05GENREPX0015 Rev0
05GENREPX0015 Rev0
Reference : WB/WB/CB859/2613269/13/R/063/3
Table 1: Visas
Contact
William Boudoux | RAMS Consultant
1.2. Glossary
1.2.1 Acronyms
Acronym Signification
BV Bureau Veritas
CM Compression Platform
CPP Central Processing Platform
FWS Full-Well-Stream
LNG Liquefied Natural Gas
MMSCFD Million Standard Cubic Feet per Day
MTTF Mean Time To Failure
MTTR Mean Time To Repair
PAD Process Availability Diagrams
RAM Reliability Availability Maintainability
WHP Wellhead Platform
Failure Rate (=lambda)
1.2.2 Definitions
Term Definitions
ISO 20815:2008 defines Availability as the “ability of an item to be in a
state to perform a required function under given conditions at a given
instant of time, or on average over a given time interval, assuming that
the required external resources are provided”.
Note: For the scope of this study, availability is defined as the ratio of
the expected average service time which is the total plant design life
minus the assumed scheduled maintenance and calculated unplanned
Availability events down-time divided by the total planned period.
This definitions applies for following objectives :
- availability of 96% for the Plant
- and availability of 96% for the Chemical Injection.
NC3 and NC8 are located in Block SK 316, approximately 180km North off Bintulu,
Sarawak with water depth ranging between 104m – 107m. NC8 field is located
approximately 7km South East of NC3. The nearby riser facility, E11RC is located
approximately 80km South West of NC3 and has an existing Trunkline 6 (TL6)
connecting E11RC to shore.
NC3 will be made as hub, which will comprise Central Processing Platform (CPP) and
Wellhead Platform (WHP) bridge-linked to it. Another WHP will be installed at NC8 and
NC 8 will be tied-back to NC3 via an inter field subsea pipeline.
NC3 and NC8 gas production is 600 MMSCFD gross for a plateau period of 15 years.
NC3 field will commence production for 5 years prior to NC8 come on stream to
supplement the production rates thereafter. Gas compression facilities shall also be
considered at NC3 in order to maintain the gas export pressure, as the well head
pressure will be getting depleted for lateral years. Gas compressor facilities shall be
located in separate platform which will be bridge linked to NC3 CPP.
Gas from NC3 and NC8 fields are the main feed gas supplier into LNG Plant Train 9
with NC3 expected to be ready for start-up in December 2015.
The results are presented on the form of diagrams. The diagram represents functional
interconnection between various equipment, sub-systems or functions to represent the
plant reliability and availability logic.
Dotted box refers to units/functions of the process where a failure does not lead to loss
of gas production. Solid lines boxes refer to units or functions where a failure can have
an impact on production availability. When a description of the system is available, as
the architecture or module capacities, that information is given and indicated on the
diagrams.
Unit Name
Unit which may have an impact
N*x%
y m3/h on gas production.
Unit Name
Unit with negligible impact on gas
N*x%
y m3/h production
NC3 Wells Production Manifold NC3 WHP Open Drain NC3 WHP Vent
Gas Production (later years)
NC8 Wells NC8 WHP Open Drain NC8 WHP Vent NC8 Instrument Air Power Generation
Output
Input 4*25% - - - (redundant from NC3
300 MMSCFD - - - CPP)
These diagrams represent the gas production on initial years and later years from well
production to NC3 CPP. Drain and Vent on NC3 WHP have a negligible impact on
availability.
After start-up of NC8 WHP, gas production will be divided between the two fields
(NC3 and NC8 – 300MMSCF). The NC8 WHP has its own utilities.
water
water
Produced Water
Treatment
water
1*100%
-
Diesel Fuel system Sea Water Lift sytem Potable Water system Cooling Water sytem Methanol
Utilities
Corrosion inhibitor Scale inhibitor Power Gen. system Flare & Vent sytem Drain system
- - 3*50% - - Output
- - - - -
These diagrams represent the NC3 CPP gas production. Condensate production and
water treatment have only a slight impact on gas production and have been excluded
from the scope of work. The gas production consists of well stream cooling (2*50%),
slug receiver (1*100%), glycol contactor (1*100%), gas metering (3*50%).
Glycol contactor and its glycol regeneration will be modeled as there is a reliability
objective on this unit.
As, the compression unit is outside scope, there is no difference between early years
and later years for the NC3 CPP.
Some utilities that have an impact on gas production availability will be modeled as
fuel gas system, nitrogen system, instrument air system, diesel fuel system, methanol
injection, corrosion inhibitor injection, scale inhibitor injection, flare and vent systems.
5.3. Tables
Dysfunctional analyses table are available in Appendix 1.
Production cases: Two production cases are analyzed: a first case with NC3
production of 600 MMSCFD until 2020, and a second case with 300 MMSCFD
from NC3 + 300 MMSCFD from NC8 until 2029.
Human factor: Human error is not taken into account within the study as it
difficult to assess. The operating staff shall be supposed to be present and
qualified to operate the facilities, well trained and in a good physical condition.
Rare events: Rare events not directly linked with a physical random
phenomenon intrinsic to plant’s components (that are phenomenon modeled in
RAM study) shall not be modeled (e.g.: fire, pipe rupture, corrosion supposed
dealt with by design; dropped object faults…). These events shall be
considered as analyzed and correctly covered in other studies like QRA.
Planned Events: Full ESD is planned every 6 months and will have a duration
of 8 hours.
Failure Modes: The failure modes taken into account in this study are only
critical failure modes provided in the databooks with the exception of the two
distillation columns C-9500 and C-9501 (Glycol Package) for which the
degraded modes have been taken into account.
For the RAM study, next assumptions have taken into account.
Future wells for NC3 and NC8 (up to 6 wells for each configuration) have not been
taken into account as the modeled design is the most conservative.
Closed and Open drain systems, as much as the Flare & vent systems, have not been
taken into account as a failure of these systems will have minor impact on production.
Water separated from the Condensate Coalescer will also be sent to the Produced
Water Treatment System. Dewatered condensate is pumped by Condensate Export
Pumps, after which it is mixed with the export gas. The Condensate Export Pumps will
spike dewatered condensate into gas export pipeline.
In the RAM study the condensate treatment have been taken into account with next
assumptions. The condensate treatment can handle condensate if:
In case of unavailability of the condensate treatment, the high high level (HHL) limit
will be reached in the Slug Receiver and Gas production will be stopped (after 90
minutes of condensate production stoppage).
The two glycol make-up pumps are modeled in a 2*50% configuration. The two
circulation pumps are modeled in a 2*100% configuration.
Power Generation is modeled with 3 Power Turbines (3*50%). The turbines can use
Fuel Gas or Diesel Gas to provide energy to the platform.
Diesel system and Fuel Gas system have been modeled. Total Fuel Gas demand is
10 MMSCFD, the main source is SDV-6001 (90%). In case of loss of the Fuel Gas
System, the Diesel system can be used. Detail analysis of failures of the Diesel
system is indicated in Appendix 1.
Equipment Type Failure MTTR Source Equivalent equipment in the data book
Rate
3 phase separator 3,59E-05 7,4 OREDA-02 §3.2.8 Separator
Air compressor (incl. 1,72E-04 60 OREDA-02 §2.2.1 Electric Motors / Compressors
Motor) OREDA-02 §1.1.1.1 Compressors / Centrifugal / Electric
Driven
Air Dryer 2,40E-05 8,8 OREDA-02 §3.2.7 Vessels / Scrubber
Air Receiver 6,76E-05 28,5 OREDA-02 §3.2.10 Vessels / Surge Tank
Blow Down Valve 1,37E-05 16,5 OREDA-02 §4.3.1.2 Valves / Ball / Flare,vent & blow-down
Chemical Injector 2,10E-05 14,3 OREDA-02 §4.3.6.1 Valves / Globe / Chemical Injection
Chemical Injection 1,44E-05 12 OREDA-02 §1.3.1.1 Electric Motors / Pump / Chemical
Pump (incl. Motor) OREDA-02 §2.2.2.1 Injection
Pumps / Centrifugal / Chemical Injection
Chemical Tank 2,89E-05 18,3 OREDA-02 §3.2 Vessels
Choke Valve 1,09E-05 9 OREDA-02 §4.3.1.3 Valves / Ball / Gas systems
Coalescer 3,44E-05 55,4 OREDA-02 §3.2.1 Vessels / Coalescer
Contactor 9,14E-05 27,1 OREDA-02 §3.2.2 Vessels / Contactor
Control Valve 1,05E-05 10,7 OREDA-02 §4.3.1 Valves / Ball
Diesel Generator 8,14E-03 8 OREDA-02 §2.1.1 Electric Generators / Motor drive
(FTS) (diesel, gas motor)
Fuel Gas Heater 1,70E-05 5 OREDA-02 §3.3.2 Heaters and boilers / Electric
Filter 1,00E-06 4 FARADIP.THREE Filter (Blocked / Leak)
Flash Drum 1,31E-05 8,4 OREADA-02 §3.2.4 Vessels / Flash Drum
Flow Meter 3,81E-06 9,8 OREDA-02 §4.2.1 Process Sensors / Flow
Glycol Pump (incl. 2,40E-05 12 OREDA-02 §2.2.2.4 Electric Motors / Pump / Cooling
Motor) OREDA-02 §1.3.1.5 systems
Pumps / Centrifugal / Cooling systems
Surge Drum 6,76E-06 28,5 OREDA-02 §3.2.10 Vessels / Surge Tank
HIPPS Valve 1,64E-05 12,6 OREDA-02 §4.4.5 Valves / ESD/PSD
Loading Arm 1,05E-05 10,7 OREDA-02 §4.3.1 Valves / Ball
Motor Operated 1,05E-05 10,7 OREDA-02 §4.3.1 Valves / Ball
The production availability of the plant is 96.94%. This figure corresponds to the ratio
between production versus planned production and includes planned shutdowns,
pigging activities and ESD Tests.
