3 - JSA Loading Off Loading
3 - JSA Loading Off Loading
Mobilization Of Route shall be decided & communicated to all drivers & operators.
Equipment &
Material Incompetent Injury / asset Gasco
driver/Operators Third Party Trained, Competent and Skilled Driver/operator.
Damage Tool Box Talk Shall be conducted.
2B 1A
JSA briefings & Hazards communication to personnel on job.
Vehicle / Equipment Injury / asset 2B PPL Speed limits shall be followed inside facility. 1A
Movement inside Route shall be defined & Communicated to operators/drivers.
Facility/Plant Damage
Driver to be conscious about Facility piping & structures.
Material shall not extend out of vehicle's body or tail board.
Ensure Reverse alarm installed on equipment and vehicles.
Banks man shall be available with heavy vehicles
Mobilization shall be done only in day time
Job Safety Analysis
Incompetent
operators/rigging 1B
crew
Gasco
asset damage, Proper compacted and leveled ground muse be choose for material off
Improper ground
3B loading/loading. 1B
condition equipment tilt over
Job Safety Analysis
Direct eye to eye contact between crane operator and signal man
Signal man wear reflecting vest
Signal error Personal Injury 2B 1B
Lifting shall be done only day time, for night activity special lighting and approval
from PPL is required
Job Safety Analysis