Operations Management Assignment
Operations Management Assignment
KEY STAKEHOLDERS:
1.0 INTRODUCTION
This document is a Management Plan which outlines the approach to managing a housing
project planning, execution control and closure to create modern affordable home suitable for a
growing family living. The Plan has been formulated out of best practice for execution of the
minor nature of the development proposed.
This document includes comment on the envisaged construction operations comprising: site
establishment, logistics and the process of managing the overall local environment. It seeks to
ensure that the works cause the minimum practicable disruption to residents including by
achieving a safe working and living environment.
The Plan provides an overview of the key project activities. Generic statements will be
amplified at the appropriate stage of the project execution together with relevant procedures
and detailed method statements. This Plan will be used as the template for developing the
construction phase health and safety plan.
The objective of this project is to build one hundred (100) affordable high-quality, single
family house units at Oyibi in the Greater Accra (Tema) municipality within 18 months. The
project is also designed to support youth employment agenda within the community. The
affordable houses units will be built from sustainably sourced materials.
The unit features will be as described in the deliverable list to improve its life span. The
average construction price (cost per unit) for a unit is approximately GHS 120,000 (Taylor,
2014, p. 1). The specification for this project involve large finished area with planned
amenities to meet demand.
b) Project Deliverables
1. A 370 square-foot finished houses, with 2 bedrooms and 1 bathroom.
2. Exterior finish in accordance with environmentally preferable products.
3. Energy independence systems, including rooftop solar energy installation.
4. Interior finish using environmentally preferable materials.
c) Project Baseline Milestones
Project Phases Activity Completion Date
1. Contract signed 6th July, 2020
2. Architectural design started 12th July, 2020
3. 30% design review 20th July, 2020
Phase One 4. 60% design review 3rd August, 2020
5. 90% design review 16th August, 2020
6. Design complete 30th August, 2020
7. Permits approved 30th September, 2020
8. Excavation complete 30th November, 2020
9. Foundation complete 8th January, 2021
10. Block works 30th January, 2020
Phase Two 10. Framing complete 14TH March, 2021
11. Roofing complete 30th April, 2021
12. Plumbing, electrical, and mechanical 4th June, 2021
installed
13. Plumbing, mechanical, electrical inspections 11th July, 2021
passed
Solar system installed 30th July, 2020
14. Exterior finish 27th August, 2021
Phase Three 15. Landscaping complete 30th October, 2021
16. Interior finish 30th December, 2021
17. Final inspection and acceptance by sponsors 22nd January, 2022
a) Analysis of Stakeholders
Stakeholder analysis is intended to identify the groups that are involved in the project in order
to ensure their communication needs are known by the project team. This is because
stakeholders need “project information to make decisions and/or contribute to project
progress” (Larson and Gray, 2014, p. 120). The analysis of the stakeholders for this project
show there are three main groups namely: Board of Directors and Shareholders of R&J
Systems Limited, The Ministry of Works and Housing, The Chief and People of Oyibi, Tema
Municipal Assembly.
b) Information Need
The various stakeholders will be updated as each sub-task is completed, and if any activity will
cause a delay, increased cost, or affect project inspection or completion of milestones as soon
as they are identified, stakeholders will be informed if required. Regular communications will
also be ensured among the project manager, project team and contractor, sponsor.
The goal of this analysis is to ensure the project defines “what information is pertinent to
stakeholders who contribute to the project’s progress” (Larson & Gray, 2014, p. 121). The
project manager will be kept apprised of aspects of the project from the project team, general
contractor, and county Inspector in order to make adjustments in time, cost, or supplies. The
project team will be responsive to all levels of the project to resolve issues as soon as practical.
c) Information Source
Sources of information to be communicated includes; Milestone reports provided by the
project team to the sponsor and project manager will include progress status for each
milestone. Project status reports are provided by the project manager and will include an
updated risk register highlighting any risks that have become issues, along with the proposed
remediation plan, primary point of contact for resolution, and project budget status.
