Micom P40 Agile: 5Th Generation
Micom P40 Agile: 5Th Generation
Grid Solutions
Technical Manual
Single/Dual Breaker Current Differential with Distance
Hardware Version: Q
Software Version: AA
Publication Reference: P54-TM-EN-1.1
Contents
Chapter 1 Introduction 1
1 Chapter Overview 3
2 Foreword 4
2.1 Target Audience 4
2.2 Typographical Conventions 4
2.3 Nomenclature 5
2.4 Compliance 5
3 Product Scope 6
3.1 Product Versions 6
3.2 Ordering Options 7
4 Features and Functions 8
4.1 Current Differential Protection Functions 8
4.2 Distance Protection Functions 8
4.3 Protection Functions 9
4.4 Control Functions 9
4.5 Measurement Functions 10
4.6 Communication Functions 10
5 Logic Diagrams 11
6 Functional Overview 13
ii P54-TM-EN-1.1
P54 Contents
Chapter 5 Configuration 73
1 Chapter Overview 75
2 Settings Application Software 76
3 Using the HMI Panel 77
3.1 Navigating the HMI Panel 78
3.2 Getting Started 78
3.3 Default Display 78
3.4 Default Display Navigation 79
3.5 Processing Alarms and Records 79
3.6 Single Line Diagram (SLD) Viewer 80
3.6.1 Circuit Breaker Control (SLD View Only) 80
3.7 Menu Structure 81
3.8 Direct Access (Menu Context Keys) 82
3.8.1 Control Inputs 82
3.9 Changing the Settings 82
3.10 Function Keys 83
P54-TM-EN-1.1 iii
Contents P54
iv P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 v
Contents P54
vi P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 vii
Contents P54
viii P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 ix
Contents P54
x P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 xi
Contents P54
xii P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 xiii
Contents P54
xiv P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 xv
Contents P54
xvi P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 xvii
Contents P54
xviii P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 xix
Contents P54
xx P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 xxi
Contents P54
xxii P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 xxiii
Contents P54
xxiv P54-TM-EN-1.1
P54 Contents
P54-TM-EN-1.1 xxv
Contents P54
xxvi P54-TM-EN-1.1
Table of Figures
Figure 1: Key to logic diagrams 12
Figure 2: Functional Overview 13
Figure 3: Hardware architecture 32
Figure 4: Coprocessor hardware architecture 33
Figure 5: Exploded view of IED 34
Figure 6: Front panel (80TE) 36
Figure 7: HMI panel 37
Figure 8: Rear view of populated case 40
Figure 9: Terminal block types 41
Figure 10: Example—fitted IP2x shields (cabling omitted for clarity) 41
Figure 11: Rear connection to terminal block 42
Figure 12: Main processor board 43
Figure 13: Power supply board 44
Figure 14: Power supply assembly 45
Figure 15: Power supply terminals 46
Figure 16: Watchdog contact terminals 47
Figure 17: Rear serial port terminals 48
Figure 18: Input module - 1 transformer board 48
Figure 19: Input module schematic 49
Figure 20: Transformer board 50
Figure 21: Input board 51
Figure 22: Standard output relay board - 8 contacts 52
Figure 23: IRIG-B board 53
Figure 24: Fibre optic board 54
Figure 25: Rear communication board 55
Figure 26: Redundant Ethernet board 56
Figure 27: Redundant IEC 61850-9-2LE board 58
Figure 28: Fully populated Coprocessor board 59
Figure 29: Software Architecture 64
Figure 30: Frequency response of FIR filters 70
Figure 31: Frequency Response (indicative only) 71
Figure 32: HMI Default Display 79
Figure 33: HMI Alarms Display 80
Figure 34: HMI SLD Display 81
Figure 35: HMI Function Keys Display 84
Figure 36: Comparison of Conventional IED and Sampled Analogue Values IED 88
Figure 37: Data sampling using an IEC 61850-9-2LE interface 89
Figure 38: Ping-pong measurement for alignment of current signals 100
Table of Figures P54
xxviii P54-TM-EN-1.1
P54 Table of Figures
P54-TM-EN-1.1 xxix
Table of Figures P54
xxx P54-TM-EN-1.1
P54 Table of Figures
P54-TM-EN-1.1 xxxi
Table of Figures P54
xxxii P54-TM-EN-1.1
P54 Table of Figures
Figure 236: Circuit Breaker Trip Conversion Logic Diagram (Module 63) 376
Figure 237: Voltage Monitor for CB Closure (Module 59) 377
Figure 238: Check Synchronisation Monitor for CB closure (Module 60) 378
Figure 239: Three-phase Autoreclose System Check Logic Diagram (Module 45) 380
Figure 240: CB Manual Close System Check Logic Diagram (Module 51) 381
Figure 241: CB State logic diagram (Module 1) 383
Figure 242: CB State logic diagram (Module 2) 384
Figure 243: Circuit Breaker Open logic diagram (Module 3) 385
Figure 244: CB In Service logic diagram (Module 4) 385
Figure 245: Autoreclose Enable logic diagram (Module 5) 386
Figure 246: Leader/Follower CB Selection Logic Diagram (Module 6) 387
Figure 247: Leader/Follower logic diagram (Module 7 & 8) 388
Figure 248: Autoreclose Modes Enable logic diagram (Module 9) 390
Figure 249: Force three-phase trip logic diagram (Module 10) 391
Figure 250: Autoreclose Initiation logic diagram (Module 11) 392
Figure 251: Autoreclose Trip Test logic diagram (Module 12) 393
Figure 252: Autoreclose initiation by internal single and three phase trip or external trip for CB1 394
(Module 13)
Figure 253: Autoreclose initiation by internal single and three phase trip or external trip for CB2 395
(Module 14)
Figure 254: Protection Reoperation and Evolving Fault logic diagram (Module 20) 396
Figure 255: Fault Memory logic diagram (Module 15) 396
Figure 256: Autoreclose In Progress logic diagram for CB1 (Module 16) 397
Figure 257: Autoreclose In Progress logic diagram for CB2 (Module 17) 398
Figure 258: Autoreclose Sequence Counter logic diagram (Module 18) 399
Figure 259: Single-phase Autoreclose Cycle Selection logic diagram (Module 19) 400
Figure 260: Three-phase Autoreclose Cycle Selection logic diagram (Module 21) 401
Figure 261: Dead time Start Enable logic diagram (Module 22) 402
Figure 262: Single-phase Leader Dead Time logic diagram (Module 24) 404
Figure 263: Three-phase Leader CB Dead Time logic diagram (Module 25 and Module 26) 405
Figure 264: Follower Enable logic diagram (Module 27) 406
Figure 265: Single-phase Follower CB timing logic diagram (Module 28) 407
Figure 266: Three-phase Follower CB timing logic diagram (Module 29) 408
Figure 267: Circuit Breaker Autoclose Logic Diagram (Modules 32 & 33) 409
Figure 268: Prepare Reclaim Initiation logic diagram (Module 34) 410
Figure 269: Reclaim Time logic diagram (Module 35) 411
Figure 270: Successful Autoreclose Signals logic diagram (Module 36) 412
Figure 271: Autoreclose Reset Successful Indication logic diagram (Modules 37 & 38) 413
Figure 272: Circuit Breaker Healthy and System Check Timers Healthy logic diagram (Module 38 414
& 40)
Figure 273: Autoreclose Shot Counters logic diagram (Modules 41 & 42) 415
P54-TM-EN-1.1 xxxiii
Table of Figures P54
xxxiv P54-TM-EN-1.1
P54 Table of Figures
P54-TM-EN-1.1 xxxv
Table of Figures P54
xxxvi P54-TM-EN-1.1
P54 Table of Figures
Figure 394: IM64 channel fail and scheme fail logic 645
Figure 395: IM64 general alarm signals logic 645
Figure 396: IM64 communications mode and IEEE C37.94 alarm signals 646
Figure 397: IM64 two-terminal scheme extended supervision 648
Figure 398: IM64 three-terminal scheme extended supervision 648
Figure 399: Example assignment of InterMiCOM signals within the PSL 658
Figure 400: Direct connection 659
Figure 401: Indirect connection using modems 659
Figure 402: RS485 biasing circuit 668
Figure 403: Remote communication using K-Bus 669
Figure 404: Board connectors 671
Figure 405: IED and REB IP address configuration 672
Figure 406: Connection using (a) an Ethernet switch and (b) a media converter 674
Figure 407: Example PRP redundant network 682
Figure 408: HSR multicast topology 683
Figure 409: HSR unicast topology 684
Figure 410: HSR application in the substation 685
Figure 411: IED attached to redundant Ethernet star or ring circuit 685
Figure 412: SNMP MIB tree 688
Figure 413: Control input behaviour 703
Figure 414: Data model layers in IEC61850 714
Figure 415: Edition 2 system - backward compatibility 718
Figure 416: Edition 1 system - forward compatibility issues 719
Figure 417: GPS Satellite timing signal 722
Figure 418: Timing error using ring or line topology 724
Figure 419: RADIUS server/client communication 747
Figure 420: Rack mounting of products 766
Figure 421: Terminal block types 768
Figure 422: 40TE case dimensions 774
Figure 423: 60TE case dimensions 775
Figure 424: 80TE case dimensions 776
Figure 425: RP1 physical connection 792
Figure 426: Remote communication using K-bus 793
Figure 427: InterMicom loopback testing 796
Figure 428: Simulated input behaviour 804
Figure 429: Test example 1 805
Figure 430: Test example 2 806
Figure 431: Test example 3 807
Figure 432: Current Differential Bias Characteristics 808
Figure 433: State impedances 825
P54-TM-EN-1.1 xxxvii
Table of Figures P54
xxxviii P54-TM-EN-1.1
CHAPTER 1
INTRODUCTION
Chapter 1 - Introduction P54
2 P54-TM-EN-1.1
P54 Chapter 1 - Introduction
1 CHAPTER OVERVIEW
This chapter provides some general information about the technical manual and an introduction to the device(s)
described in this technical manual.
This chapter contains the following sections:
Chapter Overview 3
Foreword 4
Product Scope 6
Features and Functions 8
Logic Diagrams 11
Functional Overview 13
P54-TM-EN-1.1 3
Chapter 1 - Introduction P54
2 FOREWORD
This technical manual provides a functional and technical description of General Electric's P54, as well as a
comprehensive set of instructions for using the device. The level at which this manual is written assumes that you
are already familiar with protection engineering and have experience in this discipline. The description of principles
and theory is limited to that which is necessary to understand the product. For further details on general
protection engineering theory, we refer you to General Electric's publication, Protection and Automation
Application Guide, which is available online or from our Contact Centre.
We have attempted to make this manual as accurate, comprehensive and user-friendly as possible. However we
cannot guarantee that it is free from errors. Nor can we state that it cannot be improved. We would therefore be
very pleased to hear from you if you discover any errors, or have any suggestions for improvement. Our policy is to
provide the information necessary to help you safely specify, engineer, install, commission, maintain, and
eventually dispose of this product. We consider that this manual provides the necessary information, but if you
consider that more details are needed, please contact us.
All feedback should be sent to our contact centre via:
contact.centre@ge.com
4 P54-TM-EN-1.1
P54 Chapter 1 - Introduction
2.3 NOMENCLATURE
Due to the technical nature of this manual, many special terms, abbreviations and acronyms are used throughout
the manual. Some of these terms are well-known industry-specific terms while others may be special product-
specific terms used by General Electric. The first instance of any acronym or term used in a particular chapter is
explained. In addition, a separate glossary is available on the General Electric website, or from the General Electric
contact centre.
We would like to highlight the following changes of nomenclature however:
● The word 'relay' is no longer used to describe the device itself. Instead, the device is referred to as the 'IED'
(Intelligent Electronic Device), the 'device', or the 'product'. The word 'relay' is used purely to describe the
electromechanical components within the device, i.e. the output relays.
● British English is used throughout this manual.
● The British term 'Earth' is used in favour of the American term 'Ground'.
2.4 COMPLIANCE
The device has undergone a range of extensive testing and certification processes to ensure and prove
compatibility with all target markets. A detailed description of these criteria can be found in the Technical
Specifications chapter.
P54-TM-EN-1.1 5
Chapter 1 - Introduction P54
3 PRODUCT SCOPE
The P543 and P546 devices have been designed for current differential protection of overhead line and cable
applications, as well as solidly grounded systems and Petersen Coil grounded systems. The products within this
range interface readily with the longitudinal (end-end) communications channel between line terminals. The P543
device applies to single circuit breaker applications and the P546 device is for dual circuit breaker applications.
The P54 includes high-speed current differential unit protection with optional high performance sub-cycle distance
protection, including phase segregated aided directional earth fault protection as well as in-zone transformer
differential protection (P543) and 4-shot phase-segregated autoreclose protection.
The P54 can be ordered in 40/60/80TE cases with several different digital input/output options also offered.
The P54 is available with conventional 1A/5A CT inputs and 100/120V VT inputs or with a IEC 61850-9-2LE
redundant Ethernet process bus input for sampled analogue values. Unlike a conventional IED, a device with an
IEC 61850-9-2 interface, or Sampled Value (SV) device accepts current and voltage measurement inputs, which
have already been digitized in accordance with the IEC 61850-9-2LE standard. The IEC 61850-9-2LE version of the
P54 IED accepts sampled analogue values from merging units. It does not accept analogue values directly and
therefore does not have any current or voltage transformers. This provides a number of advantages over
conventional devices, which are discussed throughout this technical manual.
The differences between the model variants are summarised in the table below:
Feature/Variant P543 P546
Number of CT Inputs 5 8
Number of VT inputs 4 5
Opto-coupled digital inputs 8-40 8-24
Standard relay output contacts 7-43 7-32
High speed high break output contacts 4-8 4-8
The 5 VTs model allow flexible configuration options, where one can be used to measure the residual voltage if
required. To do this, you must first set all relevant residual voltage input settings to measured, then the VT2
Selection setting to Broken Delta.
5th Generation P543 and P546 models cover the digital input and output options of 4th Generation P543/5 single
breaker and P544/6 dual breaker versions, so the P544/5 models are not needed in the P54 CORTEC. An IEC
61850-9-2LE option is included for P543/6 single and dual breaker models, which was previously only available on
the P546 model. P54 models are available in 40TE/60TE/80TE case sizes, whereas previous P543-6 models only
offered 60/80TE.
In the P54 CORTEC the line differential channel options and digital I/O options use separate digits to make selection
of these options simpler and more flexible. A new order option is also included to select subcylce 1/3 pole tripping
transmission distance protection or non subcycle subtransmission/distribution distance protection with 3 Pole
tripping only. The non subcycle distance protection aligns with the distance protection in the 4th Generation P445
model. Rear communication port protocol is selectable in the settings, so there is no CORTEC option. For 4th
Generation this was required as an order option.
6 P54-TM-EN-1.1
P54 Chapter 1 - Introduction
P54-TM-EN-1.1 7
Chapter 1 - Introduction P54
8 P54-TM-EN-1.1
P54 Chapter 1 - Introduction
P54-TM-EN-1.1 9
Chapter 1 - Introduction P54
Feature ANSI
NERC compliant cyber-security
Front USB communication port for configuration
Rear serial RS485 communication port for SCADA control--Courier/DNP 3.0/
16S
IEC60870-5-103 protocol selectable in settings
Rear serial FO communication ports for SCADA control (optional) –
16S
Courier/DNP 3.0/IEC60870-5-103 protocol selectable in settings
Ethernet communication (optional)--IEC61850 protocol 16E
Redundant Ethernet communication (optional)--IEC61850 protocol 16E
SNMP 16E
IRIG-B modulated and unmodulated time synchronisation (optional) CLK
IEEE 1588 PTP
10 P54-TM-EN-1.1
P54 Chapter 1 - Introduction
5 LOGIC DIAGRAMS
This technical manual contains many logic diagrams, which should help to explain the functionality of the device.
Although this manual has been designed to be as specific as possible to the chosen product, it may contain
diagrams, which have elements applicable to other products. If this is the case, a qualifying note will accompany
the relevant part.
The logic diagrams follow a convention for the elements used, using defined colours and shapes. A key to this
convention is provided below. We recommend viewing the logic diagrams in colour rather than in black and white.
The electronic version of the technical manual is in colour, but the printed version may not be. If you need coloured
diagrams, they can be provided on request by calling the contact centre and quoting the diagram number.
P54-TM-EN-1.1 11
Chapter 1 - Introduction P54
Key:
Energising Quantity AND gate &
Hardcoded setting
Pulse / Latch
Measurement Cell S
SR Latch Q
R
Internal Calculation
S
SR Latch Q
Derived setting Reset Dominant RD
Switch Multiplier X
Bandpass filter
Comparator for detecting
undervalues
12 P54-TM-EN-1.1
P54 Chapter 1 - Introduction
6 FUNCTIONAL OVERVIEW
This diagram is applicable to P54 product models. Use the key on the diagram to determine the features relevant
to the product described in this technical manual.
BUSBAR 1
52
52 SYNCH
-2
50/27
87P 87ST 21 78 68 SOTF
21FL 78DC 50/51
LINE 87N TEFD 50N 67N 67N 25
CTS 51N SEF
67 46 46BC 49 32 37 50BF VTS 64N
SEF 27 50BF
59N 79-2 25-2
59 -2
81
59R df/dt
LINE
81U
81O SELF
79 MEAS SOE DFR MON.
V00077
The following table lists the P54 ANSI numbers and the corresponding function descriptions:
Device Number Function
25 Check Sychronising
27 Phase and Line Undervoltage
32 Directional Power Protection
37 Undercurrent
46 Negative Sequence Overcurrent
49 Thermal Overload
50 Phase Definite Time Overcurrent
51 Phase Inverse-Time Overcurrent
52 Circuit Breaker Control
59 Phase and Line Overvoltage
67 Directional Phase Overcurrent
68 Power Swing blocking
78 Out-of-Step Tripping
78DC Delta (Increment) Protection
79 Autoreclose/Adaptive Autoreclose
85 Teleprotection Channel Schemes
86 Latching/Lockout Contacts
87P Line Differential – 2 or 3 Ends
87N Neutral Differential
87ST Stub Bus Protection
21BL Load Encroachment/Blinder
21FL Fault Locator
P54-TM-EN-1.1 13
Chapter 1 - Introduction P54
14 P54-TM-EN-1.1
CHAPTER 2
SAFETY INFORMATION
Chapter 2 - Safety Information P54
16 P54-TM-EN-1.1
P54 Chapter 2 - Safety Information
1 CHAPTER OVERVIEW
This chapter provides information about the safe handling of the equipment. The equipment must be properly
installed and handled in order to maintain it in a safe condition and to keep personnel safe at all times. You must
be familiar with information contained in this chapter before unpacking, installing, commissioning, or servicing the
equipment.
This chapter contains the following sections:
Chapter Overview 17
Health and Safety 18
Symbols 19
Installation, Commissioning and Servicing 20
Decommissioning and Disposal 26
Regulatory Compliance 27
P54-TM-EN-1.1 17
Chapter 2 - Safety Information P54
The documentation provides instructions for installing, commissioning and operating the equipment. It cannot,
however cover all conceivable circumstances. In the event of questions or problems, do not take any action
without proper authorisation. Please contact your local sales office and request the necessary information.
18 P54-TM-EN-1.1
P54 Chapter 2 - Safety Information
3 SYMBOLS
Throughout this manual you will come across the following symbols. You will also see these symbols on parts of
the equipment.
Caution:
Refer to equipment documentation. Failure to do so could result in damage to the
equipment
Warning:
Risk of electric shock
Warning:
Risk of damage to eyesight
Earth terminal. Note: This symbol may also be used for a protective conductor (earth) terminal if that terminal
is part of a terminal block or sub-assembly.
Note:
The term 'Earth' used in this manual is the direct equivalent of the North American term 'Ground'.
P54-TM-EN-1.1 19
Chapter 2 - Safety Information P54
Plan carefully, identify any possible hazards and determine how best to move the product. Look at other ways of
moving the load to avoid manual handling. Use the correct lifting techniques and Personal Protective Equipment
(PPE) to reduce the risk of injury.
Caution:
All personnel involved in installing, commissioning, or servicing this equipment must be
familiar with the correct working procedures.
Caution:
Consult the equipment documentation before installing, commissioning, or servicing
the equipment.
Caution:
Always use the equipment as specified. Failure to do so will jeopardise the protection
provided by the equipment.
Warning:
Removal of equipment panels or covers may expose hazardous live parts. Do not touch
until the electrical power is removed. Take care when there is unlocked access to the
rear of the equipment.
Warning:
Isolate the equipment before working on the terminal strips.
Warning:
Use a suitable protective barrier for areas with restricted space, where there is a risk of
electric shock due to exposed terminals.
Caution:
Disconnect power before disassembling. Disassembly of the equipment may expose
sensitive electronic circuitry. Take suitable precautions against electrostatic voltage
discharge (ESD) to avoid damage to the equipment.
20 P54-TM-EN-1.1
P54 Chapter 2 - Safety Information
Warning:
NEVER look into optical fibres or optical output connections. Always use optical power
meters to determine operation or signal level.
Warning:
Testing may leave capacitors charged to dangerous voltage levels. Discharge
capacitors by reducing test voltages to zero before disconnecting test leads.
Caution:
Operate the equipment within the specified electrical and environmental limits.
Caution:
Before cleaning the equipment, ensure that no connections are energised. Use a lint
free cloth dampened with clean water.
Note:
Contact fingers of test plugs are normally protected by petroleum jelly, which should not be removed.
Caution:
Equipment intended for rack or panel mounting is for use on a flat surface of a Type 1
enclosure, as defined by Underwriters Laboratories (UL).
Caution:
To maintain compliance with UL and CSA/CUL, install the equipment using UL/CSA-
recognised parts for: cables, protective fuses, fuse holders and circuit breakers,
insulation crimp terminals, and replacement internal batteries.
Caution:
Where UL/CSA listing of the equipment is required for external fuse protection, a UL or
CSA Listed fuse must be used for the auxiliary supply. The listed protective fuse type is:
Class J time delay fuse, with a maximum current rating of 15 A and a minimum DC
rating of 250 V dc (for example type AJT15).
Caution:
Where UL/CSA listing of the equipment is not required, a high rupture capacity (HRC)
fuse type with a maximum current rating of 16 Amps and a minimum dc rating of 250 V
dc may be used for the auxiliary supply (for example Red Spot type NIT or TIA).
For P50 models, use a 1A maximum T-type fuse.
For P60 models, use a 4A maximum T-type fuse.
P54-TM-EN-1.1 21
Chapter 2 - Safety Information P54
Caution:
Digital input circuits should be protected by a high rupture capacity NIT or TIA fuse with
maximum rating of 16 A. for safety reasons, current transformer circuits must never be
fused. Other circuits should be appropriately fused to protect the wire used.
Caution:
CTs must NOT be fused since open circuiting them may produce lethal hazardous
voltages
Warning:
Terminals exposed during installation, commissioning and maintenance may present a
hazardous voltage unless the equipment is electrically isolated.
Caution:
Tighten M4 clamping screws of heavy duty terminal block connectors to a nominal
torque of 1.3 Nm.
Tighten captive screws of terminal blocks to 0.5 Nm minimum and 0.6 Nm maximum.
Caution:
Always use insulated crimp terminations for voltage and current connections.
Caution:
Always use the correct crimp terminal and tool according to the wire size.
Caution:
Watchdog (self-monitoring) contacts are provided to indicate the health of the device
on some products. We strongly recommend that you hard wire these contacts into the
substation's automation system, for alarm purposes.
Caution:
Earth the equipment with the supplied PCT (Protective Conductor Terminal).
Caution:
Do not remove the PCT.
Caution:
The PCT is sometimes used to terminate cable screens. Always check the PCT’s integrity
after adding or removing such earth connections.
22 P54-TM-EN-1.1
P54 Chapter 2 - Safety Information
Caution:
Use a locknut or similar mechanism to ensure the integrity of stud-connected PCTs.
Caution:
The recommended minimum PCT wire size is 2.5 mm² for countries whose mains supply
is 230 V (e.g. Europe) and 3.3 mm² for countries whose mains supply is 110 V (e.g. North
America). This may be superseded by local or country wiring regulations.
For P60 products, the recommended minimum PCT wire size is 6 mm². See product
documentation for details.
Caution:
The PCT connection must have low-inductance and be as short as possible.
Caution:
All connections to the equipment must have a defined potential. Connections that are
pre-wired, but not used, should be earthed, or connected to a common grouped
potential.
Caution:
Check voltage rating/polarity (rating label/equipment documentation).
Caution:
Check CT circuit rating (rating label) and integrity of connections.
Caution:
Check protective fuse or miniature circuit breaker (MCB) rating.
Caution:
Check integrity of the PCT connection.
Caution:
Check voltage and current rating of external wiring, ensuring it is appropriate for the
application.
Warning:
Do not open the secondary circuit of a live CT since the high voltage produced may be
lethal to personnel and could damage insulation. Short the secondary of the line CT
before opening any connections to it.
P54-TM-EN-1.1 23
Chapter 2 - Safety Information P54
Note:
For most General Electric equipment with ring-terminal connections, the threaded terminal block for current transformer
termination is automatically shorted if the module is removed. Therefore external shorting of the CTs may not be required.
Check the equipment documentation and wiring diagrams first to see if this applies.
Caution:
Where external components such as resistors or voltage dependent resistors (VDRs) are
used, these may present a risk of electric shock or burns if touched.
Warning:
Take extreme care when using external test blocks and test plugs such as the MMLG,
MMLB and P990, as hazardous voltages may be exposed. Ensure that CT shorting links
are in place before removing test plugs, to avoid potentially lethal voltages.
Warning:
Data communication cables with accessible screens and/or screen conductors,
(including optical fibre cables with metallic elements), may create an electric shock
hazard in a sub-station environment if both ends of the cable screen are not connected
to the same equipotential bonded earthing system.
i. The installation shall include all necessary protection measures to ensure that no
fault currents can flow in the connected cable screen conductor.
ii. The connected cable shall have its screen conductor connected to the protective
conductor terminal (PCT) of the connected equipment at both ends. This connection
may be inherent in the connectors provided on the equipment but, if there is any doubt,
this must be confirmed by a continuity test.
iii. The protective conductor terminal (PCT) of each piece of connected equipment shall
be connected directly to the same equipotential bonded earthing system.
iv. If, for any reason, both ends of the cable screen are not connected to the same
equipotential bonded earth system, precautions must be taken to ensure that such
screen connections are made safe before work is done to, or in proximity to, any such
cables.
vi. Equipment temporarily connected to this product for maintenance purposes shall be
protectively earthed (if the temporary equipment is required to be protectively
earthed), directly to the same equipotential bonded earthing system as the product.
Warning:
Small Form-factor Pluggable (SFP) modules which provide copper Ethernet connections
typically do not provide any additional safety isolation. Copper Ethernet SFP modules
must only be used in connector positions intended for this type of connection.
24 P54-TM-EN-1.1
P54 Chapter 2 - Safety Information
4.9 UPGRADING/SERVICING
Warning:
Do not insert or withdraw modules, PCBs or expansion boards from the equipment
while energised, as this may result in damage to the equipment. Hazardous live
voltages would also be exposed, endangering personnel.
Caution:
Internal modules and assemblies can be heavy and may have sharp edges. Take care
when inserting or removing modules into or out of the IED.
P54-TM-EN-1.1 25
Chapter 2 - Safety Information P54
Caution:
Before decommissioning, completely isolate the equipment power supplies (both poles
of any dc supply). The auxiliary supply input may have capacitors in parallel, which may
still be charged. To avoid electric shock, discharge the capacitors using the external
terminals before decommissioning.
Caution:
Avoid incineration or disposal to water courses. Dispose of the equipment in a safe,
responsible and environmentally friendly manner, and if applicable, in accordance with
country-specific regulations.
26 P54-TM-EN-1.1
P54 Chapter 2 - Safety Information
6 REGULATORY COMPLIANCE
Compliance with the European Commission Directive on EMC and LVD is demonstrated using a technical file.
P54-TM-EN-1.1 27
Chapter 2 - Safety Information P54
Unless otherwise stated in the Technical Data section of the relevant product documentation, the equipment is
intended for indoor use only. Where the equipment is required for use in an outdoor location, it must be mounted
in a specific cabinet or housing to provide the equipment with the appropriate level of protection from the
expected outdoor environment.
28 P54-TM-EN-1.1
CHAPTER 3
HARDWARE DESIGN
Chapter 3 - Hardware Design P54
30 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
1 CHAPTER OVERVIEW
This chapter provides information about the product's hardware design.
This chapter contains the following sections:
Chapter Overview 31
Hardware Architecture 32
Mechanical Implementation 34
Front Panel 36
Rear Panel 40
Boards and Modules 42
P54-TM-EN-1.1 31
Chapter 3 - Hardware Design P54
2 HARDWARE ARCHITECTURE
The main components comprising devices based on the Px4x platform are as follows:
● The housing, consisting of a front panel and connections at the rear
● The Main processor module consisting of the main CPU (Central Processing Unit), memory and an interface
to the front panel HMI (Human Machine Interface)
● A selection of plug-in boards and modules with presentation at the rear for the power supply,
communication functions, digital I/O, analogue inputs, and time synchronisation connectivity
All boards and modules are connected by a parallel data and address bus, which allows the processor module to
send and receive information to and from the other modules as required. There is also a separate serial data bus
for conveying sampled data from the input module to the CPU. These parallel and serial databuses are shown as a
single interconnection module in the following figure, which shows typical modules and the flow of data between
them.
Keypad
Output relay boards Output relay contacts
Processor module
Front panel HMI
LCD
Opto-input boards Digital inputs
LEDs
I/O
Front port
CTs Power system currents
Memory
Interconnection
V00309
32 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
SoC
Interconnection
CPU
Flash &
Protection
DRAM
Memory
Programmable Logic
Comms between main and Optional Ch1 for current differential input
coprocessor board comms GPS
interface Ch2 for current differential input
Optional coprocessor board
V00310
P54-TM-EN-1.1 33
Chapter 3 - Hardware Design P54
3 MECHANICAL IMPLEMENTATION
All products based on the Px4x platform have common hardware architecture. The hardware is modular and
consists of the following main parts:
● Case and terminal blocks
● Boards and modules
● Front panel
The case comprises the housing metalwork and terminal blocks at the rear. The boards fasten into the terminal
blocks and are connected together by a ribbon cable. This ribbon cable connects to the processor in the front
panel.
The following diagram shows an exploded view of a typical product. The diagram shown does not necessarily
represent exactly the product model described in this manual.
The products are available in panel-mount or standalone versions. All products are nominally 4U high. This equates
to 177.8 mm or 7 inches.
The cases are pre-finished steel with a conductive covering of aluminium and zinc. This provides good grounding
at all joints, providing a low resistance path to earth that is essential for performance in the presence of external
noise.
The case width depends on the product type and its hardware options. There are three different case widths for
the described range of products: 40TE, 60TE and 80TE. The case dimensions and compatibility criteria are as
follows:
Case width (TE) Case width (mm) Case width (inches)
40TE 203.2 8
34 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
P54-TM-EN-1.1 35
Chapter 3 - Hardware Design P54
4 FRONT PANEL
Depending on the exact model and chosen options, the product will be housed in either a 40TE, 60TE or 80TE case.
By way of example, the following diagram shows the front panel of a typical unit. The front panels of the products
based on 40TE, 60TE and 80TE cases have a lot of commonality and differ only in that the 40TE front panel does
not include 10 function keys with their associated user-programmable LEDs.
36 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
The colour LCD display is an active matrix Thin Film Transistor (TFT) Liquid Crystal Display (LCD) that uses
amorphous silicon TFT as a switching device. This module is composed of a Transmissive type TFT-LCD Panel,
driver circuit and back-light unit. The resolution of the 4.0” TFT-LCD is 480x480 pixels and it can display up to
16.7M colours.
4.3 KEYPAD
The keypad consists of the following keys:
4 arrow keys to navigate the menus, changing values within the cell or
to select the next item on the SLD (organised around the Enter key).
P54-TM-EN-1.1 37
Chapter 3 - Hardware Design P54
The port is intended for temporary connection during testing, installation and commissioning. It is not intended to
be used for permanent SCADA communications. This port supports the Courier communication protocol only.
Courier is a proprietary communication protocol to allow communication with a range of protection equipment,
and between the device and the Windows-based support software package.
You can connect the unit to a PC with a USB cable up to 5 m in length.
The inactivity timer for the front port is set to 15 minutes. This controls how long the unit maintains its level of
password access on the front port. If no messages are received on the front port for 15 minutes, any password
access level that has been enabled is cancelled.
Note:
The front USB port does not support automatic extraction of event and disturbance records, although this data can be
accessed manually.
Caution:
When not in use, always close the cover of the USB port to prevent contamination.
38 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
P54-TM-EN-1.1 39
Chapter 3 - Hardware Design P54
5 REAR PANEL
The MiCOM Px40 series uses a modular construction. Most of the internal structure consists of boards and
modules that fit into slots. Some of the boards plug into terminal blocks, which are bolted onto the rear of the unit.
However, some boards such as the communications boards have their own connectors. The rear panel consists of
these terminal blocks plus the rears of the communications boards.
The back panel cut-outs and slot allocations vary. This depends on the product, the type of boards and the
terminal blocks needed to populate the case. The following diagram shows a typical rear view of a case populated
with various boards.
Note:
This diagram is just an example and may not show the exact product described in this manual. It also does not show the full
range of available boards, just a typical arrangement.
Not all slots are the same size. The slot width depends on the type of board or terminal block. For example, HD
(heavy duty) terminal blocks, as required for the analogue inputs, require a wider slot size than MD (medium duty)
terminal blocks. The board positions are not generally interchangeable. Each slot is designed to house a particular
type of board. Again this is model-dependent.
The device may use one or more of the terminal block types shown in the following diagram. The terminal blocks
are fastened to the rear panel with screws.
● Heavy duty (HD) terminal blocks for CT and VT circuits
● Medium duty (MD) terminal blocks for the power supply, opto-inputs, relay outputs and rear
communications port
● MiDOS terminal blocks for CT and VT circuits
● RTD/CLIO terminal block for connection to analogue transducers
40 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
,
Figure 9: Terminal block types
Note:
Not all products use all types of terminal blocks. The product described in this manual may use one or more of the above
types.
P54-TM-EN-1.1 41
Chapter 3 - Hardware Design P54
6.1 PCBS
A PCB typically consists of the components, a front connector for connecting into the main system parallel bus via
a ribbon cable, and an interface to the rear. This rear interface may be:
● Directly presented to the outside world (as is the case for communication boards such as Ethernet Boards)
● Presented to a connector, which in turn connects into a terminal block bolted onto the rear of the case (as is
the case for most of the other board types)
6.2 SUBASSEMBLIES
A sub-assembly consists of two or more boards bolted together with spacers and connected with electrical
connectors. It may also have other special requirements such as being encased in a metal housing for shielding
against electromagnetic radiation.
Boards are designated by a part number beginning with ZN, whereas pre-assembled sub-assemblies are
designated with a part number beginning with GN. Sub-assemblies, which are put together at the production
stage, do not have a separate part number.
42 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
The main processor board performs all calculations and controls the operation of all other modules in the IED,
including the data communication and user interfaces. This is the only board that does not fit into one of the slots.
It resides in the front panel and connects to the rest of the system using an internal ribbon cable.
The LCD and LEDs are mounted on the processor board along with the front panel communication ports.
The memory on the main processor board is split into two categories: volatile and non-volatile. The volatile
memory is DRAM, used by the processor to run the software and store data during calculations. The non-volatile
memory is Flash memory and is used to store Product Firmware, text and configuration data including the present
setting values, disturbance records, events, fault and maintenance record data.
There are two board types available depending on the size of the case:
● For models in 40TE cases
● For models in 60TE cases and larger
P54-TM-EN-1.1 43
Chapter 3 - Hardware Design P54
The power supply board provides power to the unit. One of three different configurations of the power supply
board can be fitted to the unit. This is specified at the time of order and depends on the magnitude of the supply
voltage that will be connected to it.
There are three board types, which support the following voltage ranges:
● 24/54 V DC
● 48/125 V DC or 40-100V AC
● 110/250 V DC or 100-240V AC
The power supply board connector plugs into a medium duty terminal block. This terminal block is always
positioned on the right hand side of the unit looking from the rear.
The power supply board is usually assembled together with a relay output board to form a complete subassembly,
as shown in the following diagram.
44 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
The power supply outputs are used to provide isolated power supply rails to the various modules within the unit.
Three voltage levels are used by the unit’s modules:
● 5.1 V for all of the digital circuits
● +/- 16 V for the analogue electronics such as on the input board
● 22 V for driving the output relay coils.
All power supply voltages, including the 0 V earth line, are distributed around the unit by the 64-way ribbon cable.
The power supply board incorporates inrush current limiting. This limits the peak inrush current to approximately
10 A.
Power is applied to pins 1 and 2 of the terminal block, where pin 1 is negative and pin 2 is positive. The pin
numbers are clearly marked on the terminal block as shown in the following diagram.
P54-TM-EN-1.1 45
Chapter 3 - Hardware Design P54
6.4.1 WATCHDOG
The Watchdog contacts are also hosted on the power supply board. The Watchdog facility provides two output
relay contacts, one normally open and one normally closed. These are used to indicate the health of the device
and are driven by the main processor board, which continually monitors the hardware and software when the
device is in service.
46 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
P54-TM-EN-1.1 47
Chapter 3 - Hardware Design P54
An additional serial port with D-type presentation is available as an optional board, if required.
The input module consists of the main input board coupled together with an instrument transformer board. The
instrument transformer board contains the voltage and current transformers, which isolate and scale the
analogue input signals delivered by the system transformers. The input board contains the A/D conversion and
digital processing circuitry, as well as eight digital isolated inputs (opto-inputs).
The boards are connected together physically and electrically. The module is encased in a metal housing for
shielding against electromagnetic interference.
48 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
Noise Noise
filter filter
Parallel Bus
Buffer
Transformer
board
VT
or
CT
VT
or
CT
V00239
A/D Conversion
The differential analogue inputs from the CT and VT transformers are presented to the main input board as shown.
Each differential input is first converted to a single input quantity referenced to the input board’s earth potential.
The analogue inputs are sampled and converted to digital, then filtered to remove unwanted properties. The
samples are then passed through a serial interface module which outputs data on the serial sample data bus.
The calibration coefficients are stored in non-volatile memory. These are used by the processor board to correct
for any amplitude or phase errors introduced by the transformers and analogue circuitry.
Opto-isolated inputs
The other function of the input board is to read in the state of the digital inputs. As with the analogue inputs, the
digital inputs must be electrically isolated from the power system. This is achieved by means of the 8 on-board
optical isolators for connection of up to 8 digital signals. The digital signals are passed through an optional noise
filter before being buffered and presented to the unit’s processing boards in the form of a parallel data bus.
This selectable filtering allows the use of a pre-set filter of ½ cycle which renders the input immune to induced
power-system noise on the wiring. Although this method is secure it can be slow, particularly for inter-tripping. This
can be improved by switching off the ½ cycle filter, in which case one of the following methods to reduce ac noise
should be considered.
● Use double pole switching on the input
● Use screened twisted cable on the input circuit
P54-TM-EN-1.1 49
Chapter 3 - Hardware Design P54
The opto-isolated logic inputs can be configured for the nominal battery voltage of the circuit for which they are a
part, allowing different voltages for different circuits such as signalling and tripping.
Note:
The opto-input circuitry can be provided without the A/D circuitry as a separate board, which can provide supplementary
opto-inputs.
The transformer board hosts the current and voltage transformers. These are used to step down the currents and
voltages originating from the power systems' current and voltage transformers to levels that can be used by the
devices' electronic circuitry. In addition to this, the on-board CT and VT transformers provide electrical isolation
between the unit and the power system.
The transformer board is connected physically and electrically to the input board to form a complete input module.
For terminal connections, please refer to the wiring diagrams.
50 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
The input board is used to convert the analogue signals delivered by the current and voltage transformers into
digital quantities used by the IED. This input board also has on-board opto-input circuitry, providing eight optically-
isolated digital inputs and associated noise filtering and buffering. These opto-inputs are presented to the user by
means of a MD terminal block, which sits adjacent to the analogue inputs HD terminal block.
The input board is connected physically and electrically to the transformer board to form a complete input module.
The terminal numbers of the opto-inputs are as follows:
Terminal Number Opto-input
Terminal 1 Opto 1 -ve
Terminal 2 Opto 1 +ve
Terminal 3 Opto 2 -ve
Terminal 4 Opto 2 +ve
Terminal 5 Opto 3 -ve
Terminal 6 Opto 3 +ve
Terminal 7 Opto 4 -ve
Terminal 8 Opto 4 +ve
Terminal 9 Opto 5 -ve
Terminal 10 Opto 5 +ve
Terminal 11 Opto 6 -ve
Terminal 12 Opto 6 +ve
Terminal 13 Opto 7 –ve
Terminal 14 Opto 7 +ve
Terminal 15 Opto 8 –ve
Terminal 16 Opto 8 +ve
P54-TM-EN-1.1 51
Chapter 3 - Hardware Design P54
This output relay board has 8 relays with 6 Normally Open contacts and 2 Changeover contacts.
The output relay board is provided together with the power supply board as a complete assembly, or
independently for the purposes of relay output expansion.
There are two cut-out locations in the board. These can be removed to allow power supply components to
protrude when coupling the output relay board to the power supply board. If the output relay board is to be used
independently, these cut-out locations remain intact.
The terminal numbers are as follows:
Terminal Number Output Relay
Terminal 1 Relay 1 NO
Terminal 2 Relay 1 NO
Terminal 3 Relay 2 NO
Terminal 4 Relay 2 NO
Terminal 5 Relay 3 NO
Terminal 6 Relay 3 NO
Terminal 7 Relay 4 NO
Terminal 8 Relay 4 NO
Terminal 9 Relay 5 NO
Terminal 10 Relay 5 NO
52 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
The IRIG-B board can be fitted to provide an accurate timing reference for the device. The IRIG-B signal is
connected to the board via a BNC connector. The timing information is used to synchronise the IED's internal real-
time clock to an accuracy of 1 ms. The internal clock is then used for time tagging events, fault, maintenance and
disturbance records.
IRIG-B interface is available in modulated or demodulated formats.
The IRIG-B facility is provided in combination with other functionality on a number of additional boards, such as:
● Fibre board with IRIG-B
● Second rear communications board with IRIG-B
● Ethernet board with IRIG-B
● Redundant Ethernet board with IRIG-B
There are three types of each of these boards; one type which accepts a modulated IRIG-B input, one type which
accepts a demodulated IRIG-B input and one type which accepts a universal IRIG-B input.
P54-TM-EN-1.1 53
Chapter 3 - Hardware Design P54
This board provides an interface for communicating with a master station. This communication link can use all
compatible protocols (Courier, IEC 60870-5-103, MODBUS and DNP 3.0). It is a fibre-optic alternative to the metallic
RS485 port presented on the power supply terminal block. The metallic and fibre optic ports are mutually exclusive.
The fibre optic port uses BFOC 2.5 ST connectors.
The board comes in two varieties; one with an IRIG-B input and one without:
54 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
The optional communications board containing the secondary communication ports provide two serial interfaces
presented on 9 pin D-type connectors. These interfaces are known as SK4 and SK5. Both connectors are female
connectors, but are configured as DTE ports. This means pin 2 is used to transmit information and pin 3 to receive.
SK4 can be used with RS232, RS485 and K-bus. SK5 can only be used with RS232 and is used for electrical
teleprotection. The optional rear communications board and IRIG-B board are mutually exclusive since they use
the same hardware slot. However, the board comes in two varieties; one with an IRIG-B input and one without.
P54-TM-EN-1.1 55
Chapter 3 - Hardware Design P54
This board provides dual redundant Ethernet together with an IRIG-B interface for timing.
Different board variants are available, depending on the redundancy protocol and the type of IRIG-B signal
(unmodulated and modulated). The available redundancy protocols are:
● RSTP (Rapid Spanning Tree Protocol)
● PRP (Parallel Redundancy Protocol)
● HSR (High-availability Seamless Redundancy)
● Failover
IRIG-B Connector
● Centre connection: Signal
● Outer connection: Earth
56 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
LEDs
LED Function On Off Flashing
Green Link Link ok Link broken
Yellow Activity Running PRP, RSTP traffic
RJ45 connector
Pin Signal name Signal definition
1 TXP Transmit (positive)
2 TXN Transmit (negative)
3 RXP Receive (positive)
4 - Not used
5 - Not used
6 RXN Receive (negative)
7 - Not used
8 - Not used
P54-TM-EN-1.1 57
Chapter 3 - Hardware Design P54
L1
A1
IEC 61850-9-2LE
RXA
!
TXA
SK7
L2
A2
IEC 61850-9-2LE
RXB
!
TXB
E00107
This board provides dual redundant Ethernet for IEC 61850-9-2LE process bus. The PRP and Failover redundancy
protocols are supported.
SK7 Connector
This is a service port for commissioning and testing only. Do not use this for permanent connections.
LEDs
LED Function On Off Flashing
Green Link Link ok Link broken
Yellow Activity Traffic
Note:
The 9-2LE interface fibre port does not support auto negotiation. Ensure the Ethernet port of the device connected to the 9-2
LE interface fibre port is set to 100Mbps full duplex.
58 P54-TM-EN-1.1
P54 Chapter 3 - Hardware Design
Note:
The above figure shows a coprocessor complete with GPS input and 2 fibre-optic serial data interfaces, and is not necessarily
representative of the product and model described in this manual. These interfaces will not be present on boards that do not
require them.
Where applicable, a second processor board is used to process the special algorithms associated with the device.
This second processor board provides DRAM for use with both program and data memory storage. This memory
can be accessed by the main processor board via the parallel bus. The Co-Processor Firmware image is stored
locally in Flash Memory and the firmware is then transferred directly from the flash memory to DRAM on the Co-
Pro at power up. Further communication between the two processor boards is achieved via interrupts and the
shared DRAM. The serial bus carrying the sample data is also connected to the co-processor board, using the
processor’s built-in serial port, as on the main processor board. There are several different variants of this board,
which can be chosen depending on the exact device and model. The variants are:
There are several different variants of this board, which can be chosen depending on the exact device and model.
The variants are:
● Coprocessor board with current differential inputs and GPS input
● Coprocessor board with current differential inputs only
● Coprocessor board with GPS input only
P54-TM-EN-1.1 59
Chapter 3 - Hardware Design P54
labelled Ch1 and Ch2. These serial data links are used to transfer information between two or three IEDs for
current differential applications.
Note:
The 1 pps signal is always supplied by a GPS receiver (such as a RT430).
Note:
This signal is used to control the sampling process, and timing calculations and is not used for time stamping or real time
synchronisation.
60 P54-TM-EN-1.1
CHAPTER 4
SOFTWARE DESIGN
Chapter 4 - Software Design P54
62 P54-TM-EN-1.1
P54 Chapter 4 - Software Design
1 CHAPTER OVERVIEW
This chapter describes the software design of the IED.
This chapter contains the following sections:
Chapter Overview 63
Sofware Design Overview 64
System Level Software 65
Platform Software 68
Protection and Control Functions 69
P54-TM-EN-1.1 63
Chapter 4 - Software Design P54
These elements are not distinguishable to the user, and the distinction is made purely for the purposes of
explanation. The following figure shows the software architecture.
Supervisor task
Records
and control
Protection
settings
Platform Software Layer
Event, fault,
Remote
disturbance,
Settings database communications
maintenance record
Sampling function interfaces
logging
V00307
The software, which executes on the main processor, can be divided into a number of functions as illustrated
above. Each function is further broken down into a number of separate tasks. These tasks are then run according
to a scheduler. They are run at either a fixed rate or they are event driven. The tasks communicate with each other
as and when required.
64 P54-TM-EN-1.1
P54 Chapter 4 - Software Design
P54-TM-EN-1.1 65
Chapter 4 - Software Design P54
At the conclusion of the initialization software the supervisor task begins the process of starting the platform
software. Coprocessor board checks are also made as follows:
● A check is made for the presence of the coprocessor board
If any of these checks produces an error, the coprocessor board is left out of service. The other protection
functions provided by the main processor board are left in service.
At the successful conclusion of all of these tests the unit is entered into service and the application software is
started up.
66 P54-TM-EN-1.1
P54 Chapter 4 - Software Design
A restart should clear most problems that may occur. If, however, the diagnostic self-check detects the same
problem that caused the IED to restart, it is clear that the restart has not cleared the problem, and the device takes
itself permanently out of service. This is indicated by the ‘’health-state’ LED on the front of the device, which
switches OFF, and the watchdog contact which switches ON.
P54-TM-EN-1.1 67
Chapter 4 - Software Design P54
4 PLATFORM SOFTWARE
The platform software has three main functions:
● To control the logging of records generated by the protection software, including alarms, events, faults, and
maintenance records
● To store and maintain a database of all of the settings in non-volatile memory
● To provide the internal interface between the settings database and the user interfaces, using the front
panel interface and the front and rear communication ports
The logs are maintained such that the oldest record is overwritten with the newest record. The logging function
can be initiated from the protection software. The platform software is responsible for logging a maintenance
record in the event of an IED failure. This includes errors that have been detected by the platform software itself or
errors that are detected by either the system services or the protection software function. See the Monitoring and
Control chapter for further details on record logging.
4.3 INTERFACES
The settings and measurements database must be accessible from all of the interfaces to allow read and modify
operations. The platform software presents the data in the appropriate format for each of the interfaces (LCD
display, keypad and all the communications interfaces).
68 P54-TM-EN-1.1
P54 Chapter 4 - Software Design
P54-TM-EN-1.1 69
Chapter 4 - Software Design P54
board and converts these to 8 samples per cycle based on the nominal frequency. The coprocessor calculates the
Fourier transform of the fixed rate samples after every sample, using a one-cycle window. This generates current
measurements eight times per cycle which are used for the differential protection algorithm. These are transmitted
to the remote device(s) using the HDLC (high-level data link control) communication protocol.
The coprocessor is also responsible for managing intertripping commands via the communication link, as well as
re-configuration instigated from the remote device(s).
Data exchange between the coprocessor board and the main processor board is achieved through the use of
shared memory on the coprocessor board. When the main processor accesses this memory, the coprocessor is
temporarily halted. After the coprocessor code has been copied onto the board at initialization, the main traffic
between the two boards consists of setting change information, commands from the main processor, differential
protection measurements and output data.
Filter Response
2.5
2
Full
1.5
Gain Half
1
Quarter
0.5
0
0 3 6 9 12 15 18 21
Harmonic
E00308
70 P54-TM-EN-1.1
P54 Chapter 4 - Software Design
The Fourier function acts as a filter, with zero gain at DC and unity gain at the fundamental, but with good
harmonic rejection for all harmonic frequencies up to the nyquist frequency. Frequencies beyond this nyquist
frequency are known as alias frequencies, which are introduced when the sampling frequency becomes less than
twice the frequency component being sampled. However, the Alias frequencies are significantly attenuated by an
anti-aliasing filter (low pass filter), which acts on the analog signals before they are sampled. The ideal cut-off point
of an anti-aliasing low pass filter would be set at:
(samples per cycle) ´ (fundamental frequency)/2
At 48samples per cycle, this would be nominally 1200 Hz for a 50 Hz system, or 1440 Hz for a 60 Hz system.
The following figure shows the nominal frequency response of the anti-alias filter and the Fourier filter for a 48-
sample single cycle fourier algorithm acting on the fundamental component:
1
Ideal anti-alias filter response
0.8
Fourier Response
0.6 Real anti-alias filter without anti-alias filter
response
0.4
Fourier Response
0.2 with anti-alias filter
P54-TM-EN-1.1 71
Chapter 4 - Software Design P54
an event is available to be processed and writes the event data to a fast buffer controlled by the supervisor task.
Up to 5000 time-tagged event records can be stored.
When the supervisor task receives an event record, it instructs the platform software to create the appropriate log
in non-volatile memory (DRAM). The operation of the record logging to Flash is slower than the supervisor buffer.
This means that the protection software is not delayed waiting for the records to be logged by the platform
software. However, in the rare case when a large number of records to be logged are created in a short period of
time, it is possible that some will be lost, if the supervisor buffer is full before the platform software is able to create
a new log in Flash memory. If this occurs then an event is logged to indicate this loss of information.
Maintenance records are created in a similar manner, with the supervisor task instructing the platform software to
log a record when it receives a maintenance record message. However, it is possible that a maintenance record
may be triggered by a fatal error in the relay in which case it may not be possible to successfully store a
maintenance record, depending on the nature of the problem.
For more information, see the Monitoring and Control chapter.
72 P54-TM-EN-1.1
CHAPTER 5
CONFIGURATION
Chapter 5 - Configuration P54
74 P54-TM-EN-1.1
P54 Chapter 5 - Configuration
1 CHAPTER OVERVIEW
Each product has different configuration parameters according to the functions it has been designed to perform.
There is, however, a common methodology used across the entire product series to set these parameters.
Some of the communications setup cannot be carried out using the settings applications software, it can only be
carried out using the HMI. This chapter includes concise instructions on how to configure the device, as well as a
description of the common methodology used to configure the device in general.
This chapter contains the following sections:
Chapter Overview 75
Settings Application Software 76
Using the HMI Panel 77
P54-TM-EN-1.1 75
Chapter 5 - Configuration P54
76 P54-TM-EN-1.1
P54 Chapter 5 - Configuration
The keypad provides full access to the device functionality using a range of menu options. The information is
displayed on the screen.
Keys Description Function
Menu context keys situated directly below the graphical HMI are
Menu context keys
used to navigate between pages.
Function keys (not all models) For executing user programmable functions
P54-TM-EN-1.1 77
Chapter 5 - Configuration P54
78 P54-TM-EN-1.1
P54 Chapter 5 - Configuration
The graphical display screen consists of three main areas, which can be selected using the navigation keypad.
1. The top banner displays information left to right and includes the menu label for the current display, the
user access level, the number of active alarms and the time.
2. The content area displays information related to the chosen area of navigation. For example, settings,
measurements or SLD.
3. The bottom banner displays labels for the two Menu context keys, which are used for navigating between
the menus.
P54-TM-EN-1.1 79
Chapter 5 - Configuration P54
"Ack/Clear" and "reset indication" commands are available to users with ENGINEER or OPERATOR or
INSTALLER roles.
To return to the launch view from the alarm view press the Cancel key.
80 P54-TM-EN-1.1
P54 Chapter 5 - Configuration
LED is green and the REMOTE mode is selected. The L/R Key Status DDB status is stored in non-volatile memory, so
that it’s status is recovered after an IED power cycle.
● In the SLD menu, navigate to the item of plant which you require to control using the navigation keypad
● The selected plant is highlighted with an orange border
● Use the Enter key to select the item
● Press the Open or Close key to operate
Note:
Sometimes the term "Setting" is used generically to describe all of the three types.
P54-TM-EN-1.1 81
Chapter 5 - Configuration P54
SYSTEM DATA (Col 00) VIEW RECORDS (Col 01) MEASUREMENTS 1 (Col 02) …
Language (Row 01) "Select Event [0...n]" (Row 01) IA Magnitude (Row 01) …
Password (Row 02) Menu Cell Ref (Row 02) IA Phase Angle (Row 02) …
Sys Fn Links (Row 03) Time & Date (Row 03) IB Magnitude (Row 03) …
… … … …
It is convenient to specify all the settings in a single column, detailing the complete Courier address for each
setting. The above table may therefore be represented as follows:
Setting Column Row Description
SYSTEM DATA 00 00 First Column definition
Language (Row 01) 00 01 First setting within first column
Password (Row 02) 00 02 Second setting within first column
Sys Fn Links (Row 03) 00 03 Third setting within first column
… … …
VIEW RECORDS 01 00 Second Column definition
Select Event [0...n] 01 01 First setting within second column
Menu Cell Ref 01 02 Second setting within second column
Time & Date 01 03 Third setting within second column
… … …
MEASUREMENTS 1 02 00 Third Column definition
IA Magnitude 02 01 First setting within third column
IA Phase Angle 02 02 Second setting within third column
IB Magnitude 02 03 Third setting within third column
… … …
The first three column headers are common throughout much of the product ranges. However, the rows within
each of these column headers may differ according to the product type. Many of the column headers are the
same for all products within the series. However, there is no guarantee that the addresses will be the same for a
particular column header. Therefore, you should always refer to the product settings documentation and not make
any assumptions.
82 P54-TM-EN-1.1
P54 Chapter 5 - Configuration
3. To change the value of a setting, highlight the relevant cell in the menu, then press the Enter key to change
the cell value. A settings screen will appear next to the cell. If the currently logged in user does not have the
level of access required for changing the setting, a pop-up dialog box will inform the user and prevent the
settings from being changed. Acknowledge the pop-up message, then navigate to the ‘user accounts’
section to the top of the screen (top banner) to enter the password for the required access level to change
settings.
4. To change the value on the settings screen, use the cursor keys to change the desired settings. When more
settings are available than can fit on the screen, a scroll bar on the right-hand side appears. In some cases,
a virtual keyboard is provided to enter complex characters. The IED maintains dependencies between
various settings, and only the applicable settings are displayed for changing.
5. Press the Enter key to confirm the new setting value or the Clear key or the on-screen ‘x’ to discard it.
6. To confirm the new settings, press the Enter key. Navigate away from the currently active group settings or
press the Home key. A Settings update confirmation dialogue box will appear that requires choosing of one
of the following options:
a. Save - accept all settings including the recently changed settings
b. Abort – discard recent changes and keep existing settings
c. Stay on page – return to the active settings page without saving recent changes
7. To return to the top of the menu, hold down the Up cursor key for a second or so, or press the Clear key
once. It is possible to move across columns from anywhere in the menu by using the Menu context keys at
the bottom of the display.
8. To return to the default display, press the Home key at any time.
9. Press the Enter key to accept the new settings or press the Clear key to discard the new settings.
10. The Date and time can be adjusted by navigating to the top banner and selecting the displayed time. Press
the Enter key to adjust the date and time using the calendar/clock widget that pops up.
Note:
For the protection group and disturbance recorder settings, the changes are not saved unless confirmed using the Settings
update confirmation prompt.
Note:
All other Control and support settings (such as Communications and Control inputs), however, are updated immediately after
they are entered on the front HMI without the need to confirm using the Settings update confirmation prompt.
P54-TM-EN-1.1 83
Chapter 5 - Configuration P54
The first cell down in the FUNCTION KEYS column is the Fn Key Status cell. This contains a binary string, which
represents the function key commands. Their status can be read from the binary string.
The next cell down (Fn Key 1) allows you to activate or disable the first function key (1). The Lock setting allows a
function key to be locked. This allows function keys that are set to Toggled mode and their DDB signal active
‘high’, to be locked in their active state, preventing any further key presses from deactivating the associated
function. Locking a function key that is set to the Normal mode causes the associated DDB signals to be
permanently off. This safety feature prevents any inadvertent function key presses from activating or deactivating
critical functions.
The next cell down (Fn Key 1 Mode) allows you to set the function key to Normal or Toggled. In the Toggle mode
the function key DDB signal output stays in the set state until a reset command is given, by activating the function
key on the next key press. In the Normal mode, the function key DDB signal stays energised for as long as the
function key is pressed then resets automatically. If required, a minimum pulse width can be programmed by
adding a minimum pulse timer to the function key DDB output signal.
The next cell down (Fn Key 1 Label) allows you to change the label assigned to the function. The default label is
Function key 1 in this case. To change the label you need to press the enter key and then change the text on
the bottom line, character by character. This text is displayed when a function key is accessed in the function key
menu, or it can be displayed in the PSL.
Subsequent cells allow you to carry out the same procedure as above for the other function keys.
The status of the function keys is stored in non-volatile memory. If the auxiliary supply is interrupted, the status of
all the function keys is restored. The IED only recognises a single function key press at a time and a minimum key
press duration of approximately 200 ms is required before the key press is recognised. This feature avoids
accidental double presses.
The function keys needs operator permissions to operate. If operator permissions are not held by the present user
an information dialogue is raised to inform the operation has failed.
84 P54-TM-EN-1.1
CHAPTER 6
86 P54-TM-EN-1.1
P54 Chapter 6 - Sampled Analogue Values Operation
1 CHAPTER OVERVIEW
This chapter contains the following sections:
Chapter Overview 87
Introduction To Sample Analogue Values 88
Data Resampling 89
Sampled Analogue Values Alignment 90
P54-TM-EN-1.1 87
Chapter 6 - Sampled Analogue Values Operation P54
Conventional IED
IA Fast
Direct
IB protection
CT Inputs comparison
IC algorithms
IN A/D Sample d
Scaling Ana logue
VA Conversion
Valu es
VB Standard
VT Inputs Filtering and
VC protection
Processing
VN algorithms
SAV IED
IA
IB
IC
IN Analogue Sampled Analogue Values IEC 61850
Merging Unit (in IEC61850 Ethernet frames) SAV Processing
VA
Interface
VB
VC
VN
Figure 36: Comparison of Conventional IED and Sampled Analogue Values IED
88 P54-TM-EN-1.1
P54 Chapter 6 - Sampled Analogue Values Operation
3 DATA RESAMPLING
An IEC 61850-9-2LE SAV interface receives 80 Sampled Analogue Values per cycle from the Process Bus. This is the
same for both 50 and 60 Hz. The SAV interface then resamples these Sampled Analogue Values to make the data
appear the same to the IED as analogue signals would do on its normal inputs from CTs and VTs. The resampling
frequency depends on the device.
The IEC 61850-9-2LE interface also tracks the supply frequency. This is because the Sample Analogue Values from
the Process Bus are fixed at 4000 samples/sec for 50 Hz and 4800 samples/sec at 60 Hz.
SAV IED
IA
IB
IC
Analogue Sampled Analogue Values IEC 61850
IN Resampling
Merging Unit (80 samples per cycle) SAV CPU
VA
Interface
VB
VC
VN
Process Bus
V03703
P54-TM-EN-1.1 89
Chapter 6 - Sampled Analogue Values Operation P54
4.1 CHANNEL MAPPINGS FOR SAV TEST, SAV QUESTIONABLE, SAV INVALID
These signals correspond to the analogue channels in a conventional MiCOM IED. The channel name appears on
the IED display against each bit.
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
VA VB VC VSC1 IA1 IB1 IC1 IM INSEN
90 P54-TM-EN-1.1
P54 Chapter 6 - Sampled Analogue Values Operation
to Questionable, the protection function can either be inhibited or not, depending on the chosen options in the
Trus Ques Data setting. The options are:
● Bit 0:Out of Range
● Bit 1:Bad Reference
● Bit 2:Oscillatory
● Bit 3:Old Data
● Bit 4:Inconsistent
● Bit 5:Inaccurate
The protection function will be trusted and NOT inhibited for questionable data for the items above which have
been set.
The protection function returns to the Normal state when the quality flags for all the necessary Sampled Analogue
Value inputs are Good. The quality flags can change with each sample, therefore there is a one-cycle transition
delay between the Normal and Inhibit states for each protection function.
P54-TM-EN-1.1 91
Chapter 6 - Sampled Analogue Values Operation P54
4.4 VT SWITCHING
This function is used in the P44, P54 and P84 IEDs which have an IEC 61850-9-2LE interface. It allows the user to
switch the three-phase voltage input between two independent Sampled Analogue Value frames while the IED is
in service. This may correspond to two separate voltage transformers in the primary system. The VT Switch
function also allows the single-phase check synchronising voltages to be selected from three independent
Sampled Analogue Value frames.
The VT switching function is disabled by default. To enabled it, in the IED menu IEC 61850-9-2LE, select VT Switch
Mode to Enabled.
The change of VT input is accepted only if the DDB status change is effective for a minimum of 20 ms. The selected
three-phase voltage is only displayed when VT Switch Mode is enabled.
92 P54-TM-EN-1.1
P54 Chapter 6 - Sampled Analogue Values Operation
DDB DDB
Vsc1 Select x1 Vsc1 Select 1x Vsc1 Selection
0 0 Vcs1
0 1 Vcs2
1 0 Vcs3
1 1 Unused
The selection of the voltage source for Vsc2 is controlled by the combined status of two DDBs, Vsc2 Select x1 and
Vsc2 Select 1x as shown in the following table.
DDB DDB
Vsc2 Select x1 Vsc2 Select 1x Vsc2 Selection
0 0 Vcs2
0 1 Vcs3
1 0 Vcs1
1 1 Unused
The selected single-phase voltages are only displayed when VT Switch Mode is enabled.
P54-TM-EN-1.1 93
Chapter 6 - Sampled Analogue Values Operation P54
94 P54-TM-EN-1.1
CHAPTER 7
96 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
1 CHAPTER OVERVIEW
This product provides biased, phase-segregated, numerical Current Differential protection.
This chapter introduces the principles and theory behind Current Differential protection and describes how they
are implemented in this product. Guidance for applying this protection is also provided.
The current differential protection is enabled by default, but it can be disabled if you don’t want to use it. The
current differential protection needs digital communications links to exchange the values of current between the
terminals in the scheme.
This chapter contains the following sections:
Chapter Overview 97
Current Differential Protection Principle 98
Synchronisation of Current Signals 100
Phase Current Differential Protection 103
Neutral Current Differential Protection 106
Three-Terminal Schemes 108
Transient Bias 111
Capacitive Charging Current Compensation 112
CT Compensation 113
Feeders with In-Zone Transformers 114
Logic for Feeders with In-Zone Transformers 121
Second Harmonic Blocking Logic 122
Fifth Harmonic Blocking Logic 123
Current Differential Intertripping 124
Mesh Corner and Breaker-And-A-Half Schemes 125
Stub Bus Differential Protection 127
Differential IED compatibility with previous versions 129
Application Notes 130
P54-TM-EN-1.1 97
Chapter 7 - Current Differential Protection P54
98 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
applications use three current values (one from each terminal) for the evaluation of the Bias and Differential
currents.
Line differential protection requires the comparison of power system quantities taken at the different line
terminals. For a meaningful comparison, synchronisation of the current signals is needed so that they are related
to a common time reference. Different methods are used to achieve current signal synchronisation – some
requiring external time reference signals, and some using internal timing signals.
P54-TM-EN-1.1 99
Chapter 7 - Current Differential Protection P54
Protected line
X X
A B
Digital communications link
End A End B
Curren
tA1 t vecto tB1
rs
tp1 tA1
tA2
tB2
tB*
tA3
td
tB3* tB3
tA4 rs
t vecto
tp2 Curren tB4
tA5 1 td
tA* tB3 tA tB5
The device at End A samples its current signals at times tA1, tA2, etc. The device at End B samples its current
signals at time tB1, tB2, etc. The sampling of the signals at the two ends are not synchronised, but both operate in
the same way. The filtering and processing of the current inputs produces current vectors together with timing
information, which are sent between devices as shown in the figure.
100 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
At time tA1, End A sends a data message to End B. The message contains a time tag, tA1, plus other timing,
control, and status information as well as the calculated current values. The message arrives at End B after a
channel after a propogation delay time tp1. End B registers the arrival time of the message as tB*.
Since the devices at both terminals operate in the same way, End B also sends messages to End A. In the figure,
End B sends a message at tB3. The message contains the time tag tB3. It also returns the last received time tag
from End A (tA1) and the delay time, td, between the time of the the message was received, tB*, and the sampling
time, tB3, where td = (tB3 - tB*).
The message arrives at End A after a channel propagation delay time, tp2. The arrival time is registered by End A
as tA*. From the returned time tag, tA1, End A can measure an elapsed time as (tA* - tA1). This equals the sum of
the propagation delay times, tp1, and tp2, as well as the time between End B receiving the message and returning
it. So:
(tA* - tA1) = (td + tp1 + tp2)
The device assumes that the time to communicate data between two terminals is the same in each direction, and
on this basis tp1 and tp2 can be calculated as:
tp1 = tp2 = ½(tA* - tA1 - td)
The propagation delay time is measured for each received message. This is used to monitor changes on the
communication link and to manage the response of the protection. When the propagation delay time has been
calculated, the sampling instant of the received data from End B (tB3*) can also be calculated. As shown in the
figure, the sampling time tB3* is measured by End A as:
tB3* = (tA* - tp2)
In the figure, tB3* is between tA3 and tA4. To calculate the differential and bias currents, the values at each
terminal must correspond to the same point in time. So the values received at tB3* must be aligned with values
taken at sampling instants tA3 and tA4. This is achieved by rotating the received current vector by an angle
corresponding to the time difference between tB3* and tA3 (and tA4).
After this time-alignment process, the respective differential and bias currents can be calculated.
P54-TM-EN-1.1 101
Chapter 7 - Current Differential Protection P54
ta
tA1 tB1
tA2 tp 1
tB2
tB*
tc
tA3 tB3
tB3* td
tA4 tB4
tp 2
tA5
tB5
tA*
tA6 tB6
Relay A Relay B
E02607
The GPS synchronised values at terminal A (tA1, etc.) can be individually compared with those at terminal B (tB1,
etc.) to derive the bias and differential currents. The propagation delay times are not required for the derivation of
the bias and differential currents, but they can be calculated individually as tp1, and tp2, and they are stored for
potential use if GPS synchronisation fails.
102 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
The differential and bias currents are compared against a tripping criterion which is defined by a dual-slope
characteristic as shown below. The figure shows the tripping criteria for protection of a three-terminal feeder, but
the principle is similar for a two-terminal feeder.
I diff
V02605
P54-TM-EN-1.1 103
Chapter 7 - Current Differential Protection P54
104 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
Start Isef
Disabled
&
Delta Isef
1
Disabled V02638
P54-TM-EN-1.1 105
Chapter 7 - Current Differential Protection P54
The characteristic is determined by three protection settings. You can change the settings, but we strongly
recommend retaining the default values, which are as follows:
● In Diff Is1 = 0.1 pu
● In Diff Is2 = 2.0 pu
● In Diff k1 = 10%
This provides stability for small CT mismatches, while ensuring good sensitivity to resistive faults under heavy load
conditions.
106 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
N Diff
Operate
In Diff k1
In Diff Is1
Restrain
In Diff Is2
I Bias
V02610
Figure 42: Neutral current differential characteristic
Note:
Ibias is calculated from the phase differential currents.
P54-TM-EN-1.1 107
Chapter 7 - Current Differential Protection P54
6 THREE-TERMINAL SCHEMES
Products that have two protection communications channels fitted can be applied to the protection of three-
terminal applications.
By appropriate model selection, current differential protection can be provided for two-terminal or three-terminal
feeders. A naming convention is used featuring the terms ‘Local’ and ‘Remote’. ‘Local’ is applied to the device being
described. ‘Remote’ refers to a connected device. For a two-terminal application, the remote device is referenced
in the MEASUREMENTS 3 column as ‘Remote 1’. When a third terminal is included it is referenced as ‘Remote 2’.
Sometimes what is expected to be a three-terminal scheme may need to operate as a two-terminal scheme (this
may be due to a line end being taken out for maintenance, or it may be that the line end has still to be added). In
such a case, it is possible to reconfigure the protection devices to perform as a two-terminal application. The
device that has been configured-out can be removed from the system without any alarms being raised. This
reconfiguration can be done from any of the terminals in the protection scheme, but it is generally performed at
the terminal being configured out, as it requires an interlock that is associated with the isolator at that terminal. If
you intend to use this feature you might need to create and use customised PSL files and the product must be set
up for three-terminal operation.
