Parallel Testing and Implementing New QC Material
Parallel Testing and Implementing New QC Material
QUALITY CONTROL
SYSTEM
Parallel Testing and Implementing a New Lot
of QC Materials
Templates: SLT_413, SLT_417 SLT_400
Ver.010817
2
Step-1
Run New Set of
Controls x 10
(as unknowns)
For cross-over between
two different lots of
control materials, lab may
calculate the mean for
the new material from the
first 10 measurements,
and use the CV from the
previous lot of QC
material to calculate the
SD, then used to
calculate QC limits.
Step 2.
Use SLT 413 Templates to Analyze Data (Level-1 QC Shown)
Step 2. (cont.)
Use SLT 413 Templates to Analyze Data (Level-3 QC Shown)
7
Step 3.
Compare
Preliminary Lab
Values vs. Insert ..
Mean & Range are
used on the
SLT_413 Form
Means from parallel
study should fall within
the manufacturer’s
stated range.
Step 3. (cont.)
Convert Insert
stated 3SD limits
to 2SD limits
SLT_105 and SLT_400
Daily QC Assessment
Template setup requires
user input of 2SD limits
for each analyte. SLT_414.5 Use when SD is not given
The lab will use the calculated mean, along with the peer CV to
calculate it’s interim QC limits for the new QC materials.
We note that the peer Level-1 E2 value more closely matches the
E2 value from the lab study (50.8). The most current peer reports
contain the more reliable comparative values.
10
Optionally, Lab
Previous Lot
SD’s or CV’s are
used with the
new QC means
QC Limits are
best determined
by cumulative
statistics from 3-6
months testing.
SLT_417 Used Here - Lab Mean & Peer CV
11
Verified QC
Limits are
set into
Analyzer &
LIS QC
programs.