1. A project manager has received some help from the team, and she needs help from them again so that
she can create a detailed project budget. Which project management process group is she in?
A. Initiating
C. Planning
D. Executing
A. Executing
B. Planning
C. Closing
D. Initiating
A. Project budget
A. Company processes
B. Company culture
C. Historical WBSs
5. Your team is building a website to provide resources for families and childcare providers who want to
design their own homeschooling programs. The site will include many features. As each feature is
completed, the product owner reviews it and either accepts it or tells the team what needs to be fixed.
Upon acceptance, the feature is reviewed by QA and then added to the live build. Which life cycle or
A. Hybrid
B. Incremental
C. Iterative
D. Release-driven
6. The project sponsor has just signed the project charter. What is the next thing to do?
B. Validate scope
7. The high-level project schedule constraints have just been determined. What project management
A. Initiating
B. Planning
C. Executing
92
8. 'Ihe WBS and WBS dictionary have been completed, and the project team has begun working on
identifying risks. The sponsor contacts the project manager, requesting that the responsibility
assignment matrix be issued. The project has a budget of $100,000 and is taking place in three countries
using 14 human resources. There is little risk expected for the project, and the project manager has
managed many projects similar to this one. What is the next thing to do?
9. A project manager does not have much time to spend on planning before the mandatory start date
arrives. Re therefore wants to move through, planning as effectively as possible. What advice would
you offer?
A. Make sure you have a signed project charter and then start the WBS.
C. Document all the known risks before you document the high-level assumptions.
D. Finalize the quality management plan before you determine quality metrics.
A. Integration
B. Project selection
C. Initiating
D. Planning
1 1 . Why does the agile approach plan the work continuously throughout the project?
A. Agile methods break down the work into small chunks so the team can complete one iteration
at a time.
B. An agile product owner can't know what they really need until they see a prototype in action.
C. Agile teams are asked to prioritize tasks that delivervalue, rather than spending their time planning.
D. Agile projects are subject to uncertainty and high rates of change that make upfront
planning inefficient.·
12. A project manager gets a call from a team member notifying him that there is a variance between the
speed of a system on the project and the desired or planned speed. The project manager is surprised
because that performance measurement was not identified in planning. If the project manager then
evaluates whether the variance warrants a response, he is in which part of the project management
process?
A. Initiating
B. Executing
D. Closing
13. During a team meeting, a team member asks about the measurements that will be used on the project
to assess performance. The team member feels that some of the measures related to activities assigned
to him are not valid measurements. The project is most likely in what part of the project manage
ment process?
A. Closing
C. Executing
D. Initiating
93
© 2020 RMC Publications, Inc.'" • 952.846.4484 • info@rmcls.com • www.rmcls.com
Processes and Domains T H R E E
A. Iterative
B. Unique
C. Unnecessary
D. Standardized
15. What does a project manager need to do to deliver value in the context of the organization and its
business environment?
A. Understand the organizational and project governance and how they may impact the project.
B. Review the lessons learned from other projects and use them to generate organizational
process assets.
C. Use people and process skills along with understanding the organizational and
business environment.
D. Continuously monitor any changes to the external business environment, such as competitive
16. Which project management process group generally takes the most project time and resources?
A. Planning
B. Design
C. Integration
D. Executing
17. You are managing two projects and have been assigned to a third project that has just been approved.
You begin the new project, and are able to manage it well along with the others you are managing.
During initiating, you are focused on accomplishing a number of activities. Which of the following are
A. Both process groups and domains recommend the best practices that should be followed on
all projects.
B. Since the process groups lack a definitive framework, they allow for more flexibility in the
development approach.
C. Compared to the process groups, the tasks involved in the domains are more open to interpretation
D. The process groups and domains provide a different view of the project depending on the
19. The software development project has progressed according to plan. The team is very enthusiastic
about the product they have created. Now they are looking ahead to finding new projects to work on.
You caution them that the current project cannot be considered complete until after the closing
C. Documenting the degree to which each project phase was properly closed after its completion
94
20. What key point about the process groups and domains is important to know in studying for the exam?
A. Being able to correlate these two frameworks with each other will help you understand the
B. By combining these two perspectives, you can determine the best sequence in which the work
should be done.
C. Analyzing the project characteristics from the standpoint of each of these frameworks will help
D. Since these two frameworks should be used independently of each other, you need to be able to
2 1 . The first phase of your project has come to an end. What is the most important thing to ensure is done
A. Verify that the resources are available for the next phase.
C. Confirm that the phase has reached its objectives, and have its deliverables formally accepted.
D. Recommend corrective action to bring the project results in line with project expectations.
22. During which process group does the team measure and analyze the work being done on the project?
A. Initiating
B. Executing
D. Closing
23. Which of the following is the most appropriate thing to do in project closing?
24. Which process group focuses on completing the requirements of the project?
A. Initiating
B. Planning
C. Executing
D. Closing
25. All the following occur during the planning process group except:
B. Create WBS
C. Estimate Costs
D. Sequence Activities