0% found this document useful (0 votes)
72 views3 pages

Project Document Flow Sequence For Primary Substation: SL.N o Description Prerequisite Condition For Submission

The document outlines the project document flow sequence for a primary substation. It lists 27 drawings and documents required for the project along with prerequisites for submission. It also provides documentation requirements such as title blocks, revision numbering, and requirements for submitting revised documents. A checklist is included that must be submitted with each design document selecting the appropriate status for items like previously commented drawings, comment resolution sheets, and prerequisite document approvals.

Uploaded by

Kumar Nagarajan
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
Download as docx, pdf, or txt
0% found this document useful (0 votes)
72 views3 pages

Project Document Flow Sequence For Primary Substation: SL.N o Description Prerequisite Condition For Submission

The document outlines the project document flow sequence for a primary substation. It lists 27 drawings and documents required for the project along with prerequisites for submission. It also provides documentation requirements such as title blocks, revision numbering, and requirements for submitting revised documents. A checklist is included that must be submitted with each design document selecting the appropriate status for items like previously commented drawings, comment resolution sheets, and prerequisite document approvals.

Uploaded by

Kumar Nagarajan
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1/ 3

Project document flow sequence for Primary Substation

A. List of drawings and documents:

Sl.N Description Prerequisite condition for submission


o
1 Key SLD Not linked with any documents. However to
be updated with final CT/VT details and as
per selected manufacturer’s SLD.
2 33kV SLD Not linked with any documents. However to
be updated with final CT/VT details and as
per selected manufacturer’s SLD.
3 11kV SLD Not linked with any documents. However to
be updated with final CT/VT details and as
per selected manufacturer’s SLD.
4 LVAC SLD Approval of 11 and 19
5 110V DC SLD Approval of 11,12 & vendor’s charger sizing
and battery sizing calculation
6 33kV CT/VT sizing calculation Approval of 2, Approval of 33kV Relay list by
MZEC protection department
7 11kV CT/VT sizing calculation Approval of 3, Approval of 11kV Relay list by
MZEC protection department
8 Earthing calculation Not linked with any documents.
9 Lightning protection calculation Not linked with any documents.
10 Lighting calculation Not linked with any documents.
11 Cable sizing calculation (HV/MV, LVAC & Approval of 19
DC)
12 DC load sizing calculation Not linked with any documents.
13 Protection and Block logic diagram- 33kV Approval of 6, 2
14 Protection and Block logic diagram- 11kV Approval of 7, 3
15 Equipment Layout As per GA of all vendor drawings
16 Cable trench layout Approval of 15
17 Earthing layout Approval of 8
18 Lighting and small power layouts Approval of 10
19 Load list Not linked with any documents. (only for
information as an attachment to LVAC SLD)
20 Cable Schedule Approval of 16, 11 (For information only)
21 SLDs for LDBs, PDBs and ACDB and Approval of 10 is required for LDBs and PDBs
Emergency DB
22 33kV Switchgear – vendor drawings Approval of 2, 6, 13, 29
23 33kV CRP- vendor drawings Approval of 2, 6, 13, 28, 29
24 11kV Switchgear – vendor drawings Approval of 3, 7, 14, 28, 29
25 110V DC System-vendor drawings Approval of 12 & 5
26 LVAC vendor drawings Approval of 4
27 LDB, ACDB, DC LDB and PDB vendor Approval of 21
drawings
28 Relay list Approval of 2,3
29 SCADA I/O list Not linked with any documents.
B. Documentation requirement:

1. Approved title block for the project shall be provided in all the sheets.
2. Revision number shall start from O and continue as A, B, C and so on.
3. Any revised documents shall be submitted with comments resolution sheet which shall
have stamp of both contractor & consultant and the revised portion shall be clouded with
the current revision.
4. The clear and legible scanned copy of previous commented drawings/document shall be
submitted as hard copy or CD while/before submitting the revised drawings/ document.
5. All documents shall have attestation by the consultant in each sheet.
6. When asked, proof of internal checks (self / discipline / QA) shall be produced by the
consultant.
7. Documents shall be prepared / reviewed by competent person ,with adequate design
experience, approved by MZEC for the specific project. The approved person shall be
available for discussion at MZEC office on short notice, if required.
8. Large number of correction marks will result in black points and hence documents shall be
submitted after thorough internal review.
9. The drawing/document number shall be as per the format below.
a. Tender no/Substation name in 3 to 4 letters/E/1XXX.
10. The responsibility for providing the documents complying all the MZEC policies and
practices, general engineering practices , safety features etc is solely with the contractor &
any delay due to repeated reviews shall be attributable to contractor.
11. The submission of any document shall fulfill the prerequisite condition as given in the table
shown above and other points as discussed above.
12. Duly approved deviation list for any deviation from tender specification must be attached
with first submission of drawings , if applicable.
13. With each submission the contractor shall attach a check list as follows.

Note: The serial number does not indicate the sequence of flow. The documents/ drawings which
are not linked with any other document/drawings can be submitted all in one go at the starting of
the project.

C. Checklist:

The below check list shall be submitted by selecting the appropriate status mentioned under
‘Remarks’ while submission of all design related drawings/document.

Sl. No Item Remarks


1 Copy of previous commented drawing. Attached / Not attached/ Not
applicable ( Rev O )
2 Copy of previously replied Comments Resolution Attached / Not attached/ Not
Sheet (CRS) applicable
3 Relevant supporting documents required to be Attached / Not attached/ Not
referred during the review. ( List of supporting applicable
documents)
a.
b.
4 Documents/ Drawings required to be approved/ Approved / reviewed/ Review
reviewed before submission of this document pending
5 Comment resolution sheet duly replied and attested Attached / Not attached/ Not
by contractor / consultant. applicable ( Rev 0)

You might also like