Slickline - Intervention - Checklist - IPM2
Slickline - Intervention - Checklist - IPM2
Pre-Job Issues
Ensure that there is an approved AFE with costs of job cost control.
Verify that all regulatory and government permits are issued and on board.
Verify that the OIM and relevant production personnel have been notified to
shut in the well and/or facilities. (Permit to Work process)
Verify the requirement for support vessels, i.e. barges, supply boats, crew
boats, tugs, helicopters.
Hold a Toolbox meeting to discuss the operation and safety issues with the
relevant personnel.
Ensure that the programme has been reviewed with the contractor.
Verify the wind direction and how gas will be vented during flow back/bleed-
off.
Ensure that the contractor personnel have the required experience and
training of the operation of their equipment.
Ensure that all personnel have the required training certificates (well control,
first aid, offshore certification, etc)
Verify that the Xmas tree (master valves, swab valve) was inspected and
pressure tested prior to arrival.
Verify that the master valves hold for the rig up.
Confirm the connection on the Xmas tree where the SL unit will rig up.
Slickline_Intervention_Checklist - IPM
Ensure that the weather forecast prior to rig up is favorable.
Ensure that there is a well history available showing past work and current
down-hole status of the well.
Verify the rig-up required and confirm whether there is any work in open
hole.
Confirm the weight and dimensions of the slickline unit and suitable space for
its placement.
Ensure that there is radio communications between the wireline unit and rig
floor.
Review the program and compare it to the equipment list to ensure that all
required equipment is on board prior to start of the job, including the back-
ups.
Ensure that fishing necks are known and fishing tools are available on
location prior to running any tool in hole.
Ensure that all of the components of the BOP/lubricator system are on board.
Refer to the equipment list. Verify the pressure rating of each component
and confirm that it has a compatible flange for the wellhead. Ensure all is
pressure tested and recorded prior to use.
Check the condition of all the slickline equipment, including the back-up
equipment. An inspection of all equipment should be done prior to delivery of
equipment to location.
Slickline_Intervention_Checklist - IPM
Know the maximum tension that can be applied to the diameter of slickline in
use.
Ensure that a go-devil is available if needed. Do not rely on pulling out of the
socket.
Ensure that the slickline unit has a braking system with a minimum capacity
equal to the cable breaking strength.
Ensure that slickline unit has a drive system capable of holding load in
neutral.
Slickline Operation
Verify the functions that will be done with the slickline to ensure that the
programme is suitable and that the equipment is fit for purpose.
Ensure to hold a Toolbox meeting prior to every slickline run into the well to
discuss the previous operation, the planned operation and the relevant safety
issues.
Slickline_Intervention_Checklist - IPM