An Introduction To Survey Methods and Techniques R1
An Introduction To Survey Methods and Techniques R1
and Techniques
P: (877) 322-5800
info@cedengineering.com
An Introduction to
Survey Methods
and Techniques
1. GENERAL
2. TOTAL STATIONS
3. REAL TIME KINEMATIC (RTK) GPS
4. TERRESTRIAL LIDAR (LASER) SCANNING
5. TOPOGRAPHIC DATA COLLECTION PROCEDURES
6. AUTOMATED FIELD DATA COLLECTION
7. METHODS OF DELINEATING AND DENSIFYING TOPOGRAPHIC FEATURES
(This publication is adapted from the Unified Facilities Criteria of the United States government which are
in the public domain, have been authorized for unlimited distribution, and are not copyrighted.)
1.1 TRANSIT-TAPE (CHAIN). Transit tape topographic surveys can be used to locate
points from which a map may be drawn. The method generally requires that all observed
data be recorded in a field book and the map plotted in the office. Angles from a known
station are measured from another known station or azimuth mark to the point to be
located and the distance taped (or chained) from the instrument to the point. Transit-tape
surveys typically set a baseline along which cross-section hubs were occupied and
topographic features were shot in on each cross-section. The elevation of an offset point
on a section is determined by vertical angle observations from the transit. The slope or
horizontal distance to the offset point is obtained by chaining. The accuracy may be
slightly better than the plane table-alidade method or very high (0.1 ft or less), depending
upon the equipment combinations used. Transits are still used by some surveying and
engineering firms, although on a declining basis if electronic total station equipment is
available. Transit-tape surveys can be used for small jobs, such as staking out
recreational fields, simple residential lot (mortgage) surveys, and aligning and setting
grade for small construction projects. Assuming the project is small and an experienced
operator is available, this type of survey method can be effective if no alternative
positioning method is available. Detailed procedures for performing and recording transit
tape topographic surveys can be found in most of the survey texts.
1.2 CHAINING. 100, 200, 300, or 500-foot steel tapes are used for manual distance
measurement methods. Woven, cloth, and other types of tapes may also be used for
Figure 2-5
Plane (no pun intended) table and alidade--Wild T-2 theodolite at right
(USC&GS, ca 1960s)
1.5 PLANE TABLE SURVEYING. The plane table and alidade were once the most
common tools used to produce detailed site plan maps in the field. The Egyptians are
said to have been the first to use a plane table to make large-scale accurate survey maps
to represent natural features and man-made structures. Plane table mapping is rarely
done today--plane table surveying has, for most purposes, been replaced by aerial
photogrammetry and total stations, but the final map is still similar. Plane table surveys
were performed well into the 1980s, and perhaps into the 1990s. A plane table survey
Figure 2-6
Leica TCR 705 Reflectorless Total Station
Types of measurements:
Slope distance
Horizontal angle
Vertical angle
Figure 2-7
RTK base station and radio link transmitter--and rover with backpack
5.1 ESTABLISH PRIMARY HORIZONTAL and vertical control for radial survey. This
includes bringing control into the site and establishing setup points for the radial survey.
Primary control is usually brought into the site from established NSRS
monuments/benchmarks using static or kinematic GPS survey methods and/or
differential leveling. Supplemental traverses between radial setup points can be
conducted with a total station as the radial survey is being performed. A RTK system may
require only one setup base; however, supplemental checkpoints may be required for site
calibration. Elevations are established for the radial traverse points and/or RTK calibration
points using conventional leveling techniques. Total station trigonometric elevations or
RTK elevations may be used if vertical accuracy is not critical--i.e., ± 0.1 ft.
5.2 PERFORM RADIAL SURVEYS to obtain information for mapping. Set the total station
or RTK base over control points established as described above. Measure and record the
distance from the control point up to the electronic center of the instrument (HI), as well
as the height of the prism or RTK antenna on the prism pole (HR). To prevent significant
errors in the elevations, the surveyor must report and record any change in the height of
the prism pole. For accuracy, use a suitable prism and target that matches optical and
electrical offsets of the total station. Use of fixed-height (e.g., 2-meter) prism poles is
recommended for total station or RTK observations, where practical.
