API 653.
Reply 2: No.
Yes.
No. This type of repair does not comply with the requirements
of API 653.
Reply 2: No.
Reply 1: The rest of Section 7 specifies the applicable repair
rules.
Yes.
No.
Refer to Section 9.8.1 of API 653, which requires that the rules
of 653, Section 9.8.2 and 650 be met. Section 3.7.3.1a
applies to the spacing from shell joints to insert plates,
reinforcing plates, or nozzles. Section 3.7.3.1b applies to
spacing between adjacent nozzles, reinforcing plates, insert
plates, or any combination. Section 9.8.2b specifies the
minimum size of the insert plate if a reinforcing plate is used.
These rules, including 9.8.2d, need to be worked together.
There is no conflict.
No
No. API 653 is based on the concept that tank repairs are
intended to restore the tank to API 650 condition, except
where specifically indicated otherwise, or where specific
details are not provided. In this case, repairs are not
specifically addressed in areas away from the critical zone
near the shell, thus the rules of 650 would apply. (Refer to API
650, Section 3.1.5.4 which requires 12 inches between
adjacent three-corner lap welds.) Note that there will be rules
published in the next appendix that will cover the use of
lapped patch plates, with the entire patch plate being installed
above the existing plates.
No
No. API 653 is based on configurations specifically conforming
to API 650 except where stated otherwise, or where existing
details are not covered by API 650. Refer to Section 1.1.5 and
9.1.1 of API 653. The proposed detail may or may not provide
a "level of integrity" equal to the current 650 rules. API 650 is
based on bottoms that are flat, resting on foundations that
provide adequate friction that keep the tensile stress due to
shell expansion to an insignificantly low value.
Yes, unless the patch plate covers the 3-point lap. See Note 5
in Fig. 9-5.
No, the critical zone is the entire annular ring and extends 12"
beyond the annular ring.
Yes.
No.
The committee currently has an agenda item to add a detail for
slotting through a dog-house repad. Any changes resulting
from this agenda item will appear in a future addendum or
edition to API 653.
Reply 1: Yes.
Reply 2: No.
Yes, if the thickness is not less than 3/16 inch. Refer to Table
9-1 and to Section 9.14.1 for further restrictions.
No.
API 653 has no rules on tilt of existing tank shells, per se. The
only tolerances applicable to reconstructed tank shells are for
plumbness, roundness, peaking, and banding, as defined in
Section 10.5. However, Section 10.5.6 provides rules that in
effect specify the permitted planar tilt of the foundation. Also,
refer to Appendix B, Section B.2.2.2, which provides
guidelines on rigid body tilting.
Reply 1: No.
Reply 2: No.
Reply 1: Yes.
No
Yes.
No.
The intent is only for water to be used for the hydrostatic test
so the tank shell is stressed to a higher level than in operation
to prove adequacy of repairs for product service and to
minimize the risk of brittle fracture while in service.
At the time the tank repair and testing was completed the tank
is acceptable for service per API 653, assuming there was no
prior knowledge of the noncompliant condition. If the condition
was identified after hydrotesting, that condition must be
evaluated and handled as required by the tank owner/operator
and the local jurisdiction.
Reply 1: API does not act as a consultant on specific
engineering problems or on the general understanding or
application of its standards. API’s activities in regard to
technical inquiries are limited strictly to interpretations of the
standard and to the consideration of revisions to the present
standard based on new data or technology.
Reply 2: No. The intent is only for water to be used for the
hydrostatic test so the tank shell is stressed to a higher level
than in operation to prove adequacy of repairs for product
service and to minimize the risk of brittle fracture while in
service.
Reply 1: Yes.