To reconfigure a scheme from three-terminal to two-terminal you use the Re-Configuration setting in the PROT
COMMS/IM64 column. Before you can change a configuration, two interlocking criteria need to be satisfied: The
Inhibit C Diff and Recon Interlock DDB signals (455, 456 respectively) need to be asserted. The Inhibit C Diff DDB
signal is mapped by default to one of the opto-isolated inputs and is used to ensure stability during the
reconfiguration. According to the particular model being used, the Recon Interlock DDB signal might not be
mapped by default. To reconfigure a scheme from three-terminal to two-terminal, the DDB signal must be mapped
to an opto-isolated input using the PSL. This signal is intended to be connected to reflect the state of the
switchgear at the terminal that is being taken out of service (The rationale being that if the line is open, current
does not flow and so the scheme can be protected as a two-terminal line).
Note:
The line end to be ‘configured out’ must be open before issuing a reconfiguration command. If this is not done, any current
flowing in or out of the ‘configured out’ end will be seen as fault current and when the Inhibit C Diff’input is removed, it might
cause the other devices to operate.
Reconfiguration is only permitted if all three devices are energised and communicating correctly with each other.
Four values are available for the Re-Configuration setting:
● Three Ended (stay as three-ended)
● Two Ended(L&R1) (Local + Remote 1)
● Two Ended(L&R2) (Local + Remote 2)
● Two Ended(R1&R2) (Remote 1 + Remote 2)
If the reconfigured scheme incorporates the local device, the trip outputs of the differential protection will continue
to be inhibited until the Inhibit C Diff signal at the local device is cleared. If the new reconfiguration scheme only
incorporates the remote devices, the differential protection at the remote devices are not inhibited because they
will ignore all commands from the local device unless it is a command for reconfiguration.
Setting the Re-Configuration setting to Three Ended at any terminal will restore three-terminal operation
without regard to the status of the Inhibit C Diff DDB signal or the Recon Interlock DDB signal.
The operation of the change configuration logic is as follows:
● The reconfiguration setting is changed.
● The product detects the change in setting and attempts to implement the new setting.
If the current configuration is Two-Ended and the new setting is also Two-Ended, the device blocks the change and
issues a configuration error alarm.
108 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
If the current configuration is Two-Ended and the new setting is Three-Ended, the device checks that all the
communications are healthy and sends out the restore command to the other devices. It then checks that the
scheme has stabilised as ‘Three-Ended’ after one second.
If any of the communications in the scheme were failed or if the scheme has not stabilised as Three-Ended, the
device returns to its original Two-Ended setting and issues a configuration error alarm.
If the scheme stabilises as Three-Ended, the Reconfiguration setting is updated.
If the device configuration is Three-Ended and the new setting is Two-Ended L & R1, the device first checks that the
two interlocks are energised. The differential tripping is blocked, but the backup protection can still operate the trip
outputs. The device then checks that the communication with Remote 1 is healthy and sends out the command to
the remote devices. It then checks that the scheme has stabilised as Two-Ended L & R1 after one second.
If the interlocks are not energised, or the communication with Remote 1 has failed, or the scheme does not
stabilise as Two-Ended L & R1, the device returns to Three-Ended and issues a configuration error alarm.
If the scheme stabilises as Two-Ended L & R1, the Reconfiguration setting is updated.
If the device configuration is Three-Ended and the new setting is Two-Ended L & R2, the device reacts similarly to a
Two-Ended L & R1 reconfiguration.
If the device configuration is Three-Ended and the new setting is Two-Ended R1&R2, the device reacts similarly to a
Two-Ended L & R1 reconfiguration.
Rx CH1 CH2 Tx
P54x
Tx End B Rx
Tx Rx
Rx Tx
CH2 CH1
CH1 CH2
Tx Rx
Rx Tx
E02639
P54-TM-EN-1.1 109
Chapter 7 - Current Differential Protection P54
110 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
7 TRANSIENT BIAS
Phase current differential protection stability for current transformers is assisted by a feature called Transient
Bias. This can be enabled or disabled with the transient Bias setting in the CURRENT DIFF column.
Saturation of current transformers (CTs) under heavy load or external fault conditions can cause the protection to
see differential current and could lead to tripping. Preventing CT saturation can impose high specifications and
high costs for the CTs. The Transient Bias feature allows the CT requirements to be relaxed – typically by 25%.
The Transient Bias feature recognises the changes in bias and differential currents under different conditions and
reacts as follows:
● For an internal fault, bias and differential currents start to increase together. For an external condition, bias
current will start to rise, but differential current will not. If CT saturation starts to occur for an external
condition, the differential current starts to increase after the bias current has increased.
● Detecting the relative changes in the bias and differential currents allows the device to detect whether the
differential current is due to an internal fault or due to an external condition causing CT saturation. For
external conditions, the biasing quantity is raised, transiently, to provide stability. For internal faults,
sensitivity is maintained.
P54-TM-EN-1.1 111
Chapter 7 - Current Differential Protection P54
IL IR
ZL I L = Local end line current
I CHL ICHR I R = Remote end line current
VL VR VL = Local end voltage
VR = Remote end voltage
Z L = Line impedance
I CHL = Local end charging current
I CHR = Remote end charging current
V02608
Both transient capacitive and steady-state capacitive charging currents exist. Transient inrush charging current
consists of predominately high-order harmonics, which are filtered out by the device. However, steady state AC
charging currents flow all the time that the feeder remains energised. This capacitive charging current appears as
a differential current. On long overhead lines, and on cable circuits, this capacitive charging current can be
sufficiently high to cause current differential elements to trip under healthy conditions and therefore needs to be
compensated.
To prevent maloperation due to capacitive charging currents, Phase Is1 would normally be set to at least 2.5 times
the charging current. This, however, reduces the sensitivity of the differential protection. If voltage input
connections are made, more effective compensation for capacitive charging current can be applied:
Using the voltage inputs and the line positive-sequence capacitive susceptance, the devices can calculate the
charging currents. These can then be taken into account before calculating the differential currents.
Referring to the figure above, we see that the line charging current at a particular location is equal to the voltage
at that location multiplied by the line positive sequence capacitive susceptance (Bs). The differential current is
therefore:
Idiff = IL + IR - (jVLBs/2) - (jVRBs/2) = {IL - (jVLBs/2)} + {IR - (jVRBs/2)}
The two terms in this equation represent one component that can be calculated at a local terminal and another
that can be calculated at a remote terminal. Using these values, rather than the actual phase current
measurements, will eliminate the effects caused by capacitive charging currents. So, for long line or cable
applications, if voltage transformers are connected, capacitive charging current compensation can be applied.
This is achieved by setting the Compensation setting in the CURRENT DIFF column to Cap Charging. This will
make visible a Susceptance setting into which the line positive sequence capacitive susceptance value can be
entereed.
When applied to a three-ended scheme with ends local (L), remote 1 (R1) and remote 2 (R2), the differential current
is calculated as:
Idiff = IL + IR1 + IR2 - (jVL Bs/3) - (jVR1Bs/3) - (jVR2Bs/3) = {IL - (jVLBs/3) } + {IR1 - (jVR1Bs/3) } + {IR2 -
(jVR2Bs/3)}
If the capacitive charging compensation is enabled, the current measurements in the MEASUREMENTS 3 column
display the compensated values.
112 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
9 CT COMPENSATION
The primary and secondary ratios for the phase current transformers are set in the CT AND VT RATIOS column.
These settings are used to display the phase current quantities in the MEASUREMENTS 1 column. The device can
be set to display the input current either in primary values or in secondary values.
To ensure correct operation of the differential elements, it is important that under load and through fault
conditions, the currents into the differential elements of the devices balance. If the CTs have different ratios this will
not be the case. This product has CT ratio correction (magnitude compensation) to overcome this problem.
When calculating differential and bias currents, the devices use per-unit (p.u.) quantities. CT ratio compensation is
used to scale-up the current signals to match those of the remote terminals by setting an appropriate value in the
Ph CT Corr'tion setting in the CURRENT DIFF column. Because of dynamic limitations, this scaled-up value is
limited to 40 p.u. Values exceeding this are clipped at 40 p.u.
Similarly compensated per-unit values are used in the calculation of the differential and bias currents.
The per-unit compensated values of local and remote currents as well as the per-unit values of differential and
bias currents are scaled-down by the local CT ratio correction factor and displayed in the MEASUREMENTS 3
column.
The process is outlined in the figure below:
Transmission to
Secondary CT 40 p.u. clipping
rating
Remote end
I ABC [Amps sec.] I LOCAL [p.u.] *
I LOCAL [p.u.]
* 1 / ICT rated CT_Correction
* CT_Ratio
I LOCAL [p.u.]
calculations
I DIFF [p.u.]
Diff/Bias
I REMOTE 1 [p.u.]
Decision
I BIAS [p.u.] Trip, Intertrip
Measurements 1
Trip
I REMOTE 2 [p.u.]
Settings
* 1 / CT_Correction [Amps pri. or sec .] Settings [p.u.]
* 1 / ICT rated
Primary or Primary or
Secondary CT * ICT rated
Secondary CT
rating rating
Measurements 3
V02622
For products connected to two sets of current transformers with different CT ratios, then CT1 input is used as a
reference. The product scales CT2 currents based on the PhaseCT1 Primary and PhaseCT2 Primary settings. So,
only CT1 rated current should be considered when applying CT ratio correction.
P54-TM-EN-1.1 113
Chapter 7 - Current Differential Protection P54
This (P543) product therefore provides facilities to deal with the above issues by providing:
● CT compensation for phase shifts and imbalances across the transformer
● Zero sequence compensation.
● Magnetising Inrush detection and restraint
● Second harmonic blocking.
● Overfluxing detection and restraint
● Fifth harmonic blocking.
To make these available you need to enable the differential protection for an in-zone power transformer. This is
done on a per-setting group basis. The phase differential element (Phase Diff) for the setting group concerned
must be enabled.
To enable the transformer feeder protection you set the Compensation cell in the CURRENT DIFF settings to
Transformer (P543).
114 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
Ia = IC
Yy8 120 lead Ib = IA
Ic = IB
Ia = -IB
Yy10 60 lead Ib = -IC
Ic = -IA
Ia = (IA - IB) / √3
Yd11 30 lead Ib = (IB - IC) / √3
Ic = (IC - IA) / √3
Ia = IA - (IA + IB + IC) / 3
Ydy0 0 Ib = IB - (IA + IB + IC) / 3
Ic = IC - (IA + IB + IC) / 3
Where Ia, Ib, Ic are the uncorrected values and IA, IB, IC are the corrected values.
Note:
You must set Compensation to Transformer before the Vectorial Comp setting becomes visible.
P54-TM-EN-1.1 115
Chapter 7 - Current Differential Protection P54
I0
IR1 I0 IR2
IED1 IED2
Digital communication channel
IED1 IED2
IR1 = 0 IR2 = I0
IR2 = I0 Received IR1 = I0
Received
Idiff = I0 Idiff = I0
E02611
Where a transformer winding can pass zero sequence current to an external earth fault, it is essential that some
form of zero sequence current filtering is used. This would also be applicable where in zone earthing transformers
are used. In this product, zero sequence current filtering is automatically implemented in software when a delta
connection is set for the vector compensation.
116 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
+Fm
Steady state
–Fm
2Fm
Switch on at voltage
Zero – No residual flux
E03123
Figure 47: Magnetising inrush phenomenon
We can see that inrush current is a regularly occurring phenomenon and should not be considered a fault, as we
do not wish the protection device to issue a trip command whenever a transformer is switched on at an
inconvenient point during the input voltage cycle. This presents a problem to the protection device, because it
should always trip on an internal fault. The problem is that typical internal transformer faults may produce
overcurrents which are not necessarily greater than the inrush current. Furthermore, faults tend to manifest
themselves on switch on, due to the high inrush currents. For this reason, we need to find a mechanism that can
P54-TM-EN-1.1 117
Chapter 7 - Current Differential Protection P54
distinguish between fault current and inrush current. Fortunately, this is possible due to the different natures of the
respective currents. An inrush current waveform is rich in harmonics, especially 2nd harmonics, whereas an
internal fault current consists only of the fundamental. We can therefore develop a restraining method based on
the 2nd harmonic content of the inrush current. The mechanism by which this is achieved, is called second
harmonic blocking.
Note:
You must set Compensation to Transformer before the Inrush Restraint setting becomes visible.
Note:
When used, the Inrush Restraint function must be enabled at all ends to avoid possible maloperation.
Note:
There is an Inrush Detection setting in the SUPERVISION column of the menu. The Inrush Detection setting is only visible if
the Inrush Blocking’in the CURRENT DIFF column is not being used. The function asserts the same DDB outputs as Inrush
Restraint and can be used to control other protection elements during magnetising inrush conditions. The output of Inrush
Detection does not, however, affect the Current Differential protection.
Note:
Where Inrush Restraint is used to restrain operation, it must be used at all terminals in the scheme to avoid possible
maloperation.
118 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
Magnetising inrush is considered to be present if the level of phase current is above 5% In AND the ratio of
harmonic to fundamental in that phase exceeds the Ih(2) %> value which you set.
Detection of magnetising inrush forces a phase block signal to block local and remote ends.
You can choose whether to block just the affected phase, or to block all three phases using the Ih(2) CrossBlock
cell. If you disable Ih(2) CrossBlock, only the affected phase is blocked. If you enable Ih(2) CrossBlock, all phases
are blocked.
Note:
The Id High Set cell should be set so that it is in excess of the anticipated inrush current after ratio correction has been
applied.
E03107
Such waveforms have a significant 5th harmonic content. We can therefore develop a restraining method based
on the 5th harmonic content of the inrush current. The mechanism by which this is achieved, is called fifth
harmonic blocking.
P54-TM-EN-1.1 119
Chapter 7 - Current Differential Protection P54
If the 5th Harmonic setting is enabled, then the operation of the current differential elements will be blocked if
overfluxing is detected.
Overfluxing blocking is implemented on a phase-by-phase basis. Blocking is prevented if the phase current is less
than 5% In. If the phase current exceeds 5% In, and the element is enabled, then if the ratio of fifth harmonic
current to the fundamental component exceeds the the Ih(5) %> setting, operation of the current differential is
blocked on that phase. Blocking of affected phases is applied both at local and at remote terminals.
You can choose whether to block just the affected phase, or to block all three phases using the Ih(5) CrossBlock
cell. If you disable Ih(5) CrossBlock, only the affected phase is blocked. If you enable Ih(5) CrossBlock, all phases
are blocked.
120 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
Ih(2) Block A
1
Ih(5) Block A
Ih(2) Block B
1
Ih(5) Block B
Ih(2) Block C
1
Ih(5) Block C
Figure 49: Phase Current Differential Protection logic for feeders with in-zone transformers
P54-TM-EN-1.1 121
Chapter 7 - Current Differential Protection P54
Ih(2) CrossBlock
1 Ih(2) Blk A
Enabled
1 Ih(2) Blk B
122 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
Ih(5) CrossBlock
1 Ih(5) Blk A
Enabled
1 Ih(5) Blk B
P54-TM-EN-1.1 123
Chapter 7 - Current Differential Protection P54
Note:
The term “permissive intertripping” associated with this current differential protection is not the same as that commonly used
in teleprotection schemes. It is specific to this type of Current Differential protection implementation.
A device can be configured to send a permissive intertrip command over the protection communication channel.
To use this function you need to map the Perm Intertrip DDB signal to one of the opto-inputs using the PSL.
Protected line
Consider the above diagram. If a fault occurs as shown, it will be seen by the busbar protection which can trip its
local circuit breaker. The fault will not be seen by the differential protection, however, so the fault will continue to
be fed. An input signal from the busbar protection at the faulted end can be sent as a permissive intertrip (PIT)
command to a remote terminal to cause it to permissively trip the remote circuit breaker to clear the fault.
Tripping occurs if the current remains above the Phase Is1 setting of the phase current differential elements while
the PIT command is received. The condition must remain satisfied for a minimum time setting. The time is set in the
PIT Time setting in the CURRENT DIFF column. The permissive intertrip (PIT) timer can be set between 0 and 200
ms. This time should be set to provide discrimination with other protection devices. For example, if there is a
genuine busbar fault, the time delay should be set to allow busbar protection to clear the fault. A typical setting
may be 100 to 150 ms.
You can choose whether to use the local current value sent with the PIT command to make the decision at the
remote end, or whether to use the remote current value at the receiving end for the decision. This choice is made
using the PIT I selection setting in the CURRENT DIFF column.
Note:
The permissive intertripping function always trips three-phase.
124 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
To busbar 1
CTY
End X
Protected line
CTX2
To busbar 2 V02613a
As shown in the figure above, a P546 is applied at End X as the line is fed from a breaker and a half substation
configuration. At End Y where there is a single breaker, a P543 can be installed.
An ‘Additional Bias’ quantity is calculated at terminals which have two sets of CT inputs, and the Additional Bias is
used in the calculation to determine whether to trip or to restrain.
The calculations for differential and bias currents are as follows:
At End X:
I diff = ĪCTX1 + ĪCTX2 + ĪCTY
I bias = (│ICTX1│ + │ICTX2│ + (Additional Bias if non zero) or│IREMOTE│)/2
P54-TM-EN-1.1 125
Chapter 7 - Current Differential Protection P54
In this example the Additional Bias is zero as the device at the remote end has a single set of CT inputs.
The Additional Bias (to be sent to end Y) is calculated on a per phase basis by scalar summing both local currents
(ICTX1 and ICTX2) and selecting the largest of the three calculated. This current is included in the messages
containing the information transmitted between terminals.
At End Y:
I diff = ĪCTY + ĪCTX1 + ĪCTX2
I bias = (│ICTY │ + (Additional Bias if non zero) or│IREMOTE│)/2
In this case Additional Bias is sent by End X (device with two CT inputs).
Different CT ratios can be set for CTX1 and CTX2 using the settings PhaseCT1 Primary and PhaseCT2 Primary at
end X. If different CT ratios are used, the CT1 current inputs must be connected to the CT set with the highest
primary rated current. CT1 is used as a reference and secondary current from CT2 is scaled down to match the
reference CT1.
You cannot set PhaseCT2 Primary setting above PhaseCT1 Primary.
You should keep the ratio between PhaseCT1 Primary and PhaseCT2 Primary below 4.
126 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
P54-TM-EN-1.1 127
Chapter 7 - Current Differential Protection P54
To busbar 1
CTY
End X
Protected line
CTX2
To busbar 2 V02614a
To busbar 1
CT Y
End X
Protected line
CTX2
To busbar 2 V02614
Note:
Models having distance protection feature a phase segregated stub bus protection associated with the distance protection
elements. Where applicable these are described along with the distance elements.
128 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
If an IED suffix M or Q communicates with an IED suffix B,G, or J, a monitor bit labelled H/W Bto J in Measurement 4
> Channel status becomes 1.
Differential current transformer supervision (Differential CTS) in P543 - P546 models suffix M and Q are only
compatible with P543 - P546 models suffix K & M.
P54-TM-EN-1.1 129
Chapter 7 - Current Differential Protection P54
18 APPLICATION NOTES
If capacitive charging current compensation is not used, the setting of Phase Is1 must be set above 2.5 times the
steady state charging current. Where charging current is low or negligible, the recommended setting of 0.2 pu
(factory default) should be applied.
130 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
If there is a mismatch between CTs at line ends, then the lowest primary CT rated current should be used as a
reference current for p.u. calculations (assuming that the load current cannot continuously exceed this value). This
means that the recommended settings Phase Is1 = 0.2 pu is equal to 0.2*(the lowest primary CT rated value). The
same consideration applies for other current settings such as Phase Is2.
ILOCAL = IL + IF
IREMOTE1 = -y*IL where 0<y<1
IREMOTE2 = - (1-y) IL
|Idiff|= |IF|
|Ibias| = |IL| + 0.5 |IF|
Phase current differential protection sensitivity when |Ibias| < Phase Is2:
The phase current differential protection would operate if |Idiff| > Phase k1 |Ibias| + Phase Is1
therefore:
|IF| > (Phase k1 |IL| + Phase Is1) / (1 - 0.5 Phase k1)
For Phase Is1 = 0.2 pu, Phase k1 = 30% and Phase Is2 =2.0 pu, then
● for |IL| = 1.0 pu, the phase current differential protection would operate if |IF| > 0.59 pu
● for |IL| = 1.59 pu, the phase current differential protection would operate if |IF| > 0.80 pu
If |IF| = 0.80 pu and |I| = 1.59 pu, then |Ibias| = 1.99 pu, which reaches the limit of the low percentage bias curve.
Phase current differential protection sensitivity when |bias| > Phase Is2:
The phase current differential protection would operate if |Idiff| > Phase k2 |Ibias| - (Phase k2 - Phase k1) Phase Is2 +
Phase Is1
therefore:
|IF| > (Phase k2 |IL| - (Phase k2 - Phase k1) Phase Is2 + Phase Is1) / (1 - 0.5 Phase k2)
For Phase Is1= 0.2 pu, Phase k1 = 30%, Phase Is2 = 2.0 pu and Phase k2 = 100%, then,
● for |IL| = 2.0 pu, the phase current differential protection would operate if |IF| > 1.6 pu
● for |IL| = 2.5 pu, the phase current differential protection would operate if |IF| > 2.6 pu
P54-TM-EN-1.1 131
Chapter 7 - Current Differential Protection P54
Note:
The following consideration includes references to currents used in Neutral Current Differential protection and protection of
feeders with In-zone transformers. If not applicable they may be ignored.
If the CTs at line ends have different primary ratings, then one of them is considered as a reference (the one with
the lowest primary rating). Ph CT Corr’tion should be set to 1 in the device connected to the reference CT. For all
other devices Ph CT Corr’tion is calculated as follows:
Ph CT Corr'tion IEDx = (Phase CT Primary IEDx) / (Phase CT Primary REFERENCE)
Settings Phase Is1, Phase Is2, Id High Set, Diff Is1, Diff Is2 must be calculated as pu of the reference primary
rating, then converted into local primary (secondary) values. For setting Phase Is1 in IEDX, the equations would be:
Phase Is1 [p.u.] = (Phase Is1 IABSOLUTE PRI [A]) / (Phase CT Primary REFERENCE [A])
Phase Is1 IEDx PRI. [A] = (Phase Is1 [p.u.]) (Phase CT Primary IEDx)
Phase Is1 IEDx SEC. [A] = (Phase Is1 [p.u.]) (Phase CT Sec'y IEDx)
The same considerations apply to settings Phase Is2, Id High Set, In Diff Is1, Diff Is2.
Example:
Assume that we have a three-ended application with line ends X, Y, Z (500/5, 800/5, 200/1) and Current Differential
settings in absolute primary values:
Phase Is1 ABSOLUTE PRI. = 100A
Phase Is2 ABSOLUTE PRI. = 1000A
Id High Set ABSOLUTE PRI. = 3000A
Diff Is1 ABSOLUTE PRI. = 50A
Diff Is2 ABSOLUTE PRI. = 1000A
Setting End X End Y End Z
Phase CT Primary 500A 800A 200A
Phase CT Sec’y 5A 5A 1A
Ph CT Corr’tion 500/200 = 2.5 800/200 = 4 1 (reference)
Phase Is1 [p.u.] 100/200 = 0.5 100/200 = 0.5 100/200 = 0.5
132 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
33 kV 400/1 400/1 33 kV
25 km
Protected line
P54-TM-EN-1.1 133
Chapter 7 - Current Differential Protection P54
In the case that voltage inputs are not in place, no facility to account for line charging current is available. The
setting of Phase Is1 must therefore be set above 2.5 times the steady state charging current value. In this example,
assume a cable is used and there are not VT inputs connected to the device:
Phase Is1 > 2.5(Ich)
Phase Is1 > 2.5 (25 km x 2.5 A/km)
Phase Is1 > 156.25 A
The line CTs are rated at 400 amps primary. The setting of Phase Is1 must therefore exceed 156.25/400 = 0.391 pu.
Therefore select:
Phase Is1 = 0.4 pu
If VTs are connected, a facility exists to overcome the effects of the line charging current. To use this you need to
set the Compensation setting in the CURRENT DIFF column to Cap Charging and then programme the line
positive sequence capacitive susceptance value into the Susceptance setting now apparent in the CURRENT DIFF
column. This can be calculated from the line charging current as follows (assuming a VT ratio of 33 kV / 110 V):
Ich = 25 x 2.5 A = 62.5 A
Susceptance B = wC = Ich/V
B = 62.5 A/(33/Ö3 ) kV primary
B = 3.28 x 10-3 S primary
Therefore set:
B = 3.28 mS primary (= 2.46 mS secondary)
Phase Is1 may now be set below the value of line charging current if required, however we suggest that you
choose Phase Is1 only sufficiently below the charging current to offer the required fault resistance coverage.
Where charging current is low or negligible, the recommended factory default setting of 0.2xIn should be applied.
134 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
End A End B
275 kV 4000/5 4000/5 275 kV
Protected line
45 km 30 km
P54x
Ch 1 Ch 2
If there are no VT inputs connected, the setting Phase Is1 must be 2.5 times the steady state charging current
suitably corrected for the different CT ratios as presented below in the calculation of charging current
compensated values. For an overhead line circuit with a charging current of 0.58A/km the charging current will be:
Ich = 0.58 A ( 45 + 30 + 10 ) = 49.3 A
If VT inputs are connected, there is a facility to overcome the effect of charging current. To do this you need to
enter the positive sequence capacitive susceptance value.
Considering the charging current on the circuit shown in the figure above, the following calculation applies:
Ich = 0.58 A ( 45 + 30 + 10 ) = 49.3 A
Susceptance = wC = Ich/V
B = 49.3 A/( 275/ Ö3) kV primary
B = 0.31 x 10-3 S primary.
The CT ratios on the three ends are different, so it is necessary to apply a correction factor to ensure secondary
currents balance for all conditions:
To calculate the correction factor (CF), the same primary current must be used even if this current is not the
expected load transfer for every branch. This will ensure secondary current balance for all conditions.
CT ratio correction input data is shown in the table below:
Setting End A End B End C
Phase CT Primary 4000A 4000A 1200A
Ph CT Corr’tion 4000/1200 = 3.33 4000/1200 = 3.33 1 (reference)
P54-TM-EN-1.1 135
Chapter 7 - Current Differential Protection P54
Note:
Settings shown in primary values at ends A and B appear different compared with end C. This is not a problem as the currents
at ends A and B will be multiplied by the Correction Factor, when the differential calculation is done.
136 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
Dyn1
20MVA 33/11kV
400/1 1500/1
350A 1050A
0° –30°
0.875 0.7
P540 P540
Yy0 x1.14 Yd11 x1.43
Digital communication channel
E02640
Calculate the required ratio correction factor to apply to the IEDs at each line end.
33 kV full load current = 20 MVA/(33 kV.Ö3) = 350 A
11 kV full load current = 20 MVA/(11 kV.Ö3) = 1050 A
Each of these full load (reference) currents should be corrected to CT rated current:
When a Star/Delta software interposing CT is chosen, no additional account has to be taken for the Ö3 factor
which would be introduced by the delta winding. This is accounted for by the IED.
P54-TM-EN-1.1 137
Chapter 7 - Current Differential Protection P54
These three IEDs must be rated differently, i.e. 1A for HV and MV side and 5 A for 30 kV side. This does not present a
problem for P54x IEDs as the digital signals representing the currents are in pu.
It is necessary to calculate the required ratio correction factor (CF) as well as the phase correction factor for each
end. To choose the appropriate vector compensation, it is necessary to account for phase current and zero
sequence current filtering as explained in the Transformer Feeder Example.
To calculate the correction factors, it is necessary to use the same base power (100 MVA in this particular case) for
the three sides of the transformer although the third winding actually has lower rated MVA. This is to ensure that
compensated currents balance for all conditions.
Setting HV side MV side LV side
Phase CT Primary 600A 1200A 2000A
Phase CT Sec’y 1A 1A 5A
Reference Primary 100000/(400 Ö3) = 144.3A 100000/(110 Ö3) = 524.9A 100000 (30 Ö3) = 1924.5A
(at 100 MVA basis)
Ph CT Corr’tion 600/144.3 = 4.16 1200/524.9 = 2.29 2000/1924.5 = 1.04
To choose the vector compensation setting, it should be noted that the Wye connected HV line is in phase with the
MV line current and leads the LV line current by 30o. Therefore for LV side, the phase shift must be compensated.
To account for the zero sequence current filtering in the case of an external earth fault, it is necessary to connect
the Wye connected power transformer windings to an interposing current transformer (internal IED ICT) to trap the
zero sequence current (the secondary side being connected delta).
138 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
To account for both vector compensation and zero sequence current filtering, the following vectorial
compensation setting is recommended:
● For HV side = Yd1 (-30 deg)
● For MV side = Yd1 (-30 deg)
● For LV side = Yy0 (0 deg)
Note:
It is not necessary to include the Ö3 factor in the calculation as this is incorporated in the IED algorithm.
P543 and P545 IEDs are suitable for transformer applications, as such an inrush restrain is provided on these IEDs.
By enabling inrush restrain, an additional current differential high setting (Id High set) becomes enabled.
When the inrush restrain feature is enabled, this function needs to be enabled in the IED at each line end (3 ends).
The same settings as in the previous examples are recommended:
● Is1 = 0.2 pu
● Is2 = 2 pu
● K1 = 30%
● K2 = 100%
For the current differential high setting (Id High set) the setting must be in excess of the anticipated inrush current
after ratio correction. Assuming that maximum inrush is 12 times the nominal transformer current, it would be
safe to set the IEDs at 15 times the nominal current, therefore the setting would be:
● Id high set: = 15 pu
P54-TM-EN-1.1 139
Chapter 7 - Current Differential Protection P54
In the case of a through fault as shown in the figure below, the device connected to circuit ‘A’ should see no
current so it remains stable. Under this condition, no bias current is measured by the device. To ensure stability, the
two sets of line CTs should be the same in all characteristics and equally loaded. Then the protection connection
should be at the equipotential point of the secondary leads.
In the case of circuit ‘B’ no differential current should result. However, a large bias current exists, providing a high
degree of stability if there is a through fault. This bias also ensures stability where CTs are not closely matched.
Therefore, circuit ‘B’ is the preferred connection for such applications, so products with two sets of three-phase CT
inputs would normally be specified.
Different CT ratios can be set for CT1 and CT2. CT1 current inputs of the device must be connected to the CT set
with the highest primary rated current. You cannot set PhaseCT2 Primary setting above PhaseCT1 Primary. You
should keep the ratio between PhaseCT1 Primary and PhaseCT2 Primary less than 4:
Bus 1 Bus 2
IF IF
87 87
Stub bus
inputs
A B
E02615
140 P54-TM-EN-1.1
P54 Chapter 7 - Current Differential Protection
O ut of S er vi ce
H eal t hy
C F6 P59x Modem Modem P59x F1
Tr i p
A l ar m
O ut of S er vi ce
H eal t hy
C F6
F2 F7 F2 F7
F3 OK F8 F3 OK F8
F4 F9 F4 F9
F5 | L/R F1 0 F5 | L/R F1 0
End A End B
Tr i p
H eal t hy
F2 F7
F4 F9
F5 | L/R F1 0
End C V02642
P54-TM-EN-1.1 141
Chapter 7 - Current Differential Protection P54
142 P54-TM-EN-1.1
CHAPTER 8
DISTANCE PROTECTION
Chapter 8 - Distance Protection P54
144 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
1 CHAPTER OVERVIEW
This chapter introduces the principles and theory behind the protection and describes how it is implemented in this
product. Guidance for applying this protection is also provided.
This chapter contains the following sections:
Chapter Overview 145
Introduction 146
Distance Measuring Zones Operating Principles 148
Phase and Earth Fault Distance Protection Implementation 183
Distance Isolated and Compensated Systems 195
Application Notes 209
P54-TM-EN-1.1 145
Chapter 8 - Distance Protection P54
2 INTRODUCTION
Amongst protection engineers, the basic principles of Distance Protection are widely documented and understood.
If you are reading this chapter, we assume that you are familiar with the principles of distance protection and
associated components such as Aided Schemes. However, to help you choose suitable settings, some of the
principles of operation of the Distance Measuring Zones is included in this chapter.
R
Source Line
VS IR VL=VR
ZL
V VR
V02753
The voltage V applied to the impedance loop is the open circuit voltage of the power system. Point R represents the
protection location; IR and VR are the current and voltage measured by the relay, respectively.
The impedances Zs and ZL are described as source and line impedances because of their position with respect to
the protection location. Source impedance Zs is a measure of the fault level at the relaying point. For faults
involving earth it is dependent on the method of system earthing behind the relaying point. Line impedance ZL is a
measure of the impedance of the protected section. The voltage VR applied to the relay is, therefore, IRZL. For a
fault at the reach point, this may be expressed in terms of the System Impedeance Ratio, using the following
expression:
VR = V/(SIR+1)
where SIR = ZS/ZL
146 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
From the equation above, it can be seen that the measured voltage has a significant impact on the decision
making process.
The ability of distance protection to measure accurately for a given reach point fault, depends on the voltage at
the relaying location being above a minimum value at the time of the fault. If the voltage is above this minimum
value, it is generally used to polarize the distance protection and indicate the direction of the fault. This is called
self-polarization.
If the voltage collapses below the minimum threshold necessary to make a sensible decision, alternative methods
of polarization to determine the direction of the fault are needed. Two methods that are applied are cross-
polarization and memory polarization. If a fault doesn’t affect all phases, the voltage signals on the healthy phases
can be used for the directional decision. This is called cross-polarization. If the fault causes all phase voltages to
collapse, a stored record of the pre-fault voltage can be used to make the directional decision. This is called
memory polarization. Memory polarization, cross-polarization, and self-polarization can sometimes be used in
combination.
P54-TM-EN-1.1 147
Chapter 8 - Distance Protection P54
148 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Note:
The faulted phase current (I) is generally used as the reference (0º) for the vector diagrams.
V IZ
IZ
V 90°
V02710
Figure 62: Directional mho element construction
P54-TM-EN-1.1 149
Chapter 8 - Distance Protection P54
V IZ
IZ
90°
V
V I Z
I
I Z
V02711
150 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
jX Z k ZN I N I ph
jX
V ph I ph Z replica
V IZ
Z Z
Z replica
90°
90°
R R
V I V ph I ph
V02712
Zreplica = Z(1+kZN.IN/Iph)
or if mutual compensation is applied:
Z(1+kZN.IN/Iph+kZM.IM/Iph)
P54-TM-EN-1.1 151
Chapter 8 - Distance Protection P54
Then if healthy phase currents are much less then the current of the faulty phase and the mutual compensation is
disabled:
IN @ Iph
so that
Zreplica @ Z(1 + kZN)
Thus the ZLP plane representation of the characteristic becomes static.
jX Z1 -plane
V IZ
Z
90°
V I
V I Z
R
Z
V02713
Figure 65: Offset Mho characteristics – impedance domain
152 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Z LP -plane
jX Z k ZN I N I ph
V ph I ph Z replica
Z Z replica
90°
h
h / Ip
Vp
Z replica R
Z
V ph I ph Z replica
Z k ZN I N I ph
V02714
Figure 66: Offset mho characteristics – voltage domain
where: Zreplica is the replica forward reach and Z'replica is the replica reverse reach.
With mutual compensation applied:
Zreplica = Z(1+kZN.IN/Iph + kZM.IM/Iph)
Z'replica = Z'(1+kZN.IN/Iph + kZM.IM/Iph)
If the healthy phase currents are much less than the current of the faulty phase, then the neutral current is
approximately the same as the phase current, and the terms can be simplified as follows:
Zreplica = Z(1+kZN + kZM.IM/Iph)
Z'replica = Z'(1+kZN + kZM.IM/Iph)
If the healthy phase currents are much less than the current of the faulty phase, and mutual current compensation
is not applied, then these terms can be simplified as follows:
Zreplica @ Z(1+kZN)
Z'replica @ Z'(1+kZN)
So, as with the Directional Self-Polarized Mho characteristic for earth-faults, the ZLP plane representation of the
characteristic becomes static.
P54-TM-EN-1.1 153
Chapter 8 - Distance Protection P54
Note:
The Force No Mem. DDB may be used to force the relay to work as if the memory time has elapsed, i.e. a combination of self
and cross polarisation voltage.
Note:
The Self Pol DDB indicates when the relay is working with voltage self polarization.
Operation occurs when the angle between the signals is greater than 90°.
The memory voltage Vmem is the pre-fault voltage. Assuming the pre-fault current is close to zero at the relaying
point, he pre-fault voltage is equal to the source voltage. Therefore:
Vmem = VS
IED
Dist
VS Bus I
Line
ZS ZF
V
V02715
Figure 67: Simplified forward fault
154 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
p
90° ≤ ∠ V I + ⋅ Z S − ∠ ( V I − Z ) ≤ −90°
1+ p
The Mho expansion for a forward fault is illustrated in the following diagram:
jX
Self-polarised
V IZ
Z
V I 90°
R
p
ZS
1 p p
V I ZS
1 p
V02716
Figure 68: Mho expansion – forward fault
ZS = (Vmem - V)/I
P54-TM-EN-1.1 155
Chapter 8 - Distance Protection P54
IED
Dist
Bus VS
I
Network
ZF ZL ZS
V
V02717
p
90° ≤ ∠ V I − ⋅ ( Z S + Z L ) − ∠ ( V I − Z ) ≤ −90°
1+ p
The Mho contraction for a reverse fault is illustrated in the following diagram:
156 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
p
V I (ZS ZL )
1 p
jX
90°
V IZ
p
(Z S Z L )
1 p
V I
R
Self-polarised
V02718
Figure 70: Mho contraction – reverse fault
ZS + ZL = (V - Vmem)/I
P54-TM-EN-1.1 157
Chapter 8 - Distance Protection P54
The cross-polarization voltage is generated using phase(s) not otherwise used for the particular distance or
directional measurement. While one pole is dead, and the memory is not available, the elements associated with
the remaining phases are polarized as shown in the following table:
Cross Polarizing Signal
Loop Cross Polarizing if a Pole is Dead
(No poles dead)
A-N 0.5(aVB + a2VC) aVB if C pole is dead or a2VC if B pole is dead
B-N 0.5(aVC + a2VA) aVC if A pole is dead or a2VA if C pole is dead
C-N 0.5(aVA + a2VB) aVA if B pole is dead or a2VB if A pole is dead
A-B √3VC Ð -90º 0
B-C √3VA Ð -90º 0
C-A √3VB Ð -90º 0
where a is a mathematical operator which rotates a vector through 120° and a2 denotes a rotation of 240°.
VC VC
√3VC
-90°
αVB
VA VA
α2VC
VAB
E02796
Figure 71: Cross polarizing voltage for phase to ground and phase to phase faults
The table and diagram shows polarizing signal contributions for each loop under the different operating
conditions. The proportion of cross-polarization voltage used is defined by the Dist. Polarizing (p) setting.
Note:
Cross polarization is used only when there is no memory polarization quantity available.
Note:
If no memory voltage is available or Force No Mem. is set, then the cross-polarized quantity is used instead.
The setting Dist. Polarizing (p) defines the amount of memory polarization (or if need be, cross polarization
voltage), which should be added with respect to the existing self-polarizing voltage so that:
S1 = V + pVmem.
158 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
P54-TM-EN-1.1 159
Chapter 8 - Distance Protection P54
Line Angle
+jX
Z3 (offset)
ZP (forward)
Z2
Z1
Forward
-R +R
Reverse
Z4
ZQ (reverse)
E02785
Programmable zones (zone P and Q) are also available. Similar to Zone 3, the programmable zones can be
configured as Offset, Directional Forward, or Directional Reverse.
A combination of simple comparators, each using signals derived from measured currents and voltages,
determines whether measured impedance is within a tripping zone. A separate comparator is used for each line of
each Quadrilateral.
Each tripping zone is constructed from a Quadrilateral based on that depicted in the following diagram:
jX
Tripping
Reverse Resistive Region
Reach line
Resistive
Reach line
R’ θ R +R
Z’
Reverse Impedance Reach line
-jX
E05001
In the figure, an Offset Quadrilateral characteristic is defined by its Impedance Reach, Z, (and Reverse Impedance
Reach, Z’), its Resistive Reach, R, (and Reverse Resistive Reach, R’), and the zone angle (θ).
160 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
The two near-horizontal lines (Impedance Reach Line and Reverse Impedance Reach Line) set the reactive
impedance limits of the tripping zone. The two near-vertical lines (Resistive Reach Line and Reverse Resistive
Reach Line) set the resistive impedance limits.
The Resistive Reach Lines (also called Resistive Blinders) are parallel and set at the angle of the zone’s
characteristic impedance.
The Impedance Reach Lines exhibit a characteristic tilt (slope). A line that tilts to reduce the reactive reach
(negative tilt/tilt down) encourages underreaching; A line that tilts to increase the reactive reach (positive tilt/tilt up)
encourages overreaching. The tilt can be used to reinforce the overreaching/underreaching requirements of the
zone. For example, for an underreaching Forward zone, a negative tilt will ensure that the measurement continues
to underreach, even with increasing fault resistance.
The Impedance Reach, Z, and the Resistive Reach, R, apply in the context of the direction of the protection. For a
Forward Zone, or an Offset Zone, Z and R look into the protected plant. For a Reverse Zone, Z and R look behind the
protected plant. Reactive Line tilts follow the same convention.
jX
Tripping
Region
Directional Line
R’ θ R +R
Forward direction
Z’ Reverse direction
-jX
60°
E05000
This product has a Delta Directional element that is normally used to directionalise the Distance protection.
By default, the Delta Directional element is enabled (Dir. Status in DELTADIRECTIONAL set to Enabled). In this
case, the Directional Line for the Quadrilateral is derived using superimposed fault-current (Delta I). When using the
Delta Directional element, the Directional Line angle has a default value of 60º, but you can change it with the Dir.
Char Angle setting.
If you want to use a conventional directional technique, then you can do this by disabling the Delta Directional
element. The protection will then use a conventional directional element with a fixed angle of 60º. If the
conventional directional decision is used, the directional elements are polarized by a mix of self (actual) and
P54-TM-EN-1.1 161
Chapter 8 - Distance Protection P54
memory voltage. The polarizing voltage always contains self-polarized voltage and a percentage of the pre-fault
memory voltage. The setting Dist. Polarizing varies from 0.2 (20%) to 5 (500%) and defines the proportion
between self-polarizing voltage and memory-polarizing voltage used for the directional voltage polarization as
follows:
V polarising = Vself-polarizing/Dist. Polarizing + V memory-polarizing
As it can be seen from the formula, the higher the setting Dist. Polarizing, the higher the value of memory-
polarizing voltage used.
Once the memory expires, the value of V memory-polarising is replaced by V cross-polarising cross as shown in
the following table:
Cross Polarizing Signal
Loop Cross Polarizing if a Pole is Dead
(No poles dead)
A-N 0.5(aVB + a2VC) aVB if C pole is dead or a2VC if B pole is dead
B-N 0.5(aVC + a2VA) aVC if A pole is dead or a2VA if C pole is dead
C-N 0.5(aVA + a2VB) aVA if B pole is dead or a2VC if A pole is dead
A-B √3VC Ð -90º 0
B-C √3VA Ð -90º 0
C-A √3VB Ð -90º 0
where a is a mathematical operator which rotates a vector through 120° and a2 denotes a rotation of 240°.
If Dir. Status in DELTADIRECTIONAL is set to Disabled, we recommend a setting of 1 for correct directionality in
typical applications.
The relay has the facility to deter the use of memory, with the Force No Mem. DDB. This DDB forces the relay to
work without voltage memory polarization, making it operate as if the voltage memory timer Mem Volt Dura has
expired.
The following figure illustrates two Offset zones that have been converted into Directional Forward zones by the
overlay of a Directional Line. An Offset zone is also shown for reference.
jX
Offset zone
Directional zone
Directional Line
Directional zone
-R +R
Forward direction
Figure 75: Quadrilateral Characteristic featuring 2 directional forward zones and 1 offset zone
162 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Each of the lines produced by the comparators defines a tripping limit: Impedance on one side of the line prevents
tripping whereas impedance on the other side of the line may, if the other comparators agree, allow tripping. For
example, impedance beyond the Impedance Reach Line will not allow tripping.
The combination of the comparator outputs produces a polygon shaped tripping region. The polygon may be
either 4-sided or 5-sided. The shape depends according to the settings that are applied by the five comparators
and how the Directional Line interacts with the reach lines (usually the Reverse Impedance Reach Line):
● The Directional Line may completely mask a reach line. If that is the case, the polygon will be 4-sided
(quadrilateral).
● If the Directional Line intersects a reach line, the polygon will be 5-sided.
jX
Directional Line
-R R
Forward direction
Figure 76: Five-sided polygon formed by Quadrilateral characteristic with Directional-Line intersection of
Reverse Impedance Reach Line
The applied settings will determine the intersection point. When the settings have been chosen, the following
values will affect the line intersection point:
● Impedance Reach
● Reverse Impedance Reach
● Resistive Reach
P54-TM-EN-1.1 163
Chapter 8 - Distance Protection P54
The Impedance Reach, the Resistive Reach, and the Zone Characteristic Impedance Angle, can be freely assigned.
The Directional Line Angle is 60º by default but can be varied if the Delta Directional element is enabled. The Tilt
Angle of the impedance lines has a default setting of -3º, but some variation is allowed if the Advanced setting
option is chosen.
The Reverse Impedance Reach, and the Reverse Resistive Reach are applied as a fixed ratio of the Impedance
Reach and the Resistive Reach for Directional characteristics. The ratios used vary according to the zone type. The
following tables present the different values for phase-phase characteristics and phase-earth characteristics. For
completion, the reach limit values for Offset zones are also included (although the overlaid Directional line does not
apply and the Offset characteristics will always be quadrilateral).
164 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Note:
*This is also the reverse impedance reach, if the Series Comp. setting is Enabled.
P54-TM-EN-1.1 165
Chapter 8 - Distance Protection P54
of measured currents I2 and Iph. When I2 is used as the polarizing quantity, the tilt can dynamically vary according
to the angle of I2. If Iph is used, the tilt remains fixed at the set angle.
Consider polarization of the reactance lines for the case of a phase-earth fault:
For a phase-earth fault:
V = Vph
and assuming that mutual compensation is not applied:
I = Iph + kZN.IN.
To avoid overreaching or underreaching due to the voltage drop in the arc resistance, the top line of the
characteristic should be ideally tilted by an angle:
Ð (Ifault / I)
So that the total angle of tilt should be:
Ð (Ifault / I) + σ
where Ifault is the fault current and σ is the fixed tilt of the reactance line (user setting for the Impedance Reach
line, fixed -3º preset for the Reverse Impedance Reach line.
If Z is the zone reach setting then the reactance line is formed by phase comparison between an operating signal
V – I Z (S1), and a polarizing quantity, IPOL (S2).
Ifault should be used to determine S2, but, because the Distance protection cannot measure the fault current
directly (due to the unknown infeed from the remote end), Ifault cannot be used as the polarizing current. Instead,
the angle of Ifault must be estimated. Two proven methods to estimate the angle of Ifault are:
1. The angle of Ifault can be assumed to be close to the angle of Iph
2. The angle of Ifault can be assumed to be close to the angle of the negative sequence current I2.
In case 1, the angle of Iph can be used to polarize the Quadrilateral characteristic and so the tilt of the reactance
line is fixed.
In case 2 the angle of I2 can be used to polarize the Quadrilateral characteristic. In this case, the reactance line tilt
varies dynamically according to the angle of I2.
The reactance line follows the fault resistance impedance and tilts up or down, starting from the set initial tilt angle
(σ) to avoid underreaching or overreaching.
For both fixed and dynamic tilting the validity of current polarization is controlled by the following condition:
|Ð I2 - Ð Iph | < 45º
If this condition is not fulfilled, the assumptions that the angle of Ifault is close to the angle of Iph or close to the
angle of I2 cannot be considered valid. Under such conditions the Quadrilateral characteristic could significantly
overreach or underreach. To avoid this, the distance protection automatically switches from Quadrilateral to Mho
characteristics to provide stable operation.
166 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Z1-plane
Iph j
Ð e
+jX I
V IZ
Z V I
+R
V05012
For all V/I vectors below the Impedance Reach line, the following condition is true:
Ð (V/I-Z) ≤ σ
or
Ð (V – I.Z) ≤ I + σ
If mutual compensation is not applied, for an earth-fault loop
V = Vph
and
I = Iph + kZN.IN
so the signals fed into comparator are:
S1 = Vph – Iph.Zreplica
S2 = Iph Ð σ
where: Zreplica is the replica forward reach
The impedance below the Impedance Reach line is detected when the angle between the signals is less than 0°:
For products that have mutual compensation, if the mutual compensation is applied, then
Zreplica =Z(1+kZN.IN/Iph+kZM.IM/Iph).
The following figure shows the ZLP-plane representation of the characteristic:
P54-TM-EN-1.1 167
Chapter 8 - Distance Protection P54
Z LP -plane
+jX Z k ZN I N I ph V ph I ph Z replica
Z replica
Z
V ph I ph
+R
V05004
The Impedance Reach line tilting angle in the ZLP plane is fixed at σ (Zx Tilt Top Line setting).
The Impedance Reach line tilting angle in the Z1 plane is defined as follows:
Tilt angle = Ð(Iph/I) + σ = Ð(Iph/(Iph + kZN.IN)) + σ
If the healthy phase currents are much less than the current of the faulty phase, then IN ≈ Iph. The tilting angle in
this case is fixed at the following value:
Tilt angle = Ð((1/(1 + kZN)) + σ
For products that have mutual compensation, if the mutual compensation is enabled, the tilting angle is:
Tilt angle = Ð(Iph/(Iph + kZN.IN+ kZM.IM)) + σ
The replica reach Zreplica depends on the ratio of IN/Iph. If IN ≈ Iph (and if mutual compensation is not applied)
then:
Zreplica =Z (1 + kZN)
So the characteristic is static.
The general characteristic in the ZLP plane is shown in the following figure:
168 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
ZLP plane
+jX
Zreplica
Vph / Iph
R LP RLP
+R
Z replica 3
V05005
The comparators used for the reactance lines are as per the following table:
Zone Line S1 S2 Condition
Forward or Offset Impedance Reach Vph - Iph.Zreplica Iph∠σ ∠S1 -∠S2 < 0º
Forward or Offset Reverse Impedance Reach Vph - Iph.Z’replica Iph∠-3º ∠S1 -∠S2 > 0º
Reverse Impedance Reach Vph + Iph.Zreplica -Iph∠σ ∠S1 -∠S2 < 0º
Reverse Reverse Impedance Reach Vph + Iph.Z’replica -Iph ∠-3º ∠S1 -∠S2 > 0º
P54-TM-EN-1.1 169
Chapter 8 - Distance Protection P54
● For Forward operating zones (except Zone 1) the Impedance Reach line dynamic tilt is applied to tilt the
Resistive Reach end of the line away from the +R axis.
● For Reverse operating zones the dynamically tilting line is in the opposite quadrant of the characteristic
compared with Forward/Offset Zones and the dynamic tilt moves the line away from the resistive axis.
● For Offset zones, the Impedance Reach lines tilt away from the R-axis, whilst the Reverse Impedance Reach
Lines tilt towards the +R axis. This avoids overreaching in the reverse direction.
● For products that feature single-phase tripping, when one circuit breaker pole is open during a single-pole
autoreclose sequence, dynamic tilting is automatically disabled. The fault current is used as the polarizing
signal and a fixed -7° tilt is applied. The additional tilt reduces the possibility of overreach caused by using
the faulted phase as the reference.
Note:
The tilting of the zones remains unaltered if the default direction is changed.
Zone 1 always behaves as an underreaching zone regardless of the zone direction.
All other directional zones behave as overreaching zones regardless of zone direction.
Note:
Zone 1X used in Zone 1 Extension Schemes uses the Zone 2 tilt settings to ensure that it does not underreach.
Dynamic tilting of reactance lines only occurs when the line is polarized with I2. If Iph is used as the polarizing
quantity the tilt of the Impedance Reach line is fixed. If fixed tilting is selected, Iph is always used. If dynamic tilting
is enabled, then the protection will decide whether to use I2 or Iph (and hence whether dynamic tilting will apply)
according to the angular relationship between I2 and Iph.
The following criteria are applied:
● If the angle between I2 and Iph is more than 45°, the Quadrilateral characteristics are disabled and Mho
characteristics are used instead.
● If the angle between I2 and Iph is less than 45°, Leading and lagging polarizing currents are allocated
according to the phase relations between I2 and Iph as presented in the diagram below:
I LEAD I ph I ph I LEAD I 2
I LAG I 2 I LAG I ph
I2
I ph
I2
V02728
Figure 80: Phase relations between I2 and Iph for leading and lagging polarizing currents
The comparators used for the reactance lines are allocated as per the following table:
Zone Line S1 S2 Condition
170 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Note:
*This is also the reverse impedance reach, if the Series Comp. setting is Enabled.
If ILEAD is I2 the lines are dynamically tilted up from the fixed angle.
If ILEAD is Iph, the fixed tilt applies.
If ILAG is I2, the lines are dynamically tilted down from the fixed angle.
If ILAG is Iph, the fixed tilt applies.
+jX
Z1 plane
Ð (Iph / I) +
Z
V/I
R’ +R
R
Z’
Ð (Iph / I) – 3°
V05006
P54-TM-EN-1.1 171
Chapter 8 - Distance Protection P54
+jX Z1 plane
1
Z
1 k
N
Z
R’reach Rreach
+R
Z’
V05013
a = (1/(1 + kZN))
In typical cases the sine ratio coefficient term is close to unity so the simplified equations can be used:
Rreach = RLP / ǀ (1 + kZN) ǀ,
R’reach = R’LP / ǀ (1 + kZN) ǀ,
So in terms of replica impedances and loop resistances, the comparators used for the resistance lines are as per
the following table:
Zone Line S1 S2 Condition
Forward or Offset Resistive reach Vph - Iph.RLP Iph.Zreplica ∠S1 -∠S2 > 0º
Forward or Offset Reverse resistive reach Vph - Iph.R’LP Iph.Zreplica ∠S1 -∠S2 < 0º
Reverse Resistive reach Vph + Iph.RLP -Iph.Zreplica ∠S1 -∠S2 > 0º
Reverse Reverse resistive reach Vph + Iph.R’LP -Iph.Zreplica ∠S1 -∠S2 < 0º
The Resistive Impedance Reach side of the earth zone is controlled by the Resistive Reach setting applied (Rx Gnd
Resistive). This defines the fault arc resistance that can be detected for a single phase-earth fault. For such a fault,
the fault resistance appears in the total fault loop (out and return loop), in which the line impedance is Z1 x (1 +
kZN), if IN @ Iph.
172 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Most injection test sets plot impedance characteristics in positive sequence terms, so that the right-hand intercept
appears less than the setting applied (Rn Gnd Resistive /(1+ kZN)). The left hand side is set by the Rn Gnd Res Rev
setting and acts similarly.
Note:
The resistive reach lines of earth-fault Quadrilateral characteristics are not affected by the type of tilting used by the reactive
lines (fixed or dynamic), nor by the angle values.
Note:
*This is also the reverse impedance reach, if the Series Comp. setting is Enabled.
If fixed tilting is selected, then he current input quantity for S2 is Iph in all cases.
The positive sequence reach settings used for the Earth-Fault Quadrilateral characteristics are summarised in the
table below:
Reverse Resistive
Zone Type Impedance Reach Z Reverse Impedance Reach Z’ Resistive Reach R
Reach R’
1 Ph-Earth Forward Z1 Gnd. Reach * (1 + kZN) Z1 R1 Gnd Resistive 0.25 R
Rev Reach
1 Ph-Earth Z1 Gnd. Reach * (1 + kZN) Z1’ Gnd Rev Rch * (1 + kZN) R1 Gnd Resistive R1’ Ph Res. Rev
Series Comp.
2 Ph-Earth Forward Z2 Gnd. Reach * (1 + kZN) Z2 R2 Gnd Resistive 0.25 R
2 Ph-Earth Offset Z2 Gnd. Reach * (1 + kZN) Z2’ Gnd Rev Rch * (1 + kZN) R2 Gnd Resistive R2’ Ph Res. Rev
P54-TM-EN-1.1 173
Chapter 8 - Distance Protection P54
Reverse Resistive
Zone Type Impedance Reach Z Reverse Impedance Reach Z’ Resistive Reach R
Reach R’
3 Ph-Earth Forward Z3 Gnd. Reach * (1 + kZN) Z3 R3 Gnd Resistive 0.25 R
3 Ph-Earth Reverse Z3 Gnd. Reach * (1 + kZN) Z3 R3 Gnd Resistive 0.25 R
3 Ph-Earth Offset Z3 Gnd. Reach * (1 + kZN) Z3’ Gnd Rev Rch * (1 + kZN) R3 Gnd Resistive R3’ Ph Res. Rev
4 Ph-Earth Reverse Z4 Gnd. Reach * (1 + kZN) Z4 R4 Gnd Resistive 0.25 R
P Ph-Earth Forward ZP Gnd. Reach * (1 + kZN) ZP RP Gnd Resistive 0.25 R
P Ph-Earth Reverse ZP Gnd. Reach * (1 + kZN) ZP RP Gnd Resistive 0.25 R
P Ph-Earth Offset ZQ Gnd. Reach * (1 + kZN) ZP’ Gnd Rev Rch * (1 + kZN) RP Gnd Resistive RP’ Gnd Res. Rev
Q Ph-Earth Forward ZQ Gnd. Reach * (1 + kZN) ZQ RQ Gnd Resistive 0.25 R
Q Ph-Earth Reverse ZQ Gnd. Reach * (1 + kZN) ZQ RQ Gnd Resistive 0.25 R
Q Ph-Earth Offset ZQ Gnd. Reach * (1 + kZN) ZQ’ Gnd Rev Rch * (1 + kZN) RQ Gnd Resistive RQ’ Gnd Res. Rev
1e Ph-Earth Forward Z1e Gnd. Reach * (1 + kZN) Z1e R1e Gnd Resistive 0.25 R
Rev Reach
1e Ph-Earth Z1e Gnd. Reach * (1 + kZN) Z1e’ Gnd Rev Rch * (1 + kZN) R1e Gnd Resistive R1e’ Ph Res. Rev
Series Comp.
R Ph-Earth Forward ZR Gnd. Reach * (1 + kZN) ZR RR Gnd Resistive 0.25 R
R Ph-Earth Reverse ZR Gnd. Reach * (1 + kZN) ZR RR Gnd Resistive 0.25 R
R Ph-Earth Offset ZR Gnd. Reach * (1 + kZN) ZR’ Gnd Rev Rch * (1 + kZN) RR Gnd Resistive RR’ Gnd Res. Rev
S Ph-Earth Forward ZS Gnd. Reach * (1 + kZN) ZS RS Gnd Resistive 0.25 R
S Ph-Earth Reverse ZS Gnd. Reach * (1 + kZN) ZS RS Gnd Resistive 0.25 R
S Ph-Earth Offset ZS Gnd. Reach * (1 + kZN) ZS’ Gnd Rev Rch * (1 + kZN) RS Gnd Resistive RS’ Gnd Res. Rev
where kZN = (Z0 - Z1) / 3Z1 and is defined by two settings: kZN Res Comp and KZN Res Angle.
174 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
+jX
V IZ
Z V I
+R
V05007
Referenced to the fault current I, the angle of tilt is equal to the setting σ. A negative angle sets a downward tilt
and a positive angle sets an upward tilt. Operation can occur when the operating signal lags the polarizing signal.
A negative angle sets a downward tilt and a positive angle sets an upward tilt.
For all V/I vectors below the Impedance Reach line, the following condition is true:
Ð (V/I - Z) £ σ
or
Ð (V - I.Z) £ Ð I.Ð σ
The resultant two signals provided to the comparator are:
S1 = V - I.Z
S2 = I.Ð σ
Impedance on the tripping side of the Impedance Reach line is detected when the angle between S1 and S2 is less
than 0°.
P54-TM-EN-1.1 175
Chapter 8 - Distance Protection P54
following diagram:
+jX I
II
+R
Z’ V/I
Z’
-3°
III
V / I - Z’ IV
V05014
Figure 84: Reverse impedance reach line construction
176 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
IF Xc=70%Comp. Z1 reach
Zs CT Z
Z
Xc=70% Z IF
VT Fault
Fault
Xc
Impedance
E seen by relay
V05015
P54-TM-EN-1.1 177
Chapter 8 - Distance Protection P54
Z3 reach
Source 1
Ir Xc=0.7*4 Z=4
Zs1 CT Z=1 Z=4 Z=1
Ir
Fault 1
VT
E Z=4
Xc Z ~ 1-Xc*(1+13)
Impedance
seen by
Fault 1 relay
V05016
Figure 86: Zone 3 reverse impedance reach set as directional forward or offset
Xc=0.7*4 Ir Source 1
Fault 1
VT Ir
E
Z=4
Z4 reach
V05017
Typical reverse reach setting is to cover at least to SS1. Therefore, Zone 4 = 1.2 * (13+1) * 4 = 67.2
Consider the impact of fault 1, reverse Z4 reach setting = 1.2 * (13+1) * (4*0.7) = 47
Therefore, reverse reach must be approximately 100% of the Zone 4 reach.
With these examples, it is possible to conclude reasonable settings for the reverse impedance reach lines Z’ (Zn' Ph
Rev Reach and Zn' Gnd Rev Rch) for series compensated lines and the associated adjacent lines.
178 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
IED
Dist V I Half of the loop
Bus
A
ZF
R LP
B
Network Line
V02725
The setting Rx Ph. Resistive defines the complete loop resistive reach RLP of the Distance Protection.
Since a phase-to-phase distance element measures half of the loop, the right-hand resistive reach R, of the
characteristic is equal to half of the setting value.
R = ½ Rx Ph. Resistive
+jX
V/ I V/ I-R
R ÐZ +R
V05009
For all V/I vectors which are on the left side of the right blinder the following condition is true:
Ð (V/I - R) £ Z
or
P54-TM-EN-1.1 179
Chapter 8 - Distance Protection P54
Ð (V - I.R) £ Ð I. Z
The two signals provided to the comparator are:
S1 = V - I.R
S2 = I.Z
The impedance on the left side of the right hand resistive line is detected when the angle between S1 and S2 is
greater than 0°.
+jX
ÐZ
V/ I
V/ I-R +R
R
V05010
For an offset zone, R’ is the settable reverse resistive reach (=½*Rx’ Ph Res. Rev.). . For a directional zone, R’ is fixed
at 25% of the Resistive Reach (=½*Rx Ph Res. Rev.), acting in the opposite direction.
The two signals provided to the comparator are:
S1 = V - I.R
S2 = I.Z
The impedance on the right side of the left hand resistive line is detected when the angle between S1 and S2 is less
than 0°.
180 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
+jX
V/ I
R R +R
Z
V05011 3
The comparators used for the Phase-Fault Quadrilateral zones are summarised in the following table:
Condition
Zone Line S1 S2
(ÐS1 - ÐS2)
Forward/Offset Impedance Reach Line V – I.Z I.Ð σº <0º
Forward/Offset Reverse Impedance Reach Line V – I.Z’ I.Ð 3º >0º
Forward/Offset Resistive Reach Line V – I.R I.Z >0º
Forward/Offset Reverse Resistive Reach Line V – I.R’ I.Z <0º
Reverse Impedance Reach Line V + I.Z -I.Ð σº <0º
Reverse Reverse Impedance Reach Line V + I.Z’ -I.Ð 3º >0º
Reverse Resistive Reach Line V + I.R -I.Z >0º
Reverse Reverse Resistive Reach Line V + I.R’ -I.Z <0º
The positive sequence reach settings used for the Phase-Fault Quadrilateral characteristics are summarised in the
following table:
Reverse Impedance Reverse Resistive
Zone Type Impedance Reach Z Resistive Reach R
Reach Z’ Reach R’
1 Ph-Ph Forward Z1 Ph. Reach Z1 ½*R1 Ph. Resistive 0.25 R
1 Ph-Ph Reverse Z1 Ph. Reach Z1 ½*R1 Ph. Resistive 0.25 R
Rev Reach Series
1 Ph-Ph Z1 Ph. Reach Z1’ Ph Rev Reach ½*R1 Ph. Resistive ½*R1’ Ph Res. Rev.
Comp.
1e Ph-Ph Forward Z1e Ph. Reach Z1e ½*R1e Ph. Resistive 0.25 R
1e Ph-Ph Reverse Z1e Ph. Reach Z1e ½*R1e Ph. Resistive 0.25 R
Rev Reach Series
1e Ph-Ph Z1e Ph. Reach Z1e’ Ph Rev Reach ½*R1e Ph. Resistive ½*R1e’ Ph Res. Rev.
Comp.
2 Ph-Ph Forward Z2 Ph. Reach Z2 ½*R2 Ph. Resistive 0.25 R
2 Ph-Ph Reverse Z2 Ph. Reach Z2 ½*R2 Ph. Resistive 0.25 R
2 Ph-Ph Offset* Z2 Ph. Reach Z2’ Ph Rev Reach ½*R2 Ph. Resistive ½*R2’ Ph Res. Rev.
3 Ph-Ph Forward Z3 Ph. Reach Z3 ½*R3 Ph. Resistive 0.25 R
P54-TM-EN-1.1 181
Chapter 8 - Distance Protection P54
Note:
*This is also the reverse impedance reach, if the Series Comp. setting is Enabled.
182 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
P54-TM-EN-1.1 183
Chapter 8 - Distance Protection P54
● For directional zones, the directionality element must agree with the tripping zone. Zones 1, 2, and 4 are
always directional whereas other zones are only directional if set as directional. In directional zones the
directionality element must agree with the tripping zone. For example, Zone 1 is a Forward Directional zone
and must not trip for Reverse faults. Therefore a Zone 1 trip is only allowed if the directionality element
issues a Forward decision. Zone 4 is reverse-looking so needs a Reverse decision by the directionality
element.
● The set time delay for the measuring zone must expire, with the measured fault impedance remaining
inside the zone characteristic for the duration of the delay time. Typically, Zone 1 has no time delay
(instantaneous), whereas all other zones have time delays.
● Where channel-aided distance schemes are used, the time delay tZ2 for overreaching Zone 2 may be
bypassed for some of the schemes.
Note:
Any existing trip decision is not reset under this condition. After the first cycle following a selection, the phase selector is only
permitted to change to a selection involving additional phases.
On double phase-to-earth faults, only the phase-to-phase elements are enabled. This is because they are
generally more accurate under these conditions than earth fault elements. A biased neutral current level detector
operates to indicate the involvement of earth in the fault.
184 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
AB
BC
CA
V02702
Figure 92: Phase to phase current changes for C phase-to-ground (CN) fault
As default, phase selection is made when any superimposed current exceeds 5% of nominal current (0.05 In).
Any superimposed current greater than 80% of the largest superimposed current is included in the phase selection
logic.
For applications which might experience high levels of sub-synchronous currents, the phase selector automatically
raises the threshold from the default 5% of In, in order to prevent sporadic operation whilst maintaining high
sensitivity to faults.
Note:
If you test the distance elements using test sets, which do not provide a dynamic model to generate true fault delta
conditions, you need to set Static Test Mode to Enabled in the COMMISSION TESTS column. This disables phase selector
control and forces the distance protection to use a conventional (non-delta) directional line.
The phase selector picks up on fault detection, and enables Distance protection on all elements which have been
selected by the pick-up. These elements are enabled for 2 cycles, and normally this will result in tripping. On double
ground-to-phase faults, only appropriate phase elements are enabled. This is because they are generally more
accurate than ground elements under these conditions. If, however, tripping is not initiated within the 2 cycles, for
the following 5 cycles all Distance elements (including all phase-earth elements) are enabled. During these five
cycles, this could lead to incorrect operation of earth-fault elements in case of an out-of-zone double-phase-earth
fault. This is because one of the phase-earth elements could demonstrate significant overreach, which may result
in maloperation. To help prevent this, a Biased Neutral Current Detector and a fault-type supervision are
incorporated.
P54-TM-EN-1.1 185
Chapter 8 - Distance Protection P54
I N I A I B IC
Neutral current
K 10%
The neutral current detector uses the maximum of the three phase current differences as a biasing value. The
slope of the characteristic is fixed at 10%.
Biasing the neutral current detector assures that the detector is sensitive enough to operate for any single-phase
fault, without the risk of picking up on neutral spill current during phase-to-phase faults. The neutral spill current
might arise from mismatched current transformers or current transformer saturation. The biasing also ensures
that the earth fault distance elements are generally disabled for double-phase-to-earth faults with high resistance
in the neutral. Such faults can occur in resistively earthed systems, or in solidly earthed systems due to high arc
resistance. Given that these conditions are very similar to pure phase-to-phase faults, the earth fault distance
elements can exhibit high measuring errors which the use of the neutral current detector overcomes.
There is additional supervision to inhibit the phase to ground loops in case of double phase to ground faults. This
technique checks the absolute angle between the zero-sequence current and the negative sequence current. It
allows the phase to ground element to operate only if the absolute angle between the negative sequence current
and the zero-sequence current is less than 50°. This supervision is only used in certain scenarios when the relay is
in the 5 cycle period state.
186 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
If Delta directional is used in conjunction with aided schemes, this Delta algorithm can also provide additional
protection in the form of directional comparison protection.
P54-TM-EN-1.1 187
Chapter 8 - Distance Protection P54
IF1
V1
IF/3
IF2
V2
voltage
generator
represents
voltage change
IF0 at fault location
V0
E02704
Figure 94: Superimposed sequence networks connection for an internal A-N fault
The fault is shown near to the busbar at end R of the line, and results in a connection of the positive, negative, and
zero sequence networks in series. The delta diagram shows that any fault is a generator of D, connected at the
location of the fault inception. The characteristics of the deltas are:
● The DI generated by the fault is equal to the total fault arc current.
● The DI splits into parallel paths, with part contribution from source “S” and part from remote end “R” of the
line. Therefore each element measures a lower proportion of DI.
● The DV generated by the fault is equal to the fault arc voltage minus the pre-fault voltage, so it is in anti-
phase with the pre-fault voltage.
● The DV measured by the protection is the voltage drop across the source impedance behind the protection
location. This is generally smaller than the DV measured at the fault location, because the voltage collapse
is smaller nearer to the source than at the fault.
● For fault detection, the measured DI and DV associated with the fault must be greater than the Dir I Fwd
and Dir V Fwd settings respectively.
188 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Note:
If Delta directional aided scheme is not used, Distance zone directionalizing uses fixed operating thresholds: DV=0.5V and
DI=5%In. If the fault DV is below the setting of 0.5V, a conventional distance line ensures correct forward/reverse polarizing.
For Delta directional aided schemes, sufficient DV must be present for tripping to occur.
The delta directional element will produce a forward decision when the angle between the delta volts and delta
current shifted by the Dir. Char Angle setting is greater than 90°. The Dir. Char Angle setting is the characteristic
angle of the source impedance, Zs.
Forward
Reverse
DI
Zs
RCA
To facilitate testing of the distance elements using test sets, which do not provide a dynamic model to generate
true fault delta conditions, set the Static Test setting in the COMMISSION TESTS column to Enabled. This disables
phase selector control and forces the protection to use a conventional (non-delta) directional line.
P54-TM-EN-1.1 189
Chapter 8 - Distance Protection P54
Note:
Some test sets with dynamic models have the facility to include a DC offset. We strongly recommend the use of the DC offset
because the waveform created with no DC offset sometimes creates a current step that is not realistic and this could cause a
problem in the delta algorithm.