5.5 OBTAIN POINTS IN SEQUENCE. The translation of field data to a CADD program
will connect points that have codes associated with linear features (such as the edge of
road) if the points are obtained in sequence. For example, the surveyor should define an
edge of a road by giving shots at intervals on one setup. Another point code, such as
natural ground, will break the sequence and will stop formation of a line on the subsequent
CADD file. The surveyor should then obtain the opposite road edge. Data collector
software with "field-finish" capabilities will facilitate coding of continuous features.
5.6.1 MOST CREWS WILL MAKE and record 250 to over 1,000 measurements per day,
depending on the shot point detail required. This includes any notes that must be put into
5.6.2 A ONE OR TWO-PERSON survey crew is most efficient when the spacing of the
measurements is less than 50 feet. When working within this distance, the average rod
person can acquire the next target during the time it takes the instrument operator to
complete the measurement and input the codes to the data collector. The instrument
operator usually spends about 20 seconds sighting a target and recording a measurement
and another 5-10 seconds coding the measurement. The same time sequences are
applicable for a one-man topographic survey using a robotic total station or RTK.
5.6.3 WHEN THE GENERAL SPACING of the measurements exceeds 50 feet, having a
second rod person may increase productivity. A second rod person allows the crew to
have a target available for measurement when the instrument operator is ready to start
another measurement coding sequence. Once the measurement is completed, the rod
person can move to the next shot, and the instrument operator can code the
measurement while the rod people are moving. If the distance of that move is 50 feet or
greater, the instrument will be idle if you have only one rod person.
6.1 FIELD SURVEY BOOKS. Even with fully automated data collection, field survey
books are not obsolete. They must be used as a legal record of the survey, even though
most of the observational data is referenced in a data file. Field books are used to certify
work performed on a project (personnel, date, time, etc.). They are also necessary to
record detailed sketches of facilities, utilities, or other features that cannot be easily
developed (or sketched) in a data collector. When legal boundary surveys are performed
that involve ties to corners, it is recommended that supplemental observations and notes
be maintained in the field book, even though a data collector is used to record the
observations.
6.3 FEATURE CODING AND ATTRIBUTING. Data collectors are designed to encode
observed topographic features with a systematic identification. Similar features will have
the same descriptor code--e.g., "BS" for "backsight" and "EP" for "edge of pavement."
Features that are recorded in the data collector can have additional attributes added.
Attributes might include details about the feature being located (e.g., the number of lamps
and height of a light pole).
6.4 FIELD GRAPHIC AND SYMBOLOGY DISPLAYS. Many field data collectors have
symbology libraries which can be assigned to standard features, e.g., manholes, culverts,
curb lines, etc. Plotted display of collected points with symbology can be viewed on the
data collector display screen, or transferred to a portable laptop screen that has a larger
viewing area. This allows for a visual view in the field of observed data in order to check
for errors and omissions before departing the job site. This capability is, in effect, a
modern day form of a plane table.
7.1 CROSS-SECTION SURVEY METHODS. Most site plan topographic surveys are
performed relative to project baselines. This is often called the “right-angle offset
technique”. A baseline is established along a planned or existing project axis (e.g., road
centerline) using standard traverse control survey methods, as shown in Figure 2-9.
Intermediate points are set and marked at regular intervals along the baseline (at 50-ft or
100-ft stations with intermediate stations added at critical points). The intermediate points
are marked with 2x2 inch wooden hubs, PK nails, or temporary pins with flagging. Station
hubs are occupied with a transit or total station and cross-sections are taken normal to
the baseline alignment. Points along the cross-section offsets are shot for feature and/or
elevation. Offset alignment is done either visually, with a right-angle glass, or transit,
depending on the accuracy required. Distances along offsets are measured by chaining,
stadia, or EDM (i.e., total station). Detailed notes and sketches of ground shots and
planimetric features are recorded in a standard field book, electronic data collector, or
both. Notekeeping formats will vary with the type of project and data being collected.
General industry standard notekeeping formats should be used. Examples of selected
topographic baseline notes are shown in Figures 2-10 and 2-11.
