Detecting and Solving The Coordination Curve Intersection Problem of
Detecting and Solving The Coordination Curve Intersection Problem of
a r t i c l e i n f o a b s t r a c t
Article history: This study presents a practical and effective method for inspecting and repairing curve intersection sit-
Received 9 February 2012 uations that occur in upstream and downstream coordinated overcurrent relay pairs in subtransmission
Received in revised form 4 August 2012 networks. This type of miscoordination can cause backup relays to trip before their paired primary when
Accepted 15 August 2012
faults occur, resulting in unexpected expansions of blackout areas. The proposed method is based on the
Available online 4 October 2012
IEEE and IEC standard characteristic curve equations of digital overcurrent relays and a customized curve
equation for electromechanical overcurrent relays. Consequently, the proposed method is applicable to
Keywords:
both digital and electromechanical relays. Two subtransmission network cases for the Taiwan Power
Characteristic curve
Overcurrent relay
Company were simulated to validate the proposed method.
Protection coordination © 2012 Elsevier B.V. All rights reserved.
Subtransmission system
0378-7796/$ – see front matter © 2012 Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.epsr.2012.08.009
20 Y. Lu, J.-L. Chung / Electric Power Systems Research 95 (2013) 19–27
Time Primary Relay intersection inspection method shown in Section 2 with the inter-
section elimination technique presented in Section 3 to identify and
eliminate coordination curve intersections. Finally, two cases are
simulated and discussed in Section 5, followed by the conclusion
in Section 6.
where MP , multiple of pickup current of primary DOCR; INP , pickup Mmin ≤ M ≤ Mmax (14)
current setting of primary DOCR; CTP , CT ratio of primary DOCR. where Mmin is the recommended lower limit of M and Mmax is
Substituting the multiples of pickup current of MB (=1.6), MP the recommended upper limit of M. The normal range recom-
obtained from (10), and the given time dial settings of TDB and mended by the standard BS 142 is 2–20 [14].
TDP into (11) yielded the difference of the relay operating times (4) Selectivity constraint
between the backup relay and the primary relay at the specified
fault current (ICK ) associated with MB = 1.6. Based on this operating TB ≥ TP + CTI (15)
time difference T, the curve intersection was identified. As shown
where TB is the operating time of the backup DOCR, TP is the
in Fig. 2, T < 0 indicates that an intersection situation has been
operating time of the primary DOCR, and CTI is the coordination
detected. Conversely, T > 0 means that no intersection exists, as
time interval specified between a primary DOCR and its backup
shown in Fig. 3.
DOCR, which is typically between 0.2 s and 0.5 s [17].
T = f (MB , TDB ) − f (MP , TDP ) (11)
The proposed intersection elimination technique is briefly
explained below.
Step 1: Locate the fixed point on the curve of the backup relay.
ΔT > 0
The close-in fault current (IF ) of the primary relay in a coordi-
nation pair with a curve intersection was computed and used as
the reference fault current to locate the fixed point on the origi-
Time in seconds
Start
Time in seconds
IF No
Fault current in amperes
Adjust the settings of backup
Fig. 4. An example to illustrate the intersection elimination technique.
relay with (16) and (19)
ICK(0) , ICK(1) , and ICK(2) all refer to MB = 1.6, their values were differ-
ent because of the varying pickup current settings (INB ) that were
applied to (9) to calculate these fault currents.
With the proposed approach, the original CTI and the operating
Δ T<0 time of the backup relay remained unchanged because the adjusted
Time in seconds
Δ T<0 curves of the backup relay all passed through the fixed point. In
Δ T>0 addition, none of the existing overcurrent relays had to be removed
or replaced with an advanced relay, nor was any modification to the
firmware of the relays necessary.
Fixed Point
5. Case simulation and discussion
TB TD B
CTI Two cases of subtransmission networks for the Taiwan Power
TDB1
TP Company were simulated to validate the proposed approach. The
TDB2
first case study was a multi-loop subtransmission system that had
TD P
six buses. The backup overcurrent relay involved in the intersection
ICK(0) I CK(1) I CK(2) IF was a digital relay. The second case study was a single-loop sub-
Fault current in amperes transmission network with seven buses. The backup overcurrent
relay that was adjusted for the intersection was an electrome-
Fig. 6. An example to illustrate the proposed approach. chanical relay. Simulations of protective coordination for both the
three-phase short-circuit and single-phase ground faults were con-
the curve intersection problem can be identified and immediately ducted in the two cases. However, because of limited space, the
resolved by a program implementing the proposed approach. Fur- protective coordination for the three-phase short-circuit fault is
thermore, no additional software tool for creating coordination shown in case study 1 and the protective coordination for the
curve diagrams is required in this approach. single-phase ground fault is shown in case study 2.