Note:
Distance zones are directionalized by a Delta Directional decision. The characteristic angle for this decision is set with the
Delta Directional configuration, in the DISTANCE SETUP column. The default setting is 60°.
190 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
P54-TM-EN-1.1 191
Chapter 8 - Distance Protection P54
By setting CVT Filters to Passive, the protection can trip at sub-cycle speeds, unless the actual SIR is above that
which is set. If the SIR is estimated to be higher than the setting, the instantaneous operating time is increased by
about a quarter of a power frequency cycle. The protection estimates the SIR as the ratio of nominal rated voltage
Vn to the size of the comparator vector IZ (in volts):
SIR = Vn/IZ
where:
● Vn = Nominal phase to neutral voltage
● I = Fault current
● Z = Reach setting for the zone concerned
Therefore, for slower operation, I needs to be low, as restricted by a relatively weak infeed and Z needs to be small,
as for a short line.
Sub-cycle tripping is maintained for lower SIRs, up to a ratio of 2. The instantaneous operating time is increased by
about a quarter of a power frequency cycle at higher SIRs.
Transients caused by voltage dips, however severe, do not affect the protection’s directional measurement
because it uses voltage memory.
192 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
jX
Operate area
Operate area
V00645
● Z denote values for the Load/B Impedance settings. These set the radius of the phase and earth under-
impedance circle.
● ß denote values for the Load/B Angle settings. These set the angle of the two blinder boundary lines for
phase and earth - the gradient of the rise or fall with respect to the resistive axis.
The protection can allow the load blinder to be bypassed any time that the measured voltage for the phase in
question falls below an undervoltage setting. Under such circumstances, the low voltage could not be attributed to
normal voltage excursion tolerances on load. A fault must be present on the phase in question, so it is acceptable
to override the blinder action and allow the Distance protection to trip for an in-zone measurement. The
advantage of bypassing the load blinders is that the resistive coverage for faults near to the protection location
can be higher.
To use the load blinders you must set the Load Blinders setting to Enabled. You then set appropriate values for
the blinder impedance using the Z< Blind Imp Ph and Z< Blind Imp Gnd settings, the b values using the Load/B
Angle Ph and Load/B Angle Gnd settings, and the undervoltage threshold using the Load Blinder V< setting.
P54-TM-EN-1.1 193
Chapter 8 - Distance Protection P54
Note:
Load blinding can be applied for phase and earth characteristics. Residual compensation is not applied. Phase characteristics
use phase-to-phase voltage and phase-to-phase current. Earth fault characteristics use phase-to-neutral voltage and phase-
to-neutral current.
194 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
120
100
80
60
40
20
0
11kV 22kV 33kV 65kV 110kV
Residual fault current—compensated neutral
Capacitive fault current—isolated neutral
V00756
Figure 97: Current level (amps) at which transient faults are self-extinguishing
The following figure depicts a simple network earthed through a Petersen Coil reactance. It can be shown that if
the reactor is correctly tuned, theoretically no earth fault current will flow.
P54-TM-EN-1.1 195
Chapter 8 - Distance Protection P54
Source
-I B -I C
-IC A IL
V AN V AB V ac
V AN I f I B I C
jX L
jX L jX C jX C -I B
V AN
(=I L) 0 if I B IC (=-I B) (=-I C)
If jX L
VAC VAB
V00631
Consider a radial distribution system earthed using a Petersen Coil with a phase to earth fault on phase C, shown
in the figure below:
I A1
IB1
I R1
-jXC1
I H1
IL IA2
IB2
jXL IR2
-jXC2
IH 2
I A3
IB3
I C3 = I F
I R3
-jXC3
IF
I H3 IH1 + I H2
I L = I F + I H1 + IH2 + I H3
V00632
Assuming that no resistance is present in XL or XC, the resulting phasor diagrams will be as shown in the figure
below:
196 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
IL
I H3
IL A 3V0
IH2 -IH1
IR1 = IH1
Ib1
IH1 -IH2
C B
Vres = -3Vo Vres = -3Vo
Figure 100: Phasors for a phase C earth fault in a Petersen Coil earthed system
Using a core-balance current transformer (CBCT), the current imbalances on the healthy feeders can be measured.
They correspond to simple vector addition of IA1 and IB1, IA2 and IB2, IA3 and IB3, and they lag the residual voltage
by exactly 90º.
The magnitude of the residual current IR1 is equal to three times the steady-state charging current per phase. On
the faulted feeder, the residual current is equal to IL - IH1 - IH2 (C). This is shown in the zero sequence network
shown in the following figure:
I ROF IOF
Faulty feeder
I ROH
I ROF = Residual current on faulted feeder
I ROH = Residual current on healthy feeder
IROH Healthy feeders
IL I OF = I L – IH1 – I H2 – IH3
I ROF = IH3 + I OF
so:
IH 3 IH 2 IH 1 I ROF = IL – IH1 – I H2
3XL -V0
XCO
V00640
In practical cases, however, resistance is present, resulting in the following phasor diagrams:
P54-TM-EN-1.1 197
Chapter 8 - Distance Protection P54
Resistive component
(IAH1 + I H2 + I H3)’ in feeder
Resistive component
A
in grounding coil I’ 3V0
L
C B
Restrain IL
IR 3
I R3 = I F + IH3 = IL - IH1- IH12
Restrain
Figure 102: Phase C earth fault in Petersen Coil earthed system: practical case with resistance present
If the residual voltage is used as the polarising voltage, the residual current is phase shifted by an angle less than
90° on the faulted feeder, and greater than 90° on the healthy feeders. With an RCA of 0°, the healthy feeder
residual current will fall in the ‘restrain’ area of the characteristic while the faulted feeder residual current falls in
the ‘operate’ area.
Often, a resistance is deliberately inserted in parallel with the Petersen Coil to ensure a measurable earth fault
current and increase the angular difference between the residual signals to reinforce the directional decision.
Directionality is usually implemented using a Wattmetric function, or a transient earth fault detection function
(TEFD), rather than a simple directional function, since they are more sensitive. For further information about TEFD,
refer to Transient Earth Fault Detection in the Current Protection Functions chapter.
198 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
P54-TM-EN-1.1 199
Chapter 8 - Distance Protection P54
200 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
VA VA=Ground
Ground
VC VB VC VB
All phases healthy Phase A ground fault
V02784
Therefore, we can establish an earth fault by seeing if the neutral voltage VN exceeds a settable threshold VN>
Voltage Set, and checking whether the phase-phase voltages are still balanced.
0.8(max. Vph-ph) < (min. Vph-ph)
Neutral displacement is established by comparing the neutral voltage VN with a threshold set by the setting, VN>
Voltage Set
I N I A I B IC
Neutral current
K 10%
P54-TM-EN-1.1 201
Chapter 8 - Distance Protection P54
VN
VN> Start
VN> Voltage Set
1P Time Delay
1P Mode
VAB
Voltage equilibrium
VBC
analysis
& 342
Mode
Pickup IS/Comp EF
VCA Selector
Detection of the first fault primes the detection of a second earth fault and blocks tripping of phase to phase
elements for zones 1,2,3,4 (zones P and Q do not get blocked). It also creates a DDB signal indicating a single-
phase earth fault (IS/Comp EF). Typically, with zones P and Q, the external starting zones will be used to detect if a
second earth loop converges into the impedance characteristic.
The VN> Start signal is established by comparing the neutral voltage VN with a threshold set by the setting VN>
Voltage Set. This signal is gated with another signal indicating whether the phase voltage triangle is balanced or
not and then fed into the mode selector. If the voltage triangle is balanced and there is an overvoltage condition,
then a single-phase fault is indicated.
The mode selector decides whether the single phase-to-earth fault is determined by VN> only, IN> only, VN> or
IN>, or VN> and IN>. The mode is set by the setting 1P Mode in the DISTANCE SETUP column. The single phase-to-
earth fault signal (IS/Comp EF) is then produced after a time delay set by 1P Time Delay.
202 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
VAB
VAB
VBC
VBC
1
VCA
VCA & V< Start
0.9*Vnom
890
All poles dead
First Fault
342
IS/Comp EF SD
Q Block ZxPh, x = 1 to 4
R
Healthy Condition
VN> Start
&
V< Start
1
& Second Fault
Evolving 3-phase fault
1326
ZP AB Comparator
1327
ZP BC Comparator &
1328
ZP CA Comparator
1974
ZQ AB Comparator
1975
ZQ BC Comparator &
1976
ZQ CA Comparator
Second Fault
VN> Start
V< Start &
1335
IN> Bias
V02779
A second fault is detected if additionally there is a neutral overvoltage, imbalance in the voltage triangle (phase
undervoltage) and there is enough neutral overcurrent (a minimum of 50 mA for correct device operation).
P54-TM-EN-1.1 203
Chapter 8 - Distance Protection P54
Note:
The Phase prio. 2pG setting is visible only when the Dist.Earth Mode setting is set to Is/Comp Earthing and the
BasicScheme Mode setting is set to Alternative.
204 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Second Fault
1 PrioTripEna AN
1323
ZP AN Comparator &
1
1971
ZQ AN Comparator
1 PrioTripEna BN
1324
ZP BN Comparator &
Phase Priority
1 Selector
1972
ZQ BN Comparator
1 PrioTripEna CN
1325
ZP CN Comparator &
1
1973
ZQ CN Comparator
Phase prio. 2pG
V02780
Note:
The phase preference priority selector requires that at least two of the phase to ground loops, as indicated in the table above,
are in Zone P or Q.
P54-TM-EN-1.1 205
Chapter 8 - Distance Protection P54
Zone1 Tripping
Ground only
1
Phase And Ground &
384
Block Zone 1 Gnd
960 &
Zone1 AN Element 1
1305 &
Z1 AN Comparator
& 1 & Zone 1 BN
PrioTripEna BN
961 &
Zone1 BN Element 1
1306 &
Z1 BN Comparator
& 1 & Zone 1 CN
PrioTripEna CN
744
1 Zone 1 N Start
962 &
Zone1 CN Element 1 Zone 1 Start Gnd
Zone1 Tripping
Phase only 1 Zone 1 Start Phs
1
Phase And Ground
385
Block Zone 1 Phs
1 &
Block Zones 1 - 4
963 & Zone 1 AB
Zone1 AB Element
Zone 1 AN 741
1 Zone 1 A Start
Zone 1 BN 742
1 Zone 1 B Start
Zone 1 CN 743
1 Zone 1 C Start
V02798
206 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Standard Mode
t 1985
& Z1 P time elapse
Zone 1 Start Phs 0
Alternative Mode
t 1985
Z1 P time elapse
0
V02782
Note:
Although the diagram above shows zone 1 logic only, the logic for all other zones follows the same principals.
Zone 1 AN
612
& Zone 1 N Trip
Zone 1 BN 1
608
Zone 1 CN 1 Zone 1 Trip
1985
Z1 P time elapse
Zone 1 AB
&
Zone 1 BC 1
Zone 1 CA
1984
Z1 G time elapse
& 609
Zone 1 AN 1 Zone 1 A Trip
1985
Z1 P time elapse
Zone 1 AB &
1
Zone 1 CA
1984
Z1 G time elapse
& 610
Zone 1 BN 1 Zone 1 B Trip
1985
Z1 P time elapse
Zone 1 AB &
1
Zone 1 BC
Z1 G time elapse
& 611
Zone 1 CN 1 Zone 1 C Trip
1985
Z1 P time elapse
Zone 1 BC &
1
Zone 1 CA
V02783
P54-TM-EN-1.1 207
Chapter 8 - Distance Protection P54
Note:
Although the diagram above shows zone 1 logic only, the logic for all other zones follows the same principals.
208 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
6 APPLICATION NOTES
Zone Reach
Z
Tilt Angle
Time
Delay
t
Line
Angle
Resistive
Reach
R
E02746
The following figure shows the basic settings needed to configure a forward-looking mho zone, assuming that the
load blinder is enabled.
P54-TM-EN-1.1 209
Chapter 8 - Distance Protection P54
Variable mho
Zone Reach Z
expansion by
polarizing ratio
Time
Delay
t
Load
Line Blinder
Angle
Angle β
Blinder Radius
E02747
210 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Zone 3 may also be set as a reverse directional zone. The setting chosen for Zone 3, if used, depends on its
application. Typical applications include its use as an additional time delayed zone or as a reverse back-up
protection zone for busbars and transformers.
Programmable zone elements can be set with the same options as Zone 3 (Forward, Reverse or Offset). A
programmable zone can be used as an additional forward protection zone if custom and practice requires using
more than three forward zones of Distance protection.
The Zone 4 elements may also provide back-up protection for the local busbar. Where Zone 4 is used to provide
reverse directional decisions for Blocking or Permissive Overreach schemes, Zone 4 must reach further behind the
protection than Zone 2 for the remote end protection. In such cases the reverse reach should be:
● Mho: Z4 > Remote Zone 2 reach x 120%
● Quadrilateral: Z4 > (Remote Zone 2 reach x 120%) minus the protected line impedance
Note:
In the case of the Mho, the line impedance is not subtracted. This ensures that whatever the amount of dynamic expansion of
the circle, the reverse looking zone always detects all solid and resistive faults capable of detection by Zone 2 at the remote
line end.
Note:
Because the fault current for an earth fault may be limited by tower footing resistance, high soil resistivity, and weak
infeeding; any arcing resistance is often higher than for a corresponding phase fault at the same location. It maybe necessary
to set the Rn Gnd Resistive settings to be higher than the Rn Ph Resistive setting. A setting of Rn Gnd Resistive three times that
of Rn Ph Resistive is not uncommon.
P54-TM-EN-1.1 211
Chapter 8 - Distance Protection P54
Long lines
In the case of medium and long line applications where quadrilateral distance earth-fault characteristics are used,
Zn Dynamic Tilt should be enabled and the starting tilt angle should be -3° (as per the default settings). This tilt
compensates for possible current and voltage transformer and line data errors.
For high resistive faults during power exporting, the underreaching Zone 1 is only allowed to tilt down by the angle
difference between the faulted phase and negative sequence current Ð(Iph-I2) starting from the –3° set angle. This
ensures stability of Zone 1 for high resistance faults beyond the Zone 1 reach even during heavy load conditions
(high load angle between two voltage sources) and sufficient sensitivity for high resistance internal faults. The tilt
angle for all other zones (that are by nature overreaching zones) remain at -3°.
In the case of power importing, Zone 1 remains at –3° while all other zones are allowed to tilt up by the Ð(Iph-I2)
angle difference, starting from –3°. This increases the Zone 2 and Zone 4 resistive reaches and secures correct
operation in permissive overreach and blocking type schemes.
Short lines
For very short lines, typically below 10Miles (16km), the ratio of resistive to reactance reach setting (R/X) could
easily exceed 10. For such applications the geometrical shape of the quadrilateral characteristic could be such
that the top reactance line is close or even crosses the resistive axis as presented in the following figure:
jX
High resistive internal fault
Total dynamic tilt starting from zero
Z1
-3 ° Iph -I 2
Line angle R
Iph -I 2
V02748
In the case of high resistance external faults on a short line, particularly under heavy power exporting conditions,
Zone 1 remains stable due to dynamic downwards tilting of the impedance reach line. However, the detection of
high resistance internal faults especially towards the end of the line needs consideration. In such applications you
can choose to detect high resistance faults using highly sensitive Aided Directional Earth Fault scheme, or to clear
the fault with Distance ground protection. For the Distance to operate, it is necessary to eliminate over-tilting for
internal faults by reducing the initial -3° tilting angle to zero so that the overall impedance reach line tilt is equal to
Ð(Iph-I2) angle only.
As shown in the previous figure, the internal resistive fault then falls in the Zone 1 operating characteristic.
However, for short lines the load angle is relatively low when compared to long transmission lines for the same
transfer capacity and therefore the impedance reach line dynamic tilting may be moderate. Therefore it may be
necessary to reduce the Zone 1 reach to guarantee Zone 1 stability. This is particularly recommended if the
distance protection is operating in an aided scheme. To summarise, for very short lines with large R/X setting
ratios, we recommend settiing the initial tilt angle to zero and the Zone 1 reach to 70-75% of the line impedance.
The above discussion assumes homogenous networks where the angle of the negative sequence current derived
at relaying point is very close to the total fault current angle. If the network is non-homogenous, there is a
difference in angle that causes inaccurate dynamic tilting. Therefore in such networks either quadrilateral with
fixed tilt angle or mho characteristic should be considered to avoid Zone 1 overreach.
212 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Note:
You can also use Delta Directional schemes to detect high resistance faults.
Exporting End
To secure stability, the tilt angle of Zone 1 at the exporting end has to be set negative and above the maximum
angle difference between sources feeding the resistive faults. This data should be known from load flow study, but
if unavailable, the minimum recommended setting would be the angle difference between voltage and current
measured at local end during the heaviest load condition coupled with reduced Zone 1 reach of 70-75% of the line
impedance.
Note:
With a sharp fixed tilt angle, the effective resistive coverage would be significantly reduced. Therefore for short lines, dynamic
tilting (with variable tilt angle depending on fault resistance and location) is preferred. For all other overreaching zones, set the
tilting angle to zero.
Importing End
Set zone 1 tilt angle to zero and for all other zones the typical setting should be positive and between +5° and +10°.
Note:
The setting accuracy for overreaching zones is not crucial because it does not pose a risk for distance maloperation. The
purpose is to boost Zone 2 and Zone 4 reach and improve the performance of Aided Schemes.
Note:
A negative angle is used to set a downwards tilt gradient, and a positive angle to tilt upwards.
P54-TM-EN-1.1 213
Chapter 8 - Distance Protection P54
Note:
Mho characteristics have an inherent tendency to avoid unwanted overreaching, making them very desirable for long line
protection.
214 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
The reverse fault detectors must be set more sensitively, as they are used to invoke the blocking and current
reversal guard elements. We suggest that all reverse detectors are set at 66 to 80% of the setting of the forward
detector, typically:
● Dir. V Rev = Dir. V Fwd x 0.66
● Dir. I Rev = Dir. I Fwd x 0.66
Due to the implementation method, Deltas are present only for 2 cycles on fault inception. If any distance elements
are enabled, these will automatically allow the delta forward or reverse decisions to seal-in, until such time as the
fault is cleared from the system. Therefore as a minimum, some distance zone(s) must be enabled in the DISTANCE
SETUP column as fault detectors. It does not matter what time delay is applied for the zone(s). This can either be
the typical distance delay for that zone or set to ‘Disabled’ in the SCHEME LOGIC column, if no distance tripping is
required. As a minimum, Zone 3 must be enabled, with a reverse reach such as to allow seal-in of Dir. Rev, and a
forward reach to allow seal-in of Dir. Fwd.
The applicable reaches would be:
● Zone 3 Forward: Set at least as long as a conventional Zone 2 (120-150% of the protected line)
● Zone 3 Reverse: Set at least as long as a conventional Zone 4, or supplement by assigning Zone 4 if a large
reverse reach is not preferred for Zone 3.
We generally advise a Mho characteristic in such starter applications, although quadrilaterals are acceptable. As
the Mho starter is likely to have a large radius, we strongly advise applying the Load Blinder.
Note:
When using the Special Applications filter the instantaneous operating time is increased by about a quarter of a power
frequency cycle.
P54-TM-EN-1.1 215
Chapter 8 - Distance Protection P54
Cable applications
Use 20% (0.2) memory. This results in minimum Mho expansion and keeps the protected line section well within the
expanded Mho, thereby ensuring better accuracies and faster operating times for close-up faults. This matches
the guidance previously provided for LFZP123 or LFZR applications for cable feeders
Short lines
For lines shorter than 10miles (16km), or with an SIR higher than 15, use the maximum memory polarization
(setting = 5). This ensures sufficient characteristic expansion to cover fault arc resistance.
216 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
The settings are applicable whether the Distance protection characteristics are set to Mho, or Quadrilateral. If you
choose Quadrilateral however, you will need to consider the Resistive reaches of Quadrilaterals.
For this study, we wish to protect one line of a double 230kV, 100km line between a substation at Green Valley and
a substation at Blue river. There are generating sources at Tiger Bay, 80 km from Green Valley and at Rocky Bay, 60
km from Blue River.
The single-line diagram for the system is shown in the following figure:
100 km
80 km 60 km
IED IED
E02705
P54-TM-EN-1.1 217
Chapter 8 - Distance Protection P54
Therefore set:
kZN Res Comp = 0.79
KZN Res Angle = -6.5°
From this the protection algorithm automatically calculates the required Ohmic reaches.
Alternatively, using the Setting Mode Advanced, the values can be calculated and entered manually as follows:
Required Zone 1 reach = 0.8 x 100 x 0.484Ð79.4° x 0.12 = 4.64Ð79.4° W secondary
218 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
So:
● Set Z1 Ph. Reach and Z1 Gnd. Reach = 4.64 W
● Set Z1 Ph. Angle and Z1 Gnd. Angle = 80°
Alternatively, in Simple setting mode, this reach can be set as a percentage of the protected line. Typically a
figure of at least 120% of the line between Green Valley and Blue River is used.
Alternatively, in Simple setting mode, this reach can be set as a percentage of the protected line.
P54-TM-EN-1.1 219
Chapter 8 - Distance Protection P54
Remote Zone 2 Reach = line impedance of Green Valley to Blue River + 50% line impedance from
Green valley to Tiger Bay
= (100 + 40) x 0.484Ð79.4° x 0.12
= 8.13Ð79.4° W secondary
Zone 4 Reach ³ (8.13Ð79.4° x 120%) - 5.81Ð79.4°
= 3.95Ð79.4° W secondary
This is the minimum Zone 4 Reach setting, so:
● Set Z4 Ph. Reach and Z4 Gnd. Reach = 3.96 W
● Set Z4 Ph. Angle and Z4 Gnd. Angle = 80°
Phase-Fault Elements
Ideally, the Resistive reach should be set greater than the maximum fault arc resistance for a phase-phase fault
(Ra), calculated in terms of the minimum expected phase-phase fault current, the maximum phase conductor
separation, according to the formula developed by (van) Warrington as:
Ra = (28710 x L)/If x 1.4
where:
● If = Minimum expected phase-phase fault current (A)
● L = Maximum phase conductor separation (m)
Typical figures for Ra are given, for different values of minimum expected phase fault currents, in the following
table:
220 P54-TM-EN-1.1
P54 Chapter 8 - Distance Protection
Note:
For circuits with infeed from more than one terminal, the fault resistance will appear greater. This is because the protection
cannot measure the current contribution from a remote terminal. The apparent fault resistance increase could be between 2
to 8 times the calculated resistance. For this reason, we recommended setting the zone Resistive reaches to 4 times the
calculated arc resistance.
In this example, the minimum phase fault level is 1000 MVA. This is equivalent to an effective short-circuit fault
feeding impedance of:
Earth-Fault Elements
Fault resistance would comprise arc-resistance and tower footing resistance. A typical resistive reach coverage
setting would be 40 W (primary).
For high resistance earth faults, the situation could arise where no distance elements would operate. In such
cases, supplementary earth fault protection (for example Aided DEF protection) should be applied. If
supplementary earth fault protection is used, large resistive reaches for Earth-Fault Distance protection do not
need to be used so that the Earth-Fault Resistive reach can be set according to the utility practice. In the absence
of specific guidance, a recommendation for setting Zone 1 is:
● Cables: Resistive Reach = 3 x Zone 1 reach
● Overhead lines: Choose Resistive Reach in the range [2.3 - 0.0045] x Line length(km) x Zone 1 Reach
● Lines longer than 400 km: Choose Resistive Reach = 0.5 x Zone 1 Reach
P54-TM-EN-1.1 221
Chapter 8 - Distance Protection P54
A B
Ia Ib
Zat
Zbt
Ic
Zct
Va
Va = Ia Zat + Ib Zbt C Impedance seen by relay A =
Ia
Ia = Ia + Ic
E03524
222 P54-TM-EN-1.1
CHAPTER 9
224 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
1 CHAPTER OVERVIEW
This chapter contains the following sections:
Chapter Overview 225
Introduction 226
Aided Distance Scheme Logic 227
Aided DEF Scheme Logic 252
Aided Delta Scheme Logic 267
DE Teleprotection Schemes 278
Application Notes 280
P54-TM-EN-1.1 225
Chapter 9 - Carrier Aided Schemes P54
2 INTRODUCTION
The provision of communication channels between the terminals of a protected transmission line or distribution
feeder enables unit protection to be applied.
Protection devices located at different terminals can be configured to communicate with one another in order to
implement unit protection schemes. The exchange of simple ON/OFF command signals allows unit protection to
be achieved with Distance Protection schemes (Aided Distance), Directional Earth Fault schemes (Aided DEF) and if
applicable, Delta Directional Comparison Protection schemes (Aided Delta). Schemes where a communication
channel is used to send command signals between line ends are known as Carrier Aided Schemes.
The terms ‘simplex’ and ‘duplex’ are used to describe the type of communication channel used. Simplex
communication, also sometimes referred to as half-duplex, requires only a single communication channel
between line ends. Signals can be sent in both directions but not at the same time. Duplex communication requires
two communication channels between line ends (one in each direction). Duplex communication allows signals to
be sent and received at the same time.
226 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
The underreaching options can be used to implement Carrier Aided Distance schemes. The other options can be
used with any Carrier Aided scheme application.
The following diagram shows how the schemes can be assigned.
P54-TM-EN-1.1 227
Chapter 9 - Carrier Aided Schemes P54
Scheme Function Aided Distance Aided Distance Aided DEF Aided Delta*
*Not P445
V03500
228 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Note:
The PUR schemes are only suitable for Distance protection. Therefore, if a PUR scheme is selected, the option to allocate to
other protection is not available.
Note:
For Aided Scheme 1, PUR, POR and blocking schemes can be achieved with 1 channel or 3 channel signalling for Distance
protection only. Aided DEF or Aided Delta cannot be done with 3 channel signalling.
Caution:
Zone 1,2 and 4 are required to implement the PUR/POR and Blocking Aided Schemes.
In this case, zone 1 and zone 2 should be forward and zone 4 should be reverse.
Therefore, if the relay's Setting Mode is set to Advanced and any Zone direction has
been selected that compromises the Aided Schemes, then the Aided Distance
Schemes should be forced to be disabled by the user.
Note:
This assumes a 20% typical end-zone when Zone 1 is set to 80% of the protected line.
The following are some of the main features and requirements for a permissive under-reaching scheme.
● Only a simplex channel is required.
● Scheme security is high, because the signalling channel is only keyed for faults in the protected line.
● If the circuit breaker at the remote terminal is open, faults in the remote 20% of the line are cleared using
the Zone 2 time delay of the local protection.
● If there is a weak-infeed, or zero-infeed from the remote terminal, (current below the protection sensitivity),
faults in the remote 20% of the line are cleared using the Zone 2 time delay of the local protection.
● If the signalling channel fails, basic distance scheme tripping remains available.
The PUR logic is:
● Send logic: Assert signal if Zone 1 element operates
● Permissive trip logic: Trip if the Zone 2 element picks up AND the Carrier Aided signal is received
P54-TM-EN-1.1 229
Chapter 9 - Carrier Aided Schemes P54
Zone 3
Zone 2
Zone 1
A B
Z
Z
Zone 1
Zone 2
Zone 3
CRx CRx
CTx CTx
& &
Z1 Z1
TZ1 TZ1
Trip A Trip B 1
1
Zp TZp Zp
TZp
Z2 TZ2 Z2
TZ2
Z3 TZ3 Z3
TZ3
Z4 TZ4 Z4
TZ4
E03501
Note:
This assumes a 20% typical end-zone when Zone 1 is set to 80% of the protected line.
230 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
The following are some of the main features and requirements for a POR scheme:
● The scheme requires a duplex signalling channel to prevent possible maloperation if a carrier is keyed for an
external fault. Because the signalling channel can be keyed for faults external to the protected zone, it is
vital that they are only received by, and acted upon by, the intended recipient. A simplex channel cannot
assure this.
● A POR scheme may be more advantageous than a PUR scheme for the protection of short transmission
lines. This is because the resistive coverage of the Zone 2 elements may be greater than that of the Zone 1
elements (in the case of Mho elements)
● Current reversal guard logic prevents healthy-line protection maloperation for high speed current reversals
that can be experienced on double circuit line applications, which can be caused by sequential opening of
circuit breakers.
● If the signalling channel fails, basic distance scheme tripping remains available.
The POR scheme also uses the reverse looking zone 4 as a reverse fault detector. This is used in the current
reversal logic and in the weak infeed echo feature, shown dotted in the figure below:
P54-TM-EN-1.1 231
Chapter 9 - Carrier Aided Schemes P54
Zone 4
Zone 3
Zone 2
Zone 1
Z B
Zone 1
Zone 2
Zone 3
Zone 4
CRx CRx
Zone 4 & & Zone 4
CTx CTx
1 1
LD0V LD0V
& &
& &
Z1 Z1
TZ1 Trip A Trip B
TZ1
1 1
ZP TZP ZP
TZP
Z2 TZ2 TZ2 Z2
Z3 TZ3 TZ3 Z3
Z4 TZ4 TZ4 Z4
Selectable features
E03502
The POR scheme is enhanced by POR Trip Reinforcement, and POR Weak Infeed features.
232 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
This feature is called permissive trip reinforcement. It is designed to ensure that synchronous tripping occurs at all
protected terminals.
CB Open Echo
A feature is provided which enables fast tripping to be maintained along the whole length of the protected line,
even when one terminal is open. This is the CB Open Echo feature and is initiated by a settable time CB Open Echo
Dly (250ms by default) after the Breaker Open optical isolator has been energised. This time delay prevents an
unnecessary open terminal echo due to the delay in drop off of the signal send following a trip. However, there will
be no time delay introduced in echoing the signal when the breaker is already open. This feature is Enabled by
default.
P54-TM-EN-1.1 233
Chapter 9 - Carrier Aided Schemes P54
signals so the permissive signal is lost and not received at the other line end. To overcome this problem, when the
guard is lost and no trip frequency is received, the protection opens a window of time during which the permissive
scheme logic acts as though a trip signal had been received. Two opto-isolated inputs need to be assigned: One is
for Channel Receive; The second is designated Loss of Guard (the inverse function to guard received).
The Loss of Guard logic is described in the table below:
Permissive channel Permissive Alarm
System condition Loss of guard
received trip allowed generated
Healthy Line No No No No
Internal Line Fault Yes Yes Yes No
Yes, during a 150 ms Yes, delayed on pickup by
Unblock No Yes
window 150 ms
Yes, delayed on pickup by
Signalling Anomaly Yes No No
150 ms
The window of time during which the unblocking logic is enabled starts 10ms after the guard signal is lost, and
continues for 150ms. The 10ms delay gives time for the signalling equipment to change frequency, as in normal
operation. For the duration of any alarm condition, Zone 1 extension logic is invoked if the Z1 Ext Scheme setting is
set to operate for channel failure.
t2(C) t2(D)
Fault Fault
A L1 B A L1 B
Strong Weak
source C L2 D source C L2 D
The current reversal guard incorporated in the permissive overreach scheme logic is initiated when the reverse
looking Zone 4 elements operate on a healthy line.
Once the reverse looking Zone 4 elements have operated, the permissive trip logic and signal send logic are
inhibited at substation D. The reset of the current reversal guard timer is initiated when the reverse looking Zone 4
resets. A time delay tReversal Guard is required in case the overreaching trip element at end D operates before
the signal send from the protection at end C has reset. Otherwise this would cause the product at D to overreach.
234 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Permissive tripping for the products at D and C substations is enabled again once the faulted line is isolated and
the current reversal guard time has expired.
The current reversal guard incorporated in the blocking scheme logic is initiated when a blocking element picks-up
to inhibit the channel-aided trip. When the current reverses and the reverse looking Zone 4 elements reset, the
blocking signal is maintained by the timer tReversal Guard. Therefore, the protections in the healthy line are
prevented from overreaching due to the sequential opening of the circuit breakers in the faulted line. After the
faulted line is isolated, the reverse-looking Zone 4 elements at substation C and the forward looking elements at
substation D reset.
Two variants of Blocking scheme are available:
● Blocking 1 (Reversal Guard applied to the Signal Send)
● Blocking 2 (Reversal Guard applied to the Signal Receive)
The two schemes are similar. Both schemes feature current reversal guard signals used in conjunction with reverse
looking Zone 4 elements. In the Blocking 1 scheme, the current reversal guard signal applies to the send signal,
whereas in the Blocking 2 scheme, the current reversal guard signal applies to the receive signal.
The signalling channel is keyed from operation of the reverse-looking Zone 4 elements. If the remote zone 2
element picks up, it operates after the trip delay if no block is received. Listed below are some of the main features
and requirements for a Blocking scheme:
● Blocking schemes require only a simplex communication channel.
● Reverse-looking Zone 4 is used to send a blocking signal to the remote end to prevent unwanted tripping.
● When a simplex channel is used, a blocking scheme can easily be applied to a multi-terminal line provided
that outfeed does not occur for any internal faults.
● The blocking signal is transmitted over a healthy line, and so problems associated with power line carrier
signals failing are avoided.
● Blocking schemes provide similar resistive coverage to the permissive overreach schemes.
● Fast tripping occurs at a strong source line end, for faults along the protected line section, even if there is
weak- or zero- infeed at the other end of the protected line.
● If a line terminal is open, fast tripping still occurs for faults along the whole of the protected line length.
● If the signalling channel fails to send a blocking signal during a fault, fast tripping occurs for faults along the
whole of the protected line, but also for some faults in the next line section.
● If the signalling channel is taken out of service, the protection operates in the conventional basic mode.
● A current reversal guard timer is included in the logic to prevent unwanted tripping on healthy circuits
during current reversal situations on a parallel circuits.
P54-TM-EN-1.1 235
Chapter 9 - Carrier Aided Schemes P54
Zone 4
Zone 3
Zone 2
Zone 1
A Z B
Z
Zone 1
Zone 2
Zone 3
Zone 4
CRx CRx
Fast Z4 Fast Z4
CTx CTx &
&
& &
Z1 Z1
TZ1 Trip B
TZ1
Trip A
1 1
ZP TZP ZP
TZP
Z2 TZ2 TZ2 Z2
Z3 TZ3 TZ3 Z3
Z4 Z4
TZ4 TZ4
Selectable features
E03504
236 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
The Aided 1 Scheme RX signal corresponds to a 'channel-receive' signal for scheme 1. The Aided 1 COS/LGS signal
corresponds to a 'channel out of service' or 'loss of guard' signal ('Loss of guard' is the inverse signal to 'guard
received').
As well as the default mapping, it is possible to map the signals to other inputs if required.
The window during which the unblocking logic is enabled starts 10ms after the guard signal is lost and continues
for 150ms. The 10ms delay gives time for the signalling equipment to change frequency.
Note:
If the Z1 Ext Scheme setting is set to operate for channel failure, the Zone 1 extension logic will be invoked if a channel failure
is detected.
This scheme type also provides Loss of Guard logic as described below.
Permissive Permissive Alarm
System condition Loss of guard
channel received trip allowed generated
Healthy Line No No No No
Internal Line Fault Yes Yes Yes No
Unblock No Yes Yes, during a 150 ms window Yes, delayed on pickup by 150 ms
Signalling Anomaly Yes No No Yes, delayed on pickup by 150 ms
P54-TM-EN-1.1 237
Chapter 9 - Carrier Aided Schemes P54
497
V03538-1 Aid1 Custom Send
496
Aid1 Block send
238 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid. 1 Selection
PUR 3Ch
POR 3Ch
Blocking1 3Ch
Blocking2 3Ch 1
DE Z1e 3Ch
DE Perm.Z1e3Ch
DE BlockZ1e3Ch
Aid 1 Distance
Scheme options (1)
394
Aid. 1 Selection Aid1 InhibitDist
Masking options (2)
960 &
Zone1 AN Element 1
& Signal Send A
1
963
Zone1 AB Element &
1
Zone1 CA Element 1
965
2891 &
Zone 1e AN Elem 1
2894
Zone 1e AB Elem &
1
Zone 1e CA Elem
2896
1
&
1405
984 & & 1
Zone4 AN Element 1 & Aided 1 Send A
tRG
987
Zone4 AB Element Reversal GuardA
& The tRG timer above is only present
1 496 when configured as Blocking1 3Ch and
989 Aid1 Block Send DE BlockZ1e3Ch schemes.
Zone4 CA Element
Note:
The logic shown above is for A Channel. B and C channels operate on similar principles.
P54-TM-EN-1.1 239
Chapter 9 - Carrier Aided Schemes P54
Aid. 1 Selection
PUR
POR
Blocking1
Blocking2 1
DE Z1e 1Ch
DE Perm.Z1e1Ch
DE BlockZ1e1Ch
& 317
1 Aid 1 Chan Fail
&
tDR tDW
&
1 & 494
1 Aided 1 Receive
1
& tPR
&
&
Aided 1 COS/LGS
492
&
493
Aided1 Scheme Rx &
Aid. 1 Selection
POR Unblocking
PUR Unblocking 1
Prog. Unblocking
492
Aided 1 COS/LGS
&
1430
Aided1 SchemeRxA 1527
& Aided1 Receive A
1486
Aided1 SchemeRxB 1529
& Aided1 Receive B
1502
Aided1 SchemeRxC 1531
& Aided1 Receive C
Aid. 1 Selection
Blocking1 3Ch 494
1 Aided 1 Receive
Blocking2 3Ch
PUR 3Ch
POR 3Ch 1
DE Z1e 3Ch
DE Perm.Z1e3Ch
DE BlockZ1e3Ch V03528
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
240 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Blocking2
1 1 Perm.TripZone AN
Prog. Unblocking
2891 &
Zone 1e AN Elem
Programmable
1 Perm.TripZone BN
PUR 3Ch 2892 &
Zone 1e BN Elem
POR 3Ch
Blocking1 3Ch 1 Perm.TripZone CN
2893 &
Blocking2 3Ch Zone 1e CN Elem
969 &
Zone2 AB Element 1 Perm.TripZone AB
970 &
Aid. 1 Selection
Zone2 BC Element 1 Perm.TripZone BC
DE Z1e 1Ch
DE Perm.Z1e1Ch
971 &
Zone2 CA Element 1 Perm.TripZone CA
DE BlockZ1e1Ch 1
DE Z1e 3Ch 2894 &
DE Perm.Z1e3Ch Zone 1e AB Elem
DE BlockZ1e3Ch
2895 &
Zone 1e BC Elem
2896 &
Zone 1e CA Elem
V03529-1a
P54-TM-EN-1.1 241
Chapter 9 - Carrier Aided Schemes P54
Aid. 1 Selection
PUR
PUR Unblocking
POR
POR Unblocking
Blocking1
1
Blocking2
Prog. Unblocking
Programmable
DE Z1e 1Ch
DE Perm.Z1e1Ch
DE BlockZ1e1Ch
501
Aid1 Trip Enable &
1
502
Aid1 Custom Trip Aid.1 Dist. Dly
t DST
Aid1 InhibitDist 394 1
503
1 Aid 1 Dist Trip
Perm.TripZone AN
&
1 & 633
& 1 Aided 1 Trip A
Perm.TripZone BN
&
1 & 634
& 1 Aided 1 Trip B
Perm.TripZone CN
&
1 & 635
& 1 Aided 1 Trip C
Aid 1 Distance
1 1 & 636
Ground Only & 1 Aided 1 Trip N
Phase And Ground From Aided 1 Def Trip A
Phase Only 1 From Aided 1 Delta Trip A (if applicable)
From Aided 1 Def Trip B
From Aided 1 Delta Trip B (if applicable)
From Aided 1 Def Trip C
Perm.TripZone AB From Aided 1 Delta Trip C (if applicable)
&
From Aided 1 Def Trip N
From Aided 1 Delta Trip N (if applicable)
Perm.TripZone BC
&
Notes:
Perm.TripZone CA Aided 1 scheme only shown.
&
V03529-2
242 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid. 1 Selection
PUR 3Ch
POR 3Ch
DE Z1e 3Ch
1
DE Perm.Z1e3Ch
Blocking1 3Ch 634
Aided 1 Trip B
Blocking2 3Ch
635
DE BlockZ1e3Ch Aided 1 Trip C
From Bph
1545 &
Aid1 Trip En. A
From Cph
Aid.1 Dist. Dly
394
Aid1 InhibitDist
503
t DST 1 Aid 1 Dist Trip
Perm.TripZone AN 1
& 633
1 & Aided 1 Trip A
&
Notes:
Perm.TripZone AB Only Applicable for Aided 1 scheme.
&
Perm.TripZone CA
&
V03530
Aid. 1 Selection
PUR 3Ch
POR 3Ch
DE Z1e 3Ch
1
DE Perm.Z1e3Ch
633
Blocking1 3Ch Aided PermT A Aided 1 Trip A
Blocking2 3Ch 635
Aided PermT C Aided 1 Trip C
DE BlockZ1e3Ch
1596 &
Aid1 Trip En. B
Aided PermT B Aid.1 Dist. Dly
394
Aid1 InhibitDist
503
t DST 1 Aid 1 Dist Trip
Perm.TripZone BN 1
& 634
1 & Aided 1 Trip B
&
Notes:
Perm.TripZone AB
& Only Applicable for Aided 1 scheme.
970
Perm.TripZone BC
& V03531
P54-TM-EN-1.1 243
Chapter 9 - Carrier Aided Schemes P54
Aid. 1 Selection
PUR 3Ch
POR 3Ch
DE Z1e 3Ch
DE Perm.Z1e3Ch 1
Blocking1 3Ch
633
Blocking2 3Ch Aided PermT A Aided 1 Trip A
DE BlockZ1e3Ch Aided PermT B Aided 1 Trip B
634
653 &
Aid1 Trip En. C
Aided PermT C Aid.1 Dist. Dly
394
Aid1 InhibitDist
503
t DST 1 Aid 1 Dist Trip
Perm.TripZone CN 1
& 635
1 & Aided 1 Trip C
&
Notes:
Perm.TripZone BC
& Only Applicable for Aided 1 scheme.
Perm.TripZone CA
& V03532
Aid. 1 Selection
PUR
501
& Aid1 Trip Enable
Aided 1 Receive 494 100 ms
Aid. 1 Selection
PUR 3Ch
1545
& Aid1 Trip En. A
Aided1 Receive A 1527 100 ms
1596
& Aid1 Trip En. B
Aided1 Receive B 1529 100 ms
653
& Aid1 Trip En. C
Aided1 Receive C 1531 100 ms
V03533
244 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid.1 3 EndLine
Disable
Enable &
Aided 1 Receive
&
Aid11 Sch.Rx.Ch2
Aid 1 & & Aid1 Trip Enable
Aid. 1 Selection
POR 1Ch
1
DE Z1e 1Ch
DE Perm.Z1e1Ch
Any Trip
& &
Trip Inputs 3Ph & 1 Aided 1 Echo
Send on Trip
None
Any Trip
& 1 &
Any Trip 100ms
CB Open 3 ph
& WI Echo Trip Start
CB Open A ph
& 1
CB Open B ph
CB Open C ph
1
Inhibit WI &
S
Q
R
WI Trip PSB
Inhibit Trip &
Power Swing
Reversal Guard
Weak Infeed
Echo 1
Echo and Trip
1
Distance signal send 100ms
DEF signal send 1
Delta signal send
Any Zone 3 Element V03534-1a
P54-TM-EN-1.1 245
Chapter 9 - Carrier Aided Schemes P54
Weak Infeed WI Echo Trip Start WI Trip Delay & Aid1 WI Trip 3Ph
Echo
60 ms
Echo and Trip &
1 S
Q
Aided 1 WI V< A R
& Weak Infeed S
CB Open A ph Snapshot R
Q Aid 1 WI Trip A
Aided 1 WI V< B & Logic
S
CB Open B ph R
Q Aid 1 WI Trip B
Aided 1 WI V< C & S
CB Open C ph R
Q Aid 1 WI Trip C
V03534-1b
Figure 131: POR Aided Tripping logic 1Ch (2 of 2) – Weak Infeed Trip
246 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid.1 3 EndLine
Disable
Enable &
Aided1 Receive A
&
Aid1 Sch.RxA.Ch2 1
&
& Aid1 Trip En. A
Aid. 1 Selection
POR 3Ch
DE Z1e 3Ch 1
tReversal Guard
DE Perm.Z1e3Ch
Zone 3 Element A
ms V03534-2a
P54-TM-EN-1.1 247
Chapter 9 - Carrier Aided Schemes P54
Disable
Figure 133: POR Aided Tripping logic ACh (2 of 2) – Weak Infeed Trip
Note:
The logic shown above is for A Channel. B and C channels operate on similar principles.
248 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
POR
522
Any Trip
&
Trip Inputs 3Ph
529 &
1 Echo Send
Send on Trip
None
Any Trip
& &
Any Trip
522 1 100ms
Send on Trip
Aided / Z1
&
Aid 1 Distance
Disabled
608 &
Zone 1 Trip 1
503
Aid 1 Dist Trip
505 &
Aid 1 DEF Trip 1
250 ms 100 ms
494
Aided 1 Receive
&
Aid. 1 Selection
POR
903
CB Open 3 ph 10 ms
904
CB1 Open A ph
912 &
CB2 Open A ph WI Sngl Pole Trp
905
1
CB1 Open B ph
& Disabled
913 &
CB2 Open B ph WI Trip Delay 642
906 & Aid1 WI Trip 3Ph
CB1 Open C ph
914 &
CB2 Open C ph 60 ms
Blk Send 637
833 Aid 1 WI Trip A
VTS Slow Block 638
Week Infeed
Aid 1 WI Trip B
Weak Infeed Snapshot Logic 639
&
Aided 1 WI V< A
1358 1
904
CB1 Open A ph &
912
CB2 Open A ph
1359
Aided 1 WI V< B
905
CB1 Open B ph &
913
CB2 Open B ph
1360
Aided 1 WI V< C
905
CB1 Open C ph &
913
CB2 Open C ph V03514
P54-TM-EN-1.1 249
Chapter 9 - Carrier Aided Schemes P54
Aid. 1 Selection
Blocking1
1
DE BlockZ1e1Ch
498
Aided 1 Send
1 & 501
Aid1 Trip Enable
494
Aided 1 Receive 1
492
Aided 1 COS/LGS
Aid. 1 Selection
Blocking1 3Ch
1
DE BlockZ1e3Ch
492
Aided 1 COS/LGS
1545
1406
& Aid1 Trip En. A
Aided 1 Send A 1
1
1527
Aided1 Receive A
1596
1407
& Aid1 Trip En. B
Aided 1 Send B 1
1
1529
Aided1 Receive B
653
1408
& Aid1 Trip En. C
Aided 1 Send C 1
1
1531
Aided1 Receive C
V03535
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
250 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid. 1 Selection
Blocking2
tReversal Guard
498
Aided 1 Send
1
Aided 1 Receive 494 tRGD
501
& Aid1 Trip Enable
Aided 1 COS/LGS 492 1
Aid. 1 Selection
Blocking2 3Ch
Aided 1 COS/LGS
tReversal Guard
1405
Aided 1 Send A & 1545
Aid1 Trip En. A
1 1
Aided1 Receive A 1527 tRGD
1406
Aided 1 Send B
1 & 1596
Aid1 Trip En. B
Aided1 Receive B 1529 tRGD 1
1407
Aided 1 Send C
1 & 653
Aid1 Trip En. C
Aided1 Receive C 1531 tRGD 1
V03536
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
P54-TM-EN-1.1 251
Chapter 9 - Carrier Aided Schemes P54
4.2 IMPLEMENTATION
Aided DEF protection can be used with permissive over-reach schemes or blocking schemes.
The Aided DEF protection is enabled using the Directional E/F setting in the CONFIGURATION column. This makes
the settings in the AIDED DEF column visible.
The Aided DEF requires a polarizing quantity (selected in the DEF Polarizing setting) in conjunction with a
characteristic angle setting (DEF Char. Angle) to make the directional decision.
For all models a signal derived from the phase voltage inputs can be used for polarization. For certain models with
more VT inputs, a directly measured input can be used.
You have a choice between Zero Sequence Polarizing or Negative Sequence Polarizing for the Aided DEF element.
If you choose Zero Sequence Polarization, you have a choice to enable an innovative feature known as Virtual
Current Polarization to enhance the Aided DEF function.
Aided DEF protection is blocked if any of the following conditions are met:
● An Any Trip signal is asserted by one of the integrated protection functions
● The phase selector picks up on more than one phase
● Any of the signals Pole Dead A, Pole Dead B, or Pole Dead C are asserted
Zero Sequence polarization normally uses the measurement of residual voltage (VN). This can only be achieved if a
5-limb VT or three single-phase VTs are used. A special form of zero sequence polarization called Virtual Current
Polarization is also possible with this device. Virtual Current Polarization allows directionalisation for low levels of
polarization voltage.
252 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Directional forward
90° < (angle(VNpol) +180°) - (angle(IN )- RCA) < 90°
Directional reverse
90° > (angle(VNpol) +180° - (angle(IN) - RCA) > 90°
This is represented in the following figure:
P54-TM-EN-1.1 253
Chapter 9 - Carrier Aided Schemes P54
IN angle -RCA
IN
The Polarizing voltage (VNpol) is as per the table below and RCA is the relay characteristic angle defined by the
DEF Char. Angle setting.
Phase selector pickup VNpol
A Phase Fault VB + VC
B Phase Fault VA + VC
C Phase Fault VA + VB
No Selection VN = VA + VB + VC
Note:
The virtual current polarization works if the DEF Polarizing setting is Zero Sequence, the Virtual I Pol setting is Enabled,
and the VN voltage is less than the selected value of the DEF VNpol Set setting.
The problems in these applications can be alleviated using negative phase sequence (nps) voltage for polarization.
The nps voltage threshold must be set in the cell DEF V2pol Set.
Note:
This setting is 3 times V2.
Note:
The current quantity used for operation of the Aided DEF when it is nps Polarized is the residual current, not the nps current,
i.e. settings DEF FWD Set and DEF REV Set are for residual current.
254 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Note:
The minimum negative sequence current required for nps polarisation is the value set by the setting, DEF REV Set
Directional forward
-90° < [(angle(V2) +180°) - (angle(I2) - RCA) ] < 90°
Directional reverse
-90° > [ (angle(V2) +180°) - angle(I2) - RCA) ] > 90°
where RCA is the relay characteristic angle set in the DEF Char. Angle setting.
This is represented in the following figure:
I2 angle -RCA
I2
P54-TM-EN-1.1 255
Chapter 9 - Carrier Aided Schemes P54
The following angle settings are recommended for a residual voltage polarized device:-
● Solidly earthed distribution systems: -45°
● Solidly earthed transmissions systems: -60°
If Virtual I Pol is set to ‘Disabled’ it prevents checking of the faulted phase and subsequent removal of the faulted
phase voltage. The aided DEF protection is then polarized by the residual voltage only.
For negative sequence polarization, the relay characteristic angle settings (DEF Char. Angle) must be based on the
angle of the upstream negative phase sequence source impedance. A typical setting is -60°.
The DEF FWD Set setting determines the current sensitivity (trip sensitivity) of the aided DEF aided scheme. This
setting must be set higher than any standing residual current unbalance. A typical setting will be between 10%
and 20% In.
The DEF REV Set setting determines the current sensitivity for the reverse earth fault. The setting must always be
below the aided DEF forward threshold for correct operation of blocking schemes and to provide stability for
current reversal in parallel line applications. The recommended setting is 2/3 of the Aided DEF forward setting.
Note:
The DEF REV Set setting has to be above the maximum steady state residual current imbalance.
256 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
DEF Forward
ZL
A B
DEF Forward
CRx CRx
DEF-Reverse & CTx CTx
& DEF-Reverse
1 1
Trip Trip
DEF Inst DEF Inst
1 A B
1
DEF Bu1 t
Bu1 t
Bu1 DEF Bu1
P54-TM-EN-1.1 257
Chapter 9 - Carrier Aided Schemes P54
The figures below show the element reaches, and the simplified scheme logic of the Aided Directional Earth Fault
(Aided DEF) Blocking scheme.
DEF-Forward
DEF-Reverse
ZL
A B
DEF-Forward
DEF-Reverse
CRx CRx
DEF-Reverse Start Start DEF-Reverse
CTx CTx
Stop Stop
DEF Bu1 t
Bu1 t
Bu1 DEF Bu1
DEF Bu2 t
Bu2 t
Bu2 DEF Bu2
DEF IDMT t
IDMT t
IDMT DEF IDMT
E03519
V03526
258 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Notes:
Aided 1 scheme only shown.
P445 does not provide an Aided Delta function. V03506
P54-TM-EN-1.1 259
Chapter 9 - Carrier Aided Schemes P54
Aid. 1 Selection
PUR
POR
Blocking1
Blocking2 1
DE Z1e 1Ch
DE Perm.Z1e1Ch
DE BlockZ1e1Ch
& 317
1 Aid 1 Chan Fail
&
tDR tDW
&
1 & 494
1 Aided 1 Receive
1
& tPR
&
&
Aided 1 COS/LGS
492
&
493
Aided1 Scheme Rx &
Aid. 1 Selection
POR Unblocking
PUR Unblocking 1
Prog. Unblocking
492
Aided 1 COS/LGS
&
1430
Aided1 SchemeRxA 1527
& Aided1 Receive A
1486
Aided1 SchemeRxB 1529
& Aided1 Receive B
1502
Aided1 SchemeRxC 1531
& Aided1 Receive C
Aid. 1 Selection
Blocking1 3Ch 494
1 Aided 1 Receive
Blocking2 3Ch
PUR 3Ch
POR 3Ch 1
DE Z1e 3Ch
DE Perm.Z1e3Ch
DE BlockZ1e3Ch V03528
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
260 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
1
522
Any Trip
1 From Aided 1 Distance Trip A
& From Aided 1 Delta Trip A (if applicable)
From Aided 1 Distance Trip B
& From Aided 1 Delta Trip B (if applicable)
From Aided 1 Distance Trip C
From Aided 1 Delta Trip C (if applicable)
& From Aided 1 Distance Trip N
Notes:
From Aided 1 Delta Trip N (if applicable)
Aided 1 scheme only shown. V03510
P54-TM-EN-1.1 261
Chapter 9 - Carrier Aided Schemes P54
Aid.1 3 EndLine
Disable
Enable &
Aided 1 Receive
&
Aid11 Sch.Rx.Ch2
Aid 1 & & Aid1 Trip Enable
Aid. 1 Selection
POR 1Ch
1
DE Z1e 1Ch
DE Perm.Z1e1Ch
Any Trip
& &
Trip Inputs 3Ph & 1 Aided 1 Echo
Send on Trip
None
Any Trip
& 1 &
Any Trip 100ms
CB Open 3 ph
& WI Echo Trip Start
CB Open A ph
& 1
CB Open B ph
CB Open C ph
1
Inhibit WI &
S
Q
R
WI Trip PSB
Inhibit Trip &
Power Swing
Reversal Guard
Weak Infeed
Echo 1
Echo and Trip
1
Distance signal send 100ms
DEF signal send 1
Delta signal send
Any Zone 3 Element V03534-1a
262 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Weak Infeed WI Echo Trip Start WI Trip Delay & Aid1 WI Trip 3Ph
Echo
60 ms
Echo and Trip &
1 S
Q
Aided 1 WI V< A R
& Weak Infeed S
CB Open A ph Snapshot R
Q Aid 1 WI Trip A
Aided 1 WI V< B & Logic
S
CB Open B ph R
Q Aid 1 WI Trip B
Aided 1 WI V< C & S
CB Open C ph R
Q Aid 1 WI Trip C
V03534-1b
Figure 146: POR Aided Tripping logic 1Ch (2 of 2) – Weak Infeed Trip
P54-TM-EN-1.1 263
Chapter 9 - Carrier Aided Schemes P54
POR
522
Any Trip
&
Trip Inputs 3Ph
529 &
1 Echo Send
Send on Trip
None
Any Trip
& &
Any Trip
522 1 100ms
Send on Trip
Aided / Z1
&
Aid 1 Distance
Disabled
608 &
Zone 1 Trip 1
503
Aid 1 Dist Trip
505 &
Aid 1 DEF Trip 1
250 ms 100 ms
494
Aided 1 Receive
&
Aid. 1 Selection
POR
903
CB Open 3 ph 10 ms
904
CB1 Open A ph
912 &
CB2 Open A ph WI Sngl Pole Trp
905
1
CB1 Open B ph
& Disabled
913 &
CB2 Open B ph WI Trip Delay 642
906 & Aid1 WI Trip 3Ph
CB1 Open C ph
914 &
CB2 Open C ph 60 ms
Blk Send 637
833 Aid 1 WI Trip A
VTS Slow Block 638
Week Infeed
Aid 1 WI Trip B
Weak Infeed Snapshot Logic 639
&
Aided 1 WI V< A
1358 1
904
CB1 Open A ph &
912
CB2 Open A ph
1359
Aided 1 WI V< B
905
CB1 Open B ph &
913
CB2 Open B ph
1360
Aided 1 WI V< C
905
CB1 Open C ph &
913
CB2 Open C ph V03514
264 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid. 1 Selection
Blocking1
1
DE BlockZ1e1Ch
498
Aided 1 Send
1 & 501
Aid1 Trip Enable
494
Aided 1 Receive 1
492
Aided 1 COS/LGS
Aid. 1 Selection
Blocking1 3Ch
1
DE BlockZ1e3Ch
492
Aided 1 COS/LGS
1545
1406
& Aid1 Trip En. A
Aided 1 Send A 1
1
1527
Aided1 Receive A
1596
1407
& Aid1 Trip En. B
Aided 1 Send B 1
1
1529
Aided1 Receive B
653
1408
& Aid1 Trip En. C
Aided 1 Send C 1
1
1531
Aided1 Receive C
V03535
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
P54-TM-EN-1.1 265
Chapter 9 - Carrier Aided Schemes P54
Aid. 1 Selection
Blocking2
tReversal Guard
498
Aided 1 Send
1
Aided 1 Receive 494 tRGD
501
& Aid1 Trip Enable
Aided 1 COS/LGS 492 1
Aid. 1 Selection
Blocking2 3Ch
Aided 1 COS/LGS
tReversal Guard
1405
Aided 1 Send A & 1545
Aid1 Trip En. A
1 1
Aided1 Receive A 1527 tRGD
1406
Aided 1 Send B
1 & 1596
Aid1 Trip En. B
Aided1 Receive B 1529 tRGD 1
1407
Aided 1 Send C
1 & 653
Aid1 Trip En. C
Aided1 Receive C 1531 tRGD 1
V03536
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
266 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Caution:
Aided Delta should not be used on a communications channel if that channel is being used to
implement an Aided Distance Scheme or an Aided DEF scheme. You should ensure that the Aided
Distance and Aided DEF elements are disabled if you want to apply the Aided Delta (Directional
Comparison Protection).
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
P54-TM-EN-1.1 267
Chapter 9 - Carrier Aided Schemes P54
R R
Z (T)
CRX CRX
CB CB
OPEN & Signalling Signalling & OPEN
Equipment Equipment
Trip G Trip H
1 1
TZ (T) TZ (T)
END G END H t
Z t Z
0 0
E03520
268 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
R R
Z (T)
CRX CRX
Signalling Signalling
Equipment Equipment
Trip G Trip H
1 1
E03521
P54-TM-EN-1.1 269
Chapter 9 - Carrier Aided Schemes P54
Aid. 1 Delta
Enabled
998
From Aided 1 DEF
Delta Dir Fwd AN
Signal Send
999
Delta Dir Fwd BN
Echo Send
1000
Delta Dir Fwd CN &
1 1 1
Delta Dir Fwd AB 1001 & &
1 498
1002
& Aided 1 Send
Delta Dir Fwd BC tRG
1003
Delta Dir Fwd CA
1005
Delta Dir Rev BN Aid1 Custom Send 497
1006
Delta Dir Rev CN &
1 Aid1 Block Send 496
Delta Dir Rev AB 1007
1008
Delta Dir Rev BC
Notes:
1009
Delta Dir Rev CA Aided 1 scheme only shown .
396
Aid1 Inhib Delta V03507
270 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid. 1 Selection
PUR
POR
Blocking1
Blocking2 1
DE Z1e 1Ch
DE Perm.Z1e1Ch
DE BlockZ1e1Ch
& 317
1 Aid 1 Chan Fail
&
tDR tDW
&
1 & 494
1 Aided 1 Receive
1
& tPR
&
&
Aided 1 COS/LGS
492
&
493
Aided1 Scheme Rx &
Aid. 1 Selection
POR Unblocking
PUR Unblocking 1
Prog. Unblocking
492
Aided 1 COS/LGS
&
1430
Aided1 SchemeRxA 1527
& Aided1 Receive A
1486
Aided1 SchemeRxB 1529
& Aided1 Receive B
1502
Aided1 SchemeRxC 1531
& Aided1 Receive C
Aid. 1 Selection
Blocking1 3Ch 494
1 Aided 1 Receive
Blocking2 3Ch
PUR 3Ch
POR 3Ch 1
DE Z1e 3Ch
DE Perm.Z1e3Ch
DE BlockZ1e3Ch V03528
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
P54-TM-EN-1.1 271
Chapter 9 - Carrier Aided Schemes P54
& 633
Delta Dir FWD AN 998 & 1 Aided 1 Trip A
1
& 634
Delta Dir FWD BN 999 & 1 Aided 1 Trip B
1
& 635
Delta Dir FWD CN 1000 & 1 Aided 1 Trip C
1
1001
Delta Dir FWD AB & 636
& 1 Aided 1 Trip N
1002
Delta Dir FWD BC 1
From Aided 1 Def Trip A
1003
Delta Dir FWD CA From Aided 1 Distance Trip A
From Aided 1 Def Trip B
From Aided 1 Distance Trip B
Notes: From Aided 1 Def Trip C
Aided 1 scheme only shown . From Aided 1 Distance Trip C
From Aided 1 Def Trip N
V03511 From Aided 1 Distance Trip N
272 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid.1 3 EndLine
Disable
Enable &
Aided 1 Receive
&
Aid11 Sch.Rx.Ch2
Aid 1 & & Aid1 Trip Enable
Aid. 1 Selection
POR 1Ch
1
DE Z1e 1Ch
DE Perm.Z1e1Ch
Any Trip
& &
Trip Inputs 3Ph & 1 Aided 1 Echo
Send on Trip
None
Any Trip
& 1 &
Any Trip 100ms
CB Open 3 ph
& WI Echo Trip Start
CB Open A ph
& 1
CB Open B ph
CB Open C ph
1
Inhibit WI &
S
Q
R
WI Trip PSB
Inhibit Trip &
Power Swing
Reversal Guard
Weak Infeed
Echo 1
Echo and Trip
1
Distance signal send 100ms
DEF signal send 1
Delta signal send
Any Zone 3 Element V03534-1a
P54-TM-EN-1.1 273
Chapter 9 - Carrier Aided Schemes P54
Weak Infeed WI Echo Trip Start WI Trip Delay & Aid1 WI Trip 3Ph
Echo
60 ms
Echo and Trip &
1 S
Q
Aided 1 WI V< A R
& Weak Infeed S
CB Open A ph Snapshot R
Q Aid 1 WI Trip A
Aided 1 WI V< B & Logic
S
CB Open B ph R
Q Aid 1 WI Trip B
Aided 1 WI V< C & S
CB Open C ph R
Q Aid 1 WI Trip C
V03534-1b
Figure 156: POR Aided Tripping logic 1Ch (2 of 2) – Weak Infeed Trip
274 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
POR
522
Any Trip
&
Trip Inputs 3Ph
529 &
1 Echo Send
Send on Trip
None
Any Trip
& &
Any Trip
522 1 100ms
Send on Trip
Aided / Z1
&
Aid 1 Distance
Disabled
608 &
Zone 1 Trip 1
503
Aid 1 Dist Trip
505 &
Aid 1 DEF Trip 1
250 ms 100 ms
494
Aided 1 Receive
&
Aid. 1 Selection
POR
903
CB Open 3 ph 10 ms
904
CB1 Open A ph
912 &
CB2 Open A ph WI Sngl Pole Trp
905
1
CB1 Open B ph
& Disabled
913 &
CB2 Open B ph WI Trip Delay 642
906 & Aid1 WI Trip 3Ph
CB1 Open C ph
914 &
CB2 Open C ph 60 ms
Blk Send 637
833 Aid 1 WI Trip A
VTS Slow Block 638
Week Infeed
Aid 1 WI Trip B
Weak Infeed Snapshot Logic 639
&
Aided 1 WI V< A
1358 1
904
CB1 Open A ph &
912
CB2 Open A ph
1359
Aided 1 WI V< B
905
CB1 Open B ph &
913
CB2 Open B ph
1360
Aided 1 WI V< C
905
CB1 Open C ph &
913
CB2 Open C ph V03514
P54-TM-EN-1.1 275
Chapter 9 - Carrier Aided Schemes P54
Aid. 1 Selection
Blocking1
1
DE BlockZ1e1Ch
498
Aided 1 Send
1 & 501
Aid1 Trip Enable
494
Aided 1 Receive 1
492
Aided 1 COS/LGS
Aid. 1 Selection
Blocking1 3Ch
1
DE BlockZ1e3Ch
492
Aided 1 COS/LGS
1545
1406
& Aid1 Trip En. A
Aided 1 Send A 1
1
1527
Aided1 Receive A
1596
1407
& Aid1 Trip En. B
Aided 1 Send B 1
1
1529
Aided1 Receive B
653
1408
& Aid1 Trip En. C
Aided 1 Send C 1
1
1531
Aided1 Receive C
V03535
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
276 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Aid. 1 Selection
Blocking2
tReversal Guard
498
Aided 1 Send
1
Aided 1 Receive 494 tRGD
501
& Aid1 Trip Enable
Aided 1 COS/LGS 492 1
Aid. 1 Selection
Blocking2 3Ch
Aided 1 COS/LGS
tReversal Guard
1405
Aided 1 Send A & 1545
Aid1 Trip En. A
1 1
Aided1 Receive A 1527 tRGD
1406
Aided 1 Send B
1 & 1596
Aid1 Trip En. B
Aided1 Receive B 1529 tRGD 1
1407
Aided 1 Send C
1 & 653
Aid1 Trip En. C
Aided1 Receive C 1531 tRGD 1
V03536
Note:
An Aided Distance scheme requires communication of the aided-carrier command signal(s) between line ends. Where phase-
segregated carrier-aided Distance schemes are supported, three command signals must be communicated (one to supervise
the tripping of each phase). Otherwise a single command transfer (universally applicable to all phases) is required.
An Aided Delta scheme requires a separate communication command channel to transmit a composite Delta Directional
signal (universally applicable to all phases) between line ends.
An Aided DEF scheme requires a separate communication command channel to transmit the aided-carrier command signal
(universally applicable to all phases) between line ends. If a three-pole-tripping carrier-aided Distance scheme is implemented
(i.e NOT phase-segregated) then a single, common, aided carrier signal may be shared between similar carrier-aided Distance
and DEF schemes.
P54-TM-EN-1.1 277
Chapter 9 - Carrier Aided Schemes P54
6 DE TELEPROTECTION SCHEMES
The following teleprotection schemes are specific for DE:
● DE Zone 1 Extension Scheme 1 Ch (DE Z1e 1Ch) to work with a common channel send
● DE Zone 1 Extension Scheme 3 Ch (DE Z1e 3h) to work with a per phase channel send
● DE Permissive Zone 1 Extension Scheme 1 Ch (DE Perm.Z1e1Ch) to work with a common channel send
● DE Permissive Zone 1 Extension Scheme 3 Ch (DE Perm.Z1e3Ch) to work with a per phase channel send
● DE Blocking Scheme for 1 Ch. Setting DE BlockZ1e1Ch to work with a common channel send
● DE Blocking Scheme for 3 Ch. Setting DE BlockZ1e3Ch to work with a per phase channel send
Zone 1 Extension Scheme 1 Ch (DE Z1e 1Ch) and Zone 1 Extension Scheme 3 Ch (DE Z1e 3Ch)
These schemes use the existing scheme logic as per POR 1Ch and POR 3Ch, but sending and receiving zones are
as follows:
Send logic: Zone 1
Permissive Trip Logic: Z1e AND Channel receive (done in a per phase basis for DE Z1e 3Ch)
The scheme will trip after the existing time delay Aid.1 Dist. Dly has elapsed.
Permissive Zone 1 Extension Scheme 1 Ch (DE Perm.Z1e1Ch) and Permissive Zone 1 Extension Scheme 3 Ch (DE
Perm.Z1e3Ch)
These schemes use the existing scheme logic as per POR 1Ch and POR 3Ch, but sending and receiving zones are
as follows:
Send logic: Z1e
Permissive Trip Logic: Z1e AND Channel receive (done in a per phase basis for DE Perm.Z1e3Ch)
The scheme will trip after the existing time delay Aid.1 Dist. Dly has elapsed.
Blocking Scheme for 1Ch DE BlockZ1e1Ch and Blocking Scheme for 3Ch DE BlockZ1e3Ch
These schemes use the existing scheme logic as per Blocking Scheme 1 Blocking1 1Ch and Blocking1 3Ch, but
sending and receiving zones are as follows:
Block Send logic: Zone 4
Trip Logic: Z1e AND No Channel receive (in a per phase basis for DE BlockZ1e3Ch)
The scheme will trip after the existing time delay Aid.1 Dist. Dly has elapsed. In this case, for tripping, enough time
must be allowed for the remote relay signal to pick-up and for channel delay.
278 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Note:
When a scheme is used as 3Ch, Aided DEF or Aided Delta cannot be used.
P54-TM-EN-1.1 279
Chapter 9 - Carrier Aided Schemes P54
7 APPLICATION NOTES
The time delay setting (Aid.1 Dist. Dly, Aid.2 Dist. Dly) should be set to 0 ms for fast fault clearance.
The time delay setting (Aid.1 Dist. Dly, Aid.2 Dist. Dly) should be set to 0 ms for fast fault clearance.
The POR scheme also uses the reverse looking zone 4 IED as a reverse fault detector. This is used in the current
reversal logic and in the optional weak infeed echo feature.
Weak Infeed
Where weak infeed tripping is employed, a typical voltage setting is 70% of rated phase-neutral voltage. Weak
infeed tripping is time delayed according to the WI Trip Delay value, usually set at 60ms.
To allow time for a blocking signal to arrive, a short time delay must be allowed before tripping (Aid.1 Dist. Dly, Aid.
2 Dist. Dly). The recommended delay is as follows:
● Recommended setting = Maximum signalling channel operating time + one power frequency cycle.
Note:
Two variants of a Blocking scheme are provided, Blocking 1 and Blocking 2. Both schemes operate similarly, except that the
reversal guard timer location in the logic changes. Blocking 2 may sometimes allow faster unblocking when a fault evolves
from external to internal, and hence a faster trip.
280 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
To allow time for a blocking signal to arrive, a short time delay on aided tripping must be used. The recommended
delay time setting (Aid. 1 DEF Dly., Aid. 2 DEF Dly.) is the maximum signalling channel operating time +20 ms.
The time delay (Aid. 1 Delta Dly, Aid. 2 Delta Dly) should be set to 0 ms for fast fault clearance.
Recommended delay setting (Aid. 1 Delta Dly, Aid. 2 Delta Dly): Maximum signalling channel operating time
+ 6ms.
