Industrial Training Diary
Weekly Activity Log
Name of Trainee : GAN MING KHAI
Name of Company :
Day of the
Date Projects / Activities
Week
Monday 14/02/11 1) First day, I follow Mr.Lau(site supervisor) to
construction site after that he ask me familiar the site first
which is at Kim kee Lot 13453. After that Mr. lau told
me the site lot number, therefore, I just know that every
construction site have own Lot number.
2) After me look around the site, and familiar with the site,
Mr. Lau teach and explain the procedure and the method
for setting out the site before excavation. Thus, I know
that the setting out the position of foundation must be
without any mistake before excavation.
3) The method that use to setting out the position of
foundation and for excavation that I learned from Mr.
Lau is using the black oil and square shape of wood with
dimension (make by wood) , it is the conventional
method that cant get from the book that study at college.
4) I aslo help Mr. Lao pat the wood on the ground to tag the
location that will be excavate.
5) Besides that, I also assist Mr. Lau to measure, checking
and confirm the location of setting out whether is similar
with the construction drawing or not.
6) Before I back home, Mr Lau brings me to view other site
and checking the work progress.
Tuesday 15/02/11 1) About 8.15am me and Mr.Lau reach construction site.
When we reach there, the worker during pump out the
water in the pit that for the footing before cast in the
ready mixed concrete. There totally got 60 pits that is
part of the site. They pump out the water inside the pit by
using a type of machinery.
2) After that, Mr.Lau ask me to do measurement for
indentify the quantity of concrete that have to use and
order from the supplier.
3) When the Mr.Lau order the ready mixed concrete, he
explain to me for the order rule in the market. Order the
ready mix concrete must with the range of 0.5m3. eg:
2.5m3, 3.5m3 and 4m3.
4) Because the ordered ready mixed concrete cant be
prefect utilize and will involve wastage, therefore must
do some calculation to control the concrete , it is to know
the ordered concrete whether is enough or not. If there is
not enough, thus must do calculation by using drawing to
find out the additional ready mix concrete to be order.
For example, today Mr.Lau order the ready mix concrete
of 30m3, but in the end there is not enough for the few
left pit, therefore Mr.Lau teach me to calculate/control
the needed concrete by calculation. It is to calculate the
concrete for the pit which is haven cast in the concrete
and just order the quantity of concrete for which pit is
havent cast in. In the end I found that this method can
save the material cost and the budget of company.
Because when order more, the left`s ready mixed
concrete will become wastage.
5) When the ordered ready mix concrete come, it hoist by
the mobil crane (30tone) to the location for which pit
have be cast in the concrete to form the footing.
Wednesday 16/02/11 1) At the morning, Mr.Lau ask me go to site and arrange the
mobil crane for unloading the 280 pallet of common
brick from lorry to second floor of housing. 1 pallet have
around 525 pieces of brick.
2) At there, I see the worker lay the wire mesh in every
fourth brick, it is same with the building construction
book our study at college.
3) After that. Mr.Lau sent me to count the BRC and check
there is correct with the order quantity or not.
4) At there, me also learn how to insert and locate the water
tank correct with safety. It must put below the wood
which have short spacing, because short spacing cab
receive the more load.
Thursday 17/02/11 1) In morning 8.00am, I follow my supervisor(Mr.Lau) go
to site to checking the work progress and to arrange all
the material for the worker to make sure the work is
progress smooth.
2) After that, me and Mr.Lau go to other site to confirm and
recheck the position of the pad which is setting out at last
few day. The position to be check because have to make
sure the position proper correct before excavation.
3) Mr.Lau give me a drawing which is ground floor plan
and require me to checked the position of the setting out
for excavation. After I check the position, I told Mr.Lau
that is all correct, but there is 1 position is incorrect after
Mr.Lau found out, he explain to me for the reason.
4) After going the bakri site, Mr Tiok( K&L construction
company director). He bring me and Mr. Lau go to
another site which is Bakri, Muar. At there me see the
worker lay the brick and construct roof structure. At
there, I learn that before lay the dpc, must lay a layer of a
kind of black oil to enhance the performance of prevent
moisture.
5) After going the bakri sitem Mr. Tiok bring me and
Mr.Lau go meeting with client, which is the client have a
piece of land and have to construct housing.
6) After meeting, we have lunch with all NSC. Include bar
NSC , concrete NSC and electricity NSC.
7) After lunch, Mr.Lau bring me to other site which is
tangkak and ask me to count the cement whether the
quantity is match with the quantity ordered when the NS
deliver the material on site.
8) At the last, me assist Mr.Lau to pad the centre of pit for
the worker can view the position and easy to insert the
bakau pile in right position into ground. During pad the
centrel of pit, I learn the method of get the centre of pit.
Beside that, I also learn how to see the construction
drawing on site.
1) Mr.Lau ask me go to site at Jalan Junid , Cempeka to see
the worker cast in the ready mixed concrete into the
formwork which is for the roof beam and column.
2) The ready mixed concrete is hoist by the mobile crane
direct from the lorry to the form work.
Friday 18/02/11
3) After that, Mr.Lau requires me to fetch a worker to
another site to cutting down the coconut tree. At there I
learn how the tree can be cut down with safety.
4) Because today work is regarding the mobile crane, so I
understand the cost of rent the mobile crane.
1) 8.00am me go to site which is at Kanpung Kerantan to
turn around and look at worker cast in the concrete into
formwork for construct the bridge of housing.
2) Before the lorry deliver the concrete on site, I use the
time of waiting to assist the worker dismantle the
formwork of housing bridge which is cast in the concrete
last few day ago.
3) At there me learned how to dismantle the formwork . the
Saturday 19/02/11
first step of dismantle the formwork is to remove all the
stuck , then only can remove formwork at the site and
bottom.
4) When the ready mixed concrete lorry is reach, must
require the driver to carry out the slump test on site,
because it is importance to observe the quality of the
concrete and to ensure the quality of the concrete is reach
the requirement.
Endorsement by the Industrial Training Supervisor:
The above is a true record of activities taken by the trainee in the captioned week.
Signature of Supervisor:
Name of Supervisor: Date: