Bilte Construction Contract Agreement

Download as pdf or txt
Download as pdf or txt
You are on page 1of 147

CONTRACT AGREEMENT

BETWEEN
THE REGIONAL STATE OF OROMIA
IRRIGATION AND PASTORALIST DEVELOPMENT
BUREAU

AND

ABDULJELIL KASIM GENERAL CONTRACTOR


GC-1/WWC-1

FOR

CONSTRUCTION OF FINNA OROMIA BILTE


PROJECT (Dam & Appurtenant Structures)

JANUARY, 2022
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Section I- Contract Agreement

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 1 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Contract Agreement

THIS AGREEMENT is made on the ________ day of __________, __________, between BUREAU
OF IRRIGATION AND PASTORALIST DEVELOPMENT OF OROMIA REGIONAL
STATE (hereinafter “the Public Body”), in one part, and ABDULJELIL KASIM GENERAL
CONTRACTOR GC-1/WWC-1 (hereinafter “the contractor”), in the other part:
WHEREAS, the Public Body has requested the Contractor to carryout construction of Dam and Its
appurtenant structures of Finna Bilte Dam project, and the Public Body has accepted a proposal by the
Contractor for the execution and completion of these Works and the remedying of any defects therein,
with Contract Price of the equivalent of Ethiopian Birr 95,986,458.71 (Ninety Five Million Nine
Hundred Eighty Six Thousand Four Hundred Fifty Eight Birr and 71/100 Cent only) including
15%VAT.
NOW THEREFORE the parties hereby agree as follows:
1. In this Agreement, words and expressions shall have the same meanings as are respectively
assigned to them in the Contract referred to.
2. The following documents shall constitute the Contract between the Public Body and the
Contractor, and each shall be read and construed as an integral part of the Contract:
1) Contract Agreement, including all appendices;
2) Letter of invitation
3) Special Condition of Contract
4) General Condition of Contract
5) Technical specifications
6) Drawings
7) Bill of Quantities
8) any other document listed in the SCC as forming part of the Contract,
3. This Contract shall prevail over all other Contract documents. In the event of any discrepancy or
inconsistency within the Contract documents, then the documents shall prevail in the order
4. In consideration of the payments to be made by the Public Body to the Contractor as hereinafter
mentioned, the Contractor hereby covenants with the Public Body to execute and complete the
Works, and remedy any defects therein in conformity in all respects with the provisions of the
Contract.
5. The Public Body hereby covenants to pay the Contractor in consideration of the execution and
completion of the Works and the remedying of defects therein the Contract Price or such other
sum as may become payable under the provisions of the Contract at the times and in the manner
prescribed by the Contract.
6. The Contract Price or such other sum as may be payable shall be paid in Ethiopian Birr.
In case of any contradiction between the provisions of this contract and other documents, the
provisions of this contract shall supersede.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 2 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

IN WITNESS whereof the parties thereto have caused this Agreement to be executed in accordance with
the law of Ethiopia on the day, month and year indicated above.

SIGNATURE AND SEAL

THE PUBLIC BODY THE CONTRACTOR

Signature: ___________________________ Signature: ________________________

Name: ______________________________ Name: ___________________________

Position: __________________________ Position: ________________________

WITNESSES

Name and Signature (For the Public Body) Name and Signature (For the Contractor)

1. ________________________________ 1. ______________________________

2. _____________________________ 2. ____________________________

3.______________________________ 3.____________________________






SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 3 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Section II- Special Conditions of Contract

A. General Provisions

B. The Contract

C. Obligations of the Public Body

D. Obligation of Contractor

E. Payments to the Contractor

F. Performance of the contract

G. Acceptance and Defects Liability

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 4 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Special Conditions of Contract (SCC)


GCC Clause Special Conditions of Contract
Reference
A. General Provisions

GCC 1.2(dd) The Public Body is Oromia Irrigation and Pastoralist Development Bureau

GCC 1.2 (g) The Contractor is ABDULJELIL KASIM GENERAL CONTRACTOR GC-
1/WWC-1
B. The Contract

In addition to documents listed in GCC Clause 7.1 the following documents shall
GCC 7.1 (i)
form the Contract: Minute of negotiation, if any

GCC 8.1 The governing law shall be the law of the Federal Democratic Republic of
Ethiopia.
GCC 9.1 Language of the Contract shall be English and/or Afaan Oromo.
GCC 10.2 the Public Body’s address shall be:
Public Body: Oromia Irrigation and Pastoralist Development
Bureau
Attention: Ato Alemu Regassa
Deputy Bureau Head, Irrigation And Pastoralist
Development.
Floor/Room number: Oromia Irrigation and Pastoralist Development
Bureau Building 6th Floor
P.O. Box: 20120
Town/City: Finfinne/Addis Abeba
Street Address: Sarbet
Post Code:
Country: Ethiopia
Telephone: +251-925-2847-47
Facsimile:
E-mail address
Contractor’s address shall be:
Contractor: ABDULJELIL KASIM GENERAL
CONTRACTOR GC-1/WWC-1
Attention:
Floor/Room number:
P.O. Box:
Street Address:
Town/City:
Post Code:
Country: Ethiopia
Telephone:

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 5 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

GCC Clause Special Conditions of Contract


Reference
Facsimile:
E-mail address
GCC 11.1 The Member in Charge is not applicable.

GCC 12.1 The Public Body’s Engineer shall be:


Engineer: Oromia Engineering Coorporation (ECO)
Attention: Obbo/Mr. Dereje Liben
Chief Executive Officer
P.O. Box: 870/1250
Floor Number Third Floor Room Number 329
Street Address: Akaki Kality Sub-City
Town/City: Finfinne
Post Code:
Country: Ethiopia
Telephone: +251114392162 or +2510114392470
Facsimile:
E-mail address
Not applicable
GCC 16.1
The Contractor, Sub-Contractors, and their Personnel :
GCC 17.1
Shall not be exempted from duties and indirect taxes levied by the Federal
Democratic Republic of Ethiopia, or
Shall be exempted from duties and indirect taxes levied by the Federal
Democratic Republic of Ethiopia, or
Shall be reimbursed by the Public Body for any such duties and indirect
taxes levied by the Federal Democratic Republic of Ethiopia they might
have to pay (or that the Public Body would pay such levies on behalf of the
Contractor and the Personnel).
The Public Body warrants that the Contractor, the Sub-Contractors and the
Personnel shall be exempt from (or that the Public Body shall pay on behalf of
the Contractor, the Sub-Contractors and the Personnel, or shall reimburse the
Contractor, the Sub-Contractors and the Personnel for) any indirect taxes, duties,
fees, levies and other impositions imposed, under the Applicable Law, on the
Contractor, the Sub-Contractors and the Personnel in respect of:
(a). any payments whatsoever made to the Contractor, Sub-Contractors and the
Personnel (other than nationals or permanent residents of the Federal
Democratic Republic of Ethiopia), in connection with the carrying out of the
Works;
(b). any equipment, materials and supplies brought into the Federal Democratic
Republic of Ethiopia by the Contractor or Sub-Contractors for the purpose of
carrying out the Works and which, after having been brought into such
territories, will be subsequently withdrawn there from by them;

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 6 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

GCC Clause Special Conditions of Contract


Reference
(c). any equipment imported for the purpose of carrying out the Works and paid
for out of funds provided by the Public Body and which is treated as property
of the Public Body;
(d). any property brought into the Federal Democratic Republic of Ethiopia by
the Contractor, any Sub-Contractors or the Personnel (other than nationals or
permanent residents of the Federal Democratic Republic of Ethiopia), or the
eligible dependents of such Personnel for their personal use and which will
subsequently be withdrawn there from by them upon their respective
departure from the Federal Democratic Republic of Ethiopia, provided that:
the Contractor, Sub-Contractors and Personnel, and their eligible dependents,
shall follow the usual customs procedures of the Federal Democratic
Republic of Ethiopia in importing property into the Federal Democratic
Republic of Ethiopia; and
if the Contractor, Sub-Contractors or Personnel, or their eligible dependents,
do not withdraw but dispose of any property in the Federal Democratic
Republic of Ethiopia upon which customs duties and taxes have been
exempted, the Contractor, Sub-Contractors or Personnel, as the case may
be, (i) shall bear such customs duties and taxes in conformity with the
regulations of the Federal Democratic Republic of Ethiopia, or (ii) shall
reimburse them to the Public Body if they were paid by the Public Body
at the time the property in question was brought into the Federal
Democratic Republic of Ethiopia

GCC 22.1 The percentage to apply to the value of the work not completed, representing the
public Body's additional cost for completing the Works, is 10%.
C. Obligations of the Public Body

GCC 30.2 The Public Body shall provide the following further assistance to the Contractor:
Letter of Support.
D. Obligations of the Contractor

GCC 34.5(b) The Public Body's prior approval is also required for additional works that would
adversely affect the cost of project, time extensions, Compensation claims and
rates.

GCC 39.2 (b) The amount of aggregate liability shall be 100%

The minimum insurance cover and deductibles shall be 100%


The minimum cover for insurance of the Works, Plant and Materials is 100%
The maximum deductible for insurance of the Works, Plant and Materials is 100%
GCC 40.1 The minimum cover for insurance of Equipment is 100%
The maximum deductible for insurance of Equipment is 100%.
The minimum cover for insurance of property is 100%
The maximum deductible for insurance of property is 100%

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 7 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

GCC Clause Special Conditions of Contract


Reference
The minimum cover for personal injury or death insurance is 100% with no
deductible
The amount of insurance covering liability with regard to risks and civil liability
GCC 40.3 insurance shall be: Unlimited; or
Limited
The Contractor shall submit a Program of implementation of the tasks within 7
days of delivery of the Notice of Acceptance.
GCC 41.1
The specific requirements of the Program of implementation of tasks are the
following: Work Schedule

GCC 41.4 The period between Program updates is 30 days.


The amount to be withheld for late submission of an updated Program is
500,000.00 ETB(Five Hundred Thousands).
None
GCC 47.1
None
GCC 47.2
None
GCC 50.1
None
GCC 50.4
None
GCC 52.5
None
GCC 53.1
None
GCC 55.1
The amount of the Performance Security shall be 10% of the contract price.
GCC 58.1

The types of acceptable Performance Securities are in the form of unconditional


GCC 58.4 Bank Guarantee acceptable by Public Body.
The currency shall be: in Ethiopian Birr (ETB).
Discharge of the Performance Security shall take place: not later than twenty-eight
GCC 58.8 (28) days following the date of issuing of the signed Final Statement of Account
referred to in GCC Clause 65
E. Payments to the Contractor

All payment to the Contractor under this Contract shall be made in Ethiopian Birr.
GCC 59.1

GCC 60.1 Advance payment shall be granted to the Contractor, at his request.

GCC 60.2 The amount of the advance payment shall be 30% of the contract price up on
submission of unconditional Bank Guarantee.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 8 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

GCC Clause Special Conditions of Contract


Reference
The following provisions shall apply to the advance payment and advance
payment security;
An advance payment security shall be in the form of unconditional Bank
Guarantee.
An advance payment shall be made within 30 days after project site handover work
is executed.
The repayment of advance payment shall take the form of deduction based on the
monthly payments. The repayment shall begin with 1St payment and be completed,
at the very latest, by the time 80 % of the amount of the contract has been paid.
GCC 60.9 Repayment shall be in the same currency as the advance payment.
The amount to be deducted from each payment shall be calculated using the
following formula;
𝑉𝑎∗𝐷
𝑅=
𝑉𝑡∗0.8
Where, R= the amount to be repaid
Va= the total amount of the advance payment
Vt= initial contract amount
D= the amount of the payment
The result is rounded up to two decimal places.

GCC 61.1 The retention amount is 5% of the contract price.

Price Adjustment not Applicable/Allowed.


GCC 62.7,
62.13

Arrangements for interim payments shall be the following: The contractor shall
GCC 64.1
submit statement of interim payment to the engineer in one month’s time.

GCC 64.7 The frequency of the interim payment shall be monthly basis but the amount
should not be less than 2% of the contract amount.
F. Performance of the Contract

The Scope of Works shall be defined as in Technical Specifications of this contract


GCC 70.1
The Contractor shall carry out the Works at North Showa Zone of Oromia
GCC 70.2
Regional State, in Abichu Nya’a Woreda

GCC 71.1 The Start Date shall be 15 days after site handover.

The Intended Completion Date for the whole of the Works shall be 300 calendar
GCC 72.1
days.
G. Acceptance and Defects Liability

The defect liability period shall be 365 days and commence on the date of the
GCC 88.7
provisional acceptance

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 9 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page - 10 -


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

General Conditions of Contract

Table of Clauses

A. General Provisions 14

1. Definitions 14
2. Appointment 16
3. Relationship Between the Parties 17
4. Due Diligence 17
5. Fraud and Corruption 17
6. Interpretation 18
B. The Contract 19

7. Contract Documents 19
8. Governing Law 20
9. Language 20
10. Notices and written communications 20
11. Authority of Member in Charge 20
12. Engineer and Engineer's Representative 20
13. Assignment 21
14. Subcontracting 22
15. Modifications by Change Orders 22
16. Change in Laws and Regulations 24
17. Taxes and Duties 24
18. Force Majeure 24
19. Breach of Contract 25
20. Suspension 26
21. Termination 26
22. Payment upon Termination 28
23. Arrangements on Termination 29
24. Cessation of Rights and Obligations 29
25. Cessation of Works 29
26. Settlement of Disputes 30
27. Liquidated Damages 30
28. Confidentiality 30
29. Miscellaneous 32
C. Obligations of the Public Body 32

30. Assistance and Supply of Documents 32


31. Access to the Site 33
32. Payment 33

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 11


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

33. Delayed Payments to the Contractor's Staff 33


D. Obligations of the Contractor 33

34. General Obligations 34


35. Eligibility 34
36. Code of Conduct 35
37. Control and Supervision of the Works 35
38. Personnel 36
39. Indemnification and Limitation of Liability 37
40. Insurance to be Taken Out by the Contractor 37
41. Program of Implementation of Tasks 38
42. Contractor's Drawings 39
43. Sufficiency of Bid Prices 40
44. Exceptional Risks 40
45. Health and Safety on Sites 41
46. Safeguarding Adjacent Properties 42
47. Interference with Traffic 42
48. Cables and Conduits 42
49. Setting-out of the Works 43
50. Demolished Materials 43
51. Discoveries 43
52. Temporary Works 44
53. Soil Studies 44
54. Overlapping Contracts 44
55. Patents and Licenses 45
56. Accounting, Inspection and Auditing 45
57. Data Protection 45
58. Performance Security 45
E. Payments to the Contractor 46

59. General Principles 46


60. Advance Payment 47
61. Retention Monies 48
62. Price Adjustments 49
63. Valuation of Works 51
64. Interim Payment 52
65. Final Statement of Account 53
66. Direct Payments to Sub-Contractors 53
67. Delayed Payments 54
68. Payments to Third Parties 54
69. Claims for Additional Payment 54
F. Performance of the Contract 55
SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 12
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

70. Scope of Works 55


71. Commencement of Works 55
72. Period of Execution of Works 55
73. Extension of Intended Completion Date 55
74. Compensation Events for Allowing Time Extension 56
75. Acceleration 57
76. Management Meetings 57
77. Early Warning 57
78. Delays in Implementation of Tasks 57
79. Work Register 58
80. Origin and Quality of Works and Materials 58
81. Inspection and Testing 59
82. Rejection 59
83. Ownership of Plant and Materials 60
G. Acceptance and Defects Liability 61

84. General Principles 61


85. Tests on Completion 61
86. Partial Acceptance 61
87. Provisional Acceptance 62
88. Defects Liability 62
89. Final Acceptance 63

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 13


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

General Conditions of Contract


A. General Provisions
1. Definitions

1.1 The headings and titles of these General Conditions of Contract shall not limit, alter or affect the
meaning of the Contract
1.2 The following words and expressions shall have the meanings hereby assigned to them:

(a)"Bill of Quantities" means the document forming part of the Bid and containing an
itemized breakdown of the works to be carried out in a unit price
contract, indicating a quantity for each item and the corresponding
unit price;
(b) "Completion" means the fulfillment of the Contract by the Contractor in accordance
with the terms and conditions set forth in the in the GCC Clause 87;
(c)"Contract Documents" means the documents listed in the GCC, including all attachments,
appendices, and all documents incorporated by reference therein, and
shall include any amendments thereto;
(d) "Contract Manager" means a person designated as such by the Contractor from time to
time as notified in writing to the Public Body to act as the duly
authorized representative of the Contractor for all purposes connected
with the Contract, including any authorized representative of such
person;
(e) "Contract Price" means the accepted contract amount stated in the Public Body's Letter
of Acceptance. The amount represents the initial estimate payable for
the execution of the works or such other sum as ascertained by the
final statement of account as due to the Contractor under the contract;
(f) "Contract" means the binding Contract Agreement entered into between the
Public Body and the Contractor, comprising Contract Documents
referred to therein, including all attachments, appendices, and all
documents incorporated by reference therein,
(g) "Contractor" means a natural or juridical person under contract with a Public Body
to supply works;
(h) "Day" means calendar day;

(i) "Dayworks" mean varied work inputs subject to payment on an hourly basis for
the Contractor's employees and equipment, in addition to payment for
associated materials and plants;
(j) "Defect" Defect is any part of the Works not completed in accordance with the
Contract;
(k) "Defects Liability is the period stated in the Special Conditions of Contract immediately
Period" following the date of provisional acceptance, during which the
Contractor is required to complete the works and to remedy defects
or faults as instructed by the Engineer;
(l) "Drawings" mean the drawings of the Works, as included in the Contract, and any
additional and modified drawings issued by (or on behalf of) the
Public Body in accordance with the Contract, include calculations and
other information provided or approved by the Engineer for the
carrying out of the works.
(m) "Eligible Countries" means the countries and territories eligible as listed in Section 5 of the
Bidding Documents;

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 14


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(n) "Engineer" means a person named in the Special Conditions of Contract or


appointed as such by the Public Body and notified in writing to the
Contractor to act as the representative of the Public Body to supervise
and inspect works and to test and examine the materials employed and
the quality of workmanship, including any authorized representative
of such person;
(o) "Equipment" is the Contractor's machinery, vehicles, apparatus, components and
any other articles brought temporarily to the Site to construct the
Works;
(p) "Final Acceptance Certificate(s) issued by the Engineer to the Contractor at the end of
Certificate" the Defects Liability Period stating that the Contractor has completed
its obligations to construct, complete, and maintain the Works
concerned;
(q) "General Conditions of hereinafter referred to as “GCC”, means the general contractual
Contract" provisions setting out the administrative, financial, legal and technical
clauses governing the execution of the Contract, except where
amended by the SCC or Contract Agreement;
(r) "Good Industry means the exercise of that degree of skill, diligence and foresight
Practice" which would reasonably and ordinarily be expected from a skilled and
experienced Contractor engaged in the provision of works similar to
the works under the same or similar circumstances as those applicable
to the Contract and which are in accordance with any codes of practice
published by relevant trade associations;
(s) "Government" means the Government of the Federal Democratic Republic of
Ethiopia;
(t) "In writing" shall be interpreted to include any document which is recorded in
manuscript or typescript;
(u) "Intended Completion is the date on which it is intended that the Contractor shall complete
Date" the Works. The Intended Completion Date is specified in the Special
Conditions of Contract. The Intended Completion Date may be revised
only by the Engineer by issuing an extension of time or an acceleration
order;
(v) "Liquidated damages" means the compensation stated in the contract as being payable by
Contractor to the Public Body for failure to perform the contract or
part thereof within the periods under the contract, or as payable by
Contractor to the Public Body for any specific breach identified in the
contract;
(w) "Materials" are all supplies, including consumables, used by the Contractor for
incorporation in the Works;
(x) "Member" means any of the entities that make up the joint venture / consortium
/ association; and “Members” means all these entities;
(y) "Month" means calendar month;

(z) "Party" means the Public Body or the Contractor and includes their permitted
successors and “Parties” means both of them;
(aa) "Plant" means appliances and other machinery, and, where applicable under
the law and/or practice of the Federal Democratic Republic of
Ethiopia, the temporary structures on the site required to carry out the
works but excluding equipment or other items required to form part
of the permanent works;

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 15


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(bb) "Price Schedule" means the completed schedule of prices, including the breakdown of
the overall price, submitted by the Contractor with his Bid, modified
as necessary and forming a part of the unit price contract;
(cc) "Provisional Sum" means a sum included in the contract and so designated for the
implementation of works or the supply of goods, materials, plant or
services, or for contingencies, which sum may be used in whole or in
part, or not at all, as instructed by the Engineer;
(dd) "Public Body" means public body, which is partly or wholly financed by the Federal
Government Budget, higher education institutions, and public
institutions of like nature which has the powers and duties to conclude
a Contract for the supply of Works, as specified in the SCC;
(ee) "Site" means the places provided by the Public Body where the works are to
be carried out, and other places stated in the Contract as forming part
of the site;
(ff) "Special Conditions of hereinafter referred to as “SCC”, means the conditions attached to the
Contract" Contract Agreement, which shall govern the Contract and shall
prevail over these General Conditions of Contract;
(gg) "Specification" means the Specification of the Works included in the Contract drawn
up by the Public Body setting out its requirements and/or objectives
in respect of the provision of works, specifying, where relevant, the
methods and resources to be used and/or results to be achieved;
(hh) "Start Date" is given in the Special Conditions of Contract. It is the latest date when
the Contractor shall commence execution of the Works;
(ii) "Sub-Contractor" means any natural person, private or government entity, or a
combination of the above, including its legal successors or permitted
assigns who has a Contract with the Contractor to carry out a part of
the Work in the Contract, which includes work on the Site;
(jj) "Third Party" means any person or entity other than the Public Body, the
Contractor or a Sub-Contractor;
(kk) "Works" mean all work associated with the construction, reconstruction,
upgrading, demolition, repair, renovation of a building, road, or
structure, as well as services incidental to works, if the value of those
services does not exceed that of works themselves;
2. Appointment

2.1 The Public Body appoints the Contractor to carry out the Works:
(a) Promptly (and in any event within any time targets as may be set out in the Section 6, Schedule
of Requirements) and in a professional and courteous manner so as to reflect and promote the
image of the Public Body;
(b) Strictly in accordance with the Schedule of Requirements and all provisions of the Contract;
and
(c) In accordance with all applicable laws and regulations of the Federal Democratic Republic of
Ethiopia and Good Industry Practice; and
(d) In accordance with the policies, rules, and procedures of the appropriate Authority as amended
from time to time.
(e) In accordance with the quality standards set by the Ministry of Urban Development and
Construction, Quality and Standards Authority of Ethiopia (QSAE), and applicable
international standards;

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 16


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(f) In accordance with the terms and conditions of appointment as provided in this Clause in
consideration of the Contract Price.

3. Relationship Between the Parties

3.1 Nothing contained herein shall be construed as establishing a relationship of master and servant or of
principal and agent as between the Public Body and the Contractor. The Contractor, subject to this
Contract, has complete charge of Personnel and Sub-Contractors, if any, carrying out the Works and
shall be fully responsible for the Works carried out by them or on their behalf hereunder. The
Contractor shall not incur any liabilities on behalf of the Public Body or enter into any contract or
obligation on behalf of the Public Body.

4. Due Diligence

4.1 The Contractor acknowledges that it:


(a) Has made and shall make its own enquiries to satisfy itself as to the accuracy and adequacy of
any information supplied to it by or on behalf of the Public Body;
(b) Has raised all relevant due diligence questions with the Public Body before the Effective Date;
and
(c) Has entered into this Contract in reliance on its own due diligence alone.
4.2 The Contractor acknowledges that it has inspected the Site Environment and has advised the Public
Body of any aspect of the Site Environment that is not suitable for carrying out the Works and that
the specified actions to remedy the unsuitable aspects of the Site Environment, together with a
timetable for and the costs of those actions, have been specified in the relevant parts of the Contract
for the Pre-Operational Phase.
4.3 If the Contractor has either failed to inspect the Site Environment or failed to notify the Public Body
of any required remedial actions in accordance with Clause 4.2 then the Contractor shall not be entitled
to recover any additional costs or charges from the Public Body relating to any unsuitable aspects of
the Site Environment nor shall the Contractor be entitled to seek relief in respect of any Default arising
from such failure.
4.4 Any disputes relating to due diligence shall be resolved in accordance with the Ethiopian Law.

5. Fraud and Corruption

5.1 It is the Government of the Federal Democratic Republic of Ethiopia’s policy to require that Public
Body, as well as bidders/suppliers, to observe the highest standards of ethics during the procurement
and the execution of contracts. In pursuance of this policy, the Government of the Federal Democratic
Republic of Ethiopia represented by the Public Procurement and Property Administration Agency
(herein referred to as the Agency) requires that Public Bodies shall include in bidding documents,
provisions against corrupt practices.
5.2 If the Public Body determines that the Contractor and/or its Personnel, sub-contractors, services
providers and suppliers has engaged in corrupt, fraudulent, collusive, coercive, or obstructive
practices, in competing for or in executing the Contract, then the Public Body may, after giving 14
days notice to the Contractor, terminate the Contractor's employment under the Contract, and the
provisions of GCC Clause 21 shall apply as if such expulsion had been made under GCC Sub-Clause
21.2(i).
5.3 The Agency defines, for the purposes of these provisions, the terms set forth below as follows:

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 17


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(a) “Corrupt practice” is the offering, giving, receiving or soliciting, directly or indirectly, of any
thing of value to influence the action of a public official in the procurement process or in
contract execution, and
(b) “Fraudulent practice” is any act or omission, including misrepresentation that knowingly or
recklessly misleads, or attempts to mislead, a party to obtain financial or other benefit or to
avoid an obligation.
(c) “Collusive practices" is a scheme or arrangement between two or more Contractors, with or
without the knowledge of the Public Body, designed to establish prices at artificial, non
competitive levels, and
(d) “Coercive practices” is harming or threatening to harm, directly or indirectly, persons or their
property to influence their participation in a procurement process, or affect the execution of a
contract.
(e) "Obstructive practice" is
(i) deliberately destroying, falsifying, altering or concealing of evidence material to the
investigation or making false statements to investigators in order to materially impede the
Federal Ethics and Anticorruption Commission, the Federal Auditor General and the Public
Procurement and Property Administration Agency or their auditors' investigation into
allegations of a corrupt, fraudulent, coercive or collusive practice; and/or threatening,
harassing or intimidating any party to prevent their from disclosing their knowledge of
matters relevant to the investigation or from pursuing the investigation, or
(f) acts intended to materially impede the exercise of inspection and audit rights provided for under
GCC Sub-clause 56.2.
5.4 The Agency will debar a Contractor from participation in public procurement for a specified period
of time if it at any time determines that the Contractor has engaged in corrupt, fraudulent, collusive,
coercive or obstructive practices in competing for, or in executing, a contract.
5.5 The Agency reserves the right, where a Contractor has been found by a national or international entity
to have engaged in corrupt or fraudulent practice, to declare that such a Contractor is ineligible, for a
stated period of time, to be awarded a Government funded contract.
5.6 The Agency will have the right to require that, in contracts funded by the Government of Ethiopia, a
provision be included requiring Contractors to permit the Agency to inspect their accounts and records
relating to the performance of the contract and to have them audited by auditors appointed by the
Agency, if the Contractor engages in any corrupt practice.
5.7 Any communications between the Contractor and the Public Body or the Agency related to matters
of alleged fraud or corruption must be made in writing.

6. Interpretation

6.1 In interpreting these GCC, words indicating one gender include all genders. Words indicating the
singular also include the plural and words indicating the plural also include the singular. Headings
have no significance. Words have their normal meaning under the language of the Contract unless
specifically defined. The Engineer shall provide instructions clarifying queries about these GCC.

6.2 If sectional completion is specified in the Special Conditions of Contract, references in the General
Conditions of Contract to the Works, the Completion Date, and the Intended Completion Date apply
to any Section of the Works (other than references to the Completion Date and Intended Completion
Date for the whole of the Works)..

6.3 Entire Agreement

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 18


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

This Contract contains all covenants, stipulations and provisions agreed by the Parties. No agent or
representative of either Party has authority to make, and the Parties shall not be bound by or be
liable for, any statement, representation, promise or agreement not set forth herein.
6.4 Amendment
No amendment, modification or other variation of the Contract shall be valid unless an Amendment
to Contract is made in writing, is dated, expressly refers to the Contract, and is signed by a duly
authorized representative of each party thereto.
6.5 Nonwaiver
(a) Subject to GCC Sub-Clause 6.5(b) below, no relaxation, forbearance, delay, or indulgence by
either party in enforcing any of the terms and conditions of the Contract or the granting of time
by either party to the other shall prejudice, affect, or restrict the rights of that party under the
Contract, neither shall any waiver by either party of any breach of Contract operate as waiver of
any subsequent or continuing breach of Contract.
(b) Any waiver of a party’s rights, powers, or remedies under the Contract must be in writing, dated,
and signed by an authorized representative of the party granting such waiver, and must specify
the right and the extent to which it is being waived.
6.6 Severability
If any provision or condition of the Contract is prohibited or rendered invalid or unenforceable, such
prohibition, invalidity or unenforceability shall not affect the validity or enforceability of any other
provisions and conditions of the Contract.

B. The Contract
7. Contract Documents

7.1 The documents forming the Contract shall be interpreted in the following order of precedence in the
event of any conflict between the documents comprising this Contract:
(a) Agreement, including all appendices;
(b) Letter of Invitation by the Public Body to the Contractor;
(c) The Special Conditions of Contract;
(d) The General Conditions of Contract;
(e) Technical Specifications;
(f) The design documentation (drawings);
(g) For Unit-price contracts: The Bill of Quantities and Price Schedule (after correction of
arithmetical errors);
For Lump-sum contracts: The Breakdown of the Lump-sum Price (after correction of
arithmetical errors);
(h) Any other document listed in the SCC as forming part of the Contract.
7.2 All documents forming the Contract are intended to be correlative, complementary, and mutually
explanatory.
7.3 Any action required or permitted to be taken, and any document required or permitted to be provided,
under the Contract by the Public Body or the Contractor may be taken or provided by the authorized
representatives specified in the SCC.
7.4 The Contract constitutes the entire agreement between the Public Body and the Contractor and
supersedes all communications, negotiations and agreements (whether written or oral) of parties with
SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 19
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

respect thereto made prior to the date of Contract. No agent or representative of either Party has
authority to make, and the Parties shall not be bound by or be liable for, any statement, representation,
promise or agreement not set forth herein.

8. Governing Law

8.1 The Contract, its meaning and interpretation, and relation between the Parties shall be governed by
and interpreted in accordance with the laws of the Federal Democratic Republic of Ethiopia, unless
otherwise stated in SCC.

9. Language

9.1 The Contract as well as all written and oral communication and documents relating to the Contract
exchanged by the Contractor and the Public Body, shall be in language specified in the SCC.
Supporting documents and printed literature that are part of the Contract may be in another language,
but any documents provided in another language must be accompanied by an accurate translation into
language specified in the SCC. For purposes of interpretation of the Contract, this translation shall
govern.

9.2 The Contractor shall bear all costs of translation to the governing language and all risks of the accuracy
of such translation.

10. Notices and written communications

10.1 Any notice, request or consent required or permitted to be given or made pursuant to this Contract
shall be in writing. The term “in writing” means communicated in written form with proof of receipt.
10.2 Any such notice, request or consent shall be deemed to have been given or made when delivered in
person to an authorized representative of the Party to whom the communication is addressed, or when
sent to such Party at the address specified in the SCC.
10.3 A Party may change its address for notice hereunder by giving the other Party notice in writing of
such change to the address specified in the SCC.

11. Authority of Member in Charge

11.1 In case the Contractor consists of a joint venture/consortium/ association of two or more entities, all
such entities shall be jointly and severally bound to fulfill the terms of the contract according to the
law of the Federal Democratic Republic of Ethiopia. The Members hereby authorize the entity
specified in the SCC to act on their behalf as leader with authority to bind the joint venture or
consortium in exercising all the Contractor’s rights and obligations towards the Public Body under
this Contract. The composition or the constitution of the joint venture or consortium shall not be
altered without the prior consent of the Public Body.

12. Engineer and Engineer's Representative

12.1 Except where otherwise specifically stated and subject to any restriction in the SCC, any action
required or permitted to be taken, and any document required or permitted to be executed, under this
Contract by the Public Body or the Contractor may be taken or executed by the Engineers named in
the SCC. Except as expressly stated in the SCC, the Engineer shall not have authority to relieve the
Contractor of any of his obligations under the Contract.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 20


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

12.2 Any notice, information or communication given to or made by an Engineer shall be deemed to have
been given or made by the Public Body.
12.3 The Engineer may delegate any of his duties and responsibilities to Engineer's representative after
notifying the Contractor, and may cancel any delegation after notifying the Contractor.
12.4 The role of the Engineer’s representative shall be to supervise and inspect works and to test and
examine the materials employed and the quality of workmanship. Under no circumstances will the
Engineer's representative be empowered to relieve the Contractor of his obligations under the contract
or – except where express instructions to that effect are given in the SCC – order works resulting in
an extension of the period of performance or additional costs to be paid by the Public Body or
introduce variants in the nature or scale of the works.
12.5 Any communication given by the Engineer's representative to the Contractor in accordance with the
terms of such delegation shall have the same effect as though it had been given by the Engineer,
provided that:
(a) Any failure on the part of the Engineer's representative to disapprove any work, materials or
plant shall not prejudice the authority of the Engineer to disapprove such work, materials or
plant and to give the instructions necessary for the rectification thereof;
(b) The Engineer shall be at liberty to reverse or vary the contents of such communication.
12.6 Instructions and/or orders issued by the Engineer shall be by way of administrative orders. Such orders
shall be dated, numbered and entered by the Engineer in a register, and copies thereof delivered by
hand, where appropriate, to the Contractor's representative.