P54-TM-EN-1.1 281
Chapter 9 - Carrier Aided Schemes P54
A B
Ia Ib
Zat
Zbt
Ic
Zct
Va
Va = Ia Zat + Ib Zbt C Impedance seen by relay A =
Ia
Ia = Ia + Ic
E03524
282 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
Carrier aided schemes can also be used in conjunction with distance elements to protect teed feeders. Although
Permissive Overreaching and Permissive Underreaching schemes may be used, they suffer some limitations.
Blocking schemes are generally considered to be the most suitable.
This is intended for use in the following scenario. Consider the three-ended scheme in the figure below. With a
STRONG End A and weaker Ends B and C, relays at End B and C are set with Echo (not weak infeed trip). In this
case, we can assume Zone 2 at End A can see all faults up to the busbar Ends B and C.
End A End B
Fault 1
End C
Fault 2
E03537
For Fault 1
● End A: Sees the fault in Zone 2 and sends a signal to End C and B.
● End B Echo send: Does not see the fault and, because it is an OR from both signals receive, it will send a
signal back to A and C. It will not trip because it is only an Echo
● End C Echo send: Does not see the fault at all and because is an OR from both signals receive, it will send a
signal back to A and B . It will not trip because it is only set as an Echo
● End A: Will trip as the permissive is an AND from receive signals from End B and C fault and sees the fault in
Zone 2
End B and C can also be set as a Weak Infeed Trip and as long as these relays receive a signal from both remote
ends, and conditions are met (voltage below setting WI V<Thresh., No CB open, No Distance, etc.), the relay will trip
with Weak Infeed.
P54-TM-EN-1.1 283
Chapter 9 - Carrier Aided Schemes P54
For Fault 2
● End A: Sees the fault in Zone 2 and sends a signal to End C and B.
● End B Echo send: Does not see the fault and, because is an OR from both Signals receive, it will send a signal
back to A and C. It will not trip because it is only set as an Echo
● End C Echo send: It will see the fault in the reverse direction and therefore will not send the echo and will not
trip.
● End A: Will not trip, as the permissive trip is an AND from both Signals receive from End B and C fault and in
this case NO signal has been received from End C
To ensure operation for internal faults in a POR scheme, the protection at each of the three terminals should be
able to see a fault anywhere on the protected feeder. This may demand very large Zone 2 reach settings to
address the apparent impedances seen by the Distance elements.
Although POR schemes are feasible for teed feeders, the signalling requirements and the very large Zone 2
settings can make its use unattractive.
If Zone 2 has to be too large, there are some scheme equivalents to POR that use an independent overreaching
zone Z1e, which can be used for this purpose. These schemes are DE Perm Z1e 1ch and DE Perm Z1e 3ch
284 P54-TM-EN-1.1
P54 Chapter 9 - Carrier Aided Schemes
(i) A B
(ii) A C
Z1A Z1B
(iii) A C B
No infeed
Figure 162: Problematic Fault Scenarios for PUR Scheme Application to Teed Feeders
● Scenario (i) shows a short tee connected to one nearby terminal and one distant terminal. In this case, Zone
1 elements set to 80% of the shortest connected feeder length don’t all overlap, resulting in a section not
covered by any Zone 1 element. Any fault in this section would rely on delayed Zone 2 tripping.
● Scenario (ii) shows an example where terminal C has no infeed. Distance elements at C may not operate for
faults close to the terminal. As the fault is outside the Zone 1 reaches of A and B, clearance will rely on
delayed Zone 2 tripping at A and B.
● Scenario (iii) shows an example where outfeed from terminal C feeds an internal fault via terminal B. In this
case, terminal C will not see the fault until the breaker at B has operated. The result would be sequential
(and hence delayed) tripping.
Note:
Triangulated simplex channels could be used in place of a common simplex one if prefered.
As with Permissive Underreaching (PUR) schemes, a limitation of a Blocking scheme implementation is a scenario
where outfeed from one terminal feeds an internal fault via another terminal. The terminal with the outfeed sees a
P54-TM-EN-1.1 285
Chapter 9 - Carrier Aided Schemes P54
reverse fault condition. This results in a blocking signal being sent to the two remote terminals. Although the fault
will be cleared, tripping will be prevented until the Zone 2 time delay has expired.
286 P54-TM-EN-1.1
CHAPTER 10
NON-AIDED SCHEMES
Chapter 10 - Non-Aided Schemes P54
288 P54-TM-EN-1.1
P54 Chapter 10 - Non-Aided Schemes
1 CHAPTER OVERVIEW
This chapter describes the distance schemes that do not require communication between the ends (Non-Aided
Schemes).
This chapter contains the following sections:
Chapter Overview 289
Non-Aided Schemes 290
Basic Schemes 291
Trip On Close Schemes 295
Zone 1 Extension Scheme 300
Loss of Load Scheme 302
P54-TM-EN-1.1 289
Chapter 10 - Non-Aided Schemes P54
2 NON-AIDED SCHEMES
This product provides Distance protection. The Distance protection has been designed for use as a standalone
non-unit protection, or for use with communications systems to provide unit protection (Carrier Aided schemes).
Standalone operation provides basic scheme Distance protection (e.g. instantaneous Zone 1 operation, delayed
Zone 2 protection and further delayed Back-up protection, etc.). It also implements some special standalone
schemes that don’t require communications. These are known as Non-Aided Distance Schemes.
The non-aided schemes provided in this product can be divided into the following categories:
● Basic schemes
● Trip On Close schemes
● Zone 1 Extension scheme
● Loss of Load scheme
The settings for these Non-Aided Distance Schemes are located in the SCHEME LOGIC column.
290 P54-TM-EN-1.1
P54 Chapter 10 - Non-Aided Schemes
3 BASIC SCHEMES
Basic Scheme operation is always executed if distance elements are enabled. It is the process by which the
measured line impedance is compared against the Distance measuring zone configuration (reach settings and
timers). Instantaneous or time delayed tripping or blocking signals may be issued for a specific zone according to
its settings and the measured impedance values.
There are nine basic scheme zones; Zone 1, Zone 1e, Zone 2, Zone 3, Zone 4, Zone P, Zone Q, Zone R and Zone S.
The Basic Scheme settings include:
● A mode setting, which is common to all zones
● Zone Tripping settings for each zone
● Zone phase delay settings for each zone
● Zone ground delay settings for each zone
On a per-zone basis, phase and earth-fault elements may be set to have different time delays.
To supplement Basic Scheme operation, there are also standalone scheme designs (Non-Aided Distance Schemes)
that provide timely clearance for particular fault scenarios where carrier aided signalling is either not available, or
is unnecessary. These scenarios cover Trip on Closure (including Switch On to Fault, and Trip on Reclose), Loss of
Load, and Zone1 Extension.
The Basic Scheme is continually executed, regardless of any carrier-aided acceleration schemes which may be
enabled.
P54-TM-EN-1.1 291
Chapter 10 - Non-Aided Schemes P54
Zone1 Tripping
Ground only
1
Phase And Ground &
384
Block Zone 1 Gnd
960 &
Zone1 AN Element 1
1305 &
Z1 AN Comparator
961 &
Zone1 BN Element 1
1306 &
Z1 BN Comparator
& 1 & Zone 1 CN
PrioTripEna CN
744
1 Zone 1 N Start
962 &
Zone1 CN Element 1 Zone 1 Start Gnd
Zone1 Tripping
Phase only 1 Zone 1 Start Phs
1
Phase And Ground
385
Block Zone 1 Phs
1 &
Block Zones 1 - 4
963 & Zone 1 AB
Zone1 AB Element
Zone 1 AN 741
1 Zone 1 A Start
Zone 1 BN 742
1 Zone 1 B Start
Zone 1 CN 743
1 Zone 1 C Start
V02798
292 P54-TM-EN-1.1
P54 Chapter 10 - Non-Aided Schemes
Standard Mode
t 1985
& Z1 P time elapse
Zone 1 Start Phs 0
Alternative Mode
t 1985
Z1 P time elapse
0
V02782
1984
Z1 G time elapse
Zone 1 AN
612
& Zone 1 N Trip
Zone 1 BN 1
608
Zone 1 CN 1 Zone 1 Trip
1985
Z1 P time elapse
Zone 1 AB
&
Zone 1 BC 1
Zone 1 CA
1984
Z1 G time elapse
& 609
Zone 1 AN 1 Zone 1 A Trip
1985
Z1 P time elapse
Zone 1 AB &
1
Zone 1 CA
1984
Z1 G time elapse
& 610
Zone 1 BN 1 Zone 1 B Trip
1985
Z1 P time elapse
Zone 1 AB &
1
Zone 1 BC
Z1 G time elapse
& 611
Zone 1 CN 1 Zone 1 C Trip
1985
Z1 P time elapse
Zone 1 BC &
1
Zone 1 CA
V02783
P54-TM-EN-1.1 293
Chapter 10 - Non-Aided Schemes P54
The Zone 3 time delay (tZ3) is typically set with the same considerations made for the Zone 2 time delay, except
that the delay needs to co-ordinate with the downstream Zone 2 fault clearance. A typical minimum Zone 3
operating time would be in the region of 400 ms.
The Zone 4 time delay (tZ4) needs to coordinate with any protection for adjacent lines in the protection’s reverse
direction.
Separate time delays can be applied to both phase and ground fault zones, for example where ground fault delays
are set longer to time grade with external ground/earth overcurrent protection.
Any zone (#) which may reach through a power transformer reactance, and measure secondary side faults within
that impedance zone should have a small time delay applied. This is to avoid tripping on the inrush current when
energizing the transformer.
As a general rule, if the Zone Reach setting is greater than 50% of the transformer reactance, set the Zone delay to
be 100 ms or greater. Alternatively, the 2nd harmonic detector output (which is available in the Programmable
Scheme Logic) may be used to block zones that may be at risk of tripping on inrush current. Settings for the inrush
detector are found in the SUPERVISION column.
The figure below shows the typical application of the Basic scheme.
Zone 3
Zone 2
Zone 1
Z B
Z
Zone 1
Zone 2
Zone 3
Typical application
Relay A Relay B
Z1 TZ1 TZ1 Z1
Trip A Trip B
1 1
ZP TZP TZP ZP
Z2 TZ2 TZ2 Z2
Z3 TZ3 TZ3 Z3
Z4 Z4
TZ4 TZ4
294 P54-TM-EN-1.1
P54 Chapter 10 - Non-Aided Schemes
SOTF provides instantaneous operation of selected elements if a fault is present when manual closure of the circuit
breaker is performed.
TOR provides instantaneous operation of selected elements if a persistent fault is present when the circuit breaker
attempts autoreclosure
The SOTF and TOR functions are known as Trip on Close logic. Both methods operate in parallel if mapped to the
SOTF and TOR Tripping matrix in the setting file.
The settings for Switch on to Fault (SOTF) and Trip on Reclose (TOR) are located in the TRIP ON CLOSE section of the
SCHEME LOGIC column.
SOTF and TOR are complemented by Current No Voltage level detectors (also known as CNV level detectors). These
CNV level detectors are set using the voltage and current settings located in the CB FAIL & P.DEAD column. The
same settings are used for pole dead logic detection. A 10ms time delay in the logic avoids a possible race
between very fast overvoltage and undercurrent level detectors.
The following figures show the Trip On Close function in relation to the Distance zones and the Trip On Close
function when driven by Current No Volt level detectors.
TOR Status
Enabled
878
Inhibit TOR 485 & TOR Active
t
891
Any Pole Dead S 877
0 Q TOC Active
0 R
TOC Delay t
SOTF Pulse
SOTF Status
Enabled PoleDead 1
En Pdead + Pulse
Enabled ExtPulse 1
488 &
Set SOTF
V02742
P54-TM-EN-1.1 295
Chapter 10 - Non-Aided Schemes P54
559
Fast OV PHA 10 ms
864 &
IA< Start 0
560 10 ms
Fast OV PHB
865
& 1 & 556
CNV ACTIVE
IB< Start 0
561 10 ms
Fast OV PHC
866 & 0
IC< Start
832
VTS Fast Block
TOR Tripping
Current No Volts
556 557
CNV ACTIVE & TOR Trip CNV
878
TOR Active
SOTF Tripping
Current No Volts
556 558
CNV ACTIVE & SOTF Trip CNV
879
SOTF Active
V02743
296 P54-TM-EN-1.1
P54 Chapter 10 - Non-Aided Schemes
When busbar voltage transformers are used, the Pole Dead’ signal is not produced. Connect circuit breaker
auxiliary contacts for correct operation. This is not necessary if the SOTF is activated by an external pulse.
● SOTF Delay: The time chosen should be longer than the slowest delayed-auto-reclose dead time, but
shorter than the time in which the system operator might re-energise a circuit once it had opened/tripped.
We recommend 110 seconds as a typical setting.
● SOTF Pulse: Typically this could be set to at 500ms. This time is enough to establish completely the voltage
memory of distance protection.
● TOC Reset Delay: We recommend 500ms as a typical setting (chosen to be in excess of the 16 cycles length
of memory polarizing, allowing full memory charging before normal protection resumes).
832
VTS Fast Block
560 10 ms
Fast OV PHB
865
& 1 & 556
CNV ACTIVE
IB< Start 0
561 10 ms
Fast OV PHC
866
& 0
IC< Start
558
& SOTF Trip CNV
879
SOTF Active
SOTF Tripping
Current No Volts V02758
P54-TM-EN-1.1 297
Chapter 10 - Non-Aided Schemes P54
The SOTF and TOR features stay in service for the duration of the TOC Reset Delay time, once the circuit is
energised. The delay timer starts on CB closure and is common for SOTF and TOR protection. Once this timer
expires after successful closure, all protection reverts to normal.
A user settable time delay (TOC Delay) starts when the CB opens, after which TOR is enabled. The time delay must
not exceed the minimum Dead Time setting of the auto-reclose because both times start simultaneously and TOR
protection must be ready by the time the CB closes on potentially persistent faults.
While the Trip on Reclose Mode is active, the protection trips instantaneously for pick up of any selected Distance
zone. You select the zone with the TOR Tripping setting. For example, Zone 2 could operate without waiting for the
usual time delay if a fault is in Zone 2 on CB closure. Also Current No Volts can be mapped for fast fault clearance
on line reclosure on a permanent fault. To operate for faults on the entire circuit length, at least Zone 1 and Zone 2
should be selected. If no elements are selected, the normal time delayed elements and aided scheme provide the
protection. TOR tripping is three-phase and auto-reclose is blocked.
961
Zone1 BN Element
962
Zone1 CN Element
963
1 Note: This diagram shows Zone 1 only. The other zones follow the same principles.
Zone1 AB Element
964
Zone1 BC Element
965
Zone1 CA Element
832
VTS Fast Block V02755
560 10 ms
Fast OV PHB
865
& 1 556
IB< Start 0 & CNV ACTIVE
561 10 ms
Fast OV PHC
866
&
IC< Start 0
TOR Tripping
Current No Volts V02757
298 P54-TM-EN-1.1
P54 Chapter 10 - Non-Aided Schemes
P54-TM-EN-1.1 299
Chapter 10 - Non-Aided Schemes P54
Z1 Extension (A)
ZL
A Z1A B
Z1 Extension (B)
E02739
In this scheme Zone 1X is enabled and set to overreach the protected line. A fault on the line, including one in the
end 20% not covered by Zone 1, results in instantaneous tripping followed by autoreclosure. Zone 1X has resistive
reaches and residual compensation similar to Zone 1. The autorecloser is used to inhibit tripping from Zone 1X so
that on reclosure the device operates with Basic scheme logic only, to co-ordinate with downstream protection for
permanent faults. Therefore transient faults on the line are cleared instantaneously, which reduces the probability
of a transient fault becoming permanent. However, the scheme can operate for some faults on an adjacent line,
although this is followed by autoreclosure with correct protection discrimination. Increased circuit breaker
operations would occur, together with transient loss of supply to a substation.
Fault trip Z1X time delay
First fault trip = tZ1
Fault trip for persistent fault on auto-reclose = tZ2
The Zone 1 extension scheme can be disabled, permanently enabled or just brought into service when the
communication channel fails and the aided scheme is inoperative. If used in conjunction with a channel-aided
scheme, Z1X can be set to be enabled when Ch1 or Ch2 fails, or when all channels fail, or when any channel fails.
Zone 1 extension schemes have the following reaches:
● Z1 Ext Ph range 100% to 9999 % with steps of 1%
● Z1 Ext Gnd range 100% to 9999 % with steps of 1%
● Z1 Ext Ph R range 100% to 200% with steps of 1%
● Z1 Ext Gnd R range 100% to 200% with steps of 1%
Note:
Beyond 500/IN ohms accuracy of the measurement is not guaranteed. The multiplier should result in no more than 500/IN.
300 P54-TM-EN-1.1
P54 Chapter 10 - Non-Aided Schemes
490
Reset Zone 1 Ext 876
& Z1X Active
Z1 Ext Scheme
Enabled
En. on Ch1 Fail 1
&
En. on Ch2 Fail
En. All Ch Fail
En. Any Ch Fail &
&
&
317
Aid 1 Chan Fail
318
1
Aid 2 Chan Fail
Aid. 1 Selection
DE Z1e 3Ch
1
DE Perm.Z1e3Ch
DE BlockZ1e3Ch &
1 Z1X Active
Aid1 Trip En. A
1
Aid1 Trip En. B
Aid1 Trip En. C
Aid. 1 Selection
DE Z1e 1Ch
1 &
DE Perm.Z1e1Ch
DE BlockZ1e1Ch
P54-TM-EN-1.1 301
Chapter 10 - Non-Aided Schemes P54
Zone 2 IED1
Zone 1 IED 1
Zone 1 IED 2
Zone 2 IED 2
IED 1 IED 2
V02740
Any fault in the reach of Zone 1 results in fast tripping of the local circuit breaker. For an end zone fault for IED 1
(near IED 2) with remote infeed (from IED 2), the remote breaker is tripped in Zone 1 by the remote device at IED 2.
The local device (IED 1) can recognise this by detecting loss of load current in the healthy phases. This condition, in
conjunction with operation of a Zone 2 comparator at IED 1P, can be used to trip the local circuit breaker.
Before an accelerated trip can occur, load current must be detected before the fault. The loss of load current
opens a window during which time a trip occurs if a Zone 2 comparator operates. A typical setting for this window
is 40ms as shown in the figure below, although this can be altered in the LoL Window setting. The accelerated trip
is delayed by 18ms to prevent initiation of a loss of load trip due to circuit breaker pole discrepancy occurring for
clearance of an external fault. The local fault clearance time can be deduced as follows:
t = Z1d + 2CB + LDr + 18ms
where:
● Z1d = Maximum downstream zone 1 trip time
● CB = Breaker operating time
● LDr = Upstream level detector (LOL <1) reset time
For circuits with load tapped off the protected line, care must be taken in setting the loss of load feature to ensure
that the undercurrent level detector setting is above the tapped load current. When selected, the loss of load
feature operates with the main distance scheme that is selected. This provides high speed clearance for end zone
faults when the Basic scheme is selected or, with permissive signal aided tripping schemes, it provides high speed
back up clearance for end zone faults if the channel fails.
Note:
Loss of load tripping is only available where three pole tripping is used.
302 P54-TM-EN-1.1
P54 Chapter 10 - Non-Aided Schemes
Note:
Assertion of the Any Trip DDB signal or the Inhibit LOL DDB signal will prevent LOL tripping.
LOL Scheme
Enabled
En. On Ch1 Fail 1
&
En. On Ch2 Fail
En. All Ch Fail
En. Any Ch Fail &
&
&
317
Aid 1 Chan Fail
318 1
Aid 2 Chan Fail
Tripping Mode
3 Pole
491 1 18 ms
Inhibit LoL & SD
654
Q Loss ofLoad Trip
Any trip 522 R
LOL Window
1365
I> LoL A
1366
I> LoL B &
1367
tLOL
I> LoL C
966 &
Zone2 AN Element
967 &
Zone2 BN Element
968 &
Zone2 CN Element
1
969 &
Zone2 AB Element
970 &
Zone2 BC Element
971 &
Zone2 CA Element V02741
P54-TM-EN-1.1 303
Chapter 10 - Non-Aided Schemes P54
304 P54-TM-EN-1.1
CHAPTER 11
306 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
1 CHAPTER OVERVIEW
This chapter describes special blocking and protection functions, which use Power swing Analysis.
This chapter contains the following sections:
Chapter Overview 307
Introduction to Power Swing Blocking 308
Power Swing Blocking 310
Out of Step Protection 325
P54-TM-EN-1.1 307
Chapter 11 - Power Swing Functions P54
Note:
Power swings do not involve earth, so only phase-phase impedances are affected.
For stable power swings, distance protection should not trip. To prevent tripping, a Power Swing Blocking (PSB)
function is usually provided to compliment Distance protection.
For unstable power swings, there may be a strategy for instigating a controlled system split. In this case, distance
protection should not trip during loss of stability. If unstable power swings or Pole-Slipping conditions might be
expected, certain points on the network may be designated as split points, where the network should be split if
unstable (or potentially unstable) conditions occur. Strategic splitting of the system can be achieved by means of
dedicated Out-of-Step Tripping protection (OOS or OST protection). Or it may be possible to achieve splitting by
strategically limiting the duration for which the operation of a specific distance protection is blocked during power
swing conditions.
A method often used to help understand power system stability and Pole Slipping is called Equal Area Criterion.
This is based on a number of operational curves as outlined in the figure below:
Power Curve 1
Area 2
F Area 1
A E G
Po
Out of step
D
Curve 2
Curve 3
C
B
θ
0º θ0 θ1 90º θ2 θ3 180º
Phase angle difference between two ends
V02762
Figure 177: Power transfer related to angular difference between two generation sources
The figure describes the behaviour of a power system with parallel lines connecting two sources of generation.
● Curve 1 represents pre-fault system operation through parallel lines where the transmitted power is Po.
● Curve 2 represents transmitted power during a phase-phase-earth fault.
● Curve 3 represents a new power curve when the faulted line is tripped.
308 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
At fault inception, the operating point A moves to B, which is a reduced power transfer level. There is, therefore, a
surplus of power (A to B) at that sending end and a corresponding deficit of power at the receiving end. The
sending end generators start to speed up, and the receiving end generators start to slow down, so the phase
angle θ increases, and the operating point moves along curve 2 until the fault is cleared (point C). At this point, the
phase angle is θ1. The operating point now moves to point D on curve 3 which represents the power transfer curve
when just one line is in service. There is still a power surplus at the sending end and a deficit at the receiving end,
so the generators continue to lose synchronism and the operating point moves further along curve 3.
If, at some point between E and G (point F) the generators are rotating at the same speed, the phase angle will
stop increasing. According to the Equal Area Criterion, this occurs when Area 2 is equal to Area 1. The sending end
will now start to slow down and receiving end to speed up. Therefore, the phase angle starts to decrease and the
operating point moves back towards E. As the operating point passes E, the net sending end deficit again becomes
a surplus and the receiving end surplus becomes a deficit, so the sending end generators begin to speed up and
the receiving end generators begin to slow down. With no losses, the system operating point will oscillate around
point E on curve 3, but in practise the oscillation is damped, and the system eventually settles at operating point E.
So, if Area 1 is less than Area 2, the system will oscillate but will stay in synchronism. This swing is usually called a
recoverable, or stable, power swing. If, on the contrary, the system passes point G with a further increase in angle
difference between sending and receiving ends, the system loses synchronism and becomes unstable. This will
happen if the initial power transfer Po is so high that the Area 1 is greater than Area 2. This power swing is not
recoverable and is usually called an Out-of-Step condition or a Pole Slip condition. In such a case, only system
separation and subsequent re-synchronising of the generators can restore normal system operation.
The point G is shown at approximately 120°, but this can vary. If, for example, the pre-fault transmitted power (Po)
was high and the fault clearance was slow, Area 1 would be greater. For the system to recover from this case, the
angle θ would be closer to 90º. Similarly, if the pre-fault transmitted power Po was low and fault clearance fast,
Area 1 would be small, and the angle θ could go closer to 180º with the system remaining stable.
P54-TM-EN-1.1 309
Chapter 11 - Power Swing Functions P54
310 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
Start of
power swing End of
power swing
i (t)
3 cycles
PH1
PH2
t1 t2 t3
t 2: Threshold 2 invoked. PH2 goes low on account of threshold being increased . PH1 remains high,
because there continues to be a D i
t 3: PH1 goes low as power swing has diminished and D i goes below threshold 1
V02769
Figure 178: Phase selector timing for power swing condition
P54-TM-EN-1.1 311
Chapter 11 - Power Swing Functions P54
i (t)
PH1
PH2
t1 t2 t3
t2: Fault current value appears in 2 cycle buffer . This equals present fault current value so D i is reduced to
zero. PH1 therefore goes low. PH2 remains high because value in PH 2 memory is a stored value .
t3: Fault is cleared so PH 2 goes low. PH1 stays low even though there is a new D I, because the absolute
current value is also taken into consideration .
V02770
Start of
power swing
i (t)
3 cycles
PH1
PH2
t1 t2 t3 t4 t5
t2: Threshold 2 invoked (10%In). PH2 goes low on account of threshold being increased (from 5%IN to 10%In).
PH1 remains high, because there continues to be a D i
Figure 180: Phase selector timing for fault during a power swing
312 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
Note:
If the Slow Swing feature is not Enabled, very slow power swings (< 0.5 Hz) may not be detected.
The Slow Swing method is based on changing impedance measurements and uses a pair of configurable
concentric quadrilateral zones on the impedance plane (Zone 7 and Zone 8). Since power swings don’t involve
earth, the impedance measurements are based on positive sequence quantities and only phase-phase
measurements are necessary. The characteristic is shown in the following figure:
+jX
PSB Z8 Zone 8
PSB Z7 Zone 7
Dt
ZL
Z1 = V1/I1
PSB Z7'
PSB Z8'
V02744
The elapsed time defines the rate of change of impedance. If the rate of change is high, the change is due to a
fault. If the rate of change is low, the protection indicates a slow power swing. So, if the time taken for the
impedance trajectory to pass through zone 8 into zone 7 is greater than the time defined by the PSB timer, a slow
power swing is deemed to be in progress. If the time taken for the impedance trajectory to pass through zone 8
into zone 7 is less than that defined by the PSB timer, it is deemed to be a fault.
In other words, a power swing is indicated if the following condition is true:
Dt > PSB Timer
Both Zone 7 and Zone 8 characteristics are based on the positive sequence impedance measurement; Z1 = V1/I1.
The minimum current (sensitivity) needed for Zone 7 and Zone 8 measurements is 5%In.
P54-TM-EN-1.1 313
Chapter 11 - Power Swing Functions P54
314 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
Actions upon detection of a fault during a power swing (Distance option only)
● The block signal is only removed from zones that start within 2 cycles of a fault being detected. This
improves stability for external faults during power swings. Any measuring zone that was detecting an
impedance within its characteristic before The phase selector detected the fault will remain blocked. This
minimizes the risk of tripping for a swing impedance that may naturally be passing through Zone 1, and
could otherwise cause a spurious trip if all zones were unblocked on fault inception. Any measuring zone
that picks up beyond the two cycle window will remain blocked. This minimises the risk of tripping for a
continued swing that may pass through Zone 1, and could otherwise cause a spurious trip if all zones were
allowed to unblock together.
Allow Trip should a power swing locus remain within a trip zone characteristic for a duration equal to
the zone time delay, the trip will be allowed to happen;
Blocking to keep stability for that zone, even if a power swing locus should enter it;
Delayed Unblock maintains the block for a set duration. If the swing is still present after the “PSB Timeout Set”
window has expired, tripping is allowed as normal.
A simplified logic diagram showing operation of the power swing blocking is shown below:
P54-TM-EN-1.1 315
Chapter 11 - Power Swing Functions P54
V02787
Characteristic
Both polygon characteristics are independent and have independent settings for their respective reactance and
resistive reaches.
316 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
+jX
Z6
Z5
Predictive Out of
step trip
ZL
Recoverable swing
Z5'
Z6'
V02709
Both the inner (Zone 5) and outer (Zone 6) characteristics, as shown above, are settable in positive sequence
impedance terms to ensure correct Out of Step detection during open pole swing conditions. Hence, there is only
one Z5 and Z6 positive sequence impedance polygon characteristic instead of 6 characteristics for each measured
loop. The measured positive sequence impedance is calculated as:
Z1 = V1/I1
Where V1 and I1 are positive sequence voltage and current derived from the measured phase quantities. Note that
during symmetrical power oscillations, there is no difference between phase impedance loops and positive
sequence impedance loop, whilst for the open pole oscillations the phase and positive sequence impedances are
different. This fact must be taken into account during testing/commissioning.
All four resistive blinders are parallel, using the common angle setting ‘α’ that corresponds to the angle of the total
system impedance ZT (= ZS + ZL + ZR), where ZS and ZR are equivalent positive sequence impedances at the
sending and receiving ends and ZL positive sequence line impedance. Tilting of the reactance line and residual
compensation is not implemented.
In figure above, the solid impedance trajectory represents the locus for the non-recoverable power oscillation, also
known as pole slip or out of step condition. The dotted impedance trajectory on the other hand represents a
recoverable power oscillation, usually called swings.
Operating principle
The Out of Step detection algorithm is based on measuring the speed of positive sequence impedance passing
through the set ∆Z region. As soon as measured positive sequence impedance touches the outer polygon, a timer
is started.
If the disturbance takes less than 25 ms from entering zone 6 to entering zone 5, the relay will consider this to be a
power system fault and not an out of step trip condition. The timer of 25 ms is a fixed timer in the logic and not
user accessible. During a power system fault, the speed of impedance change from a load to a fault is fast, but the
relay may operate slower for marginal faults close to a zone boundary, particularly for high resistive faults inside
P54-TM-EN-1.1 317
Chapter 11 - Power Swing Functions P54
the zone operating characteristic and close to the Z5 boundary. Therefore, the fixed time of 25 ms is implemented
to provide sufficient time for a distance element to operate and therefore to distinguish between a fault and an
extremely fast power system oscillation.
If the disturbance takes more than 25 ms but less than DeltaT set time from entering Zone 6 to entering Zone 5,
this will be seen as a very fast oscillation. Therefore, the relay will trip if setting option 2 or 4 was selected. The
minimum DeltaT setting is 30 ms, allowing 5 ms margin to the fixed 25 ms timer.
If the disturbance takes longer than the DeltaT setting time to enter Zone 5 after entering Zone 6 then it is
considered as a slow power oscillation. On entering Z5, the relay will record the polarity of the resistive part of the
positive sequence impedance. Two scenarios are possible:
1. If the resistive part of the positive sequence impedance leaves Z5 with the same polarity as previously
recorded on entering Zone 5, it is deemed a recoverable swing. No tripping will be issued.
2. If the resistive part of the positive sequence impedance has the opposite polarity when exiting Zone 5 to
that of the recorded polarity on Zone 5 entering, an Out of Step condition is recognised, followed by the
tripping if setting option 3 or 4 was selected. It should be noted that in the case when the DeltaT timer did
not expire and setting option 3 is selected, the Out of Step condition will also be detected, followed by OST
operation.
As the tripping mode for the detected Out of Step condition is always 3 ph trip, the ‘Predictive OST’ and OST DDB
signals are mapped to the 3ph tripping in the default PSL. Also, Out of Step operation will block auto-reclose
function. The Out of Step tripping time delay TOST is also available to delay the OST tripping command until the
angle between internal voltages between two ends are at 240 deg closing towards 360 deg. This is to limit the
voltage stress across the circuit breaker. In the case of a fault occurring during the swing condition, the out of step
tripping function will be blocked.
The Out of Step algorithm is completely independent from the distance elements and setting free power swing
detection function. The load blinder does not have any effect on the OST characteristics. For the Out of Step
operation, the minimum positive sequence current of 5%In must be present.
The Out of Step algorithm is given in the figure below.
Start Z5
& Fault detected
Start Z6 25ms
&
0
tost
t
0
&
& Pred. OST
de lta T ≥ t
1 0
OST Mod e
OST Disabled & OST
& Polarity Reversed?
Pred. OST Trip
1 & Polarity detector
Pred. & OST Trip
&
OST Trip & ≥
1 1 &
Start Z6
Note: R1 is me asured resistive compon ent o f positive sequ ence imp edan ce Reset fu nction
V02788
318 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
threshold, so the fault will be detected by the phase selector. Operation of the phase selector in this condition
unblocks the PSB function, to allow tripping of Distance elements.
To provide stability for external faults, the blocking signal is only removed from zones that start within two cycles
of the phase detector recognising the fault:
Any Distance element measuring an impedance inside its characteristic before the phase selector detects the fault
remains blocked. This prevents tripping for a swing impedance that may be coincidentally passing through a fast-
acting zone, and which could cause spurious tripping if all elements were unblocked without qualification.
Any Distance element that measures an impedance inside its characteristic after the two cycle ΔI window of the
phase selector has expired, remains blocked. This prevents tripping for a continued swing that may pass through a
fast acting zone which could cause spurious tripping if the element was allowed to unblock by an unqualified
phase selector reset.
Note:
The PSB Unblock dly timer is common to all elements.
The PSB Unblock dly is used to time the duration for which the swing is present. The intention is to allow the
distinction between a stable and an unstable swing. If after the timeout period the swing has still not stabilised, the
block for selected zones can be released (unblocking), giving the opportunity to split the system. If no unblocking is
required, set to maximum (10 s).
There is a further timer associated with the PSB function. This is the PSB Reset Delay timer. This timer is provided to
maintain the power swing detection for a period after the superimposed current detection (ΔI) has reset. ΔI
naturally tends to zero twice during each power swing cycle (around the current maxima and minima in the swing
element). A short time delay ensures continued PSB pick-up during these ΔI minima.
The PSB Reset Delay is used to maintain the PSB status when DI naturally is low during the swing cycle (near the
current maxima and minima in the swing envelope). A typical setting of 0.2s is used to seal-in the detection until DI
has chance to appear again.
The WI Trip PSB setting determines what will happen if a power swing is detected whilst the Weak Infeed (WI)
tripping feature is being used and the WI condition is present for longer than the WI Trip Delay time. If Blocking
is selected, the weak infeed operation will be disabled for the duration of the swing. If Delayed Unblock is
chosen, the weak infeed element block will be removed after drop off timer PSB Unblock dly has expired, even if
the swing is still present. This allows system separation when swings fail to stabilise. In Allow trip mode, the
weak infeed element is unaffected by power swing detection.
P54-TM-EN-1.1 319
Chapter 11 - Power Swing Functions P54
jX
Zone x
-10°
Blind Region
Blind Region
20%
-jX
V02775
The area is defined by lines created with angles fixed at 10° closer to the resistive axis than those created by the
load blinder angle setting (Load/B Angle Ph and Load/B Angle Gnd -10°, shown in the shaded Power Swing region
in the diagram above) and a circular arc with a radius concentric with, and equivalent to 20% greater than, the
load blinder impedance setting (Z< Blinder Imp Ph and Z< Blinder Imp Gnd +20%, shown in the shaded Power
Swing region in the diagram above).
Note:
This power swing conditions are completely independent of the slow swing associated with Zone 7 and Zone 8.
320 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
Z_OperateInternal 297
& Power Swing
Power Swing
Blocking
1691 3 cycles
Any Dist Start
t 0
& 1014
Ph1 0 t 1 P Swing Detector
t
& Block selected element
0 &
PSB Unblocking
Enabled
V Impedance
I Calculator
PSB Z7
607
PSB Z8 Slow PSB
Detector
PSB Z7'
Module
PSB Z8' Quad
PSB R7 characteristic
definition
PSB R8
PSB R7'
PSB R8'
Alpha Z7/Z8 V02799
Note:
This is a simplified representation to highlight the outputs of the Power Swing Blocking function.
P54-TM-EN-1.1 321
Chapter 11 - Power Swing Functions P54
swings, we recommend setting Slow Swing to Enabled to complement the automatic setting-free detection
algorithm.
To configure the slow power swing function you need to set the resistive and reactive limits of the Zone 7 and Zone
8 quadrilaterals. You also need to set the PSB Timer which defines the critical time period of the transition between
the two zones and which is characteristic of the slow swing.
Whichever power swing detector is responsible for applying PSB, the removal of PSB is defined by two settings –
the PSB Reset Delay and (if an unblocking philosophy is employed) the PSB Unblock dly.
Maximum Load
½ Rx Ph. Resistive
V02750
322 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
The angle Alpha should be set equal to the angle of the total impedance ZT:
a = ÐZT
+jX
Zone 8
Zone 7
ZR
ZL α = ÐZ T
ZT
Resistive reverse (R’) Resistive forward (+R)
ZS
V02751
(θ1 − θ 2 ) ⋅ f nom
∆t =
f PS
where
● angles q1 and q2 are defined in the following figure
● fnom is the nominal frequency
● fPS is the maximum Power Swing frequency to be taken into account
Since any power swing with fPS >= 0.5Hz can be detected by the setting-free delta current algorithm, only power
swings with fPS < 0.5Hz Hz need to be considered for Slow Power Swing detection. We recommended setting fPS to
1Hz because this value provides sufficient security margin.
P54-TM-EN-1.1 323
Chapter 11 - Power Swing Functions P54
ZR Zone 7 Zone 8
ZL
ZT
2 q1
q2
ZT
ZS
V02752
324 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
+jX
OST Z6 Zone 6
OST Z5 Zone 5
OST Z5'
OST Z6'
V02760
P54-TM-EN-1.1 325
Chapter 11 - Power Swing Functions P54
The OST principle uses positive sequence impedances. The positive sequence impedance is calculated as Z1 =
V1/I1, where V1 and I1 are the positive sequence voltage and current quantities derived from the measured phase
quantities. The concentric quadrilaterals are designated Zone 5 and Zone 6. Zone 5 encompasses possible system
fault impedances and sits within Zone 6. Because OST and Predictive OST quadrilaterals are based on positive
sequence impedances, all OST conditions are covered by a single measurement. Both quadrilaterals are
independent and have independent reach settings.
All four resistive blinders are parallel, using the common angle setting (a) that corresponds to the angle of the total
system impedance (ZT = ZS + ZL + ZR), where ZS and ZR are equivalent positive sequence impedances at the
sending and receiving ends and ZL positive sequence line impedance. The reactance lines are also parallel as
neither reactance line tilting nor esidual compensation is implemented.
In the figure, the purple solid impedance trajectory represents the locus for the non-recoverable power sawing,
known as a pole slip or Out Of Step condition. The dotted green impedance trajectory represents a recoverable
power swing.
As the tripping mode for the detected Out-of-Step condition is always three-phase, the Pred. OST and OST DDB
signals are mapped to the three-phase tripping signal in the default programmable scheme logic.
326 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
The Out-of-Step tripping time delay (Tost), delays the OST tripping command until the angle between internal
voltages between the two ends are at 240 degrees closing towards 360 degrees. This limits the voltage stress
across the circuit breaker. If a fault occurs during the swing condition, the Out-of-Step tripping function is blocked.
The Out-of-Step algorithm is completely independent from the distance elements and the power swing detection
function. The load blinder does not affect the OST characteristics. In common with other similar functions, a
minimum positive sequence current of 5%In is needed for Out-of-Step operation.
OST Mode
553
OST Disabled & OST
& Polarity Reversed?
Pred. OST Trip
1 & Polarity detector
Pred. & OST Trip Reset function
& Not reversed
OST Trip &
1 &
555
Start Z6
Setting OST Trip is the most commonly used approach when this protection is applied. OST Trip should be
used when Out-of-Step conditions are probable. If Out-of-Step conditions are detected, the OST command will be
issued to split the system at the pre-determined points. A disadvantage of the OST Trip option compared with
the ‘Predictive’ options is that tripping will take a little longer so that the power oscillations may escalate further
after separation and the split parts may become separately unstable. An advantage, however, is that the decision
P54-TM-EN-1.1 327
Chapter 11 - Power Swing Functions P54
to split the system will always be valid even if the accurate system data and setting parameters cannot be
obtained.
The predictive setting options Pred. OST Trip and Pred. & OST Trip are recommended for systems
where Out-of-Step conditions could possibly occur, and where an early system split should minimise the phase
shift between generation sources. This should maximise the chances for the separated parts of the system to
stabilise as quickly as possible. Special care must be taken when these settings are used to ensure that the circuit
breakers at the different terminals do not open when the voltages at different ends are in anti-phase. This is
because most circuit breakers are not designed to break current at double the nominal voltage. Attempting to
break the current at double the nominal voltage could lead to flash-over and circuit breaker damage.
‘Predictive’ settings are designed to detect and trip for fast power oscillations. When predictive tripping is used
with a circuit breaker capable of operating in typically two-cycles, the two voltages angles may rapidly move in
opposite directions at the time of opening the circuit breaker. So, if you use the predictive settings you need to
apply settings that will ensure that the circuit breaker opening occurs well before the phase difference between
the different terminals approaches 180º. This means that accurate settings can only be determined by exhaustive
system studies.
The setting Pred. & OST Trip provides two stages of OST. If a power system oscillation is very fast, the
combination of ∆R (the difference between the Zone 5 and Zone 6 resistive reaches), and the Delta T settings, must
be set so that Pred. OST Trip operates. If the oscillation is slower, the condition for the predictive OST is not
met and so tripping is dictated by the OST condition being met. For the OST condition to be met, the resistive
component of the impedance must leave Zone 5 with opposite polarity compared with when it entered. If the
polarity is opposite when Zone 5 resets, OST will trip. If the polarity is the same when Zone 5 resets, OST will not
trip. This distinguishes between a slower non-recoverable oscillation and recoverable swings.
You should disable OST for applications on lines where unrecoverable power oscillations are not expected, or not
expected to be severe. This is likely to apply to strong interconnected systems operating with three-phase tripping.
+jX
OST Z6 Zone 6
OST Z5 Zone 5
OST Z5'
OST Z6'
V02763
Figure 192: OST setting determination for the positive sequence resistive component OST R5
328 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
ZT is the total system positive sequence impedance equal to ZS + ZL + ZR, where ZS and ZR are the equivalent
positive sequence impedances at the sending and receiving ends and ZL is the positive sequence line impedance.
θ is the angular difference between the voltages at the sending and receiving ends beyond which no system
recovery is possible.
To determine the settings for OST, the minimum inner resistive reach of OST R5 (R5min) needs to be calculated.
The figure above shows that:
R5min = (ZT/2) / tan(θ/2
Next the maximum (limit value) for the outer resistive reach OST R6 (R6 max) needs to be calculated. Referring to
the figure below, point A must not overlap with the load area for the worst assumed power factor of 0.85 and the
lowest possible ZT angle α.
+jX
OST Z6 Zone 6
ZT LOAD
OST Z6'
V02764
β = 32 + 90 – α
Z load min = OA
Where:
● Z load min is the minimum load impedance radius
● 32º is the load angle that corresponds to the lower power factor of 0.85
● α is the load blinder angle (Blinder Angle) that matches the ZT angle
Therefore:
R6max < Z load min(Cos β)
Starting from the limit values R5min and R6max, the actual OST R5 and OST R6 reaches will be set in conjunction
with the Delta T setting.
P54-TM-EN-1.1 329
Chapter 11 - Power Swing Functions P54
Note:
The R6max reach must be greater than the maximum resistive reach of any distance zone to ensure correct initiation of the
25 ms and Delta T timers. However, the R5min reach could be set below the distance maximum resistive reach (inside the
distance characteristic) if an extensive resistive coverage is required, meaning that Out-of-Step protection does not pose a
restriction to the quadrilateral applications.
For each zone, we receommend setting the positive and negative limits to be the same so, OST R5’ = OST R5, OST
Z5’ = OST Z5, OST R6’ = OST R6, and OST Z6’ = OST Z6.
Note:
You cannot assume that the rate-of-change of positive sequence impedance while crossing the OST R6 – OST R5 region is the
same as the average rate-of-change of positive sequence impedance for the whole swing cycle. A false assumumption could
lead to incorrect predictive OST operation.
Note:
For a fault, the OST R6 – OST R5 region will be crossed faster than 25ms, therefore even very fast oscillations up to 7Hz will
not be mistaken as a fault condition and predictive OST will not operate.
OST setting
For the OST Trip setting option, such a precise setting of the blinders and Delta T is not necessary. This is
because for a wide ∆R region and a short Delta T setting, any oscillation will be successfully detected. However,
the fault impedance must pass through the ∆R region faster than the Delta T setting.
330 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
Therefore, for the OST Trip setting, assume that θ = 120° and set:
● OST R5 = OST R5’ = R5min = ZT/3.46
● OST R6 = OST R6’ = R6max
● Delta T = 30 ms
Delta T always expires. Therefore, the setting value given above will secure the detection of a wide range of
oscillations, starting from very slow oscillations (caused by recoverable swings) up to a fastest oscillation limit of
7Hz. Note that any fault impedance will pass the OST R6 – OST R5 region faster than the minimum settable Delta T
time of 30ms.
P54-TM-EN-1.1 331
Chapter 11 - Power Swing Functions P54
+jX
OST Z6 Zone 6
OST Z5 Zone 5
DR
OST trip
MOVs operation
ZL
OST R6' OST R5'
Resistive reverse (R’) OST R5 OST R6
Resistive forward (+R)
OST Z5'
OST Z6'
V02765
Note:
If the OST Trip setting is chosen, the timer when triggered, will eventually expire as the power oscillations progress, therefore
the MOV operation will not have any impact on Out-of-Step operation.
332 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
Power Curve 1
Area 2
F Area 1
A E G
Po
Out of step
D
Curve 2
Curve 3
C
B
θ
0º θ0 θ1 90º θ2 θ3 180º
Phase angle difference between two ends
V02762
The figure above represents power angle curves, with no AR being performed, as follows:
Curve 1 - Pre-fault system operation via parallel lines where transmitted power is Po
Curve 2 - Transmitted power significantly reduced during two-phase to ground fault
Curve 3 - New power curve when the parallel line is tripped (fault cleared)
It can be seen that at a fault instance, the operating point A moves to B, with a lower transfer level. There is
therefore a surplus of power DP=AB at the sending end and the corresponding deficit at the receiving end. The
sending end machines start to speed up, and the receiving end machines to slow down, so phase angle θ
increases, and the operating point moves along curve 2 until the fault is cleared, when the phase angle is θ1. The
operating point now moves to point D on curve 3 which represents one line in service. There is still a power surplus
at the sending end, and deficit at the receiving end, so the machines continue to drift apart and the operating
point moves along curve 3. If, at some point between E and G (point F) the machines are rotating at the same
speed, the phase angle will stop increasing. According to the Equal Area Criterion, this occurs when area 2 is equal
to area 1. The sending end will now start to slow down and receiving end to speed up. Therefore, the phase angle
starts to decrease and the operating point moves back towards E. As the operating point passes E, the net sending
end deficit again becomes a surplus and the receiving end surplus becomes a deficit, so the sending end
machines begin to speed up and the receiving end machines begin to slow down. With no losses, the system
operating point would continue to oscillate around point E on curve 3, but in practise the oscillation is dumped,
and the system eventually settles at operating point E.
P54-TM-EN-1.1 333
Chapter 11 - Power Swing Functions P54
To resume, if area 1<area 2, the system will stay in synchronism. This swing is usually called a recoverable power
swing. If, on contrary, the system passes point G with a further increase in angle difference between sending and
receiving ends, the system drifts out of synchronism and becomes unstable. This will happen if the initial power
transfer Po was set too high in the figure above, so that the area 1 is greater than area 2. This power swing is not
recoverable and is usually called out of step or out of synchronism or pole slip condition. After this, only system
separation and re-synchronising of the machines can restore normal system operation.
In the figure above, the point G is shown at approximately 120° deg, but it is not true in all cases. If, for example the
pre-fault transmitted power (Po) was too high and if the fault clearance was slow, the area 1 will be greater so for
the system to recover the angle θ would be close to 90 deg. On contrarily, if the pre-fault transmitted power Po
was low and fault clearance fast, the area 1 will be small, so that based on area comparison, the angle θ could go
closer to 180 deg and the system will still remain stable.
The actual angle difference at which system will become unstable could only be determined by a particular system
studies, but for the purpose of settings recommendation where ‘OST’ setting is selected, the typical angle beyond
which system will not recover is assumed to be 120 deg.
334 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
+jX
OST Z6 Zone 6
OST Z5 Zone 5
OST Z5'
OST Z6'
V02763
Figure 196: Setting determination for the positive sequence resistive component R5
ZT
R5 min = 2‚
tan 2
Where ZT is a total system positive sequence impedance that equals to ZS + ZL + ZS, where ZS and ZR are
equivalent positive sequence impedances at the sending and receiving ends and ZL positive sequence line
impedance. ‘θ’ is an angle difference between the internal voltages at sending and receiving ends beyond which
no system recovery is possible.
The next step is to determine the maximum (limit value) for the outer resistive reach R6. It must be insured that
Point A in Figure 8 does not overlap with the load area for the worst assumed power factor of 0.85 and the lowest
possible ZT angle .a
P54-TM-EN-1.1 335
Chapter 11 - Power Swing Functions P54
+jX
OST Z6 Zone 6
ZT LOAD
OST Z6'
V02764
β = 32 + 90 – α
Z load min = OA
R6MAX < Zload min x cos β
Where:
● Zload min is the minimum load impedance radius calculated above which already has built in sufficient
margin
● 32 deg is the load angle that corresponds to the lower power factor of 0.85
● ‘a’ is the load blinder angle that matches ZT angle
The setting of negative resistance R5’ should equal the R5 to accommodate the ‘load import’ condition. Starting
from the limit values R5MIN and R6MAX the actual R5 and R6 (including the corresponding R5’ and R6’) reaches will
be set in conjunction with the ‘Delta t’ setting below.
Note:
R6MAX reach must be greater than the maximum resistive reach of any distance zone to ensure correct initiation of the 25 ms
and ‘Delta t’ timers. However, the R5MIN reach could be set below the distance maximum resistive reach (inside the distance
characteristic) if an extensive resistive coverage is required, meaning that Out of Step protection does not pose a restriction to
the quad applications.
Setting of reactance lines Z5 and Z6 will depend on how far from the relay location the power oscillations are to be
detected. Normally, there is only one point where the system is to be initially split and that point will be determined
by system studies. For that reason, the Out of Step protection must be enabled at that location and disabled on all
others. To detect the Out of step conditions, the Z5’-Z5 and Z6’-Z6 setting must be set to comfortably encompass
the total system impedance ZT, as shown in the figure above Typical setting could be:
Z5 = Z5’ = 1/2 x 2 ZT = ZT
The Z6 and Z6’ setting is not of great importance and could be set to Z6 = Z6’ = 1.1 x Z5
336 P54-TM-EN-1.1
P54 Chapter 11 - Power Swing Functions
The aim of pushing the R5 setting to the right is to detect the fast oscillation as soon as possible to gain sufficient
time to operate the breaker before the two source voltages are in opposite direction. The only restriction would be
the limitation of the ‘Delta t’ minimum time delay of 30 ms and the speed of oscillation. Set ‘Delta t’ so that the
following condition is satisfied:
Note:
‘Delta t’ does not expire after positive sequence impedance has passed the R6-R5 region
For this setting, knowledge of the accurate rate of change of swing impedance when crossing the R6-R5 region is
essential and therefore must be based on system studies.
Assumption that the rate of change of the positive sequence impedance during crossing the R6-R5 region is
average rate of change for the whole swing cycle is wrong and could easily lead to incorrect ‘Predictive OST’
operation.
Note:
For the fault, the R6-R5 region will be passed faster than 25 ms, therefore even very fast oscillations of 7 Hz will not be
mistaken with the fault condition and ‘Predictive OST’ will not operate.
OST setting:
For the ‘OST’ setting option the precise setting of blinders and ‘Delta t’ is not necessary. This is based on the fact
that:
The wider the ∆R region and the shorter the ∆t setting, any oscillation will be successfully detected. The only
condition is that the fault impedance must pass through the ∆R region faster than ∆t setting.
Therefore, for the ‘OST’ setting assume that θ = 120° and set:
● R5 = R5’ = R5MIN = ZT/3.46
● R6 = R6’ = R6MAX
● Delta t = 30 ms
The point is that ‘Delta t’ always expires, therefore the above setting will secure the detection of a wide range of
oscillations, starting from very slow oscillations caused by recoverable swings up to the fastest oscillation of 7 Hz.
It should be noted that any fault impedance will pass the R6-R5 region faster than the minimum settable ‘Delta t’
time of 30 ms.
Predictive OST or OST setting:
As per ‘Predictive OST’ above.
P54-TM-EN-1.1 337
Chapter 11 - Power Swing Functions P54
+jX
OST Z6 Zone 6
OST Z5 Zone 5
DR
OST trip
MOVs operation
ZL
OST R6' OST R5'
Resistive reverse (R’) OST R5 OST R6
Resistive forward (+R)
OST Z5'
OST Z6'
V02765
Note:
If ‘OST’ setting is chosen, the timer when triggered, will eventually expire as the power oscillations progress, therefore MOV
operation will not have any impact on Out of Step operation.
338 P54-TM-EN-1.1
CHAPTER 12
AUTORECLOSE
Chapter 12 - Autoreclose P54
340 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
1 CHAPTER OVERVIEW
Selected models of this product provide sophisticated Autoreclose (AR) functionality. The purpose of this chapter is
to describe the operation of this functionality including the principles, logic diagrams and applications.
This chapter contains the following sections:
Chapter Overview 341
Introduction to Autoreclose 342
Autoreclose Implementation 345
Logic Modules (Single CB) 352
Logic Modules (Dual CB) 382
Setting Guidelines 433
P54-TM-EN-1.1 341
Chapter 12 - Autoreclose P54
2 INTRODUCTION TO AUTORECLOSE
Approximately 80 - 90% of faults on transmission lines and distribution feeders are transient in nature. This means
that most faults do not last long, and are self-clearing if isolated. A common example of a transient fault is an
insulator flashover, which may be caused, for example, by lightning, clashing conductors, or wind-blown debris.
Protection functions detecting the flashover will cause one or more circuit breakers to trip and may also remove
the fault. If the source is removed, the fault does not recur if the line is re-energised.
The remaining 10 – 20% of faults are either semi-permanent or permanent. A small tree branch falling onto the
line for example, could cause a semi-permanent fault. Here the cause of the fault would not be removed by
immediate tripping of the circuit, but could possibly be burnt away during a time-delayed trip. Permanent faults
could be broken conductors, transformer faults, cable faults or machine faults, which must be located and
repaired before the power supply can be restored. In many fault incidents, if the faulty line is immediately tripped
out, and time is allowed for the fault arc to de-ionise, reclosing the circuit breakers will result in the line being
successfully re-energised.
Autoreclose schemes are used to automatically reclose a circuit breaker a set time after it has been opened due to
operation of a protection element. On EHV transmission networks, Autoreclose is usually characterised by high-
speed single-phase operation for the first attempt at reclosure. This is intended to help maintain system stability
during a transient fault condition. On HV/MV distribution networks, Autoreclose is applied mainly to radial feeders,
where system stability problems do not generally arise, and is generally characterised by delayed three-phase
operation with potentially multiple reclosure attempts.
Autoreclosing provides an important benefit on circuits using time-graded protection, in that it allows the use of
instantaneous protection to provide a high speed first trip. With fast tripping, the duration of the power arc
resulting from an overhead line fault is reduced to a minimum. This lessens the chance of damage to the line,
which might otherwise cause a transient fault to develop into a permanent fault. Using instantaneous protection
also prevents blowing of fuses in teed feeders, as well as reducing circuit breaker maintenance by eliminating pre-
arc heating. When instantaneous protection is used with Autoreclose, the scheme is normally arranged to block
the instantaneous protection after the first trip. Therefore, if the fault persists after re-closure, the time-graded
protection will provide discriminative tripping resulting in the isolation of the faulted section. However, for certain
applications, where the majority of the faults are likely to be transient, it is common practise to allow more than
one instantaneous trip before the instantaneous protection is blocked.
Some schemes allow a number of re-closures and time-graded trips after the first instantaneous trip, which may
result in the burning out and clearance of semi-permanent faults. Such a scheme may also be used to allow fuses
to operate in teed feeders where the fault current is low.
When considering feeders that are partly overhead line and partly underground cable, any decision to install
Autoreclose should be subject to analysis of the data (knowledge of the frequency of transient faults). This is
because this type of arrangement probably has a greater proportion of semi-permanent and permanent
faults than for purely overhead feeders. In this case, the advantages of Autoreclose are small. It can even be
disadvantageous because re-closing on to a faulty cable is likely to exacerbate the damage.
342 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
characterised by the ohmic nonlinear behaviour of the secondary arc. If the secondary arc is extinguished the
equivalent circuit changes to a linear capacitive behaviour of the phase to earth capacitance of the open
conductor. The voltage and current goes back to normal conditions after successful reclosing.
In the majority of cases, a fixed dead time setting is applied for transmission line autoreclose schemes. This may
cause a problem if the dead time is not long enough for the fault arc to fully de-ionize. Reclosing before the arc
extinction can result in arc restrike and could cause the line protection to trip again, which may incur more stress
on the power system. Under certain conditions, the reclosing onto the fault may put system stability at risk or
damage the equipment. Hence it is desirable to have an adaptive high-speed reclosing scheme that has a variable
dead time interval to allow the breaker to close only after the fault arc has extinguished.
The patented adaptive autoreclose (AAR) technique in this relay overcomes the above issue for single pole
autoreclose applications by detecting whether the fault arc is extinguished or not and adapts the dead time. AAR
uses the pattern of the faulted phase voltage in the complex plane, which is compared with the other two healthy
phase voltages, to distinguish between transient and permanent faults in the case of a single-phase earth fault in
the transmission line. Also, it can detect when the arc is extinguished in case of a temporary fault and hence it can
facilitate successful high-speed reclosing of a transmission line.
For a single-phase fault if the fault is permanent, the faulted phase voltage magnitude and angle do not change
with time after line isolation. Whereas, for a transient fault, the faulted phase voltage magnitude increases as the
arc resistance increases until the arc is extinguished. Moreover, the angle of faulted phase voltage at the moment
when the arc is extinguished lags 90° the angle of faulted phase voltage immediately after line isolation.
The following facts can be observed for the secondary arc of single phase faults.
Fact 1. In the case of a permanent fault, the faulted phase voltage magnitude and angle remains almost constant
after line isolation after the switching transients are damped.
Fact 2. In the case of a transient fault, the voltage magnitude drops immediately after the line isolation and then it
slowly increases until the arc is extinguished.
Fact 3. In the case of a transient fault, after the line isolation, the angle δ either drops immediately and then
increases slowly or increases from the beginning until the arc is extinguished.
δ is the angle between the sum of healthy phase voltages (δh, δk) and the faulted phase (δs) at line end, δ= δh+δk-
δs
|Vs| is the voltage magnitude of the faulted phase at line end
For example, for an A phase fault, |Vs| is the A phase voltage magnitude and δ is the angle between the sum of
healthy phase voltages B and C (δh, δk) and the faulted A phase voltage at line end (δs), δ= δB+δC- δA
Fact 4. In case of a transient fault, when the arc is extinguished, the magnitude of faulted phase voltage (|Vs|)
either becomes constant after a small drop or becomes oscillatory with a constant DC component.
Fact 5. In case of a transient fault, when the arc is extinguished, the angle δ becomes constant or oscillatory with a
constant DC component.
Based on the above-mentioned facts, a new algorithm is used to detect a permanent fault and the time of arc
extinction in case of a transient fault. The adaptive reclosing function is initiated by the breaker open status which
is also used for the faulted phase selection. The breaker interruption should be detected in less than two cycles in
order to detect the fast extinguishing arcs. If the fault is a single-phase to ground fault, the faulted phase voltage
is selected and the adaptive reclosing algorithm can be initiated.
Angle δ is calculated and the magnitude of the faulted phase voltage (|Vs|) is monitored to determine the reference
time (tref). tref is the time that |Vs| starts increasing after the drop that occurs after line isolation. tref can be
determined easily by calculation of the minimum |Vs| after the initiation. If |Vs| keeps to be greater than its
minimum value for a cycle, the time point after that cycle and the corresponding δ are assigned to tref and δref. If
the reference time could not be found within 10 cycles after algorithm initiation, the time point after the 10 cycles
and the corresponding δ are assigned to tref and δref. The latter case normally happens only for permanent faults
because the voltage magnitude does not increase after line isolation.
P54-TM-EN-1.1 343
Chapter 12 - Autoreclose P54
After algorithm initiation, δ and |Vs| is low-pass filtered to attenuate all the unwanted transients. Then, the long-
window derivation of the filtered signals is obtained by fitting a line to the last 6 cycles of the data. The slope of the
fitted line is used as a long-window derivation. This method provides a smooth and reliable estimate for
derivations of δ and |Vs|.
Fact 1 can be used to detect any permanent fault. This can be done by checking δ, δd and |Vs|d. If |Vs| and δ
remain almost constant, δd and |Vs|d derivatves become very small (close to zero) and (δ - δref) will be small as
well.
Fact 2 to Fact 5 can be used to detect the transient fault and the time that the arc is extinguished. As per Facts 2
and 4, |Vs| slowly increases after tref until the arc is extinguished. This means that, after tref, |Vs|d is positive until
the arc is extinguished where |Vs|d either becomes negative and then zero or becomes oscillatory with a zero DC
component. As per Facts 3 and 5, δ slowly increases after tref until the arc is extinguished. This means that, after
tref, δd is positive until the arc is extinguished where δd becomes zero or oscillatory with a zero DC component.
Simply by checking the above-mentioned criteria, the permanent fault and transient fault with arc extinction time
can be detected.
344 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
3 AUTORECLOSE IMPLEMENTATION
Before describing this function it is first necessary to understand the following terminology:
● A Shot is an attempt to close a circuit breaker using the Autoreclose function.
● Multi-shot is where more than one Shot is attempted.
● Single-shot is where only one Shot is attempted.
● Dead Time denotes the time between initiation of the Autoreclose operation and the attempt to close the
circuit breaker. The dead time is normally a fixed time delay but can be can set to adaptive for single pole
autoreclose schemes where it is dependent on the arc extinction time for a transient single-phase fault.
● Reclaim time is the time following the initiation of the circuit breaker closing and the resetting of the
Autoreclose scheme should the Autoreclose attempt be successful and the protection does not detect a
subsequent fault condition.
● High-speed Autoreclose is generally regarded as an Autoreclose application where the Dead Time is less
than 1 second.
● Delayed Autoreclose is generally regarded as an Autoreclose application where the Dead Time is greater
than 1 second.
This product features a multiple-shot Autoreclose function, which is suitable for both High-speed Autoreclose and
Delayed Autoreclose.
The Autoreclose function can be set to perform a single-shot, two-shot, three-shot or four-shot cycle. Dead Times
for all shots can be adjusted independently.
If a circuit breaker closes successfully at the end of the Dead Time, a Reclaim Time starts. If the circuit breaker
does not trip again, the Autoreclose function resets at the end of the Reclaim Time. If the protection trips again
during the Reclaim Time, the sequence advances to the next shot in the programmed cycle. If all programmed
reclose attempts have been made and the circuit breaker does not remain closed, the Autoreclose function goes
into Lockout, whereupon manual intervention is required.
An Autoreclose cycle can be initiated by operation of an internal or external protection element provided it is
mapped correctly, and that the circuit breaker is closed when the protection operates.
You can choose to initiate the Dead Time on:
● Protection operation
● A protection reset
● A Line Dead condition
● Circuit breaker operation
At the end of the relevant Dead Time, provided system conditions are suitable, a circuit breaker close signal is
given. The system conditions to be met for closing are that:
● the system voltages are in synchronism
● or that the dead line/live bus or live line/dead bus conditions exist as indicated by the internal system check
synchronising element
● and that the circuit breaker closing spring, or other energy source, is fully charged as indicated by the circuit
breaker healthy input.
The circuit breaker close signal is removed when the circuit breaker closes.
If the protection trips and the circuit breaker opens during the Reclaim Time, the Autoreclose function either
advances to the next shot in the programmed cycle, or if all programmed reclose attempts have been made, goes
into Lockout. Each time a closure is attempted, a sequence counter is incremented by 1 and the Reclaim Time
starts again.
Autoreclose is configured in the AUTORECLOSE column of the relevant settings group. The function is disabled by
default. If you wish to use it, you must enable it first in the CONFIGURATION column.
P54-TM-EN-1.1 345
Chapter 12 - Autoreclose P54
The Autoreclose function is a logic controller implemented in software. It takes inputs and processes them
according to defined logic to generates appropriate outputs. The logic is controlled by user prescribed settings and
commands. The controlling logic is complex and so, in order to facilitate its design and understanding, it is
decomposed into smaller logic functions which, when combined together implement the complete scheme. This
section concludes with a summary of:
● the logic inputs to the Autoreclose function,
● the logic outputs from the Autoreclose function
● the Autoreclose operating sequence
● the high-level design of the system logic functionality
346 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
It can also be used if an Autoreclose cycle is likely to fail for conditions associated with the protected circuit, such
as during the Dead Time, if a circuit breaker indicates that it is not healthy to switch.
P54-TM-EN-1.1 347
Chapter 12 - Autoreclose P54
Note:
In a multi-shot AR sequence, a number of Dead Timers are used (one for each shot). All Dead Timers are enabled when the
sequence is initiated, but each timer only starts when the particular shot with which it is associated is triggered.
Protection Trip
AR in Progress
CB Open
Dead Time
Auto -close
Reclaim Time
Successful Autoreclose
V03395
Following fault inception, the protection operates and issues a trip signal. At the same time the Autoreclose in
Progress signal is asserted. Shortly afterwards the circuit breaker will open as indicated by the CB Open signal.
Opening of the CB clears the fault and the protection resets. When this happens, the Dead Timer is started and the
output remains high until the Dead Time setting expires, whereupon it resets and the Autorecloser issues the Auto-
close command to close the circuit breaker. As the fault has been cleared, the circuit breaker closes and remains
closed. When the Auto-close pulse is removed, the Reclaim Timer starts. If no further fault is detected before the
Reclaim Timer expires, the Autoreclose is considered to be successful and this is indicated by the Successful
Autoreclose signal.
348 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Protection Trip
CB1 AR in Progress
CB2 AR in Progress
CB1 Open
CB2 Open
Dead Time
Follower Time
Reclaim Time
V03398
Following fault inception, the protection operates and issues a trip signal. At the same time an Autoreclose in
Progress signal is asserted for each CB. Shortly afterwards, CB1 will open as indicated by the CB1 Open signal and
after a short delay CB2 opens. Opening of CB2 clears the fault and the protection resets. When this happens, the
Dead Timer is started and the output remains high until the Dead Time setting expires, whereupon it resets and the
Autorecloser issues the Auto-close command to close CB1. When CB1 closes, the Follower Timer starts. When the
Follower Timer expires, the Autorecloser issues the Autoclose command to close CB2. After CB2 has closed, as the
fault has been cleared, both CBs remain closed. When the Auto-close 2 pulse is removed, the Reclaim Timer starts.
If no further fault is detected before the Reclaim Timer expires, the Autoreclose is considered to be successful and
this is indicated by the Successful Autoreclose signals.
Protection Trip
AR in Progress
CB Open
Dead Time
Auto-close
Reclaim Time
Successful Autoreclose
Autoreclose Lockout
V03396
P54-TM-EN-1.1 349
Chapter 12 - Autoreclose P54
Protection Trip
CB1/CB2 AR in Progress
CB1 Open
CB2 Open
Follower Time
Reclaim Time
Lockout
V03399
AR in Progress
CB Open
Dead Time
Auto-close
Reclaim Time
Successful Autoreclose
Autoreclose Lockout
V03397
Figure 203: Autoreclose sequence for an evolving or permanent fault - single-phase operation
350 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB1/CB2 AR 1 -ph in
Progress
CB1/CB2 AR 3 -ph in
Progress
V03400
Figure 204: Autoreclose Sequence for a persistent fault on a multishot dual CB application set for single-phase
operation
Note:
For three-phase Autoreclosing, for the first shot only, Autoreclose can be performed without checking that the voltages are in
synchronism using a setting. This setting, CB1L SC Shot 1 or CB2L SC Shot 1, can be enabled to perform synch-checks on shot
1 for CB1 or CB2, or disabled to not perform the checks.
P54-TM-EN-1.1 351
Chapter 12 - Autoreclose P54
352 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
424
CB Aux 3ph(52 -B)
& 1 907
1 CB Closed 3 ph
XOR
&
CB Status Input
&
52A 3 pole
52B 3 pole
52A & 52B 3 pole & 1 903
1 CB Open 3 ph
&
&
421
CB Aux A(52 -A)
&
425 908
CB Aux A(52 -B) 1 CB Closed A ph
& 1
XOR
&
&
CB Status Input
&
52A 1 pole
52B 1 pole 904
1 CB Open A ph
52A & 52B 1 pole & 1
&
&
&
422 909
CB Aux B(52-A) 1 CB Closed B ph
426
CB Aux B(52-B)
905
Phase B 1 CB Open B ph
CB Status Input
(Same logic as phase A)
52A 1 pole
52B 1 pole
52A & 52B 1 pole
423 910
CB Aux C(52-A) 1 CB Closed C ph
427
CB Aux C(52-B)
906
Phase C 1 CB Open C ph
CB Status Input
(Same logic as phase A)
52A 1 pole
52B 1 pole t 301
1 CB Status Alm
52A & 52B 1 pole 0
P54-TM-EN-1.1 353
Chapter 12 - Autoreclose P54
905
CB Open B ph 1 CB1Op1P
906
CB Open C ph
1 CB1OpAny
903
CB Open 3 ph
1 CB1Op2/3P
³2
907 CBIST
CB Closed 3 ph
CBISMT & S 1526
Q CB In Service
R
Logic 1 1
1544
CB ARIP
Note: Module numbers shown in red are
for dual breaker logic.
V03302a
BAR CB1
V03308a Note: Module numbers shown in red are for dual breaker logic.
354 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Auto-Reclose
Enabled
& AR Disabled
HMI Command
P54-TM-EN-1.1 355
Chapter 12 - Autoreclose P54
indicates that single-phase Autoreclose is in progress. In this case, for a multi-phase fault the logic triggers a
three-phase trip and goes to lockout.
AR Mode
AR 1P
&
AR 1/3P 1 & CB1 L SPAROK
AR 3P
AR Opto
& CB1 L3 PAROK
1
1497
&
AR Mode 1P
1498 &
AR Mode 3P
846
Seq Counter = 0
847 1
Seq Counter = 1
* Defaults to High if not mapped in PSL
V03309a
356 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
847
&
Seq Counter = 1 858
1 & AR Force 3 pole
Seq Counter = 2
848 & 1
849
Seq Counter = 3
850
Seq Counter = 4
306
AR Lockout
307
A/R CB Unhealthy
1420
Inhibit AR
V03313a
When a three-phase trip is forced, the DDB signal AR Force 3 pole is asserted.
P54-TM-EN-1.1 357
Chapter 12 - Autoreclose P54
dynamics of the Autoreclose logic need to adapt. For example, if a single-phase fault evolves into a multi-phase
fault, then the operation of the Autorecloser must consequently adapt. To achieve this signals are generated to
indicate conditions such as evolving faults, re-operation of protection, combinations of initiation by internal
protection, external protection, or test features, which control the Autoreclose sequencing.
Records of initiating conditions are stored and used to control the sequencing. Initiation can be from a protection
function integrated in the product, from external protection and internal sources such as the Autoreclose test
function. Initiation can be further qualified by the phases causing the initiation. These conditions are stored in
signals that generally feature “MEM”- memory, or “AR” – Autoreclose, in the signal name.
