Primary Metering Design
Primary Metering Design
1.0 INDEX
1.0 INDEX
2.0 PURPOSE
3.0 TYPE OF ELECTRICAL SERVICE
4.0 REQUIRED METER EQUIPMENT APPROVALS
5.0 ELECTRIC METER LOCATIONS
6.0 UNDERGROUND TERMINATIONS
7.0 PRIMARY METERING OF OVERHEAD CUSTOMERS
8.0 REFERENCES
9.0 CONSTRUCTION DRAWINGS
2.0 PURPOSE
This standard provides information on the construction of metering for customers who
receive primary voltages ( 2.4kV to 24.9kV ).
Electric service to primary metered customers will be 60 hertz alternating current. The
customer shall consult SPPC prior to the purchase of equipment and the installation of wiring. The
type and voltage of service that will be supplied depends upon the load, the applicable rate schedule
and the type of electric service available in the local area.
All metering enclosures shall meet the latest Electric Utility Service Equipment
Requirements Committee (EUSERC) Specifications, as adopted by SPPC.
5.1 In order that the most satisfactory meter location may be determined and that adequate
space will be provided, SPPC must be consulted in the preliminary planning stage.
Installation of additional facilities or future relocations at the customer's expense may
be prevented by early consultation with SPPC.
5.2 Meters and metering equipment may be located in a meter room that is provided by
the customer. Meter rooms must be illuminated and must be provided with a doorway
ELECTRIC VOLUME 17
6.1 For each primary metering installation two sets of drawings must be submitted to
SPPC, Electric Metering Department, P.O. Box 10100 ( R90EM ), Reno, NV
89520. These drawings must detail the interface between SPPC and the customer. The
lead time to obtain the necessary hardware has been up to 12-14 weeks; therefore the
drawings should be submitted in advance of construction by 14 weeks minimum.
This will assure that the proper metering equipment is available upon construction.
6.3 Wireways in the high voltage switchboard service termination space designed for
terminating the utility service shall be clearly identified for such use. Utility terminations are
dead front universial bushing wells, and no live front bolted terminations will be accepted.
Service termination shall be made in the service termination enclosure or in a specially
designated space of the meter panel which has a separate removable andsealable access
plate.
The layout or design of the service termination enclosure, which requires bending the
utility service conductors, should provide space to permit a minimum cable bending
radius equal to 10-12 times the overall outside diameter of the cable. The following
table is a list of conductors found in SPPC distribution system and their associated minimum
bending radius:
Nominal System
Conductor Size Minimum Bending Radius
Voltage
15kV #1/0 12"
25kV #1/0 14"
25kV 1000 28"
ELECTRIC VOLUME 17
6.5 The service termination enclosure, socket enclosure, and test by-pass block section
shall be sealable and isolated or have barriers provided from other integral enclosure
sections which are accessible to the customer in order to effectively prevent the
attachment of unauthorized connections to unmetered conductors or terminals.
6.6 The manufacturer's rating label, or other markings used in lieu of a label, shall
show among other things: A) Whether the socket and socket enclosure is
designed for overhead service entry, underground service entry, or both;
B) That the terminating lugs are designed for both aluminum and copper conductors;
and C) The wire size range of the termination lugs.
SPPC will place pole top metering one pole from the point of interface with the customer's
lines. That is, SPPC will own and operate the lines including the metering equipment
to the customers pole. The customer will provide a means of disconnecting his facilities from
SPPC's. Each installation will require coordination with SPPC Metering Operations and
Customer Service Engineering to assure each customer is provided safe and economically
engineered service.
For each primary metering installation, two sets of drawings must be submitted to
SPPC: Electric Metering Department, P.O. Box 10100 ( R90EM ), Reno, NV 89520.
These drawings must detail the interface between SPPC and the Customer. The lead
time to obtain the necessary hardware has been up to 8-10 weeks; therefore, the drawings
should be submitted in advance of construction by 10 weeks minimum. This will assure
that the proper metering equipment is available upon construction.
8.0 REFERENCES
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17
ELECTRIC VOLUME 17