13. Assignment

13.1 An assignment is a written agreement by which the Contractor transfers its contract or part thereof to
a third party.
13.2 The Contractor shall not, without the prior written consent of the Public Body, assign the Contract or
any part thereof, or any benefit or interest thereunder, except in the following cases:
(a) A charge, in favor of the Contractor's bankers, of any monies due or to become due under the
Contract; or
(b) Assignment to the Contractor's insurers of the Contractor's right to obtain relief against any
other person liable in cases where the insurers have discharged the Contractor's loss or liability.
13.3 For the purpose of GCC Clause 13.2 the approval of an assignment by the Public Body shall not
relieve the Contractor of his obligations for the part of the Contract already performed or the part not
assigned.
13.4 If the Contractor has assigned his Contract without authorization, the Public Body may, without giving
formal notice thereof, apply as of right the sanctions for breach of Contract provided for in GCC
Clauses 19 and 21.
13.5 Assignees must satisfy the eligibility criteria applicable for the award of the Contract and they can not
be in any of the situations excluding them from participating in Contract.
13.6 Every assignment shall be subject to the provisions of this Contract and shall incorporate the terms
and conditions of this Contract.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 21


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

14. Subcontracting

14.1 A sub-contract shall be valid only if it is a written agreement by which the Contractor entrusts
performance of a part of the Contract to a third party.
14.2 In the event the Contractor requires sub-contracting of the works to Sub-Contractors that are not
included in the Contract, the Contractor shall obtain the prior written approval and clearance of Public
Body for all Sub-Contractors. The work to be sub-contracted and the identity of the subcontractors
shall be notified to the Public Body. The Public Body shall with due regard to the provisions of GCC
Clause 10 within 15 days of receipt of the notification, notify the Contractor of its decision, stating
reasons should he withhold such authorization.
14.3 The terms of any sub-contract shall be subject to and conform to the provisions of this Contract.
14.4 Sub-Contractors must satisfy the eligibility criteria applicable to the award of the contract and they
can not be in any of the situations excluding them from participating in contract.
14.5 Subject to GCC Clause 66, the Public Body shall have no contractual relations with the Sub-
Contractors.
14.6 The Contractor shall be responsible for the acts, defaults and negligence of his Sub-Contractors and
their agents or employees, as if they were the acts, defaults or negligence of the Contractor, his agents
or employees. The approval by the Public Body of the sub-contracting of any part of the contract or
of the Sub-Contractor to perform any part of the works shall not relieve the Contractor of any of his
obligations under the contract.
14.7 If a Sub-Contractor has undertaken any continuing obligation for a period exceeding that of the
Defects Liability Period under the contract towards the Contractor in respect of the work executed or
the goods, materials, plant or services supplied by the Sub-Contractor, the Contractor shall, at any
time after the expiration of the Defects Liability Period, transfer immediately to the Public Body, at
the Public Body's request and cost, the benefit of such obligation for the unexpired duration thereof.
14.8 If the Contractor enters into a subcontract without approval, the Public Body may apply, as of right
without giving formal notice thereof, the sanctions for breach of contract provided for in GCC Clauses
19 and 21.
14.9 If a Sub-Contractor is found by the Public Body or the Engineer to be incompetent in discharging its
duties, the Public Body or the Engineer may request the Contractor forthwith, either to provide a Sub-
Contractor with qualifications and experience acceptable to the Public Body as a replacement, or to
resume the implementation of the tasks itself.

15. Modifications by Change Orders

15.1 The Engineer shall have power to order any modification to any part of the works necessary for the
proper completion and /or functioning of the works. Such modifications may include additions,
omissions, substitutions, changes in quality, quantity, form, character, kind, position, dimension, level
or line and changes in the specified sequence, method or timing of execution of the works. No order
for a modification shall have the effect of invalidating the contract, but the financial effect, if any, of
all such modifications shall be valued in accordance with GCC Clauses 15.5 and 15.7.
15.2 All change orders shall be issued in writing, it being understood that:
(a) if for any reason, the Engineer shall find it necessary to give an order orally, he shall as soon
as possible thereafter confirm the order by an change order;

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 22


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(b) if the Contractor shall confirm in writing an oral order given for the purpose of GCC Clause
15.2 (a) and the confirmation shall not be contradicted in writing forthwith by the Engineer, an
change order shall be deemed to have been issued for the modification.
A change order for modification shall not be required for increase or decrease in the quantity of any
work where such increase or decrease is the result of the quantity exceeding or being less than that
stated in the bill of quantities or price schedule, as the result of valuation of works laid down in GCC
Clause 63.
15.3 Except as provided by GCC Clause 15.2 prior to any change order for modification, the Engineer
shall notify the Contractor of the nature and form of such modification. As soon as possible, after
receiving such notice, the Contractor shall submit to the Engineer a proposal containing:
(a) a description of the tasks, if any, to be implemented or the measures to be taken and a program
for execution; and
(b) any necessary modifications to the program of implementation of tasks or to any of the
Contractor's obligations under the contract; and
(c) any adjustment to the contract price in accordance with the rules as set out in this Clause.
15.4 Following the receipt of the Contractor's submission referred to in GCC Clause 15.3, the Engineer
shall, after due consultation with the Public Body and, where appropriate, the Contractor, decide as
soon as possible whether or not the modification shall be carried out. If the Engineer decides that the
modification shall be carried out he shall issue the change order stating that the modification shall be
carried out at the prices and under the conditions given in the Contractor's submission referred to in
GCC Clause 15.3 or as modified by the Engineer in accordance with GCC Clause 15.5.
15.5 The prices for all modifications ordered by the Engineer in accordance with GCC Clause 15.2 and
15.4 shall be ascertained by the Engineer in accordance with the following principles:
(a) where work is of similar character and executed under similar conditions to work priced in the
bill of quantities or price schedule it shall be valued at such rates and prices contained therein;
(b) where work is not of a similar character or is not executed under similar conditions, the rates
and prices in the contract to be agreed through negotiation between the Engineer and the
Contractor shall conform to the prevailing market price;
(c) if the nature or amount of any modification relative to the nature or amount of the whole of the
contract or to any part thereof shall be such that in the opinion of the Engineer any rate or price
contained in the contract for any item of work is by reason of such modification rendered
unreasonable, then the Engineer shall fix such rate or price as in the circumstances he shall
think reasonable and proper;
(d) where a modification is necessitated by default or breach of contract by the Contractor, any
additional cost attributable to such modification shall be borne by the Contractor.
15.6 On receipt of the change order requesting the modification, the Contractor shall proceed to carry out
the modification and be bound by these GCC in so doing as if such modification were stated in the
contract. The works shall not be delayed pending the granting of any extension of time for completion
or adjustment to the contract price. Where the order for a modification precedes the adjustment to the
contract price, the Contractor shall keep records of the costs of undertaking the modification and of
time expended thereon. Such records shall be open to inspection by the Engineer at all reasonable
times.
15.7 Where on provisional acceptance an increase or reduction in the total value of the works resulting
from a change order, or from some other circumstance which is not caused by the Contractor's default,
exceeds 25% of the initial contract price (or as modified by addendum), the Engineer shall, after
consultation with the Public Body and the Contractor determine any reduction from the contract price
as a consequence of the application of GCC Clause 15.5. The sum so determined shall be based on
SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 23
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

the amount by which the increase or decrease in value of the works exceeds 25%. The sum shall be
notified by the Engineer to the Public Body and the Contractor and the contract price adjusted
accordingly.
15.8 The total value of the works resulting from a change order shall not exceed 30% of the total value of
the initial contract price.
15.9 Any change to the terms of the Contract must be recorded in writing and executed by authorized
signatory of the Contractor and the Engineer. Such record of the change in question must address all
consequential amendments required to be made to the Contract as a result of such change.
15.10 Changes will take effect as from the date specified in the signed record of change and shall not have
retrospective effect unless expressly provided for in such record.
15.11 Each record of change must be dated and sequentially numbered. Each of the Public Body and the
Contractor will be entitled to an original executed counterpart of the record of variation.
15.12 Except as provided in any such record of variation, the Contract will continue in full force and effect.

16. Change in Laws and Regulations

16.1 Unless otherwise expressly agreed in the SCC, if, after the deadline for submission of the Bid, any
law, regulation, ordinance, order or bylaw having the force of law is enacted, promulgated, abrogated,
or changed in the Federal Democratic Republic of Ethiopia where the Site is located (which shall be
deemed to include any change in interpretation or application by the competent authorities) that
subsequently affects the Completion Date and/or the Contract Price, then such Contract Price shall
not be correspondingly increased or decreased and/or the Completion Date shall not be adjusted to
the extent that Contractor has thereby been affected in the performance of any of its obligations under
the Contract.

17. Taxes and Duties

17.1 Unless otherwise specified in the SCC, the Contractor shall bear and pay all taxes, duties, and levies
imposed on the Contractor, by all municipal, state or national government authorities, both within and
outside the Federal Democratic Republic of Ethiopia, in connection with the Works to be carried out
under the Contract,.

18. Force Majeure

18.1 For the purposes of the Contract, “Force Majeure” shall mean an event or events which are beyond
the reasonable control of a Contractor, and which makes a Contractor’s performance of its obligations
hereunder impossible or so impractical as reasonably to be considered impossible in the
circumstances, and includes:
(a) An official prohibition preventing the performance of a contract,
(b) A natural catastrophe such as an earthquake, fire, explosion, storm, floods, or other adverse
weather conditions, or
(c) International or civil war, or
(d) Other instances of Force Majeure identified as such by the civil code.
18.2 The following occurrences shall not be deemed to be cases of Force Majeure:
(a) A strike or lock-out taking of a party or affecting the branch of business in which he carries out
his activities where such strikes, lockouts or other industrial action are within the power of the
Party invoking Force Majeure to prevent, or

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 24


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(b) An increase or reduction in the price of raw materials necessary for the performance of the
contract, or
(c) The enactment of new legislation where by the obligations of the debtor becomes more onerous,
or
(d) Any event which is caused by the negligence or intentional action of a Contractor or such
Contractor’s Sub-Contractors or agents or employees; or
(e) Any event which a diligent Party could reasonably have been expected to both:
(i) Take into account from the effective date of the Contract; and
(ii) Avoid or overcome in the carrying out of its obligations; or
(f) Insufficiency of funds or failure to make any payment required hereunder.
18.3 The failure of a Contractor to fulfill any of its obligations hereunder shall not be considered to be a
breach of, or default under, the Contract insofar as such inability arises from an event of Force
Majeure, provided that the Contractor affected by such an event has taken all reasonable precautions,
due care and reasonable alternative measures, all with the objective of carrying out the terms and
conditions of the Contract.
18.4 A Party affected by an event of Force Majeure shall take all reasonable measures to
(a) Remove such Party’s inability to fulfill its obligations hereunder with a minimum of delay; and
(b) Minimize the consequences of any event of Force Majeure.
18.5 A Contractor affected by an event of Force Majeure shall notify the Public Body of such event as
soon as possible, and in any event not later than fourteen (14) days following the occurrence of such
event, providing evidence of the nature and cause of such event, and shall similarly give notice of the
restoration of normal conditions as soon as possible.
18.6 Any period within which a Contractor shall, pursuant to this Contract, complete any action or task,
shall be extended for a period equal to the time during which such Party was unable to perform such
action as a result of Force Majeure.
18.7 During the period of their inability to carry out the Works as a result of an event of Force Majeure,
the Contractor, upon instructions by the Public Body, shall either:
(a) Demobilize, in which case the Contractor shall be reimbursed for additional costs they
reasonably and necessarily incurred, and, if required by the Public Body, in reactivating the
Works; or
(b) Continue to perform his obligations under the Contract to the extent possible, in which case the
Contractor shall continue to be paid under the terms of this Contract and be reimbursed for
additional costs reasonably and necessarily incurred.
18.8 Not later than thirty (30) days after the Contractor, as the result of an event of Force Majeure, has
become unable to carry out the Works, the Parties shall consult with each other in good faith and use
all reasonable endeavors to agree appropriate terms to mitigate the effects of the Force Majeure Event
and facilitate the continued performance of the Contract.
18.9 In the case of disagreement between the Parties as to the existence or extent of Force Majeure, the
matter shall be settled according to GCC Clause 26.

19. Breach of Contract

19.1 Either party commits a breach of contract where it fails to discharge any of its obligations under the
specific contract.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 25


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

19.2 Where a breach of contract occurs, the party injured by the breach shall be entitled to the following
remedies:
(a) Compensation / Claim for liquidated damages as specified in GCC Clause 27; and/or
(b) Termination of the contract.
19.3 In any case where the Public Body is entitled to damages, it may deduct such Suspension damages
from any sums due to the Contractor or call on the appropriate guarantee.

20. Suspension

20.1 The Contractor shall, on the order of the Engineer, suspend the progress of the works or any part
thereof for such time or times and in such manner as the Engineer may consider necessary.
20.2 During the period of suspension, the Contractor shall take such protective measures as may be
necessary to safeguard the works, plant, equipment and site against any deterioration, loss or damage.
Additional expenses incurred in connection with such protective measures shall be added to the
contract price, unless such suspension is:
(a) otherwise provided for in the contract; or
(b) necessary by reason of some default of the Contractor; or
(c) necessary by reason of normal climatic conditions on site; or
(d) necessary for the safety or the proper execution of the works or any part thereof insofar as such
necessity does not arise from any act or default by the Engineer or the Public Body or from any
of the exceptional risks referred to in GCC Clause 44.
20.3 The Contractor shall not be entitled to such additions to the contract price unless he notifies the
Engineer, within 30 days after receipt of the order to suspend the works, of his intention to make a
claim for them.
20.4 The Engineer, after consultation with the Public Body and the Contractor, shall determine such extra
payment and/or extension of the period of performance to be made to the Contractor in respect of such
claim as shall, in the opinion of the Engineer, be fair and reasonable.
20.5 If the period of suspension exceeds 120 days and the suspension is not due to the Contractor's default,
the Contractor may, by notice to the Engineer, request permission to proceed within thirty (30) days
or terminate the contract.
20.6 Where the award procedure or implementation of the contract is vitiated by substantial errors or
irregularities or by suspected or proven fraud, the payments and/or implementation of the contract
shall be suspended. Where such errors, irregularities or fraud are attributable to the Contractor, the
Public Body may also refuse to make payments or may recover monies already paid, in proportion to
the seriousness of the errors, irregularities or fraud. The payments may also be suspended in cases
where there are suspected or established errors, irregularities or fraud committed by the Contractor in
the performance of another contract funded by the Federal Government of Ethiopia, which are likely
to affect the performance of the present contract

21. Termination
Termination by the Public Body
21.1 Termination shall be without prejudice to any other rights or powers under the contract of the Public
Body and the Contractor.
21.2 In addition to the grounds for termination defined in these General Conditions, the Public Body may,
by not less than thirty days written notice of termination to the Contractor stating the reason for

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 26


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

termination of the contract and the date on which such termination becomes effective. (except in the
event listed in paragraph (o) below, for which there shall be a written notice of not less than sixty
days), such notice to be given after the occurrence of any of the events specified in this GCC Sub-
Clause 21.2 (a) to (p), terminate the Contract if:
(a) The Contractor fails to carry out any or all of the Works within the period specified in the
Contract, or within any extension thereof granted by the Public Body pursuant to GCC Clause
73;
(b) The Contractor fails to remedy a failure in the performance of their obligations as specified in
a notice of suspension pursuant to GCC Clause 20 within thirty days of receipt of such notice
of suspension of assignment or within such further period as the Public Body may has
subsequently approved in writing;
(c) The Contractor becomes (or, if the Contractor consists of more than one entity, if any of its
Members becomes) insolvent or bankrupt or enters into any agreements with their creditors for
relief of debt or take advantage of any law for the benefit of debtors or go into liquidation or
receivership whether compulsory or voluntary, other than for a reconstruction or amalgamation;
(d) The Contractor fails to comply with any final decision reached as a result of direct informal
negotiation pursuant to GCC Sub-Clause 26.2 hereof;
(e) The Contractor is unable, as the result of Force Majeure, to carry out the Works for a period of
not less than sixty (60) days;
(f) The Contractor assigns the contract or sub-contracts without the authorization of the Public
Body;
(g) The Contractor has been guilty of grave professional misconduct proven by any means which
the Public Body can justify;
(h) The Contractor has been declared to be in serious breach of contract financed by the Federal
Democratic Republic of Ethiopia's budget for failure to comply with its contractual obligations.
(i) The Contractor has been engaged in corrupt or fraudulent practices in competing for or in
executing the Contract.
(j) Any organizational modification occurs involving a change in the legal personality, nature or
control of the Contractor, unless such modification is recorded in an addendum to the Contract;
(k) Any other legal disability hindering performance of the Contract occurs;
(l) The Contractor fails to provide the required guarantees or insurance, or the person providing
the underlying guarantee or insurance is not able to abide by its commitments.
(m) Where the procurement requirement of the Public Body changes for any apparent or obvious
reason;
(n) Where it emerges that the gap between the value of the Contract and the prevailing market price
is so wide that allowing the implementation of the contract to proceed places the Public Body
concerned at a disadvantage;
(o) The Public Body, in its sole discretion and for any reason whatsoever, decides to terminate the
Contract.
(p) The Contractor has delayed the completion of the Works by the number of days for which the
maximum amount of liquidated damages can be paid, as defined in the GCC Clause 27.1(b).
Termination by the Contractor
21.3 The Contractor may, by not less than thirty (30) days' written notice to the Public Body, of such notice
to be given after the occurrence of any of the events specified in GCC Sub-Clause 21.3 (a) to (d)
terminate the Contract if:

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 27


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(a) The Public Body fails to pay any money due to the Contractor pursuant to the Contract and not
subject to dispute pursuant to Clause 25, within forty-five (45) days after receiving written
notice from the Contractor that such payment is overdue;
(b) The Public Body is in material breach of its obligations pursuant to the Contract and has not
remedied the same within forty-five (45) days (or such longer period as the Contractor may
have subsequently approved in writing) following the receipt by the Public Body of the
Contractor’s notice specifying such breach;
(c) The Public Body suspends the progress of the works or any part thereof for more than 180 days,
for reasons not specified in the Contract, or not due to the Contractor's default.
(d) The Contractor is unable as the result of Force Majeure, to perform a material portion of the
Works for a period of not less than sixty (60) days; or
(e) The Public Body fails to comply with any final decision reached as a result of settlement of
disputes pursuant to GCC Clause 26 hereof.
Disputes About Events of Termination
21.4 If either Party disputes whether an event specified GCC Sub-Clauses 21.2 (a) to (n) or GCC Sub-
Clause 21.3 hereof has occurred, such Party may, within forty-five (45) days after receipt of notice of
termination from the other Party, refer the matter to settlement of disputes pursuant to GCC Clause
26 and this Contract shall not be terminated on account of such event except in accordance with the
terms of any resolution award.
21.5 In the event the Public Body terminates the Contract pursuant to the GCC Sub-Clause 21.2 (a) to (n)
the Public Body may complete the works himself or conclude any other contract with a third party at
the Contractor's own expense. However, the Contractor shall continue performance of the Contract to
the extent not terminated.
21.6 If the Public Body terminates the Contract in the event specified in GCC Sub-Clause 21.2 (o) the
notice of termination shall specify that termination is for the Public Body's convenience, the extent to
which performance of the Contractor under the Contract is terminated, and the date upon which such
termination becomes effective.

22. Payment upon Termination

22.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the
Engineer shall issue a certificate for the value of the work done and Materials ordered less advance
payments received up to the date of the issue of the certificate and less the percentage to apply to the
value of the work not completed, as indicated in the SCC. Additional Liquidated Damages shall not
apply. If the total amount due to the Public Body exceeds any payment due to the Contractor, the
difference shall be a debt payable to the Public Body.
22.2 If the Public Body terminates the Contract in the event specified in GCC Sub-Clause 21.2 (o) or
because of a fundamental breach of Contract by the Public Body, the Engineer shall issue a certificate
for the value of the work done, Materials ordered, the reasonable cost of removal of Equipment,
repatriation of the Contractor’s personnel employed solely on the Works, and the Contractor’s costs
of protecting and securing the Works, and less advance payments received up to the date of the
certificate.
22.3 In the event the Public Body terminates the Contract pursuant to the GCC Sub-Clause 21.2 (c)
termination will be without compensation to the Contractor, provided that such termination will not
prejudice or affect any right of action or remedy that has accrued or will accrue thereafter to the Public
Body.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 28


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

23. Arrangements on Termination

23.1 The Public Body and the Contractor agree that termination or expiry of the Contract shall not affect
either Party's obligations which the Contract provides shall survive the expiration or termination of
the Contract.
23.2 All Materials on the Site, Plant, Equipment, Temporary Works, and Works shall be deemed to be the
property of the Public Body if the Contract is terminated because of the Contractor’s default.
23.3 After termination or expiry all data, documents and records (whether stored electronically or
otherwise) relating in whole or in part to the provided Works shall be delivered by the Contractor to
the Public Body provided that the Contractor shall be entitled to keep copies thereof to the extent that
the information contained therein does not relate solely to the Works or to the extent that the
Contractor is required by law to maintain copies thereof or to the extent that the Contractor was
possessed of such data documents and records prior to the date of the Contract. In addition, the
Contractor shall co-operate fully with the Public Body during the handover leading to the termination
of the Contract. This co-operation shall extend to full access to all documents, reports, summaries and
any other information required to achieve an effective transition without disruption to routine
operational requirements.

24. Cessation of Rights and Obligations

24.1 Upon termination of the Contract pursuant to GCC Clauses 21, or upon the issue of the Final
Acceptance Certificate pursuant to GCC Clause 89 hereof, all rights and obligations of the Parties
hereunder shall cease, except
(a) Such rights and obligations as may have accrued on the date of termination or expiration;
(b) The obligation of confidentiality set forth in GCC Clause 28 hereof;
(c) The Contractor’s obligation to permit inspection, copying and auditing of their accounts and
records set forth in GCC Clause 56 hereof; and
(d) Any right which a Party may have under the Governing Law.

25. Cessation of Works

25.1 Upon termination of the Contract by notice of either Party to the other pursuant to GCC Clause 21 the
Contractor shall, immediately upon dispatch or receipt of such notice, take all necessary steps to bring
the Works to a close in a prompt and orderly manner, make the Site safe and secure, leave the Site as
soon as reasonably possible, and make every reasonable effort to reduce expenditures for this purpose
to a minimum.
25.2 The Engineer shall, as soon as is possible after termination, certify the value of the works and all sums
due to the Contractor as at the date of termination.
25.3 In the event of termination a report of work performed by the Contractor shall be drawn up by the
Engineer as soon as possible after inspection of the works, and inventory taken of temporary
structures, materials, plant and equipment. The Contractor shall be summoned to be present during
the inspection and the taking of the inventory. The Engineer shall also draw up statements of
emoluments still owed by the Contractor to workers employed by him in relation to the contract and
of sums owed by the Contractor to the Public Body.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 29


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

26. Settlement of Disputes

26.1 During any dispute, including a dispute as to the validity of the Contract, it is mutually agreed that
the Contractor shall continue its performance of the Contract (unless the Public Body requests in
writing that the Contractor does not do so).
26.2 The Public Body and the Contractor shall make every effort to resolve amicably by direct informal
negotiation any disagreement, controversy or dispute arising between them under or in connection
with the Contract or interpretation thereof.
26.3 If a dispute arises between the Public Body and the Contractor in relation to any matter which cannot
be resolved by the Engineer and the Contractor's Contract Manager either of them may refer such
dispute to the procedure described in GCC Sub-Clause 26.4.
26.4 In the second instance each of the Public Body and the Contractor shall appoint more senior
representatives than those referred to in Sub-Clause 26.3 to meet solely in order to resolve the matter
in dispute. Such meeting(s) shall be minuted and shall be chaired by the Public Body (but the chairman
shall not have a casting vote). Such meeting(s) shall be conducted in such manner and at such venue
(including a meeting conducted over the telephone) as to promote a consensual resolution of the
dispute in question at the discretion of the chairman.
26.5 If the Parties fail to resolve such a dispute or difference amicably within twenty-eight (28) days from
the commencement of such procedure, either party may require that the dispute be referred for
resolution through the courts in accordance with Ethiopian Law.
26.6 Only those Public Bodies that are allowed by law to proceed to arbitration can do so.

27. Liquidated Damages

27.1 Except as provided under GCC Clause 18, if the Contractor fails to carry out any or all of the Works
within the period specified in the Contract, the Public Body may without prejudice to all its other
remedies under the Contract, deduct from the Contract Price, as liquidated damages the following:
(a) A penalty of 0.1% or 1/1000 of the value of undelivered Service for each day of delay until
actual delivery or performance,
(b) The cumulative penalty to be paid by the Contractor shall not exceed 10% of the contract price.
27.2 If the delay in performing the contract affects its activities, the Public Body may terminate the contract
by giving advance notice to the Contractor pursuant to GCC Clause 21 without any obligation to wait
until the penalty reaches 10% of the value of the Contract.
27.3 If the Intended Completion Date is extended after liquidated damages have been paid, the Engineer
shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment
certificate.

28. Confidentiality

28.1 The Public Body and the Contractor shall keep confidential and shall not disclose to any third party
any documents, data, or other information furnished directly or indirectly by the other party hereto in
connection with the Contract, whether such information has been furnished prior to, during or
following completion or termination of the Contract if their disclosure would be contrary to law,
would impede law enforcement, would not be in public interest, would prejudice legitimate
commercial interest of the parties or would inhibit fair competition.. Notwithstanding the above, the
Contractor may furnish to its sub-contractors such documents, data, and other information it receives
from the Public Body to the extent required for the sub-contractor to perform its work under the

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 30


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Contract, in which event the Contractor shall obtain from such sub-contractor an undertaking of
confidentiality similar to that imposed on the Contractor under this Clause.
28.2 The Public Body shall not use such documents, data, and other information received from the
Contractor for any purposes unrelated to the Contract. Similarly, the Contractor shall not use such
documents, data, and other information received from the Public Body for any purpose other than
carrying out the Works in accordance with the Contract.
28.3 The obligation of a party under this Clause, however, shall not apply to any Confidential Information
that:
(a) The Public Body or Contractor need to share with any other institutions participating in the
financing of the Contract;
(b) Now or hereafter enters the public domain other than by breach of the Contract or other act or
omissions of that Party;
(c) Is obtained by a third party who is lawfully authorized to disclose such information;
(d) Can be proven to have been possessed by that party at the time of disclosure and which was not
previously obtained, directly or indirectly, from the other party; or
(e) Is authorized for release by the prior written consent of the other party.
28.4 The Parties shall not be prevented from using any general knowledge, experience or skills which were
in their possession prior to the commencement of the Contract;
28.5 The Contractor authorizes the Public Body to disclose the Confidential Information to such person(s)
as may be notified to the Contractor in writing by the Public Body from time to time to the extent only
as is necessary for the purposes of auditing and collating information so as to ascertain a realistic
market price for the Works carried out in accordance with the Contract, such exercise being commonly
referred to as "benchmarking". The Public Body shall use all reasonable endeavors to ensure that such
person(s) keeps the Confidential Information confidential and does not make use of the Confidential
Information except for the purpose for which the disclosure is made. The Public Body shall not
without good reason claim that the lowest price available in the market is the realistic market price.
28.6 The Contractor agrees that:
(a) Subject to GCC Sub-Clause 28.6 (b), the decision on whether any exemption applies to a
request for disclosure of recorded information is a decision solely for the Public Body;
(b) Where the Public Body is managing a request as referred to in GCC Sub-Clause 28.6 (a), the
Contractor shall co-operate with the Public Body making the request and shall respond within
five (5) working days of any request by it for assistance in determining how to respond to a
request for disclosure.
28.7 The Contractor shall procure that its sub-contractors shall provide the Public Body with a copy of all
information in its possession or power in the form that the Public Body requires within five (5)
working days (or such other period as the Public Body may specify) of the Public Body requesting
that Information.
28.8 The Public Body may consult the Contractor in relation to any request for disclosure of the
Contractor's Confidential Information in accordance with all applicable guidance.
28.9 The above provisions of this Clause shall not in any way modify any undertaking of confidentiality
given by either of the parties hereto prior to the date of the Contract.
28.10 This GCC Clause 28 shall remain in force without limit in time in respect of Confidential Information
which comprises Personal Data. Except as aforesaid and unless otherwise expressly set out in the
Contract, this GCC Clause 28 shall remain in force for a period of 3 years after the termination or
expiry of this Contract.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 31


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

28.11 In the event that the Contractor fails to comply with this GCC Clause 28, the Public Body reserves
the right to terminate the Contract by notice in writing with immediate effect.

29. Miscellaneous

29.1 Any decision, act or thing that the Public Body is required or authorized to take or do under the
Contract may be taken or done by any person authorized, either generally or specifically, by the Public
Body to take or do that decision, act or thing, provided that upon receipt of a written request the Public
Body shall inform the Contractor of the name of any person so authorized.
29.2 The Contractor may from time to time upon the request of the Public Body, execute any additional
documents and do any other acts or things which may reasonably be required to implement the
provisions of the Contract.
29.3 Any provision of the Contract which is held to be invalid or unenforceable in any jurisdiction shall be
ineffective to the extent of such invalidity or unenforceability without invalidating or rendering
unenforceable the remaining provisions hereof and any such invalidity or unenforceability in any
jurisdiction shall not invalidate or render unenforceable such provisions in any other jurisdiction.
29.4 The failure by the Public Body and Contractor to insist upon the strict performance of any provision,
term or condition of the Contract or to exercise any right or remedy consequent upon the breach
thereof shall not constitute a waiver of any such breach or any subsequent breach of such provision,
term or condition.
29.5 Each Party shall bear its own expenses in relation to the preparation, execution and implementation
of the Contract including all costs legal fees and other expenses so incurred.
29.6 The Contractor warrants represents and undertakes to the Public Body that there are no pending or
threatened actions or proceedings before any court or administrative agency which would materially
adversely affect the financial condition, business or operations of the Contractor and that there are no
material contracts existing to which the Contractor is a party which prevent it from entering into the
Contract; and that the Contractor has satisfied itself as to the nature and extent of the risks assumed
by it under the Contract and gathered all information necessary to perform its obligations under the
Contract and all other obligations assumed by it.
29.7 The rights and remedies provided in the Contract are cumulative and not exclusive of any rights or
remedies provided by any other contract or document. In this provision "right" includes any power,
privilege, remedy, or proprietary or security interest.
C. Obligations of the Public Body
30. Assistance and Supply of Documents

30.1 The Contractor may request the assistance of the Public Body in obtaining copies of laws, regulations
and information on local customs, orders or by-laws of the Federal Democratic Republic of Ethiopia,
which may affect the Contractor in the performance of his obligations under the Contract. The Public
Body may provide the assistance requested to the Contractor at the Contractor's cost.
30.2 Unless otherwise specified in the SCC, the Public Body may make all efforts necessary to facilitate
the procurement by the Contractor of:
(a) all required visas and permits, including work and residence permits, and such other documents
as shall be necessary to enable the Contractor, Sub-Contractors or Personnel to carry out the
Works;
(b) any such other assistance as may be specified in the SCC.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 32


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

30.3 Except where otherwise provided in the SCC, within 30 days of the signing of the Contract, the
Engineer shall provide to the Contractor, free of charge, a copy of the drawings prepared for the
implementation of tasks as well as two copies of the specifications and other contract documents. The
Contractor may purchase additional copies of these drawings, specifications and other documents,
insofar as they are available. Upon the final acceptance, the Contractor shall return to the Engineer all
drawings, specifications and other contract documents.
30.4 Unless it is necessary for the purposes of the Contract, the drawings, specifications and other
documents provided by the Public Body shall not be used or communicated to a third party by the
Contractor without the prior consent of the Engineer.
30.5 The Engineer shall have authority to issue to the Contractor administrative orders incorporating such
supplementary documents and instructions as shall be necessary for the proper and adequate execution
of the works and the remedying of any defects therein.

31. Access to the Site

31.1 The Public Body shall, in due time and in conformity with the progress of the works, place the site
and access thereto at the disposal of the Contractor in accordance with the program of implementation
of tasks referred to in these GCC. If possession of a part is not given by the date stated in the approved
work program, the Public Body will be deemed to have delayed the start of the relevant activities, and
this will be a Compensation Event.
31.2 The Contractor shall allow the Engineer and any person authorized by the Engineer access to the Site
and to any place where work in connection with the Contract is being carried out or is intended to be
carried out.
31.3 Any land procured for the Contractor by the Public Body shall not be used by the Contractor for
purposes other than the implementation of tasks.
31.4 The Contractor shall preserve any premises placed at his disposal in a good state while he is in
occupation and shall, if so required by the Public Body or the Engineer, restore them to their original
state on completion of the contract, taking into account normal wear and tear.
31.5 The Contractor shall not be entitled to any payment for improvements resulting from work carried out
on his own initiative.

32. Payment

32.1 In consideration of the Works performed by the Contractor under this Contract, the Public Body shall
make to the Contractor such payments and in such manner as is provided by GCC Paragraph E of this
Contract.

33. Delayed Payments to the Contractor's Staff

33.1 Where there is a delay in the payment to the Contractor's employees of wages and salaries owing and
of the allowances and contributions laid down by the law of the Federal Democratic Republic of
Ethiopia, the Public Body may give notice to the Contractor that within 15 days of the notice the
Contractor has to pay such wages, salaries, allowances and contributions.
D. Obligations of the Contractor

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 33


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

34. General Obligations

34.1 The Contractor shall, with due care and diligence, and in accordance with the provisions of the
Contract, design the works to the extent stated in the Contract, and execute, complete and remedy any
defects in the works. The Contractor shall provide all control and supervision of the works, personnel,
materials, plant, equipment and all other items, whether of a temporary or permanent nature required
in and for such design, execution, completion and remedying of any defects, insofar as specified in,
or can be reasonably inferred from, the Contract.
34.2 The Contractor shall take full responsibility for the adequacy, stability and safety of all operations and
methods of construction under the Contract.
34.3 The Contractor shall respect and abide by all laws and regulations in force in the Federal Democratic
Republic of Ethiopia and shall ensure that his personnel, their dependants, and his local employees
also respect and abide by all such laws and regulations. The Contractor shall indemnify the Public
Body against any claims and proceedings arising from any infringement by the Contractor, its Sub-
Contractors or their employees of such laws and regulations.
34.4 The Contractor shall ensure that Works conform to applicable environmental and quality standards,
that no chemical or other product/equipment is used in such a way as to cause negative impact on the
environment in general and occupational health hazards and shall employ the most recent technology,
safe and effective equipment, machinery, materials and methods, as necessary.
34.5 The Contractor shall obtain the Public Body's prior approval in writing before taking any of the
following actions:
(a) Entering into a subcontract for carrying out any part of the Works, it being understood that the
Contractor shall remain fully liable for carrying out the Works by the Sub-Contractor;
(b) Any other action that may be specified in the SCC.
34.6 The Contractor shall comply with any administrative orders given by the Engineer. Where the
Contractor considers that the requirements of an administrative order go beyond the authority of the
specific Engineer or of the scope of the Contract, it shall, on pain of being time-barred, notify the
specific contract manager, explaining its opinion, within 30 days after receipt thereof. Execution of
the administrative order shall not be suspended because of this notice.
34.7 The Contractor shall treat all documents and information received in connection with the contract as
private and confidential, and shall not, save in so far as may be necessary for the purposes of the
performance thereof, publish or disclose any particulars of the contract without the prior consent in
writing of the Public Body or the specific contract manager after consultation with the Public Body.
If any disagreement arises as to the necessity for any publication or disclosure for the purpose of the
contract, the decision of the Public Body shall be final.