Block AR
Initiate AR 1 Prot AR Block
Block AR 1 S
Q
Initiate AR R 1 Init AR
864
IA< Start &
1
865
IB< Start
866
IC< Start
577
AR Trip Test A
1
578
&
AR Trip Test B
Note: Module numbers shown in red are
579
AR Trip Test C for dual breaker logic.
522
Any Trip
V03315a
V03304a
358 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
>
TAR2/3Ph
2
1 TARANY
Init AR
523 &
Trip Output A 1 TARA
535
External Trip A S 1535
Q Trip AR MemA
R
Init AR
524 &
Trip Output B 1 TARB
536
External Trip B S 1536
Q Trip AR MemB
R
Init AR
525
&
Trip Output C 1 TARC
537
External Trip C S
1537
Q Trip AR MemC
534 R
External Trip3ph
1542 0.01
ARIP
0.1
&
1 RESPRMEM
1 0.2
AR Disabled & S
0 Q
R
Note: Module numbers shown in red are
1 for dual breaker logic.
TARANY
1535
Trip AR MemA
1536
Trip AR MemB 1 TMEMANY
1537
Trip AR MemC
=
TMEM1Ph
1
>
TMEM2/3Ph
2
& TMEM3Ph
V03317a
Figure 214: Autoreclose initiation by external trip or evolving conditions (Module 13)
Note:
The signals must be mapped as shown in the default PSL scheme.
P54-TM-EN-1.1 359
Chapter 12 - Autoreclose P54
TMEMANY 0
&
0.02 &
1 Prot Re-op
TARANY
&
Discrim Time
1554 t
1P DTime &
2911
1 0
1P ATime
847
Seq Counter = 1
1547
& Evolve 3Ph
0
LastShot & S
0.02 Q 1550
306
R & CB Failed AR
A/R Lockout
1565
Set CB Close
907 0 1
CB Closed 3 ph & Note: Module numbers shown
0.02 in red are for dual breaker logic.
1544
CB ARIP
V03449a
Figure 215: Protection Reoperation and Evolving Fault logic diagram (Module 20)
V03320a
360 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Init AR
1541
External Trip A
535 1 AR Start
536
External Trip B
537
External Trip C
534
External Trip3ph
TMEM2/3Ph
1
TMEM1Ph & 1543
& & AR Initiation
CB1 Op2/3P
S
CB1 L3 PAROK Q
1544
CB ARIP
R
1542
ARIP
1420
Inhibit AR 1
860
CB1 LARIP
Lockout Alarm
1528
CB NoAR
CB1 ARSUCC
CBARCancel
0.02
CB1OpAny
0 &
1544 1
CB ARIP
1541 Note: Module numbers shown in red are
AR Start & for dual breaker logic.
1565
Set CB Close
907 &
CB Closed 3 ph
CB1 AR OK
V03321a
P54-TM-EN-1.1 361
Chapter 12 - Autoreclose P54
1541
AR Start
&
1554
1P Dtime
1
2911
1P Atime
&
847
Seq Counter = 1
& S
Prot Re-op Q LastShot
Note: Module numbers shown in
R
red are for dual breaker logic.
V03442a
CB1 LARIP
& S
845
CB1 L SPAROK Q AR 1pole in prog
R
TMEM1Ph CB1 L SPAR
CB1 LARIP
1
CB1 L 3 PAR
V03329a
Figure 219: Single-phase Autoreclose Cycle Selection logic diagram (Module 19)
CB1 LARIP
&
S
CB1 L3 PAROK Q CB1 L 3 PAR
1547
R
Evolve 3Ph
844
1 AR 3pole in prog
TMEM3Ph
CB1Op2/3P
Note: Module numbers shown in red are
TMEMANY for dual breaker logic.
&
CB1 L SPAROK
V03334a
Figure 220: Three-phase Autoreclose Cycle Selection logic diagram (Module 21)
362 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
The DT Start by Prot determines how the protection action will initiate a dead time. The setting is always visible
and has three options Protection Reset, Protection Op (protection operation), and Disable which
should be selected if you don’t want protection action to start the dead time. These options set the basic
conditions for starting the dead time.
Selecting protection operation to start the dead time can, optionally, be qualified by a check that the line is dead.
Selecting protection reset to start the dead time can, optionally, be qualified by a check, that the circuit breaker is
open (DTStart by CB Op) before starting the dead time. For three-phase tripping applications, there is a further
option to check that the line is dead (3PDTStart WhenLD) before starting the dead time.
If DT Start by Prot is disabled, the circuit breaker must be open for the dead time to start. For three-phase tripping
applications, there is an option to check that the line is dead (3PDTStart WhenLD) before starting the dead time. To
check that the line is dead, set 3PDTStart WhenLD to enabled. To check that the circuit breaker is open, set
DTStart by CB Op to Enabled.
DT Start by Prot
Disable
1 1551
Protection Reset & DTOK All
&
Protection Op
1541
AR Start
Dead Line Time
OKTimeSP &
S
Q
1555
OK Time 3P 1 R
& S t
Q DeadLineLockout
ARIP 1542 R 0
1543 0 1
AR Initiation
0.02
889
Dead Line
1
3PDTStart WhenLD
&
Enabled
Disabled
&
DTStart by CB Op
Disabled
1
Enabled 1552
1 DTOK CB 1P
&
CB1Op1P
1553
1 DTOK CB 3P
903
&
CB Open 3 ph
V03337a
Figure 221: Dead time Start Enable logic diagram (Module 22)
P54-TM-EN-1.1 363
Chapter 12 - Autoreclose P54
364 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB1LSPAR
1552 &
DTOK CB 1P & S
Q
847
Seq Counter = 1 R & OKTimeSP
1551
DTOK All
1541
AR Start
2207
SPDTimeComp 1
DT Start by Prot
&
Protection Reset
CB1LSPAR
CB1OP2/3P
2207
SPDTimeEnabled
SP AR Dead Time
Arc Complete
Adaptive SP AR
Enabled t 1
&
Disabled 0
VA
VB &
VC
CB Open A ph
904 6-Cycle Vs
905
Buffer
CB Open B ph
δs
906
CB Open C ph
2909
AAR Perm Flt
Fault Type & Arc
Extinction
SP Min Dead Time
Detection(FTAED) 2910
AAR Temp Flt
t Block
0
SP MaxDead Time Arc Complete
t
SP MaxDT Elapsed 0
Reclose
Lockout
Adaptive SP AR
1554
CB1LSPAR & 1P DTime
& 1 CB1SPDTCOMP
2911
& 1P DTime
Arc Complete
&
V03444a
P54-TM-EN-1.1 365
Chapter 12 - Autoreclose P54
CB1 L 3 PAR
1553
&
DTOK CB1L 3P
1551
DTOK All
& S
Q
3PDTCOMP R & 1555
OK Time 3P
DT Start by Prot
Protection Reset
&
1
1541
AR Start
Logic 1 Note: Module numbers shown in red are
& for dual breaker logic.
CB1 L 3 PAR
3P AR DT Shot 1
t 1 3PDTCOMP
847 &
Seq Counter = 1 0
1556
& 3P DTime1
3P AR DT Shot 2
t
848 &
Seq Counter = 2 0
1557
& 3P DTime2
3P AR DT Shot 3
t
849 &
Seq Counter = 3 0
1558
& 3P DTime3
3P AR DT Shot 4
t
850 &
Seq Counter = 4 0
1559
& 3P DTime4
853
1 3P Dead Time IP
3PDTCOMP
1560
CB1 L 3 PAR & 3P DTime
& CB13PDTCOMP
V03340a
366 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
1565
Set CB Close
306 & S
A/R Lockout Logic 1 Q 854
Auto Close
R
Prot Re-op
0.1s
1542
1
ARIP
1544
CB ARIP
1566
907
& CB Control
CB Closed 3 ph
V03349a
P54-TM-EN-1.1 367
Chapter 12 - Autoreclose P54
CB1SPDTCOMP
& S
1565 Q SETCB1SPCL
Set CB Close R
CB13PDTCOMP
1573
&
CB SCOK
1572 &
CB Fast SCOK 1 S
1555
&
OK Time 3P Q SETCB13PCL
R
V03352a
SPAR ReclaimTime
SETCB1SPCL
& t 1568
CB1 LARIP & 1P Reclaim TComp
Logic 1 0
854
Auto Close
1567
& 1P Reclaim Time
3PAR ReclaimTime
SETCB13PCL
& t 1570
CB1 LARIP & 3P Reclaim TComp
Logic 1 0
854
Auto Close
1569
Close Pulse Time & 3P Reclaim Time
1567
1P Reclaim Time t
1569
1
3P Reclaim Time 0
&
Prot Re-op & CBARCancel
907
CB Closed 3 ph
1544
& Note: Module numbers shown in red are
CB ARIP for dual breaker logic.
V03355a
1570
3P Reclaim TComp
1568
1
1P Reclaim TComp & S 852
Q CB Succ 3P AR
RD
SETCB13PCL 0
&
CB1Op2/3P 0.02S
907 & S
CB Closed 3 Ph Q
R
V03358a
368 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB1OpAny
1541
1
AR Start
1 RESCB1 ARSUCC
Res AROK by UI
Enabled
&
Reset AROK Ind
Yes
Res AROK by NoAR
Enabled
&
AR Disabled
1517
Ext Rst AROK
&
Res AROK by Ext
Enabled
Res AROK by TDly
Enabled
&
AROK Reset Time
t
CB1 ARSUCC
0
V03361a
Figure 228: Autoreclose Reset Successful Indication logic diagram (Module 37)
P54-TM-EN-1.1 369
Chapter 12 - Autoreclose P54
CB Healthy Time
CB1 L 3 PAR
1515
OK Time 3P 1
1572
CB Fast SCOK
CB1SPDTCOMP 1
& S t 307
CB13PDTCOMP Q AR CB Unhealthy
RD 0
436
CB Healthy
306
A/R Lockout 1
907
CB Closed 3 Ph
V03363a If the DDB signal CB1 Healthy is not mapped in PSL, it defaults to High.
Figure 229: Circuit Breaker Healthy and System Check Timers Healthy logic diagram (Module 39)
370 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
1565
Set CB Close Increment
CB Total Shots Counter
Reset
1571
CB Succ 1P AR Increment
CB Successful SPAR Shot 1 Counter
CB Succ 3P AR 852 Reset
& Increment
848
Seq Counter = 2 CB Successful 3PAR Shot 2 Counter
Reset
V03366a
P54-TM-EN-1.1 371
Chapter 12 - Autoreclose P54
CB Control by
Opto Note: If the DDB signal CB Healthy is not mapped in PSL it defaults to High.
Opto+Local
1
Opto+Remote
Opto+Rem+Local
Trip Pulse Time
838
HMI Trip Control Trip
1
& S t
439 & Q 302
Init Trip CB RD 0 & CB Trip Fail
440 &
Init close CB Man Close Delay Close Pulse Time
1 842
Close in Prog
HMI Close
& S t
CB ARIP 1544 Q 839
RD 0 & Control Close
854 1 S t
Auto Close Q
RD 0
443
Reset Close Dly
522 303
Any Trip & CB Close Fail
1
838
Control Trip
534
External Trip3Ph 1
1
535
External Trip A
537
External Trip C
1 1
903
CB Open 3 ph
904
CB Open A ph
905 Note: Module numbers shown in red are
CB Open B ph & for dual breaker logic.
906
CB Open C ph
907
CB Closed 3 ph
1
908
CB Closed A ph
CB Closed B ph 909
1 CB Healthy Time
910
CB Closed C ph
t 304
436 & Man CB Unhealthy
CB Healthy 0
t 305
1574 & No C/S Man Close
CB Man SCOK 0
V03369a
372 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
TAR2/3Ph S t
Q 1575
RD 0 1 CB Fail Pr Trip
903 & S
CB Open 3 Ph Q
RD
907
CB Closed 3 Ph
TARA
& S
TMEM2/3Ph Q t
RD 1
0
904
& S
CB1 Open A ph Q
RD
907
CB Closed 3 Ph 1 Note: Module numbers shown in red are
for dual breaker logic.
TARB
& S
TMEM2/3Ph Q
RD
905
& S
CB1 Open B Ph Q
RD
907
CB Closed 3 Ph 1
TARC
& S
TMEM2/3Ph Q
RD
906
& S
CB1 Open C Ph Q
RD
907
CB Closed 3 Ph 1
V03376a
Figure 232: Circuit Breaker Trip Time Monitoring logic diagram (Module 53)
P54-TM-EN-1.1 373
Chapter 12 - Autoreclose P54
FLTMEM 3P
&
Multi Phase AR
BAR 3 Phase
1
BAR 2 and 3 Ph
&
FLTMEM 2P 306
A/R Lockout
303
CB Close Fail
1575
CB Fail Pr Trip 1385
Mod 4 AR In Service
CB1OpAny & S
Q
1544 R
CB ARIP &
448
Block CB AR
307
A/R CB Unhealthy
Mod 53 RESCB1LO
A/R No Checksync 308 &
1547
Evolve 3Ph S
Q
PROTRE-OP R
LastShot &
1544
CB ARIP
1 BAR CB1
Evolve Lock &
Prot AR Block
1526
CB In Service
&
TMEM2/3Ph
0
CB1 L3 PAROK
0.02s
374 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
If set to User Interface then a command, CB mon LO reset, becomes visible. This command can be used to
reset the lockout from a user interface.
An Autoreclose lockout generates an Autoreclose lockout alarm. Autoreclose lockout conditions can be reset by
various commands and setting options found under the CB CONTROL column.
If Res LO by CB IS is set to Enabled, a lockout is reset if the circuit breaker is successfully closed manually. For
this, the circuit breaker must remain closed long enough so that it enters the “In Service” state.
If Res LO by UI is set to Enabled, the circuit breaker lockout can be reset from a user interface using the reset
circuit breaker lockout command in the CB CONTROL column.
If Res LO by NoAR is set to Enabled, the circuit breaker lockout can be reset by temporarily generating an AR
disabled signal.
If Res LO by TDelay is set to Enabled, the circuit breaker lockout is automatically reset after a time delay set in
the LO Reset Time setting.
If Res LO by ExtDDB is Enabled, the circuit breaker lockout can be reset by activation of an external input
mapped in the PSL to the relevant reset lockout DDB signal.
Res LO by CB IS
Enabled
&
CB1CRLO
Res LO by UI
Enabled
&
Reset CB LO
Yes
Res LO by NoAR
Enabled
& 1 RESCB1LO
AR Disabled
Res LO by ExtDDB
Enabled
&
446
Reset Lockout
Res LO by TDelay
Enabled
&
LO Reset Time
306 t
A/R Lockout
0
V03382a
Figure 234: Reset Circuit Breaker Lockout Logic Diagram (Module 57)
P54-TM-EN-1.1 375
Chapter 12 - Autoreclose P54
904
CB Open A ph
1
905
CB Open B ph
906
CB Open C ph
&
V03384a
Dwell
522
1 Any Trip
530 100 ms
Trip Inputs A
531
Trip Inputs B
>
S
Trip Inputs C 532 2 Q 527
2/3 Ph Fault
R
892
Pole Dead A &
1 S
528
Q 3 Ph Fault
R
893 & 1
Pole Dead B 1
&
894
1
Pole Dead C
&
V03386a
Figure 236: Circuit Breaker Trip Conversion Logic Diagram (Module 63)
376 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
System Checks
Enabled
VAN 888
Live Line & Live Line
VBN
VCN 889
Select Dead Line & Dead line
VAB
VBC 886
Live Bus & Live Bus
VCA
VBus
VBus Dead Bus & 887
Dead Bus
Voltage Monitors
438
MCB/VTS
1521
MCB/VTS CB CS
1522
1
Inhibit LL
1523
1
Inhibit DL
1524
1
Inhibit LB
1525
1
Inhibit DB
V01257
P54-TM-EN-1.1 377
Chapter 12 - Autoreclose P54
System Checks
880
Disabled SysChks Inactive
Enabled
CS1 Criteria OK
VAN &
VBN CS2 Criteria OK
&
VCN
Select CS1 SlipF> 1578
VAB & CS1 SlipF>
1582
& CS Vbus<
CS1 Vl>Vb 1586
& CS1 Vl>Vb
CS1 Vl<Vb 1588
& CS1 Vl<Vb
CS1 Fl>Fb 1590
& CS1 Fl>Fb
CS1 Fl<Fb 1591
& CS1 Fl<Fb
CS1 AngHigh+ 1592
& CS1 AngHigh+
CS1 AngHigh- 1593
& CS1 AngHigh-
CS2 Fl>Fb 1493
& CS2 Fl>Fb
CS2 Fl<Fb 1494
& CS2 Fl<Fb
CS2 AngHigh+
& 1495
CS2 AngHigh+
CS2 AngHigh-
& 1496
CS2 AngHigh-
CS2 Status
884
Enabled & Check Sync 2 OK
882
CS2 Enabled V01259
378 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
For single-phase Autoreclose no voltage or synchronism check is required as synchronising power is flowing in the
two healthy phases. Three-phase Autoreclose can be performed without checking that voltages are in
synchronism for the first shot (and only the first shot). The settings to permit Autoreclose without checking voltage
synchronism on the first shot are:
● CB1L SC Shot 1 for circuit breaker 1 as a leader,
● CB1F SC Shot 1 for circuit breaker 1 as a follower,
● CB2L SC Shot 1 for circuit breaker 2 as a leader,
● CB2L SC Shot 1 for circuit breaker 2 as a follower.
When the circuit breaker has closed, the Autoreclose function asserts a DDB signal Set CB1 Close, which indicates
that an attempt has been made to close the circuit breaker. At this point, the Reclaim Time starts. If the circuit
breaker remains closed after the reclaim timer expires, the Autoreclose cycle is complete, and signals are
generated to indicate that Autoreclose was successful. These are:
● CB1 Succ 1P AR (Single-phase Autoreclose CB1)
● CB2 Succ 1P AR (Single-phase Autoreclose CB2)
● CB1 Succ 3P AR (Three-phase Autoreclose CB1)
● CB2 Succ 3P AR (Three-phase Autoreclose CB2)
These signals increment the relevant circuit breaker successful Autoreclose shot counters, as well as resetting the
Autoreclose in progress signal.
The relevant circuit breaker successful Autoreclose shot counters are:
● CB1 SUCC SPAR (Single-phase Autoreclose CB1)
● CB1 SUCC 3PAR Shot1 (Three-phase Autoreclose CB1, Shot 1)
● CB1 SUCC 3PAR Shot2 (Three-phase Autoreclose CB1, Shot 2)
● CB1 SUCC 3PAR Shot3 (Three-phase Autoreclose CB1, Shot 3)
● CB1 SUCC 3PAR Shot4 (Three-phase Autoreclose CB1, Shot 4)
● CB2 SUCC SPAR (Single-phase Autoreclose CB2)
● CB2 SUCC 3PAR Shot1 (Three-phase Autoreclose CB2, Shot 1)
● CB2 SUCC 3PAR Shot2 (Three-phase Autoreclose CB2, Shot 2)
● CB2 SUCC 3PAR Shot3 (Three-phase Autoreclose CB2, Shot 3)
● CB1 SUCC 3PAR Shot4 (Three-phase Autoreclose CB2, Shot 4)
P54-TM-EN-1.1 379
Chapter 12 - Autoreclose P54
CB SC ClsNoDly
Enabled 1572
& CB Fast SCOK
CB SC CS1
Enabled 1
&
883
Check Sync 1 OK
CB SC CS2
Enabled
&
854
Check Sync 2 OK
CB SC DLLB
Enabled
889 &
Dead Line
886
Live Bus
CB SC LLDB
Enabled
1573
888 & 1 CB SCOK
Live Line
887
Dead Bus
CB SC DLDB
Enabled
889 &
Dead Line
887
Dead Bus
CB SC Shot 1
Note: If the DDB signal Ext CS OK is not mapped in PSL, it defaults to High.
Disabled
&
847
Seq Counter = 1
CB SC all
Disabled
&
900
Ext CS OK
V03372a
Figure 239: Three-phase Autoreclose System Check Logic Diagram (Module 45)
380 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CBM SC CS1
Enabled
&
883
Check Sync 1 OK
CBM SC CS2
Enabled
&
884
Check Sync 2 OK
CBM SC DLLB
Enabled
889
&
Dead Line
886
Live Bus
CBM SC LLDB
Enabled
1574
888
& 1 CB Man SCOK
Live Line
887
Dead Bus
CBM SC DLDB
Enabled
889
&
Dead Line
887
Dead Bus
CBM SC required
Disabled
& Note: If the DDB signal Ext CS OK is not mapped in PSL, it defaults to High.
900
Ext CS OK
V03374a
Figure 240: CB Manual Close System Check Logic Diagram (Module 51)
P54-TM-EN-1.1 381
Chapter 12 - Autoreclose P54
382 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
424
CB1 Aux 3ph(52-B)
& 1 907
1 CB1 Closed 3 ph
XOR
&
&
&
421
CB1 Aux A(52-A)
&
425 908
CB1 Aux A(52-B) 1 CB1 Closed A ph
& 1
XOR
&
&
&
&
&
422 909
CB1 Aux B(52-A) 1 CB1 Closed B ph
905
Phase B 1 CB1 Open B ph
CB1 Status Input
(Same logic as phase A )
52A 1 pole
52B 1 pole
52A & 52B 1 pole
423 910
CB1 Aux C(52-A) 1 CB1 Closed C ph
906
Phase C 1 CB1 Open C ph
CB1 Status Input
(Same logic as phase A )
52A 1 pole
52B 1 pole 301
1 CB1 Status Alm
52A & 52B 1 pole
P54-TM-EN-1.1 383
Chapter 12 - Autoreclose P54
428
CB2 Aux 3ph(52A)
&
432
CB2 Aux 3ph(52B)
& 1
1 915 CB2 Closed 3 ph
XOR
&
&
&
429
CB2 Aux A(52-A)
&
433 916
CB2 Aux A(52-B) 1 CB2 Closed A ph
& 1
XOR
&
&
&
&
&
430 917
CB2 Aux B(52-A) 1 CB2 Closed B ph
434
CB2 Aux B(52-B)
913
Phase B 1 CB2 Open B ph
CB2 Status Input
(Same logic as phase A)
52A 1 pole
52B 1 pole
52A & 52B 1 pole
431 918
CB2 Aux C(52-A) 1 CB2 Closed C ph
435
CB2 Aux C(52-B)
914
Phase C 1 CB2 Open C ph
CB2 Status Input
(Same logic as phase A)
52A 1 pole
52B 1 pole 323
1 CB2 Status Alm
52A & 52B 1 pole
384 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
1 CB1OpAny
903
CB1 Open 3 ph
1 CB1Op2/3P
³2
912
CB2 Open A ph
913
CB2 Open B ph 1 CB2Op1P
914
CB2 Open C ph
1 CB2OpAny
911
CB2 Open 3 ph
1 CB2Op2/3P
³2
V03390a
V03407a
P54-TM-EN-1.1 385
Chapter 12 - Autoreclose P54
Auto-Reclose
Enable
& AR DISABLED
HMI Comand
1385
IEC 60870 Comand Autoreclose AR In Service
Status
1382 Default = ON 1
AR On Pulse
1383
AR OFF Pulse
1384
AR Enable
1609
AR Enable CB1 *
1
1605
AR Enable CB2 *
386 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Leader Select By
Menu
&
Select Leader
1 Pref LCB1
CB1
CB2
&
Leader Select By
Opto
&
1408
1 Pref LCB2
CB2 Lead
&
Leader Select By
Control
&
CB2 Lead
Set
V03306a
P54-TM-EN-1.1 387
Chapter 12 - Autoreclose P54
& S
Pref LCB2 Q
R 1 SET LCB2
&
1528
CB1 NoAR
0.1 &
1435
CB2 ARIP
0 1
&
1385
AR in Service
1609
AR Enable CB1
1526 1528
CB1 in Service & CB1 NoAR
306
CB1 AR Lockout
BAR CB1
ARIP 1542 &
1 S 1530
& Q Leader CB1
Set LCB1 R
&
Reset L-F
0.1s
Foll SP AROK &
1 1
Foll 3P AROK
1431 &
Leader CB2
1 & 1432 Follower CB1
CB2 LFRC
1385
AR in Service
1605
AR Enable CB2
1428 1429
CB2 in Service & CB2 NoAR
328
CB2 AR Lockout
BAR CB2
ARIP 1542 &
1 S
& Q 1431 Leader CB2
Set LCB2 R
&
Reset L-F
0.1s
&
1
Foll SP AROK
1
Foll 3P AROK &
1530 1433
Leader CB1 & Follower CB2
1
CB1 LFRC V03307a
388 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Single-phase Autoreclosing is permitted only for the first shot of an Autoreclose cycle. In a multi-shot Autoreclose
cycle the second and subsequent trips will always be three-phase.
For multi-phase faults, you can use the Multi Phase AR setting in the AUTORECLOSE column to configure the
following options:
● Allow Autoreclose for all fault types (Allow Autoclose)
● Block Autoreclose for 2-phase and 3-phase faults (BAR 2 and 3 ph)
● Block Autoreclose for 3-phase faults (BAR 3 Phase)
P54-TM-EN-1.1 389
Chapter 12 - Autoreclose P54
1497
&
AR Mode 1P Invalid AR Mode
1498 & 5s
AR Mode 3P 331
See Note Invalid AR Mode
1409 & 0
Foll AR Mode 1P
1410
&
Foll AR Mode 3P
CB2L SPAROK
& CB1 F 3PAROK
Foll SP AROK
1605
AR Enable CB2 & CB2 F SPAROK
&
CB1L SPAROK
& CB2 F 3PAROK
Foll 3P AROK
V03310a
390 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB1 L SPAROK
1
CB1 F SPAROK
1554
CB1 ARIP
&
TARANY
847
&
Seq Counter = 1
1
Seq Counter = 2 848 &
1 858
849
& AR Force CB1 3P
Seq Counter = 3
850
Seq Counter = 4
306
CB1 AR Lockout
307
AR CB1 Unhealthy
1420
Inhibit AR
CB2Tripping Mode
3 Pole
&
1 and 3 pole
1431
Leader CB2
CB2 L SPAROK
1
CB2 F SPAROK
1435
CB2 ARIP
&
TARANY
847
&
Seq Counter = 1
1
Seq Counter = 2 848 &
1 1485
849
& AR Force CB2 3P
Seq Counter = 3
850
Seq Counter = 4
328
CB2 AR Lockout
329
AR CB2 Unhealthy
1420
Inhibit AR
CB1Tripping Mode
3 Pole
&
1 and 3 pole
1530
Leader CB1
1585
AR In Service
NUM CBs 1
CB1 Only
Both CB1&CB2
1
CB2 Only
V03314a
P54-TM-EN-1.1 391
Chapter 12 - Autoreclose P54
Block AR
Initiate AR 1 Prot AR Block
Block AR 1 S
Q
Initiate AR R 1 Init AR
864
IA< Start &
1
865
IB< Start
866
IC< Start
577
AR Trip Test A
1
578
&
AR Trip Test B
Note: Module numbers shown in red are
579
AR Trip Test C for dual breaker logic.
522
Any Trip
V03315a
392 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
V03304a
P54-TM-EN-1.1 393
Chapter 12 - Autoreclose P54
CB2 TARA
CB2 TARB 1
CB2 TARC
Num CBs
CB1 only TAR2/3pH
CB2 only 1
Both CB1&CB2
1 TARANY
Init AR
523
&
CB1 Trip OutputA 1 TARA
535
CB1 Ext Trip A S
1535
Q CB1 Trip AR MemA
R
Init AR
524
&
CB1 Trip OutputB 1 TARB
536
CB1 Ext Trip B S
1536
Q CB1 Trip AR MemB
R
Init AR
525
&
CB1 Trip OutputC 1 TARC
537
CB1 Ext Trip C S
1537
Q CB1 Trip AR MemC
534 R
CB1 Ext Trip3ph
1542 0.01
ARIP
0.1
&
1 RESPRMEM
1 0.2
AR Disabled & S
0 Q
R
1
TARANY
1499
CB2 Trip AR MemA
1500
CB2 Trip AR MemB 1
1 TMEMANY
1501
CB2 Trip AR MemC
1535
CB1 Trip AR MemA
1536
CB1 Trip AR MemB 1
1537
CB1 Trip AR MemC
=
TMEM1Ph
1
TMEM2/3Ph
& TMEM3Ph
V03318a
Figure 252: Autoreclose initiation by internal single and three phase trip or external trip for CB1 (Module 13)
Note:
For single-phase Autoreclose, these signals must be mapped as shown in the default PSL scheme.
394 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Num CBs
CB1 only >
CB2 TAR2/3PH
CB2 only 1 2
Both CB1&CB2
Init AR
1601 &
CB2 Trip OutputA 1 CB2 TARA
539
CB2 Ext Trip A S
1499
Q CB2 Trip AR MemA
R
Init AR
1602 &
CB2 Trip OutputB 1 CB2 TARB
540
CB2 Ext Trip B S 1500
Q CB2 Trip AR MemB
R
Init AR
1603 &
CB2 Trip OutputC 1 CB2 TARC
541
CB2 Ext Trip C S
1501
Q CB2 Trip AR MemC
538 R
CB2 Ext Trip3ph
RESPRMEM
>
CB2 TMEM2/3Ph
2
Figure 253: Autoreclose initiation by internal single and three phase trip or external trip for CB2 (Module 14)
Note:
For single-phase Autoreclose, these signals must be mapped as shown in the default PSL scheme.
P54-TM-EN-1.1 395
Chapter 12 - Autoreclose P54
TMEMANY 0
&
0.02 &
1 Prot Re-op
TARANY
&
Discrim Time
& Reset L-F
t
1P Time Delay 1554
&
2911 1 0
1P ATime
847
Seq Counter = 1
1547
& Evolve 3Ph
0
LastShot & S
0.02 Q
1550
306
R & CB1 Failed AR
CB1 AR Lockout
328
1
CB2 AR Lockout
1565
Set CB1 Close
907 0 1
CB1 Closed 3 ph &
0.02
1544
CB1 ARIP
1449
Set CB2 Close & 1441
CB2 Failed AR
915 0 1
CB2 Closed 3 ph &
0.02
1544
CB2 ARIP
V03450a
Figure 254: Protection Reoperation and Evolving Fault logic diagram (Module 20)
V03320a
396 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
TMEM2/3Ph
1
TMEM1Ph & 1543
& & CB1 AR Init
CB1 Op2/3P
S
CB1 L 3PAROK Q
1544
CB1 ARIP
1 R
CB1 F 3PAROK
1542
1 ARIP
1420
Inhibit AR 1
860
CB1 LO Alarm
1528
CB1 NoAR
CB1 ARSUCC
CBARCancel
0.02
CB1 OpAny
0 &
1
1544
CB1 ARIP
1541
AR Start &
1565
Set CB1 Close
907
&
CB1 Closed 3 ph
1435
CB2 ARIP
1530 & CB1 L ARIP
Leader CB1
1
1432 & CB1 F ARIP
Follower CB1
V03322a
Figure 256: Autoreclose In Progress logic diagram for CB1 (Module 16)
P54-TM-EN-1.1 397
Chapter 12 - Autoreclose P54
Init AR
CB2 Ext Trip A
539 1
540
CB2 Ext Trip B
541
CB2 Ext Trip C
538
CB2 Ext Trip 3ph
CB2 TMEM2/3Ph
1
CB2 TMEM1Ph & 1434
& & CB2 AR Init
CB2Op2/3P
S
CB2 L 3PAROK Q
1435
CB2 ARIP
1 R
CB2 F 3PAROK
1420
Inhibit AR 1
1599
CB2 LO Alarm
1429
CB2 NoAR
CB2 ARSUCC
CBARCancel
0.02
CB2OpAny
0 &
CB2 ARIP 1
1541
AR Start &
1449
Set CB2 Close
915 &
CB2 Closed 3 ph
1431
& CB2 L ARIP
Leader CB2
1
1433
& CB2 F ARIP
Follower CB2
V03324a
Figure 257: Autoreclose In Progress logic diagram for CB2 (Module 17)
398 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
1541
AR Start
&
1544
1P Dtime
1
2911
1P Atime
&
847
Seq Counter = 1
Sequence Counter 846
Seq Counter = 0
847
Increment on rising edge Seq Counter = 1
848
Reset on falling edge Seq Counter = 2
849
Single Pole Shot Seq Counter = 3
850
Three Pole Shot Seq Counter = 4
851
Seq Counter > 4
1546
Seq Counter>Set
& S
Prot Re-op Q LastShot
R
V03443a
P54-TM-EN-1.1 399
Chapter 12 - Autoreclose P54
CB1 L ARIP
& S
CB1 L SPAROK Q CB1 L SPAR
R
TMEM1PH
1
CB1 L 3PAR
CB2 L ARIP
& S
CB2 L SPAROK Q CB2 L SPAR
R
CB2 TMEM1PH
1 845
CB2 L 3PAR 1 CB1 AR 1p InProg
CB1 F ARIP
& S
CB2 L SPAR Q CB1F SPAR
R
CB1 F SPAROK
TMEM1PH
CB1 F 3PAR 1 855
CB2 AR 1p InProg
1
CB2 L 3PAR
CB2 F ARIP
& S
CB1 L SPAR Q CB2 F SPAR
R
CB2 F SPAROK
CB2 TMEM1PH
CB2 F 3PAR
1
CB1 L 3PAR
V03330a
Figure 259: Single-phase Autoreclose Cycle Selection logic diagram (Module 19)
400 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB1L ARIP
& S
CB1 L 3PAROK Q CB1 L 3PAR
R
1547
Evolve 3Ph
TEMEM3Ph 1
CB1Op2/3P
TMEMANY
& 844
CB1 L SPAROK 1 CB1 AR 3p InProg
CB2 L ARIP
& S
CB2 L 3PAROK Q CB2 L 3PAR
R
CB2 TMEM 3Ph
1
CB2Op2/3P
1411
1 CB2 AR 3p InProg
&
CB2 L SPAROK
CB1 F ARIP
& S
Q CB1 F 3PAR
CB1 F 3PAROK R
1
CB1Op2/3p
&
CB1 F SPAROK
CB2 F ARIP
& S
Q CB2 F 3PAR
CB2 F 3PAROK R
1
CB2Op2/3P
&
CB2 F SPAROK
V03335a
Figure 260: Three-phase Autoreclose Cycle Selection logic diagram (Module 21)
The DT Start by Prot determines how the protection action will initiate a dead time. The setting is always visible
and has three options Protection Reset, Protection Op (protection operation), and Disable which
should be selected if you don’t want protection action to start the dead time. These options set the basic
conditions for starting the dead time.
Selecting protection operation to start the dead time can, optionally, be qualified by a check that the line is dead.
Selecting protection reset to start the dead time can, optionally, be qualified by a check, that the circuit breaker is
open (DTStart by CB Op) before starting the dead time. For three-phase tripping applications, there is a further
option to check that the line is dead (3PDTStart WhenLD) before starting the dead time.
If DT Start by Prot is disabled, the circuit breaker must be open for the dead time to start. For three-phase tripping
applications, there is an option to check that the line is dead (3PDTStart WhenLD) before starting the dead time. To
P54-TM-EN-1.1 401
Chapter 12 - Autoreclose P54
check that the line is dead, set 3PDTStart WhenLD to enabled. To check that the circuit breaker is open, set
DTStart by CB Op to Enabled.
DT Start by Prot
Disable
1 1551
Protection Reset & DTOK All
&
Protection Op
1541
AR Start
Dead Line Time
OKTimeSP &
S
Q
1555
OK Time 3P 1 R
& S t
1542
Q DeadLineLockout
ARIP R 0
1543
CB1 AR Init 0 1
1
CB2 AR Init 1434
0.02
889
Dead Line
1
3PDTStart WhenLD
&
Enabled
Disabled
DT Start by Prot
Protection Reset
1
Disable &
845
CB1 AR 1p InProg
855
CB2 AR 1p InProg &
&
DTStart by CB Op
Disabled
1
Enabled
1552
1 DTOK CB1L 1P
CB1Op1P &
CB2OpAny
1
1553
903 1 DTOK CB1L 3P
CB1 Open 3 ph &
911
CB2 Open 3 ph
1
1442
1 DTOK CB2L 1P
CB2Op1P &
CB1OpAny
1
1443
911 1 DTOK CB2L 3P
CB2 Open 3 ph &
903
CB1 Open 3 ph
1
Num CBs
CB1 Only
CB2 Only
V03338a
Figure 261: Dead time Start Enable logic diagram (Module 22)
402 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
The output signals from the FTAED Module are the P_Fault, T_Fault and the Arc complete signals which indicate a
permanent fault detection, transient fault detection and arc extinction.
The T_Fault signal is high during a transient fault condition and the Arc complete signal is high only after complete
de-ionization of the faulted arc during transient fault conditions. During a permanent fault condition, the P_Fault
output signal of the AAR module is high, and it is routed to the AR lockout logic diagram (Module 55) to stop further
autoreclose actions if required.
The CB1SPDTCOMP and CB1SPATCOMP signals in Module 24 are inputs to the Circuit Breaker Auto Close Logic
Diagram (Module 32). The CB1SPDTCOMP signal is high in cases where the Adaptive SP AR is setting is 0 and
CB1SPATCOMP is high in cases where the Adaptive SP AR setting is 1.
P54-TM-EN-1.1 403
Chapter 12 - Autoreclose P54
CB1LSPAR
1552 &
DTOK CB1L 1P 1
& S
CB2LSPAR Q
1442 & R & OKTimeSP
DTOK CB2L 1P
847
Seq Counter = 1
1551
DTOK All
2205
SPDTimeComp
1552
AR Start
1
DT Start by Prot
&
Protection Reset
CB1LSPAR
1
CB2LSPAR
CB1OP2/3P
&
CB2OP2/3P
2207
SPDTimeEnabled
Arc Complete
SP AR Dead Time
1
Adaptive SP AR t
&
Disabled 0
Enabled 2205
SPDTimeComp
VA AAR Enable
VB
VC
&
PrefLCB1
905
CB1 Open A ph
Gr eatest broken
curr ent total 912
CB2 Open A ph
6-Cycle
PrefLCB1 Buffer Vs 2909
CB1 Open B ph 906 P_Fault
Gr eatest broken
curr ent total 913
CB2 Open B ph δs 2910
PrefLCB1 T_Fault
Fault Type & Arc
907
CB1 Open C ph
Gr eatest broken Extinction
curr ent total
CB2 Open C ph 914 Detection(FTAED) Arc Complete
Block
SP Min Dead Time
t
0
SP Max Dead Time
t
SP Max DT Elapsed 0
Reclose
V03343 Lockout
2205
SPDTimeComp
CB1LSPAR & 1554
1 1P DTime
AAR Enable
CB2LSPAR &
& 1 CB1SPDTCOMP
Arc Complete
&
&
1 CB2SPDTCOMP
&
& 2910
1 1P ATime
&
V03445a
Figure 262: Single-phase Leader Dead Time logic diagram (Module 24)
404 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB1 L 3PAR
1553 &
DTOK CB1L 3P
1
CB2 L 3PAR
1443
&
DTOK CB2L 3P
1551
& S
DTOK All Q 1555
R & OK Time 3P
3PDTCOMP
1541
AR Start
CB1 L 3PAR
1
CB2 L 3PAR
2206
3PDTimeEnabled
3P AR DT Shot 1
t 1 2204
3PDTimeComp
847 &
Seq Counter = 1 0
1556
& 3P DTime1
3P AR DT Shot 2
t
848 &
Seq Counter = 2 0
1557
& 3P DTime2
3P AR DT Shot 3
t
849
&
Seq Counter = 3 0
1558
& 3P DTime3
3P AR DT Shot 4
t
850 &
Seq Counter = 4 0
1559
& 3P DTime4
853
1 3P Dead Time IP
2204
3PDTimeComp
1560
CB1 L 3PAR & CB1 3P DTime
& CB13PDTCOMP
1444
CB2 L 3PAR & CB2 3P DTime
& CB23PDTCOMP
V03405a
Figure 263: Three-phase Leader CB Dead Time logic diagram (Module 25 and Module 26)
P54-TM-EN-1.1 405
Chapter 12 - Autoreclose P54
BF if LFail Cls
Disabled
&
306
1
CB1 AR Lockout
907
CB1 Closed 3 ph
Logic 1
&
CB2 F SPAR 1
Logic 1
&
CB2 F 3PAR
841
Control CloseCB2
& S
Q
CB2 F SPAR & 1488
En CB1 Follower
1 RD
CB2 F 3PAR
907
CB1 Closed 3 ph 1
303
CB1 Close Fail
1541
AR Start
BF if LFail Cls
Disabled
&
328 1
CB2 AR Lockout
915
CB2 Closed 3 ph
Logic 1
&
CB1 F SPAR 1
Logic 1
&
CB1 F 3PAR
V03346a
406 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Dynamic F/L
Enabled
&
CB1 LFRC
1
CB2 LFRC
CB1Op1P
CB1 F SPAR &
1
1488
En CB1 Follower
& 1561
1PF TComp
1561 1 1PF TComp
CB2Op1P & S
Q
R
CB2 F SPAR
1445
En CB2 Follower
847
Seq Counter = 1
1541 1 t
AR Start
0
CB1 F SPAR
1
CB2 F SPAR
CB1Op2/3P
&
CB2Op2/3P
Follower Time
& CB1SPFTCOMP
& CB2SPFTCOMP
V03347a
P54-TM-EN-1.1 407
Chapter 12 - Autoreclose P54
Dynamic F/L
Enabled
&
CB1 LFRC
1
CB2 LFRC
903
CB1 open 3 ph
CB1 F 3PAR &
1
1488
En CB1 Follower
& 1562
3PF TComp 1562 1 3PF TComp
CB2 open 3 ph
911 & S
Q
R
CB2 F 3PAR
1445
En CB2 Follower
1541 1 t
AR Start
0
CB1 F 3PAR
1
CB2 F 3PAR
Follower Time
& CB13PFTCOMP
CB2F3PAR &
& CB23PFTCOMP
V03348a
408 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB13PDTCOMP
1573
&
CB1L SCOK 1
1572
CB1 Fast SCOK
1555
&
OK Time 3P
522
Any Trip
328
CB2 AR Lockout &
&
CB2 Healthy 437
CB2SPDTCOMP If the DDB signal CB2 Healthy is not mapped in PSL, it defaults to
High.
CB2Op1P &
CB2 L 3PAR
911
CB2 Open 3 ph
CB23PDTCOMP
1455
&
CB2L SCOK 1
1454
CB2 Fast SCOK
1555
&
OK Time 3P
Figure 267: Circuit Breaker Autoclose Logic Diagram (Modules 32 & 33)
P54-TM-EN-1.1 409
Chapter 12 - Autoreclose P54
circuit breaker to close goes high following completion of a dead time in a subsequent Autoreclose cycle. Where
the reclaim extend time signal is set, the reclaim time cannot time out and reset the Autoreclose cycle before the
time delayed protection has fully operated
If the circuit breaker is closed and has not tripped again when the reclaim time expires, signals are generated to
indicate successful Autoreclose. These signals increment the relevant circuit breaker successful Autoreclose shot
counters and reset the relevant Autoreclose in progress signal.
The “successful Autoreclose” signals generated from the logic can be reset by various commands and settings
options available under CB CONTROL menu settings as follows:
If Res AROK by UI is set to Enabled, all the signals can be reset by user interface command Reset AROK Ind from
the CB CONTROL menu.
If Res AROK by NoAR is set to Enabled, the signals for each circuit breaker can be reset by temporarily
generating an Autoreclose disabled signal according to the logic shown.
If Res AROK by Ext is set to Enabled, the signals can be reset by activation of an external input signal
appropriately mapped in the PSL.
If Res AROK by TDly is set to Enabled, the signals are automatically reset after a time delay set in AROK Reset
Time.
CB1SPDTCOMP
1
CB1SPFTCOMP & S
1565
Q SETCB1SPCl
Set CB1 Close R
CB13PDTCOMP
1573
&
CB1L SCOK
1572
CB1 Fast SCOK & S
1555
& 1
OK Time 3P Q SETCB13PCl
R
CB13PFTCOMP
1491
&
CB1F SCOK
CB2SPDTCOMP
1
CB2SPFTCOMP & S
1449
Q SETCB2SPCl
Set CB2 Close R
CB23PDTCOMP
1455
&
CB2L SCOK
1454
CB2 Fast SCOK & S
1555
& 1
OK Time 3P Q SETCB23PCl
R
CB23PFTCOMP
1456
&
CB2F SCOK
V03353a
410 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB1 F ARIP
SETCB1SPCL 1
1567
SETCB13PCL & 1P Reclaim Time
SETCB2SPCL &
CB2 L ARIP
CB2 LFRC
&
SETCB1SPCL 1
&
CB1 LFRC
&
SETCB2SPCL 1
&
CB2 LFRC &
&
SETCB13PCL
&
CB1 LFRC 1
&
SETCB23PCL
Dynamic F/L
Enabled
&
LeaderSPAR
SETCB13PCL
CB2 F ARIP 3PAR ReclaimTime
1
SETCB23PCL
V03404a
P54-TM-EN-1.1 411
Chapter 12 - Autoreclose P54
1570
3P Reclaim TComp
1568
1
1P Reclaim TComp & S 852
Q CB1 Succ 3P AR
RD
SETCB13PCL 0
&
CB1Op2/3P 0.02S
907
& S
CB1 Closed 3 ph Q
R
1570
3P Reclaim TComp
1568
1
1P Reclaim TComp & S 1451
Q CB2 Succ 1P AR
RD
SetCB2SPCl 0
&
CB2Op1P 0.02S
915
& S
CB2 Closed 3 ph Q
R
ResCB2ARSucc 1 CB2ARSucc
1570
3P Reclaim TComp
1568
1
1P Reclaim TComp & S 1452
Q CB2 Succ 3P AR
RD
SetCB23PCl 0
&
CB2Op2/3P 0.02S
915
& S
CB2 Closed 3 ph Q
R
1
V03359a
412 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB1OpAny
1541
1
AR Start
1 RESCB1 ARSUCC
Res AROK by UI
Enabled
&
Reset AROK Ind
Yes
Res AROK by NoAR
Enabled
&
AR Disabled
1
Num CBs
CB1 Only
1517
Ext Rst CB1 AROK
&
Res AROK by Ext
Enabled
Res AROK by TDly
Enabled
&
AROK Reset Time
t
CB1 ARSUCC
0
CB2OpAny
1541
1
AR Start
1 ResCB2ARSucc
Res AROK by UI
Enabled
&
Reset AROK Ind
Yes
Res AROK by NoAR
Enabled
&
AR Disabled
1
Num CBs
CB1 Only
1417
Ext Rst CB2 AROK
&
Res AROK by Ext
Enabled
Res AROK by TDly
Enabled
&
AROK Reset Time
t
CB2ARSucc
0 V03362a
Figure 271: Autoreclose Reset Successful Indication logic diagram (Modules 37 & 38)
P54-TM-EN-1.1 413
Chapter 12 - Autoreclose P54
synchronism timer expires, an alarm is set to inform that the check synchronism is not satisfied and cancels the
Autoreclose cycle.
CB Healthy Time
CB1 L 3PAR
1555
OK Time 3P 1
1572
CB1 Fast SCOK
CB1SPDTCOMP
1
CB1SPFTCOMP & S t 307
Q AR CB1 Unhealthy
RD 0
CB13PDTCOMP
CB13PFTCOMP
436
CB1 Healthy
306
CB1 AR Lockout 1
907
CB1 Closed 3 Ph
Check Sync Time
CB13PDTCOMP
1573
1 S
CB1L SCOK Q t 308
RD 1 AR CB1 No C/S
0
306
CB1 AR Lockout
907
1
CB1 Closed 3 Ph
CB13PFTCOMP
1491
1 S Note: If the DDB signal CB1 Healthy is not mapped in PSL, it defaults to High.
CB1F SCOK Q
RD
306
CB1 AR Lockout
907
1
CB1 Closed 3 Ph
CB Healthy Time
CB2 L 3PAR
1555
OK Time 3P 1
1454
CB2 Fast SCOK
CB2SPDTCOMP
1
CB2SPFTCOMP & S t 329
Q AR CB2 Unhealthy
RD 0
CB23PDTCOMP
CB23PFTCOMP
437
CB2 Healthy
328
CB2 AR Lockout 1
915
CB2 Closed 3 Ph
Check Sync Time
CB23PDTCOMP
1455
1 S
CB2L SCOK Q t 330
RD 1 AR CB2 No C/S
0
328
CB2 AR Lockout
915
1
CB2 Closed 3 Ph
CB23PFTCOMP
1456
1 S Note: If the DDB signal CB2 Healthy is not mapped in PSL, it defaults to High.
CB2F SCOK Q
RD
328
CB2 AR Lockout
915
1
CB2 Closed 3 Ph V03364a
Figure 272: Circuit Breaker Healthy and System Check Timers Healthy logic diagram (Module 38 & 40)
414 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
The logic provides the following summary information for each circuit breaker
● Overall total number of shots (Number of Autoreclose attempts)
● Number of successful 1st shot single-phase Autoreclose sequences
● Number of successful 1st shot three-phase Autoreclose sequences
● Number of successful 2nd shot three-phase Autoreclose sequences
● Number of successful 3rd shot three-phase Autoreclose sequences
● Number of successful 4th shot three-phase Autoreclose sequences
● Number of failed Autoreclose cycles which forced a circuit breaker to lockout
1565
Set CB1 Close Increment
CB1 Total Shots Counter
Reset
1571
CB1 Succ 1P AR Increment
CB1 Successful SPAR Shot 1 Counter
CB1 Succ 3P AR 852 Reset
847
& Increment
Seq Counter = 1 CB1 Successful 3PAR Shot 1 Counter
Reset
& Increment
848
Seq Counter = 2 CB1 Successful 3PAR Shot 2 Counter
Reset
849
& Increment
Seq Counter = 3 CB1 Successful 3PAR Shot 3 Counter
Reset
850
& Increment
Seq Counter = 4 CB1 Successful 3PAR Shot 1 Counter
Reset
1544 0
CB1 Arip
0.02 & Increment
CB1 Failed AR Counter
Reset
306
CB1 AR Lockout
1518
Ext Rst CB1Shots
1
Reset CB Shots
Yes
1449
Set CB2 Close Increment
CB2 Total Shots Counter
Reset
1451
CB2 Succ 1P AR Increment
CB2 Successful SPAR Shot 1 Counter
CB2 Succ 3P AR 1452 Reset
847
& Increment
Seq Counter = 1 CB2 Successful 3PAR Shot 1 Counter
Reset
& Increment
848
Seq Counter = 2 CB2 Successful 3PAR Shot 2 Counter
Reset
849
& Increment
Seq Counter = 3 CB2 Successful 3PAR Shot 3 Counter
Reset
850
& Increment
Seq Counter = 4 CB2 Successful 3PAR Shot 1 Counter
Reset
1435 0
CB2 Arip
0.02 & Increment
CB2 Failed AR Counter
Reset
328
CB2 AR Lockout
1418
Ext Rst CB2Shots
1
Reset CB Shots
Yes V03367a
Figure 273: Autoreclose Shot Counters logic diagram (Modules 41 & 42)
P54-TM-EN-1.1 415
Chapter 12 - Autoreclose P54
CB Control by
Opto
Note: If the DDB signal CB1 Healthy or CB2 Healthy is not mapped in PSL, it
Opto+Local defaults to High.
1
Opto+Remote
Opto+Rem+Local
Trip Pulse Time
838
HMI Trip Control TripCB1
1
& S t
439
& Q 302
Init Trip CB1 RD 0 & CB1 Trip Fail
440
&
Init close CB1 Man Close Delay Close Pulse Time
1 842
CB1 Close inProg
HMI Close
& S t
CB1 ARIP 1544 Q 839
RD 0 & Control CloseCB1
854
1 S t
Auto Close CB1 Q
RD 0
443
Rst CB1 CloseDly
522 303
Any Trip & CB1 Close Fail
1
838
Control TripCB1
534
CB1 Ext Trip3ph 1
1
535
CB1 Ext Trip A
536
CB1 Ext Trip B
537
CB1 Ext Trip C
1 1
903
CB1 Open 3 ph
904
CB1 Open A ph
905
CB1 Open B ph &
906
CB1 Open C ph
907
CB1 Closed 3 ph
1
908
CB1 Closed A ph
CB1 Closed B ph 909
1 CB Healthy Time
910
CB1 Closed C ph
t 304
436
& ManCB1 Unhealthy
CB1 Healthy 0
t 305
1574
& NoCS CB1ManClose
CB1 Man SCOK 0
V03370a
416 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
CB Control by
Opto
Opto+Local Note: If the DDB signal CB1 Healthy, or CB2 healthy is not mapped in PSL, it defaults to
1 High.
Opto+Remote
Opto+Rem+Local
Trip Pulse Time
840
HMI Trip Control TripCB2
1
& S t
441
& Q 324
Init Trip CB2 RD 0 & CB2 Trip Fail
442
&
Init close CB2 Man Close Delay Close Pulse Time
1 1453
CB2 Close inProg
HMI Close
& S t
CB2 ARIP 1435 Q 841
RD 0 & Control CloseCB2
1448
1 S t
Auto Close CB2 Q
RD 0
1419
Rst CB2 CloseDly
522 325
Any Trip & CB2 Close Fail
1
840
Control TripCB2
538
CB2 Ext Trip3ph 1
1
539
CB2 Ext Trip A
540
CB2 Ext Trip B
541
CB2 Ext Trip C
1 1
911
CB2 Open 3 ph
912
CB2 Open A ph
913
CB2 Open B ph &
914
CB2 Open C ph
915
CB2 Closed 3 ph
1
916
CB2 Closed A ph
CB2 Closed B ph 917
1 CB Healthy Time
918
CB2 Closed C ph
t 326
437
& ManCB2 Unhealthy
CB2 Healthy 0
t 327
1458
& NoCS CB2ManClose
CB2 Man SCOK 0
V03344a
P54-TM-EN-1.1 417
Chapter 12 - Autoreclose P54
TAR2/3Ph S t
Q 1575
RD 0 1 CB1 Fail Pr Trip
903
& S
CB1 Open 3 Ph Q
RD
907
CB1 Closed 3 Ph
TARA
& S
TMEM2/3Ph Q t
RD 1
0
903 & S
CB1 Open 3 Ph Q
RD
907
CB1 Closed 3 Ph 1
TARB
& S
TMEM2/3Ph Q
RD
903
& S
CB1 Open 3 Ph Q
RD
907
CB1 Closed 3 Ph 1
TARC
& S
TMEM2/3Ph Q
RD
903 & S
CB1 Open 3 Ph Q
RD
907
CB1 Closed 3 Ph 1
CB2 TAR2/3Ph S t
Q 1459
RD 0 1 CB2 Fail Pr Trip
911 & S
CB2 Open 3 Ph Q
RD
915
CB2 Closed 3 Ph
CB2 TARA
& S
CB2 TMEM2/3Ph Q t
RD 1
0
911 & S
CB2 Open 3 Ph Q
RD
915
CB2 Closed 3 Ph 1
CB2 TARB
& S
CB2 TMEM2/3Ph Q
RD
911
& S
CB2 Open 3 Ph Q
RD
915
CB2 Closed 3 Ph 1
CB2 TARC
& S
CB2 TMEM2/3Ph Q
RD
911 & S
CB2 Open 3 Ph Q
RD
915
CB2 Closed 3 Ph 1
V03377a
Figure 276: Circuit Breaker Trip Time Monitoring logic diagram (Modules 53 & 54)
418 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
● Block Autoreclose. If the block Autoreclose DDB is asserted whilst Autoreclose is in progress, the cycle goes
to lockout.
● Protection function selection. Setting ‘Block AR’ against a particular protection function in the AUTORECLOSE
column means that operation of the protection will block Autoreclose and force lockout.
● Circuit breaker failure to close. If a circuit breaker fails to close Autoreclose is blocked and forced to lockout.
● Circuit breaker remains open at the end of the reclaim time. An Autoreclose lockout is forced if the circuit
breaker is open at the end of the reclaim time.
● Circuit breaker fails to close when the close command is issued.
● Circuit breaker fails to trip correctly.
● Three-phase dead time started by ‘line dead’ violation. If the line does not go dead within the Dead Line
Time setting, the logic forces the Autoreclose sequence to lockout. Determination of when to start the timer
is made in the 3PDTStart WhenLD setting.
● Block Follower if Leader fails to close is set. If the setting BF if Lfail Cls in the AUTORECLOSE column is set to
Enable, the active Follower circuit breaker will lockout if the Leader circuit breaker fails to reclose.
● Leader/Follower invalid selection using opto-isolated input. If the Leader/Follower Autoreclose mode in the
AUTORECLOSE settings is set to be selected using the opto-isolated inputs, then if the logic detects an invalid
Autoreclose mode combination, it forces both circuit breakers to lockout if a trip occurs.
P54-TM-EN-1.1 419
Chapter 12 - Autoreclose P54
FLTMEM 3P
&
Multi Phase AR
BAR 3 Phase
1
BAR 2 and 3 Ph
&
FLTMEM 2P
303
CB1 Close Fail
BF if LFail Cls
& 306
CB1 AR Lockout
Enabled
CB2 LFRC
& 1385
CB1 F ARIP Mod 5 AR In Service
&
CB2 AR Lockout 328
Num CBs & S
Q
R
CB1 Fail Pr Trip 1575 Both CB1&CB2
1
CB1 Only
CB1OpAny
1544
CB1 ARIP & Mod 57-58 RESCB1LO
Block CB1 AR 448 &
307
AR CB1 Unhealthy
308
AR CB1 No C/S
1547
Evolve 3Ph S
Q
Prot Re-op R
LastShot &
1544
CB1 ARIP
Evolve Lock & 1 BARCB1
Prot AR Block
1526
CB1 In Service
&
TMEM2/3Ph
CB1 L 3PAROK 0
1
CB1 F 3PAROK 0.02s
1526
CB1 In Service
&
TMEM1Ph
CB1 L SPAROK 0 Note: This diagram shows the logic for CB1 only. The logic for
1 CB2 follows the same principles and is not repeated.
CB1 F SPAROK 0.02s
1546
Seq Counter>Set
301
CB1 Status Alm
CB1 L ARIP Trip Pulse Time
1
CB1 F ARIP
Set CB1 Close 1565 t
&
Set CB2 Close 1449 0
CB2OpAny
1428
&
CB2 In Service
1526
CB1 In Service
&
Num CBs
&
Both CB1&CB2
1459
CB2 Fail Pr Trip
Invalid AR Mode
&
1543
CB1 AR Init
1544
1
CB1 ARIP
DeadLineLockout
1544
CB1 ARIP
2909
&
AAR Perm Flt
V03447a
420 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
FLTMEM 3P
&
Multi Phase AR
BAR 3 Phase
1
BAR 2 and 3 Ph
&
FLTMEM 2P
325
CB2 Close Fail
BF if LFail Cls
& 328
CB2 AR Lockout
Enabled
CB1 LFRC
& 1385
CB2 F ARIP Mod 5 AR In Service
&
CB1 AR Lockout 306
Num CBs & S
Q
R
CB2 Fail Pr Trip 1459 Both CB1&CB2
1
CB1 Only
CB2OpAny
1435
CB2 ARIP & Mod 57-58 RESCB2LO
Block CB2 AR 1421 &
329
AR CB2 Unhealthy
330
AR CB2 No C/S
1547
Evolve 3Ph S
Q
ProtRe_Op R
LastShot &
1435
CB2 ARIP
EvolveLock & 1 BARCB2
ProtARBlock
1428
CB2 In Service
&
CB2 TMEM2/3Ph
CB2 L 3PAROK 0
1
CB2 F 3PAROK 0.02s
1428
CB2 In Service
&
CB2 TMEM1Ph
CB2 L SPAROK 0
1
CB2 F SPAROK 0.02s
1546
Seq Counter>Set
323
CB2 Status Alm
CB2 L ARIP Trip Pulse Time
1
CB2 F ARIP
Set CB2 Close 1449 t
&
Set CB1 Close 1565 0
CB1OpAny
1526
&
CB1 In Service
1428
CB2 In Service
&
Num CBs
&
Both CB1&CB2
1575
CB1 Fail Pr Trip
Invalid AR Mode
&
1434
CB2 AR Init
1435
1
CB2 ARIP
DeadLineLockout
1435
CB2 ARIP
2909
&
AAR Perm Flt V03448a
P54-TM-EN-1.1 421
Chapter 12 - Autoreclose P54
If set to User Interface then a command, CB mon LO reset, becomes visible. This command can be used to
reset the lockout from a user interface.
An Autoreclose lockout generates an Autoreclose lockout alarm. Autoreclose lockout conditions can be reset by
various commands and setting options found under the CB CONTROL column.
If Res LO by CB IS is set to Enabled, a lockout is reset if the circuit breaker is successfully closed manually. For
this, the circuit breaker must remain closed long enough so that it enters the “In Service” state.
If Res LO by UI is set to Enabled, the circuit breaker lockout can be reset from a user interface using the reset
circuit breaker lockout command in the CB CONTROL column.
If Res LO by NoAR is set to Enabled, the circuit breaker lockout can be reset by temporarily generating an AR
disabled signal.
If Res LO by TDelay is set to Enabled, the circuit breaker lockout is automatically reset after a time delay set in
the LO Reset Time setting.
If Res LO by ExtDDB is Enabled, the circuit breaker lockout can be reset by activation of an external input
mapped in the PSL to the relevant reset lockout DDB signal.
422 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Res LO by CB IS
Enabled
&
CB1CRLO
Res LO by UI
Enabled
&
Reset CB1 LO
Yes
Res LO by NoAR
Enabled
& 1 RESCB1LO
ARDisabled
1
Num CBs
CB2 Only
Res LO by ExtDDB
Enabled
&
446
Rst CB1 Lockout
Res LO by TDelay
Enabled
&
LO Reset Time
306
t
CB1 AR Lockout
0
Res LO by CB IS
Enabled
&
CB2CRLO
Res LO by UI
Enabled
&
Reset CB2 LO
Yes
Res LO by NoAR
Enabled
& 1 RESCB2LO
ARDisabled
1
Num CBs
CB2 Only
Res LO by ExtDDB
Enabled
&
1422
Rst CB2 Lockout
Res LO by TDelay
Enabled
&
LO Reset Time
328
t
CB2 AR Lockout
0
V03383a
Figure 279: Reset Circuit Breaker Lockout Logic Diagram (Modules 57 & 58)
P54-TM-EN-1.1 423
Chapter 12 - Autoreclose P54
328
CB2 AR Lockout
1 0.04 1607
CB2 LO Alarm 1599 & Pole Discrep CB2
0
1606
Pol Disc CB2 Ext
855
&
CB2 AR 1p InProg
912
CB2 Open A ph
1
913
CB2 Open B ph
914
CB2 Open C ph
&
V03385a
424 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
&
894
1
Pole Dead C
&
V03387a
Figure 281: Circuit Breaker Trip Conversion Logic Diagram (Module 63)
P54-TM-EN-1.1 425
Chapter 12 - Autoreclose P54
System Checks
Enabled
VAN 888
Live Line & Live Line
VBN
VCN 889
Select Dead Line & Dead line
VAB
VBC 886
Live Bus 1 & Live Bus 1
VCA
VBus 2
1461
Live Bus 2 & Live Bus 2
MCB/VTS 438
1521 1462
MCB/VTS CB1 CS Dead Bus 2 & Dead Bus 2
1423
MCB/VTS CB2 CS
Voltage Monitors
1522 1
Inhibit LL
1523 1
Inhibit DL
1524 1
Inhibit LB 1
1525
1
Inhibit DB 1
1424 1
Inhibit LB 2
1425 1
Inhibit DB 2
V 01258
426 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Sys checks CB 1
880
Disabled SChksInactiveCB 1
Enabled
CS1 Criteria OK
VAN &
VBN CS2 Criteria OK
&
VCN
Select CB1 CS1 SlipF> 1578
VAB & CB1 CS1 SlipF>
CS Vbus1< 1582
& CS Vbus<
CB1 CS1 Vl>Vb 1586
& CB1 CS1 Vl> Vb
CB1 CS1 Vl<Vb 1588
& CB1 CS1 Vl< Vb
CB1 CS1 Fl>Fb 1590
& CB1 CS1 Fl>Fb
CB1 CS1 Fl<Fb 1591
& CB1 CS1 Fl<Fb
CB1 CS1 AngHigh+ 1592
& CB1 CS1 AngHigh+
CB1 CS1 AngHigh- 1593
& CB1 CS1 AngHigh-
CB1 CS2 Fl>Fb 1493
& CB1 CS2 Fl>Fb
CB1 CS2 Fl<Fb 1494
& CB1 CS2 Fl<Fb
CB1 CS2 AngHigh+ 1495
& CB1 CS2 AngHigh+
CB1 CS2 AngHigh- 1496
& CB1 CS2 AngHigh-
CB1 CS AngRotACW 1594
& CB1 CS AngRotACW
1521
MCB/VTS CB CS CB1 CS AngRotCW 1595
438 & CB1 CS AngRotCW
MCB/VTS
832 CB1 CS2 Vl>Vb 1587
VTS Fast Block & CB1 CS2 Vl> Vb
1
319
F out of Range CB1 CS2 Vl<Vb 1589
& CB1 CS2 Vl< Vb
CB1 CS1 Status
883
Enabled & CB1 CS1 OK
881
CB1 CS1 Enabled
CB1 CS2 Status
884
Enabled & CB1 CS2 OK
882
CB1 CS2 Enabled V01260
Figure 283: Check Synchronisation Monitor for CB1 closure (Module 60)
P54-TM-EN-1.1 427
Chapter 12 - Autoreclose P54
Sys checks CB 2
1484
Disabled SChksInactiveCB 2
Enabled
CS1 Criteria OK
VAN &
&
CS Vbus2> 1585
& CS Vbus2>
&
CS Vbus2<
Check Synchronisation Function
1584
& CS Vbus2<
CB2 CS1 Vl>Vb 1470
& CB2 CS1 Vl> Vb
CB2 CS1 Vl<Vb 1472
& CB2 CS1 Vl< Vb
CB2 CS1 Fl>Fb 1474
& CB2 CS1 Fl>Fb
CB2 CS1 Fl<Fb 1476
& CB2 CS1 Fl<Fb
CB2 CS1 AngHigh+ 1478
& CB2 CS1 AngHigh+
CB2 CS1 AngHigh- 1479
& CB2 CS1 AngHigh-
CB2 CS2 Fl>Fb 1475
& CB2 CS2 Fl>Fb
CB2 CS2 Fl<Fb 1477
& CB2 CS2 Fl<Fb
CB2 CS2 AngHigh+ 1480
& CB2 CS2 AngHigh+
CB2 CS2 AngHigh- 1481
& CB2 CS2 AngHigh-
CB2 CS AngRotACW 1482
& CB2 CS AngRotACW
1521
MCB/VTS CB CS CB2 CS AngRotCW 1483
438 & CB2 CS AngRotCW
MCB/VTS
832 CB2 CS2 Vl>Vb 1471
VTS Fast Block & CB2 CS2 Vl> Vb
1
319
F out of Range CB2 CS2 Vl<Vb 1473
& CB2 CS2 Vl< Vb
CB2 CS1 Status
1577
Enabled & CB2 CS1 OK
1426
CB2 CS1 Enabled
CB2 CS2 Status
884
Enabled & CB1 CS2 OK
1427
CB2 CS2 Enabled V01268
Figure 284: Check Synchronisation Monitor for CB2 closure (Module 61)
428 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
For single-phase Autoreclose no voltage or synchronism check is required as synchronising power is flowing in the
two healthy phases. Three-phase Autoreclose can be performed without checking that voltages are in
synchronism for the first shot (and only the first shot). The settings to permit Autoreclose without checking voltage
synchronism on the first shot are:
● CB1L SC Shot 1 for circuit breaker 1 as a leader,
● CB1F SC Shot 1 for circuit breaker 1 as a follower,
● CB2L SC Shot 1 for circuit breaker 2 as a leader,
● CB2L SC Shot 1 for circuit breaker 2 as a follower.
When the circuit breaker has closed, the Autoreclose function asserts a DDB signal Set CB1 Close, which indicates
that an attempt has been made to close the circuit breaker. At this point, the Reclaim Time starts. If the circuit
breaker remains closed after the reclaim timer expires, the Autoreclose cycle is complete, and signals are
generated to indicate that Autoreclose was successful. These are:
● CB1 Succ 1P AR (Single-phase Autoreclose CB1)
● CB2 Succ 1P AR (Single-phase Autoreclose CB2)
● CB1 Succ 3P AR (Three-phase Autoreclose CB1)
● CB2 Succ 3P AR (Three-phase Autoreclose CB2)
These signals increment the relevant circuit breaker successful Autoreclose shot counters, as well as resetting the
Autoreclose in progress signal.
The relevant circuit breaker successful Autoreclose shot counters are:
● CB1 SUCC SPAR (Single-phase Autoreclose CB1)
● CB1 SUCC 3PAR Shot1 (Three-phase Autoreclose CB1, Shot 1)
● CB1 SUCC 3PAR Shot2 (Three-phase Autoreclose CB1, Shot 2)
● CB1 SUCC 3PAR Shot3 (Three-phase Autoreclose CB1, Shot 3)
● CB1 SUCC 3PAR Shot4 (Three-phase Autoreclose CB1, Shot 4)
● CB2 SUCC SPAR (Single-phase Autoreclose CB2)
● CB2 SUCC 3PAR Shot1 (Three-phase Autoreclose CB2, Shot 1)
● CB2 SUCC 3PAR Shot2 (Three-phase Autoreclose CB2, Shot 2)
● CB2 SUCC 3PAR Shot3 (Three-phase Autoreclose CB2, Shot 3)
● CB1 SUCC 3PAR Shot4 (Three-phase Autoreclose CB2, Shot 4)
P54-TM-EN-1.1 429
Chapter 12 - Autoreclose P54
CB1L SC ClsNoDly
Enabled 1572
& CB1 Fast SCOK
CB1L SC CS1
Enabled 1
&
883
CB1 CS1 OK
CB1L SC CS2
Enabled
&
884
CB1 CS2 OK
CB1L SC DLLB
Enabled
889
&
Dead Line
886
Live Bus 1
CB1L SC LLDB
Enabled
1573
888
& 1 CB1L SCOK
Live Line
887
Dead Bus 1
CB1L SC DLDB
Enabled
889
&
Dead Line
Dead Bus 1 887 Note: If the DDB signal CB1 Ext CS OK is not mapped in PSL, it defaults to High.
CB1L SC Shot 1
Disabled
&
847
Seq Counter = 1
CB1L SC all
Disabled
&
900
CB1 Ext CS OK V03373a
Figure 285: Three-phase AR System Check logic diagram for CB1 as leader (Module 45)
CB2L SC ClsNoDly
Enabled 1454
& CB2 Fast SCOK
CB2L SC CS1
Enabled 1
&
1577
CB2 CS1 OK
CB2L SC CS2
Enabled
&
1463
CB2 CS2 OK
CB2L SC DLLB
Enabled
889
&
Dead Line
1461
Live Bus 2
CB2L SC LLDB
Enabled
1455
888
& 1 CB2L SCOK
Live Line
887
Dead Bus 1
CB2L SC DLDB
Enabled
889
&
Dead Line
1462
Dead Bus 2
CB2L SC Shot 1 Note: If the DDB signal CB2 Ext CS OK is not mapped in PSL, it defaults to High.