The availability of the plant is 97.27%. This figure means that the plant is available
97.27% of the time, meaning able to produce gas (above 0% production). This figure
takes into account that production is only carried out by NC3 between 2015 and 2020
and that production is carried by both WHP NC3 and NC8 between 2021 and 2030.
The reliability of the plant is 99.16% (it corresponds to the production availability
without consideration of planned events shutdowns).
One important element to take into consideration regarding the reliability is the number
of times when the system will reach 0% of gas production. The analysis from Petri
Nets and Monte-Carlo simulation estimation is that during 15 years, the system will
After start-up of NC8, the mean production availability decreases. This is due to NC8
WHP Utilities which insert new possible failures into the system. However, in case of
NC8 failure, gas production is still ensured by NC3 (300 MMSCFD – 50% of gas
production).
NC8 Utilities that includes Power Generation and Air Instrument Unit;
NC3 CPP Well Stream Cooling Unit;
NC3 CPP Gas Dehydration Unit;
NC3 CPP Utilities ;
The unavailability of NC8 WHP Utilities is caused by the Air Instrument unit. As Air
compressors / Air dryers are redundant, unavailability is coming from air receivers V-
5470 and V-5500.
This unit will produce 50% of the output if one exchanger in one of the two branches is
in failure and/or maintenance.
The unit will produce 0% of the output if the two branches are unavailable. However,
the main contributor to this production case is a failure of the SDV-2006.
The reliability objective (96%) of the Glycol package is fulfilled by the design.
In order to increase the availability for this unit, the attention should be given to the
distillation columns C-9500 / C-9501. For these columns, reliability data issued from
OREDA-02 are indicated hereafter.
For these two components, there is no critical failure mode identified for the distillation
columns. The identified failure modes in the OREDA are only degraded failure modes
which prevent the system from providing its output within specifications. Such a failure
would usually, but not necessarily, be gradual or partial, a may develop into a critical
failure.
Recommendation: One assumption of this RAM study is to take into account only
critical failure modes for the different components. As this data is not available for
distillation columns, degraded failure modes have been taken into account
(conservative approach). A sensitivity case can be created without these two columns
in order to be consistent between the failure mode taken into account for all the
components.
The mean value for Chemical Injection Availability is 99.86%. This figure does not take
into account a planned event shutdown for preventive maintenance. With a planned
event shutdown of 1 week each year, the availability reaches 97.95%.
No impact on gas production has been implemented since chemical injections are
used only for start-up and/or intermittent operation.
First, a functional analysis has been conducted to identify functions and units that
should be assessed in the next phase of the study (see Step 1: Production Availability
Diagrams).
Then, a dysfunctional analysis has been conducted to identify components that may
jeopardize the gas production. This analysis is presented in Appendix (see Step 2:
Dysfunctional Analysis).
The 3rd step has consisted to identify and list assumptions for the study (see Step 3:
Selection of reliability data and assumptions).
The 4th step has allowed modeling the NC3 WHP, the NC8 WHP and the NC3 CPP to
calculate RAM indicators and to compare these indicators to RAM objectives (see
Step 4: Availability Analysis).