The General Contractor and sub-contractor status reports will be provided by the respective
entity and will include, at a minimum, actual and projected percent of completion of the task,
status of known risks, and emerging risks. Issue reports will be updated by the responsible
party per the schedule given in the below matrix. New issues affecting scope, schedule, or
budget will be reported to the project manager by the responsible party immediately.
Approved change requests are the sole responsibility of the project manager. Change requests
shall be formulated and submitted by the project team to the project manager and will include
recommended corrective or preventative actions to remedy or avoid potential shortfalls or
undesirable conditions.
It will be the responsibility of the party that cannot meet their respective task on time, within
budget, or within scope, to notify the required audience in writing within 24 hours of the issue
being identified. It will be the recipient’s requirement to reply with their response or solution
in writing within 24 hours of being notified. The exception to this is if the approval from the
sponsor is required. Any approval costing more than GHS 2,000 or delaying the primary
project by more than one week must have the sponsor’s signed approval.
GANTT CHART
2020 2021 2022
Activity Node Activity (Task) Start End Dur July Aug Sept October Nov Dec Jan Feb March April May June July Aug Sept Oct Nov Dec Jan
1.1 Project Initiation 30/06/2020 06/07/2020 7
1.2 Project planning 01/07/2020 31/08/2020 60
1.3 Project design 01/07/2020 31/08/2020 60
1.4 Permitting 01/08/2020 30/09/2020 60
1.5 Foundation works 01/10/2020 08/01/2021 100
1.6 Block works 01/11/2020 30/01/2021 90
1.7 Framing and Roofing 09/01/2021 14/03/2021 60
1.8 Electrical works 01/03/3021 30/04/2021 60
1.9 Plumbing works 12/04/2021 11/06/2021 60
1.10 Solar system 01/06/2021 30/07/2021 60
1.11 Exterior finish works 18/07/2021 27/08/2021 45
1.12.1 Dry wall 15/06/2021 30/07/2021 45
1.12.2 Interior finish carpentry 01/08/2021 30/09/2021 60
1.12.3 Interior painting 02/11/2021 31/12/2021 60
Kitchen and bathroom
1.12.4 01/10/2021 30/11/2021 60
cabinetry
1.12.5 Floor finish 01/11/2021 30/12/2021 60
1.13 Landscaping 01/09/2021 30/10/2021 60
1.14 Monitoring and control 15/10/2020 25/12/2021 450
1.15 Project closure 01/01/2022 14/01/2022 14
Final inspection and
1.16
acceptance by sponsors. 15/01/2022 22/01/2022 7
This will help to manage time constrains as a result of slacks. Where there are leads, proper
arrangements will be made to capitalize on them to cover delays in other activities. Therefore a
schedule control system will be adopted which will includes the paper-work, tracking systems,
and approval levels necessary for authorizing changes.
5.0 PROJECT BUDGET MANAGEMENT APPROACH
The budget the affordable housing project will be managed not to exceed GHS 120,000. In
preparing the budget, the top-down estimate approach will be adopted. This will also involve
budgeted cost of work scheduled which will provide accurate tracking of each deliverable to
find out if it is under cost or over cost as compared to the project estimate. This tracking will
take into account cost of resources paid.
Microsoft Project 2013 will be used by the team to track the variance over time utilizing the
report option. The variance over time in Microsoft Project 2013 allows for the project manager
and the project team to evaluate cost variance (CV) and schedule variances (SV) for the project
based on status date. Such that if CV is negative, then the project is over budgeted. If SV is a
positive value, then the project is behind schedule. Where Cost Variance (CV) = Earned Value
(EV)-Actual Cost (AC). The earned value is the budgeted cost of work performed (BCWP).
Scheduled Variance (SV) = Earned Value (EV)-Planned Value (PV).
a) Proposed Cost Estimate
REFERENCE
• Larson, E. W., & Gray, C. F. (2014). Project management: The managerial process. (6 th
ed.). New York, NY: McGraw-Hill Education.
• Project Management International. (2013). A guide to the project management body of
knowledge (5th ed.). Newtown Square, PA: Project Management Institute.
• Taylor, H. (2014). Cost of constructing a home. National Association of Home Builders.
Retrieved from http://www.nahb.org/generic.aspx. (Accessed on 12th June, 2020)