Disabled
&
847
Seq Counter = 1
CB2L SC all
Disabled
&
901
CB2 Ext CS OK V03345a
Figure 286: Three-phase AR System Check logic diagram for CB2 as leader (Module 46)
430 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
&
CB1F SC CS1
Enabled 1
&
883
CB1 CS1 OK
CB1F SC CS2
Enabled
&
884
CB1 CS2 OK
CB1F SC DLLB
Enabled
889
&
Dead Line
886
Live Bus 1
CB1F SC LLDB
Enabled
1491
888
& 1 CB1F SCOK
Live Line
887
Dead Bus 1
CB1F SC DLDB
Enabled
889
&
Dead Line
Dead Bus 1 887 Note: If the DDB signal CB1 Ext CS OK is not mapped in PSL, it
defaults to High.
CB1F SC Shot 1
Disabled
&
847
Seq Counter = 1
CB1F SC all
Disabled
&
900
CB1 Ext CS OK V03401a
Figure 287: Three-phase AR System Check logic d for CB1 as follower (Module 47)
&
CB2F SC CS1
Enabled 1
&
1577
CB2 CS1 OK
CB2F SC CS2
Enabled
&
1463
CB2 CS2 OK
CB2F SC DLLB
Enabled
889
&
Dead Line
1461
Live Bus 2
CB2F SC LLDB
Enabled
1456
888
& 1 CB2F SCOK
Live Line
887
Dead Bus 1
CB2F SC DLDB
Enabled
889
&
Dead Line
1462
Dead Bus 2 Note: If the DDB signal CB2 Ext CS OK is not mapped in PSL, it defaults to High.
CB2F SC Shot 1
Disabled
&
847
Seq Counter = 1
CB2F SC all
Disabled
&
901
CB2 Ext CS OK V03402a
Figure 288: Three-phase AR System Check logic diagram for CB2 as follower (Module 48)
P54-TM-EN-1.1 431
Chapter 12 - Autoreclose P54
CB1M SC CS1
Enabled
&
883
CB1 CS1 OK
CB1M SC CS2
Enabled
&
884
CB1 CS2 OK
CB1M SC DLLB
Enabled
889
&
Dead Line
886
Live Bus 1
CB1M SC LLDB
Enabled
1574
888
& 1 CB1 Man SCOK
Live Line
887
Dead Bus 1
CB1M SC DLDB
Enabled Note: If the DDB signal CB1 Ext CS OK is not mapped in PSL, it
& defaults to High.
889
Dead Line
887
Dead Bus 1
CB1M SC required
Disabled
&
900
CB1 Ext CS OK
CB2M SC CS1
Enabled
&
1577
CB2 CS1 OK
CB2M SC CS2
Enabled
&
1463
CB2 CS2 OK
CB2M SC DLLB
Enabled
889
&
Dead Line
1461
Live Bus 2
CB2M SC LLDB
Enabled
1458
888
& 1 CB2 Man SCOK
Live Line
1462
Dead Bus 2
CB2M SC DLDB
Enabled
&
Dead Line 889 Note: If the DDB signal CB2 Ext CS OK is not mapped in PSL, it
defaults to High.
1462
Dead Bus 2
CB2M SC required
Disabled
&
901
CB2 Ext CS OK V03375a
Figure 289: CB Manual Close System Check Logic Diagram (Modules 51 & 52)
432 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
6 SETTING GUIDELINES
P54-TM-EN-1.1 433
Chapter 12 - Autoreclose P54
434 P54-TM-EN-1.1
P54 Chapter 12 - Autoreclose
Local end protection (Time delayed Back up protection, like distance Z2 element) may detect this fault after a time
delay (typically > 200 ms). In addition to the delays associated with the back-up protection (typically >200 ms), time
must be allowed for the Leader circuit breaker to re-trip (50 - 100 ms), and a safety margin needs to be added so
that a minimum Follower time could be around 500 ms.
If the Autoreclose of the Leader circuit breaker is successful, the Follower circuit breaker can be allowed to
Autoreclose. Delaying the Autoreclose of the Follower circuit breaker will allow any transients to decay before the
switching. If the transient decay figure is known, it can be used to determine a minimum Follower Time value. The
larger of the two values can then be used as the minimum Follower Time.
Note:
The Follower circuit breaker should only be reclosed if the system is healthy. In a dual circuit breaker scheme where the
system is healthy, the Follower circuit breaker acts more like a bus coupler. In this case there is no need for fast switching and
a time delay in excess of 1s is often appropriate. The default Follower time in this product is chosen as 5 s and this can
comfortably be applied to most applications.
P54-TM-EN-1.1 435
Chapter 12 - Autoreclose P54
436 P54-TM-EN-1.1
CHAPTER 13
CB FAIL PROTECTION
Chapter 13 - CB Fail Protection P54
438 P54-TM-EN-1.1
P54 Chapter 13 - CB Fail Protection
1 CHAPTER OVERVIEW
The device provides a Circuit Breaker Fail Protection function. This chapter describes the operation of this function
including the principles, logic diagrams and applications.
This chapter contains the following sections:
Chapter Overview 439
Circuit Breaker Fail Protection 440
Circuit Breaker Fail Implementation 441
Circuit Breaker Fail Logic 443
Application Notes 449
P54-TM-EN-1.1 439
Chapter 13 - CB Fail Protection P54
440 P54-TM-EN-1.1
P54 Chapter 13 - CB Fail Protection
You can configure the CBF elements CB Fail 1 Timer and CBF Fail 2 Timer to operate for trips triggered by
protection elements within the device. Alternatively you can use an external protection trip by allocating one of the
opto-inputs to the External Trip DDB signal in the PSL.
You can reset the CBF from a breaker open indication (from the pole dead logic) or from a protection reset. In these
cases resetting is only allowed if the undercurrent elements have also been reset. The resetting mechanism is
determined by the settings NonIProt Rst and Ext Prot Rst.
The resetting options are summarised in the following table:
Initiation (Menu Selectable) CB Fail Timer Reset Mechanism
IA< operates AND IB< operates AND IC< operates AND IN< operates or
Current based protection (e.g.50/51/46/21/87)
through Ext Rst DDB in PSL
Sensitive Earth Fault element ISEF< Operates or Ext Rst SEF DDB
Five options are available:
● All I< and IN< elements operate or Ext Rst CBF DDB
Non-current based protection (e.g. 27/59/81/32L) ● Protection element reset AND (all I< and IN< elements operate
or Ext Rst DDB
● CB open (all 3 poles) AND all I< and IN< elements operate
Five options are available.
● All I< and IN< elements operate
● External trip reset AND all I< and IN< elements operate
● CB open (all 3 poles) AND all I< and IN< elements operate
External protection
● Prot Reset OR I<: External trip reset OR all I< and IN< elements
operate
● Rst or CBOp & I<: External trip reset OR Pole Dead AND all I< and
IN< elements operate
P54-TM-EN-1.1 441
Chapter 13 - CB Fail Protection P54
442 P54-TM-EN-1.1
P54 Chapter 13 - CB Fail Protection
WI Prot Reset
Enabled
ISEF<FastUndercurrent
1
2938
Ext Rst SEF
ZCDStateA
ZCDStateB
ZCD function
ZCDStateC
ZCDStateSEF
V09000
P54-TM-EN-1.1 443
Chapter 13 - CB Fail Protection P54
2081 1 S
Ext Trip AExc
& 4 Q TripStateExt A
1
RD
Exclus.CBF sig.
3
1
Ext Prot Reset
Yes
2 0 I< Only
&
1 CB Open & I<
892
Pole Dead A 1 2 Prot Reset & I<
&
3 Prot Reset OR I<
0 4 Rst OR CBOp & I<
IA<FastUndercurrent
OR
2930
Ext RSt CBF 4
2931
Latch ATripResetIncomp
Ext Rst CBF A
3
2
&
1
&
0
Logic 0
V09001a
2081 1 S
Ext Trip AExc
& 4 Q TripStateExtACB1
1 RD
3
Exclus.CBF sig. 1
CB1 Ext Prot Rst
Yes
2 0 I< Only
&
1 CB Open & I<
904
CB1 Open A ph 1 2 Prot Reset & I<
&
3 Prot Reset OR I<
0 4 Rst OR CBOp & I<
IA<FastUndercurrent
OR
2930
Ext Rst CB1F 4
LatchATripResetIncompCB1
Ext Rst CB1F A 2931
3
2
&
1
&
0
Logic 0
V09002a
444 P54-TM-EN-1.1
P54 Chapter 13 - CB Fail Protection
TripStateExtA 1 TripStateA
2931
Ext Rst CBF A
534
External Trip3Ph
&
2080
1 S
CB1 Ext Trip 3PhE
& 4 Q
1 1
RD
3
Exclu s.CBF sig. 1
Ext Prot Reset
Yes
2 0 I< Only
&
890
1 CB Open & I<
All Poles Dead
1 1 2 Prot Reset & I<
892
&
Pole Dead A 3 Prot Reset OR I<
893
0 4 Rst OR CBOp & I<
Pole Dead B &
894
Pole Dead C
4
Latch3PhTripResetIncomp
3
2930
Ext Rst CBF
2
&
IA<FastUndercurrent
IB<FastUndercurrent & OR 1
&
IC<FastUndercurrent
0
ExtTrip Only Ini 0
Enabled
874
& S
CBF Non I Trip
2 Q
&
RD
890
All Poles Dead
1 1
892
&
Pole Dead A Non IProt Rst
893
0 0 I< Only
Pole Dead B &
1 CB Open & I<
894
Pole Dead C 2 Prot Reset & I<
IA<FastUndercurrent
IB<FastUndercurrent & OR
2
&
IC<FastUndercurrent LatchNonITripResetIncomp
2930
1
Ext Rst CBF &
0
Logic 0
V09003a
P54-TM-EN-1.1 445
Chapter 13 - CB Fail Protection P54
TripStateExtA 1 TripStateACB1
2931
Ext Rst CB1F A
534
CB1 Ext Trip3Ph
&
2080
1 S
CB1 Ext Trip 3PhE
& 4 Q
1 1
RD
3
Exclu s.CBF sig. 1
CB1 Ext Prot Rst
Yes
2 0 I< Only
&
534 1 CB Open & I<
CB1 Open 3 ph
1 1 2 Prot Reset & I<
904
&
CB1 Open A ph 3 Prot Reset OR I<
905
0 4 Rst OR CBOp & I<
CB1 Open B ph &
906
CB1 Open C ph
4
Latch3PhTripResetIncompCB1
3
2930
Ext Rst CB1F
2
&
IA<FastUndercurrent
IB<FastUndercurrent & OR 1
&
IC<FastUndercurrent
0
ExtTrip Only Ini 0
Enabled
874
& S
CBF Non I Trip
2 Q
&
RD
890
All Poles Dead
1 1
892
&
Pole Dead A CB1 NonIProt Rst
893
0 0 I< Only
Pole Dead B &
1 CB Open & I<
894
Pole Dead C 2 Prot Reset & I<
IA<FastUndercurrent
IB<FastUndercurrent & OR
2
&
IC<FastUndercurrent LatchNonITripResetIncompCB1
2930
1
Ext Rst CB1F &
0
Logic 0
V09004a
446 P54-TM-EN-1.1
P54 Chapter 13 - CB Fail Protection
835
1 Bfail2 Trip 3ph
CBZCDStateA
WIINFEEDA
1
TripStateA
& & 1672
t 1 CB Fail1 Trip A
CB Fail 1 Status
0
Enabled
CB Fail 1 Timer
1
& 1675
TripStateA t 1 CB Fail2 Trip A
&
0
CB Fail 2 Status
Enabled
CB Fail 2 Timer
ZCDStateSEF
1
TripStateSEF
& &
t
CB Fail 1 Status
0
Enabled
CB Fail 1 Timer
1
&
TripStateSEF t
&
0
CB Fail 2 Status
Enabled
CB Fail 2 Timer
*1: Not used in P445.
V00732a
Note:
This diagram shows only phase-A for a single-CB device. The diagrams for phases B and C follow the same principle and are
not repeated here.
P54-TM-EN-1.1 447
Chapter 13 - CB Fail Protection P54
835
1 CB1 Fail2 Trip
CB1 ZCD State A
WI INFEED A
1
TripStateA CB1
& & 1672
t 1 CB1 Fail1 Trip A
CB1 Fail1 Status
0
Enabled
1
& 1675
TripStateA t 1 CB1 Fail2 Trip A
&
0
CB1 Fail2 Status
Enabled
ZCD StateSEF
1
TripStateSEF
& &
t
CB1 Fail1 Status
0
Enabled
1
&
TripStateSEF t
&
0
CB1 Fail2 Status
Enabled
V00742
Note:
This diagram shows only phase-A for the first CB (CB1) of a dual-CB device. The diagrams for phases B and C and for the
second CB (CB2) follow the same principle and are not repeated here.
448 P54-TM-EN-1.1
P54 Chapter 13 - CB Fail Protection
5 APPLICATION NOTES
For any protection function requiring current to operate, the device uses operation of undercurrent elements to
detect that the necessary circuit breaker poles have tripped and reset the CB fail timers. However, the
undercurrent elements may not be reliable methods of resetting CBF in all applications. For example:
● Where non-current operated protection, such as under/overvoltage or under/overfrequency, derives
measurements from a line connected voltage transformer. Here, I< only gives a reliable reset method if the
protected circuit would always have load current flowing. In this case, detecting drop-off of the initiating
protection element might be a more reliable method.
● Where distance schemes include Weak Infeed trip logic. The reset of the Weak infeed trip condition should
be used in addition to the undercurrent check. WI Prot Reset should be set to enabled.
● Where non-current operated protection, such as under/overvoltage or under/overfrequency, derives
measurements from a busbar connected voltage transformer. Again using I< would rely on the feeder
normally being loaded. Also, tripping the circuit breaker may not remove the initiating condition from the
busbar, and so drop-off of the protection element may not occur. In such cases, the position of the circuit
breaker auxiliary contacts may give the best reset method.
You can reset the CBF from a breaker open indication (from the pole dead logic) or from a protection reset. In these
cases resetting is only allowed if the undercurrent elements have also been reset. The resetting mechanism is
determined by the settings Non I Prot Reset and Ext Prot Reset.
If the CBF protection is initiated by an external protection trip, then two resetting options Prot Reset OR I< and Rst
or CBOp & I< are provided. These settings don’t necessarily require undercurrent element (I<) operation, as shown
in the table below. These options are useful if re-tripping is not implemented, as they allow avoiding back-tripping
due to spurious short-time energisation of External Trip opto-inputs.
Warning:
If you are using Prot Reset OR I< or Rst or CBOp & I<, do not connect the External Trip inputs to the
Trip Conversion logic inputs in the PSL.
P54-TM-EN-1.1 449
Chapter 13 - CB Fail Protection P54
CBF resets:
1. Undercurrent element asserts
2. Undercurrent element asserts and the
breaker status indicates an open position
3. Protection resets and the undercurrent
Fault occurs element asserts
CBF Safety
Protection Maximum breaker reset margin
Normal operating time clearing time time time
operation
t
Local 86 Remote CB
operating clearing time
time
The following examples consider direct tripping of a 2-cycle circuit breaker. Typical timer settings to use are as
follows:
Typical Delay For 2 Cycle Circuit
CB Fail Reset Mechanism tBF Time Delay
Breaker
CB interrupting time + element reset time (max.) + error in tBF
Initiating element reset 50 + 50 + 10 + 50 = 160 ms
timer + safety margin
CB auxiliary contacts opening/ closing time (max.) + error in tBF
CB open 50 + 10 + 50 = 110 ms
timer + safety margin
CB interrupting time + undercurrent element (max.) + safety
Undercurrent elements 50 + 25 + 50 = 125 ms
margin operating time
Note:
All CB Fail resetting involves the operation of the undercurrent elements. Where element resetting or CB open resetting is
used, the undercurrent time setting should still be used if this proves to be the worst case.
Where auxiliary tripping relays are used, an additional 10-15 ms must be added to allow for trip relay operation.
450 P54-TM-EN-1.1
CHAPTER 14
452 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
1 CHAPTER OVERVIEW
The primary purpose of this product is not overcurrent protection. It does however provide a range of current
protection functions to be used as backup protection. This chapter assumes you are familiar with overcurrent
protection principles and does not provide detailed information here. If you require further information about
general overcurrent protection principles, please refer either to General Electric's publication, Protection and
Automation Application Guide, earlier incarnations of this technical manual, or one of our technical manuals from
our P40 Agile Modular distribution range of products such as the P14.
This chapter contains the following sections:
Chapter Overview 453
Phase Fault Overcurrent Protection 454
Negative Sequence Overcurrent Protection 457
Earth Fault Protection 460
Sensitive Earth Fault Protection 465
High Impedance REF 470
Thermal Overload Protection 472
Broken Conductor Protection 476
Transient Earth Fault Detection 478
P54-TM-EN-1.1 453
Chapter 14 - Current Protection Functions P54
454 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
Under system fault conditions, the fault current vector lags its nominal phase voltage by an angle depending on
the system X/R ratio. The IED must therefore operate with maximum sensitivity for currents lying in this region. This
is achieved by using the IED characteristic angle (RCA). This is the is the angle by which the current applied to the
IED must be displaced from the voltage applied to the IED to obtain maximum sensitivity.
The device provides a setting I> Char Angle, which is set globally for all overcurrent stages. It is possible to set
characteristic angles anywhere in the range –95° to +95°.
A directional check is performed based on the following criteria:
Directional forward
-90° < (angle(I) - angle(V) - RCA) < 90°
Directional reverse
-90° > (angle(I) - angle(V) - RCA) > 90°
For close up three-phase faults, all three voltages will collapse to zero and no healthy phase voltages will be
present. For this reason, the device includes a synchronous polarisation feature that stores the pre-fault voltage
information and continues to apply this to the directional overcurrent elements for a time period of 3.2 seconds.
This ensures that either instantaneous or time-delayed directional overcurrent elements will be allowed to operate,
even with a three-phase voltage collapse.
P54-TM-EN-1.1 455
Chapter 14 - Current Protection Functions P54
IDMT/DT
I>1 Current Set 656
& & I>1 Trip A
IDMT/DT
I>1 Current Set 657
& & I>1 Trip B
IDMT/DT
I>1 Current Set 658
& & I>1 Trip C
761
I>1 Direction 1 I>1 Start
Directio nal check
832 Timer
VTS Fast Block
Settings 655
I> Blocking &
1 I>1 Trip
VTS Blocks I>1
463
Inhibit I>1
401 Note: For the purpose of clarity, this diagram shows
I>1 Timer Block
the first relevant stage number for each signal and
setting name.
V00735
1016
Ih(2) Loc Blk A
1017 463
Ih(2) Lock Blk B 1 Inhibit I>1
1018
Ih(2) Loc Blk C
V09009a
456 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
P54-TM-EN-1.1 457
Chapter 14 - Current Protection Functions P54
567
I2>1 Start
I2
IDMT/DT
I2>1 Current Set 571
& & & I2>1 Trip
928
CTS Block
562
I2> Inhibit
I2>1 Direction
V2
Directional
I2> V2pol Set
check
833
VTS Slow Block
I2> VTS Blocking &
VTS Blocks I2>1
562
I2> Inhibit
563
I2>1 Tmr Blk
Note: For the purpose of clarity, this diagram shows the first
relevant stage number for each signal and setting name.
V00736
458 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
For the negative phase sequence directional elements to operate, the device must detect a polarising voltage
above a minimum threshold, I2> V2pol Set. This must be set in excess of any steady state negative phase
sequence voltage. This may be determined during the commissioning stage by viewing the negative phase
sequence measurements in the device.
P54-TM-EN-1.1 459
Chapter 14 - Current Protection Functions P54
Depending on the device model, it will provide one or more of the above means for Earth fault protection.
I
top = 5.8 − 1.35 log e
IN > Setting
where:
460 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
Note:
Although the start point of the characteristic is defined by the "ΙN>" setting, the actual current threshold is a different setting
called "IDG Ιs". The "IDG Ιs" setting is set as a multiple of "ΙN>".
Note:
When using an IDG Operate characteristic, DT is always used with a value of zero for the Rest characteristic.
An additional setting "IDG Time" is also used to set the minimum operating time at high levels of fault current.
10
8 IDGIsIsSetting
IDG SettingRange
Range
time (seconds)
(seconds)
6
Operating time
5
Operating
3
IDG Time
IDG Time Setting
Setting Range
Range
2
0
1 10 100
I/IN>
V00611
P54-TM-EN-1.1 461
Chapter 14 - Current Protection Functions P54
Small levels of residual voltage could be present under normal system conditions due to system imbalances, VT
inaccuracies, device tolerances etc. For this reason, the device includes a user settable threshold (IN> VNPol set),
which must be exceeded in order for the DEF function to become operational. The residual voltage measurement
provided in the MEASUREMENTS 1 column of the menu may assist in determining the required threshold setting
during the commissioning stage, as this will indicate the level of standing residual voltage present.
Note:
Residual voltage is nominally 180° out of phase with residual current. Consequently, the DEF elements are polarised from the
"-Vres" quantity. This 180° phase shift is automatically introduced within the device.
462 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
777
IN>1 Start
IN
IDMT/DT
IN>1 Current Set 671
& & & IN>1 Trip
928
CTS Block
467
Inhibit IN>1
IN>1 Directional
VN
833
VTS Slow Block
IN> Blocking &
VTS Blocks IN>1
467
Inhibit IN>1
405
IN>1 Timer Blk
V2
Negative Sequence Polarisation Note: For the purpose of clarity, this diagram shows
the first relevant stage number for each signal and
V00737 setting name.
P54-TM-EN-1.1 463
Chapter 14 - Current Protection Functions P54
464 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
P54-TM-EN-1.1 465
Chapter 14 - Current Protection Functions P54
EPATR Curve
1000
100
Time in Secs
10
1
0.1 1 10 100 1000
Current in Primary A (CT Ratio 100A/1A)
V00616
781
ISEF>1 Start
IN Sensitive
IDMT/DT
ISEF>1 Current 675
& & & ISEF>1 Trip
928
CTS Block
ISEF>1 Direction
VN
833
VTS Slow Block
&
ISEF> Blocking
VTS Blks ISEF>1
1724
Inhibit ISEF>1
409
ISEF>1 Timer Blk
Note: For the purpose of clarity, this diagram
shows the first relevant stage number for each
V00738
signal and setting name.
466 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
Ia1
Ib1
IR1
jXc1
IH1
Ia2
Ib2
IR2
jXc2
IH2
Ia3
Ib3
IH1 + IH2 + IH3
IR3
jXc3
E00627
The protection elements on the healthy feeder see the charging current imbalance for their own feeder. The
protection element on the faulted feeder, however, sees the charging current from the rest of the system (IH1 and
IH2 in this case). Its own feeder's charging current (IH3) is cancelled out.
With reference to the associated vector diagram, it can be seen that the C-phase to earth fault causes the
voltages on the healthy phases to rise by a factor of √3. The A-phase charging current (Ia1), leads the resultant A
phase voltage by 90°. Likewise, the B-phase charging current leads the resultant Vb by 90°.
P54-TM-EN-1.1 467
Chapter 14 - Current Protection Functions P54
Vaf
Restrain
Vapf
IR1
Ib1
Operate
Ia1
Vbf
Vcpf Vbpf
Vres
(= 3Vo)
Figure 306: Phasor diagrams for insulated system with C phase fault
The current imbalance detected by a core balanced current transformer on the healthy feeders is the vector
addition of Ia1 and Ib1. This gives a residual current which lags the polarising voltage (–3Vo) by 90°. As the healthy
phase voltages have risen by a factor of Ö3, the charging currents on these phases are also Ö3 times larger than
their steady state values. Therefore, the magnitude of the residual current IR1, is equal to 3 times the steady state
per phase charging current.
The phasor diagram indicates that the residual currents on the healthy and faulted feeders (IR1 and IR3
respectively) are in anti-phase. A directional element (if available) could therefore be used to provide discriminative
earth fault protection.
If the polarising is shifted through +90°, the residual current seen by the relay on the faulted feeder will lie within
the operate region of the directional characteristic and the current on the healthy feeders will fall within the
restrain region.
The required characteristic angle setting for the SEF element when applied to insulated systems, is +90°. This is for
the case when the protection is connected such that its direction of current flow for operation is from the source
busbar towards the feeder. If the forward direction for operation were set such that it is from the feeder into the
busbar, then a –90° RCA would be required.
Note:
Discrimination can be provided without the need for directional control. This can only be achieved, however, if it is possible to
set the IED in excess of the charging current of the protected feeder and below the charging current for the rest of the system.
468 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
Cable gland
Cable box
Cable gland/shealth
earth connection
“Incorrect”
No operation
SEF
“Correct”
Operation
SEF
E00614
If the cable sheath is terminated at the cable gland and directly earthed at that point, a cable fault (from phase to
sheath) will not result in any unbalanced current in the core balance CT. Therefore, prior to earthing, the
connection must be brought back through the CBCT and earthed on the feeder side. This then ensures correct
relay operation during earth fault conditions.
P54-TM-EN-1.1 469
Chapter 14 - Current Protection Functions P54
Healthy CT Saturated CT
Protected
circuit
A-G
Zm1 Zm2
I = Is + IF
RCT1 RCT2
I IF
RL1 IS RL3
Vs RST
R
RL2 RL4
V00671
When subjected to heavy through faults the line current transformer may enter saturation unevenly, resulting in
imbalance. To ensure stability under these conditions a series connected external resistor is required, so that most
of the unbalanced current will flow through the saturated CT. As a result, the current flowing through the device
will be less than the setting, therefore maintaining stability during external faults.
Voltage across REF element Vs = IF (RCT2 + RL3 + RL4)
Stabilising resistor RST = Vs/Is –RR
where:
● IF = maximum secondary through fault current
● RR = device burden
● RCT = CT secondary winding resistance
● RL2 and RL3 = Resistances of leads from the device to the current transformer
● RST = Stabilising resistor
High Impedance REF can be used for either delta windings or star windings in both solidly grounded and
resistance grounded systems. The connection to a modern IED are as follows:
470 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
Phase A
Phase A
Phase B
Phase B
Phase C
Phase C
I Phase A
I Phase B
I Phase C
RSTAB I Neutral
I Neutral RSTAB
IED IED
Connecting IED to star winding for High Connecting IED to delta winding for High
Impedance REF Impedance REF
V00680
P54-TM-EN-1.1 471
Chapter 14 - Current Protection Functions P54
I 2 − ( KI FLC )2
t = −τ log
I 2 − I p2
e
where:
● t = time to trip, following application of the overload current I
● t = heating and cooling time constant of the protected plant
● I = largest phase current
● IFLC full load current rating (the Thermal Trip setting)
● K = a constant with the value of 1.05
● Ip = steady state pre-loading before application of the overload
( − t / τ1 ) ( −t / τ 2 )
I 2 − ( KI FLC )2
0.4e + 0.6e =
I − I p
2 2
where:
● t1 = heating and cooling time constant of the transformer windings
● t2 = heating and cooling time constant of the insulating oil
472 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
IA
IB Max RMS
Thermal State
IC
Thermal Trip
680
Thermal Trip
Characteristic Thermal trip
Disabled threshold
Thermal Calculation
Single
Dual
Time Constant 1
Time Constant 2
445
Reset Thermal
785
Thermal Alarm
Thermal Alarm
V00630
The magnitudes of the three phase input currents are compared and the largest magnitude is taken as the input
to the thermal overload function. If this current exceeds the thermal trip threshold setting a start condition is
asserted.
The Start signal is applied to the chosen thermal characteristic module, which has three outputs signals; alarm trip
and thermal state measurement. The thermal state measurement is made available in one of the MEASUREMENTS
columns.
The thermal state can be reset by either a digital signal (Opto, GOOSE, InterMiCOM), if assigned to this function
using programmable scheme logic or the HMI panel menu.
P54-TM-EN-1.1 473
Chapter 14 - Current Protection Functions P54
Figures based
on equation
E00728
Figure 311: Spreadsheet calculation for dual time constant thermal characteristic
100000
100
10
1
1 10
Current as a Multiple of Thermal Setting
V00629
474 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
Note:
The thermal time constants given in the above tables are typical only. Reference should always be made to the plant
manufacturer for accurate information.
θ − θ p
e( − t / τ ) =
e
θ −1
where:
● θ = thermal state = I2/K2IFLC2
● θp = pre-fault thermal state = Ip2/K2IFLC2
Note:
A current of 105%Is (KIFLC) has to be applied for several time constants to cause a thermal state measurement of 100%.
Area mm2 6 - 11 kV 22 kV 33 kV 66 kV
25 – 50 10 minutes 15 minutes 40 minutes –
70 – 120 15 minutes 25 minutes 40 minutes 60 minutes
150 25 minutes 40 minutes 40 minutes 60 minutes
185 25 minutes 40 minutes 60 minutes 60 minutes
240 40 minutes 40 minutes 60 minutes 60 minutes
300 40 minutes 60 minutes 60 minutes 90 minutes
P54-TM-EN-1.1 475
Chapter 14 - Current Protection Functions P54
Low current
928
CTS Block
V00739a
476 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
Note:
A minimum value of 8% negative phase sequence current is required for successful operation.
Since sensitive settings have been employed, we can expect that the element will operate for any unbalanced
condition occurring on the system (for example, during a single pole autoreclose cycle). For this reason, a long time
delay is necessary to ensure co-ordination with other protection devices. A 60 second time delay setting may be
typical.
The following example was recorded by an IED during commissioning:
Ifull load = 500A
I2 = 50A
therefore the quiescent I2/I1 ratio = 0.1
To allow for tolerances and load variations a setting of 20% of this value may be typical: Therefore set:
I2/I1 = 0.2
In a double circuit (parallel line) application, using a 40% setting will ensure that the broken conductor protection
will operate only for the circuit that is affected. A setting of 0.4 results in no pick-up for the parallel healthy circuit.
Set I2/I1 Time Delay = 60 s to allow adequate time for short circuit fault clearance by time delayed protections.
P54-TM-EN-1.1 477
Chapter 14 - Current Protection Functions P54
478 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
This product does not use the above techniques for directionalisation. This product uses an innovative patented
technique called Transient Reactive Power method to determine the fault direction of an earth fault in a
compensated network.
Note:
In this product, TEFD is implemented for 50Hz only.
The FTD outputs two signals to indicate whether the fault is steady state or intermittent.
P54-TM-EN-1.1 479
Chapter 14 - Current Protection Functions P54
It can be shown that the residual voltage and residual current components can be reliably used as discriminative
criteria between a faulty and healthy feeder at 220Hz.
The admittance response of a healthy distributed feeder is shown below using a Pi model:
ANGLE/DEGREE
V00916
In the above figure, the phase response of the admittance is consistent at 90o up to frequency f1 (approximately
3000Hz). For a compensated faulty feeder, the admittance response is shown below using a Pi model:
ANGLE/DEGREE
V00917
We can observe that the phase angle (and thus, the reactive power flow) changes from 90o to -90o at frequencies
higher than f2. Based on the above, we have clear direction discrimination between a healthy and faulted feeder
at any frequency between f2 and f1 approximately.
Note:
The resonant frequency in the above system is 70Hz. For a perfectly compensated system, this will be 50Hz.
MiCOM relays use an anti-aliasing band pass filter with cut-off frequency of 150Hz. Furthermore, at 220Hz the
post-filter magnitude is approximately 0.5pu, and at 330Hz, it is less than 0.2pu. To avoid any integer harmonics,
and to avoid severely attenuated quantities due to the filter, we have chosen 220Hz as the most suitable frequency
for direction determination.
In the forward direction, the residual voltage leads the residual current by 90°, and in the reverse direction the
residual voltage lags the residual current by 90°. These criteria can be used to directionalise the fault.
480 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
The residual voltage (Vres) after passing through the bandpass filter tuned to 220 Hz, has 90° added to its phase.
The residual current (Ires) is also passed through a 220 Hz bandpass filter, but no phase shift is applied. The
resulting components which we shall call VH1 and IH2 are therefore in antiphase with each other for forward
faults and in phase if the forward line is not faulted.
The VH1 and IH2 components are passed through a sign filter and multiplied to create a reactive power
component in the range of -1 to +1. This is the transient reactive power Qtran. If Qtran > 0, then there forward line is
healthy. If Qtran < 0, then the forward line is faulty.
There are two modes of operation for the direction detector; Standard and Advanced. Standard mode is used in
most cases and is described here. Advanced mode is for special applications that deviate from the standard model
of two or more geographically close feeders outgoing from a power transformer. The following default settings are
recommended for majority of applications:
● Dir>Vnf Thresh 8.000 V
● Dir>Inf Thresh 50.00 mA
● Dir>Qn Thresh 100.0e-3
● Dir>Qr Thresh 40.00e-3
When TEF>Dir Mod is set to Advance, the following settings become visible:
● Dir>Qs Thresh 50.00e-3
● Qn Smooth fct 20.00e-3
● Operate.Cycles 6
Here, Qs is an integration of Qn, with the window of integration being the first Operate cycles setting after the start
signal is triggered. Qs is used as a further discriminative directional feature if direction cannot be determined by Qn
only. QS is calculated by the following formula:
( t = K *T )
Q =∫ (Q )
S ( t =0 ) N (t )
Where ‘K’ is the setting Operate Cycles. Operate Cycles affects Qs only.
Qn Smooth fact is a smoothing factor for consecutive Qn values which prevents sudden changes in the value of
Qn. The calculated new value of Qn is:
new_valueQn = old_value*(1-smoothing_factor)+ new_value*smoothing_factor.
It is important to note that all settings for the TGFD function, including those at 220Hz, can be set based on 50Hz
nominal secondary values. This is because the gain of the 220Hz transient filter is 1.
The inputs to this module are:
● The residual voltage
● The residual current
● Dir> Vnf Thresh (defines the threshold for the residual voltage sign filter).
● Dir> Inf Thresh (defines the threshold for the residual current sign filter
The DD outputs two signals to indicate a forward fault and a reverse fault
P54-TM-EN-1.1 481
Chapter 14 - Current Protection Functions P54
Qtran Thresholds
The setting Dir>Qn Thresh is the forward direction Qtran threshold calculated from the quantised Vnf and Inf
values.
The setting Dir>Qr is the reverse direction Qtrans threshold calculated from the quantised Vnf and Inf values.
The following DDBs are also available:
Timer Block: used to inhibit the TEF function and reset all associated DDBs
Reset TEF: can be configured as a user-defined manual reset alarms
TEF Alarm Output: This is the main TEF alarm that can be mapped to a relay output for a trip
V NRMS
1794
TEF VN> Start & TEF> Start
TEF Detection
Enabled
1800
TEF> Timer Block
1798
VN
VN Enable Steady & TEF> Steady
FTD> VN
FA Fault Type
FTD> Time Window Detector Module
Dir>Inf Thresh
1796
Reverse & TEF>DIR REV
TEF>Dir Status
Enabled
V09005
VNRMS Average -
VN RMS low pass
filter
Ʃ Pulse
Permanent
+ Decision Intermittent
Counter
Disturbance
FTD> VN
FTD> Fault Count
FTD> Time Window
V00906
482 P54-TM-EN-1.1
P54 Chapter 14 - Current Protection Functions
220Hz
VH1 Sign filter
Add 90°
VN phase shift -0.1
Forward (faulty)
Dir>Vnf Thresh
Qtran
X
220Hz
IH2 Sign filter
IN Reverse (healthy)
0.04
Dir>Inf Thresh
Note: In standard mode, Qtran comparison threshold is fixed at -0.1 for the
forward direction and +0.04 for the reverse direction.
V00907
P54-TM-EN-1.1 483
Chapter 14 - Current Protection Functions P54
TEFD FWD
TEF>DIR FWD 1795
100 Forward Start
1 & pickup SR User Alarm
ISEF>1 Start 781 400
SDEF FWD
SDEF REV
782
ISEF>2 Start Reverse Start
100
& pickup SR User Alarm
TEF>DIR REV 1796 1 0
TEFD REV
V09007
484 P54-TM-EN-1.1
CHAPTER 15
486 P54-TM-EN-1.1
P54 Chapter 15 - Voltage Protection Functions
1 CHAPTER OVERVIEW
The device provides a wide range of voltage protection functions. This chapter describes the operation of these
functions including the principles, logic diagrams and applications.
This chapter contains the following sections:
Chapter Overview 487
Undervoltage Protection 488
Overvoltage Protection 491
Compensated Overvoltage 494
Residual Overvoltage Protection 496
P54-TM-EN-1.1 487
Chapter 15 - Voltage Protection Functions P54
2 UNDERVOLTAGE PROTECTION
Undervoltage conditions may occur on a power system for a variety of reasons, some of which are outlined below:
● Undervoltage conditions can be related to increased loads, whereby the supply voltage will decrease in
magnitude. This situation would normally be rectified by voltage regulating equipment such as AVRs (Auto
Voltage Regulators) or On Load Tap Changers. However, failure of this equipment to bring the system
voltage back within permitted limits leaves the system with an undervoltage condition, which must be
cleared.
● If the regulating equipment is unsuccessful in restoring healthy system voltage, then tripping by means of
an undervoltage element is required.
● Faults occurring on the power system result in a reduction in voltage of the faulty phases. The proportion by
which the voltage decreases is dependent on the type of fault, method of system earthing and its location.
Consequently, co-ordination with other voltage and current-based protection devices is essential in order to
achieve correct discrimination.
● Complete loss of busbar voltage. This may occur due to fault conditions present on the incomer or busbar
itself, resulting in total isolation of the incoming power supply. For this condition, it may be necessary to
isolate each of the outgoing circuits, such that when supply voltage is restored, the load is not connected.
Therefore, the automatic tripping of a feeder on detection of complete loss of voltage may be required. This
can be achieved by a three-phase undervoltage element.
● Where outgoing feeders from a busbar are supplying induction motor loads, excessive dips in the supply
may cause the connected motors to stall, and should be tripped for voltage reductions that last longer than
a pre-determined time.
The undervoltage stages can be configured either as phase-to-neutral or phase-to-phase voltages in the V<
Measur't Mode cell.
There is no Timer Hold facility for Undervoltage.
Stage 2 can have definite time characteristics only. This is set in the V<2 Status cell.
Outputs are available for single or three-phase conditions via the V< Operate Mode cell for each stage.
488 P54-TM-EN-1.1
P54 Chapter 15 - Voltage Protection Functions
& IDMT/DT
684
V<1 Voltage Set & V<1 Trip A/AB
V< Hysteresis
V< Hysteresis
791
V<1 Time Delay V<1 Start C/CA
& IDMT/DT
686
V< Measur't Mode & V<1 Trip C/CA
1
&
V<1 Voltage Set
788
1 V<1 Start
V< Hysteresis &
&
V<1 Time Delay
890
1
All Poles Dead &
683
V<1 Poledead Inh 1 V<1 Trip
& &
Enabled &
832
VTS Fast Block
471
V<1 Timer Block
414
V<1 Timer Block
V< Operate Mode
Any Phase
Three Phase
Notes: This diagram does not show all stages. Other stages follow similar principles.
VTS Fast Block only applies for directional models.
V00829
Figure 321: Undervoltage - single and three phase tripping mode (single stage)
The Undervoltage protection function detects when the voltage magnitude for a certain stage falls short of a set
threshold. If this happens a Start signal, signifying the "Start of protection", is produced. This Start signal can be
blocked by the VTS Fast Block signal and an All Poles Dead signal. This Start signal is applied to the timer module
to produce the Trip signal, which can be blocked by the undervoltage timer block signal (V<(n) Timer Block). For
each stage, there are three Phase undervoltage detection modules, one for each phase. The three Start signals
from each of these phases are OR'd together to create a 3-phase Start signal (V<(n) Start), which can be be
activated when any of the three phases start (Any Phase), or when all three phases start (Three Phase), depending
on the chosen V< Operate Mode setting.
The outputs of the timer modules are the trip signals which are used to drive the tripping output relay. These
tripping signals are also OR'd together to create a 3-phase Trip signal, which are also controlled by the V< Operate
Mode setting.
If any one of the above signals is low, or goes low before the timer has counted out, the timer module is inhibited
(effectively reset) until the blocking signal goes high.
In some cases, we do not want the undervoltage element to trip; for example, when the protected feeder is de-
energised, or the circuit breaker is opened, an undervoltage condition would obviously be detected, but we would
not want to start protection. To cater for this, an All Poles Dead signal blocks the Start signal for each phase. This
is controlled by the V<Poledead Inh cell, which is included for each of the stages. If the cell is enabled, the relevant
stage will be blocked by the integrated pole dead logic. This logic produces an output when it detects either an
open circuit breaker via auxiliary contacts feeding the opto-inputs or it detects a combination of both
undercurrent and undervoltage on any one phase.
P54-TM-EN-1.1 489
Chapter 15 - Voltage Protection Functions P54
Voltage drop-off threshold, defined as a percentage of set voltage, may be adjusted via the V< Hysteresis setting.
For example, where the V<Hysteresis default setting is 2, relay pick-up will be at set voltage and drop-off will be at
102% of set voltage.
490 P54-TM-EN-1.1
P54 Chapter 15 - Voltage Protection Functions
3 OVERVOLTAGE PROTECTION
Overvoltage conditions are generally related to loss of load conditions, whereby the supply voltage increases in
magnitude. This situation would normally be rectified by voltage regulating equipment such as AVRs (Auto Voltage
Regulators) or On Load Tap Changers. However, failure of this equipment to bring the system voltage back within
permitted limits leaves the system with an overvoltage condition which must be cleared.
Note:
During earth fault conditions on a power system there may be an increase in the healthy phase voltages. Ideally, the system
should be designed to withstand such overvoltages for a defined period of time.
The overvoltage stages can be configured either as phase-to-neutral or phase-to-phase voltages in the V>
Measur't Mode cell.
There is no Timer Hold facility for Overvoltage.
Stage 2 can have definite time characteristics only. This is set in the V>2 Status cell.
Outputs are available for single or three-phase conditions via the V> Operate Mode cell for each stage.
P54-TM-EN-1.1 491
Chapter 15 - Voltage Protection Functions P54
IDMT/DT
692
V>1 Voltage Set & V>1 Trip A/AB
V> Hysteresis
V> Hysteresis
799
V>1 Time Delay V>1 Start C/CA
IDMT/DT
694
V> Measur't Mode & V>1 Trip C/CA
1
&
V>1 Voltage Set
796
1 V>1 Start
V> Hysteresis &
&
V>1 Time Delay
473
1
Inhibit V>1 &
416 691
V>1 Timer Block 1 V>1 Trip
&
V> Operate Mode &
Any Phase
Three Phase
Notes: This diagram does not show all stages. Other stages follow similar principles.
VTS Fast Block only applies for directional models.
V00828
Figure 322: Overvoltage - single and three phase tripping mode (single stage)
The Overvoltage protection function detects when the voltage magnitude for a certain stage exceeds a set
threshold. If this happens a Start signal, signifying the "Start of protection", is produced. This Start signal can be
blocked by the VTS Fast Block signal. This start signal is applied to the timer module to produce the Trip signal,
which can be blocked by the overvoltage timer block signal (V>(n) Timer Block). For each stage, there are three
Phase overvoltage detection modules, one for each phase. The three Start signals from each of these phases are
OR'd together to create a 3-phase Start signal (V>(n) Start), which can then be activated when any of the three
phases start (Any Phase), or when all three phases start (Three Phase), depending on the chosen V> Operate Mode
setting.
The outputs of the timer modules are the trip signals which are used to drive the tripping output relay. These
tripping signals are also OR'd together to create a 3-phase Trip signal, which are also controlled by the V> Operate
Mode setting.
If any one of the above signals is low, or goes low before the timer has counted out, the timer module is inhibited
(effectively reset) until the blocking signal goes high.
Voltage drop-off threshold, defined as a percentage of set voltage, may be adjusted via the V> Hysteresis setting.
For example, where the V>Hysteresis default setting is 2, relay pick-up will be at set voltage and drop-off will be at
98% of set voltage.
492 P54-TM-EN-1.1
P54 Chapter 15 - Voltage Protection Functions
This type of protection must be co-ordinated with any other overvoltage devices at other locations on the system.
P54-TM-EN-1.1 493
Chapter 15 - Voltage Protection Functions P54
4 COMPENSATED OVERVOLTAGE
The Compensated Overvoltage function calculates the positive sequence voltage at the remote terminal using the
positive sequence local current and voltage and the line impedance and susceptance. This can be used on long
transmission lines where Ferranti Overvoltages can develop under remote circuit breaker open conditions.
Vr D − C Vs
= ×
Ir − BA Is
where
● Vr is the voltage at the receiving end
● Ir is the current at the receiving end
● Vs is the measured voltage at the sending end
● Is is the measured current at the sending end
● A= D = cosh(y.l)
● B = Zc.sinh(y.l)
● C = Yc.sinh(y.l)
● y.l = Ö(Z.Y)
● Zc = 1/Yc = Ö(Z/Y)
● Y = total line capacitive charging susceptance
● Zc = characteristic impedance of the line (surge impedance)
There are two stages to provide both alarm and trip stages where required. Both stages can be set independently.
Stage 1 can be set to IDMT, DT or Disabled, in the V1>1 Cmp Funct cell. Stage 2 is DT only and is enabled or
disabled in the V1>2 Cmp Status cell.
The IDMT characteristic on the first stage is defined by the following formula:
t = K/(M - 1)
where:
● K = Time multiplier setting
● t =Operating time in seconds
● M = Remote Calculated voltage / IED setting voltage
494 P54-TM-EN-1.1
P54 Chapter 15 - Voltage Protection Functions
V1 Cmp
The Compensated Overvoltage module (V1 Cmp) is a level detector that detects when the voltage magnitude
exceeds a set threshold, for each stage. When this happens, the comparator output produces a Start signal
(V1>(n) Cmp Start), which signifies the "Start of protection". This can be blocked by a VTS Fast block signal. This
Start signal is applied to the timer module. The output of the timer module is the V1> (n) Cmp Trip signal which is
used to drive the tripping output relay.
Voltage drop-off threshold, defined as a percentage of set voltage, may be adjusted via the Cp V Hysteresis
setting. For example, where the Cp V Hysteresis default setting is 2, relay pick-up will be at set voltage and drop-
off will be at 98% of set voltage.
This type of protection must be co-ordinated with any other overvoltage devices at other locations on the system.
P54-TM-EN-1.1 495
Chapter 15 - Voltage Protection Functions P54
496 P54-TM-EN-1.1
P54 Chapter 15 - Voltage Protection Functions
804
VN>1 Start
VN
The Residual Overvoltage module (VN>) is a level detector that detects when the voltage magnitude exceeds a set
threshold, for each stage. When this happens, the comparator output produces a Start signal (VN>(n) Start), which
signifies the "Start of protection". This can be blocked by a VTS Fast block signal. This Start signal is applied to the
timer module. The output of the timer module is the VN> (n) Trip signal which is used to drive the tripping output
relay.
P54-TM-EN-1.1 497
Chapter 15 - Voltage Protection Functions P54
E S IED F
ZS ZL
VA
VA
VC VB VC VB VC VB
VA VRES
VRES
VA
VB VB VB
VC VC VC
VRES = ZS0
X3E
2ZS1 + ZS0 + 2ZL1 + ZL0
E00800
As can be seen from the above diagram, the residual voltage measured on a solidly earthed system is solely
dependent on the ratio of source impedance behind the protection to the line impedance in front of the protection,
up to the point of fault. For a remote fault far away, the ZS/ZL: ratio will be small, resulting in a correspondingly
small residual voltage. Therefore, the protection only operates for faults up to a certain distance along the system.
The maximum distance depends on the device setting.
498 P54-TM-EN-1.1
P54 Chapter 15 - Voltage Protection Functions
E S IED F
ZS ZL
N
ZE
VA - G
S R VA - G
G,F G,F
G,F
VC - G VC - G VC - G
VB - G VB - G VB - G
VB - G VB - G VB - G
VA - G VA - G
VC - G VC - G VC - G
ZS0 + 3ZE
VRES = X3E
2ZS1 + ZS0 + 2ZL1 + ZL0 + 3Z
E
E00801
An impedance earthed system will always generate a relatively large degree of residual voltage, as the zero
sequence source impedance now includes the earthing impedance. It follows then that the residual voltage
generated by an earth fault on an insulated system will be the highest possible value (3 x phase-neutral voltage),
as the zero sequence source impedance is infinite.
P54-TM-EN-1.1 499
Chapter 15 - Voltage Protection Functions P54
500 P54-TM-EN-1.1
CHAPTER 16
502 P54-TM-EN-1.1
P54 Chapter 16 - Frequency Protection Functions
1 CHAPTER OVERVIEW
The device provides a range of frequency protection functions. This chapter describes the operation of these
functions including the principles, logic diagrams and applications.
This chapter contains the following sections:
Chapter Overview 503
Frequency Protection 504
Independent R.O.C.O.F Protection 507
P54-TM-EN-1.1 503
Chapter 16 - Frequency Protection Functions P54
2 FREQUENCY PROTECTION
Power generation and utilisation needs to be well balanced in any industrial, distribution or transmission network.
These electrical networks are dynamic entities, with continually varying loads and supplies, which are continually
affecting the system frequency. Increased loading reduces the system frequency and generation needs to be
increased to maintain the frequency of the supply. Conversely decreased loading increases the system frequency
and generation needs to be reduced. Sudden fluctuations in load can cause rapid changes in frequency, which
need to be dealt with quickly.
Unless corrective measures are taken at the appropriate time, frequency decay can go beyond the point of no
return and cause widespread network collapse, which has dire consequences.
Normally, generators are rated for a particular band of frequency. Operation outside this band can cause
mechanical damage to the turbine blades. Protection against such contingencies is required when frequency does
not improve even after load shedding steps have been taken. This type of protection can be used for operator
alarms or turbine trips in case of severe frequency decay.
Clearly a range of methods is required to ensure system frequency stability. The frequency protection in this device
provides both underfrequency and overfrequency protection.
Frequency Protection is implemented in the FREQ PROTECTION column of the relevant settings group.
504 P54-TM-EN-1.1
P54 Chapter 16 - Frequency Protection Functions
1155
Averaging F<1 Start
DT
1161
F<1 Setting & F<1 Trip
F<1 Status
Enabled
1167
Inhibit F<1
890
All Poles Dead
1
1370
Freq Not Found
1149
F<1 Timer Block V00861
If the frequency is below the setting and not blocked the DT timer is started. If the frequency cannot be
determined, the function is blocked.
P54-TM-EN-1.1 505
Chapter 16 - Frequency Protection Functions P54
Freq 1159
Averaging F>1 Start
DT
1165
F>1 Setting & F>1 Trip
F>1 Status
Enabled
1171
Inhibit F>1
890
All Poles Dead
1
1370
Freq Not Found
1153
F>1 Timer Block V00862
If the frequency is above the setting and not blocked, the DT timer is started and after this has timed out, the trip is
produced. If the frequency cannot be determined, the function is blocked.
506 P54-TM-EN-1.1
P54 Chapter 16 - Frequency Protection Functions
● df/dt>1 Dir'n: sets the direction of change you wish to check (positive, negative, or both)
In addition, start, trip and timer block DDB signals are available for each stage, as well as an inhibit signal to inhibit
all four stages.
Frequency 597
df/dt df/dt>1 Start
determination
& DT 601
df/dt Avg . Cycles 1 df/dt>1 Trip
-1
df/dt>1 Dir ¶n 1
Positive
Both
1
Negative
1370
Freq Not Found
1368
Freq High 1
Freq Low 1369
592
Inhibit df/dt
593
df/dt Tmr Blk
V00869
P54-TM-EN-1.1 507
Chapter 16 - Frequency Protection Functions P54
508 P54-TM-EN-1.1
CHAPTER 17
510 P54-TM-EN-1.1
P54 Chapter 17 - Power Protection Functions
1 CHAPTER OVERVIEW
Power protection is used for protecting generators. Although the main function of this device is for feeder
applications, it can also be used as a cost effective alternative for protecting small distributed generators, typically
less than 2 MW.
This chapter contains the following sections:
Chapter Overview 511
Overpower Protection 512
Underpower Protection 515
P54-TM-EN-1.1 511
Chapter 17 - Power Protection Functions P54
2 OVERPOWER PROTECTION
With Overpower, we should consider two distinct conditions: Forward Overpower and Reverse Overpower.
A forward overpower condition occurs when the system load becomes excessive. A generator is rated to supply a
certain amount of power and if it attempts to supply power to the system greater than its rated capacity, it could
be damaged. Therefore overpower protection in the forward direction can be used as an overload indication. It can
also be used as back-up protection for failure of governor and control equipment. Generally the Overpower
protection element would be set above the maximum power rating of the machine.
A reverse overpower condition occurs if the generator prime mover fails. When this happens, the power system
may supply power to the generator, causing it to motor. This reversal of power flow due to loss of prime mover can
be very damaging and it is important to be able to detect this with a Reverse Overpower element.
512 P54-TM-EN-1.1
P54 Chapter 17 - Power Protection Functions
3 Phase Watts
3 Phase VA
Power1 3Ph Watt & DT
1 & 1823 Power 1 3Ph Trip
Power1 3Ph VAR
Active -1 X &
Reactive
Power1 Direction
Forward
Reverse
Power1 Function Note: This diagram does not show all stages. Other stages follow similar principles.
Over This diagram shows A phase for single phase input and signals. B and C
phases follow similar principles.
833
VTS Slow Block
1
1839
Power 1 Block V00919
P54-TM-EN-1.1 513
Chapter 17 - Power Protection Functions P54
In some applications, the level of reverse power in the case of prime mover failure may fluctuate. This may be the
case for a failed diesel engine. To prevent cyclic initiation and reset of the main trip timer, an adjustable reset time
delay is provided. You will need to set this time delay longer than the period for which the reverse power could fall
below the power setting. This setting needs to be taken into account when setting the main trip time delay.
Note:
A delay in excess of half the period of any system power swings could result in operation of the reverse power protection
during swings.
514 P54-TM-EN-1.1
P54 Chapter 17 - Power Protection Functions
3 UNDERPOWER PROTECTION
Although the Underpower protection is directional and can be configured as forward or reverse, the most common
application is for Low Forward Power protection.
When a machine is generating and the circuit breaker connecting the generator to the system is tripped, the
electrical load on the generator is cut off. This could lead to overspeeding of the generator if the mechanical input
power is not reduced quickly. Large turbo-alternators, with low-inertia rotor designs, do not have a high over
speed tolerance. Trapped steam in a turbine, downstream of a valve that has just closed, can rapidly lead to over
speed. To reduce the risk of over speed damage, it may be desirable to interlock tripping of the circuit breaker and
the mechanical input with a low forward power check. This ensures that the generator circuit breaker is opened
only after the mechanical input to the prime mover has been removed, and the output power has reduced enough
such that overspeeding is unlikely. This delay in tripping the circuit breaker may be acceptable for non-urgent
protection trips (e.g. stator earth fault protection for a high impedance earthed generator). For urgent trips
however (e.g. stator current differential protection), this Low Forward Power interlock should not be used.
P54-TM-EN-1.1 515
Chapter 17 - Power Protection Functions P54
3 Phase Watts
3 Phase VA
Power1 3Ph Watt & DT
1 & 1823 Power 1 3Ph Trip
Power1 3Ph VAR
Active -1 X &
Reactive
Power1 Direction
Forward
Reverse
Power1 Function
Under
Note: This diagram does not show all stages. Other stages follow similar principles.
All Poles Dead 890
& This diagram shows A phase for single phase input and signals. B and C
phases follow similar principles.
P1 Poledead Inh 1
Enabled
833
VTS Slow Block
1
1839
Power 1 Block V00920
516 P54-TM-EN-1.1
P54 Chapter 17 - Power Protection Functions
When required for interlocking of non-urgent tripping applications, the threshold setting of the low forward power
protection function should be less than 50% of the power level that could result in a dangerous overspeed
condition on loss of electrical loading.
When required for loss of load applications, the threshold setting of the low forward power protection function, is
system dependent, however, it is typically set to 10 - 20% below the minimum load. The operating mode should be
set to operate for the direction of the load current, which would typically be reverse for a pump storage machine
application where Forward is the Generating direction and Reverse is the motoring direction.
For interlocking non-urgent trip applications the time delay associated with the low forward power protection
function could be set to zero. However, some delay is desirable so that permission for a non-urgent electrical trip is
not given in the event of power fluctuations arising from sudden steam valve/throttle closure. A typical time delay
is 2 seconds.
For loss of load applications the pick-up time delay is application dependent but is normally set in excess of the
time between motor starting and the load being established. Where rated power cannot be reached during
starting (for example where the motor is started with no load connected) and the required protection operating
time is less than the time for load to be established then it will be necessary to inhibit the power protection during
this period. This can be done in the PSL using AND logic and a pulse timer triggered from the motor starting to
block the power protection for the required time.
When required for loss of mains or loss of grid applications where the distributed generator is not allowed to
export power to the system, the threshold setting of the reverse power protection function, should be set to a
sensitive value, typically <2% of the rated power.
The low forward power protection function should be time-delayed to prevent false trips or alarms being given
during power system disturbances or following synchronisation. A time delay setting, of 5 s should be applied
typically.
The delay on the reset timers would normally be set to zero.
To prevent unwanted alarms and flags, the protection element can be disabled when the circuit breaker is open
via Pole Dead logic.
Setting guidelines
Each stage of power protection can be selected to operate as a reverse reactive power stage by selecting the
Power1 Function (or other stage) cell to Over and the Power1 Direction (or other stage) cell to Reverse.
The power threshold setting of the negative reactance power protection, Power1 3Ph VAr or Power1 1Ph VAr (or
other stage) should be set to supervise the steady state and dynamic stability limits for under excitation protection.
The following figure shows an example of the typical settings, Q1 and Q2.
The disadvantage of this method is that the measurement is not very sensitive during low voltage operation of the
generator. The reactive power elements can be blocked in the PSL from an undervoltage start signal if this is a
problem. This method is less secure than the impedance method and so is often used just to alarm.
If the static limit characteristic Q1 is exceeded, the voltage regulator must first have the opportunity of increasing
the excitation. For this reason, a time delayed trip of typically 5-10s is used Power1 TimeDelay (or other stage). A
shorter delay of 0.5s can be used for Q2.
P54-TM-EN-1.1 517
Chapter 17 - Power Protection Functions P54
+P
Under Over
excited excited
-Q
Q1
Q2
V04234
Q1 = VN2/Xd
Q2 > = 2 VN2/Xd
Where:
VN = Machine nominal voltage
Xd = Generator direct-axis synchronous reactance in ohms
When required for loss of mains or loss of grid applications where the distributed generator is not allowed to
export power to the system, the threshold setting of the reverse reactive power protection function, Power1 3Ph
VAr or Power1 1Ph VAr (or other stage), should be set to a suitable value, typically <2% of the rated reactive power.
The reverse reactive power protection function should be time-delayed, to prevent false trips or alarms being given
during power system disturbances or following synchronization, a typical time delay is 5 s.
518 P54-TM-EN-1.1
CHAPTER 18
520 P54-TM-EN-1.1
P54 Chapter 18 - Current Transformer Requirements
1 CHAPTER OVERVIEW
P54-TM-EN-1.1 521
Chapter 18 - Current Transformer Requirements P54
2 RECOMMENDED CT CLASSES
You can use Class X current transformers with a knee point voltage greater or equal to that calculated. You can
also use class 5P protection CT. These have a knee-point voltage equivalent, which can be approximated from the
following calculations:
Vk = (VA ´ ALF)/In + (RCT ´ ALF ´ In)
where:
● Vk = Knee-point voltage
● VA = Voltampere burden rating
● ALF = Accuracy limit factor
● In = CT nominal secondary current
● RCT = CT resistance
522 P54-TM-EN-1.1
P54 Chapter 18 - Current Transformer Requirements
For IEDs with the settings: Is1 = 20%, Is2 = 2In, k1 = 30%, k2 = 100% and for (If ´ X/R) £ 600 (3-end applications):
K must have the value 65 or as calculated by: K = 40 + (0.35(If ´ X/R))
For higher (If ´ X/R) up to 2600, K = 256
P54-TM-EN-1.1 523
Chapter 18 - Current Transformer Requirements P54
Note:
It is not necessary to repeat the calculation for earth faults, as the phase reach calculation is the worst-case for CT
dimensioning.
524 P54-TM-EN-1.1
P54 Chapter 18 - Current Transformer Requirements
P54-TM-EN-1.1 525
Chapter 18 - Current Transformer Requirements P54
6 WORKED EXAMPLES
The power system and the line parameters used in these examples are as follows:
● Single circuit operation between Green Valley and Blue River
● System voltage = 230 kV
● System frequency = 50 Hz
● System grounding = solid
● CT ratio = 1200/1
● Line length = 100 km
● Line positive sequence impedance Z1 = 0.089 + j 0.476 ohm per km
● Bus fault level = 40 kA
● Primary time constant = 120 ms
526 P54-TM-EN-1.1
P54 Chapter 18 - Current Transformer Requirements
P54-TM-EN-1.1 527
Chapter 18 - Current Transformer Requirements P54
528 P54-TM-EN-1.1
CHAPTER 19
530 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
1 CHAPTER OVERVIEW
As well as providing a range of protection functions, the product includes comprehensive monitoring and control
functionality.
This chapter contains the following sections:
Chapter Overview 531
Event Records 532
Disturbance Recorder 536
Measurements 537
CB Condition Monitoring 545
CB State Monitoring 558
Circuit Breaker Control 562
Pole Dead Function 569
System Checks 571
Switch Status and Control 582
Test Mode 585
P54-TM-EN-1.1 531
Chapter 19 - Monitoring and Control P54
2 EVENT RECORDS
General Electric devices record events in an event log. This allows you to establish the sequence of events that led
up to a particular situation. For example, a change in a digital input signal or protection element output signal
would cause an event record to be created and stored in the event log. This could be used to analyse how a
particular power system condition was caused. These events are stored in the IED's non-volatile memory. Each
event is time tagged.
The event records can be displayed on an IED's front panel but it is easier to view them through the settings
application software. This can extract the events log from the device and store it as a single .evt file for analysis on
a PC.
The event records are detailed in the VIEW RECORDS column. The first event (0) is always the latest event. After
selecting the required event, you can scroll through the menus to obtain further details.
If viewing the event with the settings application software, simply open the extracted event file. All the events are
displayed chronologically. Each event is summarised with a time stamp obtained from the Time & Date cell) and a
short description relating to the event obtained from the Event Text cell). You can expand the details of the event
by clicking on the + icon to the left of the time stamp.
The following table shows the correlation between the fields in the setting application software's event viewer and
the cells in the menu database.
Field in Event Viewer Equivalent cell in menu DB Cell reference User settable?
Left hand column header VIEW RECORDS ® Time & Date 01 03 No
Right hand column header VIEW RECORDS ® Event Text 01 04 No
Description SYSTEM DATA ® Description 00 04 Yes
Plant reference SYSTEM DATA ® Plant Reference 00 05 Yes
Model number SYSTEM DATA ® Model Number 00 06 No
Address Displays the Courier address relating to the event N/A No
Event type VIEW RECORDS ® Menu Cell Ref 01 02 No
Event Value VIEW RECORDS ® Event Value 01 05 No
Evt Unique Id VIEW RECORDS ® Evt Unique ID 01 FE No
532 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
Standard events are further sub-categorised internally to include different pieces of information. These are:
● Protection events (starts and trips)
● Maintenance record events
● Platform events
Note:
The first event in the list (event 0) is the most recent event to have occurred.
P54-TM-EN-1.1 533
Chapter 19 - Monitoring and Control P54
V01234
The event is logged as soon as the fault recorder stops. The time stamp assigned to the fault corresponds to the
start of the fault. The timestamp assigned to the fault record event corresponds to the time when the fault
recorder stops.
Note:
We recommend that you do not set the triggering contact to latching. This is because if you use a latching contact, the fault
record would not be generated until the contact has been fully reset.
534 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
The Event Value cell for this type of event is a 32 bit binary string representing the state of the relevant DDB
signals. These binary strings can also be viewed in the COMMISSION TESTS column in the relevant DDB batch cells.
Not all DDB signals can generate an event. Those that can are listed in the RECORD CONTROL column. In this
column, you can set which DDBs generate events.
P54-TM-EN-1.1 535
Chapter 19 - Monitoring and Control P54
3 DISTURBANCE RECORDER
The disturbance recorder feature allows you to record selected current and voltage inputs to the protection
elements, together with selected digital signals. The digital signals may be inputs, outputs, or internal DDB signals.
The disturbance records can be extracted using the disturbance record viewer in the settings application software.
The disturbance record file can also be stored in the COMTRADE format. This allows the use of other packages to
view the recorded data.
The integral disturbance recorder has an area of memory specifically set aside for storing disturbance records. The
number of records that can be stored is dependent on the recording duration. The minimum duration is 0.1 s and
the maximum duration is 10.5 s.
When the available memory is exhausted, the oldest records are overwritten by the newest ones.
Each disturbance record consists of a number of analogue data channels and digital data channels. The relevant
CT and VT ratios for the analogue channels are also extracted to enable scaling to primary quantities.
The fault recording times are set by a combination of the Duration and Trigger Position cells. The Duration cell
sets the overall recording time and the Trigger Position cell sets the trigger point as a percentage of the duration.
For example, the default settings show that the overall recording time is set to 1.5 s with the trigger point being at
33.3% of this, giving 0.5 s pre-fault and 1 s post fault recording times.
With the Trigger Mode set to Single, if further triggers occurs whilst a recording is taking place, the recorder will
ignore the trigger. However, with the Trigger Mode set to Extended, the post trigger timer will be reset to zero,
extending the recording time.
You can select any of the IED's analogue inputs as analogue channels to be recorded. You can also map any of the
opto-inputs output contacts to the digital channels. In addition, you may also map a number of DDB signals such
as Starts and LEDs to digital channels.
You may choose any of the digital channels to trigger the disturbance recorder on either a low to high or a high to
low transition, via the Input Trigger cell. The default settings are such that any dedicated trip output contacts will
trigger the recorder.
It is not possible to view the disturbance records locally via the front panel LCD. You must extract these using
suitable setting application software such as MiCOM S1 Agile.
536 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
4 MEASUREMENTS
P54-TM-EN-1.1 537
Chapter 19 - Monitoring and Control P54
the fault locator of the zero sequence mutual coupling can be eliminated by using the mutual compensation
feature provided.
It should be noted that in relays fitted with both a DEF element and a fault locator, the mutual compensation
current input terminals are shared with the DEF zero sequence current polarising input. And so, DEF zero
sequence current polarising cannot be used at the same time as fault locator mutual compensation.
The fault locator is optional on the underground cable version of the relay, where it is recommended that it is used
for metering purposes only (see the Metering section, below) as fault location accuracy cannot be relied upon for
this application.
Ip mZr (1-m)Zr Iq
Zsp Zsq
Vp Rf
Ep Eq
If
E01291
538 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
By evaluating equation Vp = mIpZr + IfRf at the instant in time when the fault current passes through zero and
considering only the real components, then the Rf |If| term becomes zero i.e. t = (( p/2)-d)/ w and the equation
simplifies to:
|Vp|cos(((p/2)-d) + s) = m |Zr| |Ip| cos(((p/2)-d) + e)
Therefore, the fault location m can be calculated if the angle of the fault current d is known.
Estimating d the phase of the fault current If:
The fault vector If is obtained from an algorithm which uses superimposed currents, that is, the change of currents
following the instant of fault.
Superimposed currents are indicated with an apostrophe ( ' ).
The sequence diagram for superimposed currents for an A-G fault is shown in the figure below:
3Rf
I2 '
Ip2 '
I0 '
Ip0 '
P54-TM-EN-1.1 539
Chapter 19 - Monitoring and Control P54
540 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
Replica impedance Zr
The fault location calculation needs vectors derived from the line voltage (Vp) and from the relay's "replica
impedance" voltage (IpZr) under fault conditions. The replica impedance is derived from the relay settings and is
effectively set to the same value as the total line impedance. i.e.
Zr = Zline / θ line + Zresidual / / θ residual
This "replica impedance" is modified using the mutual compensation factor when the mutual compensation
feature is used. i.e.
Zr = Zline / θ line + Zresidual / / θ residual + Zmutual/ / θ mutual
Where :
Zresidual = kZN*Zline
Zmutual = kZm*Zline
P54-TM-EN-1.1 541
Chapter 19 - Monitoring and Control P54
Ip mZr (1-m)Zr Iq
Zsp Zsq
Vp Rf
Ep Eq
If
E01291
542 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
Ip Z r
Vp
If = 0
Vp Ip Z r
E01295
i.e.:
Phase advanced vector Vp
= |Vp| [cos(s) + jsin(s) ] * [ sin(d) + jcos(d) ]
= |Vp| [-sin(s-d) + jcos(s-d) ]
Phase advanced vector IpZr
P54-TM-EN-1.1 543
Chapter 19 - Monitoring and Control P54
4.3.8 METERING
The metering calculations are continuously performed using the same fourier technique used by the fault locator.
The results of these calculations are continuously updated and can be viewed using the relay user interface.
544 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
5 CB CONDITION MONITORING
The device records various statistics related to each circuit breaker trip operation, allowing an accurate
assessment of the circuit breaker condition to be determined. These statistics are available in the CB CONDITION
column. The menu cells are register values only and cannot be set directly. They may be reset, however, during
maintenance. The statistics monitored are:
● Total Current Broken: A register stores the total amount of current that the CB has broken is stored in an
accumulator, giving at any time a measure of the total amount of current that the CB has broken since the
value was last reset.
● Number of CB operations: A counter registers the number of CB trips that have been performed for each
phase, giving at any time the total number of trips that the CB has performed since the value was last reset.
● CB Operate Time: A register stores the total amount of time the CB has transitioned from closed to open is
stored in an accumulator, giving at any time a measure of the total time that the CB has spent tripping since
the values was last reset.
● Excessive Fault Frequency: A counter registers the number of CB trips that have been performed for all
phases, giving at any time the total number of trips performed since the value was last reset.
These statistics are available in the CB CONDITION column. The menu cells are register values only and cannot be
set directly. They may be reset, however, during maintenance.
Note:
When in Commissioning test mode the CB condition monitoring registers are not updated.