35. Eligibility

35.1 The Contractor and its Sub-Contractors shall have the nationality of an eligible country pursuant to
Section 5 of the Bidding Documents. A Contractor or Sub-Contractor shall be deemed to have the
nationality of a country if it is a citizen or constituted, incorporated, or registered, and operates in
conformity with the provisions of the laws of that country.
35.2 The Contractor and its Sub-Contractors shall provide Personnel who shall be citizens of eligible
countries and use goods with their origin from an eligible country.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 34


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

36. Code of Conduct

36.1 The Contractor shall, at all times, act loyally and impartially in respect of any matter relating to this
Contract and as a faithful adviser to the Public Body in accordance with the rules and/or code of
conduct of its profession as well as with appropriate discretion. The Contractor shall, in particular, at
all times refrain from making any public statements concerning the Works without the prior approval
of the Public Body, and from engaging in any activity which conflicts with its obligations towards the
Public Body under the contract. It shall not commit the Public Body without its prior written consent,
and shall, where appropriate, make this obligation clear to third parties.
36.2 If the Contractor or any of its Sub-Contractors, personnel, agents or servants offers to give or agrees
to offer or to give or gives to any person, any bribe, gift, gratuity or commission as an inducement or
reward for doing or forbearing to do any act in relation to the contract or any other contract with the
Public Body, or for showing favor or disfavor to any person in relation to the contract or any other
contract with the Public Body, then the Public Body may terminate the contract, without prejudice to
any accrued rights of the Contractor under the contract.
36.3 The payments to the Contractor under the contract shall constitute the only income or benefit it may
derive in connection with the contract and neither it nor its personnel shall accept any commission,
discount, allowance, indirect payment or other consideration in connection with, or in relation to, or
in discharge of, its obligations under the contract.
36.4 The Contractor shall not have the benefit, whether directly or indirectly, of any royalty, gratuity or
commission in respect of any patented or protected article or process used in or for the purposes of
the contract or the project, without the prior written approval of the Public Body.
36.5 The Contractor and its staff shall maintain professional secrecy, for the duration of the contract and
after completion thereof. In this connection, except with the prior written consent of the Public Body,
neither the Contractor nor the personnel employed or engaged by it shall at any time communicate to
any person or entity any confidential information disclosed to them or discovered by them, or make
public any information as to the recommendations formulated in the course of or as a result of the
Works. Furthermore, they shall not make any use prejudicial to the Public Body, of information
supplied to them and of the results of studies, tests and research carried out in the course and for the
purpose of performing the contract.
36.6 The execution of the contract shall not give rise to unusual commercial expenses. If such unusual
commercial expenses emerge, the contract will be terminated. Unusual commercial expenses are
commissions not mentioned in the contract or not stemming from a properly concluded contract
referring to the contract, commissions not paid in return for any actual and legitimate service,
commissions remitted to a tax haven, commissions paid to a recipient who is not clearly identified or
commission paid to a company which has every appearance of being a front company.
36.7 The Contractor shall supply to the Public Body on request supporting evidence regarding the
conditions in which the contract is being executed. The Public Body may carry out whatever
documentary or on-the spot checks it deems necessary to find evidence in case of suspected unusual
commercial expenses.

37. Control and Supervision of the Works

37.1 The Contractor shall himself control and supervise the works or shall appoint a Contract Manager to
do so. Such appointment shall be submitted to the Engineer for approval.
37.2 The Contract Manager shall be suitably qualified in accordance with the Schedule of Requirements.
In addition a work history/biography will be submitted to the Engineer for approval.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 35


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

37.3 The Contractor shall forthwith give notice in writing to the Engineer of the identity of the person
appointed as Contract Manager for approval. The approval may at any time be withdrawn. Should the
Engineer refuse to approve, or withdraw approval of the appointment, he shall set out the grounds on
which his decision is based, and the Contractor shall submit an alternative appointment without delay.
The address of the Contractor's representative shall be deemed to be the address for service given by
the Contractor.
37.4 If the Engineer withdraws his approval of the Contractor's Contract Manager, the Contractor shall, as
soon as is practicable, after receiving notice of such withdrawal, remove the Contract Manager from
the works and replace him with another Contract Manager approved by the Engineer.
37.5 The Contractor's Contract Manager shall have full authority to make any decision necessary for the
execution of the works, to receive and carry out administrative orders and to countersign the work
register referred to in GCC Clause 79 or attachment, where appropriate. In any event, the Contractor
shall be responsible for ensuring that the works are carried out satisfactorily including ensuring that
the specifications and administrative orders are adhered to by his own employees and by his sub-
Contractors and their employees.
37.6 Any notice, information, instruction or other communication given or made to the Contract Manager
shall be deemed to have been given or made to the Contractor.
37.7 The Contractor shall inform the Engineer of the identity of any person authorized to act for any period
as deputy for the Contract Manager before the start of that period.
37.8 The Contractor shall provide a sufficient complement of supervisory staff in addition to the Contract
Manager, to ensure that the Contractor’s staff engaged in and about the provision of the Works at the
Site are adequately supervised and properly perform their duties at all times.
37.9 All persons appointed to managerial and supervisory positions in accordance with the Schedule of
Requirements must be to the acceptance of the Engineer who will have the right to veto the
appointment of any candidate who is deemed to be unsuitable.

38. Personnel

38.1 The persons employed by the Contractor must be sufficient in number, and permit the optimum use
of the human resources. Such employees must have the skills and experience necessary to ensure due
progress and satisfactory execution of the works.
38.2 The Contractor shall make his own arrangements for the engagement of all staff and labor. The rates
of remuneration and the general working conditions, as laid down by the law of the Federal democratic
Republic of Ethiopia, shall apply as a minimum to employees on the Site.
38.3 The Contractor shall employ the key personnel named in the Schedule of Key Personnel, as referred
to in the SCC, to carry out the functions stated in the Schedule of Requirements or other personnel
approved by the Engineer. The Engineer will approve any proposed replacement of key personnel
only if their relevant qualifications and abilities are substantially equal to or better than those of the
personnel listed in the Schedule of Requirements.
38.4 The Contractor acknowledges that the Key Personnel are essential to the proper provision of the
Works to the Public Body. The Contractor shall ensure that the role of any Key Personnel is not vacant
for any longer than [10] Working Days and that any replacement shall be as or more qualified and
experienced as the previous incumbent of such role and is fully competent to carry out the tasks
assigned to the role of the member of Key Personnel whom he or she has replaced.
38.5 The Contractor shall immediately replace all employees indicated by the Engineer, in a letter stating
reasons, as likely to jeopardize the satisfactory execution of the works

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 36


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

38.6 If the Engineer asks the Contractor to remove a person who is a member of the Contractor’s staff or
work force, stating the reasons, the Contractor shall ensure that the person leaves the Site within seven
days and has no further connection with the work in the Contract.
38.7 The Public Body shall not be liable for the cost of replacing any member of the Contractor’s staff and
the Contractor shall indemnify the Public Body against all Employee Liabilities that may arise in this
respect.

39. Indemnification and Limitation of Liability

39.1 At its own expense, the Contractor shall indemnify, protect and defend, the Public Body, its agents
and employees, from and against all actions, claims, losses or damage arising from any act or omission
by the Contractor in the performance of the Works, including any violation of any legal provisions,
or rights of third parties, in respect of patents, trade marks and other forms of intellectual property
such as copyrights.
39.2 At its own expense, the Contractor shall indemnify, protect and defend the Public Body, its agents
and employees, from and against all actions, claims, losses or damages arising out of the Contractor’s
failure to perform its obligations provided that:
(a) The Contractor is notified of such actions, claims, losses or damages not later than 30 days after
the Public Body becomes aware of them;
(b) The ceiling on the Contractor’s liability shall be limited to an amount equal to total Contract
Price as stated in the SCC, but such ceiling shall not apply to actions, claims, losses or damages
caused by the Contractor’s willful misconduct;
(c) The Contractor’s liability shall be limited to actions, claims, losses or damages directly caused
by such failure to perform its obligations under the contract and shall not include liability
arising from unforeseeable occurrences incidental or indirectly consequential to such failure.
39.3 The aggregate liability of the Contractor to the Public Body shall not exceed the total contract value.
39.4 The Contractor shall have no liability whatsoever for actions, claims, losses or damages occasioned
by:
(a) The Public Body omitting to act on any recommendation, or overriding any act, decision or
recommendation, of the Contractor, or requiring the Contractor to implement a decision or
recommendation with which the Contractor disagrees or on which it expresses a serious
reservation; or
(b) The improper execution of the Contractor’s instructions by agents, employees or independent
Contractors of the Public Body.
39.5 The Contractor shall remain responsible for any breach of its obligations under the contract for such
period after the Works have been performed as may be determined by the law governing the contract.

40. Insurance to be Taken Out by the Contractor

40.1 The Contractor shall provide, in the joint names of the Public Body and the Contractor, insurance
cover against loss or damage for which he is liable under the contract in the amounts and deductibles
stated in the SCC. Such insurance shall, unless the SCC provide otherwise, cover:
(a) the Works, together with Materials and Plant for incorporation therein, to the full replacement
cost against all loss or damage from whatever cause arising other than from Force Majeure or
risks attributable under the contract to the Public Body;
(b) an additional sum of 15% of such replacement cost, or as may be specified in the SCC, to cover
any additional costs of and incidental to the rectification of loss or damage including
SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 37
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

professional fees and the cost of demolishing and removing any part of the works and of
removing debris of whatever nature;
(c) the Contractor's Equipment and other things brought onto the Site by the Contractor, for a sum
sufficient to provide their replacement at the Site.
40.2 The Contractor shall take out insurance covering his liability with regard to industrial accidents and
civil liabilities to any person employed by him on the works, to the Public Body and any employee of
that authority, arising from the execution of the works. Such liability shall be unlimited in the case of
personal injuries.
40.3 The Contractor shall take out insurance covering liability with regard to risks and civil liability
resulting from an act or omission attributed to him, to his legal successors or agents. Such insurance
shall be for at least the amount stated in the SCC. Furthermore, he shall ensure that all his sub-
contractors have taken out a similar insurance.
40.4 By requiring such insurance, Public Body shall not be deemed or construed to have assessed the risk
that may be applicable to the Contractor under this Contract. The Contractor shall assess its own risks
and if deemed to be appropriate and/or prudent, should maintain adequate limits and/or broader
insurance coverage than that stipulated above. The Contractor is not relieved of any liability or other
obligations assumed or pursuant to the Contract by reason of its failure to obtain or maintain insurance
in sufficient amounts, duration, or types.
40.5 Insurance shall be provided at the Contractor’s expense and shall not be charged directly to the Public
Body.
40.6 All the insurance referred to in this Clause shall be taken out within 30 days of the notification of the
award of the Contract, and shall be subject to approval by the Public Body. Such insurance shall take
effect from the commencement of the Works and remain in force until final acceptance of the Works.
40.7 The Public Body shall be notified by the Contractor or its Insurance Carrier at least 30 days prior to
any material change to or cancellation of any of insurance coverage.
40.8 Prior to the commencement of the Works under this Contract, the Contractor or its Insurance Carrier
shall provide a Certificate(s) of Insurance (COI) evidencing compliance with all requirements for
insurance coverage. The COI shall be submitted to the Public Body for review and approval. For the
duration of the Contract, the Contractor or its Insurance Carrier shall provide updated COI’s to
evidence renewals or other changes to insurance policies or coverage, and payment of the current
premiums whenever they are required to do so by the Public Body or the Engineer.
40.9 Notwithstanding the obligations of the Contractor to insure in accordance with this Clause, the
Contractor shall be solely liable and shall indemnify the Public Body and the Engineer against any
claims for damage to property or personal injuries arising from the execution of the works by the
Contractor, his sub-contractors and employees in connection with the Works

41. Program of Implementation of Tasks

41.1 Completing the work program given as part of the Bid, the Contractor shall within the time stated in
the SCC provide the Engineer with a program of implementation of the tasks, broken down by activity
and by month and include the following information:
(a) the order in which the Contractor proposes to carry out the works;
(b) the time limits within which submission and approval of the drawings are required;
(c) an organization chart containing the names, qualifications and curricula vitae of the staff
responsible for the Site,

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 38


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(d) a general description of the method including the sequence, by month and by nature which the
Contractor proposes to carry out the works;
(e) a plan for the setting out and organization of the Site, and
(f) such further details and information as the Engineer may reasonably require.
41.2 The Engineer shall return these documents to the Contractor with his approval or any relevant remarks
within ten days of receipt, except where the Engineer, within those ten days, notifies the Contractor
of his wish for a meeting.
41.3 An update of the program shall be a program showing the actual progress achieved on each activity
and the effect of the progress achieved on the timing of the remaining work, including any changes
to the sequence of the activities.
41.4 The Contractor shall submit to the Engineer for approval an updated program at intervals no longer
than the period stated in the SCC. If the Contractor does not submit an updated Program within this
period, the Engineer may withhold the amount stated in the SCC from the next payment certificate
and continue to withhold this amount until the next payment after the date on which the overdue
Program has been submitted.
41.5 The approval of the program by the Engineer shall not relieve the Contractor from any of his
obligations under the contract. The Contractor may revise the program and submit it to the Engineer
again at any time. A revised program shall show the effect of modifications and Compensation Events.
41.6 No material alteration to the program shall be made without the approval of the Engineer. If, however,
the progress of the works does not conform to the program, the Engineer may instruct the Contractor
to revise the program and submit the revised program to him for approval.

42. Contractor's Drawings

42.1 The Contractor shall submit to the Engineer for approval:


(a) Such drawings, documents, samples and /or models as may be specified in the contract within
the time limits laid down therein or in the program of implementation of tasks;
(b) Such drawings as the Engineer may reasonably require for the implementation of tasks.
(c) In the case of bridges and other reinforced concrete structures, the Contractor shall carry out
the requisite soil surveys before commencing work on the foundations. The Contractor must
submit the results of these surveys and the calculations for the foundations, in triplicate, to the
Engineer at least one month before commencing construction of the works in question.
(d) The Contractor shall prepare, at its own expense, all design and construction drawings and other
documents and objects necessary for the proper execution of the Contract, and in particular
drawings and design calculations and the reinforcement drawings for reinforced concrete
structures. The Contractor shall submit, in triplicate, construction, design and reinforcement
drawings, design calculations and any other documents or objects it is to provide for the
Engineer’s approval at least one month before commencing construction of the works in
question.
Within 15 days of receiving the drawings, design calculations, objects and other documents required
under (c) and (d), the Engineer shall return them to the Contractor with either his endorsement or his
remarks.
42.2 If the Engineer fails to notify his decision of approval referred to in GCC Clause 41.1 within the time
limits referred to in the contract or the approved program of implementation of tasks, such drawings,
documents, samples or models shall be deemed to be approved at the end of the time limits specified.
If no time limit is specified, they shall be deemed to be approved 30 days after receipt.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 39


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

42.3 Approved drawings, documents, samples and models shall be signed or otherwise identified by the
Engineer and shall not be departed from except as otherwise instructed by the Engineer. Any
Contractor's drawings, documents, samples or models which the Engineer fails to approve, shall be
forthwith modified to meet the requirements of the Engineer and resubmitted by the Contractor for
approval. Within 15 days of being notified of the Engineer’s remarks, the Contractor shall make the
requisite corrections, adjustments etc. to the documents, drawings, design calculations etc. The
corrected or adjusted documents, drawings, design calculations etc. shall be resubmitted for the
Engineer’s approval under the same procedure.
42.4 The Contractor shall supply additional copies of approved drawings in the form and number stated in
the contract or in subsequent administrative orders.
42.5 The approval of the drawings, documents, samples or models by the Engineer shall not relieve the
Contractor from any of his obligations under the contract.
42.6 The Engineer shall have the right at all reasonable times to inspect all contract drawings, documents,
samples or models at the Contractor's premises.
42.7 Before provisional acceptance of the works, the Contractor shall supply operation and maintenance
manuals together with drawings, which shall be in such detail as will enable the Public Body to
operate, maintain, adjust and repair all parts of the works. Unless otherwise stated in the Special
Conditions, the manuals and drawings shall be in the language of the Contract. The works shall not
be considered to be completed for the purpose of provisional acceptance until such manuals and
drawings have been supplied to the Public Body.

43. Sufficiency of Bid Prices

43.1 The Contractor shall be deemed to have inspected and examined the Site and its surroundings and to
have satisfied himself before submitting his Bid, as to the nature of the ground and sub-soil, and to
have taken into account the form and nature of the Site, the extent and nature of the work and materials
necessary for the completion of the works, the means of communication with and access to the site,
the accommodation he may require and in general to have obtained for himself all necessary
information as to risks, contingencies and all other circumstances influencing or affecting his tender.
43.2 The Contractor shall be deemed to have satisfied himself before submitting his tender as to the
correctness and sufficiency of the tender and of the rates and prices stated in the bill of quantities or
price schedule which shall, except in so far as it is otherwise provided in the Contract, cover all his
obligations under the contract.
43.3 Since the Contractor is deemed to have determined his prices on the basis of his own calculations,
operations and estimates, he shall carry out without additional charge any work which is the subject
of any item whatsoever in his tender for which he neither indicates a unit price nor a firm sum.

44. Exceptional Risks

44.1 If during the execution of the works the Contractor encounters artificial obstructions or physical
conditions which could not reasonably have been foreseen by an experienced Contractor, and if the
Contractor is of the opinion that additional costs will be incurred and/or an extension of the period of
implementation of the tasks will be necessary as a result of this, he shall give notice to the Engineer
in accordance with GCC Clauses 69 and/or 73. The Contractor shall specify in such notice the artificial
obstructions and/or physical conditions, giving details of the anticipated effects thereof, the measures
he is taking or intends to take and the extent of the anticipated delay in or interference with the
execution of the works.
44.2 Following receipt of the notice, the Engineer may inter alia:

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 40


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(a) Require the Contractor to provide an estimate of the cost of the measures he is taking or intends
to take;
(b) Approve measures referred to in GCC Sub-Clause 44.2 (a) with or without modification;
(c) Give written instructions as to how the artificial obstructions or physical conditions are to be
dealt with;
(d) Order a modification, a suspension, or termination of the contract.
44.3 To the extent that the Engineer shall decide that the whole or part of the said artificial obstructions or
physical conditions could not reasonably have been foreseen by an experienced Contractor, the
Engineer shall:
(a) take into account any delay suffered by the Contractor as a result of such obstructions or
conditions in determining any extension of the period of implementation of tasks to which the
Contractor is entitled under GCC Clause 73; and/or
(b) in case of artificial obstructions or physical conditions other than weather conditions, determine
additional payments due to the Contractor in accordance with GCC Clause 69.
44.4 Weather conditions shall not entitle the Contractor to claims under GCC Clause 69.
44.5 If the Engineer decides that the artificial obstructions or physical conditions could, in whole or in part,
have been reasonably foreseen by an experienced Contractor, he shall so inform the Contractor as
soon as practicable.

45. Health and Safety on Sites

45.1 The Contractor shall have the right to forbid access to the Site to any person not involved in the
performance of the contract, with the exception of persons authorized by the Engineer or the Public
Body.
45.2 The Contractor shall ensure the safety on sites during the whole period of execution and shall be
responsible for taking the necessary steps, in the interests of his employees, agents of the Public Body
and third parties, to prevent any loss or accident which may result from carrying out the works.
45.3 The Contractor shall take all essential steps, on his own responsibility and at his expense, to ensure
that existing structures and installations are protected, preserved and maintained. He shall be
responsible for providing and maintaining at his expense all lighting, protection, fencing and security
equipment which proves necessary for the proper implementation of the tasks or which may
reasonably be required by the Engineer.
45.4 If, during the implementation of the tasks, urgent measures are necessary to obviate any risk of
accident or damage or to ensure security following any accident or damage, the Engineer shall give
formal notice to the Contractor to do what is necessary. If the Contractor is unwilling or unable to
undertake the necessary measures, the Engineer may carry out the work at the expense of the
Contractor to the extent that the Contractor is liable.
45.5 While carrying out the Works, the Contractor shall comply, and shall ensure that its employees
comply with, the requirements of relevant Health and Safety and other relevant legislation,
45.6 The Contractor shall nominate a Health and Safety Representative to liaise with the Engineer on all
Health and Safety matters.
45.7 The Contractor’s staff shall follow a system of accident recording in accordance with the Contractor’s
own accident reporting procedures.
45.8 All notifiable accidents shall immediately be brought to the attention of the Engineer.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 41


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

45.9 The Contractor shall ensure the co-operation of its personnel in all prevention measures designed
against fire, or any other hazards, and shall notify the Public Body of any change in the Contractor's
working practices or other occurrences likely to increase such risks or to cause new hazards.
45.10 The Contractor shall provide such first aid facilities and ensure that his staffs abide by such first aid
procedures as shall be required by the Public Body.

46. Safeguarding Adjacent Properties

46.1 On his own responsibility and at his expense, the Contractor shall take all the precautions required by
good construction practice and by the prevailing circumstances to safeguard adjacent properties and
avoid causing any abnormal disturbance therein.
46.2 The Contractor shall indemnify the Public Body against the financial consequences of all claims by
neighboring landowners or residents to the extent that the Contractor is liable and to the extent that
the damage to adjacent properties is not the result of a hazard created through the design or method
of construction imposed by the Public Body or the Engineer upon the Contractor

47. Interference with Traffic

47.1 The Contractor shall ensure that the works and installations do not cause damage to, or obstruct traffic
on, communication links such as roads, railways, waterways and airports, except as permitted under
the SCC. He shall, in particular, take account of weight restrictions when selecting routes and vehicles.
47.2 Any special measures which the Contractor considers necessary or which are specified in the SCC or
which are required by the Public Body in order to protect or strengthen sections of roads, tracks or
bridges, shall be at the expense of the Contractor, whether or not they are carried out by the Contractor.
The Contractor shall inform the Engineer of any special measures he intends to take before carrying
them out. The repair of any damage caused to roads, tracks or bridges by the transport of materials,
plant or equipment shall be at the expense of the Contractor.

48. Cables and Conduits

48.1 Where, in the course of carrying out the works, the Contractor encounters bench-marks indicating the
course of underground cables, conduits and installations, he shall keep such bench-marks in position
or replace them, should execution of the works have necessitated their temporary removal. Such
related operations require the authorization of the Engineer.
48.2 The Contractor shall be responsible for the preservation, removal and replacement, as the case may
be, of the cables, conduits and installations specified by the Public Body in the contract and for the
cost thereof.
48.3 Where the presence of cables, conduits and installations has not been specified in the contract but is
revealed by bench-marks and references, the Contractor shall be under a general duty of care and
similar obligations regarding preservation, removal and replacement to those set out above. In this
case, the Public Body shall compensate him for expenditure, to the extent that such work is necessary
for the execution of the contract.
48.4 However, the obligations to remove and replace cables, conduits and installations and the expenditure
resulting therefrom shall not be the responsibility of the Contractor if the Public Body decides to
accept that responsibility. The same shall apply where this obligation and the expenditure resulting
therefrom devolve upon another specialist administration or an agent.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 42


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

48.5 When any work on the site is likely to cause disturbances in or damage to a public utility service, the
Contractor shall immediately inform the Engineer in writing, giving a reasonable period of notice so
that suitable measures can be taken in time to allow work to continue normally.

49. Setting-out of the Works

49.1 The Contractor shall be responsible for:


(a) the accurate setting-out of the Works in relation to original marks, lines and levels of reference
given by the Engineer;
(b) the correctness, of the position, levels, dimensions and alignment of all parts of the Works; and
(c) the provision of all necessary instruments, appliances and labor in connection with the
foregoing responsibilities.
49.2 If, at any time during the execution of the Works, any error appears in the position, levels, dimensions
or alignment of any part of the Works, the Contractor, shall, if the Engineer so requires, at the
Contractor's cost, rectify such error to the satisfaction of the Engineer, unless such error is based on
incorrect data supplied by the Engineer, in which case the Public Body shall be responsible for the
cost of rectification.
49.3 The checking of any setting-out or of any line or level by the Engineer shall not in any way relieve
the Contractor of his responsibility for the accuracy thereof and the Contractor shall carefully protect
and preserve all bench-marks, sight-rails, pegs and other items used in setting-out the Works.

50. Demolished Materials

50.1 Where the contract includes demolition work, materials and articles obtained therefrom shall, unless
the SCC and /or the law of the Federal Democratic Republic of Ethiopia otherwise provide and subject
to the provisions of GCC Clause 51, be the property of the Contractor.
50.2 If the SCC reserve to the Public Body the right of ownership of materials or all or part of the articles
obtained from the demolition work, the Contractor shall take all the necessary precautions to ensure
that these are preserved. He shall be liable for any destruction of, or damage to, such materials or
articles caused by him or his agents.
50.3 Irrespective of the use to which the Public Body intends to put the materials or articles, in respect of
which he reserves the right of ownership, all costs incurred in transporting and storing them and all
warehouse charges at the place indicated by the Engineer shall be borne by the Contractor for any
carriage not exceeding 100 meters.
50.4 Except where the SCC provide otherwise, the Contractor shall, at his expense, progressively remove
rubble and other demolition materials, rubbish and debris from the Site.

51. Discoveries

51.1 Discoveries of any interest whatsoever made during excavation or demolition work shall be brought
immediately to the attention of the Engineer. The Engineer shall decide how such discoveries are to
be dealt with, taking due account of the law of the Federal Democratic Republic of Ethiopia.
51.2 The Public Body reserves the right of ownership of materials found during the excavation and
demolition work carried out on land belonging to him, subject to compensating the Contractor for any
special efforts.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 43


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

51.3 Artifacts, antiquities and natural, numismatic, or other objects which are of scientific interest, and also
rare objects or objects made of precious metals found during excavation or demolition work shall be
the property of the Public Body.
51.4 In the event of disagreements, the Public Body shall have sole authority to decide as to the
qualifications set out in GCC Clauses 51.1 and 51.3.

52. Temporary Works

52.1 The Contractor shall carry out at his expense all the temporary works to enable the Works to be carried
out. He shall submit specification and drawings showing the proposed temporary work to the
Engineer, who is to approve them if they comply with the specification and drawings. The Contractor
shall take into account any observations made to him by the Engineer while assuming responsibility
for these drawings.
52.2 The Contractor shall be responsible for design of Temporary Works.
52.3 The Engineer’s approval shall not alter the Contractor’s responsibility for design of the temporary
works.
52.4 The Contractor shall obtain approval of third parties to the design of the temporary works, where
required.
52.5 Where the design of particular temporary works is specified in the SCC to be the responsibility of the
Public Body, the Engineer shall provide the Contractor with all drawings necessary in reasonable time
to enable the Contractor to undertake the temporary works in accordance with his program. In such
cases, the Public Body shall be solely responsible for the safety and adequacy of the design. However,
the Contractor shall be responsible for the proper construction.

53. Soil Studies

53.1 Subject to the SCC and to the technical specifications, the Contractor shall make available to the
Engineer, the personnel and equipment necessary for carrying out any soil survey which the Engineer
considers reasonably necessary. The Contractor shall be compensated for the actual cost of the
manpower and equipment used or made available in such work, if not already provided for in the
contract.

54. Overlapping Contracts

54.1 The Contractor shall, in accordance with the requirements of the Engineer, afford all reasonable
opportunities for carrying out their work to any other Contractors employed by the Public Body or
any other public authorities who may be employed on or near the Site in the execution of any work
not included in the contract, or of any contract which the Public Body may enter into in connection
with, or ancillary to, the works.
54.2 If, however, the Contractor, on the written request of the Engineer, makes available to any such
Contractor, or public authority, or to the Public Body, any roads or ways for the maintenance of which
the Contractor is responsible, or permits the use by any such other persons of the Contractor's
temporary works, scaffolding or other equipment on the site, or provides any other service of
whatsoever nature, which was not provided for in the contract, the Public Body shall pay to the
Contractor in respect of such use or service, such sums and/or grant such extension of time, as shall,
in the opinion of the Engineer, be reasonable.
54.3 The Contractor shall not by reason of this Clause be relieved of any of his obligations under the
Contract nor shall he be entitled to any claims other than those provided for in GCC Clause 54.2.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 44


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

54.4 In no circumstances may difficulties arising with regard to one contract entitle the Contractor to
modify or delay implementation of other contracts. Similarly, the Public Body may not take advantage
of such difficulties to suspend payments due under another contract.

55. Patents and Licenses

55.1 Except where otherwise provided in the SCC, the Contractor shall indemnify the Public Body and the
Engineer against any claim resulting from the use as specified in the contract of patents, licenses,
drawings, designs, models, or brand or trade marks, except where such infringement results from
compliance with the design or specification provided by the Public Body and /or the Engineer.

56. Accounting, Inspection and Auditing

56.1 The Contractor shall keep, and shall cause its Sub-Contractors to keep, accurate and systemic accounts
and records in respect of the Contract, in accordance with internationally accepted accounting
principles and in such form and detail as will clearly identify all relevant time charges and costs.
56.2 For the purpose of the examination and certification of the Public Body's accounts; or any examination
of the economy, efficiency and effectiveness with which the Public Body has used its resources, the
Federal Auditor General and the Public Procurement and Property Administration Agency or its
auditors may inspect all accounts and records relating to the performance of the Contract and the
submission of the Proposal to provide the Works which are owned, held or otherwise within the
control of the Contractor and may require the Contractor to produce such oral or written explanation
as he considers necessary. The Contractor acknowledges that it will fully cooperate with any counter
fraud policy or investigation carried out by authorized body at any time.

57. Data Protection

57.1 The Contractor shall comply with all applicable data protection legislation. In particular the
Contractor agrees:
(a) To maintain appropriate technical and organizational security measures;
(b) To only process Personal Data for and on behalf of the Public Body, in accordance with the
instructions of the Public Body and for the purpose of performing its obligations under the
Contract;
(c) To allow the Public Body to audit the Contractor's compliance with the requirements of this
Clause on reasonable notice and/or to provide the Public Body with evidence of its compliance
with the obligations set out in this Clause.
57.2 The Contractor agrees to indemnify and keep indemnified the Public Body against all claims and
proceedings and all liability, loss, costs and expenses incurred in connection therewith by the Public
Body as a result of any claim made or brought by any individual or other legal person in respect of
any loss, damage or distress caused to that individual or other legal person as a result of the
Contractor's unauthorized processing, unlawful processing, destruction of and/or damage to any
Personal Data processed by the Contractor, its employees or agents in the Contractor's performance
of the Contract or as otherwise agreed between the Parties.

58. Performance Security

58.1 The Contractor shall, within fifteen (15) days from signing the contract, provide a Performance
Security for the due performance of the Contract in the amount specified in the SCC.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 45


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

58.2 Notwithstanding the provision of Sub-clause above a conditional insurance bond shall be accepted as
Performance Security.
58.3 The proceeds of the Performance Security shall be payable to the Public Body as compensation for
any loss resulting from the Contractor’s failure to complete its obligations under the Contract.
58.4 The Performance Security shall be denominated in currency specified in the SCC, and shall be in the
form of cash, cheque certified by a reputable bank, letter of credit, or Bank Guarantee in the format
specified in the SCC.
58.5 No payments shall be made in favor of the Contractor prior to the provision of the Performance
Security. The Performance Security shall continue to remain valid until the contract has been fully
and properly implemented.
58.6 During the performance of the contract, if the natural or legal person providing the Performance
Security is not able to abide by his commitments, the Performance Security shall cease to be valid.
The Public Body shall give formal notice to the Contractor to provide a new Performance Security on
the same terms as the previous one. Should the Contractor fail to provide a new Performance Security
the Public Body may terminate the Contract.
58.7 The Public Body shall demand payment from the Performance Security of all sums for which the
guarantor is liable under the Performance Security due to the Contractor's default under the Contract,
in accordance with the terms of the Performance Security and up to the value thereof. The guarantor
shall, without delay, pay those sums upon demand from the Public Body and may not raise any
objection for any reason whatsoever. Prior to making any claim under the Performance Security, the
Public Body shall notify the Contractor stating the nature of the default in respect of which the claim
is to be made.
58.8 The Performance Security shall be discharged by the Public Body and returned to the Contractor not
later than twenty-eight (28) days following the date of issuing of the signed Final Statement of
Account referred to in GCC Clause 65, for its total amount except for amounts which are the subject
of amicable settlement of disputes, unless specified otherwise in the SCC.
58.9 Notwithstanding the provision of GCC Sub-Clause 58.2 above, the Performance Security may be
returned to the Contractor where the Procurement Endorsing Committee ascertains that the
noncompliance of the Contractor does not affect the interest of, or entail additional cost on the Public
Body and is not due to the fault of the Contractor.
58.10 The Public Body shall be required to submit any document in its possession in relation to a
procurement in which it authorizes the return of the Performance Security to the Contractor and
account for its action under the preceding GCC Sub-Clause 58.9 of this GCC to the Public
Procurement and Property Administration Agency or other competent body if and when required to
do so.
E. Payments to the Contractor
59. General Principles

59.1 Payments shall be made in currency as specified in the SCC. The SCC shall lay down the
administrative or technical conditions governing advance payments, interim and/or final payments
made in accordance with the GCC.
59.2 Payments due by the Public Body shall be made to the bank account mentioned on the Bidder
Certification of Compliance form completed by the Contractor.
59.3 Payments to the Contractor of the amounts due under each of the interim payment certificates and the
final statement of account issued by the Engineer shall be made by the Public Body within 90 days of

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 46


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

such certificate of statement being delivered to the Public Body. The date of payment shall be the date
on which the paying institution's account is debited. The payment certificate shall not be admissible
if one or more essential requirements are not met.
59.4 Interim payment certificates or final statement of account must be accompanied with copies of
invoices and other appropriate supporting materials of the amounts payable.
59.5 The Contractor's invoice shall be correctly rendered if:
(a) The invoice is addressed to the Public Body's officer specified in the Contract to receive
invoices and identifies the number of relevant Contract;
(b) The invoice includes date of issuance and its serial number;
(c) The amount claimed in the invoice is due for payment;
(d) The amount specified in the invoice is correctly calculated in accordance with the Contract;
(e) The invoice includes the name and address of Contractor to whom payment is to be sent;
(f) The invoice includes the name, title, and phone number of person to notify in the event of
defective invoice;
(g) The invoice includes Contractor's bank account information, and
(h) The invoice is, where appropriate, certified as sales tax exempt.
Failure to provide such information will entitle the Public Body's to delay payment until such
information is provided.
59.6 The period referred to in GCC Clause 59.3 may be suspended by notifying the Contractor that the
payment certificate or the final statement of accounts cannot be fulfilled because the sum is not due,
because appropriate substantiating documents have not been provided or because there is evidence
that the expenditure might not be eligible. In the latter case, an inspection may be carried out on the
spot for the purpose of further checks. The Contractor shall provide clarifications, modifications or
further information within 30 days of being asked to do so. Within 30 days of receipt of the
clarification, the Engineer shall decide and issue if need be a revised payment certificate or a final
statement of account and the payment period shall continue to run from this date.
59.7 The Contractor undertakes to repay any amounts paid in excess of the final amount due to the Public
Body before the deadline indicated in the debit note which is 45 days from the issuing of that note.
59.8 Should the Contractor fail to make repayment within the deadline set by the Public Body, the Public
Body may (unless the Contractor is a government-owned enterprise) increase the amounts due by
adding interest at the rediscount rate applied by the National bank of Ethiopia on the first day of the
month in which the time-limit expired, plus three and a half percentage points. The default interest
shall be incurred over the time which elapses between the date of the payment deadline set by the
Public Body and the date on which payment is actually made. Any partial payments shall first cover
the interest thus established.
59.9 Amounts to be repaid to the Public Body may be offset against amounts of any kind due to the
Contractor. This shall not affect the parties' right to agree on payment in installments. Bank charges
involved in the repayment of amounts due to the Public Body shall be borne entirely by the Contractor.

60. Advance Payment

60.1 If the SCC so provide, advance payment shall be granted to the Contractor, at his request, for
operations connected with the implementation of the tasks, in the cases listed hereinafter:
(a) as a lump-sum advance enabling Contractor to meet expenditure resulting from the
commencement of the contract;

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 47


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(b) if Contractor affords proof of the conclusion of a contract for the purchase or order of materials,
plant, equipment, machines and tools, necessary for the execution of the contract, and of any
other substantial prior expenses such as the acquisition of patents or study costs.
60.2 The SCC shall state the amount of the advance payment which shall not exceed 30% of the total
contract price.
60.3 No advance payment shall be granted until:
(a) The conclusion of the Contract;
(b) Provision to the Public Body by the procedure of the Performance Security in accordance with
GCC Clause 58; and by
(c) Provision to the Public Body by the Contractor of an advance payment security in an amount
equal to the advance payment they receive in the form of a certified cheque or unconditional
bank guarantee at their option from a reputable bank or letter of guarantee written by a
competent body organizing and overseeing small and micro enterprises established under the
relevant law.
60.4 Advance payment security shall remain effective until the advance payment has been completely
repaid by the Contractor out of interim payments under the contract.
60.5 The Contractor shall use the advance payment only to pay for Equipment, Plant, Materials, and
mobilization expenses required specifically for execution of the Contract. The Contractor shall
demonstrate that advance payment has been used in this way by supplying copies of invoices or other
documents to the Engineer. Should the Contractor misuse any portion of the advance payment, it shall
become due and repayable immediately and no further advance payments will be made to him.
60.6 Should the advance payment security cease to be valid and the Contractor fail to re-validate it, either
a deduction equal to the amount of the advance payment may be made by the Public Body from future
payments due to the Contractor under the contract, or the Public Body may apply the provisions of
GCC Clause 58.6.
60.7 If the contract is terminated for any reason whatsoever, the guarantees securing the advance payment
may be invoked forthwith in order to repay the balance of the advance payment still owed by the
Contractor, and the guarantor shall not delay payment or raise objection for any reason whatever.
60.8 The advance payment security provided for in this GCC Clause shall be released as and when advance
payment is repaid.
60.9 Further conditions and procedures for granting and repaying advance payment shall be as laid down
in the SCC.

61. Retention Monies

61.1 The sum which shall be retained from interim payments by way of guarantee to meet the Contractor's
obligations during the Defects Liability Period, and the detailed rules governing that guarantee, shall
be stipulated in the SCC, provided that it shall, in no case, exceed 10% of the contract price.
61.2 Subject to the approval of the Public Body, the Contractor may, if he so wishes, substitute, not later
than the date fixed for the commencement of the works, these retention sums by a retention guarantee
issued in accordance with GCC Clause 58.
61.3 The sum retained or the retention guarantee shall be released within 45 days of the issuing of the
signed final statement of account referred to in GCC Clause 65.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 48


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

62. Price Adjustments

62.1 Adjustments of contract prices shall be allowed after twelve (12) months from the effective date of
the Contract where it is verified that the performance of the contract requires more than 18 months.
62.2 Request for price adjustment in relation to a particular work items under this Contract may be filed
by the Contractor after twelve (12) months from the effective date of the Contract where it is verified
that the performance of the contract requires more than 18 months, which adjusted price takes effect
as the new Contract Price in relation to that work item on the expiration of 30 days from the date on
which the Public Body receives notification of that adjusted price from the Contractor, unless another
date is agreed in writing between the Parties.
62.3 All prices shall be firm unless the Contractor has provided claim for price adjustment. The Contractor
may invoke this provision at any time during the Contract by notice in writing to the Engineer.
62.4 The Public Body can increase or decrease the Contract Price amount as described by this Clause.
62.5 Price Adjustment shall be applicable as payable in full for the original scheduled completion period.
62.6 In the event the completion of contract exceeds the original scheduled period:
(a) In case of default on the part of the Contractor causing delay in original scheduled completion,
the rate of Price Adjustment will be frozen at the original scheduled date of completion;
however Price Adjustment will be applicable till actual completion. While computing Price
Adjustment beyond the scheduled completion period, in the event the rate is reduced, then that
reduced rate will be applied.
(b) The Price Adjustment will be payable in full for the extended period if the Contractor has been
granted an extension of time for no fault on the part of the Contractor, duly approved by the
Public Body.
62.7 Unless specifically stated otherwise in the Contract, the basis for compensation will be only those
categories of inputs, which are specifically listed as specified items in the SCC.
62.8 An adjustment of the Contract Price, depending of selected categories of contract price, shall be
limited to an amount which takes account of price indexes or price indicators issued by Ethiopian
Central Statistical Agency or Public Procurement and Property Administration Agency.
62.9 Notwithstanding the provision of GCC Sub-Clause above, price information available from a
renowned local producer or competent foreign institution may be used in case the Ethiopian Central
Statistical Agency or Public Procurement and Property Administration Agency are not in a position
to issue current price indexes,
62.10 Contractor shall submit to the Public Body for review and approval all calculations and supporting
information necessary to determine the price adjustment.
62.11 Adjustments in compensation may be either plus or minus depending on the differences between the
Benchmark Price Index and the Monthly Price Index.
62.12 To determine the adjustment on each item any such price variation shall be calculated in accordance
with the following formula by applying the combination of above said criteria:

PA =  NV + A
(MLI − BLI ) + B (MMI − BMI ) + C (MEI − BEI ) + D (MFI − BFI )(BC )Q

 BLI BMI BEI BFI 
Where:
PA = The amount of the Price adjustment to be paid to, or recovered from, the
Contractor, in currency specified in SCC;

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 49


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

NV= The fraction which represents Non Variable element of the Contract Price that is
free of contract price adjustment, as specified in the Contractor's Bid;
A= The fraction of the Contract Price subject to adjustment in accordance with
movements of the selected Average Labor Category Earnings Index;
MLI = The most recently available selected Average Labor Category Earnings Index on the
date on which the Public Body received notification of the proposed increased price from
the Contractor;
BLI = Benchmark Average Labor Category Earnings Index applicable to the Works either:
(a) at the bid closing date, or
(b) if the Contract Price has been adjusted previously, the date on which the Public Body
received notification from the Contractor in respect of the last adjustment to effect
the current Contract Price;
B= The fraction of the Contract Price subject to adjustment in accordance with
movements of the selected Material Price Index
MMI = The most recently available selected Material Price Index on the date on which the
Public Body received notification of the proposed increased price from the Contractor;
BMI = Benchmark selected Material Price Index applicable to the Works either:
(c) at the bid closing date, or
(d) if the Contract Price has been adjusted previously, the date on which the Public Body
received notification from the Contractor in respect of the last adjustment to effect
the current Contract Price;
C= The fraction of the Contract Price subject to adjustment in accordance with
movements of the selected Equipment Price Index
MEI = The most recently available selected Equipment Price Index on the date on which the
Public Body received notification of the proposed increased price from the Contractor;
BEI = Benchmark selected Equipment Price Index applicable to the Works either:
(a) at the bid closing date, or
(b) if the Contract Price has been adjusted previously, the date on which the Public Body
received notification from the Contractor in respect of the last adjustment to effect
the current Contract Price;
D= The fraction of the Contract Price subject to adjustment in accordance with
movements of the Average Fuel Price Index
MFI = The most recently available Average Fuel Price Index on the date on which the Public
Body received notification of the proposed increased price from the Contractor;
BFI = Benchmark Average Fuel Price Index applicable to the Works either:
(a) at the bid closing date, or
(b) if the Contract Price has been adjusted previously, the date on which the Public Body
received notification from the Contractor in respect of the last adjustment to effect the
current Contract Price;
BC = Current Contract Price applicable to the Works
Q= Quantity;
And where:
(a) NV+A+B+C+D are equal to 1.00
62.13 The fraction for each specified element and exact combination of elements that will be applied in the
formula for price adjustment shall be determined in the SCC.
62.14 An increase in the Contract Price takes effect as the new Contract Price in relation to the selected
category on the first day of the next Payment Period following receipt of an application for increase

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 50


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

provided the application is received no later than 14 days prior to the commencement of that Payment
Period.
62.15 An increase in the Contract Price takes effect as the new Contract Price in relation to the selected
categories of inputs on the expiration of 30 days from the date on which the Public Body receives
notification of the increased price from the Contractor, unless another date is agreed in writing
between the Parties;
62.16 When the Contractor varies the Contract Price of a Product or Service it must supply a copy of a
revised Pricing Schedule which incorporates the proposed changes in price and specifies the date on
which the proposed variation in price is to take effect in accordance with GCC Sub-Clauses 62.14 and
62.15.
62.17 The Contractor shall, when it notifies or requests a price adjustment under GCC Sub-Clause 62.12,
provide to the Public Body such Document or other information as the Contractor considers
appropriate for the purpose of substantiating the requested price adjustment.
62.18 Where the Public Body questions a price increase notified or requested under GCC Sub-Clause 62.12,
and the Contractor is not able, on the basis of the information it provided to the Public Body, to
substantiate to the Public Body any, or a part of, the notified or requested price adjustment, the
Contract Price shall be increased by only so much as the Contractor is able to substantiate and:
(a) the substantiated increased Contract Price shall take effect as the new Contract Price in relation
to the Works as the case may be, on the date referred to in GCC Sub-Clause 62.14 or 62.15
unless another date is agreed in writing between the Parties; and
(b) the Contractor shall, if it has not already done so, supply a suitably revised Pricing Schedule in
accordance with the requirements of GCC Sub-Clause 62.16.
62.19 Any discount offered by the Contractor under this Agreement cannot be reduced during the Term of
this Contract without the agreement in writing of the Public Body.

63. Valuation of Works

63.1 The following methods shall apply to the valuation of works:


(a) For unit-price (admeasurement) contracts:
(i) The amount due under the contract shall be calculated by applying the unit rates to the
quantities actually executed for the respective items, in accordance with the Contract;
(ii) The quantities set out in the bill of quantities shall be the estimated quantities of the works,
which shall not be taken as the actual and correct quantities of the works to be executed
by the Contractor in fulfillment of his obligations under the Contract;
(iii) The Engineer shall determine by measurement the actual quantities of the works executed
by the Contractor, and these shall be paid for in accordance with GCC Clause 64. Unless
otherwise provided in the SCC no additions shall be made to the items in the bill of
quantities except as a result of a modification in accordance with GCC Clause 15 or
another provision of the Contract entitling the Contractor to additional payment;
(iv) The Engineer shall, when he requires any parts of the works to be measured, give
reasonable notice to the Contractor to attend, or to send a qualified agent to represent him.
The Contractor or his agent shall assist the Engineer in making such measurements and
shall furnish all particulars required by the Engineer. Should the Contractor not attend, or
omit to send such agent, the measurement made by the Engineer or approved by him shall
be binding on the Contractor;
(b) For lump-sum contracts, the amount due under the Contract shall be determined on the basis of
the breakdown of the overall contract price, or on the basis of a breakdown expressed as a
SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 51
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

percentage of the contract price corresponding to completed stages of the works. Where items
are accompanied by quantities, these shall be firm quantities for which the Contractor has
submitted his all-in price, and shall be paid for irrespective of the quantities of work actually
carried out.

64. Interim Payment

64.1 Unless otherwise specified in the SCC, the Contractor shall submit monthly statement for interim
payment to the Engineer at the end of each period referred to in GCC Clause 64.7 in a form approved
by the Engineer. The monthly statement shall include the following items, as applicable:
(a) The estimated contract value of the permanent works implemented up to the end of the period
in question;
(b) An amount reflecting any price adjustment pursuant to GCC Clause 62;
(c) An amount to be withheld as retention sum under GCC Clause 61;
(d) Any credit and/or debit for the period in question in respect of plant and materials on Site
intended for, but not yet incorporated in, the permanent works in the amount and under the
conditions set out in GCC Clause 64.2;
(e) An amount to be deducted on account of the advance payment repayment under the provisions
of GCC Clause 60; and
(f) Any other sum to which the Contractor may be entitled under the Contract.
64.2 The Contractor shall be entitled to such sums as the Engineer may consider proper in respect of plant
and materials intended for, but not yet incorporated in, the permanent works provided that:
(a) The plant and materials conform with the specifications for the permanent works and are set
out in batches in a way that they may be recognized by the Engineer;
(b) Such plant and materials have been delivered to the Site, and are properly stored and protected
against loss or damage or deterioration to the satisfaction of the Engineer;
(c) The Contractor's record of requirements, orders, receipts and use of plant and materials under
the contract are kept in a form approved by the Engineer and such records are available for
inspection by the Engineer;
(d) The Contractor submits with his statement, the estimated value of the plant and materials on
Site together with such documents as may be required by the Engineer for the purpose of
valuation of the plant and materials and providing evidence of ownership and payment
therefore; and
(e) Where the SCC so provide, ownership of the plant and materials referred to in GCC Clause 83
shall be deemed to be vested in the Public Body.
64.3 Approval by the Engineer of any interim payment certified by him in respect of plant and materials
pursuant to this GCC Clause shall be without prejudice to the exercise of any power of the Engineer
under the Contract to reject any plant or materials which are not in accordance with the provisions of
the Contract.
64.4 The Contractor shall be responsible for any loss or damage to, and for the cost of storing and handling
of, such plant and materials on site and shall effect such additional insurance as may be necessary to
cover the risk of such loss or damage from any cause.
64.5 Within 30 days of receipt of the said statement for interim payment, it shall be approved or amended
in such manner that, in the Engineer's opinion, the application reflects the amount due to the
Contractor in accordance with the Contract. In cases where there is a difference of opinion as to the
value of an item, the Engineer's view shall prevail. On determination of the amount due to the
Contractor, the Engineer shall, within the same 30 days deadline, issue and transmit to the Public
SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 52
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Body for payment and to the Contractor for information, an Interim Payment Certificate for the
amount due to the Contractor and shall inform the Contractor of the works for which payment is being
made.
64.6 The Engineer may, by an Interim Payment Certificate, make any corrections or modifications to any
previous certificate issued by him and shall have power to modify the valuation in or withhold the
issue of, any Interim Payment Certificate if the works or any part thereof is not being carried out to
his satisfaction.
64.7 Unless the SCC provide otherwise, the frequency shall be one interim payment per month.

65. Final Statement of Account

65.1 Unless otherwise agreed in the SCC, the Contractor shall not later than 90 days after the issue of the
Final Acceptance Certificate referred to in GCC Clause 89, submit to the Engineer a draft final
statement of account with supporting documents showing in detail the value of the work done in
accordance with the Contract, together with all further sums which the Contractor considers to be due
to him under the Contract in order to enable the Engineer to prepare the final statement of account.
65.2 Within 60 days after receipt of the draft final statement of account and of all information reasonably
required for its verification, the Engineer shall prepare the final statement of account, which
determines:
(a) the amount which in his opinion is finally due under the Contract; and
(b) after establishing the amounts previously paid by the Public Body and all sums to which the
Public Body is entitled under the Contract, the balance, if any, due from the Public Body to the
Contractor, or from the Contractor to the Public Body, as the case may be.
65.3 The Engineer shall issue to the Public Body or to its duly authorized representative, and to the
Contractor, the final statement of account showing the final amount to which the Contractor is entitled
under the Contract. The Public Body or its duly authorized representative and the Contractor shall
sign the final statement of account as an acknowledgement of the full and final value of the work
implemented under the Contract and shall promptly submit a signed copy to the Engineer. However,
the final statement of account shall not include amounts in dispute which are the subject of
negotiations or amicable settlement.
65.4 The final statement of account signed by the Contractor shall constitute a written discharge of the
Public Body confirming that the total in the final statement of account represents full and final
settlement of all monies due to the Contractor under the Contract, other than those amounts which are
the subject of amicable settlement. However, such discharge shall become effective only after any
payment due in accordance with the final statement of account has been made and the performance
security referred to in GCC Clause 58 has been returned to the Contractor.
65.5 The Public Body shall not be liable to the Contractor for any matter or thing whatsoever arising out
of, or in accordance with, the Contract or execution of the works, unless the Contractor shall have
included a claim in respect thereof in his draft final statement of account.

66. Direct Payments to Sub-Contractors

66.1 When the Engineer receives a claim from a Sub-Contractor duly approved under GCC Clause 14 to
the effect that the Contractor has not met his financial obligations so far as the Sub-Contractor is
concerned, the Engineer shall give notice to the Contractor either to pay the Sub-Contractor or to
inform him of the reasons why payment should not be made. Should such payment not be made, or
reasons not be given within the period of notice, the Engineer may, after satisfying himself that the
work has been carried out, certify, and the Public Body shall meet the debt claimed by the Sub-

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 53


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Contractor out of the sums remaining due to the Contractor. The Contractor shall remain entirely
responsible for the work in respect of which direct payment has been made.
66.2 If the Contractor gives adequate reasons for refusing to meet all or part of the debt claimed by the
Sub-Contractor, the Public Body shall only pay to the Sub-Contractor such sums as are not in dispute.
Sums claimed by the Sub-Contractor in respect of which the Contractor has given adequate reasons
for his refusal to pay shall be paid by the Public Body only after the parties have come to an amicable
settlement or after a judgment of a court has been duly notified to the Engineer.
66.3 Direct payments to Sub-Contractors shall not exceed the value at contract prices of the services
performed by the Sub-Contractors for which they request payment; the value at contract prices shall
be calculated or assessed on the basis of the bill of quantities, the price schedule or the breakdown of
the lump sum price.
66.4 Direct payments to Sub-Contractors shall be made entirely in the currency specified in SCC Clause
59.1.
66.5 The provisions of this GCC Clause shall apply subject to the requirements of the law applicable by
virtue of GCC Clause 68 concerning the right to payment of creditors who are beneficiaries of an
assignment of credit or of a collateral security.

67. Delayed Payments

67.1 Once the time-limit referred to in GCC Clause 59.3 has expired, the Contractor – unless the Contractor
is a public body which is partly or wholly financed by the Federal Government Budget – shall upon
demand, submitted within two months of receiving late payment, be entitled to late-payment interest
at the rediscount rate applied by the National bank of Ethiopia on the first day of the month in which
the time-limit expired, plus three and a half percentage points. The interest shall be payable for the
time elapsed between the expiry of the payment deadline and the date on which the Public Body’s
account is debited. .
67.2 Any default in payment of more than 120 days from the expiry of the period laid down in GCC Clause
67.1 shall entitle the Contractor either not to perform the Contract or to terminate it.

68. Payments to Third Parties

68.1 All orders for payments to third parties may be carried out only after an assignment made in
accordance with GCC Clause 13. The assignment shall be notified to the Public Body.
68.2 Notification of beneficiaries of the assignment shall be the sole responsibility of the Contractor.
68.3 In the event of a legally binding attachment of the property of the Contractor affecting payments due
to him under the contract, without prejudice to the time limit laid down in GCC Clause 67, the Public
Body shall have 30 days, starting from the day when it receives notification of the definitive lifting of
the obstacle to payment, to resume payments to the Contractor.

69. Claims for Additional Payment

69.1 If under the Contract there are circumstances which the Contractor considers entitle him to additional
payment, the Contractor shall:
(a) if he intends to make any claim for additional payment, give to the Engineer notice of his
intention or make such claim within 15 days after the said circumstances become known to the
Contractor, stating the reason for his claim; and

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 54


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(b) submit full and detailed particulars of his claim as soon as it is reasonably practicable, but no
later than 60 days after the date of such notice, unless otherwise agreed by the Engineer. In case
the Engineer agrees to another deadline than the said 60 days, the agreed upon deadline will in
any event, require that such particulars shall be submitted no later than the date of submission
of the draft final statement of account. The Contractor shall thereafter promptly submit such
further particulars as the Engineer may reasonably require assessing the validity of the claim.
69.2 When the Engineer has received the full and detailed particulars of the Contractor's claim that he
requires, he shall, without prejudice to GCC Clause 44.4, after due consultation with the Public Body
and, where appropriate, the Contractor, determine whether the Contractor is entitled to additional
payment and notify the parties accordingly.
69.3 The Engineer may reject any claim for additional payment which does not comply with the
requirements of this GCC Clause.
F. Performance of the Contract
70. Scope of Works

70.1 Subject to the SCC, the Works to be carried out shall be as specified in the Section 6, Schedule of
Requirements.
70.2 The Contractor shall construct and install the Works at sites and locations as are specified in the SCC
in accordance with the Specifications and Drawings or as agreed by the Parties in writing.

71. Commencement of Works

71.1 The Public Body shall fix the Start Date on which execution of the Works is to commence in the SCC
or by administrative order issued by the Engineer.
71.2 The Start Date for commencing execution of the Works shall be not later than 120 days following
notification of award of contract unless agreed otherwise by the parties.

72. Period of Execution of Works

72.1 The period of execution of Works shall commence on the Start Date fixed in accordance with GCC
Clause 71.1 and shall be as laid down in the SCC, without prejudice to extensions of the period which
may be granted under GCC Clause 73.
72.2 The Contractor shall carry out the Works in accordance with the Program of implementation of tasks
submitted by the Contractor, as updated with the approval of the Engineer, and complete them by the
Intended Completion Date.
72.3 If provision is made for distinct periods of implementation for separate lots, in cases where one
Contractor is awarded more than one lot per contract, the periods of implementation for the separate
lots will not be accumulated.

73. Extension of Intended Completion Date

73.1 The Contractor may request an extension of the Intended Completion Date if he is or will be delayed
in completing the contract by any of the following causes:
(a) Exceptional weather conditions in the Federal Democratic Republic of Ethiopia;
(b) Artificial obstructions or physical conditions which could not reasonably have been foreseen
by an experienced Contractor;

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 55


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(c) Compensation Event occurs or a change order for modification is issued which makes it
impossible for completion to be achieved by the Intended Completion Date;
(d) Administrative orders affecting the date of completion other than those arising from the
Contractor's default;
(e) Failure of the Public Body to fulfill his obligations under the Contract;
(f) Any suspension of the works which is not due to the Contractor's default;
(g) Force majeure;
(h) Any other causes referred to in these GCC which are not due to the Contractor's default.
73.2 The Contractor shall, within 15 days of becoming aware that delay may occur, notify the Engineer of
his intention to make a request for extension of the Intended Completion Date to which he may
consider himself entitled, and shall, unless otherwise agreed between the Contractor and the Engineer,
within 21 days from the notification deliver to the Engineer full and detailed particulars of the request,
in order that such request may be investigated at the time.
73.3 Within 21 days from receipt of the Contractor's detailed particulars of the request, the Engineer shall,
by written notice to the Contractor after due consultation with the Public Body and, where appropriate,
the Contractor, grant such extension of the Intended Completion Date as may be justified, either
prospectively or retrospectively, or inform the Contractor that he is not entitled to an extension.
73.4 If the Contractor has failed to give early notification of a delay or has failed to cooperate in dealing
with a delay, the delay by this failure shall not be considered in assessing the new Intended
Completion Date.

74. Compensation Events for Allowing Time Extension

74.1 The following shall be Compensation Events allowing for time extension:
(a) The Public Body does not give access to a part of the Site by the Site Possession Date stated in
the Contractor’s approved work program;
(b) The Public Body modifies the Schedule of other Contractors in a way that affects the work of
the Contractor under the Contract;
(c) The Engineer orders a delay or does not issue Drawings, Specifications, or instructions required
for execution of the Works on time;
(d) The Engineer instructs the Contractor to uncover or to carry out additional tests upon work,
which is then found to have no Defects;
(e) The Engineer unreasonably does not approve a subcontract to be let;
(f) The Engineer gives an instruction for dealing with an unforeseen condition, caused by the
Public Body, or additional work required for safety or other reasons.
(g) Other Contractors, public authorities, utilities, or the Public Body do not work within the dates
and other constraints stated in the Contract, and they cause delay;
(h) The advance payment is delayed;
(i) The Engineer unreasonably delays issuing Interim Payment Certificates;
(j) Other Compensation Events described in the SCC or determined by the Public Body and force
majeure.
74.2 If a Compensation Event would prevent the work being completed before the Intended Completion
Date, the Intended Completion Date shall be extended. The Engineer shall decide whether and by how
much the Intended Completion Date shall be extended.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 56


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

74.3 The Contractor shall not be entitled to compensation to the extent that the Public Body’s interests are
adversely affected by the Contractor not having given early warning.

75. Acceleration

75.1 When the Public Body wants the Contractor to finish before the Intended Completion Date, the
Engineer will obtain priced proposals for achieving the necessary acceleration from the Contractor. If
the Public Body accepts these proposals, the Intended Completion Date will be adjusted accordingly
and confirmed by both the Public Body and the Contractor.
75.2 If the Contractor’s priced proposals for acceleration are accepted by the Public Body, they are
incorporated in the Contract Price and treated as a modification.

76. Management Meetings

76.1 Either the Engineer or the Contractor may require the other to attend a formal management meeting,
to discuss the Public Body's levels of satisfaction in respect of the Works carried out under the
Contract, to review the plans for remaining work, and to agree any necessary action to address areas
of dissatisfaction. The Contractor will not obstruct or withhold its agreement to any such necessary
action. Such meetings shall be attended by duly authorized and sufficiently senior employees of both
the Public Body and the Contractor together with any other relevant attendees. The Parties shall agree
a standing agenda for such Reviews.
76.2 The Engineer shall record the business of management meetings and provide copies of the record to
those attending the meeting and to the Public Body. The responsibility of the parties for actions to be
taken shall be decided by the Engineer either at the management meeting or after the management
meeting and stated in writing to all who attended the meeting.

77. Early Warning

77.1 The Contractor shall warn the Engineer at the earliest opportunity of specific likely future events or
circumstances that may adversely affect the quality of the work increase the Contract Price or delay
the execution of the Works. The Engineer may require the Contractor to provide an estimate of the
expected effect of the future event or circumstance on the Contract Price and Completion Date. The
estimate shall be provided by the Contractor as soon as reasonably possible.
77.2 The Contractor shall cooperate with the Engineer in making and considering proposals for how the
effect of such an event or circumstance can be avoided or reduced by anyone involved in the work
and in carrying out any resulting instruction of the Engineer.

78. Delays in Implementation of Tasks

78.1 If the Contractor fails to complete the works within the time period(s) specified in the Contract the
Public Body shall, without formal notice and without prejudice to his other remedies under the
contract be entitled to liquidated damages for every day or part thereof which shall elapse between
the end of the period specified for implementation of tasks or extended Intended Completion Date
under GCC Clause 72 and the actual date of completion, at the rate and up to the maximum amount
specified in the GCC Clause 27. If the works have been the subject of partial acceptance in accordance
with GCC Clause 86, the liquidated damages specified in the GCC Clause 27 may be reduced in the
proportion which the value of the accepted part bears to the value of the whole of the works.
78.2 If the Public Body has become entitled to the maximum claim under GCC Clause 78.1 he may, after
giving notice to the Contractor:

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 57


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(a) Seize the performance guarantee; and /or


(b) Terminate the contract; and
(c) Enter into a contract with a third party at the Contractor's cost for the provision of the balance
of the works.

79. Work Register

79.1 A work register shall, unless otherwise provided by the SCC, be kept on the site by the Engineer, who
shall enter in it at least the following information:
(a) the weather conditions, interruptions of work owing to inclement weather, hours of work,
number and type of workmen employed on the site, materials supplied, equipment in use,
equipment not in working order, tests carried out, samples dispatched, unforeseen
circumstances, as well as orders given to the Contractor;
(b) detailed statements of all the quantitative and qualitative elements of the work done and the
supplies delivered and used, capable of being checked on the Site and relevant in calculating
payments to be made to the Contractor.
79.2 The statements shall form an integral part of the work register but may, where appropriate, be recorded
in separate documents. The technical rules for drawing up the statements shall be as set out in the
SCC.
79.3 The Contractor shall ensure that statements are drawn up, in good time and in accordance with the
SCC, in respect of work, services and supplies which cannot be measured or verified subsequently;
failing this, he shall accept the decisions of the Engineer, unless, at his own expense, he provides
evidence to the contrary.
79.4 Entries made in the work register as work progresses shall be signed by the Engineer and
countersigned by the Contractor or his representative. If the Contractor objects, he shall communicate
his views to the Engineer within 15 days following the date on which the entry or the statements
objected to be recorded. Should Contractor fail to countersign or to submit his views within the period
allowed, the Contractor shall be deemed to agree with the notes shown in the register. The Contractor
may examine the work register at any time and may, without removing the document, make or receive
a copy of entries which he considers necessary for his own information.
79.5 The Contractor shall, on request, provide the Engineer with the information needed to keep the work
register in good order.

80. Origin and Quality of Works and Materials

80.1 All goods purchased under the contract shall have their origin in any eligible source country as defined
in the Section 5 of the Bidding Documents.
80.2 The works, components and materials shall conform to the specifications, drawings, surveys, models,
samples, patterns and other requirements in the SCC which shall be held at the disposal of the Public
Body or the Engineer for the purposes of identification throughout the period of performance.
80.3 Any preliminary technical acceptance stipulated in the SCC shall be the subject of a request sent by
the Contractor to the Engineer. The request shall indicate the reference to the contract, the lot number
and the place where such acceptance is to take place, as appropriate. The components and materials
specified in the request must be certified by the Engineer as meeting the requirements for such
acceptance prior to their incorporation in the works.
80.4 Even if materials or items to be incorporated in the works or in the manufacture of components have
been technically accepted in this way, they may still be rejected and must be replaced immediately by

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 58


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

the Contractor if a further examination reveals defects or faults. The Contractor may be given the
opportunity to repair and make good materials and items which have been rejected, but such materials
and items will be accepted for incorporation in the works only if they have been repaired and made
good to the satisfaction of the Engineer.

81. Inspection and Testing

81.1 The Contractor shall ensure that the components and materials are delivered to the site in time to allow
the Engineer to proceed with acceptance of the components and materials. The Contractor is deemed
to have fully appreciated the difficulties which he might encounter in this respect, and he shall not be
permitted to advance any grounds for delay in fulfilling his obligations.
81.2 The Engineer shall be entitled, either by himself or his agent, to inspect, examine, measure and test
the components, materials and workmanship, and check the progress of preparation, fabrication or
manufacture of anything being prepared, fabricated or manufactured for delivery under the contract
in order to establish whether the components, materials and workmanship are of the requisite quality
and quantity. This shall take place at the place of manufacture, fabrication, preparation or on the site
or at such other places as may be specified in the contract.
81.3 For the purposes of such tests and inspections, the Contractor shall:
(a) provide to the Engineer, temporarily and free of charge, such assistance, test samples, parts,
machines, equipment, tools or materials and labor as are normally required for inspection and
testing;
(b) agree, with the Engineer, on the time and place for tests;
(c) provide access for the Engineer at all reasonable times to the place where the tests are to be
carried out.
81.4 If the Engineer is not present on the date agreed for tests, the Contractor may, unless otherwise
instructed by the Engineer, proceed with the tests, which shall be deemed to have been made in the
Engineer's presence. The Contractor shall forthwith forward duly certified copies of the test results to
the Engineer, who shall, if he has not attended the test, be bound by the test results.
81.5 When components and materials have passed the tests referred to in this GCC Clause, the Engineer
shall notify the Contractor or endorse the procedure's certificate to that effect.
81.6 If the Engineer and the Contractor disagree on the test results, each shall give a statement of his views
to the other within 15 days after such disagreement arises. The Engineer or the Contractor may require
such tests to be repeated on the same terms and conditions or, if either party so requests, by an expert
to be selected by common consent. All test reports shall be submitted to the Engineer who shall
communicate the results of these tests without delay to the Contractor. The results of the re-testing
shall be conclusive. The cost of the re-testing shall be borne by the party whose views are proved
wrong by the re-testing.
81.7 In the performance of his duties, the Engineer and all persons authorized by him shall disclose only
to those persons who are entitled to know of it information which he has obtained by reason of his
inspection and testing of the methods of manufacture and operation of the undertaking.

82. Rejection

82.1 Components and materials which are not of the specified quality shall be rejected. A special mark
may be applied to the rejected components or materials. This shall not be such as to alter them or
affect their commercial value. Rejected components and materials shall be removed by the Contractor
from the site within a period which the Engineer shall specify, failing which they shall be removed

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 59


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

by the Engineer as of right at the expense and risk of the Contractor. Any work incorporating rejected
components or materials shall be rejected.
82.2 The Engineer shall, during the progress of the works and before the works are taken over, have the
power to order or decide:
(a) the removal from the Site, within such time limits as may be specified in the order, of any
components or materials which, in the opinion of the Engineer, are not in accordance with the
contract;
(b) the substitution of proper and suitable components or materials; or
(c) the demolition and proper re-execution, or satisfactory repair, notwithstanding any previous
test thereof or interim payment therefore, of any work which, in respect of components,
materials, workmanship or design by the Contractor for which he is responsible, is not, in the
opinion of the Engineer, in accordance with the Contract.
82.3 The Engineer shall, as soon as reasonably practicable, give to the Contractor notice in writing of his
decision specifying particulars of the alleged defects.
82.4 The Contractor shall with all speed and at his expense make good the defects so specified. If the
Contractor does not comply with such order, the Public Body shall be entitled to employ other persons
to carry out the same and all expenses consequent thereon or incidental thereto may be deducted by
the Public Body from any monies due or which may become due to the Contractor.
82.5 The provisions of this GCC Clause shall not affect the right of the Public Body to claim under GCC
Clauses 19 and 78.

83. Ownership of Plant and Materials

83.1 All equipment, temporary works, plant and materials provided by the Contractor shall, when brought
on the Site, be deemed to be exclusively intended for the execution of the works and the Contractor
shall not remove the same or any part thereof, except for the purpose of moving it from one part of
the site to another, without the consent of the Engineer. Such consent shall, however, not be required
for vehicles engaged in transporting any staff, labor, equipment, temporary works, plant or materials
to or from the Site.
83.2 The SCC may provide that all equipment, temporary works, plant and materials on Site owned by the
Contractor or by any company in which the Contractor has a controlling interest shall, for the duration
of the execution of the works, be:
(a) vested in the Public Body; or
(b) made subject to a lien in favor of the Public Body; or
(c) made subject to any other arrangement regarding priority interest or security.
83.3 In the event of termination of the contract in accordance with GCC Clause 21 due to the Contractor's
breach of Contract, the Public Body shall be entitled to use the equipment, temporary works, plant
and materials on Site in order to complete the works.
83.4 Any agreement for the hire by the Contractor of equipment, temporary works, plant and materials
brought onto the Site, shall contain a provision that on request in writing made by the Public Body
within 7 days after the date on which the termination under GCC Clause 21 becomes effective, and
on the Public Body undertaking to pay all hire charges in respect thereof from such date, the owner
thereof will hire such equipment, temporary works, plant or materials to the Public Body on the same
terms as they were hired by the Contractor, except that the Public Body shall be entitled to permit the
use thereof by any other Contractor employed by him for completing the works under the provisions
of GCC Clause 21.5.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 60


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

83.5 Upon termination of the contract before completion of the works, the Contractor shall deliver to the
Public Body any plant, temporary works, equipment or materials the property in which has vested in
the Public Body or been made subject to a lien by virtue of GCC Clause 83.2. If he fails to do so, the
Public Body may take such appropriate action as it deems fit in order to obtain possession of such
plant, temporary works, equipment and materials and recover the cost of so doing from the Contractor.
G. Acceptance and Defects Liability
84. General Principles

84.1 Verification of the works by the Engineer with a view to provisional or final acceptance shall take
place in the presence of the Contractor. The absence of the Contractor shall not be a bar to verification
on condition that the Contractor has been summoned in due form at least 30 days prior to the date of
verification.
84.2 Should exceptional circumstances make it impossible to ascertain the state of the works or otherwise
proceed with their acceptance during the period fixed for provisional or final acceptance, a statement
certifying such impossibility shall be drawn up by the Engineer after consultation, where possible,
with the Contractor. The verification shall take place and a statement of acceptance or rejection shall
be drawn up by the Engineer within 30 days following the date on which such impossibility ceases to
exist. The Contractor shall not invoke these circumstances in order to avoid his obligation to present
the works in a state suitable for acceptance.

85. Tests on Completion

85.1 The works shall not be accepted until the prescribed verifications and tests have been carried out at
the expense of the Contractor. The Contractor shall notify the Engineer of the date on which such
verification and tests may commence.
85.2 Works which do not satisfy the terms and conditions of the Contract, or in the absence of such terms
and conditions, which are not carried out in accordance with trade practices in the Federal Democratic
Republic of Ethiopia, shall, if required, be demolished and rebuilt by the Contractor or repaired to the
satisfaction of the Engineer, otherwise this shall be done as of right after due notice at the expense of
the Contractor, by order of the Engineer. The Engineer may also require the demolition and
reconstruction by the Contractor, or repair to the satisfaction of the Engineer, under the same
conditions of work, in which unacceptable materials have been used, or carried out in the periods of
suspension provided for in GCC Clause 20.

86. Partial Acceptance

86.1 The Public Body may make use of the various structures, parts of structures or sections of the works
forming part of the contract as and when they are completed. Any taking over of the structures, parts
of structures or sections of the works by the Public Body shall be preceded by their partial provisional
acceptance. However, works may in cases of urgency be taken over prior to acceptance provided an
inventory of outstanding work is drawn up by the Engineer and agreed to by the Contractor and the
Engineer beforehand. Once the Public Body has taken possession of a structure, a part thereof or
section of the works, the Contractor shall no longer be required to make good any damage resulting
otherwise than from faulty construction or workmanship.
86.2 The Engineer may, at the request of the Contractor and if the nature of the works so permits proceeds
with partial provisional acceptance, provided that the structures, parts of structures or sections of the
works are completed and suited to the use as described in the Contract.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 61


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

86.3 In the cases of partial provisional acceptance referred to in GCC Sub-Clauses 86.1 and 86.2 the
Defects Liability Period provided for in GCC Clause 88 shall, unless the SCC provide otherwise, run
as from the date of such partial provisional acceptance.

87. Provisional Acceptance

87.1 The works shall be taken over by the Public Body when they have satisfactorily passed the tests on
completion and a certificate of provisional acceptance has been issued or is deemed to have been
issued.
87.2 The Contractor may apply, by notice to the Engineer, for a certificate of provisional acceptance not
earlier than 15 days before the works, in the Contractor's opinion, are complete and ready for
provisional acceptance. The Engineer shall within 30 days after the receipt of the Contractor's
application either:
(a) issue the certificate of provisional acceptance to the Contractor with a copy to the Public Body
stating, where appropriate, his reservations, and, inter alia, the date on which, in his opinion,
the works were completed in accordance with the Contract and ready for provisional
acceptance; or
(b) reject the application giving his reasons and specifying the action which, in his opinion, is
required of the Contractor for the certificate to be issued.
87.3 If the Engineer fails either to issue the certificate of provisional acceptance or to reject the Contractor's
application within the period of 30 days, he shall be deemed to have issued the certificate on the last
day of that period. The certificate of provisional acceptance shall not be deemed to be an admission
that the works have been completed in every respect. If the works are divided by the contract into
sections, the Contractor shall be entitled to apply for separate certificates for each of the sections.
87.4 Upon provisional acceptance of the works, the Contractor shall dismantle and remove temporary
structures as well as materials no longer required for use in connection with the performance of the
contract. He shall also remove any litter or obstruction and redress any change in the condition of the
Site as required by the contract.
87.5 Immediately after provisional acceptance, the Public Body may make use of all the works as
completed.

88. Defects Liability

88.1 The Contractor shall be responsible for making good any defect in, or damage to, any part of the
works which may appear or occur during the Defects Liability Period and which arises either from:
(a) the use of defective plant or materials or faulty workmanship or design of the Contractor; and/or
(b) any act or omission of the Contractor during the Defects Liability Period.
88.2 The Contractor shall at his own cost make good the defect or damage as soon as practicable. The
Defects Liability Period for all items replaced or renewed shall recommence from the date when the
replacement or renewal was made to the satisfaction of the Engineer. If the contract provides for
partial acceptance, the Defects Liability Period shall be extended only for the part of the works
affected by the replacement or renewal.
88.3 If any such defect appears or such damage occurs, during the period referred to in GCC Clause 88.1,
the Public Body or the Engineer shall notify the Contractor. If the Contractor fails to remedy a defect
or damage within the time limit stipulated in the notification, the Public Body may:

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 62


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

(a) carry out the works himself, or employ someone else to carry out the works, at the Contractor's
risk and cost, in which case the costs incurred by the Public Body shall be deducted from monies
due to or from securities held against the Contractor or from both; or
(b) terminate the Contract.
88.4 If the defect or damage is such that the Public Body has been deprived substantially of the whole or a
part of the benefit of the works, the Public Body shall, without prejudice to any other remedy, be
entitled to recover all sums paid in respect of the parts of the works concerned together with the cost
of dismantling such parts and clearing the Site.
88.5 In case of emergency, where the Contractor cannot be reached immediately or, having been reached,
is unable to take the measures required, the Public Body or the Engineer may have the work carried
out at the expense of the Contractor. The Public Body or the Engineer shall as soon as practicable
inform the Contractor of the action taken.
88.6 Where the SCC stipulates that the maintenance work, necessitated by normal wear and tear, shall be
carried out by the Contractor, such work shall be paid for from a provisional sum. Deterioration
resulting from the circumstances provided for in GCC Clause 44 or from abnormal use shall be
excluded from this obligation unless it reveals a fault or defect justifying the request for repair or
replacement under GCC Clause 88.
88.7 The defects liability shall be stipulated in the SCC. If the duration of the Defects Liability Period is
not specified, it shall be 365 days. The Defects Liability Period shall commence on the date of
provisional acceptance.
88.8 After provisional acceptance and without prejudice to the defects liability referred to in this GCC
Clause, the Contractor shall no longer be responsible for risks which may affect the works and which
result from causes not attributable to him. However, the Contractor shall be responsible as from the
date of provisional acceptance for the soundness of the construction, as laid down in the in the
Ethiopian law.

89. Final Acceptance

89.1 Upon the expiry of the Defects Liability Period, or where there is more than one such period, upon
the expiry of the latest period, and when all defects or damage have been rectified, the Engineer shall
issue to the Contractor a Final Acceptance Certificate and a copy thereof to the Public Body stating
the date on which the Contractor completed his obligations under the Contract to the Engineer's
satisfaction. The Final Acceptance Certificate shall be given by the Engineer within 30 days after the
expiration of the above stated period, or as soon as any works ordered under GCC Clause 88 have
been completed to the satisfaction of the Engineer.
89.2 The works shall not be considered as completed until the Final Acceptance Certificate has been signed
by the Engineer and delivered to the Public Body, with a copy to the Contractor.
89.3 Notwithstanding the issue of the Final Acceptance Certificate, the Contractor and the Public Body
shall remain liable for the fulfillment of any obligation incurred under the contract prior to the issue
of the Final Acceptance Certificate, which remains unperformed at the time such Final Acceptance
Certificate is issued. The nature and extent of any such obligation shall be determined by reference to
the provisions of the contract.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 63


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Section IV - Works Requirements












SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 64
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)


Section 4(A). Scope of Works
The scope of the work is construction of all civil works of Finna Bilte dam body and its appurtenant
structures project. The specification shall apply to the civil works required in the construction of the
WORKS as described in the document.
The main construction activities performed in this contract are:
• Camping facilities for consultant and client representative shall be constructed as per bill of
quantity and drawing of this project. However, the contractor can built temporary homes and store
like for his key personnel or workers or can rent houses at proximity of the project. The
construction cost for contractor camp shall be deemed to have covered by his own and have the
right to demolish and took at any time. Camp site is selected due consultation with the
communities, Kebele and woreda officials.
• Dam body and its appurtenant structures construction
• Inspection and/or access roads

The works shall perform according to the technical specification and the given drawings either in hard
or soft copy. If there are problems during construction time, it is advisable to request the representatives
in written before continuing the actual work. Hence, preparation of detail work plan, preparation of
working drawings, working methodology etc shall be the responsibility of the contractor.
Location of irrigation project (including the command area under construction)
S.N Project Name Zone Districts Location
Easting Northing
1 Finna Bilte Dam North Showa Abichu Nya’a 527113 1058213
Note: Specific sites for construction material shall be decided in consultation with woreda

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 65


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Section 4 (B). Technical Specifications

PART-1 Description of Works


1.1. General
Before commencement of the work, the Engineer will upon contractor’s written request, indicate
locations and coordinates for the permanent topographic benchmark and monuments, which are to be
used. This applies also to the benchmarks shown in the contract drawings.
1.2. Data on the Works

Information’s regarding on levels, Dimensions, alignments and gradients of the works are shown on
the drawing or else specified separately. All Dimensions, distances and levels of the designs are
indicated in metric system or specified.
Table1 the major works of the camp facilities are the following;
Drawing title
Camping facilities
1. Living rooms
2. Offices
3. Kitchen
4. Shower
5. Toilets
6. Depot (----)
7. etc
Notice: -Camp drawings of Consultancy/Engineer representative drawings shall be given either in soft
or hard copy separately. But, Contractor campy drawings are provided and approved by Engineer in
the same compound.
Table-2 the works of the Dam Body and Its Appurtenant Structures are the following; drawings
shall be given either in soft or hard copy separately.
Drawing title
1. Dam body and its Appurtenant Structures
2. Other structures

Table-3 Inspection and Access Road


DRAWINGS
1. Layout and profiles
2. Road section

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 66


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

1. Surveying and setting out works


The Contractor shall be responsible for the true and proper setting out of the works and for the
correctness of the positions, levels, dimensions and alignment of all parts of the works and for the
provisions of all necessary instruments, appliances and labor in connection therewith. If at any time
during the progress of the works, any error shall appear or arise in the position, levels, dimensions
or alignment of any part of the works, the Contractor, on being required to do so by the Engineer,
shall at his own expense rectify such error to the satisfaction of the Engineer.
The checking of any setting out or of any line or level by the Engineer shall not in any way relieve
the Contractor of his responsibility for correctness thereof. The Contractor shall carefully protect
and preserve all benchmarks, sight rails, pegs and other things used in setting out the works.
Payment will be made for this work item in lump sum as set forth the Bill of Quantities of General
provision
2. Construction Technology

Table-4 Construction method


The works to be done
Remark
No. Type of work using
Machinery Labor
1 Site clearing and excavation  
2 Mortar mixing  
3 Masonry work 
For Intake and spillway and
4 Concrete mixing   major structures, machinery
shall be used
5 Concrete work  
6 Plastering mixing  
7 Plastering work 
8 Fill production  
9 Fill & compaction  
Stone collection and
10  
production
11 Fill and stone transport  
12 Cement and sand transport  

Note: - For Hand mixing, an excess of 10% cement shall be added in mix proportion.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 67


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

PART –2. Work Man Ship and Materials

2.1 Work Man Ship

The works are to be constructed using labor-intensive methods so far as such methods are
practicable and economic.
All workmanship shall be of the best quality appropriate to each category work. Except
where otherwise stated or approved by the engineer, all mater and shall be assembled in
accordance with in the Dimensional for structural work.
2.2 Material

All material used in the works shall be of the best quality of their respective kinds as specified
or described in the technical specification, Drawings and bill of quantities. The contractor
shall use locally produced materials preference to imported materials provided that they
comply with the specification and are available timely and in sufficient quantities.
The material shall be free from defect and imperfection and also recently manufactured.

2.3 Material Testing

Material testing shall be done in the field level or laboratory to maintain the degree of quality
here as specified or described in the technical specification.
The Contractor shall supply the Engineer with certificates of compliance obtained from the
suppliers of products such as cement, steel reinforcement, gabion boxes and other fabricated
materials and equipment used in the Works. Should the Contractor wish to change supplier,
certificates from the new supplier must be approved by the Engineer.
The Contractor shall provide, maintain and laboratory technical staffs with laboratory
equipment required for field/Site tests at his own expense throughout the Contract, to the
satisfaction of the Engineer. Where additional tests are required at Laboratory level, their
cost is also covered by contractor.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 68


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

2.4 Surveying Equipment

Surveying equipment’s with accessories are required but not limited to the following both in
number and type;
1. Total station with accessories 1
2. Automatic level 1
3. Level tripod 1
4. Level staff 2
5. Steel tape (50m) 1
6. Steel tape (5m) 1
7. Clipboard 1
8. Hammer 30kg 1

The provision of surveying equipment’s shall be considered among the Contractor’s general
obligations and shall not be paid for separately.
At the end of the project the equipment will remain the property of the Contractor.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 69


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

PART-3. Mobilization for Project Construction

3.1. Mobilization

Mobilization is understood to be the full process of furnishing all staff, labour, materials, tools,
equipment and incidentals necessary to perform, complete and maintain all works required for
moving in to the Site and shall include:

i. Transport of all items of equipment to the sites where they are to be used in the Works and
their installations;
ii. Supply of construction materials;
iii. Mobilization of all staff and labour to the Site; and
iv. Erection of all temporary works for Contractor’s facilities;
In other words, mobilization shall consist of preparatory work and operations including, but not
limited to, those necessary to the movement of personnel, equipment, supplies and incidentals to
the project site; and for all other work and operations which must be performed or costs incurred
prior to beginning work on the various items on the project site.

The Contractor’s Program shall include full details of her/his intended mobilization procedure.
This will ensure completion of the mobilization tasks given in paragraphs (i), (ii) and (iii) above
within the agreed specified date from the Start Date.

3.2. Demobilization

Demobilization shall consist of cleanup work and operations including, but not limited to, those
necessary to the removal of personnel, tools, equipment, and incidentals from the project site. It
should be communicated with potential stakeholders.
1. Demobilization of all staff and labour from the Site; and
2. Dismantling of the work site and removal of all installations, equipment and temporary works
so that the Site is left in a neat and tidy condition to the satisfaction of an Engineer.
Similarly, the Contractor’s Programme shall include full details of her/his intended demobilization
procedure.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 70


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

3.3. Payment

Payment for mobilization and demobilization will be made at the lump sum price shown in the Priced
Bill of Quantities.
Mobilization payment shall be in the proportion of mobilization performance with the approval of
the engineer.
The demobilization payment shall be effect with final payment upon completion of the contract
and removal of equipment and clean- up of the work areas to the satisfaction of the Engineer.

3.4. Camp facilities

All camps shall be located with the prior approval of the Engineer in collaboration with the
department responsible for Environmental Monitoring and Safety, Land use and Agriculture
and local officials at appropriate sites taking into consideration, not only the permanent works
but also the peculiar environmental and social situation of the area. Camps shall not be located
within or in the proximity of urban centers, on fertile farmlands/Irrigable area and forested lands
that are either owned by Farmers’ Cooperatives, Government Organizations, (eg Forestry
Priority Areas and other sensitive areas such as ecological sites; dense forests; banks of water
sources; and within wetland ecosystems) or NGOs. They shall be located at least 1km away
from streams and rivers.
Camp shall be constructed for employer representatives /consultant key personnel as per bill of
quantity and drawings of the contract. But the contractor shall design and provide drawings for
approval and accordingly construct camp for the housing, feeding and others services for his
workers or key personnel in the same camp compound specified for employer representatives
/consultant key personnel. Total cost of contractor Camp facilities to be approved by Engineer
in no case, shall not exceed lump sum in Bill of Quantity.
All hutments and building erected by the contractor on the site at his own expenses, shall, from
the time of their erection until the completion of the works is the property of the employer and
the contractor shall not be demolished or remove any buildings without the written permission
of the Engineer. On the completion of the works, they shall become the property of the
contractor who shall remove them entirely with all drains and restore the surface of the land to
its original condition or other reasonable condition to the satisfaction of the Engineer.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 71


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Contractually erected structures and/or buildings are the property of the Employer and will later
be transferred to the user community.
3.4.1 Measurement and Payments

The contractor shall submit a breakdown of the lump sum price bid for mobilization and
project construction, to the Engineer within ten days of the date of award of contract and/or
site possession. The breakdown shall reflect in reasonable detail as determined by the
engineer, the cost of each of the principal items of the work included for payment under the
contract lump sum prices and, subject to such revision as the Engineer may require, shall be
used as basis for partial and final payment as the work is performed.
Measurement will be made of the mobilization of facilities for project construction and work
related camp establishment.
For Lump Sum contracts, Payment will be made for lump sum prices. For admeasurement
contracts, payment shall be made multiplying the rate by the quantity of item completed.
3.5. Hours and days of working
The Contractor shall plan her/his work on the basis of a seven days of working week, for 8
hours. Should the Contractor require additional working hours, or weekend working, he shall
submit a request to the supervisor engineer for permission to work extended hours, giving
full reasons for the requests. Approval to such requests will not be granted on a regular basis,
but only in exceptional circumstances. Notwithstanding the foregoing nothing in this
Contract will restrict the Contractor undertaking any tasks at any time where such tasks are
essential for the saving of life or property or for the safety of the Works, in which case the
Contractor shall immediately advise the supervisor engineer.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 72


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

3.6. Project Signboard


The Contractor shall, within six (6) weeks of the receipt of the Letter of Acceptance (erection
may wait till site possession), provide and erect project signboards of size that can accommodate
project details with allowable space b/n words and lines written in Afaan Oromo and English
at locations directed by the Engineer. The Contractor shall maintain the signboards in good
condition.
The indicator post, sheet metal using RHS as column and stiffening, shall be of the required
dimension to at least indicate the name of the project, employer, contractor, consultant, source
of fund, project cost, distance and the command area and the number of beneficiary households.
The detail drawings are provided by Engineer in consultation of Employer’ representative.
Payment for signboard will be made as specified in Bill of Quantities forming the contract.
3.7. Fencing

3.7.1. Temporary fencing

The Contractor shall erect, maintain and remove suitable and approved temporary fencing to
enclose such areas of land, (such as Supervisor’s/Contractor’s offices and yards, construction
works being carried out beside buildings, canal, or footpaths and any other place where the
Contractor’s operations will endanger lives or public property), occupied by the Contractor within
the Site as may be necessary to implement his obligations under the Contract, to the satisfaction
of an Engineer.

3.7.2. Permanent fencing

The Contractor shall erect, maintain and suitable and approved permanent fencing to enclose
permanent structures but not limited to: -
Consultant and Client Camp Compound
Permanent fence can be constructed of 2.0m height & 15cm φ eucalyptus poles placed every 2m
with barbed wire at 20cm vertical interval & erected in 0.6m depth embedded with concrete
Payment shall be made in accordance with the agreed unite rate and the corresponding unit of
measurement in the contract.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 73


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

3.8. Dewatering
The Contractor shall be responsible for preventing the ingress of water into excavations.
The preventative measures shall include the construction of proper drainage channels; diversion
channels; sumps; the supply and operation of the necessary bailing and pumping equipment;
and the construction of suitable watertight cofferdams.
The dewatering measures, with the exception of pumping, shall be maintained until the
backfilling has been completed.
Between the various construction stages pumping may be interrupted as agreed by the Engineer.
Any draining or pumping of water from cofferdams or the interior of any foundation enclosure
shall be done in such a manner as to preclude the possibility of any portion of the concrete, fill
material or mortar materials being carried away and wet

3.8.1. Measurement and Payment

No separate payment will be made for Dewatering activities unless otherwise specified in Bill
of Quantities forming the contract.
3.9. Access, inspection or service road
Access, service and inspection roads indicated as per ERA standard in bill of quantities, shall
be done at least to the minimum standard set by Ethiopian road authority. Refer the detail from
Ethiopian road authority website. However, simple and temporary access roads, which are not
stated in the bid document; shall not be paid and shall be covered by contractor own cost.

3.9.1. Measurement and Payment

The measurement shall be either in kilometer or as per the unit of measurement indicated in the
bill of quantities. If the site requires major crossing structures than stated in the bill of quantities,
it shall be paid separately

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 74


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

PART –4 Excavation and Earthwork

4.1 Scope of Work


Before commencement of the actual work on the site, there shall be in agreement with the
Engineer about the existing ground levels.
This section covers excavation for access roads, Dam foundation, Spillway, Inlet and outlet,
road crossings and cross-drainage structures and compaction backfill of wing wall of cross-
drainage structure and disposal of all excavation except the necessary material for construction.
The disposal place shall be as ordered by Engineer. The disposal place shall be selected by site
the Engineer or Project Coordinator in consultation with the woreda. For projects having
access/Inspection road construction, the disposal (cart away) place shall be up to 3km and shall
be disposed in a manner and site/place approved by the Engineer. The method of disposal shall
comply with environmental, social and other safety issues stated in this contract and general
regulations.

4.2. Clearing and Grubbing


Scope
This Division covers the clearing of the Site and grubbing necessary for the construction of the
permanent Works in accordance with these Specifications; and the removal and disposal of
materials resulting from clearing and grubbing. This work shall also include the preservation
from injury or defacement of all vegetation and objects designated to remain.
Description of Work
a. Clearing
Where directed by the Engineer, clearing shall consist of the removal of all trees and tree roots,
fences and all other existing structures other than simple site clearing works as specified
including the disposal of all material resulting from the clearing and grubbing to a maximum
depth of 200mm.

It shall also include the removal and disposal of structures that obtrude, encroach upon or
otherwise obstruct the work and which can be cleared by means of a labor, loader, excavator,
bulldozer of 22tonne mass and flywheel power of 270kW. This also includes the demolition
and removal of any other masonry or concrete structures that obstruct the work.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 75


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Any trees, structures or artefacts, either identified on the Drawings or noted on Site for care and
retention, shall be clearly marked off on the Site in a manner approved by the Engineer to avoid
accidental damage during construction operations. Should any such identified trees, structures
or artefacts be damaged inadvertently, or otherwise, the Contractor must report the same to the
Engineer in writing explaining any known reasons for the damage. Damage deemed to be
caused by the negligence of the Contractor shall be repaired at the Contractor’s cost.
b. Conservation of Topsoil
Where topsoil exists within the limits of the area to be cleared and/or grubbed, the Engineer shall
designate areas for removal of the topsoil together with any grass and other suitable vegetation. If
not used immediately, the topsoil shall be transported and deposited in stockpiles for later use.
c. Conservation of Vegetation
Where provided for in the Contract, certain designated plants encountered in the reservoir area
buffer zone and borrow areas shall be carefully protected by the Contractor.

The tendered rate for the specific measurement and payment item shall include the general
requirements
Clearing and grubbing ............................................................................ M2

4.2 Classification of Excavation Materials


4.2.1 General
The terms of the below formations are hereby defined for the purpose of this contract only for
classifying excavated materials for payment.

a) Hard Rock (sound rock)


This classification covers the basaltic or other rock type, which is black, dark grey and etc in
color. This rock is very hard. The normal means of excavation requires the uses of explosives.
Where blasting is not permitted, the contractor shall use heavy-duty rock breaking equipment.
Highly interlocked boulders of wide areal extent (above 2 meter in both ways) that require
machine to be excavated will be included under this type of rock. Slightly fractured rocks that
require heavy-duty machine to be excavated shall be grouped under hard rock.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 76


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

b) Soft Rock
This classification may include but not necessarily limited to basaltic and ignimbrite rocks. It is
rather soft, can easily be hewn, and can be excavated by means of sledge hammers, wedges and
miners bars. Isolated volume of boulder of any size interlocked to a reasonable degree that
require manual materials or simple machine are also grouped under this type of rock. Moderately
to highly fractured/jointed and/ or weathered rocks are categorized under soft rock. Volcanic
ash, tuff, river deposits and highly weathered materials are grouped under soft rock.
c) Earth
Earth shall mean all material except hard and soft rock as defined above in clauses a and b. Earth
shall include, but not necessarily be limited to, all geologically recent materials overlying rock
such as alluvium, black-cotton and talus, all layers of earth which are cemented so that the earth
becomes conglomerate, decomposed materials shall be considered as earth.

d) In all formation
In all formation shall mean excavation in hard, soft rock and earth materials.
e) Formation classification: - the formation classification for estimating of rate is as follows.
The depth classification works for all types of formations.
Depth of
0-1.5m 1.5-3m >3m
excavation

4.2.2 Excavation Open Cut


a) Excavation Method
The contractor shall perform all open cut excavation and grading to the final elevation lines and
grades shown on the drawings or approved by the Engineer. The rock Excavation in the
foundation area of the structures shall be done by such care full methods as line route cutting
or chiseling using skill labor. The contractor plan his excavation operations in the rock area in
such manner that the bulk of material produced is of < 30mmsize. The responsibility for the
success of excavation method shall rest with the contractor regardless of approval by engineer.
The rock excavation from the main canal and others structures’ foundation area be stockpiled
as per instruction of the Engineer.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 77


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

b) Excavation Extent
Excess excavation performed by the contractor for any purpose or reason, except that order in
writing by the engineer, shall be at the expense of the contractor. All excavation for structures
shall be carried to foundation material satisfactory to the engineer regardless of whether the
elevation therefore is higher or lower than the elevation shown on the drawings. All necessary
precautions shall be taken to preserve the material below and beyond the lines of all excavation
in undisturbed conditions. All over excavation required by the engineer to be backfilled shall
be back filled by the contractor in the accordance with the instruction of engineer. Materials for
use in the work shall be carefully excavated to produce the material in form suitable for the
work.
c) Excavation allowable
Except for trench excavation and Earthen channel excavation, Excavation for structures
construction shall be performed within the working space for excavation limits indicated below.
The following table illustrates the depth of excavation and the tolerance to be applied .
Depth of excavation 0-1m 1-2m 2-3m >4m
Working Space 15cm-20cm 21cm-40cm 41cm-60cm 61cm-1m

4.2.3. Measurement and Payment


The measurement and payment for excavation shall be according to the type of excavation that
is hard rock or soft rock or earth, as classified in the field by the engineer. The item rate for
payment of excavation with tolerances as specified under excavation tolerance for backfill or
waste shall include the disposition of material in the specified manner. Payment will be made
for the number of excavated cubic meters measured as provided above at the contract unit price.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 78


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Part -5 EARTHWORKS AND EMBANKMENT CONSTRUCTION


5.1 Dam Embankments

The dam embankments shall consist of compacted clay core, granular shell and rock fill. The
various filters and drains, shall also be included. The upstream slope of the Dam shall have riprap
protection.

The embankment shall be constructed to conform at the end of the Defects Liability Period to the
finished levels shown on the Drawings.

The Contractor shall provide and maintain proper profile rails showing the position and inclination
of the various slopes.

Notwithstanding this condition, lengths of the dam embankment may be constructed at different
times, with the requirement that the temporary transverse slope (in a direction parallel to the dam
axis) of the placed fill (to include core and shoulder zones) does not exceed 1:4 (vertical :
horizontal). When the fill placing is recommenced against this slope, it shall be first cut back to
well compacted material, without shrinkage cracks and with the correct moisture, for the core
material. The new fill shall be thoroughly keyed onto this slope by supplementary compaction in
an upstream-downstream direction, where each new layer meets the slope.

The new fill layers will connect to the existing fill by cutting in the existing slope “steps”
(horizontal) of 3 core layers depth on which the end of the new layer shall be compacted. The
“steps” shall be cut one at a time.

The difference in elevation at the boundaries between adjacent material zones shall not exceed 0.5m.

All material for the riprap protection, the rock fill, shell, clay core and the various
filters/transitions/ and drains shall be obtained from sources approved by the Engineer. Potential
Borrow Areas, Potential quarry locations which have been investigated within and outside of the
reservoir area, may be utilised by the Contractor for rock, shell and core material, as long as the
requirements of this Specification (with respect to these materials), are satisfied.

5.2 Dam Fills – Materials

This specification covers materials for permanent earthworks in the form of the Main
Embankments and backfill behind structures, as well as temporary earthworks such as the
cofferdam.

Although quarries and Borrow Areas should be opened to provide the fill materials required,
nevertheless it is anticipated that substantial proportions of material obtained from excavations

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 79


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

will be suitable for use as fill in the dam. All reasonable measures shall be taken to maximize use
of excavated material in the permanent works.

Materials shall not be transported to the Site until all tests, analyses and final inspections have
been made and certified copies of reports of tests and analyses or manufacturer's warranties have
been submitted to the Engineer. The tests specified in the standard Specification shall be carried
out by the manufacturers of the materials or by an approved testing laboratory and three certified
copies of test reports shall be supplied.

5.2.1 Impervious Fill

Material for impervious fill shall be core material or alluvium from the borrow pits or dam
excavation with at least 35% of the material by weight finer than 0.075 mm (No. 200 BS
sieve) and 70% finer than 5 mm. It shall have a minimum Plasticity Index of 15. Maximum
particle size shall be 50 mm.

Earth fill Material for construction of the core zone for the embankments shall be taken from
the approved sites. The material shall lie within the grading limits given in determined by
Test Methods 9.2 and 9.5 of BS 1377: Part 2: 1990.

As far as practicable, the core materials shall be conditioned in the borrow pits before
excavation. Where the natural moisture content of the materials in the borrow pits is higher
than required, it shall be exposed to the air, scarified and ploughed in order to reduce the
moisture content uniformly prior to excavation.

If, before excavation operations at any location in the borrow pits, the moisture is lower than the
target moisture, additional wetting shall be introduced into the borrow pits by irrigation,
at least 3 Days in advance of excavation operations. Care shall be exercised to moisten the
material uniformly prior to excavation, avoiding both excessive run-off and accumulation of
water in depressions.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 80


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

5.2.2 Filter and Drainage Materials

5.2.2.1 Shell Material

The upstream shell affords stability against end of construction, rapid drawdown, earthquake,
and other loading conditions. The downstream shell acts as a drain that controls the line of
seepage and provides stability under high reservoir levels and during earthquakes. For the most
effective control of through seepage and seepage during reservoir drawdown, the
permeability should increase progressively from the core out toward each slope.
Shell materials shall be reasonably free of deleterious Substances like lumps of clay, organic
matter, and other substances not defined which may possess undesirable characteristics. The
material shall not contain silica sand in sufficient quantity to prevent bonding.
Plasticity (AASHTO T89 and AASHTO T90) - That portion of the material passing the No.
40 sieve shall be non-plastic. Carbonates (FM 5-514) - The minimum percentage of
carbonates of calcium and magnesium shall be 50.

Graduation Requirements: Materials classified as dredged shell shall meet the


following graduation requirements:

5.2.2.2 Filter Material

These shall comply with the following requirements:

Fine (F1) and coarse filter (F2) are required for filtering and discharging purposes. IF proposed
filter sources seemed to have much fine content and hence it will need processing during
implementation such as washing the silt. Alternatively, sand for either filter or concrete works can
be obtained by crushing. Therefore, the contractor should confirm the suitability of the proposed
sources for the mentioned purpose and should proceed if any only if gets approval from the
engineer. If this is not possible alternatives should be presented to the engineer for his approval.

The water absorption (ASTM C128) shall not exceed 4%, the percentage wear in the Los Angeles
abrasion test (ASM C131) shall not exceed 35% and when subjected to the sodium soundness test
(ASTM 88) the weighted average loss after 5 cycles shall not exceed 12%.

Filter materials after compaction shall be evenly graded within the limits Material which has
become mixed or contaminated with other fill materials shall not be used.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 81


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Materials for the various filters, and drainage layers shall be obtained from sources approved
by the Engineer and shall conform to the grading requirements given in Table below as
determined by Test Methods 9.2 and 9.5 of BS 1377: Part 2: 1990.

5.2.2.3 Riprap/Stone Material

Riprap is an assemblage of rocks “nested” together to protect a structure or area


from the action of water. The rock lumps forming the riprap protection to the dam shall be graded
by weight in accordance with the requirements given in Table below.

The rock lumps shall be dense, sound, angular and resistant to abrasion and the river water
composition and shall be free from cracks, seams, weathering and other defects that would
tend to increase unduly their destruction by water. Water rounded boulders shall not be used.

Riprap Stone shall be hard field or quarry stone not susceptible to disintegration or
excessive weathering on exposure to the atmosphere or water. It shall be free from soft
material such as sand, clay, shale or organic material and shall not contain an excessive
amount of elongated or flakey stone.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 82


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Riprap grading Limits

Samples prepared in accordance with applicable designations of the US Bureau of


Reclamation's "Concrete Manual", eighth edition, shall meet the requirements given in Table
below.

5.2.3 Rock Fill


Rock fill material shall be approved rock fill obtained from the quarries or excavations. The
material shall comply with the grading limits shown in Table below.In addition the fines
(passing 0.425mm) shall be non-plastic, as determined in accordance with Methods 4 and 5
of Bs 1377: Part 2: 1990.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 83


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Grade of rockfill

The rock types are Basaltic hard rock which is available within short. . Rock fill material shall be
approved rock fill obtained from the quarries and structural excavations such as spillway.

5.2.4 Backfill to Structures

Material for backfill shall be either durable, free-draining, well-graded crushed rock with a
maximum size of 75 mm or earth fill as specified above, as shown on the Drawings or directed by
the Engineer.

5.2.5 Dam Fills - Placing and Compaction

This specification covers permanent earthworks in the form of the main embankment and backfill
behind structures and temporary cofferdams.

The embankments shall comprise core, selected filter, granular shell, drainage and rock fill
materials.

The Contractor shall provide and maintain proper profile rails showing the position and inclination
of the various slopes. No filling will be approved in the absence of proper setting out and survey
control.

The Contractor shall take all measures necessary to ensure the safety of personnel working at the
toe of external embankment slopes, including catch fences and such other measures as are
considered necessary by the Engineer. Notwithstanding the foregoing the Contractor shall remain
solely responsible for the safety of the Works and all personnel.

5.2.6 Trial Fills

Before placing any fill in the permanent Works the Contractor shall construct a trial fill, for the
construction of the dam embankment, using the plant and materials he proposes to use for the
permanent works. The purpose of this trial fill is to determine working practices necessary to
achieve the required in-situ density and moisture content and to demonstrate that the Contractor's

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 84


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

working methods and equipment are satisfactory. The trial fill shall be constructed in a location to
be agreed with the Engineer.

If there is a change in the nature of the fill material, the Engineer may direct that additional
laboratory tests and/or trial fill are required to assess whether any change in working practice is
required. The Engineer shall decide which additional laboratory tests are required and the
Contractor shall comply and submit the test results for the Engineer’s approval of the said material.
If the Engineers rejects the material shall not be used by the Contractor for the dam construction.

The trial fill shall be so located as to allow a clear run of at least 50 m for the fill and the compaction
equipment and shall contain not less than 2000 m3 of each of the following:

a. Compacted shoulder fills


b. Filter and Drainage fills

The Contractor shall use the same equipment and techniques to construct the trial fill as that
which he proposes to use to construct the main embankment. In coordination with the Engineer
the Contractor shall determine on the trial fill the layer thickness, loading of the rollers and the
number of roller passes required to achieve the specified degree of compaction.

In demonstrating his working methods the Contractor shall cover the following items:

a. Setting out
b. Layer thickness control
c. Spreading and grading of fill
d. Wetting of fill material (in addition to Borrow area wetting)
e. Compaction of fill
f. Reworking of a failed layer
g. Removal of a failed layer
h. Method of working after rain
i. Control and finish of upstream and downstream face of dam.

The fill placed in the trial fill shall cover the full range of moisture contents permitted.

In addition to in-situ density moisture content and laboratory compaction tests to demonstrate
conformity to the specified degree of compaction, the Contractor shall carry out other testing and
investigations as agreed with the Engineer, to provide an independent check on the density
achieved. This shall include:

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 85


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

▪ Levelling the surface of each layer in a 1.5m grid between each pass of the roller
to determine the relationship between settlement and number of passes.
▪ Particle size distribution tests.
▪ Trial trench to examine segregation within layers and degree of interlocking
between layers.

Before commencing the trial fill the Contractor shall submit in writing his proposals for carrying
out the trials for the approval of the Engineer. On completion of the trial fill the Contractor shall
submit a report on the trials to the Engineer.

No fill shall be placed as part of the permanent works until the trial fill relevant to that section of
work has been completed, and the approval of the Engineer.

If the fill material changes: textures/color/gradation/characteristics etc., It shall not be placed as


part of any dam unless the Contractor proves with lab. Results and trial fills, the show that said
material to be suitable for the zone in which it is supposed to serve as fill and answer the
specification demands, fully, satisfying the Engineer and after his approval in writing.

5.2.7 Equipment
5.2.7.1 Vibratory Rollers

Vibratory rollers shall have a total static weight of not less than 15 ton with at least 90 percent of
the weight transmitted to the ground through a single smooth drum for granular material and pad
foot (7” high) roller for core material, when the roller is standing in a level position. The diameter
of the drum shall be larger than 1.5 m. The frequency of vibration during operations shall not be
greater than 25 Hertz, for core and 32 Hertz for filter and drainage materials and at those
frequencies; the dynamic force shall be not less than 18,000 kg. The roller shall be operated at
speeds not to exceed 3km per hour. The character and efficiency of this equipment shall be subject
to the approval of the Engineer. The same weight, static/dynamic forces, velocity, etc., are required
of self-propelled vibratory compactors.

5.2.7.2 Power Tampers

Compaction of material, in areas where it is impracticable to use a heavy roller or tractor, shall be
performed by the use of approved power tampers or vibratory rollers of smaller size, which will
give the Target Density at the correct moisture.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 86


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

5.2.7.3 Impervious Fill

Earth fill shall be placed and compacted in continuous layers which are approximately horizontal
and not more than 150 mm compacted thickness, or as directed by the Engineer. Vibratory roller
or similar with the recommended type of drums approved, shall be used.

Before placing any layer, the surface of the underlying layer shall be moistened and/or worked
with a scarifier or other suitable equipment if in the opinion of the Engineer such moistening or
working is necessary to ensure that there is a satisfactory bond between the two layers.
Furthermore, before placing a new layer, any material in underlying layers shall be removed or
re-worked to the satisfaction of the Engineer if in his opinion:

▪ It has been compacted outside the limits of moisture content specified herein, or
▪ It has received less compaction than specified herein, or
▪ It has been cracked by drying, softened by wetting, or damaged by any other cause.

At the time of compaction in the embankment, each portion of the fill shall have moisture
content within the range "Proctor Optimum Moisture Content" (OMC) to OMC + 2%, or within
such other range related to the Proctor Optimum as the Engineer may determine.

If it is necessary to add water, this shall be done well in advance of placing by spraying at the
borrow pits. Supplementary water may be added on the embankment, but only from tankers
producing a uniform spray controlled from the cab. Water tankers with leaky valves or fittings
will not be permitted on the embankment. If it is necessary to dry the material all necessary
work such as ripping, aeration with rotary cultivators, harrowing, etc. shall be carried out before
transporting the material to the embankment.

The Contractor shall be responsible for ensuring that the moisture content of each portion of fill
is uniform and within the specified limits at the time of compaction and shall use such plant as
may be necessary to achieve this.

Any material which has been placed in the embankment and prepared for compaction at
moisture content outside the limits specified and any material being compacted, which has been
damaged by drying or wetting or any other cause, shall be removed or re-worked to the
satisfaction of the Engineer.

Holes formed in the embankment by the removal of samples for tests shall be filled tamped and
consolidated in homogeneity with the surrounding fill.

The routes taken on the embankment by vehicles and mechanical plant shall be varied to avoid
tracking and local over compaction.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 87


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Impervious fill shall be compacted in such a manner that the average percentage compaction of
the fill at any time defined as the ratio Filed Dry Density to Laboratory Maximum Dry Density
shall be not less than 98%.

Material which has been compacted to a dry density less than that required by this Specification
or at moisture content outside the specified range shall be removed or re-worked and re-
compacted until the required properties are achieved. In this case the field dry densities recorded
before removal or re-compaction of the material shall be omitted from the calculations of mean
percentage compaction and standard deviation.

5.2.7.4 Filter and Drainage Material

Filter materials associated with the concrete face are to be placed next to slopes of up to 1
vertical to 0.3 horizontal. The Contractor shall form and compact the inner slopes to form a
neat, uniform and workmanlike appearance.

Great care shall be taken to avoid segregation, and where this occurs the coarse material shall be
removed and replaced by material of the specified grading.

The filter, granular shell and drainage layers shall be placed in approximately horizontal layers
not exceeding 200mm compacted thickness.

Each layer shall be thoroughly compacted by means of a vibrating compaction machine (static
weight between 15 and 25 kg/cm of drum) to achieve a minimum field dry density of 93% of
maximum index density.

In order not to “Contaminate” the filter material by impervious core material or coarser
transition zone material, the Filters will always be placed 1 layer above the adjacent fills of core
material on one side and coarser filter/transition zone on the other side.

In the horizontal “Drainage Carpet”, the layers being horizontal, the above procedure doesn’t
apply.

5.2.7.5 Rock fill

The material to be compacted shall be off-loaded on the previously finished compacted and
approved layer, as continuation of the Present Rock fill layer be spread, pushed and levelled by
means of bulldozers or other suitable equipment over the face in such a manner that the fine
material is well mixed with the rock. Hauling, spreading and compacting equipment shall be
routed uniformly over the full width of the layer to be compacted. After the material has been
dumped on the fill, oversize material be bladed off the fill and disposed of so that layer thickness
need not be dictated by the presence of isolated large rocks.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 88


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

The Engineer may direct that additional action be taken and the Contractor will abide.

Unless otherwise indicated on the Drawings, rock fill shall be compacted in continuous layers
which are approximately horizontal and not more than the thickness given in Table below or as
determined from the trial fill. Each layer shall be compacted by vibrating rollers. The compacted
surface shall have a uniform appearance; concentrations of large stones shall be removed and
replaced by finer materials.

Water shall be sprayed/flushed on the rock fill in a volume of 15% *** of the rock fill volume;
the spray being distributed uniformly over the layer.

Water shall be added as necessary to the other rock fill zones to maximize the density that is being
achieved. This will be determined from the trial fill, although subject to amendment as directed
by the Engineer.

Rock fill Materials


Function Placing & Compaction****
Zone Layer Thickness after No of passes of a 17 t
compaction, m ** vibratory roller ***
4 Upstream shoulder 0.9 4
4 Downstream shoulder 0.9 4
** Subject to amendment following the trial fill
*** Subject to Results and amendment following the trail fill by a 17t toed vibratory roller
****
If the results show the need for a bigger/different type of compactor/roller the Contractor shall present the
new substitute compactor/roller characteristics for approval only after trial fill results show the substitute to
be adequate to his satisfaction shall the Engineer approve it in writing.

5.2.8 Backfill to Structures

Backfill shall be placed in layers not more than 200mm thick and lightly tamped if the material is
crushed rock, or compacted to a density of not less than 95% of Standard Proctor optimum density
if the material is earth fill.

Within 1 meter of concrete structures the method of compaction shall be such as to avoid damage
to the structure. Compaction shall be by means of compressed air tampers rather than heavy rollers,
and the layer thickness shall be adjusted accordingly to achieve the required density of the
material.

5.2.8.1 Fill Sampling

The Contractor shall take samples as directed by the Engineer to enable the following tests to be
carried out:

a. Field bulk density and moisture content

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 89


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

b. Laboratory compaction
c. Particle size distribution
d. Plastic and liquid limits

The minimum rate of sampling and testing shall be as shown in Table below

The actual frequency of sampling may be greater than this and shall be determined from the results
of previous tests, the quality of the material revealed during such tests and the uniformity of such
quality. The frequency may be amended as required by the Engineer.

In the event that individual compaction tests on samples of fill material result in widely ranging
values for Proctor Optimum moisture content and Proctor Maximum dry density, and maximum
index density the Engineer may require that during the construction of the trial embankments and
from time to time during the construction of the actual embankments, laboratory Proctor
compaction and maximum index density tests shall be carried out at the same frequency as field
density tests on material taken from the fill adjacent to the location of the filed density test.

Should the fill placed, in the opinion of the Engineer, be likely not to comply with the
Specification, the Contractor shall, if directed by the Engineer, Carry out additional tests.

Minimum Rate of Sampling and Testing


Location of Material Quantity of fill placed per sample (m3)
Field density
and Laboratory Particle
Relative Density Shear
moisture compaction size Permeability
Density in Place strength
content test * distribution
tests
Core * 400 1200 2400 4,000 3-4
Filter 400 2400 1200 2400 **
occasionally
Drainage 400 2400 na 2400 -“-
Backfill to 250 500 500
structures
Granular pervious 250 500 500 -“-
fill
Rock fill 15,000 4,000 -“-
Note: * Also to include Plastic and Liquid Limits
** As directed by the Engineer

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 90


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

5.2.9 Field Density and Compaction Testing


5.2.9.1 Granular Materials

Test methods shall be as follows:

a) Field Density of all Rock fill

ASTM D5030-89 'Density of Soil and Rock in place by the Water


Replacement Method in a Test Pit'.

b) Field Density of Filter, granular shell and Drainage Materials (Filter and
transition zones) BS 1377: Part 9:1990 Section 2.2 'Sand replacement method
suitable for fine-medium and coarse-grained soils (Large pouring cylinder
method).
c) Moisture Content

BS 1377; Part 2: 1990 Section 3.2.

d) Maximum Index Density

ASTM D4253-93 'Maximum Index Density and Unit Weight of Soils


using a Vibratory Table'.

Both dry and wet methods shall be carried out, and the maximum index density taken as
the higher of the results of the two test methods.

The laboratory maximum index density and moisture content shall be corrected to allow
for the particles larger than 75 mm in the field grading using the following equations:

 1 − 0.05 (I − F ) 
YF = YL G  
 (I − F )YL + FG 

WF = FWL + (L − F )Ws

Where:

F Ratio of dry mass of % passing 75 mm to dry mass of whole filed grading

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 91


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

I Laboratory maximum index density

G Bulk specific gravity (oven dry) of particles larger than 75 mm

WL Laboratory moisture content

Ws Moisture content of particles larger than 75 mm

WF Filed moisture content

5.2.9.2 Impervious Fill

Test methods shall be as follows:

All standards quoted shall be of the latest update. Dates below, referred to, specify the exact
location of the discussed subjects.

a. Field Density

British Standard BS 1377: Part 9: 1990, Section 2.2 "Sand replacement method suitable
for fine, medium and coarse-grained soils (large pouring cylinder method)". This test
is commonly referred to as the "Sand Replacement Test".

b. Moisture Content

BS 1377: Part 2: 1990 section 3.2.

c. Proctor Maximum Dry Density

British standard, BS 1377: Part 4: 1990, Section 3.3, "Method using 2.5 kg rammer for
soil with particles up to medium-gravel size", and Section 3.4 "Method using 2.5 kg
rammer for soils with some coarse-gravel size particles". This test is commonly
referred to as the "Proctor Compaction Test".

The "Proctor Optimum" moisture content (OMC) shall be defined as "the moisture content
which will result in a maximum dry unit weight of soil when subject to the Proctor Compaction
Test".

5.2.9.3 Tolerances

Earthworks shall be constructed within the following tolerances:

Vertical elevations - 0mm/ + 100mm

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 92


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Horizontal dimensions - 250mm/ + 250mm

5.3 Borrow Areas and Quarries

The Contractor will excavate provisional Test Pits in each Borrow Area as directed by the
Engineer to verify the amount of the available material in placement and depth, approved by the
Engineer.

Each Test Pit shall be logged for its material layers. An accurate map of each Borrow Area or
Quarry shall be submitted to the Engineer’s Representative for approval.

The map shall be to scale and include for each Test Pit: the logs, including material description,
layers thickness, depth of Test Pit and any other data demanded by the Engineer.

All Alluvium, Rock fill and core materials for the dams shall be obtained from the borrow areas
(BA), spillway excavation and quarries (Q) shown on the Drawings. The BA & Q for material for
the core zone and embankment shoulders should have been proved to contain adequate quantities
for construction of the Works, by the additional test pits the Contractor has excavated, within the
areas expropriated by the Employer.

The location and extent of additional borrow pits within borrow areas shall be as agreed with the
Engineer.

In operating the borrow areas and Quarries the Contractor shall take due note of the variable
moisture conditions which occur throughout the year. The Contractor should note that there will
be a seasonal variation in groundwater levels and a consequent variation in the natural moisture
content depending on the extent and intensity of the rainfall in the wet season (normally July to
September). This variation will extend into the dry season and the Contractor should take
appropriate measures for either “drying out” or “wetting up” the fill material as appropriate.
Borrow and Quarry areas shall be operated such that slopes are free draining, with the provision
of temporary drainage ditches as required.

The Contractor should stockpile separately Construction material of each type to be used for the
works in enough quantity to ensure the continuation of the works without interruption.

Each type of construction material shall be stockpiled in separate storing area approved by the
Engineer and kept from mixing with other type Construction materials, by methods approved by
the Engineer.

Final excavated surfaces of borrow pits shall be graded to slopes not steeper than 1: 1.5 for Borrow
Pits and 1:0.5 (vertical : horizontal) for Quarries. They shall be operated so as not to impair the
usefulness or mar the appearance of any part of the Works or any other property of the Employer.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 93


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

The surfaces of heaps of rejected materials shall be trimmed and left in a reasonably smooth,
drained, and even condition. Where final slopes of borrow pits extend above full supply level,
these shall be hydro seeded.

Other than as shown on the drawings as part of the construction of the Works, no excavation for
fill material shall be permitted within 100 m of the upstream toes of the different dams
embankments.

In any case a blanket of at least 1m thick impermeable material shall be left at the bottom of the
Borrow Areas, to ensure minimum seepage.

5.4 Permitted Deviations

Except as limited by minimum thickness of thin zones the deviations from the defined boundary
between the various zones shall not exceed the tolerances given in Table below.

Permitted Deviations
Maximum deviation measured
Boundary
horizontally (m)
Item
Towards the Towards the
former zone latter zone
1. Between the core zone and the shoulder zone 0.0 0.5
2. Between the nominal core zone and the 0.3 0.0
chimney drain
3. Between the shoulder zone and the chimney 0.3 0.0
drain
4. Between the shoulder zone and the drainage 0.3 0.0
blanket
5. Between the shoulder zone and the Carpet 0.3 0.0
Drain
The tolerance requirement for the horizontal drains shall be to maintain a minimum slope of
1:30.

5.5 Compaction Trials

Prior to placing any embankment material in the Works the Contractor shall construct trial
embankments using the earth fill materials for core zone, cofferdam material and the embankments
shoulder excavated from the proposed borrow/ quarry areas.

In constructing the trial embankment, the same Equipment and technique shall be used by the
Contractor as that which he proposes to use in constructing the embankment properly. In
collaboration with the Engineer the Contractor shall determine the number of roller passes and the

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 94


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

loading of the rollers required to achieve the degrees of compaction specified for the embankments
shoulder zones and the core zone.

Self-propelled towed rollers shall be pulled by tractors which are adequately powered to work
satisfactorily when the rollers are fully loaded, including working on slopes.

5.6 Preparation of Foundations and Abutments in Rock

Where material for the earth fill core is to be placed against rock foundations or abutments the
rock shall be excavated to the lines and dimensions indicated on the drawings. The rock shall be
so shaped as to form a smooth and regular surface to the satisfaction of the Engineer so that the
core can be properly compacted against it. All cavities, fissures, and areas where a smooth surface
cannot be achieved shall be treated with concrete.

Before placing the earth fill core material against the rock foundation all obvious cracks in the
rock shall be cleaned out and cement slurry in the proportions of:
1 Part Cement: 2 Parts Water shall be spread over the contact zone and in the cracks.

5.7 Excavation of Cut off Trench at Dam

The cut off trench at the Dam will be founded, as indicated on the Drawings or as directed by the
Engineer.

Where the cut off trench is founded on rock, the sequence of excavation shall be:

a) Excavate down to rock level.


b) Excavate moderately weathered or partially weathered rock to depths directed by
the Engineer, by the use of hydraulic breakers, jack hammers or other such
equipment for the excavation in rock (blasting of the rock will not be permitted).
c) Clean up of the exposed rock, including picking and barring of loose rock.
d) Place cement slurry over the exposed rock surface, at locations as directed by the
Engineer to the requirements specified.

5.8 Construction of Clay Core

Materials approved for inclusion in the core of the embankment shall be compacted in layers not
exceeding 0.2m before compaction and in such a manner that field densities as measured in-situ
using Test Nr 15(B) of BS 1377 achieve a compaction of not less than 98% when compared with
the maximum dry density arrived at by means of Test Nr 12 of BS 1377 (standard proctor - 2.5 kg
hammer method). The moisture content of the material shall be controlled preferably at the borrow
area as specified in Clause 5.9, to give uniformly distributed in-situ moisture content after

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 95


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

compaction, as a percentage of the optimum moisture content determined by Test Nr 12 of BS


1377 (2.5 kg rammer method) as defined in Table hereunder.

Percentage of Optimum Moisture Content


Location Percentage of Optimum Moisture Content (OMC)
Core Zone Between OMC and 2% wet of OMC
Where compacted material does not meet the requirements specified above, it shall be removed
or re-worked as indicated by the Engineer. If for any reason the surface of the earth fill material
becomes so smooth or dry that, in the opinion of the Engineer, it cannot be properly bonded with
the succeeding layer, then the Contractor shall remove the surface layer and scarify or water the
newly exposed surface, or both, to the satisfaction of the Engineer, before recommencing filling
operations.

If smooth rollers are employed, the surface of the clay shall be scarified and target moisture kept,
before a further layer is placed on top.

Where the material is placed against the sides of the core trench, steep rock faces or the spillway
walls, it may be necessary to use hand held compacting equipment to achieve the required degree
of compaction.

The surface of the core shall be sealed by rolling with a smooth roller or other approved means
and an adequate cross-fall provided during or before rainfall in order to facilitate surface
drainage and prevent the ingress of water into the core material.

5.9 Construction of Riprap Protection

Approved material for inclusion in the riprap protection shall be transported without intermediate
handling direct to the point of final use, where it shall be dumped and graded off in a manner to
ensure that the larger rock fragments are uniformly distributed and the smaller rock fragments fill
the spaces between the larger rock fragments to form compact uniform layers of riprap of the
specified thicknesses as shown on the Drawings. Hand placing will be required only to the extent
necessary to secure the results specified above.

5.10 Construction of Internal Drainage Layers and Filters

The drainage layers, and filters in the dam embankment shall be constructed of material complying
with the requirements.

As the drainage layers or filters are steeply inclined 1:0.4 (vertical: horizontal), they shall be
brought up in 0.30 m horizontal layers, and compacted by approved vibratory equipment to achieve
the specified density. As specified formerly, the filter and drainage layers shall be at all times at
least 1-2 layers higher than the core material and rock fill. This will prevent the introduction of

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 96


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

other material into the filter/drainage material. The filter fill will always be 1 layer higher than the
drainage layer. This will not apply for the horizontal “Carpet Drain”.

Where the material is to form filter/drainage layers which are horizontal it may, subject to the
approval of Engineer, be placed in layers not exceeding 0.30 m in thickness after compaction.
During or immediately prior to compaction, the material shall be thoroughly wetted. The outer and
inner boundaries of each layer shall be true to the lines, dimensions, elevations shown on the
Drawings.

It is of the utmost importance to ensure that the drainage layers and filters are not contaminated by
other fill materials and the Contractor shall ensure that constructional traffic does not cross such
sections of the embankment or otherwise contaminate the drainage or filter material. If, the
Contractor finds out that, or in the Engineer’s opinion, contamination does take place, the
contaminated material shall be removed from the Works and the Contractor shall have no claim
for payment for such material so removed.

The Density Index (ID) of the compacted material shall not be less than 70% as determined by
Test Method Nr 4 of BS 1377: Part 4: 1990.

5.11 Control of Moisture Content

Moisture content of the embankment material shall be controlled as far as practicable at the borrow
pits as defined to give uniformly distributed in situ moisture contents after compaction within the
limits given for the various materials. Supplementary water, if required, may be added to the
material by sprinkling on the embankment and shall be mixed uniformly throughout the layer
before compaction.

Measurement and Payment

The rates tendered shall include full compensation for the excavation, hauling, spreading,
showering and compaction of surfaces

Payment will be made for the number of compacted cubic meters measured as provided above at
the contract unit price per cubic meter for shell material

Collectively the rates shall also include full compensation for all other incidentals necessary for
completing the work as specified.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 97


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

5.12 Test on Embanking Material

Whilst embanking is in progress periodic site tests will be made by the Engineer in the borrow
pit and on the material, to ascertain the grading, moisture content, index properties, compaction
characteristics and other such properties of the embanking material.

Unless otherwise approved by the Engineer field control tests of the core and shoulder materials
will be made for every layer, or approximately every 400 m³ of material placed to ascertain the
density and moisture content of the fill, to ensure adequate compaction.

Tests will be made by the Engineer’s Representative on the filter, drainage and bedding material
for approximately every 200 m³ placed on the embankment.

All tests will be made in accordance with the various parts of BS 1377: 1990 where applicable or
in accordance with other recognized standards, as specified.

In all cases the tests will be performed at the laboratory provided in accordance with under the
supervision of the Engineer but the Contractor shall deliver samples to the laboratory as required
by the Engineer.

The performance of the tests specified in no way relieves the Contractor of his responsibility to
ensure by similar test or any other means that the embanking materials are placed in accordance
with the requirements of this Specification.

Laboratory Testing Equipment

The following materials test shall be conducted either with fully equipped laboratory unit on project site
or conducted in arranged laboratory unit to carry out the tests listed below in accordance with the
procedures laid down in British, or other approved standards. Frequency of sampling and sample size
shall be based on the

a) Embankment Materials:

i) Determination of moisture content.

ii) Determination of the density/moisture relation for soils (standard and modified Proctor
compaction test).

iii) Determination of dry density of soil in the field.

iv) Particle size analysis (by sieving and hydrometer).

v) Atterberg Limits (minimum one set of Fallcone and one set of Casagrande).

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 98


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

vi) Relative density of cohesionless material (Test ASTM No. 2049-69).

b) Concrete aggregates/aggregates:

i) Particle size analysis (by sieving with mechanical sieve shaker).

ii) Specific gravity

iii) Density

iv) Organic impurities

v) Clay and silt content.

vi) Moisture content.

c) Fresh Concrete:

i) Slump.

ii) Density

d) Hardened Concrete - Cube Samples:

i) Crushing strength (1560 kN compression machine, hand-operated).

ii) Weight.

Whenever directed by the Engineer, from time to time during the construction period, any
supplementary items considered necessary to carry out soils and materials testing mentioned
above shall be provided by the Contractor at no additional cost.

Laboratory equipment shall be properly calibrated and shall conform to the requirements of the
relevant British Standards (BS) or other approved standards.

Sufficient spare parts and consumables to cover normal usage during the period of the Contract
shall be provided together with a supply of distilled water, gas and etc as required.

Items of laboratory equipment lost or damaged, for any reason, shall be replaced immediately by
the Contractor. On completion of the Contract, all laboratory testing equipment’s shall revert to
the Contractor.

The provision of laboratory equipment’s with all its reagents shall be considered among the
Contractor’s general obligations and shall not be paid for separately.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 99


Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Laboratory Staff

A senior laboratory technician will be provided by the Contractor as indicated on personnel


requirement.

The Contractor shall provide a sufficient number of competent qualified laboratory technicians
who shall be suitably experienced in laboratory testing to a high standard and who are capable of
producing reliable and consistent results all at the direction and approval of the Engineer.

the Contractor shall provide all such suitable labour, as the Engineer may deem necessary for the
assistance of the laboratory technicians and for the expeditious completion of testing works.

It shall be the discretion of the Engineer to select laboratory technicians and labourers whom he
considers reliable and suitable

5.13 Settlement Allowance

In the setting out and construction of the embankment an allowance shall be made for post-
construction settlement. The nominal crest level shall be raised by the amount shown on the
embankment camber diagram by steepening the slopes of the embankments.

Dam Surfacing and Finishing works


When the embankment has been constructed, and all major outlets and drains installed, the dam can
then be finished off. It is quite important that the training banks along the spillway sides are well
established with grass cover and protected with other erosion prevention measures before the spillway
is to be used. Rains on an unprotected embankment and water flow through an incomplete spillway
can, at the least, cause minor rills and gullies and, at worst, destroy the structure altogether. Therefore,
when most of the heavy earthmoving and other work has been done, it is vitally important not to
neglect the minor finishing touches that, if delayed, can negate much or all of the work already
performed.
Inspection Requirements
At the time of siting the dam it should have been made clear to the local community/dam owner that
to maintain the dam in good condition and to prolong its life as a sound, useful water resource,
competent and timely inspection and maintenance are going to be required.
Training Banks
Training banks are required along one or both sides of the spillway to keep floodwater away from the
downstream toe and shoulder of the embankment and within the channel. Training banks are often

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 100
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

constructed without a core, but often will use the same slopes as the main embankment. However, the
design can vary according to site conditions and crest widths and heights can be reduced as required.
In construction, care should be taken to avoid traversing the spillway and no earth should be removed
from the channel bed for this bank unless cut is required to form the spillway.
Concrete or stone pitching at the end of the main embankment and along the inner sides of the training
banks may be advisable.
Other Works
In finishing the main embankment, the crest should be given a slight downward slope towards the
reservoir so as to encourage runoff towards the reservoir and the less erodible upstream section of the
embankment. The accumulation of water on and in the downstream shoulder must be avoided.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 101
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

PART-6 Plain and Reinforced Concrete

6.1 Scope of Work


This section cover manufacture, forming, transporting, placing stripping of forms, finishing
and curing of concrete in the structures included in the specifications.

6.2 Composition and Quality


Concrete shall be composed of Portland cement, water, fine and coarse aggregate. Cyclopean
concrete shall be composed of 60% mass concrete C-20 and 40% of hand placed boulder,
(100mm-300mm). The concrete mix should be made as per the requirement of the designer
covered by the specification. For the quality of the work, the following mix ratio shall be
adopted.
Concrete Mix Ratio
Concrete Mix Contents of
SN Box Size
type ratio material
sand-4 box
1 C-5 1:4:6 Gravel-6 box 18x40x50cm
Cement-50kg
sand-3.5 box
2 C-7 1:3.5:6 Gravel-6 box 18x40x50cm
Cement-50kg
sand-3 box
3 C-10 1:3:6 Gravel-6 box 18x40x50cm
Cement-50kg
sand-2 box
4 C-15 1:2:4 Gravel-4 box 18x40x50cm
Cement-50kg
sand-2 box
5 C-20 1:2:3 Gravel-3 box 18x40x50cm
Cement-50kg
sand-1.5 box
6 C-25 1:1.5:3 Gravel-3 box 18x40x50cm
Cement-50kg
sand-1.5
7 C-30 1:1.5:2.5 Gravel-2.5 18x40x50cm
Cement-50kg
NOTE: - hand mix shall be allowed for concrete type C-5-C15, and shall not be allowed for
concrete of class C20 & above. This shall comply with 1.5, Construction methodology.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 102
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

6.3 Cement
Cement shall be furnished package as approved by the Engineer. It shall be Portland cement
and shall conform to British or other standard that are acceptable to the engineer. The cement
shall be tested at storage site in accordance with the accepted standards or ASTM
requirements. No cement shall be used until notice has been given by the engineer that test
results are satisfactory, but if unsatisfactory it shall be removed from the site of work.
Cement which has been in storage at project site longer that (4) four months shall not be used
until retest proves it shall be satisfactory.
During transportation, cement shall be completely protected from moisture exposure.
Cement which has been adversely affected by moisture as determined by the Engineer shall
be rejected. Cement shall be stored in dry weather tight and properly ventilated structure.

6.4. Aggregates

Fine aggregates shall be generally consist of natural sand and coarse aggregates consists of
natural gravel, or crushed gravel or combination thereof. The Contractor shall bring concrete
aggregate from approved location which is natural deposits or shall produce crushed
aggregate from approved location. The aggregates will be sampled as delivered to the mixer
to determine compliance with specification provision. Aggregates as delivered to the mixers
shall consist of clean and uncoated particles.
6.4.1 Fine Aggregate
The grading and uniformity of fine aggregate as delivered to the mixers shall conform to the
following requirements.
U.S. Standard Percentage Weight
Sieve Size Passing individual sieve
1” 100
¾” 90-100
3/8” 20-40
No. 4 0-5
Note: the silt content shall be less than 5%. In addition to the grading limits the fine aggregate
as delivered to the mixer, shall have a fineness modulus of not less than 2.3 or more than
3.10.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 103
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

6.4.2. Coarse Aggregate

The grading of coarse aggregate shall conform to the following requirements as delivered to
the mixer.

Sieve Designation Percent


Ethiopian Standard Square Mesh Passing
3/8” 100
No. 4 95-100
No. 3 80-100
No. 16 50-85
No. 30 25-60
No. 50 10-30
No. 100 2-10

The shape of particles fine aggregate and in coarse aggregate shall be generally spherical or
cubical. The quantity of flat and elongated particles in the coarse aggregate, as defined and
determined by standard tests approved by the Engineer shall not exceed 25 %.

Aggregates shall be stored at the site of work in such a manner as to prevent inclusion of
foreign materials in concrete. Sufficient aggregate shall be maintained at site at all times to
permit continues placement and completion of any lift of concrete started.
All fine and coarse aggregates shall be remaining in free draining basin at site for at least
6hours before placing.
Flakiness, soundness, silica reaction, abrasion, ACV, AIV etc tests are as per engineers
satisfaction.
6.5. Water

Water for washing aggregates and for mixing and curing concrete shall be fresh water and
free from injurious amounts of oil, acid, salt, alkali, organic matter or other deleterious
substances as determined by standard tests approved by the engineer.

6.6. Proportion of Concrete

The proportion of all materials entering into concrete shall be directed by the Engineer. The
proportion will be changed wherever such change is determined necessary to maintain the
standard of quality regard to the structure covered by these specifications and to varying
conditions encountered during construction.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 104
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

The cement of concrete for various parts of the structures depending on the structural
requirements (150kgs/m3 to 360kgs/m3) and water cement ratio will vary from 0.4 to 0.50
depending on the strength of concrete and type of structure (mostly adopted water/cement =
0.45). The amount of water used in the concrete shall be regulated as required to secure concrete
of proper consistency. Additions of water to compensate for stiffening of concrete before placing
will not be permitted. Uniformity in concrete consistency from batch to batch will be required.

6.7 Mixing

The concrete mixer shall be installed at the site of work at locations selected by the contractor
and approved by the engineer. Mixer shall be capable of combing the materials in to uniform
mixer and of discharging without segregation. Suitable water measuring device shall be provided
by the contractor which be capable of measuring mixing water within the specified requirements
for each batch to control water cement ratio. Additional of water will not be permitted.
The mixer shall be operated at a drum speed designated by the manufactures on the nameplate.
The mixer shall be maintained in satisfactory operating conditions, and mixer drum shall be kept
free of hardened concrete.

6.8 Hand Mixing

When the mixing of concrete by hand is permitted, the cement, fine and coarse aggregates shall
be mixed on a close-fitting stage.
PROCEDURE OF MIXING BY HAND MIX is as follow:
In hand mix, the materials shall be first mixed well dry and then water added by means of rose
headed can.
Mixing shall be done on water tight plate form. Mixing shall be continuous till the whole mass
is homogenous appearance and color.
An excess of 10% of cement often allowed

NOTE: - hand mix shall be allowed for class 5-15 concrete, and shall not be allowed for
Concrete of class C-20 and above

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 105
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

6.9 Conveying
Concrete shall be conveyed from mixers to forms as rapidly as practicable, by method which
will prevent segregation or loss of ingredients. Any hopper through which the concrete
passes shall be conical in shape. There shall be no vertical drop greater than 1.5m except
where suitable equipment is provided to prevent segregation and where specifically
authorized.

6.10 Placing

No concrete shall be placed in the structure until the methods of placement have been
approved by the Engineer. Approval of the method of placement proposed will not relieve
the contractor of responsibility for its adequacy.
Concrete shall be worked in to corners and angles of the forms and around all reinforcement
and embedded items without permitting the materials to segregate. Concrete shall be
deposited as close as possible to its final position in the forms. The depositing of concrete
shall be regulated so that the concrete may be effectively compacted with horizontal layers
approximately30 to 45 cm in thickness. The surface of construction joints shall be kept
continuously wet for at least eighteen hours during the twenty four hours period prior to
placing concrete except as otherwise directed by the engineer. All free water shall be
removed and the construction joint shall be dry of water prior to placement of concrete.
Concrete placement will not be permitted; when in the option of the Engineer weather
conditions prevent proper placement and consolidation.
Concrete shall be placed within thirty minutes, after it has been mixed, unless otherwise
approved by the engineer. Transportation of concrete directly over the fixed reinforcement
during the depositing shall not be allowed without proper provisions to avoid displacing or
any other harm to the reinforcement. In placing concrete through reinforcement care shall
be taken that no segregation of the coarse aggregate occurs.
Concrete shall be compacted with mechanical vibrating equipment supplemented by hand
spading and tamping. In no case shall vibrators be used to transport concrete inside the forms.
The vibrating equipment shall be of the internal type and shall at all times be adequate in
number of units and power of each unit to properly consolidate all concrete.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 106
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Rock surface upon which concrete is to be placed shall be clean, free from soil, standing or
running water, mud rummy rock, coatings, debris, lose or semidetached or unsound
fragments. Immediately before concrete is placed, all rock surfaces shall be thoroughly
cleaned by use of air water jets or other approved methods. All rock surfaces shall be kept
continuously wet for at least 24 hours immediately prior to placing concrete thereon.

