Project Management Lecture Presentation PDF
Project Management Lecture Presentation PDF
MANAGEMENT
FRANI | LEE | MELAD | TAN, V. | TRINIDAD
TABLE OF CONTENTS
Network-Planning
01 Project Management Models 03
Explain what projects are Analyze projects using
and how projects are network-planning models
organized
Project Management
02 Managing Projects Information Systems 04
Evaluate projects using Exemplify how
earned value management network-planning models and
earned value management
are implemented in
commercial software
packages
PROJECT
MANAGEMENT
PROJECT
A series of related jobs
usually directed toward
some major output and
requiring a significant
amount of time to
perform.
PROJECT
MANAGEMENT
Project management is
defined as planning,
directing and controlling
resources to meet the
technical, cost and time
constraints of the project.
PROJECT MANAGERS
Technical skills
People Skills
Resolve Conflicts
PROJECT CATEGORIES
ORGANIZATIONAL STRUCTURE: PURE PROJECT
● Small project-focused team that works full-time for the
project
● Advantages
○ Project manager has full authority
○ One boss only
○ Decisions are made quickly
○ High team pride, motivation and commitment
● Disadvantages
○ Duplication of resources
○ Organizational goals and policies are ignored
○ Falls behind in knowledge of new technology
○ Worries about life after the project; project
termination is delayed
ORGANIZATIONAL STRUCTURE: FUNCTIONAL PROJECT
● Advantages
○ Enhanced communication between functional
divisions
○ Project manager ensures successful completion of
project
○ Team members have a functional “home” after project
completion (vs. Pure project organization)
○ Policies of the parent organization is followed,
increasing support for the project
ORGANIZATIONAL STRUCTURE: MATRIX PROJECT
● Disadvantages
○ Two bosses (functional vs. project manager)
○ Doomed to fail unless PM has strong negotiation
skills
○ Danger/risk of suboptimization: PMs hoard resources
for their own projects, thus harming other projects
ROLE OF PROJECT MANAGER
Project
Tasks
Subtasks
WP
ORGANIZING PROJECT TASKS
For example you instructor asked that you perform an analysis using
the following steps
1. Select a Company
2. Obtain the company’s annual report and perform a ratio analysis
3. Collect technical stock price data and construct charts
4. Individually review the data and make a team decision on whether
to buy the stock
Select a company
A(01) ALL MEMBERS
1 week
Ratio analysis
B(02) 2 MEMBERS
2 weeks
Sequence of Activities
02 Determine the required sequence of
activities and construct a network
reflecting the precedence relationship
Critical Path Method
Immediate
Activity Designation Time (Weeks)
Predecessors
Sequence of Activities
02 Determine the required sequence of
activities and construct a network
reflecting the precedence relationship
Critical Path
03 Determine the critical path
Precedence Relationship
Identify Activity Critical Path Method
01 Identify each activity to be done in the
project and estimate how long it will
take to complete each activity
Sequence of Activities
02 Determine the required sequence of
activities and construct a network
reflecting the precedence relationship
Critical Path
03 Determine the critical path
Early/Late
Start/Finish
04 Determine the early
start/finish and late
start/finish schedule
Slack Time
● Slack Time
○ Leeway in when an activity
can start and finish
● Early start and finish
● Late start and finish
Early Start and Late
Start Schedule
○ NT: 2 days
○ CT: 1 day
○ NC: $6
○ CC: $10
STEP 1: PREPARE CPM DIAGRAM WITH ACTIVITY COSTS
○ NT: 2 days
○ CT: 1 day
○ NC: $6
○ CC: $10
STEP 1: PREPARE CPM DIAGRAM WITH ACTIVITY COSTS
How do we draw the entire diagram
given all of these values?
● Activity B ● Activity D
○ NT: 5 days ○ NT: 3 days
○ CT: 2 days ○ CT: 1 day
○ NC: $9 ○ NC: $5
○ CC: $18 ○ CC: $9
● Activity C
○ NT: 4 days
○ CT: 3 days
○ NC: $6
○ CC: $8
STEP 1: PREPARE CPM DIAGRAM WITH ACTIVITY COSTS
How do we draw the entire diagram
given all of these values?
● Activity B ● Activity D
○ NT: 5 days ○ NT: 3 days
○ CT: 2 days ○ CT: 1 day
○ NC: $9 ○ NC: $5
○ CC: $18 ○ CC: $9
● Activity C
○ NT: 4 days
○ CT: 3 days
○ NC: $6
○ CC: $8
STEP 2: DETERMINE THE COST PER UNIT OF TIME TO
EXPEDITE EACH ACTIVITY
● Assume that activity time and cost has a linear relationship
● Get the slope of the line
(CC - NC)
Slope =
(NT - CT)
● Start with reducing the critical path time by one day using the
lowest-cost activity
● Recompute and find the new critical path and reduce it by one also
● Repeat until there can be no further reduction in the project
completion time
STEP 4: SHORTEN THE CRITICAL PATH AT THE LEAST COST
STEP 4: SHORTEN THE CRITICAL PATH AT THE LEAST COST
STEP 4: SHORTEN THE CRITICAL PATH AT THE LEAST COST
STEP 4: SHORTEN THE CRITICAL PATH AT THE LEAST COST
STEP 4: SHORTEN THE CRITICAL PATH AT THE LEAST COST
STEP 4: SHORTEN THE CRITICAL PATH AT THE LEAST COST
STEP 4: SHORTEN THE CRITICAL PATH AT THE LEAST COST
STEP 5a: PLOT PROJECT DIRECT, INDIRECT, AND
TOTAL-COST CURVES
($20)
($15)
($10) ($10) ($10) ($10)
STEP 5a: PLOT PROJECT DIRECT, INDIRECT, AND
TOTAL-COST CURVES
($45)
($42) ($37)
($33)
($30)
($28)
($26)
($20)
($15)
($10) ($10) ($10) ($10)
STEP 5a: PLOT PROJECT DIRECT, INDIRECT, AND
TOTAL-COST CURVES
STEP 5b: FIND THE MINIMUM-COST SCHEDULE
PROJECT
MANAGEMENT
INFORMATION
SYSTEMS
The Microsoft Project