Circuit breaker lockout, can be caused by the following circuit breaker condition monitoring functions:
● Maintenance lockout
● Excessive fault frequency lockout
● Broken current lockout
If the circuit breaker is locked out, the logic generates a lockout alarm
Pha se BCurrent
Set Set Cumulative IB b roken In
Reset
Phase CCurrent
Set Set Cumulative IC broken In
526
Trip 3 ph t Reset
534 1
External Trip3ph 0
Reset CB Data
447 1 Note: A ll timers ha ve 1 cycle pickup delay
Reset CB Data V01272
P54-TM-EN-1.1 545
Chapter 19 - Monitoring and Control P54
CB1PhaseBCurrent
Set Set CB1 Cumulative IB broken In
Reset
CB1PhaseCCurrent
Set Set CB 1 Cumulative IC broken In
526
CB1 Trip 3ph t Reset
534
1
CB1 Ext Trip3ph 0
523 Note: Broken current totals not incremented when device is in test mode
CB1 Trip OutputA t 1
535 1
CB1 Ext Trip A 0
524
CB1 Trip OutputB t 1
536 1
CB1 Ext Trip B 0
525
CB1 Trip OutputC t 1
537
1
CB1 Ext Trip C 0
Reset CB Data
447
1
Reset CB Data
CB2PhaseACurrent
Set Set CB2 Cumulative IA broken In
Reset
CB2PhaseBCurrent
Set Set CB2 Cumulative IB broken In
Reset
CB2PhaseCCurrent
Set Set CB 2 Cumulative IC broken In
1600
CB2 Trip 3ph t Reset
538
1
CB2 Ext Trip3 ph 0
546 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
523
Trip Output A 1 Increment
535 1
External Trip A Phase A Trip Counter
Reset
524
Trip Output B 1 Increment
536 1
External Trip B Phase B Trip Counter
Reset
525
Trip Output C 1 Increment
537 1
External Trip C Phase C Trip Counter
Reset
Reset CB Data
447 1
Reset CB Data
V01276
523
CB1 Trip OutputA 1 Increment
535
1
CB1 Ext Trip A CB1 Phase A Trip Counter
Reset
524
CB1 Trip OutputB 1 Increment
536
1
CB1 Ext Trip B CB1 Phase B Trip Counter
Reset
525
CB1 Trip OutputC 1 Increment
537
1
CB1 Ext Trip C CB1 Phase C Trip Counter
Reset
Reset CB1 Data
447
1
Rst CB1 Dat a
1600
CB2 Trip 3ph
538
1
CB2 Ext Trip3ph
1601
CB2 Trip OutputA 1 Increment
539
1
CB2 Ext Trip A CB2 Phase A Trip Counter
Reset
1602
CB2 Trip OutputB 1 Increment
540
1
CB2 Ext Trip B CB2 Phase B Trip Counter
Reset
1603
CB2 Trip OutputC 1 Increment
541
1
CB2 Ext Trip C CB2 Phase C Trip Counter
Reset
Reset CB2 Data
1597
1
Rst CB2 Dat a
V01277
P54-TM-EN-1.1 547
Chapter 19 - Monitoring and Control P54
523
Trip Output A 1 Start
External Trip A 535 CB operating time phase A Increment
Stop CBOpTimePhA Counter
IA < fixed threshold Reset
1
892
Pole Dead A
524
Trip Output B 1 Start
External Trip B 536 CB operating time phase B Increment
Stop CBOpTimePhB Counter
IB < fixed threshold Reset
1
893
Pole Dead B
525
Trip Output C 1 Start
External Trip C 527 CB operating time phase C Increment
Stop CBOpTimePhC Counter
IC < fixed threshold
1 Reset
894
Pole Dead C
Reset CB Data
447
1
Reset CB Data
V01274
548 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
523
CB1 Trip OutputA 1 Start
524
CB1 Trip OutputB 1 Start
1600
CB2 Trip 3ph
538 1
CB2 Ext Trip3ph
1601
CB2 Trip OutputA 1 Start
1602
CB2 Trip OutputB 1 Start
1603
CB2 Trip OutputC 1 Start
P54-TM-EN-1.1 549
Chapter 19 - Monitoring and Control P54
V01278
CB1FltFreqTime
1600
CB2 Trip 3ph
538
1
CB2 Ext Trip3ph 1 Increment
CB2 Trip OutputA 1601 CB2 Excessive Fault Frequency Counter
539
1 Reset
CB2 Ext Trip A
1602
CB2 Trip OutputB
540
1 S t
CB2 Ext Trip B Q
R 0 1
1603
CB2 Trip OutputC
541
1
CB2 Ext Trip C
1599
CB2 LO Alarm
CB2FltFreqTime
V01279
550 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
CB Failed to Trip S
Q
R t
CB Open 3 ph 903 &
0
860
Lockout Alarm
907
CB Closed 3 ph
1
908
CB Closed A ph
909
CB Closed B ph &
CB Closed C ph 910
Rst CB mon LO by
CB Close
CB mon LO RstDly
V01280
Rst CB mon LO by
CB Close
CB mon LO RstDly
CB mon LO reset
Yes
1 Reset CB2 Lockout Alarm
Clear Alarms
Rst CB mon LO by
CB Close
CB mon LO RstDly
V01281
P54-TM-EN-1.1 551
Chapter 19 - Monitoring and Control P54
I^ Lockout
CB Time Lockout
Reset Indication 1
Yes
Reset CB Data
Yes 1
447
Reset CB Data
S
860
Q Lockout Alarm
Reset lockout Alarm R
Control CB Unhealthy
Control no Check Synch
CB failed to trip
CB failed to close V01282
552 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
CB1 I^ Lockout
Clear Alarms 1
P54-TM-EN-1.1 553
Chapter 19 - Monitoring and Control P54
CB2 I^ Maint
Alarm Enabled
& 1113
Greatest broken current t otal & CB2 I^ Maint
S
CB2 I^ Maint Q
R 1 321 CB2 Monitor Alm
CB2 I^ Lockout
Alarm Enabled 1114
& CB2 I^ Lockout
CB2 I^ Lockout
Clear Alarms 1
554 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
If Res LO by UI is set to Enabled, the circuit breaker lockout can be reset from a user interface using the reset
circuit breaker lockout command in the CB CONTROL column.
If Res LO by NoAR is set to Enabled, the circuit breaker lockout can be reset by temporarily generating an AR
disabled signal.
If Res LO by TDelay is set to Enabled, the circuit breaker lockout is automatically reset after a time delay set in
the LO Reset Time setting.
If Res LO by ExtDDB is Enabled, the circuit breaker lockout can be reset by activation of an external input
mapped in the PSL to the relevant reset lockout DDB signal.
Res LO by CB IS
Enabled
&
CB1CRLO
Res LO by UI
Enabled
&
Reset CB LO
Yes
Res LO by NoAR
Enabled
& 1 RESCB1LO
AR Disabled
Res LO by ExtDDB
Enabled
&
446
Reset Lockout
Res LO by TDelay
Enabled
&
LO Reset Time
306 t
A/R Lockout
0
V03382a
Figure 351: Reset Circuit Breaker Lockout Logic Diagram (Module 57)
P54-TM-EN-1.1 555
Chapter 19 - Monitoring and Control P54
Res LO by CB IS
Enabled
&
CB1CRLO
Res LO by UI
Enabled
&
Reset CB1 LO
Yes
Res LO by NoAR
Enabled
& 1 RESCB1LO
ARDisabled
1
Num CBs
CB2 Only
Res LO by ExtDDB
Enabled
&
446
Rst CB1 Lockout
Res LO by TDelay
Enabled
&
LO Reset Time
306
t
CB1 AR Lockout
0
Res LO by CB IS
Enabled
&
CB2CRLO
Res LO by UI
Enabled
&
Reset CB2 LO
Yes
Res LO by NoAR
Enabled
& 1 RESCB2LO
ARDisabled
1
Num CBs
CB2 Only
Res LO by ExtDDB
Enabled
&
1422
Rst CB2 Lockout
Res LO by TDelay
Enabled
&
LO Reset Time
328
t
CB2 AR Lockout
0
V03383a
Figure 352: Reset Circuit Breaker Lockout Logic Diagram (Modules 57 & 58)
The dielectric withstand of the oil generally decreases as a function of I2t, where ‘I’ is the broken fault current and
‘t’ is the arcing time within the interrupter tank. The arcing time cannot be determined accurately, but is generally
556 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
dependent on the type of circuit breaker being used. Instead, you set a factor (Broken I^) with a value between 1
and 2, depending on the circuit breaker.
Most circuit breakers would have this value set to '2', but for some types of circuit breaker, especially those
operating on higher voltage systems, a value of 2 may be too high. In such applications Broken I^ may be set
lower, typically 1.4 or 1.5.
The setting range for Broken I^ is variable between 1.0 and 2.0 in 0.1 steps.
Note:
Any maintenance program must be fully compliant with the switchgear manufacturer’s instructions.
P54-TM-EN-1.1 557
Chapter 19 - Monitoring and Control P54
6 CB STATE MONITORING
CB State monitoring is used to verify the open or closed state of a circuit breaker. Most circuit breakers have
auxiliary contacts through which they transmit their status (open or closed) to control equipment such as IEDs.
These auxiliary contacts are known as:
● 52A for contacts that follow the state of the CB
● 52B for contacts that are in opposition to the state of the CB
This device can be set to monitor both of these types of circuit breaker state indication. If the state is unknown for
some reason, an alarm can be raised.
Some CBs provide both sets of contacts. If this is the case, these contacts will normally be in opposite states.
Should both sets of contacts be open, this would indicate one of the following conditions:
● Auxiliary contacts/wiring defective
● Circuit Breaker (CB) is defective
● CB is in isolated position
Should both sets of contacts be closed, only one of the following two conditions would apply:
● Auxiliary contacts/wiring defective
● Circuit Breaker (CB) is defective
If any of the above conditions exist, an alarm will be issued after a 5 s time delay. An output contact can be
assigned to this function via the programmable scheme logic (PSL). The time delay is set to avoid unwanted
operation during normal switching duties.
In the CB CONTROL column there is a setting called CB Status Input. This cell can be set at one of the following
four options:
● None
● 52A
● 52B
● Both 52A and 52B
Where None is selected no CB status is available. Where only 52A is used on its own then the device will assume a
52B signal opposite to the 52A signal. Circuit breaker status information will be available in this case but no
discrepancy alarm will be available. The above is also true where only a 52B is used. If both 52A and 52B are used
then status information will be available and in addition a discrepancy alarm will be possible, according to the
following table:
Auxiliary Contact Position CB State Detected Action
52A 52B
Open Closed Breaker open Circuit breaker healthy
Closed Open Breaker closed Circuit breaker healthy
Alarm raised if the condition persists for greater than
Closed Closed CB failure
5s
Alarm raised if the condition persists for greater than
Open Open State unknown
5s
The Circuit Breaker status can be monitored in the serial and Ethernet data protocols. For example, IEC
60870-5-103, DNP 3.0 and IEC 61850.
IEC 60870-5-103 protocol: The CB status can be monitored from individual private information numbers.
DNP 3.0 protocol: The CB status can be monitored from individual Binary Inputs.
558 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
IEC 61850 protocol: The CB status can be monitored in ‘XCBR’ Logical Node(s).
424
CB Aux 3ph(52 -B)
& 1 907
1 CB Closed 3 ph
XOR
&
CB Status Input
&
52A 3 pole
52B 3 pole
52A & 52B 3 pole & 1 903
1 CB Open 3 ph
&
&
421
CB Aux A(52 -A)
&
425 908
CB Aux A(52 -B) 1 CB Closed A ph
& 1
XOR
&
&
CB Status Input
&
52A 1 pole
52B 1 pole 904
1 CB Open A ph
52A & 52B 1 pole & 1
&
&
&
422 909
CB Aux B(52-A) 1 CB Closed B ph
426
CB Aux B(52-B)
905
Phase B 1 CB Open B ph
CB Status Input
(Same logic as phase A)
52A 1 pole
52B 1 pole
52A & 52B 1 pole
423 910
CB Aux C(52-A) 1 CB Closed C ph
427
CB Aux C(52-B)
906
Phase C 1 CB Open C ph
CB Status Input
(Same logic as phase A)
52A 1 pole
52B 1 pole t 301
1 CB Status Alm
52A & 52B 1 pole 0
P54-TM-EN-1.1 559
Chapter 19 - Monitoring and Control P54
424
CB1 Aux 3ph(52-B)
& 1 907
1 CB1 Closed 3 ph
XOR
&
&
&
421
CB1 Aux A(52-A)
&
425 908
CB1 Aux A(52-B) 1 CB1 Closed A ph
& 1
XOR
&
&
&
&
&
422 909
CB1 Aux B(52-A) 1 CB1 Closed B ph
905
Phase B 1 CB1 Open B ph
CB1 Status Input
(Same logic as phase A )
52A 1 pole
52B 1 pole
52A & 52B 1 pole
423 910
CB1 Aux C(52-A) 1 CB1 Closed C ph
906
Phase C 1 CB1 Open C ph
CB1 Status Input
(Same logic as phase A )
52A 1 pole
52B 1 pole 301
1 CB1 Status Alm
52A & 52B 1 pole
560 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
428
CB2 Aux 3ph(52A)
&
432
CB2 Aux 3ph(52B)
& 1
1 915 CB2 Closed 3 ph
XOR
&
&
&
429
CB2 Aux A(52-A)
&
433 916
CB2 Aux A(52-B) 1 CB2 Closed A ph
& 1
XOR
&
&
&
&
&
430 917
CB2 Aux B(52-A) 1 CB2 Closed B ph
434
CB2 Aux B(52-B)
913
Phase B 1 CB2 Open B ph
CB2 Status Input
(Same logic as phase A)
52A 1 pole
52B 1 pole
52A & 52B 1 pole
431 918
CB2 Aux C(52-A) 1 CB2 Closed C ph
435
CB2 Aux C(52-B)
914
Phase C 1 CB2 Open C ph
CB2 Status Input
(Same logic as phase A)
52A 1 pole
52B 1 pole 323
1 CB2 Status Alm
52A & 52B 1 pole
P54-TM-EN-1.1 561
Chapter 19 - Monitoring and Control P54
Circuit Breaker control is only possible if the circuit breaker in question provides auxiliary contacts. The CB Status
Input cell in the CB CONTROL column must be set to the type of circuit breaker. If no CB auxiliary contacts are
available then this cell should be set to None, and no CB control will be possible.
The CB control by cell is used to enable or disable local control options, remote control options, and combinations
of both.
The output contact can be set to operate following a time delay defined by the setting Man Close Delay. One
reason for this delay is to give personnel time to safely move away from the circuit breaker following a CB close
command.
The control close cycle can be cancelled at any time before the output contact operates by any appropriate trip
signal, or by activating the Reset Close Dly DDB signal.
The length of the trip and close control pulses can be set via the Trip Pulse Time and Close Pulse Time settings
respectively. These should be set long enough to ensure the breaker has completed its open or close cycle before
the pulse has elapsed.
If an attempt to close the breaker is being made, and a protection trip signal is generated, the protection trip
command overrides the close command.
The Reset Lockout by setting is used to enable or disable the resetting of lockout automatically from a manual
close after the time set by Man Close RstDly.
If the CB fails to respond to the control command (indicated by no change in the state of CB Status inputs) an
alarm is generated after the relevant trip or close pulses have expired. These alarms can be viewed on the LCD
display, remotely, or can be assigned to output contacts using the programmable scheme logic (PSL).
Note:
The CB Healthy Time and Sys Check time set under this menu section are applicable to manual circuit breaker operations
only. These settings are duplicated in the AUTORECLOSE menu for autoreclose applications.
The Lockout Reset and Reset Lockout by settings are applicable to CB Lockouts associated with manual circuit
breaker closure, CB Condition monitoring (Number of circuit breaker operations, for example) and autoreclose
lockouts.
The device includes the following options for control of a single circuit breaker:
● The IED menu (local control)
● The CB Open/Close keys and the SLD on the graphical HMI
● The opto-inputs (local control)
● SCADA communication (remote control)
562 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
P54-TM-EN-1.1 563
Chapter 19 - Monitoring and Control P54
Protection Trip
Trip
Remote
Control
Trip Close
Remote
Control
Close
Local
Remote
Trip Close
E01207
DNP 3.0 protocol: The CB position can be controlled from Binary Outputs/Control Relay Output Blocks.
IEC 61850 protocol: The CB position can be controlled in the ‘CSWI’ Logical Node that is linked to the ‘XCBR’ Circuit
Breaker Logical Node.
564 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
Time. If the CB does not indicate a healthy condition within the time period following a Close command, the device
will lockout and alarm.
P54-TM-EN-1.1 565
Chapter 19 - Monitoring and Control P54
440 &
Init close CB Man Close Delay Close Pulse Time
1 842
Close in Prog
HMI Close
& S t
CB ARIP 1544 Q 839
RD 0 & Control Close
854 1 S t
Auto Close Q
RD 0
443
Reset Close Dly
522 303
Any Trip & CB Close Fail
1
838
Control Trip
534
External Trip3Ph 1
1
535
External Trip A
537
External Trip C
1 1
903
CB Open 3 ph
904
CB Open A ph
905 Note: Module numbers shown in red are
CB Open B ph & for dual breaker logic.
906
CB Open C ph
907
CB Closed 3 ph
1
908
CB Closed A ph
CB Closed B ph 909
1 CB Healthy Time
910
CB Closed C ph
t 304
436 & Man CB Unhealthy
CB Healthy 0
t 305
1574 & No C/S Man Close
CB Man SCOK 0
V03369a
566 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
440
&
Init close CB1 Man Close Delay Close Pulse Time
1 842
CB1 Close inProg
HMI Close
& S t
CB1 ARIP 1544 Q 839
RD 0 & Control CloseCB1
854
1 S t
Auto Close CB1 Q
RD 0
443
Rst CB1 CloseDly
522 303
Any Trip & CB1 Close Fail
1
838
Control TripCB1
534
CB1 Ext Trip3ph 1
1
535
CB1 Ext Trip A
536
CB1 Ext Trip B
537
CB1 Ext Trip C
1 1
903
CB1 Open 3 ph
904
CB1 Open A ph
905
CB1 Open B ph &
906
CB1 Open C ph
907
CB1 Closed 3 ph
1
908
CB1 Closed A ph
CB1 Closed B ph 909
1 CB Healthy Time
910
CB1 Closed C ph
t 304
436
& ManCB1 Unhealthy
CB1 Healthy 0
t 305
1574
& NoCS CB1ManClose
CB1 Man SCOK 0
V03370a
P54-TM-EN-1.1 567
Chapter 19 - Monitoring and Control P54
CB Control by
Opto
Opto+Local Note: If the DDB signal CB1 Healthy, or CB2 healthy is not mapped in PSL, it defaults to
1 High.
Opto+Remote
Opto+Rem+Local
Trip Pulse Time
840
HMI Trip Control TripCB2
1
& S t
441
& Q 324
Init Trip CB2 RD 0 & CB2 Trip Fail
442
&
Init close CB2 Man Close Delay Close Pulse Time
1 1453
CB2 Close inProg
HMI Close
& S t
CB2 ARIP 1435 Q 841
RD 0 & Control CloseCB2
1448
1 S t
Auto Close CB2 Q
RD 0
1419
Rst CB2 CloseDly
522 325
Any Trip & CB2 Close Fail
1
840
Control TripCB2
538
CB2 Ext Trip3ph 1
1
539
CB2 Ext Trip A
540
CB2 Ext Trip B
541
CB2 Ext Trip C
1 1
911
CB2 Open 3 ph
912
CB2 Open A ph
913
CB2 Open B ph &
914
CB2 Open C ph
915
CB2 Closed 3 ph
1
916
CB2 Closed A ph
CB2 Closed B ph 917
1 CB Healthy Time
918
CB2 Closed C ph
t 326
437
& ManCB2 Unhealthy
CB2 Healthy 0
t 327
1458
& NoCS CB2ManClose
CB2 Man SCOK 0
V03344a
568 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
It can also be used to block operation of underfrequency and undervoltage elements where applicable.
IA 20 ms
t
I< Current Set &
892
0 1 Pole Dead A
VA
V<
&
904
CB Open A ph
IB 20 ms
t
V<
&
905
CB Open B ph
IC 20 ms
t
&
833
VTS Slow Block 890
& All Poles Dead
906
CB Open C ph
&
903
CB Open 3 ph
V01247
If both the line current and voltage values fall below a certain threshold, or a CB Open condition is asserted from
the state control logic, the device initiates a Pole Dead condition. The current and voltage thresholds can be set
with the I< Current Set and the V< settings respectively, in the CBFAIL&P.DEAD column.
If one or more poles are dead, the device indicates which phase is dead and asserts the Any Pole Dead DDB
signal. If all phases are dead the Any Pole Dead signal is accompanied by the All Poles Dead signal.
If the VT fails, a VTS Slow Block signal is taken from the VTS logic to block the Pole Dead indications that would be
generated by the undervoltage and undercurrent thresholds.
Note:
If the VT is connected at the busbar side, auxiliary contacts (52a or 52b) must be connected to the IED for a correct pole dead
indication.
P54-TM-EN-1.1 569
Chapter 19 - Monitoring and Control P54
V<
&
904
CB1 Open A ph
&
912
CB2 Open A ph
20 ms
t
V<
905 &
CB1 Open B ph
&
913
CB2 Open B ph
20 ms
t
891
1 Any Pole Dead
V<
833
&
VTS Slow Block 890
& All Poles Dead
CB1 Open C ph 906 &
&
914
CB2 Open C ph
&
911
CB2 Open 3 ph
V01269
If both the line current and voltage values fall below a certain threshold, or a CB Open condition is asserted from
the state control logic, the device initiates a Pole Dead condition. The current and voltage thresholds can be set
with the I< Current Set and the V< settings respectively, in the CBFAIL&P.DEAD column.
If one or more poles are dead, the device indicates which phase is dead and asserts the Any Pole Dead DDB
signal. If all phases are dead the Any Pole Dead signal is accompanied by the All Poles Dead signal.
If the VT fails, a VTS Slow Block signal is taken from the VTS logic to block the Pole Dead indications that would be
generated by the undervoltage and undercurrent thresholds.
Note:
If the VT is connected at the busbar side, auxiliary contacts (52a or 52b) must be connected to the IED for a correct pole dead
indication.
570 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
9 SYSTEM CHECKS
In some situations it is possible for both "bus" and "line" sides of a circuit breaker to be live when a circuit breaker is
open - for example at the ends of a feeder that has a power source at each end. Therefore, it is normally necessary
to check that the network conditions on both sides are suitable, before closing the circuit breaker. This applies to
both manual circuit breaker closing and autoreclosing. If a circuit breaker is closed when the line and bus voltages
are both live, with a large phase angle, frequency or magnitude difference between them, the system could be
subjected to an unacceptable shock, resulting in loss of stability, and possible damage to connected machines.
The System Checks functionality involves monitoring the voltages on both sides of a circuit breaker, and if both
sides are live, performing a synchronisation check to determine whether any differences in voltage magnitude,
phase angle or frequency are within permitted limits.
The pre-closing system conditions for a given circuit breaker depend on the system configuration, and for
autoreclosing, on the selected autoreclose program. For example, on a feeder with delayed autoreclosing, the
circuit breakers at the two line ends are normally arranged to close at different times. The first line end to close
usually has a live bus and a dead line immediately before reclosing. The second line end circuit breaker now sees a
live bus and a live line.
If there is a parallel connection between the ends of the tripped feeder the frequencies will be the same, but any
increased impedance could cause the phase angle between the two voltages to increase. Therefore just before
closing the second circuit breaker, it may be necessary to perform a synchronisation check, to ensure that the
phase angle between the two voltages has not increased to a level that would cause unacceptable shock to the
system when the circuit breaker closes.
If there are no parallel interconnections between the ends of the tripped feeder, the two systems could lose
synchronism altogether and the frequency at one end could "slip" relative to the other end. In this situation, the
second line end would require a synchronism check comprising both phase angle and slip frequency checks.
If the second line-end busbar has no power source other than the feeder that has tripped; the circuit breaker will
see a live line and dead bus assuming the first circuit breaker has re-closed. When the second line end circuit
breaker closes the bus will charge from the live line (dead bus charge).
P54-TM-EN-1.1 571
Chapter 19 - Monitoring and Control P54
9.1.1 VT CONNECTIONS
The device provides inputs for a three-phase "Main VT" and at least one single-phase VT for check synchronisation.
Depending on the primary system arrangement, the Main VT may be located on either the line-side of the busbar-
side of the circuit breaker, with the Check Sync VT on the other. Normally, the Main VT is located on the line-side (as
per the default setting), but this is not always the case. For this reason, a setting is provided where you can define
this. This is the Main VT Location setting, which is found in the CT AND VT RATIOS column.
The Check Sync VT may be connected to one of the phase-to-phase voltages or phase-to-neutral voltages. This
needs to be defined using the CS Input setting in the CT AND VT RATIOS column. Options are, A-B, B-C, C-A, A-N, B-
N, or C-N.
572 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
origin whose radius is equal to the nominal line voltage magnitude. The minimum voltage magnitude at which the
system can be considered as Live, is the magnitude difference between the bus and line voltages.
0º
Check Sync
Stage 2 Limits
Check Sync
Stage 1 Limits
V
BUS
Live Volts
Rotating
Vector
Nomical
Volts
V LINE
Dead Volts
±180º
System Split
E01204 Limits
P54-TM-EN-1.1 573
Chapter 19 - Monitoring and Control P54
VAN 888
Live Line & Live Line
VBN
VCN 889
Select Dead Line & Dead line
VAB
VBC 886
Live Bus & Live Bus
VCA
VBus
VBus Dead Bus & 887
Dead Bus
Voltage Monitors
438
MCB/VTS
1521
MCB/VTS CB CS
1522
1
Inhibit LL
1523
1
Inhibit DL
1524
1
Inhibit LB
1525
1
Inhibit DB
V01257
574 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
VAN 888
Live Line & Live Line
VBN
VCN 889
Select Dead Line & Dead line
VAB
VBC 886
Live Bus 1 & Live Bus 1
VCA
VBus 2
1461
Live Bus 2 & Live Bus 2
MCB/VTS 438
1521 1462
MCB/VTS CB1 CS Dead Bus 2 & Dead Bus 2
1423
MCB/VTS CB2 CS
Voltage Monitors
1522 1
Inhibit LL
1523 1
Inhibit DL
1524 1
Inhibit LB 1
1525
1
Inhibit DB 1
1424 1
Inhibit LB 2
1425 1
Inhibit DB 2
V 01258
P54-TM-EN-1.1 575
Chapter 19 - Monitoring and Control P54
1582
& CS Vbus<
CS1 Vl>Vb 1586
& CS1 Vl>Vb
CS1 Vl<Vb 1588
& CS1 Vl<Vb
CS1 Fl>Fb 1590
& CS1 Fl>Fb
CS1 Fl<Fb 1591
& CS1 Fl<Fb
CS1 AngHigh+ 1592
& CS1 AngHigh+
CS1 AngHigh- 1593
& CS1 AngHigh-
CS2 Fl>Fb 1493
& CS2 Fl>Fb
CS2 Fl<Fb 1494
& CS2 Fl<Fb
CS2 AngHigh+
& 1495
CS2 AngHigh+
CS2 AngHigh-
& 1496
CS2 AngHigh-
CS2 Status
884
Enabled & Check Sync 2 OK
882
CS2 Enabled V01259
576 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
CS Vbus1< 1582
& CS Vbus<
CB1 CS1 Vl>Vb 1586
& CB1 CS1 Vl> Vb
CB1 CS1 Vl<Vb 1588
& CB1 CS1 Vl< Vb
CB1 CS1 Fl>Fb 1590
& CB1 CS1 Fl>Fb
CB1 CS1 Fl<Fb 1591
& CB1 CS1 Fl<Fb
CB1 CS1 AngHigh+ 1592
& CB1 CS1 AngHigh+
CB1 CS1 AngHigh- 1593
& CB1 CS1 AngHigh-
CB1 CS2 Fl>Fb 1493
& CB1 CS2 Fl>Fb
CB1 CS2 Fl<Fb 1494
& CB1 CS2 Fl<Fb
CB1 CS2 AngHigh+ 1495
& CB1 CS2 AngHigh+
CB1 CS2 AngHigh- 1496
& CB1 CS2 AngHigh-
CB1 CS AngRotACW 1594
& CB1 CS AngRotACW
1521
MCB/VTS CB CS CB1 CS AngRotCW 1595
438 & CB1 CS AngRotCW
MCB/VTS
832 CB1 CS2 Vl>Vb 1587
VTS Fast Block & CB1 CS2 Vl> Vb
1
319
F out of Range CB1 CS2 Vl<Vb 1589
& CB1 CS2 Vl< Vb
CB1 CS1 Status
883
Enabled & CB1 CS1 OK
881
CB1 CS1 Enabled
CB1 CS2 Status
884
Enabled & CB1 CS2 OK
882
CB1 CS2 Enabled V01260
Figure 367: Check Synchronisation Monitor for CB1 closure (Module 60)
P54-TM-EN-1.1 577
Chapter 19 - Monitoring and Control P54
Sys checks CB 2
1484
Disabled SChksInactiveCB 2
Enabled
CS1 Criteria OK
VAN &
&
CS Vbus2> 1585
& CS Vbus2>
&
CS Vbus2<
Check Synchronisation Function
1584
& CS Vbus2<
CB2 CS1 Vl>Vb 1470
& CB2 CS1 Vl> Vb
CB2 CS1 Vl<Vb 1472
& CB2 CS1 Vl< Vb
CB2 CS1 Fl>Fb 1474
& CB2 CS1 Fl>Fb
CB2 CS1 Fl<Fb 1476
& CB2 CS1 Fl<Fb
CB2 CS1 AngHigh+ 1478
& CB2 CS1 AngHigh+
CB2 CS1 AngHigh- 1479
& CB2 CS1 AngHigh-
CB2 CS2 Fl>Fb 1475
& CB2 CS2 Fl>Fb
CB2 CS2 Fl<Fb 1477
& CB2 CS2 Fl<Fb
CB2 CS2 AngHigh+ 1480
& CB2 CS2 AngHigh+
CB2 CS2 AngHigh- 1481
& CB2 CS2 AngHigh-
CB2 CS AngRotACW 1482
& CB2 CS AngRotACW
1521
MCB/VTS CB CS CB2 CS AngRotCW 1483
438 & CB2 CS AngRotCW
MCB/VTS
832 CB2 CS2 Vl>Vb 1471
VTS Fast Block & CB2 CS2 Vl> Vb
1
319
F out of Range CB2 CS2 Vl<Vb 1473
& CB2 CS2 Vl< Vb
CB2 CS1 Status
1577
Enabled & CB2 CS1 OK
1426
CB2 CS1 Enabled
CB2 CS2 Status
884
Enabled & CB1 CS2 OK
1427
CB2 CS2 Enabled V01268
Figure 368: Check Synchronisation Monitor for CB2 closure (Module 61)
578 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
CS Vline <
& CS Vline<
CS Vbus <
& CS Vbus<
CS Vline > Vbus
& CS Vline>Vbus
CS Vline < Vbus
& CS Vline<Vbus
CS1 Fline > Fbus
& CS1 Fline>Fbus
CS1 Fline < Fbus
& CS1 Fline<Fbus
CS1 Angle not OK+
& CS1 Ang Not OK +
CS1 Angle not OK-
& CS1 Ang Not OK -
CS2 Fline > Fbus
& CS2 Fline>Fbus
CS2 Fline < Fbus
& CS2 Fline<Fbus
CS2 Angle not OK+
& CS2 Ang Not OK +
CS2 Angle not OK-
& CS2 Ang Not OK -
Angle rotating anticlockwise
& CS Ang Rot ACW
Angle rotating clockwise
VTS Fast Block & CS Ang Rot CW
1
F out of Range
CS1 Status
Enabled & Check Sync 1 OK
CS1 Enabled
CS2 Status
Enabled & Check Sync 2 OK
CS2 Enabled
SS Status
Enabled & System Split
SysSplit Enabled
Note: This diagram does not show all stages. Other stages follow similar principles.
V01205 VTS Fast Block only applies for directional models.
P54-TM-EN-1.1 579
Chapter 19 - Monitoring and Control P54
1574
Live Line 888 CB Man SCOK
&
887
Dead Bus 1 899
AR Sys Checks
&
889
Dead Line
&
886
Live Bus
V02101
By enabling both CS1 and CS2, the device can be configured to allow CB closure if either of the two conditions is
detected.
For manual circuit breaker closing with synchronism check, some utilities might prefer to arrange the logic to
check initially for condition 1 only. However, if a System Split is detected before the condition 1 parameters are
satisfied, the device will switch to checking for condition 2 parameters instead, based on the assumption that a
significant degree of slip must be present when system split conditions are detected. This can be arranged by
suitable PSL logic, using the System Check DDB signals.
580 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
closing occurs at close to 0º therefore minimising the impact to the power system. The actual closing angle is
subject to the constraints of the existing product architecture, i.e. the protection task runs twice per power system
cycle, based on frequency tracking over the frequency range of 40 Hz to 65 Hz.
P54-TM-EN-1.1 581
Chapter 19 - Monitoring and Control P54
XSWI1 XSWI2
XCBR
XSWI3 Legend:
XSWI4 XSWI1 = Disconnector 1
XSWI2 = Disconnector 2
XSWI3 = Disconnector 3
XSWI4 = Earthing Switch
XCBR = Circuit Breaker
V01241
This bay shows four switches of the type LN XSWI and one circuit breaker of type LN XCBR. In this example, the
switches XSWI1 – XSWI3 are disconnectors and XCSWI4 is an earthing switch.
For the device to be able to control the switches, the switches must provide auxiliary contacts to indicate the
switch status. For convenience, the device settings refer to the auxiliary contacts as 52A and 52B, even though
they are not circuit breakers.
There are eight sets of settings in the SWITCH CONTROL column, which allow you to set up the Switch control, one
set for each switch. These settings are as follows:
SWITCH1 Type
This setting defines the type of switch. It can be a load breaking switch, a disconnector, an earthing switch or a
high speed earthing switch.
SWI1 Status Inpt
This setting defines the type of auxiliary contacts that will be used for the control logic. For convenience, the device
settings refer to the auxiliary contacts as 52A and 52B, even though they are not circuit breakers. "A" contacts
match the status of the primary contacts, whilst "B" contacts are of the opposite polarity.
SWI1 Control by
This setting determines how the switch is to be controlled. This can be Local (using the device directly) remote
(using a communications link), or both.
SWI1Trip/Close
This is a command t o directly trip or close the switch.
SWI1 Trp Puls T and SWI1 Cls Puls T
582 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
These settings allow you to control the width of the open and close pulses.
SWI1 Sta Alrm T
This setting allows you to define the duration of wait timer before the relay raises a status alarm.
SWI1 Trp Fail T and SWI1 Cls Fail T
These settings allow you to control the delay of the open and close alarms when the final switch status is not in
line with expected status.
SWI1 Operations
This is a data cell, which displays the number of switch operations that have taken place. It is an accumulator,
which you can reset using the Reset SWI1 Data setting
Reset SWI1 Data
This setting resets the switch monitoring data.
Note:
Settings for switch 1 are shown, but settings for all other switch elements are the same.
IEC 61850 protocol: The Switch position can be controlled in the ‘CSWI’ Logical Node that is linked to the ‘XSWI’
Switch Logical Node.
t
& SWI1 Input Alm
0
&
&
V01243
P54-TM-EN-1.1 583
Chapter 19 - Monitoring and Control P54
SWI1 Control by 1
&
Local 1
Local+Remote
1
Remot e &
Local
Remot e
&
SWI1 Pulse Timer Ctrl
Enabled
SWI1 Cls Puls T
SWI1 Trip/Close
Close SWI1 Trp P uls T
Trip
&
&
1 SWI1 Control Alm
&
SWI1 Cls Fail T
S t
Q
R 0
S t
Q
R 0
V01242
584 P54-TM-EN-1.1
P54 Chapter 19 - Monitoring and Control
11 TEST MODE
The behaviour of the IED is dependant on if it is in normal operation or in one of the Test Modes. This is reflected in
some of the data that can be monitored and affects the allowed control operations, particularly using the IEC
61850 protocol.
The mode of operation is set using the IED Test Mode cell under the COMMISSION TESTS column. See the
Commissioning Instructions chapter for more information.
When the IED is in either Test or Contacts Blocked mode, IEC 61850 status and measurement data will be
transmitted with its quality parameter set to test, so that the receiver understands that they have been issued by a
device under test and can respond accordingly.
When the IED is in either Test or Contacts Blocked’ mode, the IED only responds to IEC 61850 MMS controls from
the client with the 'test' flag set (with the exception of controls on System/LLN0.Mod).
P54-TM-EN-1.1 585
Chapter 19 - Monitoring and Control P54
586 P54-TM-EN-1.1
CHAPTER 20
SUPERVISION
Chapter 20 - Supervision P54
588 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
1 CHAPTER OVERVIEW
This chapter describes the supervison functions.
This chapter contains the following sections:
Chapter Overview 589
Current Differential Supervision 590
Voltage Transformer Supervision 600
Current Transformer Supervision 604
Trip Circuit Supervision 610
P54-TM-EN-1.1 589
Chapter 20 - Supervision P54
Which starter elements are used and in which combination depend on the specific application and customer
requirements. The device provides complete flexibility, allowing you to use each of them individually or in
combination with one another using PSL.
The starter element settings are located in the CURRENT DIFF column. You can choose to enable, or disable them,
or select Idiff Permit (discussed later). They are disabled by default.
590 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
If a starter element picks up, the associated DDB signal is asserted. These can be used to block the current
differential protection. These DDB signals are:
● I1 Lo Start (Positive phase-sequence fixed threshold start)
● Del I1 Lo Start (Rate-of-change of positive phase-sequence current)
● I2 Lo Start (Negative phase-sequence fixed threshold start)
● Del I2 Lo Start (Rate-of-change of negative phase-sequence current)
If elements are set to Disabled, then the DDB signals cannot be asserted.
If elements are set to Enabled, then the DDB signals will be asserted if appropriate conditions are met. This will
allow you to use PSL to customize supervision of Current Differential protection operation. These signals do not
directly affect the operation of the Current Differential function. In order to directly influence the operation of the
current differential function you need to set one or more of the starter elements to Idiff Permit.
If elements are set to Idiff Permit, then the DDB Start signals will also be asserted if the appropriate
conditions are met, so you can use the PSL to customise supervision of Current Differential protection operation. In
addition however, if any one or more elements are set to IDiff Permit, then fixed internal logic is employed to
produce an internal signal (Permit CDiff) that supervises the Current Differential protection by either inhibiting it or
permitting it.
P54-TM-EN-1.1 591
Chapter 20 - Supervision P54
813
& I1 Lo Sta rt
Start I1 low
Start I1
Disabled
1/8 cycle
PU
S 809
Q Del I1 Lo Start
Delt a I1 low & R
546 1
Block Delta PU
Delt a I1
Disabled
Reset Lo w Time
811
& I2 Lo Sta rt
Start I2 Low
Start I2
Disabled
1/8 cycle
PU
S 807
Q Del I2 Lo Start
Delt a I2 low & R
546
Block Delta 1
PU
548 827
Block Start I2 1 Any L ow S et Sta rt
Delt a I2 1
Reset Lo w Time
Disabled
825
1 Any Delta St art
Start I1
Idiff permit 826
1 Any Thresh Sta rt
Delt a I1
Idiff
Start
permit
I1
&
Start I2
Idiff permit
Delt a I2
Idiff permit
&
Start I1 low
&
1 Permit Cdiff
Delt a I1 low
&
Start I2 Low
&
Delt a I2 low
V02 600
592 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
This function is completely different to the I1 and I2 starters. It is necessary to enable at all relay ends of the line
protected for this function to work correctly.
Start Isef and Delta Isef elements can be set to Enabled or Disabled. If both elements are set to Disabled,
The line differential protection completely ignores this check and DDB signals Start Isef Low and Delta Isef Low
cannot be asserted.
If one or both elements are set to Enabled, all multiphase faults ignore this check, and single phase to ground
faults are only allowed to issue a differential trip if the threshold of the differential element has been exceeded or a
differential intertrip has been received and the threshold of Start Isef or Delta Isef has been exceeded. DDB
signals, Start Isef Low and Delta Isef Low will be asserted if appropriate conditions are met.
Start Isef supervision should be set above the maximum unbalanced current expected in the protected circuit. This
could happen during maximum load condition. A margin of 20% above that value is recommended to take
account of the accuracy of the element and the measurement.
P54-TM-EN-1.1 593
Chapter 20 - Supervision P54
Diff Trip B
1 1
Diff Trip C
IDiff>Start A
&
IDiff>Start B
1
IDiff>Start C
Diff Trip B
&
Diff Trip A
1 1
Diff Trip C
IDiff>Start B
&
IDiff>Start A
1
IDiff>Start C
Diff Trip C
&
Diff Trip A
1
Diff Trip B 1
IDiff>Start C &
IDiff>Start A 1 SEF Permit Cdiff
IDiff>Start B 1
1
Receive Diff Intertrip B
&
IN
Receive Diff Intertrip C
& &
Start Isef Low
Receive Diff Intertrip A
Start Isef 1
Disabled Receive Diff Intertrip B
IN Delta
1996
Start Isef Low
Delta Isef Low
& 1997 1 &
Delta Isef Low
Delta Isef
Disabled
Diff Trip A
Diff Trip B
1
Receive Diff Intertrip B
Diff Trip C
594 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
Permit Cdiff SD
Q
1 R 738
IDiff>Start A & IDiff>Start A
Phase A Operate threshold &
&
reached
739
IDiff>Start B & IDiff>Start B
Phase B Operate threshold &
&
reached
740
IDiff>Start C & IDiff>Start C
Phase C Operate threshold &
&
reached
Start Isef
Disabled
&
Delta Isef
1
Disabled
V02636
P54-TM-EN-1.1 595
Chapter 20 - Supervision P54
Operate
Region
K2 slope
Supervise
Region
Restrain
K1 Slope
Region
IS1
IS2 Ibias
V02603
The change to the characteristic is determined by two timers (Char Mod Time, and Char Mod RstTime) found in
the PROT COMMS/IM64 column. These timers start when the switched communication path condition is
recognised. These timers define how long the modification to the tripping characteristics is applied for. A
communications delay alarm (Comm Delay Alarm) is also raised at the same time.
When the Comm Delay Tol setting has been exceeded for two consecutive calculations, the K1 slope is increased
to 200%. When the 200% slope reaches the IS2 setting, the characteristic tracks a horizontal line until it meets
with the K2 slope which the characteristic then follows.
The characteristic normally returns to normal when the Char Mod Time expires, but a mechanism is provided to
accelerate the reset if system conditions permit by using an additional timer Char Mod RstTime which is set to a
value less than the Char Mod Time.
The Char Mod RstTime can be enabled or disabled. If it is enabled, then it starts when the Char Mod Time starts. If
the Char Mod RstTime has expired, but the Char Mod Time is still running, AND IF the bias current is above 5% In,
AND IF the differential current is below 10% of bias current on all phases, then the Char Mod Time is reset and the
characteristic returns to normal. If these conditions are not met, then the characteristic remains increased for the
duration of the Char Mod Time. The Char Mod RstTime should be set greater than the minimum switching delay
expected, and less than the Char Mod Time.
We don’t recommend it, but If you don’t want the tripping characteristic to be changed during communications
switching operations, you should set Char Mod Time to 0.
596 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
Referring to the Switched Communication Path Supervision feature, if communication switching takes place, the
Current Differential protection will detect a propagation delay change and invoke a temporary increase in the
tripping threshold for a period set in the Char Mod Time setting column. When the timer expires, the standard
characteristic is restored. Whilst the timer is active, the differential protection will be stable for asymmetric
communication paths but if the asymmetry persists when the characteristic switches back, the protection might
trip. Using the current differential supervision feature, the condition can be detected and maloperation can be
prevented.
The function superimposes a second dual slope characteristic (defined by the settings IDiff Isup1 and IDiff Isup2
and Phase k1 slope of the current differential protection) onto the standard operating characteristic as shown in
the figure below:
Idiff
K2 slope
Operate
Supervise
(Block or Alarm)
K1 Slope
Restrain
IS1
Isup1
If you choose to use the function, we recommend that you set the pickup value of the differential supervision
function (IDiff Isup1) be set at 80% of the Is1 setting and the IDiff Isup2 setting to 200% of Is2. The delay between
the condition being recognised and the alarm being raised is determined by the Idiff Sup TDelay setting.
Note:
Idiff Sup TDelay must always be set greater than the value set in Char Mod time.
P54-TM-EN-1.1 597
Chapter 20 - Supervision P54
GPS Standard
If GPS -> Standard is selected, the time alignment of the current data is performed by using the values of
propagation delay times (tp1, tp2) that were calculated and stored prior to the GPS failure. Each terminal continues
to measure the overall propagation delay (tp1+tp2). If the overall propagation delay remains unchanged, the
differential protection will continue to use the stored values until the GPS synchronisation is restored.
A communications delay tolerance setting (Comm Delay Tol) is provided. If the overall propagation delay changes
but by an amount less than this setting, the differential protection will continue to use the stored values of tp1 and
tp2 until GPS synchronisation is restored. If the overall propagation delay changes by an amount more than this
setting, the differential protection will be blocked until GPS synchronisation is restored.
GPS Inhibit
With GPS -> Inhibit selected, if the propagation delay times are equal when the GPS synchronisation is lost,
the product reverts to the ping-pong method of time alignment. If the propagation delays are not equal when the
GPS signal is lost, the product performs in the same way as if GPS -> Standard had been selected, using the
stored propagation delay times.
If the propagation delay changes by more than the Comm Delay Tol setting, the differential protection is blocked
until GPS synchronisation is restored.
GPS Restrain
If GPS -> Restrain is selected in the GPS Sync setting, the supervision applied to the Current Differential
function is the same as that for Switched Communications Paths Supervision described previously, and based on
increasing the bias quantity if path switching is detected.
In this case, if GPS has failed, and if the difference between successive propagation delay time measurements
exceeds the user settable Comm Delay Tol value, the device asserts the Comm Delay Alarm DDB signal and
initiates the temporary change in the bias characteristic managed by the Char Mod Time and Char Mod RstTime
settings.
598 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
Setting Description.
When Current Diff is enabled and if GPS Sync is not disabled, the absolute difference between the
Transmission and Reception propagation delay on channel 1 is calculated. The maximum value is displayed
MaxCh1 Tx-RxTime
in the MEASUREMENTS 4 column. The value is compared against the MaxCh1 Tx-RxTime setting. If the
setting is exceeded, an alarm, MaxCh1 Tx-RxTime DDB is raised.
When Current Diff is enabled and if GPS Sync is not disabled, if channel 2 is used, the absolute difference
between the Transmission and Reception propagation delay is calculated. The maximum value is displayed
MaxCh2 Tx-RxTime
in the MEASUREMENTS 4 column. The value is compared against the MaxCh2 Tx-RxTime setting. If the
setting is exceeded, an alarm, MaxCh2 Tx-RxTime DDB is raised.
This sets the time delay after which the GPS Alarm signal is asserted following a loss of GPS signal or by
GPS Fail Timer
initiation by the GPS transient fail alarm function described by the setting GPS Trans Fail.
To enable (activate) or disable (turn off) the transient GPS Fail alarm function described by the GPS Trans
GPS Trans Fail
Count and GPS Trans Timer settings.
Sets the count for the number of failed GPS signals which must be exceeded in the GPS Trans Timer setting
GPS Trans Count
window after which the GPS Fail Timer is initiated.
Sets the rolling time window in which the GPS Trans Count must be exceeded after which the GPS Fail Timer
GPS Trans Timer
is initiated.
P54-TM-EN-1.1 599
Chapter 20 - Supervision P54
The first condition would require VTS to block the voltage-dependent functions.
In the second condition, voltage dependent functions should not be blocked, as tripping is required.
To differentiate between these two conditions an overcurrent level detector is used (VTS I> Inhibit). This prevents a
VTS block from being issued in case of a genuine fault. This overcurrent level detector is only enabled for 240 ms
600 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
following line energization (based on an All Poles Dead signal drop off). It must still be set below any three-phase
fault along the line.
If the line is closed where a three-phase VT failure is present, the overcurrent detector will not operate and a VTS
block will be applied. Closing onto a three-phase fault will result in operation of the overcurrent detector and
prevent a VTS block being applied.
Thresholds
The negative sequence thresholds used by the element are:
● V2 = 10 V (fixed)
● I2 = 0.05 to 0.5 In settable (default 0.05 In).
Fuse Fail
The device includes a setting (VT Connected ) in the CT AND VT RATIOS column, which determines whether there
are voltage transformers connected to it. If set to No, this setting has no effect.
If set to No it causes the VTS logic to set the VTS Slow Block and VTS Fast Block DDBs, but not raise any alarms. It
also disables the VTS function. This prevents the pole dead logic working incorrectly if there is no voltage or
current. It also blocks the distance, under voltage and other voltage-dependant functions. However, it does not
affect the CB open part of the logic.
A VTS condition can be raised by a mini circuit breaker (MCB) status input, by internal logic using IED
measurement, or both. The setting VTS Mode is used to select the method of indicating VT failure.
P54-TM-EN-1.1 601
Chapter 20 - Supervision P54
& 1
890
All Poles Dead
IAIA
240ms
Hardcoded threshold
&
V2
MCB/VTS 438
&
VTS Status
Indication
293
Blocking 1 VT Fail Alarm
891 S
Any Pole Dead 20ms 1
240ms Q
& 0 R
895
&
VTS Acc Ind
5
Cycle 1½
½ Cycle
832 1404
VT Fail Alarm Cycle 1 VT Fail Alarm
890
&
All Poles Dead ½ V01261
Cycle
602 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
Note:
All non-distance voltage-dependent elements are blocked by the VTS Fast Block DDB.
If a miniature circuit breaker (MCB) is used to protect the voltage transformer output circuits, MCB auxiliary
contacts can be used to indicate a three-phase output disconnection. It is possible for the VTS logic to operate
correctly without this input, but this facility has been provided to maintain compatibility with some practises.
Energising an opto-isolated input assigned to the MCB/VTS provides the necessary block.
The VTS function is inhibited if:
● An All Poles Dead DDB signal is present
● Any phase overcurrent condition exists
● A Negative Phase Sequence current exists
● If the phase current changes over the period of 1 cycle
P54-TM-EN-1.1 603
Chapter 20 - Supervision P54
If the ratio is non-zero, we can assume one of two conditions are present:
● The system has an unbalanced fault (both I2 and I1 are non-zero)
● There is a 1 or 2 phase CT problem (both I2 and I1 are non-zero)
Measurement at a single end cannot provide any more information than this. However, if the ratio is calculated at
all ends and compared, the device can make a decision based on the following criteria:
● If the ratio is non-zero at more than two ends, it is almost certainly a genuine fault condition and so the CT
supervision is prevented from operating.
● If the ratio is non-zero at one end, there is a chance of either a CT problem or a single-end fed fault
condition.
A second criterion looks to see whether the differential system is loaded or not. For this purpose the device looks
at the positive sequence current I1. If load current is detected at one-end only, the device assumes that this is an
internal fault condition and prevents CTS operation. However, if load current is detected at two or more ends, this
indicates CT failure, so CTS operation is allowed.
There are two modes of operation, Indication and Restrain. You determine the mode of operation with the
CTS Status setting. In Indication mode, a CTS alarm is raised but there is no effect on tripping. In Restrain
mode, the differential protection is blocked for 20 ms after CT failure detection, then the Current Differential
threshold setting is raised above the load current.
For correct operation of the scheme, Differential CTS must be enabled at each end of the protected zone.
604 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
483
Inhib it CTS
522 &
Any Trip
487
Disable CTS
931
CT1 L i1>
1
CT1 R1 i1> 933 >
=
935
2
CT1 R2 i1>
937
CT1 L i2/i1>>
CTS S tatus CTS Time Delay
Indicat io n
939
CT1 R1 i2/ i1 >
& Pickup S
294
Q CT Fail Alarm
CT1 R2 i2/ i1 > 941 & R
1
928
CTS Reset Mode CTS S tatus & CTS B lock
&
CTS S tatus
941
CT1 R2 i2/ i1>
Restra in
930
CTS Restrain
& Picku p
CTS S tatus 1 & 929
CTS B lock Diff
Ind icat io n
1 Pickup* S
296
Q Remot e CT Alarm
& R
941
CT1 R2 i2/ i1>>
937
CT1 L i2/i1>
P54-TM-EN-1.1 605
Chapter 20 - Supervision P54
483
Inh ib it CTS
522 &
Any Trip
487
Disable CTS
931
CT1 L i1>
CT2 L i1>
932 1
CT1 R1 i1>
933 >
934 =
CT2 R1 i1>
935
2
CT1 R2 i1>
936
CT2 R2 i1>
943
CT1 L i2/i1>>
CTS S tatus CTS Time Delay
938
CT2 L i2/i1>
Ind icat ion
939
CT1 R1 i2/ i1 >
940
& Picku p S
CT2 R1 i2/ i1> 294
Q CT1 Fa il Alarm
CT1 R2 i2/ i1>
941 & R
942
CT2 R2 i2/ i1>
606 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
The voltage transformer connection used must be able to refer zero sequence voltages from the primary to the
secondary side. Therefore, this element should only be enabled where the VT is of a five-limb construction, or
comprises three single-phase units with the primary star point earthed.
The CTS function is implemented in the SUPERVISION column of the relevant settings group, under the sub-heading
CT SUPERVISION.
The following settings are relevant for CT Supervision:
● CTS Status: to disable or enable CTS
● CTS VN< Inhibit: inhibits CTS if the zero sequence voltage exceeds this setting
● CTS IN> Set: determines the level of zero sequence current
● CTS Time Delay: determines the operating time delay
& Pickup S
CTS IN> Set 294
Q CT Fail Alarm
VN * & R
CTS Status 1
Indication
Restrain
V01263
P54-TM-EN-1.1 607
Chapter 20 - Supervision P54
& Pickup S
CTS I N> Set 294
Q CT1 Fail Alarm
VN & R
CTS S tatus 1
In ind ica tion mode, t imer is set to 20 ms
Ind icat io n
Restra in
& Picku p S
CTS I N> Set 295
Q CT2 Fail Alarm
VN & R
483
Inh ib it CTS
1
487
Disab le CTS
CTS S tatus 1
In indicatio n mo de, t imer is set to 20ms
Ind icat io n
Where the magnitude of residual voltage during an earth fault is unpredictable, the element can be disabled to
prevent protection elements being blocked during fault conditions.
608 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
Note:
The minimum generated i2/i1 ratio will be 50% (case of one CT secondary phase lead being lost), and therefore a setting of
40% is considered appropriate to guarantee sufficient operating speed.
P54-TM-EN-1.1 609
Chapter 20 - Supervision P54
Note:
A 52a CB auxiliary contact follows the CB position. A 52b auxiliary contact is the opposite.
+ve
Blocking diode
52B
When the CB is closed, supervision current passes through the opto-input, blocking diode and trip coil. When the
CB is open, supervision current flows through the opto-input and into the trip coil via the 52b auxiliary contact.
This means that Trip Coil supervision is provided when the CB is either closed or open, however Trip Path
supervision is only provided when the CB is closed. No supervision of the trip path is provided whilst the CB is open
(pre-closing supervision). Any fault in the trip path will only be detected on CB closing, after a 400 ms delay.
610 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
Trip Circuit Voltage Opto Voltage Setting with R1 Fitted Resistor R1 (ohms)
110/125 48/54 2.7k
220/250 110/125 5.2k
Warning:
This Scheme is not compatible with Trip Circuit voltages of less than 48 V.
0 0
Opto Input dropoff Straight *Output Relay
400 0
50
& pickup Latching LED
0
User Alarm
The opto-input can be used to drive a Normally Closed Output Relay, which in turn can be used to drive alarm
equipment. The signal can also be inverted to drive a latching programmable LED and a user alarm DDB signal.
The DDO timer operates as soon as the opto-input is energised, but will take 400 ms to drop off/reset in the event
of a trip circuit failure. The 400 ms delay prevents a false alarm due to voltage dips caused by faults in other
circuits or during normal tripping operation when the opto-input is shorted by a self-reset trip contact. When the
timer is operated the NC (normally closed) output relay opens and the LED and user alarms are reset.
The 50 ms delay on pick-up timer prevents false LED and user alarm indications during the power up time,
following a voltage supply interruption.
+ve
52B
R1 Opto-input 1
Circuit Breaker
-ve
R2 Opto-input 2
V01215
P54-TM-EN-1.1 611
Chapter 20 - Supervision P54
When the breaker is closed, supervision current passes through opto input 1 and the trip coil. When the breaker is
open current flows through opto input 2 and the trip coil. No supervision of the trip path is provided whilst the
breaker is open. Any fault in the trip path will only be detected on CB closing, after a 400 ms delay.
Warning:
This Scheme is not compatible with Trip Circuit voltages of less than 48 V.
0 0
1 dropoff straight *Output Relay
400 0
50
& pickup Latching LED
0
User Alarm
In TCS scheme 2, both opto-inputs must be low before a trip circuit fail alarm is given.
+ve
R3
Output Relay Trip coil
Trip path 52A
R2
52B
When the CB is closed, supervision current passes through the opto-input, resistor R2 and the trip coil. When the
CB is open, current flows through the opto-input, resistors R1 and R2 (in parallel), resistor R3 and the trip coil. The
612 P54-TM-EN-1.1
P54 Chapter 20 - Supervision
supervision current is maintained through the trip path with the breaker in either state, therefore providing pre-
closing supervision.
Warning:
This Scheme is not compatible with Trip Circuit voltages of less than 48 V.
0 0
Opto Input dropoff Straight *Output Relay
400 0
50
& pickup Latching LED
0
User Alarm
P54-TM-EN-1.1 613
Chapter 20 - Supervision P54
614 P54-TM-EN-1.1
CHAPTER 21
616 P54-TM-EN-1.1
P54 Chapter 21 - Digital I/O and PSL Configuration
1 CHAPTER OVERVIEW
This chapter introduces the PSL (Programmable Scheme Logic) Editor, and describes the configuration of the digital
inputs and outputs. It provides an outline of scheme logic concepts and the PSL Editor. This is followed by details
about allocation of the digital inputs and outputs, which require the use of the PSL Editor. A separate "Settings
Application Software" document is available that gives a comprehensive description of the PSL, but enough
information is provided in this chapter to allow you to allocate the principal digital inputs and outputs.
This chapter contains the following sections:
Chapter Overview 617
Configuring Digital Inputs and Outputs 618
Scheme Logic 619
Configuring the Opto-Inputs 621
Assigning the Output Relays 622
Fixed Function LEDs 623
Configuring Programmable LEDs 624
Function Keys 626
Control Inputs 627
P54-TM-EN-1.1 617
Chapter 21 - Digital I/O and PSL Configuration P54
618 P54-TM-EN-1.1
P54 Chapter 21 - Digital I/O and PSL Configuration
3 SCHEME LOGIC
The product is supplied with pre-loaded Fixed Scheme Logic (FSL) and Programmable Scheme Logic (PSL).
The Scheme Logic is a functional module within the IED, through which all mapping of inputs to outputs is handled.
The scheme logic can be split into two parts; the Fixed Scheme Logic (FSL) and the Programmable Scheme Logic
(PSL). It is built around a concept called the digital data bus (DDB). The DDB encompasses all of the digital signals
(DDBs) which are used in the FSL and PSL. The DDBs included digital inputs, outputs, and internal signals.
The FSL is logic that has been hard-coded in the product. It is fundamental to correct interaction between various
protection and/or control elements. It is fixed and cannot be changed.
The PSL gives you a facility to develop custom schemes to suit your application if the factory-programmed default
PSL schemes do not meet your needs. Default PSL schemes are programmed before the product leaves the
factory. These default PSL schemes have been designed to suit typical applications and if these schemes suit your
requirements, you do not need to take any action. However, if you want to change the input-output mappings, or
to implement custom scheme logic, you can change these, or create new PSL schemes using the PSL editor.
The PSL consists of components such as logic gates and timers, which combine and condition DDB signals.
The logic gates can be programmed to perform a range of different logic functions. The number of inputs to a logic
gate are not limited. The timers can be used either to create a programmable delay or to condition the logic
outputs. Output contacts and programmable LEDs have dedicated conditioners.
The PSL logic is event driven. Only the part of the PSL logic that is affected by the particular input change that has
occurred is processed. This minimises the amount of processing time used by the PSL ensuring industry leading
performance.
The following diagram shows how the scheme logic interacts with the rest of the IED.
Goose inputs
V02011
P54-TM-EN-1.1 619
Chapter 21 - Digital I/O and PSL Configuration P54
Example:
Date/time: This cell displays the date and time when the PSL scheme was downloaded to the IED.
Example:
18 Nov 2002
08:59:32.047
Grp(n) PSL ID: This cell displays a unique ID number for the downloaded PSL scheme.
Example:
Grp(n) PSL ID
ID - 2062813232
620 P54-TM-EN-1.1
P54 Chapter 21 - Digital I/O and PSL Configuration
P54-TM-EN-1.1 621
Chapter 21 - Digital I/O and PSL Configuration P54
Note:
Contact Conditioners are only available if they have not all been used. In some default PSL schemes, all Contact Conditioners
might have been used. If that is the case, and you want to use them for something else, you will need to re-assign them.
On the toolbar there is another button associated with the relay outputs. The button looks like this:
This is the "Contact Signal" button. It allows you to put replica instances of a conditioned output relay into the PSL,
preventing you having to make cross-page connections which might detract from the clarity of the scheme.
622 P54-TM-EN-1.1
P54 Chapter 21 - Digital I/O and PSL Configuration
You enable the automatic self-resetting with the Sys Fn Links cell in the SYSTEM DATA column. A '0' disables self
resetting and a '1' enables self resetting.
The reset occurs when the circuit is reclosed and the Any Pole Dead signal has been reset for three seconds
providing the Any Start signal is inactive. The reset is prevented if the Any Start signal is active after the breaker
closes.
The Trip LED logic is as follows:
Any Trip S
Q Trip LED Trigger
Reset R
1
Reset Relays/LED
Sys Fn Links
Trip LED S/Reset
3s
&
Any Start
V01211
P54-TM-EN-1.1 623
Chapter 21 - Digital I/O and PSL Configuration P54
DDB signals are mapped in the PSL and used to illuminate the LEDs. For single-coloured programmable LEDs there
is one DDB signal per LED. For tri-coloured LEDs there are two DDB signals associated with the LED. Asserting LED
# Grn will illuminate the LED green. Asserting LED # Red will illuminate the LED red. Asserting both DDB signals will
illuminate the LED amber.
The illumination of an LED is controlled by means of a conditioner. Using the conditioner, you can decide whether
the LEDs reflect the real-time state of the DDB signals, or whether illumination is latched pending user intervention.
To map an LED in the PSL you should use the LED Conditioner button in the toolbar to import it. You then condition
it according to your needs. The output(s) of the conditioner respect the attribute you have assigned.
The toolbar button for a tri-colour LED looks like this:
Note:
LED Conditioners are only available if they have not all been used up, and in some default PSL schemes they might be. If that
is the case and you want to use them for something else, you will need to re-assign them.
On the toolbar there is another button associated with the LEDs. For a tri-coloured LED the button looks like this:
It is the "LED Signal" button. It allows you to put replica instances of a conditioned LED into the PSL, preventing you
having to make cross-page connections which might detract from the clarity of the scheme.
624 P54-TM-EN-1.1
P54 Chapter 21 - Digital I/O and PSL Configuration
Note:
All LED DDB signals are always shown in the PSL Editor. However, the actual number of LEDs depends on the device
hardware. For example, if a small 20TE device has only 4 programmable LEDs, LEDs 5-8 will not take effect even if they are
mapped in the PSL.
P54-TM-EN-1.1 625
Chapter 21 - Digital I/O and PSL Configuration P54
8 FUNCTION KEYS
For most models, a number of programmable function keys are available. This allows you to assign function keys
to control functionality via the programmable scheme logic (PSL). Each function key is associated with a
programmable tri-colour LED, which you can program to give the desired indication on activation of the function
key.
These function keys can be used to trigger any function that they are connected to as part of the PSL. The function
key commands are found in the FUNCTION KEYS column.
Each function key is associated with a DDB signal as shown in the DDB table. You can map these DDB signals to
any function available in the PSL.
The Fn Key Status cell displays the status (energised or de-energised) of the function keys by means of a binary
string, where each bit represents a function key starting with bit 0 for function key 1.
Each function key has three settings associated with it, as shown:
● Fn Key (n), which enables or disables the function key
● Fn Key (n) Mode, which allows you to configure the key as toggled or normal
● Fn Key (n) label, which allows you to define the function key text that is displayed
The Fn Key (n) cell is used to enable (unlock) or disable (unlock) the function key signals in PSL. The Lock setting has
been provided to prevent further activation on subsequent key presses. This allows function keys that are set to
Toggled mode and their DDB signal active ‘high’, to be locked in their active state therefore preventing any
further key presses from deactivating the associated function. Locking a function key that is set to the “Normal”
mode causes the associated DDB signals to be permanently off. This safety feature prevents any inadvertent
function key presses from activating or deactivating critical functions.
When the Fn Key (n) Mode cell is set to Toggle, the function key DDB signal output will remain in the set state
until a reset command is given. In the Normal mode, the function key DDB signal will remain energised for as long
as the function key is pressed and will then reset automatically. In this mode, a minimum pulse duration can be
programmed by adding a minimum pulse timer to the function key DDB output signal.
The Fn Key Label cell makes it possible to change the text associated with each individual function key. This text
will be displayed when a function key is accessed in the function key menu, or it can be displayed in the PSL.
The status of all function keys are recorded in non-volatile memory. In case of auxiliary supply interruption their
status will be maintained.
Note:
All function key DDB signals are always shown in the PSL Editor. However, the actual number of function keys depends on the
device hardware. For example, if a small 20TE device has no function keys, the function key DDBs mapped in the PSL will not
take effect.
626 P54-TM-EN-1.1
P54 Chapter 21 - Digital I/O and PSL Configuration
9 CONTROL INPUTS
The control inputs are software switches, which can be set or reset locally or remotely. These inputs can be used to
trigger any PSL function to which they are connected. There are three setting columns associated with the control
inputs: CONTROL INPUTS, CTRL I/P CONFIG and CTRL I/P LABELS. These are listed in the Settings and Records
appendix at the end of this manual.
P54-TM-EN-1.1 627
Chapter 21 - Digital I/O and PSL Configuration P54
628 P54-TM-EN-1.1
CHAPTER 22
FIBRE TELEPROTECTION
Chapter 22 - Fibre Teleprotection P54
630 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
1 CHAPTER OVERVIEW
This chapter provides information about the fibre-optic communication mechanism,which is used to provide unit
schemes and general-purpose teleprotection signalling for protection of transmission lines and distribution
feeders. The feature is called Fibre Teleprotection.
This chapter contains the following sections:
Chapter Overview 631
Protection Signalling Introduction 632
Fibre Teleprotection Implementation 634
IM64 Logic 645
Application Notes 647
P54-TM-EN-1.1 631
Chapter 22 - Fibre Teleprotection P54
Direct Tripping
In direct tripping applications (also known as intertripping), signals are sent directly to the master trip relay. Receipt
of the command causes circuit breaker operation. The method of communication must be reliable and secure
because any signal detected at the receiving end causes a trip of the circuit at that end. The communications
system must be designed so that interference on the communication circuit does not cause spurious trips. If a
spurious trip occurs, the primary system might be unnecessarily isolated.
Permissive Tripping
Permissive trip commands are always monitored by a protection relay. The circuit breaker is tripped when receipt
of the command coincides with a ‘start’ condition being detected by the protection relay at the receiving end
responding to a system fault. Requirements for the communications channel are less onerous than for direct
632 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
tripping schemes, since receipt of an incorrect signal must coincide with a ‘start’ of the receiving end protection for
a trip operation to take place. The intention of these schemes is to speed up tripping for faults occurring within the
protected zone.
Blocking Scheme
Blocking commands are initiated by a protection element that detects faults external to the protected zone.
Detection of an external fault at the local end of a protected circuit results in a blocking signal being transmitted to
the remote end. At the remote end, receipt of the blocking signal prevents the remote end protection operating if it
had detected the external fault. Loss of the communications channel is less serious for this scheme than in others
as loss of the channel does not result in a failure to trip when required. However, the risk of a spurious trip is higher.
Historically, pilot wires and channels (discontinuous pilot wires with isolation transformers or repeaters along the
route between signalling points) have been the most widely used due to their availability, followed by Power Line
Carrier Communications (PLCC) techniques and radio. In recent years, fibre-optic systems have become the usual
choice for new installations, primarily due to their complete immunity from electrical interference. The use of fibre-
optic cables also greatly increases the number of communication channels available for each physical fibre
connection and thus enables more comprehensive monitoring of the power system to be achieved by the
provision of a large number of communication channels.
P54-TM-EN-1.1 633
Chapter 22 - Fibre Teleprotection P54
634 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
Rx IED B Tx
Ch1 Ch2
Tx Rx
Remote 1
Tx Rx Tx Rx
Ch2 Ch1
Local Remote 2
IED A IED C
Ch1 Ch2
Rx Tx Rx Tx
V02500
Note:
In the PROT COMMS/ IM64 column, Extended IM64 mode is only available when the Comms Mode is set to either, 128
kbits/s or IEEE C37.94. When the Comms Mode is set to IEEE C37.94, Ch1 N*64 kbits/s and Ch2 N*64 kbits/s
settings are available and should be set to a minimum of 2.
Note:
A universal address (0-0) is used as default. If this is used all products use the same address ‘0-0’. This is primarily intended to
help test the product before it goes into service. We strongly recommend not to use 0-0 in service since any communications
switching or loopback condition will not be detected and may cause false tripping.
P54-TM-EN-1.1 635
Chapter 22 - Fibre Teleprotection P54
Note:
For a three-terminal scheme, the A, B, and C parts of the address group should match the figure shown earlier for a
triangulated scheme where device A has address A, device B has address B, and device C has address C.
Note:
In the PROT COMMS/ IM64 column, Extended IM64 mode is only available when the Comms Mode is set to either, 128
kbits/s or IEEE C37.94. When the Comms Mode is set to IEEE C37.94, Ch1 N*64 kbits/s and Ch2 N*64 kbits/s
settings are available and should be set to a minimum of 2.
Action of each IM64 input signal is managed by attributes defined by three settings associated with it. These are
set in the PROT COMMS/IM64 column and are of the form:
● IM 1 Cmd Type (command type)
● IM 1 FallBackMode (fallback modes)
● IM 1 DefaultValue (default values)
636 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
Note:
In the PROT COMMS/ IM64 column, Extended IM64 mode is only available when the Comms Mode is set to either, 128
kbits/s or IEEE C37.94. When the Comms Mode is set to IEEE C37.94, Ch1 N*64 kbits/s and Ch2 N*64 kbits/s
settings are available and should be set to a minimum of 2.
Note:
In the PROT COMMS/ IM64 column, Extended IM64 mode is only available when the Comms Mode is set to either, 128
kbits/s or IEEE C37.94. When the Comms Mode is set to IEEE C37.94, Ch1 N*64 kbits/s and Ch2 N*64 kbits/s
settings are available and should be set to a minimum of 2.
P54-TM-EN-1.1 637
Chapter 22 - Fibre Teleprotection P54
failure by reverting to a master-slave-slave configuration where the terminal with healthy communications with
the other terminals makes the tripping decision and sends intertrip commands to the other two. The master can
also send 8 (or 32*) IM64 teleprotection commands to the remote terminals. The same commands are sent to both
terminals .
In this IM64 application, the 8 bits (or 32 bits*) of both Logical Channels (Ch1 and Ch2) are available, Logical
Channel 1 is assigned to Physical Channel 1, and Logical Channel 2 is assigned to Physical Channel 2. To
implement a true redundancy scheme that will work correctly, the same IM64 bit assignments should be made at
all three terminals and the signals on Logical Channel 2 should be assigned identically to those on Logical Channel
1. Upon reception, the matched bits should be logically ‘OR’ed when mapped in the PSL.
In this application the command bits are packaged with the Current Differential signals. Current Differential
protection and the IM64 signalling will be maintained in the event of a single communication channel failure.