6.11. Concrete standards


Summary of Concrete Standards and their Characteristics
Maximum
Maximum Size of Compressive Strength Minimum Cément Slump
Class Water Cement
Aggregate, mm at 28 days (MPa) Content (kg/cm) (mm)
Ratio
C-5 20 5 - - 76+25
C-10 20 10 - - 75+25
C-20 40* 20 - 250 75+25
C-25 40* 25 0.5 300 75+25
C-30 40* 30 0.5 300 75+25
* Maximum aggregate size is 20mm for element less than 200mm thick.

6.12. Expansion –Contraction and Construction Joints


Construction joints provided in the project since the bed of the river is basalt rock formation.
This construction joint utilized to monolithic the structures. The surface of the construction
joints shall be prepared for receiving the next structure by cleaning the river bed and the
abutments using air –water cutting. These Joints (Anchor bars) shall be provided at the
location indicated on the drawings or otherwise approved by the engineer. To Anchor or
joint the concrete with the bed rock, the rock shall be chiseled up to 15cm to 50cm depth as
indicated the working drawings.
Expansion-contraction joint shall be provided at the location indicated on the drawings or
directed by the Engineer. In no case shall any fixed metal embedded in the concrete be
continuous through an expansion-contraction joint. Expansion –contraction joint filler will
consist of tar filler or self-expanding cork or any other material and type as directed by the
Engineer.
Water stops of copper (sheet metal) and polyvinylchloride (PVC) shall be installed in the
joints as shown on the drawings or otherwise directed. Adequate provision should be made
to support and completely protect the water stops during the progress of the work. The

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 107
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

contractor shall replace or repair, at his expense, any water stop punctured or otherwise
damaged before final acceptance of the work.
Method of measurement:- The method of measurement shall be in leaner meter and the
method of payment made by multiplying the length of installed meter multiplied by the unit
rate entered.
6.13. Curing and Protection

All concrete shall be cured for a period of not less than 14 consecutive days. The curing
methods shall be approved by the Engineer. Unhardened concrete shall be protected from
rain and flowing water. Concrete shall be moist-cured by maintaining all surfaces
continuously (not periodically) wet for the duration of the entire curing period. Water for
curing shall be clean and free from any elements, which will cause staining, or discoloration
of the concrete. Where forms of wood lagging are used and left in place during curing, the
lagging shall be kept wet at all times. Horizontal construction joints and finished horizontal
surface cured with sand shall be covered with minimum uniform thickness of 5cm of sand,
which shall be kept continuously saturated during entire curing period.

6.14. Material Requirements for Falsework and Formwork

(a) Falsework
Falsework shall consist of either purpose-made; or proprietary timber; or metal,
props, beams, bracings or ties; adequate to support the forces imposed during construction
of the concrete structure without excessive deflection.
All props shall be provided with suitable base plates to distribute the superimposed loads.
The props shall also be adjustable to support the beams to the level required by the design.

(b) Formwork
Formwork shall be provided to produce hardened concrete to the lines, levels and shapes
shown on the Drawings or specified elsewhere. It shall have adequate strength to
carry all applied loads, including the pressure of fresh concrete, vibration loads, weight
of workers and equipment, without loss of shape.
Forms shall be mortar tight and designed to allow removal without risk of damage to the
completed structure.
Joints in the formwork shall be perpendicular to the main axis of the shape of the
concrete.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 108
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Design of formwork for high sections shall be such that it shall not be necessary to
drop concrete freely from a height greater than 1.5m or to move concrete along the
formwork after deposition.
Material used for formwork shall be sound and suitable for the purpose intended and
surface finish specified.
Provision shall be made for the accurate location and firm support of fittings, bolts,
anchorages and formers of holes as shown on the Drawings. Temporary fittings used for
the support of the formwork shall be arranged to permit removal without damage to the
concrete.
The use of wires and or bolts extending to the surface of the concrete shall not be
permitted except where shown on the Drawings.
Forms for edges of concrete shall be filleted and, for re-entrant angles, chamfered as
shown on the
Drawings.
Formwork shall consist of purpose-made or proprietary timber; metal or plastic boarding;
or sheeting;
adequate to support the forces during construction of the concrete structure without
excessive deflection.

Construction Requirements

Formwork shall be so designed as to be sufficiently rigid to ensure that the specified


dimensional tolerances can be achieved under the combined action of self-weight, dead load
and imposed loads as well as the additional loads resulting from the rate of concreting, the
layer thickness of the concrete cast in one operation and the method of placing and compaction.

Before the concrete is placed, all dirt and foreign matter shall be removed from the
forms and the forms shall be thoroughly wetted with water.

Removal of forms and false work


Falsework and formwork shall not be removed before the concrete has attained sufficient
strength to support its own mass and any loads, which may be imposed on it. This condition
shall be assumed to require the formwork to remain in place after the concrete has
been placed, for the appropriate minimum period of time given in Table 8204/1.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 109
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Forms that do not support the dead load of concrete members and forms for railings and
barriers may be removed 24 hours after the concrete is placed.
Falsework and formwork shall be carefully removed without exposing the cast concrete
to damage, disturbance or shock.
Weather may be regarded as being "normal" when atmospheric temperatures
adjacent to the concrete, as measured by a maximum-and-minimum thermometer, do
not fall below 15°C, and as "cold" when temperatures, similarly measured, fall below
5°C. When the minimum temperatures fall between these values, the length of the period
after which the formwork may be removed shall be determined by interpolation between
the periods specified for normal and cold weather.
Any period during which the temperature remains below 2°C shall be disregarded in
calculating the minimum time which shall elapse before the forms are removed.
Minimum Form/Support Release Criteria
Percent of Specified 28- Minimum Number of
Structural Element
Day Strength (%) Days Since Last Pour
Columns and wall faces(not yet
50 3
supporting loads)
Mass piers and mass abutments(not
yet supporting loads) except pier 50 3
caps
Box Girders 80 21
Simple span girders, T-beam
girders, slab bridges, cross beams,
caps, pier caps not continuously 80 21
supported, struts, and top slabs of
concrete box culverts.
Trestle slabs where supported on
70 10
wood stringers
Slabs and overhangs where
supported on steel stringers or pre- 70 10
stressed concrete girders
Pier caps continuously supported 60 7
Arches, continuous span bridges,
90 21
rigid frames

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 110
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Remedial Treatment of Formed Surfaces

(a) General
The surfaces shall be inspected by the Engineer immediately after the formwork has been
removed and agreement s h a l l be reached with the Engineer regarding any remedial
treatment that may be required. The remedial treatment shall be carried out without delay.
No surfaces may be treated before inspection by the Engineer.

(b) Repairs to surface defects


Surface defects such as small areas of honeycombing, cavities produced by form ties, large
isolated blow-holes, broken corner edges, etc. shall be repaired with mortar having a
cement and sand ratio equal to that of the concrete being repaired.
For the repair of large or deep areas of honey combing and defects, special approved
methods and techniques, such as pneumatically applied mortar, pressure grouting and
epoxy bonding agents may be used on approval of the Engineer.
Where, in the opinion of the Engineer, the extent of the honeycombing or defects is of
such a degree that doubt exists about the effectiveness of repair work, the Contractor shall,
at his own cost, perform a load test to prove that the structural safety of the repaired
member has not been prejudiced, failing which, the structure shall be rebuilt in part or in
full at the Contractor's cost.
Where the concrete has been damaged by adhesion to the formwork panel, the cracked and
loose concrete shall be removed; or where the fresh concrete has lifted off at construction
joints, the crack shall be scraped out immediately on both sides of the wall to a depth of
at least 50 mm. The cavities so formed shall then be repaired as described herein.

(c) Rubbing the surfaces


If the finish of exposed formed surfaces does not comply with the requirements for
uniformity of texture, appearance and colour, the Contractor shall, when so instructed by
the Engineer, rub down the exposed surfaces of the entire structure or of any part of it as
specified herein.
The surface shall be saturated with water for at least one (1) hour. Initial rubbing shall be done
with a medium-coarse carborundum stone, where a small amount of mortar, having a sand
to cement ratio equal to that of the concrete being repaired, is used on the surface. Rubbing
shall be continued until all form marks, projections and irregularities have been removed
and a uniform surface has been obtained. The paste produced by the rubbing shall be left

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 111
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

in place. The final rubbing shall be carried out with a fine carborundum stone and water. This
rubbing shall continue until the entire surface is of a smooth, even texture and is uniform in
colour. The surface shall then be washed with a brush to remove surplus paste and powder.
Where the concrete surfaces formed by sliding formwork require treatment to achieve the
surface finish specified for the member, the concrete shall, as soon as the surfaces under the
formwork are exposed, be floated with rubber-lined floats to the desired finish.

Measurement and Payment


The unit of measurement shall be the square metre, and only the actual area of formwork
in contact with the finished face of the concrete shall be measured. Formwork for the
different classes of finish shall be measured separately.
The tendered rates shall include full compensation for procuring and furnishing all
materials required; erecting the falsework and formwork; constructing the forms; forming
the grooves, fillets, chamfers and stop-ends for construction joints; treating and preparing
the forms; all bolts, nuts, ties, struts and stays; stripping and removing the formwork
after completion of the work; all labour, equipment and incidentals; and rubbing
and surface treatment.

6.15. Furnish and Install Reinforcement Bars


The construction crew or the contraction shall furnish, cut, bend and place all reinforcement
bars and structure shape as indicated on drawings. All reinforcement shall be, when
surrounding concrete is placed, free from loose, flaky rust, and scale and free from oil, grease
or other coating which might destroy or reduce its bond with concrete. All reinforcement
shall be secured in placed by use of metal of concrete supports, spacers or tics, as approved.
Such supports shall be sufficient strength to maintain the reinforcement in place throughout
the concrete operation. All placing shall be in accordance with drawings furnished or as
approved by the Engineer.
Steel Reinforcement for Structures
This covers the furnishing and placing of steel reinforcement in concrete structures.
Materials Requirement
(a) Steel reinforcement
Deformed and plain carbon steel reinforcing bars shall conform to the requirements of AASHTO
M-31 and ASTM A615.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 112
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Low alloy steel, deformed and plain billet steel bars, for concrete reinforcement shall be Grade
60 to ASTM A 706. The nominal area of the bar, as given below of AASHTO M-31 or ASTM A
706, shall be used for computation.
Steel fabric reinforcement shall comply with AASHTO M-225, M-221 or M-54 as appropriate.
Hard drawn mild steel wire reinforcement shall comply with AASHTO M-55, welded steel wire
fabric for concrete reinforcement.
Deformed steel wire for concrete reinforcement shall comply with AASHTO M-225 and cold
drawn steel wire for concrete reinforcement shall comply with AASHTO M-32.
(b) Mass of Reinforcing Bars
The mass of Reinforcing Bars is shown in the Table below. The Contractor shall provide the
manufacturer's chart for the exact calculations.
Table 1: Mass of Reinforcing Bars(as recommended by the South African Reinforced Concrete
Association)
Bar Diameter (mm) Mass (kg/m)
8 0.395
10 0.617
12 0.888
14 1.21
16 1.58
20 2.47
25 3.85
32 6.31
40 9.86
Note: for tensile strength and elongation of steel reinforcement refer ASTM
(c) Mechanical couplers
Mechanical couplers shall be used only if pre-approved or detailed in the contract documents or
authorized in writing by the Engineer. Such mechanical splices shall develop in tension or
compression, as required, at least 125% of the specified yield strength of the bar being spliced.
When requested by the Engineer, up to two field couplers out of each 100, or portion thereof,
placed in the work and chosen at random by the Engineer, shall be removed by the Contractor
and tested by the Engineer for compliance to the required 125% of the specified yield strength of
the bars being spliced
(d) Supply and Storage of Materials
Steel reinforcement shall only be used from a source with prior approval of the Engineer.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 113
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Steel reinforcement shall be stacked off the ground and, in aggressive environments, protection
shall be provided in the form of sheds or tarpaulins. All reinforcement shall be rust free and the
Engineer shall be entitled to reject on inspection any reinforcement showing signs of rusting.
Different grades of reinforcement shall be stored in separate locations and shall be clearly
identified and logged. Steel delivered directly to site shall also be logged accordingly by the
Contractor.
Details of each consignment showing source of supply; manufacturer’s certificate of test
strength; constituents (% carbon etc); and date of rolling shall be submitted to the Engineer.
However, this will not relieve the Contractor of any responsibility for testing the material as
instructed by the Engineer.
Construction Requirements
(a) Equipment
The equipment used for the cutting, cropping and bending of the reinforcement shall be capable
of producing prefabricated or in-situ assemblies complying with the requirements of this
Division.
(b) Bending of Reinforcement
Reinforcement shall be cut and bent to the dimensions shown on the Drawings and in accordance
with American Concrete Institute (ACI 315)
All reinforcement shall be bent at temperatures in the range of 5ºC to 100ºC unless otherwise
approved by the Engineer.
The Contractor shall submit a Bar Bending Schedule at least thirty (30) days prior to the
placement of the reinforcement, for the Engineer's approval. All costs for the preparation of the
schedule shall be incidental to the work.
No flame cutting of steel bars shall be permitted except with the approval of the Engineer.
Except as otherwise approved, all bars shall be bent cold and bending shall be done slowly, a
steady, even pressure being used without jerk or impact.
If approved, hot bending of bars of at least 32 mm diameter will be permitted, provided that the
bars do not depend for their strength on cold working.
When hot bending is approved, the bars shall be heated slowly to a cherry red heat (not above
840ºC) and after bending shall be allowed to cool slowly in air. Quenching with water shall not
be permitted.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 114
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Reinforcing bars that have already been bent shall not be re-bent at the location of the original
bend without the permission of the Engineer.
(c) Surface Conditions
Immediately before the concrete is placed around the reinforcement, the reinforcement shall be
clean, free from mud, oil, grease, paint, loose rust, loose mill scale or any other substance that
can have an adverse chemical effect on the steel or concrete, or reduce the bond.
(d) Placing and Fixing
Reinforcement shall be secured against displacement during the placement and compaction of
the concrete.
Reinforcement shall be positioned as shown on the Drawings and accurately secured in these
positions within the tolerance of these specifications by tying with wire or by the use of suitable
clips or, where permitted by the Engineer, by tack welding. The wire adjacent to permanently
exposed faces and the internal faces of hollow box superstructures shall be 1.2 mm diameter
stainless steel.
(e) Cover
The term "cover" in this context shall mean the minimum clear thickness of concrete between the
surface of the reinforcement and face of the concrete.
The cover to any bar in an outer layer of reinforcement shall not be less than the minimum cover
shown on the Drawings and shall not exceed the minimum by more than 4% of the overall
dimension of the member, measured in the same direction, or by more than 20 mm, whichever is
the lesser.
Where no cover is indicated, the minimum cover provided shall not be less than the appropriate
values shown in Table below.
The cover shall be increased by the expected depth of any surface treatment (eg when concrete is
bush-hammered or when rebates are provided).
Additional cover as directed by the Engineer shall be provided if porous aggregates are used.
Concrete spacer blocks shall be made with 5 mm maximum size aggregate and shall be of the
same strength and material source as the surrounding concrete. Tying wire complying with the
requirements of this clause shall be cast into the block for the purpose of tying it to the
reinforcement. The blocks shall be formed in specially manufactured moulds and the concrete
compacted in a table vibrator all to the approval of the Engineer.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 115
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Cover blocks or spacers required for ensuring that the specified cover is obtained shall be of a
material, shape, and design acceptable to the Engineer.
The Contractor shall provide adequate support to reinforcement by way of stools/chairs. The
stools/chairs shall be suitably robust, and fixed securely so that they cannot swivel or move. The
stools/chairs shall have sufficient strength to perform the required functions, taking into account
amongst others temporary loads such as the weight of workmen and wet concrete, and forces
caused by vibrators and other methods of compacting the concrete.
Table 2: Minimum concrete cover over reinforcement
Water/Cement Ratio ≤0.40 0.4 to 0.5 ≥0.50
Situation Cover (mm) Cover (mm) Cover (mm)
Direct exposure to salt water 80 100 120
Cast against earth (i.e. Bottom of footings) 60 75 90
Exterior other than above 40 50 60
Interior other than above (i.e. Up to ∅35 Bar 32 40 48
hollow structures) ∅45 and ∅55Bars 40 50 60
Up to ∅35 Bar 35 35 42
Bottom of cast-in place slabs
∅45 and ∅55Bars 40 50 60
Precast soffit form panels 20 20 24
Non-corrosive environments 32 40 48
Precast Reinforced Piles
Corrosive environments 60 75 90
Precast Pre-stressed Piles 40 50 60
Non-corrosive environments 40 50 60
Corrosive environments 60 75 90
Cast-in-place Piles General Protected 60 75 90
Shells 40 50 60
Auger cast, tremie concrete or slurry 60
75 90
construction

6.16. Measurement and Payment


6.16.1. Furnish and install reinforcing steel
Measurement will be made of the number of kilograms of reinforcement steel acceptably
placed on the basis of the lengths of bars installed in accordance with the drawings.

Payment will be made for the number of kilogram measured as provided above at the
applicable contract unit prices per kilograms and shall constitute full compensation for
furnishing, delivering and handling, cutting bending, cleaning, placing, blinding and
supporting the bars and all other work related to its item. Rates for reinforcing steel shall
also include cost for steel having 6mm diameter and tying wire.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 116
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

6.16.2 Furnish and install water stop


Measurement will made of the number of linear meters of water stops acceptably placed in
the work based on the applicable unit linear meter material.
Payment will made of the number of linear meters measured as provided above at the
contract unit price, which is fixed by the Engineer, and shall include full compensation for
splicing material and all other work related to the item. The Bill of quantity the sheet metal
is stetted as lump sum.
6.16.3 Concrete work
Measurement will be made of the number of cubic meters of concrete acceptably placed as
directed by the Engineer.
Payment will made for the number of cubic meters measured as provided above at the
contract unit price per cubic meters for concrete, and shall constitute full compensation for
all work related to the item.
The tendered rate for concrete also includes formwork unless specified in this Bill of quantity
separately.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 117
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

PART-7 Stone Work, Gabions, Material sharing schedules, etc.


7.1 Stone Masonry
Masonry shall be constructed from stones in cement mortar and shall be built to the lines and
levels as shown on the drawings or as directed by the Engineer.

The stone shall be sound, hard stone or rock and clean. Stone for masonry shall be taken out as
nearly as possible to specified standard or directed by the Engineer. The stones shall be set in
position with their natural beds as near as possible to horizontal and interstices between the
stones shall be completely filled with mortar. Stones are to be selected and placed so as to keep
the amount of mortar the minimum. The stone to mortar ratio shall be 60:40 with mortar mix
of 1:3 or as directed by the engineer. Stones shall be a fair face showing an ever distribution of
stone size. Bond stones shall be laid in staggered position.

Shifting or tapping masonry after mortar has been its initial set will not be tolerated. Where
adjustment must be made, the mortar shall first remove and replace with fresh mortar. All joints
are to be properly filled with mortar and vertical joints shall not be continued.
All stones, including exposed faces of individual stones and bond stones, shall be laid with their
longest axis normal to the face of the wall in which the stones are set.

Bond stones shall be provided at the rate of not less than one to every square meter of exposed
face.
Bond stones shall measure not less than 150mm by 150mm on the exposed face and not less
than 450mm in length or the full thickness of the wall if the latter is less than 450mm. The
stones shall be so handled as not to jar or displace the stones already set.
7.2. Dressing and Cleaning
The stone shall be dressed to remove any thin or weak portions. Immediately after being laid, and
while the mortar is fresh, all face stone shall be thoroughly cleaned of mortar stains and shall be
kept clean until the work is completed. If ordered by the Engineer, the surface of the masonry shall
be cleaned using wire brushes and an approved acid before final acceptance.
7.3. Pointing
The pointing or finishing of joints shall be as shown on the Drawings or as otherwise indicated
by the Engineer. When raked joints are called for, all mortar in exposed face joints and beds

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 118
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

shall be raked out squarely to the depth noted on the Drawings. Stone faces in the joints shall
be cleaned free of mortar.
When weather joints are called for, the beds shall be weather struck. The joints shall be slightly
raked to conform to the bed weather joint and in no case shall the mortar be flush with the faces
of the stones.
The mortar in joints on top surfaces shall be crowned slightly at the center of the masonry to
provide drainage.
This sub-clause also applies to re-pointing in extension work or in the repair of the existing
masonry work. Cracks in the masonry of the existing bridges and culverts shall be repaired as
follows:

- Deteriorated and loose mortar particles, dirt and other undesirable materials shall be raked
free and loose stones shall be chopped out.
- The joints shall be cleaned by wire brushing, sandblasting, or by other acceptable means,
to the full depth of deteriorated mortar but in no case less than 75 mm.
- Voids and cavities which are encountered shall be cleaned.
- The surface texture of the exposed faces shall not be damaged.
- The joints shall be dampened and filled completely with cement mortar, packed solidly
into the joints and voids.
- The masonry shall be kept damp during the repointing operations.
- The masonry joints shall be finished to match the existing mortar joints and the stone work
left clean and free of mortar droppings.

7.4 Plastering of masonry walls

Plastering of masonry faces shall be made with cement mortar of appropriate mix often 1:3
and thickness as approved by the engineer. Retaining walls made of masonry have to be
provided with proper drainage provisions as indicated on the drawing or otherwise specified
by the engineer.
Where shown on the Drawings or called for by the Engineer, the Contractor shall plaster the
surface with cement mortar, consisting of one part cement to three parts of sand by volume
to a minimum thickness of 12 mm of plaster unless otherwise instructed by the Engineer.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 119
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

The tendered rate shall include full compensation for furnishing all materials, removal of
deleterious materials; ensuring a clean surface; mixing and placing the plaster; and all other
work necessary for completing the work

7.5 Hardcore

Hardcore shall be of sound, hard stone or rock or hand, broken concrete, cruciform and not
less than 100mm in size with the exception that sufficient binding material of smaller sizes
will be permitted. Hard core for masonry bed shall not be permitted unless otherwise
specified or as approved by the engineer.

7.6Masonry work
a) Measurement

Measurement will be made for the quantified volume of masonry work acceptable placed to
the line, Level, grades and cross section shown on the drawing or established by the engineer.
The unit of measurement for plastering and pointing is in square meter acceptably placed,
cured and smooth.

b) Payment

Payment shall be made for the quantified volume of measured as provided above at the
contract unit price for the masonry work and shall constitute full compensation for quarrying
transporting material to the site, mixing mortar and all other work related to item. Payment
for plastering and pointing shall be made in square meter at the contract unit price.
6.6 Weep holes
All walls and abutments shall be provided with weep holes. Unless otherwise shown on the
Drawings or directed by the Engineer, the weep holes shall be placed horizontally at the
lowest point where free outlets for water can be obtained and shall be spaced at not more
than 2m centers in a staggered manner. The length of weep holes shall not be less than the
thickness of the wall of the abutment and shall be at least 50mm diameter PVC or other pipe
materials approved by the Engineer. Weep holes must be provided with synthetic filter fiber
fabric as shown on the Drawings, specified in the Particular Specifications or as directed by
the Engineer

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 120
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

The unit of measurement shall be either the linear meter of pipe/weep hole or the number of
pipes/weep holes of each type and size of pipe/weep hole completed.
The tendered rates shall include full compensation for supplying all the materials;
manufacturing and installing the pipes; and making weep holes
7.7 Gabions and Mattresses
A. Scope
This Division covers the material and construction requirements for gabion walls and
mattresses used in aprons for retaining walls, lining of channels, revetments, and other anti-
erosion structures in accordance with the Drawings or as ordered by the Engineer.
B. Materials for Gabions
(I) Rock
Stones or rock for filling gabions shall be obtained from sources located by the Contractor
and approved by the Engineer.
Rocks used as filling for cages shall be clean, hard, sound, durable and un-weathered
boulders or rock fragments.
No rock particles shall exceed the maximum size given in Table and at least 85% of the rocks
shall have a size equal to or above minimum size given in the table.
Depth of cage
Minimum (mm) Maximum (mm)
(mm)
0.2 75* or 95**125 125
0.3 100 200
0.5 100 250
1 100 300
*Using 60 x 80 mm mesh
**Using 80 x 100 mm mesh
(II) Wire
All wire used in the fabrication of the gabions and in the wire operations during construction
shall be to ASTM A 910, Grade # 1010 or 1015, having a tensile strength of not less than
350 MPa.
Cold drawn steel wire fabric shall meet the requirements of AASHTO M-55.
(III) Galvanizing

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 121
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

All wire used in the fabrication of gabions shall be galvanized in accordance with the
provisions of ASTM A 641 with Class 3 coating or aluminized with a coating weight as per
ASTM A 809 for Class A heavy galvanized mild steel wire.
The unit of measurement shall be in meter cube.
The tendered rates shall include full compensation for approved boulder supply, gabion mesh
supply and all other materials; manufacturing, placement etc.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 122
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

PART-8: Installation of Slide Gates

8.1 Scope of the Work


This section covers the performance of all work in connection with gate installation. All
materials furnished by the contractor under this section should conform to the BS or ASTM,
where applicable or others of the same level.

8.2 Derby Screen (Trash Rack)


The contractor shall furnish, assemble and install trash racks including anchorage and
arrangement required for satisfactory installation.
All material used shall be at highest grade free from defects and imperfections, all material
shall be as classified and grade designated on the drawings or as instructed by the engineer.

8.3. Under Sluice, Intake and other Gates


The type and class of materials from which the gate to be fabricated shall be as specified on
the drawings or as directed by the Engineer.
The contractor is to supply, fabricate, deliver and erect under sluice, intake and other gates
including the spindle or other mechanism with related equipment, anchorage and fixing
materials, Gate guiding steel works according to the specifications and drawings and shall
comply with the requirement of the relevant ASTM unless otherwise specified.
Welding of structural steel shall generally conform to the requirement as prescribed in the
“structural Welding Code” of the American Welding Society and to the following
description. The contractor shall inform the engineer about the type of electrodes which will
be used for the works and supply test samples of / and carry out tests on the welded work
when required by the Engineer. All affected parts must be free to expand during the welding
and all welds shall be continuous.
The exposed and submerged sheet metal / angle iron shall be painted in accordance with the
provision of this clause or as directed by the Engineer. All painting and surface preparation
work shall be carried out at the site.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 123
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

8.4 Materials of gates


Structural steel such as all gates, all framework, spindle, angles , anchors, mounting parts, steel
plates – unless otherwise specified the following constructions shall be fabricated from the
structural steel-St-37(DIN 17100 0r ASTM-A 36.
Anchors bolt shall be furnished with at least two nits. All Anchors bolts shall be hot –dip
galvanized. Bronze- Bushings rings and suts for operating dives it fabricated from bronze shall
be cast bronze.
Gates seals-the rubber sealing shall be size and shape as shown the drawings. The fixing bolts
shall be of stainless steel. Rubber seals shall be manufactured from synthetic rubber exclusively
made of SBR (Styrene Batadiene Rubber) meeting the following requirements.

8.5 Installation
The contractor shall assemble, install and test the under sluice, offtake and other gates including
seals, spindle, the embedded steel works and sill assembly in the accordance with details shown
the drawings or specified by the Engineer. The contractor shall be strictly following the assembly
and installation procedures, which shall be recommended by the suppliers.

8.6 Measurement and Payments

8.6.1 Furnish and install derby screen at the off-take structure


Measurement will be made for a derby screen acceptably provided and installed according to the
specification and drawings as complete unit in the off take point (lump sum).
Payment will be made for a complete unit measured as provided above at the contract unit per
for furnish and install trash rack and shall constitute full compensation for manufacture,
transportation to the site, and installation including painting and all other works related to the
item.
8.6.2 Furnish and install under sluice, off take and other Gates
Measurement will be made for gates acceptably provided and installed according to the
specification and drawings as complete unit in the under sluice, off take and other gates channel
as number or lump sum.
Payment will be made for a complete unit measured as provided above at the contract unit per
for furnish and install gates and shall constitute full compensation for manufacture,
transportation to the site, and installation including painting and all other works related to the
item.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 124
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

PART-9 Submittals
9.1.Employer’s submittals

9.1.1. Contract documents

The Contractor will be provided with full set of the Contract documents for his own use. A complete
set of Contract documents supplied by an Engineer and all further instructions issued by him shall be
kept at all times by the Contractor on the Site and available to an Engineer and his staff.

9.1.2. Design drawings

The Drawings which are included in the either in bidding documents or provided during negotiation
(for negotiated contracts) and which will form part of the Drawings to be used for the construction of
the Works show the work to be carried out in accordance with the Contract in sufficient detail for the
Contractor to fully plan his activities will be provided through engineer.

The Contractor shall check the Drawings carefully and advise the engineer, in writing, of any
ambiguities, discrepancies, errors or omissions and a full instruction will be furnished to the
Contractor should any ambiguities, discrepancies, errors or omissions be found. The Contractor shall
be required to perform the work in accordance with such further instructions or issued Drawings.
Although the Drawings are prepared to scale, work shall be based upon dimensions shown on the
Drawings and not on dimensions scaled from the Drawings.

9.1.3. Specification

Specification is one of the contract documents. It will be provided for contractor through engineer to
be referred and adopted in the contract period by the contractor and the engineer.

The Contractor shall check the technical specification carefully and advise the engineer, in writing,
of any ambiguities, discrepancies, errors or omissions and a full instruction will be furnished to the
Contractor should any ambiguities, discrepancies, errors or omissions be found. The Contractor shall
be required to perform the work in accordance with such further issued technical specification.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 125
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

9.2.Contractor’s submittals

9.2.1. Working drawings

The Contractor shall prepare and submit to an Engineer such working as may be necessary to
illustrate his proposed designs and method of working.
These working drawings shall be prepared to appropriate scales and include plans, elevations and
sections, consist of an electronic copy of the drawing (if available), one print and one copy of
design calculations, specification and parts catalogues; be signed by a qualified engineer
responsible for the design, checked and approved by the Contractor prior to submission;
Bear the title, Contract No. -------:
The engineer shall signify his approval or request modifications. The Contractor shall modify the
designs and drawings, as may be required by the engineer.

The Works shall be constructed in accordance with the approved working Drawings a copy of such
Drawings shall be kept on the Site at all times until the completion of the Contract. All Drawings,
on which changes are made, shall have the revisions clearly marked and dated.

Construction of any portion of the Works shall not commence until the design and drawings have
been approved in writing by an Engineer and thereafter no change shall be made to any Drawings
so approved without the permission of the Project

9.2.2. Shop drawings

The Contractor shall, in close consultation with the Engineer, prepare all the Shop Drawings
deemed necessary for the execution of the Works and shall submit the same for approval to the
Engineer well in advance to allow specified days in the contract for Engineer's checking and
approval. The approval procedure shall be agreed upon with the Engineer. Fabrication and
installation shall not proceed until the review is completed.
Where more than one type of shop drawing has been specified for one item, e.g., lay-out details,
and dimensional drawings, the shop drawings shall be submitted together, to enable the Engineer
to review the drawings as a package.
Shop drawings shall indicate the tag number of instruments and they shall clearly show the features
and details applicable to the equipment being supplied. Shop drawings shall be prepared using

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 126
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

accepted drafting techniques which will result in drawings of equal or better quality than the
contract drawings.
Catalogue pages or drawings applicable to an entire family or range of equipment will not be
accepted as shop drawings unless they are clearly marked up to show the pertinent data for the
particular materials.
Manufacturer's catalogues, manuals, or price lists will not be accepted as shop drawings, although
such material may be used as supplemental information to the shop drawings.
Shop drawings shall be detailed using the metric system. No shop drawings detailed using the
imperial system of dimensioning will be accepted.
If, after one review by the Engineer, the Contractor fails to submit correct shop drawings, the
Owner will be entitled to deduct from any payments due to the Contractor the additional costs to
the Owner of the engineering services incurred as a result of the Contractor's failure to submit
correct shop drawings.
The Contractor shall submit to the Engineer for his approval, at least fifteen (15) days before
their proposed use, three printed copies of all working drawings such as stress sheets, shop
drawings, erection plans, false work plans, temporary diversions or cofferdam plans, bending
diagrams for reinforcing steel, or any other supplementary plans or similar data necessary for
construction of the Works as agreed with the Engineer. The drawings shall be A3 size in general
conformity with the requirements of the Technical Specifications, the tender drawings and the
requirements of the Engineer.
The Engineer shall request changes by marking up the changes required on one (1) copy of
the drawings submitted by the Contractor and by returning the marked-up copy to the
Contractor for rectification by the Contractor. The Contractor shall incorporate the changes
and submit three (3) printed copies and one (1) digital copy of the revised drawings to the
Engineer.
The Contractor shall immediately notify the Engineer in writing of any objections to changes
requested by the Engineer. The final decision of the Engineer shall be communicated in
writing to the Contractor within fifteen (15) days and the Contractor shall abide by the
decision.
These are the general obligations for the contractor and there is no separate payment.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 127
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

9.2.3. Samples

Samples, or as otherwise specified, shall be submitted to the Engineer for review of those products
and materials for which samples are required. Samples shall be submitted a minimum of thirty days
prior to the date for approval required by the Contractor for procurement of the materials.

Samples shall be submitted with complete information concerning manufacturer's data, applicable
standards, test results, and location of installation on the project.

Materials for which samples have been approved by the Engineer shall be used only in those areas
and locations for which the approval was granted. Materials for which samples have been rejected
shall not be delivered to the site, or if delivered, shall be removed promptly.

9.2.4. As-built drawings

On completion of the Works, the Contractor shall submit to the engineer As-built Drawings as
specified, including final reduced levels and size and height of the elements of the Works.

The As-built Drawings for the whole Works are to be produced by the Contractor and submitted
to the engineer as specified in Contract Document to scales approved by the Engineer. All ‘As-
built’ drawings shall be produced on A1 or A3 paper size using the AutoCAD drawing system.
Two paper copies of each drawing shall be submitted for review and approval by an Engineer.
Following the correction of any errors or omissions identified by an Engineer the Contractor shall
submit the final ‘As-built’ drawings as: -
a) An electronic copy of each drawing;
b) Three copies of all A1 drawings in bound albums; and
c) Three copies of all A3 drawings (including reduced copies of the A1 drawings) in bound
albums.
Final bar-bending schedules shall be submitted with corresponding bar-marks on approved ‘As-Built’
drawings. Structural steel drawings, supplier’s drawings, fabrication and shop drawings, large scale
detail drawings including all structural steel connection details not shown nor provided by Project
Coordinator, and any additional drawings, shall be prepared by Contractor and submitted together
with detailed design calculations.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 128
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

A sample of the format of the As-Built drawing which contains title block, text and symbols, metric
units, drawing scales etc will be issued to the Contractor by an Engineer and this shall form the
basis of presentations of As-Built drawings.
All costs related to the supply to the engineer of the mentioned number of drawings and
calculations shall be deemed to be included in the rates in the bill of quantities any extra copy of
the drawings and/or calculations which may be required, shall be supplied against the unit rate as
included in the bill of quantities.

