Module 10
Module 10
Chapter 10
EARTHWORKS
One important aspect of roadway design is determining the amount of earthwork necessary on a
project. The manual method for determining earth excavation and embankment amounts involves
three steps: cross sections of the proposed highway are placed on the original ground cross sections,
the areas in cut and the areas in fill are calculated, and the volumes between the sections are
computed.
𝑳
𝑽𝒑 = 𝟔 (𝑨𝟏 + 𝟒𝑨𝒎 + 𝑨𝟐 )
𝑨𝟏 +𝑨𝟐
𝑽𝑬 = ( 𝟐
)𝑳
• PRISMOIDAL CORRECTION, 𝑉𝑐
- To be subtracted algebraically from the volume by the end area method
𝑳
𝑽𝒄 = 𝟏𝟐 (𝒃𝟏 − 𝒃𝟐 )(𝒉𝟏 − 𝒉𝟐 )
𝑽𝒑 = 𝑽𝑬 − 𝑽𝒄
1
Example Problem 1:
Given is the cross-section notes of an earthwork between Station 10+000 and 10+200. Assume both stations to
have the same side slope and width of the same base.
Compute the ff:
a) Side slope of both sections
b) Value of x at Sta. 10+200 if it has a cross sectional area of 14.64 sq.m.
c) Volume of earthwork between Sta. 10+000 and Sta. 10+200 using end area method with prismoidal
correction
Solution:
c) Volume of earthwork between Sta. 10+000 and Sta. 10+200 using end area method with
prismoidal correction
(𝐴𝑆𝑡𝑎.10+000 +𝐴𝑆𝑡𝑎.10+200 )𝐿
𝑉𝐸 = 2
𝐴𝑆𝑡𝑎.10+000 = 𝐴1 + 𝐴2 + 𝐴3 + 𝐴4
1
𝐴𝑆𝑡𝑎.10+000 = 2 [(3)(2.3) + (1.5)(6.45) + (1.5)(4.5) + (3)(1)]
𝐴𝑆𝑡𝑎.10+000 = 13.163 𝑚2
(13.163+14.64)200
𝑉𝐸 = 2
= 2780.3 𝑚3
𝐿
𝑉𝑐 = 12 (𝑏1 − 𝑏2 )(ℎ1 − ℎ2 )
𝑏1 = 6.45 + 4.5 = 10.95
𝑏2 = 6 + 6.9 = 12.9
ℎ1 = 1.5 𝑚
ℎ2 = 1.2 𝑚
200
𝑉𝑐 = 12
(10.95 − 12.9)(1.5 − 1.2)
3
𝑉𝑐 = −9.75 𝑚
𝑉𝑝 = 𝑉𝐸 − 𝑉𝑐
𝑉𝑝 = 2780.3 − (−9.75)
𝑽𝒑 = 𝟐𝟕𝟗𝟎. 𝟎𝟓 𝒎𝟑 answer
2
Example Problem 2:
The center height of the road at Sta. 7+110 is 2.00m fill while at Sta. 7+160 is 1.20m cut. From Sta. 7+110 to the
other station makes a uniform slope of 4.8%.
Solution:
3
Example Problem 3:
In determining the position of the balance line in the profile diagram, a horizontal grade line is drawn such that
the length of the cut is 850m and that of fill is 1200m. The profile area between the ground line and the grade line
in the cut is 7800 sq.m. while that of fill is 8500 sq.m. if the road bed is 10.00m wide for cut and 8.00m wide for fill
and if the side slope for cut is 1.5:1 while that for fill is 2:1. Assume a level section with an average value of cut
and fill for each stretch.
Solution:
4
Example Problem 4:
The following data are results of the earthwork computations of areas, free haul distance and limits of economical
haul by analytical solution instead of graphical solution (mass diagram). The cross sectional area at station 1+460 is
40 sq.m. In fill and at station 2+060, the cross sectional area is 60 sq.m. In cut. The balancing point is at station
1+760 where area is equal to zero. Assume the ground surface to be sloping upward uniformly from sta. 1+460 to
1+760 and then with slightly steeper slope to 2+060. Assume free haul ditance = 50 m. And limit of economical haul
= 450 m.
Solution:
𝐴1 = 40.452 𝑚2
𝐴2 = 4.494 𝑚2
40.452+4.494
𝑉𝑜 = ( 2
) (179.79)
5
40 𝐴3 4𝐴
300
= 247.74 = 27.53
𝐴3 = 33.032 𝑚2
𝐴4 = 3.671 𝑚2
33.032+3.671
𝑉𝑜 = ( ) (220.21)
2