Assignment 2

This document outlines a group assignment for a project management course. It includes: 1) Two groups are assigned questions involving network diagrams, activity schedules, and float calculations for two sample projects. 2) The questions also require explaining the fundamental rules of network construction and short notes on critical path method (CPM) and program evaluation and review technique (PERT). 3) A third group is assigned questions involving determining the critical path, probability of completion, and sufficient time for high probability of completion using optimistic, most likely, and pessimistic time estimates for another sample project. 4) This last group is also asked to explain critical path method and PERT in detail with diagrams. The document

Uploaded by

Tejaswani R
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
Download as pdf or txt
0% found this document useful (0 votes)
25 views2 pages

Assignment 2

This document outlines a group assignment for a project management course. It includes: 1) Two groups are assigned questions involving network diagrams, activity schedules, and float calculations for two sample projects. 2) The questions also require explaining the fundamental rules of network construction and short notes on critical path method (CPM) and program evaluation and review technique (PERT). 3) A third group is assigned questions involving determining the critical path, probability of completion, and sufficient time for high probability of completion using optimistic, most likely, and pessimistic time estimates for another sample project. 4) This last group is also asked to explain critical path method and PERT in detail with diagrams. The document

Uploaded by

Tejaswani R
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 2

SETHU INSTITUTE OF TECHNOLOGY

An Autonomous Institution
Pulloor - 626 115, Kariapatti (TK), Virudhunagar District.

DEPARTMENT OF CIVIL ENGINEERING


19UME701-PROJECT MANAGEMENT &FINANCE
ASSIGNMENT II
(Group Assignment)

Date of Announcement:11/08/2023 Date of Submission :20/08/2023

GROUP QUESTIONS MARK


NO
1 a.The following table list the activities, duration and their sequence of operation. Draw 20
the network diagram for these activities and prepare a table showing their ES,EF,LS and
LF times and also find the TF, Independent float and Interfering float for each activity.
Determine the critical path and its duration.(Apply)
Activity 1-2 1-3 1-4 2-7 3-4 4-5 4-7 5-6 5-7 5-8 6-8 7-8
Duration
(days) 8 10 5 6 3 7 0 4 3 6 5 5

b. Explain the fundamental rules involved in the network construction?(Understand) 20


2 a.The following table list the activities, duration and their sequence of operation. Draw 20
the network diagram for these activities and prepare a table showing their ES,EF,LS and
LF times and also find the TF, Independent float and Interfering float for each activity.
Determine the critical path and its duration. (Apply)
Activity 1-2 1- 1- 2-5 3-6 3- 4-7 5-6 5-8 6-9 7-9 8-10 9-11 10-
3 4 7 11
Duration 8 9 8 4 6 7 5 4 8 4 6 6 9 7
(days)

b. Write short notes on CPM and PERT.(Understand) 20


3 a.The following table shows the activity relationship of a 8 event project and it is 20
optimistic, most likely and pessimistic time estimates. Determine i) Critical path and its
standard deviation
ii) Probability of completion of project in 41 days
iii) Time duration that will provide 95% probability of its completion in time.(Apply)
Time Estimate
Activity Optimistic Most likely Pessimistic
1-2 2 5 8
2-3 8 11 20
3-4 0 0 0
2-4 4 7 16
2-5 4 9 20
4-6 7 10 13
5-6 3 7 17
3-7 3 5 13
6-7 2 3 10
7-8 2 4 6
20
b. Explain in detail about critical path method with a neat sketch . (Understand)
4 G) The following table shows the activity relationship of a 8 event project and it is 20
optimistic, most likely and pessimistic time estimates. (Apply)
Determine i) Critical path and its standard deviation
ii) Probability of completion of project in 45 days
iii) Time duration that will provide 91% probability of its completion in time
Time Estimate

Activity Optimistic Most likely Pessimistic

A-B 4 6 10
B-C 10 14 22

C-D 3 5 7
B-D 0 0 0

B-E 5 10 21

D-F 8 10 14

E-F 4 8 18
C-G 4 6 14

F-G 3 4 11
G-H 4 6 8

20
b. Explain in detail about PERT relationship with a neat sketch.(Understand)

Rubrics

CONTENT MARKS
Content 20 Marks
Calculation 20 Marks
Presentation 05 Marks
Timely Submission 05 Marks
Total Marks 50 Marks

Prepared by Approved by
Dr.A.M.ArunMohan HOD/Civil