Fig. 6 shows an example demonstrating the process of the pro-
posed intersection inspection and elimination approach. In Fig. 6, 5.1. Case study 1
TDP and TDB represent the original coordination curves of the
primary and the backup relays, respectively. The operating time Fig. 7 shows the multi-loop subtransmission system that had
difference (T) of the relay pair derived from the fault current ICK(0) six buses, referred to in the simulation as BusA, BusB, BusC, BusD,
associated with MB = 1.6 was less than zero, indicating that the two BusE, and BusF. All of the buses had a voltage rank of 69 kV.
curves intersected. Therefore, the time dial setting of the backup The rated current was 1200 A and the CT ratio was 1200/5. The
relay required adjustment to resolve this intersection. Following source impedances of BusA were Z1 = 0.00260 + j0.03528 p.u. and
the first adjustment, the curve of the backup relay with the time Z0 = 0.14353 + j0.65428 p.u. Additional relevant data concerning the
dial setting of TDB1 was obtained. By computing the operating time DOCRs are shown in Fig. 7. The DOCRs used in the protective
difference between this curve and curve TDP using check current coordination included electromechanical phase inverse directional
ICK(1) , it was determined that the intersection still existed because overcurrent relays CR-8, electromechanical ground inverse direc-
T < 0. Therefore, the adjustment had to be continued. TDB2 was tional overcurrent relays CRP-8 [18], and digital overcurrent relays
the new curve of the backup relay acquired from the second adjust- SPAJ140C [14], all of which were manufactured by the ABB Com-
ment. The operating time difference between this curve and curve pany.
TDP with check current ICK(2) became greater than zero. Therefore, For the protective coordination for the three-phase short-circuit
the intersection was eliminated and the process stopped. Although fault, the intersections were found in two zones: BusB#610 →
930 930
1200/5 1200/5
G CR-8:5/2
CRP-8:1/2
CR-8:5/0.5
CRP-8:0.5/0.5 Bus E
Bus F
Fig. 7. Multi-loop subtransmission network with 6 buses in the Taiwan Power Company.
24 Y. Lu, J.-L. Chung / Electric Power Systems Research 95 (2013) 19–27
Fig. 8. Coordination curve diagram with the original relay settings. Fig. 9. Coordination curve diagram showing the adjustments of backup relay
B#610:67.
BusC#620 → BusD#630 and BusA#680 → BusF#620. However, Table 1 lists the data related to curve intersection detec-
because of their similarity, only the miscoordination of the tion and the relay setting adjustments on the coordination relay
BusB#610 → BusC#620 → BusD#630 section is discussed. A com- pair of backup relay B#610(67:SPAJ140C) and primary relay
mercial ASPEN OneLiner [19] was used to produce the coordination C#620(67:CR-8) for the proposed approach. The right-hand side of
curve diagrams for demonstration purposes. Table 1 shows information regarding curve intersection detection,
The isolation of the phase-to-phase or three-phase short-circuit and the left-hand side shows information on the setting adjust-
faults of the transmission lines was facilitated by phase overcur- ments of backup relay B#610:67. The settings of B#610:67 were
rent relays that provided faster tripping for the heavy short-circuit initially specified as a pickup current setting (INB ) of 5, a time dial
faults. Generally, because the three-phase short-circuit fault gener- setting (TDB ) of 0.18, and a derived multiple of pickup current (MB )
ates a maximum fault current, it should be considered when setting of 4.66. The computed operating time difference (T) between the
the protective relays for coordination. relay pair was −2.65, as shown in the first data row (No. 0) in Table 1.
Fig. 8 shows the coordination curve diagram of the DOCRs along Therefore, a curve intersection was detected and had to be resolved.
the BusB#610 → BusC#620 → BusD#630 section. Curve 1 was the Column “No.” in the table indicates the ordinal numbers of
coordination curve of the BusD#630:67 relay, Curve 2 was the coor- adjustment. For example, No. 1 means the first adjustment, No. 2
dination curve of the BusC#620:67 relay, and Curve 3 was the the second adjustment, and so on. Following several adjustments,
coordination curve of the BusB#610:67 relay. With all of the tap each with an incrementally adjusted amount of pickup current set-
values set to 5 A, Curve 3 intersected with Curve 2 at the point ting of 0.5 A, T became greater than zero at the fourth adjustment
corresponding to the fault current of 3300 A because inconsistent with INB = 7 and TDB = 0.14. Therefore, the intersection was elimi-
time–current characteristics existed among the various types of nated.
employed relays. Therefore, if a three-phase short-circuit close-in Fig. 9 shows the result of these adjustments and, for better
fault occurred on BusC#620:67, the upstream BusB#610:67 relay presentation, only two of the adjusted curves associated with the
activated before the BusC#620:67 relay as the fault current was less pickup current settings of 6 A and 7 A corresponding to backup relay
than 3300 A, causing a blackout in the entire BusC section. B#610:67. Curve 4 had a pickup current setting of 7 A on the backup
relay and no longer intersected with its primary relay C#620:67.
