Model Review Objectives
Model Review Objectives
For sure 30%,60% and 90% 3D modeling review are important, but I guess we shouldn't consider them
as P&ID review stage, in 3D model review we can change equipment location orientation by rotating,
structure , ladders, and piping, which are not related to P&ID review ,
Objectives of 30% model review
The 30% 3D model review is performed to serve the following objectives:
To fix the equipment location considering the available information.
To identify primary operational/assessable/maintenance points or platforms.
To identify improvements considering the safety and operation aspects.
To release foundation loads for structural design.
To finalize the equipment nozzle orientation and send the information to the vendor.
To finalize the main underground isometrics for fabrication.
60% Model Review:
To check if the design is at par with the safety philosophies and requirements.
To determine the location of secondary fire/safety equipment
To find out if the main equipment locations are in order and updated.
To review the location of minor equipment.
To review the secondary operability/accessibility/maintainability as required.
To review and release buried isometric for IFC.
To release the updated nozzle orientation information to the vendor.