9.2.5. Operation and maintenance manuals

The Contractor shall provide operating and maintenance instructions for Plant, including
instrumentation, to be supplied and installed under the Contract, it is intended that these instructions
will be incorporated in the Operator’s Maintenance Manuals for the Works to be compiled by the
Engineer and to this end they shall be in loose leaf form on paper of A4 international size.
Operating and maintenance manuals shall generally take the following form and shall contain the
following information: -
a. Step-by-step procedures for any operation likely to be carried out during the life of the
Plant;

b. Maintenance and troubleshooting information, including charts showing lubrication,


checking, testing and replacement procedures to be carried out daily, weekly, monthly and
at longer intervals;

c. Where applicable, fault location charts to facilitate tracing the cause of malfunction;

d. Technical details;

e. Description of the installation;

f. Final settings of relays, timers etc.

g. Complete parts list.

The manuals shall have a hard cover bound with the name and title of the installation clearly marked
on it. The manual shall be properly indexed and contain dividers with tabs between each section. All
data must be organized in a neat and concise manner.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 129
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

9.2.6. Payment

Unless otherwise clearly specified in the bill of quantity of this contract, additional payment will not
be made for any submittals. The cost of this work is deemed to be included in the price tendered for
the supply and installation of the items for which submittals are required.

9.3.Consultant’s submittals

9.3.1. Project completion report

The consultant shall provide a completion report and reference drawings at the end of the contract
in accordance with Consultants’ terms of reference. This is generally taken to be the end of the
Defects Liability period.
It is therefore recommended that the Consultants be required to provide a Project Completion
Report at least two weeks before the intended Taking-Over inspection and that the report includes
the As-Built drawings, Irrigation infrastructure Inventory and the structures condition surveys.
The Project Completion Report should comprise but not necessarily be limited to the following:

▪ The rationale for undertaking the project


▪ A description of the project and its location
▪ Details of the parties involved in the project
▪ Details of the Funding Agencies
▪ Comments on the general implementation of the works
▪ Comments on problems encountered in the implementation of the works
▪ Details of solutions to problems encountered
▪ Comments on the project design
▪ Details of all design changes with the rationale therefore
▪ Maintenance requirements and additional work required
▪ A financial statement

At the time of taking over, the only information which will not be available for the report at this
stage will be the final financial details of the project and the information related to the Consultancy
contract which can be included in an addendum or revision of the report at the end of the Defects
Liability Period.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 130
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Therefore, on completion of the Defects Liability Period the Consultant should be required to
submit a final consolidated version of the Project Completion report containing all of the above
information in its finalized form plus the following:

• All finalized Project Completion Report details


• Details of the Consultant's Staff inputs
• Details of the Consultant’s supervision contract
• Problems encountered by the Consultant in supervising the contract
• Comments on the contract
• Financial details of the Consultant's contract.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 131
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Section V – Bill of Quantity

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 132
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Bill of Quantities
1.1. General
• The Bill of Quantities shall be read in conjunction with the Conditions of contract, the
special provisions, the specifications and the Drawings. It also comprises the Bills with
their summary.
1.2. Quantities
• The quantities set out in the Bill of Quantities are estimated quantities of the work and
they are not to be taken as the actual and correct quantities of the works to be executed
by the contractor in fulfillment of this obligation under the contract.
• Except where specifically an expressly stated in the specifications or Bill of Quantities,
the permanent works only shall be measured. The works shall be measured net to the
Dimensions shown on the Drawings or ordered by the Engineer. Such measurements
shall be made not withstanding any general or local custom to the contrary.
1.3. Rates and Prices
• The rates shall include but not way of limitation, labor, transport and materials, the
provision, maintenance, use and repair of all plant, equipment and appliance of every
kind, the construction and maintenance of all temporary works of every description and
the performance of all services that may be required for the proper execution, completion
and maintenance of the works in full and complete in accordance with the provisions of
the Contract Documents, and the undertaking of all obligations and responsibilities there
in defined.
• The contractor shall be deemed to have fully considered all the conditions, obligations
and requirements of the contract Document before entering the respective rates against
the general items.
• Unless otherwise stated in the Bill of Quantities or in the specifications or approved by
the Engineer, the quantities for all items shall be measured net in accordance with the
Drawings, no allowance being made for waste.
• Except where specifically and an expressly stated in the specifications or Bill of
Quantities, the excavation unite rate estimated and entered in the bill of quantities by the
contractor should be also includes cart away.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 133
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

1.4. Provisional Quantities


• Items in the Bill of Quantities material “provisional Quantity” are provisional items and
shall only be executed if they are the subject of a written instruction from the Engineer.
The rates and prices for such items shall be used for the valuation of works so ordered
by the Engineer in writing whether the quantities shown are used wholly or in part and
the contract price shall be varied by deduction of the amount of each such item and by
addition of the value of the work performed (if any) as ordered by the Engineer.
1.5. Lump Sum
Lump sum items included in the Bill of Quantities up on submission of breakdown in order
that progress payments may reasonably reflect the distribution of the lump sums over the
period of the contract. The breakdown will not necessarily apply to the valuation of the
quoted lump sum.
1.6. Rate only
If rate only is agreed in the original contract, the contractor will be liable to undertake the
work with the rate entered and agreed previously.

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 134
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Table; - Cost Summary of the project


SN Description Total Cost
Bill No. 1 General Provisions 5,110,000.00
Bill No. 2 Camp Works 1,468,888.30
Bill No. 3 Dam body 27,958,064.73
Bill No. 4 Dam instrumentation 679,632.46
Bill No. 5 Spillway 42,780,165.24
Bill No. 6 Intake Tower and Access Bridge 3,968,416.93
Bill No. 7 Gravel Access road 1,501,318.17
Total of carried to summary 83,466,485.83
VAT 15% 12,519,972.87
Grand Total of Project Work 95,986,458.71

Table: -Bill of quantity and cost


Item
Item Description Unit Qty Unit Price Amount
Nr.
Mobilization and Demobilization of Contractor's
Equipment and Manpower including transport to Site, 1,500,000.0
1.10 LS 1.00 1,500,000.00
erection, maintenance and removal from Site on 0
completion
Provision of contractor Camp facilities including
2,700,000.0
1.20 residential rooms, office ,Stores,Café & Kitchen, Toilet , LS 1.00 2,700,000.00
0
Shower , guard house and other services
Preparation and submission of As-Built Drawings (
1.30 LS 1.00 50,000.00 50,000.00
Electronic and Hard Copies)
Preparation and submission of Operation and Maintenance
1.40 LS 1.00 50,000.00 50,000.00
Manuals
1.50 Temporary access and haul roads. LS 1.00 500,000.00 500,000.00
1.60 Survey and setting out LS 1.00 10,000.00 10,000.00
Provide and erect sign boards each at junction on the main
1.70 No. 3.00 20,000.00 60,000.00
road as ordered by Engineer
Provide water and power supply including all running cost mont
1.80 12.00 20,000.00 240,000.00
and installation hs
Sub total 5,110,000.00
Total bill No 1 Carried to total Summary 5,110,000.00
Bill No.2: Camp Works
Camp (Staff residence & office(3m x 13.85), Café &
2.00
Kitchen (6x4x2), Toilet & Shower (4x2x2)
2.10 Residential rooms & office
2.1.1 Earth Work
2.1.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 116.34 20.44 2,377.72
Excavation for stone masonry foundation; 0.5m width and
2.1.1.2 m3 29.80 140.23 4,178.98
0.4 m depth
Cart away and dispose excavated surplus material to a
2.1.1.3 m3 36.00 26.85 966.72
distance not exceeding 500m

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 135
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
Supply and fill hard core with hard basaltic or equivalent
2.1.1.4 stone, well compacted and blinded with crushed stone to a m2 99.70 208.75 20,812.54
finished thickness of 25 cm
2.1.2 Masonry and Concrete Work
Supply and construct 500mm thick trachitic or equivalent
2.1.2.1 stone masonry foundation wall below ground level bedded m3 10.30 2,080.45 21,428.61
in cement mortar mix 1:3
Supply and construct 500mm thick trachitic or equivalent
2.1.2.2 stone masonry foundation wall above ground level bedded m3 10.00 2,296.70 22,967.04
in cement mortar mix 1:3
2.1.2.3 Mass concrete fill on floor slab (100mm) C-15. m2 91.40 343.23 31,370.93
2.1.3 Carpentry and Walling
Supply, assemble and fix in position eucalyptus wall post
2.1.3.1 of length 3 m with span length of 1.2m m 63.00 78.36 4,936.77
Supply and fix purlin in Eucalyptus wood size 8 cm
2.1.3.2 m 150.00 74.50 11,174.80
nailed into eucalyptus truss
Supply and fix wall cover in G-32 corrugated galvanized
iron sheet fixed into Eucalyptus wood purlin with dome
2.1.3.3 m2 263.00 416.80 109,619.41
headed galvanized nails (purlin and ridge cover measured
separately)
Supply and fix 8mm thich chip wood internal wall cover.
2.1.3.4 Price shall include 4 x 5 cm wooden buttons m2 150.00 1,025.98 153,896.81

2.1.4 Carpentry and Roofing


Supply, assemble and fix in position 10cm dia eucalyptus
upper and lower roof truss members of a given length and
2.1.4.1 m 88.60 100.30 8,886.56
span price shall include the application of three coats and
external anti-termite treatment as per the drawing
Supply, assemble and fix in position 8 cm dia eucalyptus
diagonal roof truss members of a given length and span
2.1.4.2 m 158.00 78.36 12,381.10
price shall include the application of three coats and
external anti-termite treatment as per the drawing
Supply and fix purlin in eucalyptus wood size diam 8cm
2.1.4.3 nailed into eucalyptus truss including three coats of anti - m 317.00 74.50 23,616.08
termite external treatment
Supply and fix roof cover in G-32 corrugated galvanized
iron sheet fixed into Eucalyptus wood purlin with dome
2.1.4.4 m2 217.00 454.14 98,547.43
headed galvanized nails (purlin and ridge cover measured
separately)
Supply and fix 8 mm chipwood ceiling. Price shall
2.1.4.5 m2 45.00 1,025.98 46,169.04
include 4 x 5 cm wooden buttons
2.1.4.6 Supply and fix CIS windows size 1x1.2m No 8.00 499.09 3,992.74
2.1.4.7 Supply and fix CIS doors size 1.0x2.10m No 8.00 1,306.83 10,454.62
Other office Furniture( six chairs, six tables and and one
2.1.4.8 LS 1.00 50,000.00 50,000.00
shelf) as ordered by Engineer
2.1.5 Finishing
2.1.5.1 Floor screed in cement mortar 20 mm thick (1:3 mortar) m2 73.12 333.58 24,391.52
Sub total 662,169.41
2.20 Cafe ,Kitchen and worker living rooms
2.2.1 Earth Work
2.2.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 36.48 20.44 745.57

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 136
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
Excavation for stone masonry foundation; 0.5m width and
2.2.1.2 m3 10.00 140.23 1,402.34
0.4 m depth
Cart away and dispose excavated surplus material to a
2.2.1.3 m3 13.00 26.85 349.09
distance not exceeding 1km.
Provide and fill hard core with hard basaltic or equivalent
2.2.1.4 stone, well compacted and blinded with crushed stone to a m2 37.00 208.75 7,723.81
finished thickness of 25 cm
2.2.2 Masonry and Concrete Work 0.00
Supply and construct 500 mm thick trachitic or
2.2.2.1 equivalent stone masonry foundation wall below ground m3 4.00 2,080.45 8,321.79
level bedded in cement mortar mix 1:3
Supply and construct 500 mm thick high trachitic or
2.2.2.2 equivalent stone masonry foundation wall above ground m3 4.00 2,296.70 9,186.82
level bedded in cement mortar mix 1:3
2.2.2.3 Mass concrete fill on floor slab (100mm), C-15 m2 33.30 351.38 11,701.01
2.2.3 Carpentry and Walling 0.00
Supply, assemble and fix in position eucalyptus wall post
2.2.3.1 of length 3 m span price shall include the external anti- m 117.00 78.36 9,168.28
termite treatment as per the drawing
Supply and fix purlin in Eucalyptus wood size 8 cm
2.2.3.2 m 120.00 74.50 8,939.84
nailed into eucalyptus truss
Supply and fix wall cover in G-32 corrugated galvanized
iron sheet fixed into eucalyptus wood purlin with dome
2.2.3.3 m2 121.00 416.80 50,433.26
headed galvanized nails (purlin and ridge cover measured
separately)
2.2.4 Carpentry and Roofing 0.00
Supply, assemble and fix in position 10cm dia eucalyptus
upper and lower roof truss members of a given length and
2.2.4.1 m 105.00 100.30 10,531.48
span price shall include the application of three coats and
external anti-termite treatment as per the drawing
Supply, assemble and fix in position 8 cm dia eucalyptus
diagonal roof truss members of a given length and span
2.2.4.2 m 150.00 78.36 11,754.21
price shall include the application of three coats and
external anti-termite treatment as per the drawing
Supply and fix purlin in Eucalyptus wood size 8 cm
2.2.4.3 m 125.00 74.50 9,312.33
nailed into eucalyptus truss
Supply and fix roof cover in G-32 corrugated galvanized
iron sheet fixed into eucalyptus wood purlin with dome
2.2.4.4 m2 79.00 454.14 35,876.71
headed galvanized nails (purlin and ridge cover measured
separately)
2.2.4.5 Supply and fix CIS windows size 1x1.2m No 2.00 746.76 1,493.52
2.2.4.6 Supply and fix CIS doors size 1.0x2.10m No 3.00 1,934.03 5,802.10
2.2.5 Finishing 0.00
2.2.5.1 Floor screed in cement mortar 20 mm thick, (1:3 mortar) m2 32.83 331.56 10,885.80
Sub total 193,627.97
2.30 Shower and Toilet
2.3.1 Earth Work
2.3.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 24.00 20.44 490.50
Excavation for stone masonry foundation and pit
2.3.1.2 ecxavation cording to as drwaing specification. m3 77.00 140.23 10,798.05

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 137
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
Cart away and deposit excavated surplus material to a
2.3.1.3 m3 100.10 26.85 2,688.02
distance not exceeding 1km.
2.3.2 Masonry and Concrete Work
Supply and construct 500mm thick trachitic or
2.3.2.1 equivalent stone masonry foundation wall below ground m3 28.80 2,080.45 59,916.88
level bedded in cement mortar mix 1:3
Slab for the toilet including reinforcement bar , form work
2.3.2.2 and concrete C-20 with 150mm thick m3 2.40 3,777.12 9,065.08
Mass concrete fill on floor slab (150mm) for shower, C-
2.3.2.3 m2 1.20 3,513.82 4,216.58
15
2.3.3 Carpentry and Walling
Supply, assemble and fix in position eucalyptus wall post
2.3.3.1 of length 3.5 m span price shall include the external anti- m 50.00 78.36 3,918.07
termite treatment as per the drawing
Supply and fix purlin in Eucalyptus wood size 8 cm
2.3.3.2 m 100.00 74.50 7,449.87
nailed into eucalyptus truss
Supply and fix wall cover in G-32 corrugated galvanized
iron sheet fixed into eucalyptus wood purlin with dome
2.3.3.3 m2 156.00 416.80 65,021.40
headed galvanized nails (purlin and ridge cover measured
separately)
2.3.4 Carpentry and Roofing
Supply, assemble and fix in position 10cm dia eucalyptus
upper and lower roof truss members of a given length and
2.3.4.1 m 33.00 100.30 3,309.89
span price shall include the application of three coats and
external anti-termite treatment as per the drawing
Supply, assemble and fix in position 8 cm dia eucalyptus
diagonal roof truss members of a given length and span
2.3.4.2 m 120.00 78.36 9,403.36
price shall include the application of three coats and
external anti-termite treatment as per the drawing
Supply and fix purlin in Eucalyptus wood size 8 cm
2.3.4.3 m 160.00 74.50 11,919.79
nailed into eucalyptus truss
Supply and fix roof cover in G-32 corrugated galvanized
iron sheet fixed into eucalyptus wood purlin with dome
2.3.4.4 m2 62.00 454.14 28,156.41
headed galvanized nails (purlin and ridge cover measured
separately)
2.3.4.5 Supply and fix CIS doors size 1.0x2.10m No 6.00 750.19 4,501.15
Sub Total 220,855.05
2.40 Laboratory (8x6)m2
2.4.1 Earth Work
2.4.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 38.40 20.44 784.81
Excavation for stone masonry foundation; 0.5m width and
2.4.1.2 m3 12.00 140.23 1,682.81
0.4 m depth
Cart away and deposit excavated surplus material to a
2.4.1.3 m3 15.60 26.85 418.91
distance not exceeding 1km.
Provide and fill hard core with hard basaltic or equivalent
2.4.1.4 stone, well compacted and blinded with crushed stone to a m2 18.72 208.75 3,907.83
finished thickness of 25 cm
2.4.2 Concrete and Block Work
Supply and construct 500 mm thick trachitic or
2.4.2.1 equivalent stone masonry foundation wall below ground m3 12.00 2,080.45 24,965.37
level bedded in cement mortar mix 1:3

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 138
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
Supply and construct 500 mm thick trachitic or
2.4.2.2 equivalent stone masonry foundation wall above ground m3 12.00 2,296.70 27,560.45
level bedded in cement mortar mix 1:3
2.4.2.3 Mass concrete fill on floor slab (100mm), C-10 m2 57.60 368.40 21,219.94
2.4.3 Carpentry and Walling
Supply, assemble and fix in position eucalyptus wall post
2.4.3.1 of length 3 m span price shall include the external anti- No 62.40 78.36 4,889.75
termite treatment as per the drawing
Supply and fix purlin in Eucalyptus wood size 8 cm
2.4.3.2 m 150.00 74.50 11,174.80
nailed into eucalyptus truss
Supply and fix Wall cover in G-32 corrugated galvanized
iron sheet fixed into eucalyptus wood purlin with dome
2.4.3.3 m2 193.60 416.80 80,693.22
headed galvanized nails (purlin and ridge cover measured
separately)
2.4.4 Carpentry and Roofing 0.00
Supply, assemble and fix in position 10 cm dia.
eucalyptus roof truss of a given length &span price shall
2.4.4.1 No 33.60 100.30 3,370.07
include the application of three coats and external anti-
termite treatment as per the drawing
Supply, assemble and fix in position 8 cm dia eucalyptus
diagonal roof truss members of a given length and span
2.4.4.2 m 120.00 78.36 9,403.36
price shall include the application of three coats and
external anti-termite treatment as per the drawing
Supply and fix purlin in Eucalyptus wood size 8 cm
2.4.4.3 m 200.00 74.50 14,899.74
nailed into eucalyptus truss
Supply and fix roof cover in G-32 corrugated galvanized
iron sheet fixed into eucalyptus wood purlin with dome
2.4.4.4 m2 120.00 454.14 54,496.27
headed galvanized nails (purlin and ridge cover measured
separately)
2.4.4.5 Supply and fix CIS windows size 1x1.2m No 2.00 746.76 1,493.52
2.4.4.6 Supply and fix CIS doors size 1.0x2.10m No 2.00 1,934.03 3,868.06
2.4.5 Finishing
2.4.5.1 Floor screed in cement mortar 20 mm thick, (1:3 mortar) m2 52.50 331.56 17,406.94
Sub total 2.4 282,235.87
Fence 2.0m height & 15cm φ eucalyptus poles placed
2.4.6 every 2m with barbed wire at 20cm vertical interval & m 200.00 550.00 110,000.00
erected in 0.6m depth embedded with concrete
Sub total 2.4.6 110,000.00
TOTAL BILL No. 2 CARRIED TO SUMMARY 1,468,888.30
BILL PART 3-EARHEN FILL DAM BODY
3.10 Earthwork & excavation
Top soil removal, 25 cm and place the removed material in
16,097.4
3.1.1 the d/s of the dam including despose and or placing up of m2 20.44
9
it according toan engineer order 328,995.64
Bulk cut off trench excavation 0-1.5mof silt clay soi
3.1.2 m3 1,216.82 66.76
l(according to geologist rec.n)
81,232.53
3
3.1.3 Bulk cut off trench excavation 1.5-3m m 1,454.50 81.95 119,192.89
3
3.1.4 Bulk excavation from more than 3m m 1,454.50 131.12 190,708.63
Sub-total 720,129.69

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 139
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
3.20 Compacted earthfill
3.2.1 Selected fill with clay material and compactions of the
trench Section as shown in the drawing and specification,
4,125.82 230.00
includes production of fill material, transportation and
compaction complete in all aspect m3 948,939.61
3.2.2 Selected fill with clay material and compactions of the
core Section as shown in the drawing and specification, 14,034.4
230.00
includes production of fill material, transportation and 9
compaction complete in all aspect m3 3,227,933.44
3.2.3 Selected fill with shell material and compaction of the
shell embankment Section as shown in the drawing and 41,845.2
210.00
specification, includes production of fill material, 4
transportation and compaction complete in all aspect m3 8,787,501.10
Sub-total 12,964,374.16
3.30 Transion Filter
3.3.1 Sand filter-Construction of filter (F1) with clean
washed,concrete sand as shown in the drawing and
m3 1,186.39 350.00
specification, includes production of fill material,
transportation and compaction complete in all aspect 415,236.32
3.3.2 Gravel filter-Construction of filter (F2) with clean
screened fine gravel, includes supply of gravel material, m3 1,186.39 330.00
transportation and compaction complete in all aspect 391,508.53
Sub-total 806,744.86
3.40 Toe drain Filter
Sand filter-Construction of filter (F1) with clean
washed,concrete sand as shown in the drawing and
3.4.1 m3 3,150.00 350.00
specification, includes production of fill material,
transportation and compaction complete in all aspect 1,102,499.04
Gravel filter-Construction of filter (F2) with clean
3.4.2 screened fine gravel, includes supply of gravel material, m3 4,725.00 330.00
transportation and compaction complete in all aspect
1,559,248.64
3.50 Slope protection
3.5.1 Upstream slope protection
3.5.1.1 stone reprap as it is shown on the Drawing m2 6,812.26 283.57 1,931,750.29
3.5.2 Downstream protection 0.00
3.5.2.1 Production ,transporation ,spreading and little compaction
m2 6,438.42 94.71
of 20 cm top soil 609,778.07
3.5.2.2 Supply and placing of Sodding m 2
6,438.42 20.00 128,768.38
3.5.3 Protection of the dam crest (Selected materials for
m3 883.80 99.96
preferable for Dam crest) 88,347.55
Sub-total 5,420,391.98
3.60 Down stream dam toe drainage
12,520.5
3.6.1 Drainage trench Excavation (Toe of Dam) m3 65.56
0 820,818.58
Construction of drain with clean screened fine gravel,(F2)
12,029.5
3.6.2 includes supply of gravel material, transportation and m3 330.00
0
compaction complete in all aspect 3,969,735.00
Produce,supply and place 30 cm rock riprap/Dry stone
3.6.3 m3 491.00 283.57
pitching/ in trapezoidal toe drain channel 139,232.63
Sub total 3.6 4,929,786.21

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 140
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
3.70 Temporary canal conduit For construction
3.7.1 Clearing of site to remove top soil to a depth of 200 mm
Clearing and grubing bushes trees and shrubs on the
16,080.5
3.7.2 alignment of mian canal to the width of canal and m2 20.44 328,650.24
9
embankment and debth of 0.2m.
41,068.4
3.7.3 Channel Excavation m3 65.56 2,692,361.89
1
Canal Embankment fill and compaction Spread &
3.7.4 compact 20 cm thick m3 956.61 99.96 95,625.70
layer by layer
Sub-total sub-3.8 3,116,637.84
TOTAL BILL No. 3 CARRIED TO SUMMARY 27,958,064.73
Bill Dam Instrumentation
No.4
4.10 Supply and install piezometers in embankment No 2.00 120,555.00 241,110.00
4.20 Supply and install Deformation Monitoring Monuments in
No 2.00 135,744.90
embankment 271,489.80
4.30 Produce and install concrete Bench mark No 2.00 1,000.00 2,000.00
4.40 Supply and Intsall water level staff in the irrigation intake
No 1.00 55,093.66
structure 55,093.66
4.50 Supply and install Seepage measuring weir (V-Notch)
No 1.00 109,939.00
supply and installation 109,939.00
Sub-total 679,632.46
TOTAL BILL No. 4 CARRIED TO SUMMARY 679,632.46
Bill No.5 Spillway
5.10 Earthwork & excavation
Site clearing/Stripping of topsoil to a depth of 0.2 m or 17,000.0
5.1.1 m2 20.44
more 0 347,440.76
Bulk excavation up to 1.5 including disposal as ordered by 19,125.0
5.1.2 m3 65.56
engineers 0 1,253,796.20
Bulk excavation from 1. 5 to 3 m or more including
5.1.3 m3 6,375.00 81.95
disposal as ordered by engineers 522,415.08
5.1.4 Back fill from excavated material behind retaining walls m3 477.00 66.76 31,843.67
Compacted granular backfill on the back of walls from
5.1.5 m3 1,540.00 99.96
imported selected materials as per the specification 153,943.47
5.1.6 Cart away excavated material as ordered by engineers m3 3,400.00 26.85 91,301.30
Sub total 2,400,740.47
5.20 Masonry work
25 cm hard core in retaining walls,approach channel and
5.2.1 m2 5,100.00 208.61
chut below cyclopean concrete 1,063,919.50
50 cm thick masonry wall below ground level in 1:3
5.2.2 cement mortar in u/s and d/s floor cut offs up to a m3 75.00 2,058.31
maximum depth of 1.0 m 154,373.32
30 cm thick masonry work in 1:3 cement mortar in
5.2.3 m3 450.00 2,058.31
approach channel floor below concrete 926,239.90
Masonry wall in retaining walls in approach channel
5.2.4 m3 60.00 2,272.30
sections 136,338.27
5.2.5 Cyclopean Concrete in Ogee Weir m3 80.58 1,295.95 104,424.08
5.2.6 Masonry wall in weir walls above ground level m3 10.23 2,272.30 23,244.87

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 141
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
30 cm thick Cyclopean Concrete work in chute floor
5.2.7 m3 4,650.00 1,295.95
below concrete 6,026,179.70
5.2.8 Masonry wall in retaining walls in chute sections m3 558.00 2,272.30 1,267,945.90
30 cm thick Cyclopean Concrete work in stiling basin
5.2.9 m3 60.00 1,295.95
floor below concrete 77,757.16
5.2.10 Masonry wall in retaining walls instiling basin sections m3 6.44 2,272.30 14,628.19
5.2.11 40 cm hand placed rock riprap in trapezoidal exit channel m3 400.00 283.57 113,427.81
Sub total 9,908,478.71
5.30 Concrete work
16,000.0
5.3.1 10 cm thick blinding concrete C-10 m2 343.23
0 5,491,628.12
Provide cut and fix in position smooth finish formwork 2
5.3.2 m 2,896.00 1,009.98
Type "F3" 2,924,899.75
15cm thick C 25 reinforced concrete in top of the weir and
5.3.3 d/s inclined face with a minimum cement content of 360 m3 9.00 3,935.77
kg/m3 including formwork. 35,421.91
C 25 reinforced concrete in upstream and downs stream
5.3.4 weir cut off with a minimum cement content of 360 kg/m3 m3 22.80 3,935.77
including as indicated in drawings and specification 89,735.50
C 25 reinforced concrete in chute section and stilling
5.3.5 basin floor/bed with a minimum cement content of 360 m3 2,325.00 3,935.77
kg/m3 as indicated in drawings and specification 9,150,659.61
C 25 reinforced concrete in chute section cutoff
5.3.6 wall/anchorage with a minimum cement content of 360 m3 558.00 3,935.77
kg/m3 as indicated in drawings and specification 2,196,158.31
16mm & 8mm deformed bar Steel reinforcement according
5.3.7 to structural drawings. Price includes cutting, bending, kg 1,106.17 114.64
placing in position and tying wire ogee part of weir 126,807.05
12 mm & 8mm deformed bar Steel reinforcement according
70,885.4
5.3.8 to structural drawings. Price includes cutting, bending, kg 114.64
3
placing in position and tying wire of chute 8,126,010.58
Sub-total 28,141,320.81
5.40 Drain Pipe
5.4.1 ∅200mm non perforated longitudinal drain pipe m 620.00 519.62 322,164.40
5.4.2 ∅100mm perforated lateral pipe at 20m spacing m 775.00 452.01 350,304.84
5.4.3 Supply and place gravel surrounding the peroforated pipe m3 3,100.00 330.00 1,023,000.00
Sub total 1,695,469.24
5.50 Miscellaneous
5.5.1 Supply and fix 250 mm PVC water-stops m 412.00 628.00 258,736.00
2
5.5.2 Resin bonded cork filler (20 mm thick) m 123.60 950.00 117,420.00
5.5.3 Polysulphide sealant (20 mm wide x 30 mm deep) m 430.00 600.00 258,000.00
Sub total 5.6 634,156.00
TOTAL BILL No. 5 CARRIED TO SUMMARY 42,780,165.24
Bill No. 6 IRRIGATION INLET AND OUTLET
6.00 Intake Tower And Access Bridge
6.00 Outlet works
6.10 Earthwork & excavation
Shell Material Spreading and compaction to the required
6.1.1 m2 142.00 95.82 13,607.12
rate

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 142
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
Fill with Sand Filter Material from borrow pits with in haul
6.1.2 m3 71.00 350.00 24,850.00
distance 20km, including compaction
Fill with Gravel Filter Material from borrow pits with in
6.1.3 m3 248.50 330.00 82,005.00
haul distance 20km, including compaction
6.1.3 Back fill from imported granular material m3 42.60 66.76 2,843.90
3
6.1.4 Cart away excavated material as ordered by Engineers m 28.40 26.85 762.63
Sub-total 124,068.66
6.20 Masonry work
50 cm Hard core in retaining walls at terminal
6.2.1 m3 9.80 208.61 2,044.39
structure/stilling basin below concrete
6.2.2 Masonry wall in terminal structure in basin depth m3 9.52 2,272.30 21,632.34
Sub-total 23,676.73
6.3 Pipes & Fitting
6.3.1 800mm Steel pipe of 6mm thickness with full accessories m 71.00 26,640.00 1,891,440.00
6.3.2 800mm diameter Butter fly valve with full accessories Pc 2.00 600,000.00 1,200,000.00
Sub-total 3,091,440.00
6.40 Concrete work
C 25 reinforced concrete in the intake tower frame with a
6.4.1 minimum cement content of 360 kg/m3 including m3 7.00 3,935.77 27,550.37
formworks.
6.4.2 10 cm C25 concrete in terminal structure/stilling basin m2 7.10 3,935.77 27,943.95
12mm deformed bar Steel reinforcement according to
6.4.3 structural drawings. Price includes cutting, bending, placing kg 225.78 114.64 25,882.22
in position and tying wire
6.4.4 16 mm deformed bar Steel reinforcement of intake tower kg 1,630.81 114.64 186,949.82
Installing of Trashrack in intake tower 10cmx10cm opening
6.4.5 m2 1.00 20,000.00 20,000.00
with 12mm dia. steel reinforcement
Sub-total 288,326.36
6.50 Tower Bridge
400mm thickness of Crushed Rock for Foot pad of the
6.5.1 m3 1.80 208.61 375.50
Bridge
6.5.2 Mass concrete on dam bod (cyclopean60%,concrete40%) m3 2.40 3,432.27 8,237.44
Reinforcement concrete class C-25 Bottom Slab of Foot
6.5.3 m3 2.40 3,935.77 9,445.84
Bridge
Supply, cut, bend and fix in position high yield steel
6.5.4 kg 178.20 114.64 20,428.11
reinforcement bars of dia. 12mm

Supply, cut, bend and fix in position high yield steel


6.5.5 kg 361.13 114.64 41,398.44
reinforcement bars of dia. 16mm
Handrail steel pipe in different dia. As shown in the
6.5.6 m 259.68 1,250.00 324,600.00
drawing
6.5.10 Formwork m2 36.06 1,009.98 36,419.85
Sub-total sub-3.7 440,905.18
TOTAL BILL No. 6 CARRIED TO SUMMARY 3,968,416.93
Bill
Access road for construction
No. 7

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 143
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Item
Item Description Unit Qty Unit Price Amount
Nr.
7.00 Gravel access road of 6 m wide km 2.00
Clearing and grabbing works in areas including interceptor
7.10 m2 25,200.0 14.76 371,965.99
drain & working areas as specified by the engineer
Excavation cut/fill earth works of the road section in normal
7.20 m3 7,800.00 65.56 511,352.17
soil including side drains
7.30 Spreading & compaction for camber formation m2 12,000.0 20.00 240,000.00
Fill and compaction works of 150 mm thick selected gravel
7.40 m3 1,800.00 210.00 378,000.00
wearing material
Total 1,501,318.17

TOTAL BILL No. 6 CARRIED TO SUMMARY 1,501,318.17

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 144
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

Section VI – ANNEXES

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 145
Contract Agreement Finna Bilte Project Construction (Dam and Appurtenant Structures)

ANNEXES (Additional Documents Forming the Contract)


1. List of Machinery & Equipment
S.N Items of Equipment Unit Quantity
1 Dozer 200HP and above No. 2
2 Excavator 0.5cm2 and above, minimum 140HP No. 4
4 Grader 140 HP and above No 2
5 Roller 15 Ton Smooth Wheel Compactor No 3
6 Roller 15 Ton or above Sheep Foot Compactor No 5
7 Shower Truck 10m3 and above No 2
8 Dump Truck 14m3 and above No 14
9 Double Cabin 4WD No 2
10 Pick up No 2
11 Truck mounted or Concrete mixer 500-750 litre No 2
12 Hand Compacter No 3
13 Fuel Truck No 1
2. Key Personnel
General Specific Work
No. Position Education Qualification Experience experience with
Required (Year) similar work (years)
B.Sc/MSC in Irrigation Engineering, B.SC.10
B.SC.8years/MSC
1 Project Manager Hydraulic, Dam Engineering or related fields years/MSC 8
6years
of study years
B.Sc/MSC in Irrigation Engineering,
B.SC.8years/MSC B.SC.6years/MSC
2 Site Engineer1 Hydraulic, Dam Engineering or related fields
6years 4 years
of study
Diploma in Water/Civil Engineering or B.SC.8years/MSC B.SC.6years/MSC
3 Site Engineer2
related fields of study 6years 4 years
Diploma in Water/Civil Engineering or B.SC.7years/MSC B.SC.5years/MSC
4 Office Engineer
related fields of study 5years 3 years
Construction Technic Diploma in Water/ Construction or
5 7 years 5 years
Forman1 related fields of study from TVET College

Construction Technic Diploma in Water/ Construction or


6 6years 5years
Forman2 related fields of study from TVET College

Construction Technic Diploma in Water/ Construction or


7 6 years 5 years
Forman3 related fields of study from TVET College

B.Sc./Diploma in surveying technology, B.SC.5 years/ B.SC.5 years/


8 Surveyor1
Technic Diploma Surveying Diploma 3 years Diploma 3 years

Geologist/material B.Sc/MSC in Geology, Geotechnical B.SC.8years/MSC B.SC.6 years/MSC


9
Engineer Engineering or related fields of study 6years 4years

Laboratory B.Sc/MSC in Geology, Geotechnical B.SC.7years/MSC B.SC.5years/MSC


10
technician Engineering or related fields of study 5years 3years

SBD-Works (NCB) - Prepared by the FPPA Version 1, August 2011) Page 146

You might also like