The multiple of pickup current of the curve was 3.33, which was
Table 1 acceptable according to the standard BS 142 [14]. Fig. 10 shows the
Intersection check and setting adjustment for the B#610(67:SPAJ140C) and
revised coordination curve diagram with the pickup current and
C#620(67:CR-8) pair.
time dial settings of backup relay B#610:67 adjusted to be 7 A and
Adjust settings of backup relay Check curve intersection (MBck = 1.6) 0.14, respectively. As shown in Fig. 10, the curve intersection was
No. INB TDB MB ICK MPck T eliminated by using the proposed method.
0 5.0 0.18 4.66 1920 1.60 −2.65
1 5.5 0.17 4.24 2112 1.76 −1.08 5.2. Case study 2
2 6.0 0.16 3.88 2304 1.92 −0.55
3 6.5 0.15 3.58 2496 2.08 −0.08 Fig. 11 shows the single-loop subtransmission system with
4 7.0 0.14 3.33 2688 2.24 0.11
seven buses that had a voltage rank of 69 kV. The rated current was
Y. Lu, J.-L. Chung / Electric Power Systems Research 95 (2013) 19–27 25
Fig. 10. Revised coordination curve diagram for the three-phase short-circuit fault Fig. 12. Coordination curve diagram with the original relay settings.
case.
1200 A and the CT ratio was 1200/5. The source impedances of BusA
were Z1 = 0.00229 + j0.02946 p.u. and Z0 = 0.13895 + j0.64157 p.u. Curve 6 was the coordination curve of the BusG#610:67N relay,
Additional relevant data concerning the DOCRs are shown in Fig. 11. Curve 5 was the coordination curve of the BusF#610:67N relay, and
The DOCRs used in the protective coordination included elec- so on. Curve 7 intersected Curve 6 at the point corresponding to the
tromechanical phase inverse directional overcurrent relays CR-8, single-phase ground fault current of 890 A because inconsistent
electromechanical ground inverse directional overcurrent relays time–current characteristics existed among the various types of
CRP-8 [18], and digital overcurrent relays SPAJ140C [14], all of relays.
which were manufactured by the ABB Company. The electrome- Table 2 presents the data related to curve intersection detec-
chanical phase inverse directional overcurrent relays IBC51 and tion and the relay setting adjustments for the coordination
electromechanical ground inverse directional overcurrent relays relay pair of backup relay A#610(67N:IBCG51) and primary relay
IBCG51 manufactured by GE Co. were also included [20,21]. G#610(67N:CRP-8) for the single-phase ground faults for the pro-
Fig. 12 shows the coordination curve diagram of the posed approach. As shown in Table 2, the settings of A#610:67N
DOCRs clockwise along the route of BusB#610 → BusC#610 → were initially specified as a pickup current setting (INB ) of 0.8, a time
BusD#620 → BusE#620 → BusF#610 → BusG#610 → BusA#610. dial setting (TDB ) of 7.5, and a derived multiple of pickup current
Curve 7 was the coordination curve of the BusA#610:67N relay, (MB ) of 16.25, and the computed operating time difference (T)
Fig. 11. Single-loop subtransmission network with 7 buses in the Taiwan Power Company.
26 Y. Lu, J.-L. Chung / Electric Power Systems Research 95 (2013) 19–27
Table 2
Intersection check and setting adjustment for the A#610(67N:IBCG51) and
G#610(67N:CRP-8) pair.
6. Conclusions
Fig. 13. Coordination curve diagram showing the adjustments of backup relay
This paper proposes a practical and effective approach for
A#610:67N. detecting and solving the coordination curve intersection problem
Y. Lu, J.-L. Chung / Electric Power Systems Research 95 (2013) 19–27 27
of overcurrent relays in subtransmission systems. The advantages [5] A.J. Urdaneta, H. Resterpo, J. Sanchez, J. Fajardo, Coordination of directional
of this method include substantial performance improvements overcurrent relays timing using linear programming, IEEE Transactions on
Power Delivery 11 (1) (1996) 122–129.
and cost reduction compared to the traditional manual calculation [6] A.J. Urdaneta, L.G. Perez, H. Restrepo, Optimal coordination of directional over-
method. The proposed approach can be used for both digital and current relays considering dynamic changes in the network topology, IEEE
electromechanical overcurrent relays. In addition, none of the exist- Transactions on Power Delivery 12 (4) (1997) 1458–1464.