A grid pattern of cross-sections is also used for topographic survey of large areas, such
as wetlands, orchards, swamps, etc. This is also illustrated in Figure 2-9 above where the
cross-sections southeast of the PT extend a considerable distance from the baseline. In
general, the maximum distance to extend the baseline is a function of the feature
accuracy requirements and the precision of the survey instrument. For total stations,
ground shots on a prism rod out to 1,000 ft and greater are usually acceptable. Transit
stadia distances should not extend out beyond 500 ft. If coverage beyond 1,000 ft is
needed, then additional baselines need to be run through the area and intermediate
cross-sections should be connected between these baselines. (In current practice, this is
Figure 2-10
Sketch of profile line and cross-section
7.2 RADIAL SURVEY METHODS. (Figure 2-12). Plane tables were especially suited to
radial survey methods; thus, most surveys using total stations or RTK now utilize this
technique. Radial observation are made with the instrument (total station or RTK base
station) set up over a single point that has full project area visibility (or in the case of RTK,
can encompass radio or cell phone ranges well beyond visible limitations with a total
station). Thus, topographic features, baseline stakeout, and elevations be surveyed
without having to occupy separate stations along a fixed baseline. COGO packages will
automatically compute radial distances and azimuths to linear or curved baseline stations,
and visually guide the stakeout process. RTK surveys methods are a unique form of radial
survey methods—RTK controller COGO packages are used to reduce GPS observations
Figure 2-12
Topographic detail densification using radial survey methods--instrument set at point
“MON A” and radial shot points (planimetric features or elevations) are observed
7.3 PLANIMETRIC FEATURES. Planimetric features are tied in using either cross-
section or radial survey methods. The amount of detail required on a feature depends on
Checking: Check data points by various means including reviewing the resultant DTM,
reviewing breaklines in profile, and locating some data points from more than one setup.
Products: The surveys branch is responsible for developing and delivering final, checked
engineering survey products, including DTMs, to the survey requestors. Products can be
tailored to the needs of the requestor whenever feasible, but normally should be kept in
digital form and include the following items:
Converted and adjusted existing record alignments, as requested. (CAiCE project
subdirectory)
Surveyed digital alignments of existing roadways and similar facilities. (CAiCE
project subdirectory)
CAiCE DTM surface files. (CAiCE project subdirectory)
2-D CADD MicroStation design files, .dgn format.
Hard copy topographic map with border, title block, labeled contours, and
planimetry.
File of all surveyed points with coordinates and descriptions. (CTMED, .rpt, format)
7.8 UTILITY SURVEY DETAIL METHODS. It is important to locate all significant utility
facilities. Utilities are surveyed using either total station or RTK techniques. The
CALTRANS Surveys Manual recommends that accuracy specifications for utilities that
are data points located on paved surfaces or any engineering works should be located
within ±10 mm horizontally and ±7 mm vertically. Data points on original ground should
be located within ±30 mm horizontally and vertically. The following are lists of facilities
and critical points to be located for various utilities--as recommended in the CALTRANS
Surveys Manual.
Underground Lines
Cables/lines (denote direct burial or conduit, if known), etc.
Manholes, pull boxes, and transformer pads
Crossing at centerline or right of way lines
For lines parallel to right of way – location ties as necessary to show relationship
to the right of way lines
Railroads
Profile and location 60 m each side of the proposed roadway right of way lines
Method: Total station radial survey, GPS fast-static, kinematic, or RTK. Accuracy
Standard: Data points located on paved surfaces or engineering works should be located
within ±10 mm horizontally and ±7 mm vertically. Data points on original grounds should
be located within ±30 mm horizontally and vertically. Review field survey package for
possible higher required accuracy.
Checking: Check data points by various means including, reviewing the resultant DTM,
reviewing breaklines in profile, and locating some data points from more the one setup.
Products:
3-D digital graphic file of mapped area
Hard copy topographic map with border, title block, and planimetry (contours and
elevations only if specifically requested)
File of all surveyed points with coordinates and descriptions
Accuracy Standard: Data points located on paved surfaces or any engineering works
should be located within ±10 mm horizontally and ±7 mm vertically. Data points on original
ground should be located within ±30 mm horizontally and vertically.
Products:
File of all surveyed points with coordinates and descriptions
Sketch or map showing locations of data points
Accuracy Standard: Data points located on paved surfaces or any engineering works
should be located within ±10 mm horizontally and ±7 mm vertically. Data points on original
ground should be located within ±30 mm horizontally and vertically.
Products:
File of all surveyed points with coordinates and descriptions
Sketch or map showing vertical clearances