[7] L.G. Perez, A.J. Urdaneta, Optimal coordination of directional overcurrent relays
ing overcurrent relays must be removed or replaced with advanced considering definite time backup relaying, IEEE Transactions on Power Delivery
relays, and they do not require modifications to their firmware. Fur- 14 (4) (1999) 1276–1284.
thermore, dissimilar to the conventional method, the adjustments [8] D. Birla, R.P. Maheshwari, H.O. Gupta, A new nonlinear directional over-
current relay coordination technique, and banes and boons of near-end
do not alter the originally specified CTI.
faults based approach, IEEE Transactions on Power Delivery 21 (3) (2006)
Two cases regarding subtransmission networks in the Taiwan 1176–1182.
Power Company were simulated to validate the feasibility of the [9] F. Razavi, H.A. Abyaneh, M. Al-Dabbagh, R. Mohammadi, H. Torkaman, A new
comprehensive genetic algorithm method for optimal overcurrent relays coor-
proposed method. These demonstrated its suitability for applica-
dination, Electric Power Systems Research 78 (2008) 713–720.
tion in the power industry. [10] P.P. Bedekar, S.R. Bhide, Optimum coordination of directional overcurrent
relays using the hybrid GA-NLP approach, IEEE Transactions on Power Delivery
26 (1) (2011) 109–119.
Acknowledgments
[11] IEEE Std C37.112-1996, IEEE Standard Inverse-Time Characteristic Equations
for Overcurrent Relays.
The authors would like to thank Wen-Shiow Kao, the Presi- [12] IEEE PSRC Committee, IEEE standard inverse-time characteristic equations for
dent of Taoyuan Innovation Institute of Technology, for his useful overcurrent relays, IEEE Transactions on Power Delivery 14 (3) (1999) 868–872.
[13] IEC Publication 255-3 (1989-05), Single Input Energizing Quality Measuring
advice that contributed to the original version of this document. Relays with Dependent or Independent.
This study was sponsored by the National Science Council, Taiwan, [14] User’s Manual and Technical Description, SPCJ4D29 Combined Overcurrent and
under Project No. NSC 100-2221-E-129-002-MY2. Earth-Fault Relay Module, ABB Co., Coral Springs, FL, 1997.
[15] J.C. Tan, P.G. McLaren, R.P. Jayasinghe, P.L. Wilson, Software model for inverse
time overcurrent relays incorporating IEC and IEEE standard curves, in:
References Proceedings of the 2002 IEEE Canadian Conference on Electrical & Computer
Engineering, 2002, pp. 37–41.
[1] A.S. Noghabi, J. Sadeh, H.R. Mashhadi, Considering different network topologies [16] Protection and Control Manual, Merlin Gerin Sepam 2000 Metering and Pro-
in optimal overcurrent relay coordination using a hybrid GA, IEEE Transactions tection Function, Schneider Electric Co., St. Louis, MO, 1999.
on Power Delivery 24 (4) (2009) 1857–1863. [17] W.A. Elmore, Protective Relaying Theory and Applications, 2nd ed., Marcel
[2] P.E. Sutherland, Protective device coordination in an industrial power system Dekker Inc., New York, 2004.
with multiple sources, IEEE Transactions on Industry Applications 33 (4) (1997) [18] Instruction 41-131Q, Types CR, CRC, CRP and CRD Directional Overcurrent
1096–1103. Relays, ABB Co., Coral Springs, Florida, 1998.
[3] D. Birla, R.P. Maheshwari, H.O. Gupta, An approach to tackle the threat of sym- [19] User’s Manual, ASPEN OneLiner V1999, Advanced Systems for Power Engineer-
pathy trips in directional overcurrent relay coordination, IEEE Transactions on ing, Inc., San Mateo, CA, 1999.
Power Delivery 22 (2) (2007) 851–858. [20] Instructions GEK-49821F, Phase Directional Overcurrent Relays, General Elec-
[4] D. Birla, R.P. Maheshwari, H.O. Gupta, Time-overcurrent relay coordination: a tric Co., Ontario, Canada, 1999.
review, International Journal of Emerging Electric Power Systems 2 (2) (2005) [21] Instructions GEK-100581, Ground Directional Overcurrent Relays, General
1–13. Electric Co., Ontario, Canada, 2003.