Note:
In the PROT COMMS/ IM64 column, Extended IM64 mode is only available when the Comms Mode is set to either, 128
kbits/s or IEEE C37.94. When the Comms Mode is set to IEEE C37.94, Ch1 N*64 kbits/s and Ch2 N*64 kbits/s
settings are available and should be set to a minimum of 2.
This Chain topology (normally invoked when a communication link fails) can be used to save cost in a three-
terminal scheme. This is because two legs are cheaper to install than full triangulation implementation. Also if a
suitable communication link is not available between two of the line ends, it may be the only option. If a Chain
topology is used, or one link in a fully triangulated scheme is lost, the operating delay of the teleprotection
commands increases by approximately 7 ms, plus the communications channel signalling delay, due to the
extended path length and additional processing.
638 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
Connections are made using appropriate fibre-optic cables terminated with BFOC/2.5 connectors. The transmitter
of one device (for example Tx1) is connected to the receiver of another (Rx1 or Rx2 according to the scheme set-
up)
Products can be supplied with the following fibre-optic channel arrangements:
Ch 1 Ch2
850 nm 850 nm
1300 nm multi-mode Not fitted
1300 nm multi-mode 1300 nm multi-mode
1300 nm single-mode Not fitted
1300 nm single-mode 1300 nm single-mode
1550 nm single-mode Not fitted
1550 nm single-mode 1550 nm single-mode
850 nm 1300 nm multi-mode
850 nm 1300 nm single-mode
850 nm 1550 nm single-mode
1300 nm multi-mode 850 nm
1300 nm single-mode 850 nm
1550 nm single-mode 850 nm
P54-TM-EN-1.1 639
Chapter 22 - Fibre Teleprotection P54
Note:
When the relay is set to 32bit InterMiCOM64 application mode (Extended IM64 setting Enabled), the relay is not compatible
with P592. Please contact General Electric for G.703, V.35 or X.21 electrical circuit converter.
P59x interface units are housed in 10TE wide, 4U high cases. They provide optical-electrical conversion. The optical
characteristics match those of the 850nm interface on the protection device. When used, you need one unit for
each transmitter/receiver pair. That means one unit at each end of each communications channel as
demonstrated in the figure below.
640 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
Note:
P59x interface units should be mounted as close as possible to the telecommunications equipment to minimise interference
on the electrical connections.
P54-TM-EN-1.1 641
Chapter 22 - Fibre Teleprotection P54
Note:
To use this configuration, you need to set Comms Mode to ‘IEEE C37.94’. You then need to remove the power supply from the
product and then re-apply the power. The setting is now effective. If ‘IEEE C37.94’ is used, it applies to both communication
channels.
The IEEE C37.94 standard defines an N*64 kbits/s selection, where N is a number between 1 and 12 and selects
the channel used in the multiplexer. The value of N is set on a per channel basis by setting Ch1 N*64kbits/s (and
Ch2 N*64kbits/s where applicable) to N (1 to 12). For convenience an auto-detect setting is provided, if using the
Extended IM64 mode, and therefore 128Kb/s, then a minimum of 2 slots will need to be configured. Setting to
Auto means that the device will automatically determine which multiplexer channel to use.
When P59x units are used in the communications channel of the protection scheme, the following must be set:
● Comms Mode
● Baud Rate Chn (n = 1 or 2)
● Clock Source Chn (n = 1 or 2)
You should set the Comms Mode setting to Standard or C37.94, and you should match the Baud Rate to the
channel data rate.
For V.35, you should set the Clock Source to External for a multiplexer network which is supplying a master
clock signal, or to Internal for a multiplexer network recovering signal timing from the equipment (clock
recovery). For G.703 and X.21, you always set the clock source to External.
Note:
When you are using C37.94 between the IED and the P591, you must set one of the converters as a master and the other as a
slave.
642 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
There are seven settings associated with the IM64 protection signalling communications supervision which are
listed below and described in the settings table:
● Comm Fail Timer
● Comm Fail Mode
● Channel Timeout
● IM Msg Alarm Lvl
● Prop Delay Stats
● MaxCh 1 PropDelay
● MaxCh 2 PropDelay
A communication alarm is raised if the message error rate exceeds the IM Msg Alarm Lvl setting and persists for
the period defined by the Comm Fail Timer setting. Using the default settings will raise an alarm for a persistent Bit
Error Rate (BER) of 1.5 x 10 –3.
The alarm will be apparent at the receiving device, which will reflect the alarm back to the transmitting device.
Note:
The Comm Fail Mode setting applies only to devices configured for dual redundant or three-terminal configuration. It defines
what combination of failures on the two communications channels is used to indicate an alarm.
Note:
The MaxCh1 PropDelay and MaxCh2 PropDelay settings for Channel 1 (and Channel 2 if fitted) are only visible if the Prop
Delay Stats setting is Enabled.
Note:
The comms message format is not backwards compatible if the Comms Mode is 128Kbps or IEEE C37.94 and IM64 is
configured to 32 bits (Extended IM64 set to Enabled).
P54-TM-EN-1.1 643
Chapter 22 - Fibre Teleprotection P54
Note:
All devices in a scheme must be capable of Extended IM64 operation.
The Invalid Mesg Fmt alarm and the IM64 SchemeFail alarm will activate if the received comms message is not of
the correct format and data rate.
Once the new comms configuration has been set, an alarm Comms Changed will be active to prompt the user to
reboot the relay. Once rebooted, the changed comms configuration will be active.
644 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
4 IM64 LOGIC
Channel Timeout
t
No Received Messages Ch 1 Ch1 Timeout
0 t
1
Poor Channel Quality Ch 1 0 1 Signalling Fail
Ch1 Degraded
Channel Timeout
1
Scheme Setup &
3 terminal
&
V02502
Loopback Mode
Internal
1 Test Loopback
External
Scheme Setup
3 terminal
& Ch2 Passthrough
Channel 2 IM64 Bits
received from channel 1
V02503
P54-TM-EN-1.1 645
Chapter 22 - Fibre Teleprotection P54
Message Evaluation
message (IEEE C37.94) Ch1 Signal Lost
Message Info
Channel 1
Error in Transit
Ch1 Path Yellow
Message Info
Comms Mode
IEEE C37.94 Channel Mismatch Ch1 Mismatch RxN
1 IEEE C37.94
Error in Receive
Message Evaluation
Ch2 Signal Lost
Message Info
Channel 1
Error in Transit
Ch2 Path Yellow
Message Info
Channel 2 Communication Channel Mismatch Ch2 Mismatch RxN
message (IEEE C37.94)
Comms Mode
Standard S
Q
IEEE C37.94 RD
& Comms Changed
S
Q
RD
Relay Power Up
Figure 396: IM64 communications mode and IEEE C37.94 alarm signals
646 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
5 APPLICATION NOTES
Effective communications are essential for the performance of teleprotection schemes. Disturbances on the
communications links need to be detected and reported so that appropriate actions can be taken to ensure that
the power system does not go unprotected.
P54-TM-EN-1.1 647
Chapter 22 - Fibre Teleprotection P54
Opto 1
Control Input 1
Non-
Signalling Fail & Latching
LED 8
V02505
In this example scheme, several signals are used to permanently pass an IM64 signal to the remote terminal.
These signals take account of the local ability to receive IM64 messages, local test/loopback modes and any other
external methods of switching the signalling scheme out of service. If any of these driving signals are energised,
the IM64 message is reset (a “0” sent on IM64 bit 8--or bit 32 if Extended IM64 mode is Enabled). This causes
both ends to raise an alarm (LED 8 in the example) or switch the aided scheme out of service due to loss of
channel.
This is intended only as an example. You may need to customise it for your application requirements.
Opto 1
Control Input 1
Non-
Signalling Fail & Latching
LED 8
V02506
In this example if both channels at any one terminal fail to receive information, this is communicated to the other
terminals. An alarm is raised and the aided scheme is switched out of service. The example given above, also takes
into account the test modes and local switching, so the scheme is signalled out of service at all terminals if one
terminal is locally disabled.
648 P54-TM-EN-1.1
P54 Chapter 22 - Fibre Teleprotection
The logic presented above is intended only as an example. You may need to customise it for your application
requirements.
P54-TM-EN-1.1 649
Chapter 22 - Fibre Teleprotection P54
650 P54-TM-EN-1.1
CHAPTER 23
ELECTRICAL TELEPROTECTION
Chapter 23 - Electrical Teleprotection P54
652 P54-TM-EN-1.1
P54 Chapter 23 - Electrical Teleprotection
1 CHAPTER OVERVIEW
This chapter contains the following sections:
Chapter Overview 653
Introduction 654
Teleprotection Scheme Principles 655
Implementation 656
Configuration 657
Connecting to Electrical InterMiCOM 659
Application Notes 660
P54-TM-EN-1.1 653
Chapter 23 - Electrical Teleprotection P54
2 INTRODUCTION
Electrical Teleprotection is an optional feature that uses communications links to create protection schemes. It can
be used to replace hard wiring between dedicated relay output contacts and digital input circuits. Two products
equipped with electrical teleprotection can connect and exchange commands using a communication link. It is
typically used to implement teleprotection schemes.
Using full duplex communications, eight binary command signals can be sent in each direction between
connected products. The communication connection complies with the EIA(RS)232 standard. Ports may be
connected directly, or using modems. Alternatively EIA(RS)232 converters can be used for connecting to other
media such as optical fibres.
Communications statistics and diagnostics enable you to monitor the integrity of the communications link, and a
loopback feature is available to help with testing.
654 P54-TM-EN-1.1
P54 Chapter 23 - Electrical Teleprotection
P54-TM-EN-1.1 655
Chapter 23 - Electrical Teleprotection P54
4 IMPLEMENTATION
Electrical InterMiCOM is configured using a combination of settings in the INTERMICOM COMMS column, settings in
the INTERMICOM CONF column, and the programmable scheme logic (PSL).
The eight command signals are mapped to DDB signals within the product using the PSL.
Signals being sent to a remote terminal are referenced in the PSL as IM Output 1 - IM Output 8. Signals received
from the remote terminal are referenced as IM Input 1 - IM Input 8.
Note:
As well as the optional Modem InterMiCOM, some products are available with a feature called InterMiCOM64 (IM64). The
functionality and assignment of commands in InterMiCOM and InterMiCOM64 are similar, but they act independently and are
configured independently.
656 P54-TM-EN-1.1
P54 Chapter 23 - Electrical Teleprotection
5 CONFIGURATION
Electrical Teleprotection is compliant with IEC 60834-1:1999. For your application, you can customise individual
command signals to the differing requirements of security, speed, and dependability as defined in this standard.
You customise the command signals using the IM# Cmd Type cell in the INTERMICOM CONF column.
Any command signal can be configured for:
● Direct intertripping by selecting ‘Direct’. (this is the most secure signalling but incurs a time delay to deliver
the security).
● Blocking applications by selecting ‘Blocking’. (this is the fastest signalling)
● Permissive intertripping applications by selecting ‘Permissive. (this is dependable signalling that balances
speed and security)
Note:
When used in the context of a setting, ‘#’ specifies which command signal (1-8) bit is being configured.
To ensure that command signals are processed only by their intended recipient, the command signals are
packaged into a message (sometimes referred to as a telegram) which contains an address field. A sending device
sets a pattern in this field. A receiving device must be set to match this pattern in the address field before the
commands will be acted upon. 10 patterns have been carefully chosen for maximum security. You need to choose
which ones to use, and set them using the Source Address and Receive Address cells in the INTERMICOM COMMS
column.
The value set in the Source Address of the transmitting device should match that set in the Receive Address of the
receiving device. For example set Source Address to 1 at a local terminal and set Receive Address to 1 at the
remote terminal.
The Source Address and Receive Address settings in the device should be set to different values to avoid false
operation under inadvertent loopback conditions.
Where more than one pair of devices is likely to share a communication link, you should set each pair to use a
different pair of address values.
Electrical InterMiCOM has been designed to be resilient to noise on communications links, but during severe noise
conditions, the communication may fail. If this is the case, an alarm is raised and you can choose how the input
signals are managed using the IM# FallBackMode cell in the INTERMICOM CONF column:
• If you choose Latched, the last valid command to be received can be maintained until a new valid message is
received.
• If you choose Default, the signal will revert to a default value after the period defined in the IM#
FrameSyncTim setting has expired. You choose the default value using the IM# DefaultValue setting.
Subsequent receipt of a full valid message will reset the alarm, and the new command signals will be used.
As well as the settings described above, you will need to assign input and output signals in the Programmable
Scheme Logic (PSL). Use the ‘Integral Tripping’ buttons to create the logic you want to apply. A typical example is
shown below.
P54-TM-EN-1.1 657
Chapter 23 - Electrical Teleprotection P54
E002521
Note:
When an Electrical InterMiCOM signal is sent from a local terminal, only the remote terminal will react to the command. The
local terminal will only react to commands initiated at the remote terminal.
658 P54-TM-EN-1.1
P54 Chapter 23 - Electrical Teleprotection
IED IED
DCD 1 1 DCD
RxD 2 2 RxD
TxD 3 3 TxD
DTR 4 4 DTR
GND 5 5 GND
6 6
RTS 7 7 RTS
8 8
9 9
E02522
For direct connection, the maximum baud rate can generally be used.
E02523
This type of connection should be used when connecting to devices that have the ability to control the DCD line.
The baud rate should be chosen to be suitable for the communications network. If the Modem does not support
the DCD function, the DCD terminal on the IED should be connected to the DTR terminal.
P54-TM-EN-1.1 659
Chapter 23 - Electrical Teleprotection P54
7 APPLICATION NOTES
Electrical InterMiCOM settings are contained within two columns; INTERMICOM COMMS and INTERMICOM CONF.
The INTERMICOM COMMS column contains all the settings needed to configure the communications, as well as the
channel statistics and diagnostic facilities. The INTERMICOM CONF column sets the mode of each command signal
and defines how they operate in case of signalling failure.
Short metallic direct connections and connections using fire-optic converters will generally be set to have the
highest signalling speed of 19200b/s. Due to this high signalling rate, the difference in operating time between the
direct, permissive, and blocking type signals is small. This means you can select the most secure signalling
command type (‘Direct’ intertrip) for all commands. You do this with the IM# Cmd Type settings. For these
applications you should set the IM# Fallback Mode to Default. You should also set a minimal intentional delay
by setting IM# FrameSyncTim to 10 msecs. This ensures that whenever two consecutive corrupt messages are
received, the command will immediately revert to the default value until a new valid message is received.
For applications that use Modem and/or multiplexed connections, the trade-off between speed, security, and
dependability is more critical. Choosing the fastest baud rate (data rate) to achieve maximum speed may appear
attractive, but this is likely to increase the cost of the telecommunications equipment. Also, telecommunication
services operating at high data rates are more prone to interference and suffer from longer re-synchronisation
times following periods of disruption. Taking into account these factors we recommend a maximum baud rate
setting of 9600 bps. As baud rates decrease, communications become more robust with fewer interruptions, but
overall signalling times increase.
At slower baud rates, the choice of signalling mode becomes significant. You should also consider what happens
during periods of noise when message structure and content can be lost.
● In ‘Blocking’ mode, the likelihood of receiving a command in a noisy environment is high. In this case, we
recommend you set IM# Fallback Mode to Default, with a reasonably long IM# FrameSyncTim setting.
Set IM# DefaultValue to ‘1’. This provides a substitute for a received blocking signal, applying a failsafe for
blocking schemes.
● In ‘Direct’ mode, the likelihood of receiving commands in a noisy environment is small. In this case, we
recommend you set IM# Fallback Mode to Default with a short IM# FrameSyncTim setting. Set IM#
DefaultValue to ‘0’. This means that if a corrupt message is received, InterMiCOM will use the default value.
This provides a substitute for the intertrip signal not being received, applying a failsafe for direct
intertripping schemes.
● In ‘Permissive’ mode, the likelihood of receiving a valid command under noisy communications conditions is
somwhere between that of the ‘Blocking’ mode and the ‘Direct’ intertrip mode. In this case, we
recommended you set IM# Fallback Mode to Latched.
The table below presents recommended IM# FrameSyncTim settings for the different signalling modes and baud
rates:
Minimum Recommended "IM# FrameSyncTim" Setting
Minimum Setting Maximum Setting
Baud Rate Direct Intertrip Mode Blocking Mode
(ms) (ms)
600 100 250 100 1500
1200 50 130 50 1500
2400 30 70 30 1500
4800 20 40 20 1500
9600 10 20 10 1500
19200 10 10 10 1500
660 P54-TM-EN-1.1
P54 Chapter 23 - Electrical Teleprotection
Note:
As we have recommended Latched operation, the table does not contain recommendations for ‘Permissive’ mode. However, if
you do select ‘Default’ mode, you should set IM# FrameSyncTim greater than those listed above. If you set IM#
FrameSyncTim lower than the minimum setting listed above, the device could interpret a valid change in a message as a
corrupted message.
P54-TM-EN-1.1 661
Chapter 23 - Electrical Teleprotection P54
662 P54-TM-EN-1.1
CHAPTER 24
COMMUNICATIONS
Chapter 24 - Communications P54
664 P54-TM-EN-1.1
P54 Chapter 24 - Communications
1 CHAPTER OVERVIEW
This product supports Substation Automation System (SAS), and Supervisory Control and Data Acquisition (SCADA)
communication through multiple interfaces and a choice of data protocols.
All products support rugged serial communications for SCADA and SAS applications. Optionally, any product can
support Ethernet communications for IEC 61850, cyber security and remote access, either through a single port or
industry-standard redundant ports.
This chapter contains the following sections:
Chapter Overview 665
Communication Interfaces 666
Serial Communication 667
Ethernet Board Versions 670
Board Connections 671
Configuring IP Addresses 672
Redundant Ethernet Configurator 674
Redundant Ethernet Communication 680
Redundancy Protocols 681
General Functions for Redundant Ethernet Boards 687
Simple Network Time Protocol (SNTP) 693
Data Protocols 694
Read Only Mode 720
Time Synchronisation 722
P54-TM-EN-1.1 665
Chapter 24 - Communications P54
2 COMMUNICATION INTERFACES
The products have a number of standard and optional communication interfaces. The standard and optional
hardware and protocols are summarised below:
Port Availability Physical lnterface Use Data Protocols
Front Standard USB Type B Local settings Courier
Rear Port 1 SCADA Courier, IEC60870-5-103, DNP3.0
Standard RS232 / RS485 / K-Bus
(RP1 copper) Remote settings (order option)
Rear Port 1 SCADA Courier, IEC60870-5-103, DNP3.0
Optional Fibre
(RP1 fibre) Remote settings (order option)
Rear Port 2 SCADA SK4: Courier only
Optional RS232 / RS485 / K-Bus
(RP2) Remote settings SK5: InterMiCOM only
IEC 61850
Ethernet Optional Ethernet IEC 61850, Courier (tunnelled)
Remote settings
Note:
Optional communications boards are always fitted into slot A. It is only possible to fit one optional communications board,
therefore RP2 and Ethernet communications are mutually exclusive.
Note:
On RP1, any one of the data protocols can be selected at one time, from the COMMUNICATIONS Menu (it is no longer
necessary to select one as a product order option).
666 P54-TM-EN-1.1
P54 Chapter 24 - Communications
3 SERIAL COMMUNICATION
The physical layer standards that are used for serial communications for SCADA purposes are:
● EIA(RS)485 (often abbreviated to RS485)
● K-Bus (a proprietary customization of RS485)
USB is used for local communication with the IED (for transferring settings and downloading firmware updates).
RS485 is similar to RS232 but for longer distances and it allows daisy-chaining and multi-dropping of IEDs.
K-Bus is a proprietary protocol quite similar to RS485, but it cannot be mixed on the same link as RS485. Unlike
RS485, K-Bus signals applied across two terminals are not polarised.
It is important to note that these are not data protocols. They only describe the physical characteristics required
for two devices to communicate with each other.
For a description of the K-Bus standard see K-Bus and General Electric's K-Bus interface guide reference R6509.
A full description of the RS485 is available in the published standard.
P54-TM-EN-1.1 667
Chapter 24 - Communications P54
Note:
Some devices may be able to provide the bus bias, in which case external components would not be required.
6 – 9 V DC
180 Ω bias
Master 120 Ω
180 Ω bias
0V 120 Ω
V01000
Warning:
It is extremely important that the 120 Ω termination resistors are fitted. Otherwise
the bias voltage may be excessive and may damage the devices connected to the
bus.
3.3 K-BUS
K-Bus is a robust signalling method based on RS485 voltage levels. K-Bus incorporates message framing, based on
a 64 kbps synchronous HDLC protocol with FM0 modulation to increase speed and security.
The rear interface is used to provide a permanent connection for K-Bus, which allows multi-drop connection.
A K-Bus spur consists of up to 32 IEDs connected together in a multi-drop arrangement using twisted pair wiring.
The K-Bus twisted pair connection is non-polarised.
It is not possible to use a standard EIA(RS)232 to EIA(RS)485 converter to convert IEC 60870-5 FT1.2 frames to K-
Bus. A protocol converter, namely the KITZ101 or KITZ102, must be used for this purpose. Please consult General
Electric for information regarding the specification and supply of KITZ devices. The following figure demonstrates a
typical K-Bus connection.
668 P54-TM-EN-1.1
P54 Chapter 24 - Communications
C C C
RS232 K-Bus
Note:
An RS232-USB converter is only needed if the local computer does not provide an RS232 port.
Further information about K-Bus is available in the publication R6509: K-Bus Interface Guide, which is available on
request.
P54-TM-EN-1.1 669
Chapter 24 - Communications P54
Board variants
Board Part No. Compatible With
Redundant Ethernet PRP/HSR/RSTP/Failover, 2 multi-mode fibre ports + Any PRP, HSR, RSTP or standard
ZN0087 001
Modulated/Un-Modulated IRIG-B Ethernet network.
Redundant Ethernet PRP/HSR/RSTP/Failover, 2 copper ports RJ45 + Any PRP, HSR, RSTP or standard
ZN0087 002
Modulated/Un-Modulated IRIG-B Ethernet network.
Redundant Ethernet PRP/HSR/RSTP/Failover, 1 copper port RJ45 + 1 multi-mode Any PRP, HSR, RSTP or standard
ZN0087 003
fibre port + Modulated/Un-Modulated IRIG-B Ethernet network.
When using any of the redundant Ethernet boards on an IED the final product will have two MAC addresses and
will require two IP addresses, one for the managed embedded switch that handles the redundancy and one for the
IED that handles the communications at protocol level and to S1 Agile. The MAC address of the embedded switch
is printed on the board. The MAC address of the IED is printed on the rear panel of the IED. The redundant Ethernet
board is fitted into Slot A of the IED, which is the optional communications slot.
All Ethernet connections are made with 1300 nm multi mode 100BaseFx fiber optic Ethernet ports (ST® connector).
The boards support IEC 61850 over Ethernet.
670 P54-TM-EN-1.1
P54 Chapter 24 - Communications
5 BOARD CONNECTIONS
IRIG-B Connector
● Centre connection: Signal
● Outer connection: Earth
LEDs
LED Function On Off Flashing
Green Link Link ok Link broken
Yellow Activity Running PRP, RSTP traffic
P54-TM-EN-1.1 671
Chapter 24 - Communications P54
6 CONFIGURING IP ADDRESSES
An IP address is a logical address assigned to devices in a computer network that uses the Internet Protocol (IP) for
communication between nodes. IP addresses are stored as binary numbers but they are represented using
Decimal Dot Notation, where four sets of decimal numbers are separated by dots as follows:
XXX.XXX.XXX.XXX
For example:
10.86.254.85
An IP address in a network is usually associated with a subnet mask. The subnet mask defines which network the
device belongs to. A subnet mask has the same form as an IP address.
For example:
255.255.255.0
Both the IED and the REB each have their own IP address. The following diagram shows the IED as IP1 and the REB
as IP2.
Note:
IP1 and IP2 are different but use the same subnet mask.
The REB IP address (IP2) must be configured through the Ethernet network.
PRP/HSR/RSTP/Failover
From S1 Agile 2.0.1. onwards cards that support the PRP/HSR/RSTP/Failover protocols in any of the combinations
are configured using the Redundant Ethernet Configurator software tool. If you are using a ZN008700X card only
this tool supports it. If using S1 Agile 1.4.2 or older you will need to use the PRP/HSR Configurator for PRP and/or
HSR, and the RSTP Configurator for RSTP cards.
672 P54-TM-EN-1.1
P54 Chapter 24 - Communications
P54-TM-EN-1.1 673
Chapter 24 - Communications P54
RJ45
Ethernet switch
Media
Converter
TXA RXA TXB RXB
TX RX
IED IED
(a) (b)
V01806
Figure 406: Connection using (a) an Ethernet switch and (b) a media converter
674 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Select the device you wish to configure. The MAC address of the selected device is highlighted.
P54-TM-EN-1.1 675
Chapter 24 - Communications P54
676 P54-TM-EN-1.1
P54 Chapter 24 - Communications
● Proxy Node Table Max Entries: This is the maximum number of entries in the ProxyTable
● Entry Forget Time: This is the time after which an entry is removed from the duplicates
● Node Reboot Interval: This is the minimum time during which a node that reboots remains silent
Note:
When assigning the bridge priority, make sure the root of the network is the Ethernet switch, not the IEDs. This reduces the
number of hops to reach all devices in the network. Also make sure the priority values for all IEDs are higher than that of the
switch.
P54-TM-EN-1.1 677
Chapter 24 - Communications P54
General tab
The Filtering Database contains two types of entry; static and dynamic. The Static Entries are the source addresses
entered by an administrator. The Dynamic Entries are the source addresses learnt by the switch process. The
Dynamic Entries are removed from the Filtering Database after the Ageing Time. The Database holds a maximum
of 1024 entries.
1. To access the forwarding database functions, if required, click the Filtering Database button in the main
window
2. To view the Forwarding Database Size, Number of Static Entries and Number of Dynamic Entries, click Read
Database Info
3. To set the Ageing Time, enter the number of seconds in the text box and click the Set button
678 P54-TM-EN-1.1
P54 Chapter 24 - Communications
To delete an entry from the forwarding database, select the entry and click the Delete Entry button
P54-TM-EN-1.1 679
Chapter 24 - Communications P54
680 P54-TM-EN-1.1
P54 Chapter 24 - Communications
9 REDUNDANCY PROTOCOLS
REB variants for each of the following protocols are available:
● PRP (Parallel Redundancy Protocol)
● HSR (High-availability Seamless Redundancy)
● RSTP (Rapid Spanning Tree Protocol)
● Failover
PRP and HSR are open standards, so their implementation is compatible with any standard PRP or HSR device
respectively. PRP provides "bumpless" redundancy. RSTP is also an open standard, so its implementation is
compatible with any standard RSTP devices. RSTP provides redundancy, however, it is not "bumpless".
P54-TM-EN-1.1 681
Chapter 24 - Communications P54
DAN DAN
SAN DAN
LAN B
LAN A
REDUNDANCY
BOX
VDAN
VDAN
E01028
In a DAN, both ports share the same MAC address so it does not affect the way devices talk to each other in an
Ethernet network (Address Resolution Protocol at layer 2). Every data frame is seen by both ports.
When a DAN sends a frame of data, the frame is duplicated on both ports and therefore on both LAN segments.
This provides a redundant path for the data frame if one of the segments fails. Under normal conditions, both LAN
segments are working and each port receives identical frames. There are two ways of handling this: Duplicate
Accept and Duplicate Discard.
The General Electric RedBox is the H382 switch. This is compatible with any other vendor's PRP device.
682 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Source
Singly Attached
Nodes
Only about half of the network bandwidth is available in HSR for multicast or broadcast frames because both
duplicate frames A & B circulate the full ring.
P54-TM-EN-1.1 683
Chapter 24 - Communications P54
Source
C frame
A frame B frame
Singly Attached
Nodes
D frame
Destination V01031
For unicast frames, the whole bandwidth is available as both frames A & B stop at the destination node.
684 P54-TM-EN-1.1
P54 Chapter 24 - Communications
T1000 switch
LINK
RX
PC SCADA
TX
reset LINK
RX
TX
DS Agile gateways
P54-TM-EN-1.1 685
Chapter 24 - Communications P54
The RSTP solution is based on open standards. It is therefore compatible with other Manufacturers’ IEDs that use
the RSTP protocol. The RSTP recovery time is typically 300 ms but it increases with network size, therefore cannot
achieve the desired bumpless redundancy.
To ensure optimal performance of the protocol, make sure that one of the Ethernet switches is always the root of
the RSTP topology.
9.4 FAILOVER
Failover is a simple redundancy mechanism that is not tied to any protocol. It works by selecting a main port and a
switching time that can be as low as 2 seconds. When the main port link fails, the redundant port becomes
physically active. At no point are both ports physically active, which means it can be used on any redundant or
non-redundant network.
686 P54-TM-EN-1.1
P54 Chapter 24 - Communications
10.1 FORWARDING
The MiCOM Ethernet switch products support store and forward mode. The switch forwards messages with known
addresses to the appropriate port. The messages with unknown addresses, the broadcast messages and the
multicast messages are forwarded out to all ports except the source port. MiCOM switches do not forward error
packets, 802.3x pause frames, or local packets. 802.1p priority tagging is enabled on all ports.
The following figure shows the structure of the SNMP MIB tree. There are no limits on the width and depth of the
MIB tree.
P54-TM-EN-1.1 687
Chapter 24 - Communications P54
iso = 1
org = 3
dod = 6
internet = 1
mgmt = 2 private = 4
mib-2 = 1 enterprises = 1
sysDescr = 1
E01033
The top four levels of the hierarchy are fixed. These are:
● International Standards Organization (iso)
● Organization (org)
● Department of Defence (dod)
● Internet
Management (mgmt) is the main public branch. It defines network management parameters common to devices
from all vendors. Underneath the Management branch is MIB-II (mib-2), and beneath this are branches for
common management functions such as system management, printers, host resources, and interfaces.
The private branch of the MIB tree contains branches for large organizations, organized under the enterprises
branch. This is not applicable to General Electric.
Address Name
0 CCITT
1 ISO
3 Org
6 DOD
688 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Address Name
1 Internet
2 mgmt
1 Mib-2
1 sys
1 sysDescr
3 sysUpTime
4 sysName
Remote Monitoring
16 RMON
1 statistics
1 etherstat
1 etherStatsEntry
9 etherStatsUndersizePkts
10 etherStatsOversizePkts
12 etherStatsJabbers
13 etherStatsCollisions
14 etherStatsPkts64Octets
15 etherStatsPkts65to127Octets
16 etherStatsPkts128to255Octets
17 etherStatsPkts256to511Octets
18 etherStatsPkts512to1023Octets
Various SNMP client software tools can be used. We recommend using an SNMP MIB browser, which can perform
the basic SNMP operations such as GET, GETNEXT and RESPONSE.
Note:
When communicating with the Redundant Ethernet Card, there are two IP addresses visible: one for the IED and one for the
Ethernet switch on the redundant Ethernet board. To access the network using SNMP, use the IP address of the redundant
Ethernet board switch and not that of the IED. See the Configuration chapter for further information.
P54-TM-EN-1.1 689
Chapter 24 - Communications P54
Address Name
1 lreInterfaceConfigTable
1 lreInterfaceConfigEntry
1 lreInterfaceConfigIndex
2 lreRowStatus
3 lreNodeType
4 lreNodeName
5 lreVersionName
6 lreMacAddressA
7 lreMacAddressB
8 lreAdapterAdminStateA
9 lreAdapterAdminStateB
10 lreLinkStatusA
11 lreLinkStatusB
12 lreDuplicateDiscard
13 lreTransparentReception
14 lreHsrLREMode
15 lreSwitchingEndNode
16 lreRedBoxIdentity
17 lreSanA
18 lreSanB
19 lreEvaluateSupervision
20 lreNodesTableClear
21 lreProxyNodeTableClear
1 lreStatistics
1 lreStatisticsInterfaceGroup
0 lreStatisticsInterfaces
1 lreInterfaceStatsTable
1 lreInterfaceStatsIndex
2 lreCntTotalSentA
3 lreCntTotalSentB
4 lreCntErrWrongLANA
5 lreCntErrWrongLANB
6 lreCntReceivedA
7 lreCntReceivedB
8 lreCntErrorsA
9 lreCntErrorsB
10 lreCntNodes
11 IreOwnRxCntA
12 IreOwnRxCntB
3 lreProxyNodeTable
1 lreProxyNodeEntry
1 reProxyNodeIndex
2 reProxyNodeMacAddress
690 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Address Name
3 Org
6 Dod
1 Internet
2 mgmt
1 mib-2
1 System
1 sysDescr
3 sysUpTime
5 sysName
7 sysServices
2 interfaces
2 ifTable
1 ifEntry
1 ifIndex
2 ifDescr
3 ifType
4 ifMtu
5 ifSpeed
6 ifPhysAddress
7 ifAdminStatus
8 ifOpenStatus
9 ifLastChange
10 ifInOctets
11 ifInUcastPkts
12 ifInNUcastPkts
13 ifInDiscards
14 ifInErrors
15 ifInUnknownProtos
16 ifOutOctets
17 ifOutUcastPkts
18 ifOutNUcastPkts
19 ifOutDiscards
20 ifOutErrors
21 ifOutQLen
22 ifSpecific
16 rmon
1 statistics
1 etherStatsTable
1 etherStatsEntry
1 etherStatsIndex
2 etherStatsDataSource
3 etherStatsDropEvents
4 etherStatsOctets
P54-TM-EN-1.1 691
Chapter 24 - Communications P54
Address Name
5 etherStatsPkts
6 etherStatsBroadcastPkts
7 etherStatsMulticastPkts
8 etherStatsCRCAlignErrors
9 etherStatsUndersizePkts
10 etherStatsOversizePkts
11 etherStatsFragments
12 etherStatsJabbers
13 etherStatsCollisions
14 etherStatsPkts64Octets
15 etherStatsPkts65to127Octets
16 etherStatsPkts128to255Octets
17 etherStatsPkts256to511Octets
18 etherStatsPkts512to1023Octets
19 etherStatsPkts1024to1518Octets
20 etherStatsOwner
21 etherStatsStatus
Various SNMP client software tools can be used. General Electric recommends using an SNMP MIB browser, which
can perform the basic SNMP operations such as GET, GETNEXT and RESPONSE.
Note:
When communicating with the Redundant Ethernet Card, there are two IP addresses visible: one for the IED and one for the
Ethernet switch on the redundant Ethernet board. To access the network using SNMP, use the IP address of the redundant
Ethernet board switch and not that of the IED. See the Configuration chapter for further information.
692 P54-TM-EN-1.1
P54 Chapter 24 - Communications
P54-TM-EN-1.1 693
Chapter 24 - Communications P54
12 DATA PROTOCOLS
The products support a wide range of protocols to make them applicable to many industries and applications. The
exact data protocols supported by a particular product depend on its chosen application, but the following table
gives a list of the data protocols that are typically available.
DATA PROTOCOLS
Data Protocol Layer 1 Interface Description
Standard for SCADA communications developed by General
Courier USB, K-Bus, RS232, RS485, Ethernet
Electric.
The relationship of these protocols to the lower level physical layer protocols are as follows:
IEC 60870-5-103
Data Protocols DNP3.0 IEC 61850
Courier Courier Courier Courier Courier
Data Link Layer EIA(RS)485 Ethernet EIA(RS)232 K-Bus USB
Physical Layer Copper or Optical Fibre USB Type B
The product supports switchable serial communication data protocol on the Rear Port 1 (RP1) interface (it is no
longer necessary to select the protocol as a product order option). This setting cell is RP1 Protocol in the
COMMUNICATIONS column. For example, the product can now be configured to provide IEC 61850 on the Ethernet
interface and DNP3.0 on the serial port concurrently.
12.1 COURIER
This section should provide sufficient detail to enable understanding of the Courier protocol at a level required by
most users. For situations where the level of information contained in this manual is insufficient, further
publications (R6511 and R6512) containing in-depth details about the protocol and its use, are available on
request.
Courier is a General Electric proprietary communication protocol. Courier uses a standard set of commands to
access a database of settings and data in the IED. This allows a master to communicate with a number of slave
devices. The application-specific elements are contained in the database rather than in the commands used to
interrogate it, meaning that the master station does not need to be preconfigured. Courier also provides a
sequence of event (SOE) and disturbance record extraction mechanism.
694 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Optional Ethernet board (NIC) - for remote communication with the S1 Agile settings application software across
an Ethernet network.
For either of the serial rear ports, both the IED address and baud rate can be selected using the front panel menu
or by the settings application software.
Note:
Changing the RP2 Port Config setting (K-Bus, EIA(RS)232) requires the IED to be rebooted, for the change to become effective.
With the exception of the Disturbance Recorder settings, changes made to the control and support settings are
implemented immediately and stored in non-volatile memory. Changes made to the Protection settings and the
Disturbance Recorder settings are stored in ‘scratchpad’ memory and are not immediately implemented. These
need to be committed by writing to the Save Changes cell in the CONFIGURATION column.
Method 1
This uses a combination of three commands to perform a settings change:
First, enter Setting mode: This checks that the cell is settable and returns the limits.
1. Preload Setting: This places a new value into the cell. This value is echoed to ensure that setting corruption
has not taken place. The validity of the setting is not checked by this action.
2. Execute Setting: This confirms the setting change. If the change is valid, a positive response is returned. If
the setting change fails, an error response is returned.
3. Abort Setting: This command can be used to abandon the setting change.
This is the most secure method. It is ideally suited to on-line editors because the setting limits are extracted before
the setting change is made. However, this method can be slow if many settings are being changed because three
commands are required for each change.
Method 2
The Set Value command can be used to change a setting directly. The response to this command is either a
positive confirm or an error code to indicate the nature of a failure. This command can be used to implement a
setting more rapidly than the previous method, however the limits are not extracted. This method is therefore most
suitable for off-line setting editors such as MiCOM S1 Agile, or for issuing preconfigured control commands.
P54-TM-EN-1.1 695
Chapter 24 - Communications P54
Event Types
The IED generates events under certain circumstances such as:
● Change of state of output contact
● Change of state of opto-input
● Protection element operation
● Alarm condition
● Setting change
● Password entered/timed-out
696 P54-TM-EN-1.1
P54 Chapter 24 - Communications
The Menu Database contains tables of possible events, and shows how the contents of the above fields are
interpreted. Fault and Maintenance records return a Courier Type 3 event, which contains the above fields plus two
additional fields:
● Event extraction column
● Event number
These events contain additional information, which is extracted from the IED using column B4. Row 01 contains a
Select Record setting that allows the fault or maintenance record to be selected. This setting should be set to the
event number value returned in the record. The extended data can be extracted from the IED by uploading the text
and data from the column.
The PSL settings can be uploaded and downloaded to and from the IED using this mechanism. The settings
application software must be used to edit the settings. It also performs checks on the validity of the settings before
they are transferred to the IED.
P54-TM-EN-1.1 697
Chapter 24 - Communications P54
synchronization Courier event will be generated/produced whether the time-synchronization message is sent as a
global command or to any individual IED address.
If the clock is being synchronized using the IRIG-B input then it will not be possible to set the device time using the
Courier interface. An attempt to set the time using the interface will cause the device to create an event with the
current date and time taken from the IRIG-B synchronized internal clock.
698 P54-TM-EN-1.1
P54 Chapter 24 - Communications
● General interrogation
● Cyclic measurements
● General commands
● Disturbance record extraction
● Private codes
If the optional fibre optic port is fitted, a menu item appears in which the active port can be selected. However, the
selection is only effective following the next power up.
The IED address and baud rate can be selected using the front panel menu or by the settings application software.
12.2.2 INITIALISATION
Whenever the device has been powered up, or if the communication parameters have been changed a reset
command is required to initialize the communications. The device will respond to either of the two reset
commands; Reset CU or Reset FCB (Communication Unit or Frame Count Bit). The difference between the two
commands is that the Reset CU command will clear any unsent messages in the transmit buffer, whereas the
Reset FCB command does not delete any messages.
The device will respond to the reset command with an identification message ASDU 5. The Cause of Transmission
(COT) of this response will be either Reset CU or Reset FCB depending on the nature of the reset command. The
content of ASDU 5 is described in the IEC 60870-5-103 section of the Menu Database, available from General
Electric separately if required.
In addition to the above identification message, it will also produce a power up event.
P54-TM-EN-1.1 699
Chapter 24 - Communications P54
Setting: Description:
In this mode, the IED behaviour for IEC 60870-5-103 protocol is identical to pre-Software Version 91 IEDs.
All the implemented signals (IEC 60870-5-103 compatible range and private range signals) are enabled for
Fixed
IEC 60870-5-103 communication. The COT behaviour will be according to the device IEC 60870-5-103 profile.
This mode is provided for backward compatibility. This is the default setting.
In this mode, the user can select which IEC 60870-5-103 private range signals are enabled for IEC
60870-5-103 communication.
The selection is done using DDB mask setting cells in the PROTOCOL CFG column. The DDB mask value
Std+UserConfig controls only the signal selection (enabled or disabled) for IEC 60870-5-103 communication. It does not
modify the COT behaviour of the signals. The COT behaviour of the private range signals will be according to
the device IEC 60870-5-103 profile.
By default, only IEC 60870-5-103 standard signals are enabled. All private range signals are disabled.
When the Config Mode cell is set to Std+UserConfig, the DDB masks become visible in the PROTOCOL CFG
column. These masks function in a similar way to the DDB masks in the RECORD CONTROL column. Editing these
masks controls the DDB signals that are enabled for communication of the equivalent IEC 60870-5-103 private
range signal, as listed in the IEC 60870-5-103 profile in the Menu Database.
Within these masks, only individual DDBs that are equivalent to IEC 60870-5-103 private range signals are
editable. By default, all of the individual DDBs that are equivalent to IEC 60870-5-103 private range signals are set
to 0 (zero), that is disabled for communication. Setting any individual DDB to 1 (one), enables the equivalent IEC
60870-5-103 private range signal for communication.
Within these masks, individual DDBs that are either equivalent to IEC 60870-5-103 standard range signals, or do
not have any equivalent IEC 60870-5-103 private range signal, are not editable.
The IEC 60870-5-103 profile in the Menu Database contains a complete listing of all events produced by the
device.
From Software Version 91 onwards, the IEC 60870-5-103 private range signals can be individually selected for
spontaneous communication, by settting the Config Mode cell to Std+UserConfig, and configuring the DDB
masks as required.
700 P54-TM-EN-1.1
P54 Chapter 24 - Communications
12.2.8 COMMANDS
A list of the supported commands is contained in the Menu Database. The device will respond to other commands
with an ASDU 1, with a cause of transmission (COT) indicating ‘negative acknowledgement’.
Note:
IEC 60870-5-103 only supports up to 8 records.
P54-TM-EN-1.1 701
Chapter 24 - Communications P54
Setting: Description:
Disabled No blocking selected.
When the monitor blocking DDB Signal is active high, either by energising an opto input or control input,
Monitor Blocking reading of the status information and disturbance records is not permitted. When in this mode the device
returns a "Termination of general interrogation" message to the master station.
When the command blocking DDB signal is active high, either by energising an opto input or control input,
Command Blocking all remote commands will be ignored (i.e. CB Trip/Close, change setting group etc.). When in this mode the
device returns a "negative acknowledgement of command" message to the master station.
The baud rate can be selected using the front panel menu or by the settings application software.
When using a serial interface, the data format is: 1 start bit, 8 data bits, 1 stop bit and optional configurable parity
bit.
Note:
For the DNP Events to be transmitted it is mandatory to have the corresponding DDBs of the Configured Point Index to be
included in the Courier Event Record. The RECORD CONTROL Menu lists all the DDBs, and the mask settings control their
inclusion/exclusion as a Courier Event.
702 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Control Input
(Latched)
Aliased Control
Input
(Latched)
Control Input
(Pulsed )
Aliased Control
Input
(Pulsed )
The pulse width is equal to the duration of one protection iteration
V01002
Many of the IED’s functions are configurable so some of the Object 10 commands described in the following
sections may not be available. A read from Object 10 reports the point as off-line and an operate command to
Object 12 generates an error response.
Examples of Object 10 points that maybe reported as off-line are:
● Activate setting groups: Ensure setting groups are enabled
● CB trip/close: Ensure remote CB control is enabled
● Reset NPS thermal: Ensure NPS thermal protection is enabled
● Reset thermal O/L: Ensure thermal overload protection is enabled
● Reset RTD flags: Ensure RTD Inputs is enabled
● Control inputs: Ensure control inputs are enabled
P54-TM-EN-1.1 703
Chapter 24 - Communications P54
counter and stores it in the corresponding Object 21 frozen counter. The freeze and clear function resets the Object
20 running counter to zero after freezing its value.
Binary counter and frozen counter change event values are available for reporting from Object 22 and Object 23
respectively. Counter change events (Object 22) only report the most recent change, so the maximum number of
events supported is the same as the total number of counters. Frozen counter change events (Object 23) are
generated whenever a freeze operation is performed and a change has occurred since the previous freeze
command. The frozen counter event queues store the points for up to two freeze operations.
704 P54-TM-EN-1.1
P54 Chapter 24 - Communications
total interoperability guide. This table, in combination with the subsequent Implementation and Points List tables
should provide a complete interoperability/configuration guide for the device.
The following table provides the device profile in a similar format to that defined in the DNP 3.0 Subset Definitions
Document. While it is referred to in the DNP 3.0 Subset Definitions as a "Document", it is just one component of a
total interoperability guide. This table, in combination with the subsequent Implementation and Points List tables
should provide a complete interoperability/configuration guide for the device.
DNP 3.0
Device Profile Document
Vendor Name: General Electric
Device Name: MiCOM P40Agile Protection Relays – compact and modular range
Models Covered: All models
Highest DNP Level Supported*: For Requests: Level 2
*This is the highest DNP level FULLY supported. Parts of level 3 are For Responses: Level 2
also supported
Device Function: Slave
Notable objects, functions, and/or qualifiers supported in addition to the highest DNP levels supported (the complete list is described in the
DNP 3.0 Implementation Table):
For static (non-change event) object requests, request qualifier codes 00 and 01 (start-stop), 07 and 08 (limited quantity), and 17 and 28 (index)
are supported in addition to the request qualifier code 06 (no range (all points))
Static object requests sent with qualifiers 00, 01, 06, 07, or 08 will be responded with qualifiers 00 or 01
Static object requests sent with qualifiers 17 or 28 will be responded with qualifiers 17 or 28
For change-event object requests, qualifiers 17 or 28 are always responded
16-bit and 32-bit analogue change events with time may be requested
The read function code for Object 50 (time and date) variation 1 is supported
Analogue Input Deadbands, Object 34, variations 1 through 3, are supported
Floating Point Analogue Output Status and Output Block Objects 40 and 41 are supported
Sequential file transfer, Object 70, variations 2 through 7, are supported
Device Attribute Object 0 is supported
Maximum Data Link Frame Size (octets): Transmitted: 292
Received: 292
Maximum Application Fragment Size (octets) Transmitted: Configurable (100 to 2048). Default 2048
Received: 249
Maximum Data Link Retries: Fixed at 2
Maximum Application Layer Retries: None
Requires Data Link Layer Confirmation: Configurable to Never or Always
Requires Application Layer Confirmation: When reporting event data (Slave devices only)
When sending multi-fragment responses (Slave devices only)
Timeouts while waiting for:
Data Link Confirm: Configurable
Complete Application Fragment: None
Application Confirm: Configurable
Complete Application Response: None
Others:
Data Link Confirm Timeout: Configurable from 0 (Disabled) to 120s, default 10s.
Application Confirm Timeout: Configurable from 1 to 120s, default 2s.
Select/Operate Arm Timeout: Configurable from 1 to 10s, default 10s.
Need Time Interval (Set IIN1-4): Configurable from 1 to 30, default 10min.
Application File Timeout 60 s
P54-TM-EN-1.1 705
Chapter 24 - Communications P54
DNP 3.0
Device Profile Document
Analog Change Event Scan Period: Fixed at 0.5s
Counter Change Event Scan Period Fixed at 0.5s
Frozen Counter Change Event Scan Period Fixed at 1s
Maximum Delay Measurement Error: 2.5 ms
Time Base Drift Over a 10-minute Interval: 7 ms
Sends/Executes Control Operations:
Write Binary Outputs: Never
Select/Operate: Always
Direct Operate: Always
Direct Operate - No Ack: Always
Count > 1 Never
Pulse On Always
Pulse Off Sometimes
Latch On Always
Latch Off Always
Queue Never
Clear Queue Never
Note: Paired Control points will accept Pulse On/Trip and Pulse On/Close, but only single point will accept the Pulse Off control command.
Reports Binary Input Change Events when no specific variation Configurable to send one or the other
requested:
Reports time-tagged Binary Input Change Events when no specific Binary input change with time
variation requested:
Sends Unsolicited Responses: Never
Sends Static Data in Unsolicited Responses: Never
No other options are permitted
Default Counter Object/Variation: Configurable, Point-by-point list attached
Default object: 20
Default variation: 1
Counters Roll Over at: 32 bits
Sends multi-fragment responses: Yes
Sequential File Transfer Support:
Append File Mode No
Custom Status Code Strings No
Permissions Field Yes
File Events Assigned to Class No
File Events Send Immediately Yes
Multiple Blocks in a Fragment No
Max Number of Files Open 1
706 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Request Response
Object
(Library will parse) (Library will respond with)
Object Variation Function Codes (dec) Qualifier Codes Function Codes Qualifier Codes (hex)
Description (dec)
Number Number (hex)
1 0 Binary Input (Variation 0 is used to 1 (read) 00, 01 (start-stop)
request default variation) 22 (assign class) 06 (no range, or all)
07, 08 (limited qty)
17, 27, 28 (index)
1 1 Binary Input 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
(default - see 06 (no range, or all) 17, 28 (index - see note 2)
note 1) 07, 08 (limited qty)
17, 27, 28 (index)
1 2 Binary Input with Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 28 (index)
2 0 Binary Input Change - Any 1 (read) 06 (no range, or all)
Variation 07, 08 (limited qty)
2 1 Binary Input Change without Time 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
07, 08 (limited qty)
2 2 Binary Input Change with Time 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
07, 08 (limited qty)
10 0 Binary Output Status - Any 1 (read) 00, 01 (start-stop)
Variation 06 (no range, or all)
07, 08 (limited qty)
17, 27, 28 (index)
10 2 Binary Output Status 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
(default - see 06 (no range, or all) 17, 28 (index - see note 2)
note 1) 07, 08 (limited qty)
17, 28 (index)
12 1 Control Relay Output Block 3 (select) 17, 28 (index) 129 response echo of request
4 (operate)
5 (direct op)
6 (dir. op, noack)
20 0 Binary Counter - Any Variation 1 (read) 00, 01 (start-stop)
22 (assign class) 06 (no range, or all)
07, 08 (limited qty)
17, 27, 28 (index)
7 (freeze) 00, 01 (start-stop)
8 (freeze noack) 06 (no range, or all)
9 (freeze clear) 07, 08 (limited qty)
10 (frz. cl. Noack)
20 1 32-Bit Binary Counter with Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
20 2 16-Bit Binary Counter with Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
20 5 32-Bit Binary Counter without Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
(default - see 06 (no range, or all) 17, 28 (index - see note 2)
note 1) 07, 08 (limited qty)
17, 27, 28 (index)
20 6 16-Bit Binary Counter without Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
21 0 Frozen Counter - Any Variation 1 (read) 00, 01 (start-stop)
06 (no range, or all)
07, 08 (limited qty)
17, 27, 28 (index)
21 1 32-Bit Frozen Counter with Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
21 2 16-Bit Frozen Counter with Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
P54-TM-EN-1.1 707
Chapter 24 - Communications P54
Request Response
Object
(Library will parse) (Library will respond with)
Object Variation Function Codes (dec) Qualifier Codes Function Codes Qualifier Codes (hex)
Description (dec)
Number Number (hex)
21 5 32-Bit Frozen Counter with Time of 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
Freeze 06 (no range, or all) 17, 28 (index - see note 1)
07, 08 (limited qty)
17, 27, 28 (index)
21 6 16-Bit Frozen Counter with Time of 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
Freeze 06 (no range, or all) 17, 28 17, 28 (index - see note 1)
07, 08 (limited qty)
17, 27, 28 (index)
21 9 32-Bit Frozen Counter without Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
(default - see 06 (no range, or all) 17, 28 (index - see note 2)
note 1) 07, 08 (limited qty)
17, 27, 28 (index)
21 10 16-Bit Frozen Counter without Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
`22 0 Counter Change Event - Any 1 (read) 06 (no range, or all)
Variation 07, 08 (limited qty)
22 1 32-Bit Counter Change Event 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
(default - see without Time 07, 08 (limited qty)
note 1)
22 2 16-Bit Counter Change Event 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
without Time 07, 08 (limited qty)
22 5 32-Bit Counter Change Event with 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
Time 07, 08 (limited qty)
22 6 16-Bit Counter Change Event with 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
Time 07, 08 (limited qty)
23 0 Frozen Counter Event (Variation 0 1 (read) 06 (no range, or all)
is used to request default 07, 08 (limited qty)
variation)
23 1 32-Bit Frozen Counter Event 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
(default - see 07, 08 (limited qty)
note 1)
23 2 16-Bit Frozen Counter Event 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
07, 08 (limited qty)
23 5 32-Bit Frozen Counter Event with 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
Time 07, 08 (limited qty)
23 6 16-Bit Frozen Counter Event with 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
Time 07, 08 (limited qty)
30 0 Analog Input - Any Variation 1 (read) 00, 01 (start-stop)
22 (assign class) 06 (no range, or all)
07, 08 (limited qty)
17, 27, 28 (index)
30 1 32-Bit Analog Input 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
30 2 16-Bit Analog Input 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
30 3 32-Bit Analog Input without Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
(default - see 06 (no range, or all) 17, 28 (index - see note 2)
note 1) 07, 08 (limited qty)
17, 27, 28 (index)
30 4 16-Bit Analog Input without Flag 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
30 5 Short floating point 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
32 0 Analog Change Event - Any 1 (read) 06 (no range, or all)
Variation 07, 08 (limited qty)
708 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Request Response
Object
(Library will parse) (Library will respond with)
Object Variation Function Codes (dec) Qualifier Codes Function Codes Qualifier Codes (hex)
Description (dec)
Number Number (hex)
32 1 32-Bit Analog Change Event 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
(default - see without Time 07, 08 (limited qty)
note 1)
32 2 16-Bit Analog Change Event 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
without Time 07, 08 (limited qty)
32 3 32-Bit Analog Change Event with 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
Time 07, 08 (limited qty)
32 4 16-Bit Analog Change Event with 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
Time 07, 08 (limited qty)
32 5 Short floating point Analog 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
Change Event without Time 07, 08 (limited qty)
32 7 Short floating point Analog 1 (read) 06 (no range, or all) 129 response 17, 28 (index)
Change Event with Time 07, 08 (limited qty)
34 0 Analog Input Deadband (Variation 1 (read) 00, 01 (start-stop)
0 is used to request default 06 (no range, or all)
variation) 07, 08 (limited qty)
17, 27, 28 (index)
34 1 16 Bit Analog Input Deadband 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
2 (write) 00, 01 (start-stop)
07, 08 (limited qty)
17, 27, 28 (index)
34 2 32 Bit Analog Input Deadband 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
(default - see 06 (no range, or all) 17, 28 (index - see note 2)
note 1) 07, 08 (limited qty)
17, 27, 28 (index)
2 (write) 00, 01 (start-stop)
07, 08 (limited qty)
17, 27, 28 (index)
34 3 Short Floating Point Analog Input 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
Deadband 06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
2 (write) 00, 01 (start-stop)
07, 08 (limited qty)
17, 27, 28 (index)
40 0 Analog Output Status (Variation 0 1 (read) 00, 01 (start-stop)
is used to request default 06 (no range, or all)
variation) 07, 08 (limited qty)
17, 27, 28 (index)
40 1 32-Bit Analog Output Status 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
(default - see 06 (no range, or all) 17, 28 (index - see note 2)
note 1) 07, 08 (limited qty)
17, 27, 28 (index)
40 2 16-Bit Analog Output Status 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
40 3 Short Floating Point Analog 1 (read) 00, 01 (start-stop) 129 response 00, 01 (start-stop)
Output Status 06 (no range, or all) 17, 28 (index - see note 2)
07, 08 (limited qty)
17, 27, 28 (index)
41 1 32-Bit Analog Output Block 3 (select) 17, 28 (index) 129 response echo of request
4 (operate) 27 (index)
5 (direct op)
6 (dir. op, noack)
41 2 16-Bit Analog Output Block 3 (select) 17, 28 (index) 129 response echo of request
4 (operate) 27 (index)
5 (direct op)
6 (dir. op, noack)
41 3 Short Floating Point Analog 3 (select) 17, 27, 28 (index) 129 response echo of request
Output Block 4 (operate)
5 (direct op)
6 (dir. op, noack)
P54-TM-EN-1.1 709
Chapter 24 - Communications P54
Request Response
Object
(Library will parse) (Library will respond with)
Object Variation Function Codes (dec) Qualifier Codes Function Codes Qualifier Codes (hex)
Description (dec)
Number Number (hex)
1 1 (read) 07 (limited qty = 1) 129 response 07 (limited qty = 1)
50 (default - see Time and Date
note 1)
2 (write) 07 (limited qty = 1)
60 0 Not defined
60 1 Class 0 Data 1 (read) 06 (no range, or all)
60 2 Class 1 Data 1 (read) 06 (no range, or all)
07, 08 (limited qty)
22 (assign class) 06 (no range, or all)
60 3 Class 2 Data 1 (read) 06 (no range, or all)
07, 08 (limited qty)
22 (assign class) 06 (no range, or all)
60 4 Class 3 Data 1 (read) 06 (no range, or all)
07, 08 (limited qty)
22 (assign class) 06 (no range, or all)
70 0 File Event - Any Variation 1 (read) 06 (no range, or all)
07, 08 (limited qty)
22 (assign class) 06 (no range, or all)
70 2 File Authentication 29 (authenticate) 5b (free-format) 129 response 5B (free-format)
70 3 File Command 25 (open) 5b (free-format)
27 (delete)
70 4 File Command Status 26 (close) 5b (free-format) 129 response 5B (free-format)
30 (abort)
70 5 File Transfer 1 (read) 5b (free-format) 129 response 5B (free-format)
70 6 File Transfer Status 129 response 5B (free-format)
70 7 File Descriptor 28 (get file info) 5b (free-format) 129 response 5B (free-format)
Note:
A Default variation refers to the variation responded to when variation 0 is requested and/or in class 0, 1, 2, or 3 scans.
Note:
For static (non-change-event) objects, qualifiers 17 or 28 are only responded to when a request is sent with qualifiers 17 or
28, respectively. Otherwise, static object requests sent with qualifiers 00, 01, 06, 07, or 08, will be responded to with qualifiers
00 or 01. For change-event objects, qualifiers 17 or 28 are always responded to.
710 P54-TM-EN-1.1
P54 Chapter 24 - Communications
processed due to formatting errors or the requested data is not available, the IIN is always returned with the
appropriate bits set.
Bit Indication Description Supported
Octet 1
Set when a request is received with the destination address of the all stations
address (6553510). It is cleared after the next response (even if a response to a
0 All stations message received global request is required). Yes
This IIN is used to let the master station know that a "broadcast" message was
received by the relay.
Set when data that has been configured as Class 1 data is ready to be sent to
the master.
1 Class 1 data available Yes
The master station should request this class data from the relay when this bit
is set in a response.
Set when data that has been configured as Class 2 data is ready to be sent to
the master.
2 Class 2 data available Yes
The master station should request this class data from the relay when this bit
is set in a response.
Set when data that has been configured as Class 3 data is ready to be sent to
the master.
3 Class 3 data available Yes
The master station should request this class data from the relay when this bit
is set in a response.
The relay requires time synchronization from the master station (using the
Time and Date object).
4 Time-synchronization required Yes
This IIN is cleared once the time has been synchronized. It can also be cleared
by explicitly writing a 0 into this bit of the Internal Indication object.
Set when some or all of the relays digital output points (Object 10/12) are in the
Local state. That is, the relays control outputs are NOT accessible through the
5 Local DNP protocol. No
This IIN is clear when the relay is in the Remote state. That is, the relays control
outputs are fully accessible through the DNP protocol.
Set when an abnormal condition exists in the relay. This IIN is only used when
6 Device in trouble the state cannot be described by a combination of one or more of the other IIN No
bits.
Set when the device software application restarts. This IIN is cleared when the
7 Device restart master station explicitly writes a 0 into this bit of the Internal Indications Yes
object.
Octet 2
0 Function code not implemented The received function code is not implemented within the relay. Yes
The relay does not have the specified objects or there are no objects assigned
to the requested class.
1 Requested object(s) unknown Yes
This IIN should be used for debugging purposes and usually indicates a
mismatch in device profiles or configuration problems.
Parameters in the qualifier, range or data fields are not valid or out of range.
This is a 'catch-all' for application request formatting errors. It should only be
2 Out of range Yes
used for debugging purposes. This IIN usually indicates configuration
problems.
Event buffer(s), or other application buffers, have overflowed. The master
station should attempt to recover as much data as possible and indicate to the
3 Buffer overflow Yes
user that there may be lost data. The appropriate error recovery procedures
should be initiated by the user.
The received request was understood but the requested operation is already
4 Already executing
executing.
Set to indicate that the current configuration in the relay is corrupt. The
5 Bad configuration Yes
master station may download another configuration to the relay.
P54-TM-EN-1.1 711
Chapter 24 - Communications P54
Note:
Code numbers 10 through to 126 are reserved for future use.
712 P54-TM-EN-1.1
P54 Chapter 24 - Communications
6. Move down to the next cell (RP1 Parity). This cell controls the parity format used in the data frames. The
parity can be set to be one of None, Odd or Even. Make sure that the parity format selected on the IED is
the same as that set on the master station.
7. If the optional fibre optic connectors are fitted, the RP1 PhysicalLink cell is visible. This cell controls the
physical media used for the communication (Copper or Fibre optic).
8. Move down to the next cell (RP1 Time Sync). This cell affects the time synchronisation request from the
master by the IED. It can be set to enabled or disabled. If enabled it allows the DNP3.0 master to
synchronise the time on the IED.
The standard adheres to the requirements laid out by the ISO OSI model and therefore provides complete vendor
interoperability and flexibility on the transmission types and protocols used. This includes mapping of data onto
Ethernet, which is becoming more and more widely used in substations, in favour of RS485. Using Ethernet in the
substation offers many advantages, most significantly including:
● Ethernet allows high-speed data rates (currently 100 Mbps, rather than tens of kbps or less used by most
serial protocols)
● Ethernet provides the possibility to have multiple clients
● Ethernet is an open standard in every-day use
● There is a wide range of Ethernet-compatible products that may be used to supplement the LAN installation
(hubs, bridges, switches)
P54-TM-EN-1.1 713
Chapter 24 - Communications P54
Data Attributes
stVal q t PhA PhB PhC
Data Objects
Pos A
Logical Nodes : 1 to n
LN1: XCBR LN2: MMXU
V01008
714 P54-TM-EN-1.1
P54 Chapter 24 - Communications
The IEC 61850 compatible interface standard provides capability for the following:
● Read access to measurements
● Refresh of all measurements at a standard rate.
● Generation of non-buffered and buffered multi-client reports on change of status or measurement
● SNTP time synchronization over an Ethernet link. (This is used to synchronize the IED's internal real time
clock.
● GOOSE peer-to-peer communication
● Disturbance record extraction by IEC 61850 MMS file transfer. The record is extracted as an ASCII format
COMTRADE file
Note:
Setting changes are not supported in the current IEC 61850 implementation. Currently these setting changes are carried out
using the settings application software.
P54-TM-EN-1.1 715
Chapter 24 - Communications P54
number anomalies. If an anomaly is detected, the 'out-of-order' GOOSE message is discarded. When a message is
discarded the last valid message remains active until a new valid GOOSE message is received or its validity period
(TAL) expires.
Out-of-order GOOSE message indicators and reporting are provided to the subscriber via the IEC61850 LGOS
logical node.
716 P54-TM-EN-1.1
P54 Chapter 24 - Communications
To help with this process, the settings application software provides an IEC 61850 Configurator tool, which allows
the pre-configured IEC 61850 configuration file to be imported and transferred to the IED. As well as this, you can
manually create configuration files for all products, based on their original IED capability description (ICD file).
Other features include:
● The extraction of configuration data for viewing and editing.
● A sophisticated error checking sequence to validate the configuration data before sending to the IED.
Note:
Some configuration data is available in the IEC61850 CONFIG. column, allowing read-only access to basic configuration data.
Any new configuration sent to the IED is automatically stored in the inactive configuration bank, therefore not
immediately affecting the current configuration.
Following an upgrade, the IEC 61850 Configurator tool can be used to transmit a command, which authorises
activation of the new configuration contained in the inactive configuration bank. This is done by switching the
active and inactive configuration banks. The capability of switching the configuration banks is also available using
the IEC61850 CONFIG. column of the HMI.
The SCL Name and Revision attributes of both configuration banks are available in the IEC61850 CONFIG. column
of the HMI.
Edition 2 implementation requires use of version 3.8 of the IEC 61850 configurator, which is installed with version
2.0.1 of MiCOM S1 Agile.
P54-TM-EN-1.1 717
Chapter 24 - Communications P54
Ed2
MMS
C C
L/ R
GOOSE
BAY
Ed1 devices in Ed2 system:
GOOSE OK
MMS OK
TOOLS (SCL files) OK V01056
Figure 415: Edition 2 system - backward compatibility
An Edition 2 IED cannot normally operate within an Edition 1 IEC 61850 system. An Edition 2 IED can work for
GOOSE messaging in a mixed system, providing the client is compatible with Edition 2.
718 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Ed1
MMS
C C
L/ R
GOOSE
BAY
Ed1 devices in Ed2 system:
GOOSE OK
MMS Not OK
TOOLS (SCL files) Not OK V01057
Figure 416: Edition 1 system - forward compatibility issues
Of these, only ENS and ENC types are available from a MiCOM P40 IED when publishing GOOSE messages, so Data
Objects using these Common Data Classes should not be published in mixed Edition 1 and Edition 2 systems.
For compatibility between Edition 1 and Edition 2 IEDs, SCL files using SCL schema version "2.1" must be used. For
a purely Edition 2 system, use the schema version "2007B4".
P54-TM-EN-1.1 719
Chapter 24 - Communications P54
Note:
For IEC 60870-5-103, Read Only Mode function is different from the existing Command block feature.
720 P54-TM-EN-1.1
P54 Chapter 24 - Communications
Using the PSL, these signals can be activated by opto-inputs, Control Inputs and function keys if required.
P54-TM-EN-1.1 721
Chapter 24 - Communications P54
14 TIME SYNCHRONISATION
In modern protection schemes it is necessary to synchronise the IED's real time clock so that events from different
devices can be time stamped and placed in chronological order. This is achieved in various ways depending on the
chosen options and communication protocols.
● Using the IRIG-B input (if fitted)
● Using the SNTP time protocol (for Ethernet IEC 61850 versions)
● Using IEEE 1588 Precision Time Protocol (PTP)
● By using the time synchronisation functionality inherent in the data protocols
The time synchronisation sources can be configured in a priority order using the Primary Source and Secondary
Source cells in the DATE AND TIME column. If the Primary source becomes unavailable, the Secondary source will
be used, if available.
GPS satellite
IRIG-B
V01040
The IRIG-B time code signal is a sequence of one second time frames. Each frame is split up into ten 100 mS slots
as follows:
● Time-slot 1: Seconds
● Time-slot 2: Minutes
722 P54-TM-EN-1.1
P54 Chapter 24 - Communications
● Time-slot 3: Hours
● Time-slot 4: Days
● Time-slot 5 and 6: Control functions
● Time-slots 7 to 10: Straight binary time of day
The first four time-slots define the time in BCD (Binary Coded Decimal). Time-slots 5 and 6 are used for control
functions, which control deletion commands and allow different data groupings within the synchronisation strings.
Time-slots 7-10 define the time in SBS (Straight Binary Second of day).
14.2 SNTP
SNTP is used to synchronise the clocks of computer systems over packet-switched, variable-latency data
networks, such as IP. SNTP can be used as the time synchronisation method for models using IEC 61850 over
Ethernet. A time synchronisation accuracy of within 5 ms is possible.
The device is synchronised by the main SNTP server. This is achieved by entering the IP address of the SNTP server
into the IED using the IEC 61850 Configurator software described in the settings application software manual. A
second server is also configured with a different IP address for backup purposes.
This function issues an alarm when there is a loss of time synchronisation on the SNTP server. This could be
because there is no response or no valid clock signal.
The HMI menu does not contain any configurable settings relating to SNTP, as the only way to configure it is using
the IEC 61850 Configurator. However it is possible to view some parameters in the COMMUNICATIONS column
under the sub-heading SNTP parameters. Here you can view the SNTP server addresses and the SNTP poll rate in
the cells SNTP Server 1, SNTP Server 2 and SNTP Poll rate respectively.
The SNTP time synchronisation status is displayed in the SNTP Status cell in the DATE AND TIME column.
P54-TM-EN-1.1 723
Chapter 24 - Communications P54
Grand Master
RSTP Network
<8 Hops, so <1ms
additional timing error
V01061a
724 P54-TM-EN-1.1
P54 Chapter 24 - Communications
The time synchronisation for each protocol is described in the relevant protocol description section.
P54-TM-EN-1.1 725
Chapter 24 - Communications P54
726 P54-TM-EN-1.1
CHAPTER 25
CYBER-SECURITY
Chapter 25 - Cyber-Security P54
728 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
1 OVERVIEW
In the past, substation networks were traditionally isolated and the protocols and data formats used to transfer
information between devices were often proprietary.
For these reasons, the substation environment was very secure against cyber-attacks. The terms used for this
inherent type of security are:
● Security by isolation (if the substation network is not connected to the outside world, it cannot be accessed
from the outside world).
● Security by obscurity (if the formats and protocols are proprietary, it is very difficult to interpret them).
However, note that these are not recognised defences against attackers.
The increasing sophistication of protection schemes, coupled with the advancement of technology and the desire
for vendor interoperability, has resulted in standardisation of networks and data interchange within substations.
Today, devices within substations use standardised protocols for communication. Furthermore, substations can be
interconnected with open networks, such as the internet or corporate-wide networks, which use standardised
protocols for communication. This introduces a major security risk making the grid vulnerable to cyber-attacks,
which could in turn lead to major electrical outages.
Clearly, there is now a need to secure communication and equipment within substation environments. This
chapter describes the security measures that have been put in place for our range of Intelligent Electronic Devices
(IEDs).
Note:
Cyber-security compatible devices do not enforce NERC compliance, they merely facilitate it. It is the responsibility of the user
to ensure that compliance is adhered to as and when necessary.
P54-TM-EN-1.1 729
Chapter 25 - Cyber-Security P54
The threats to cyber-security may be unintentional (e.g. natural disasters, human error), or intentional (e.g. cyber-
attacks by hackers).
Good cyber-security can be achieved with a range of measures, such as closing down vulnerability loopholes,
implementing adequate security processes and procedures and providing technology to help achieve this.
Examples of vulnerabilities are:
● Indiscretions by personnel (users keep passwords on their computer)
● Bad practice (users do not change default passwords, or everyone uses the same password to access all
substation equipment)
● Bypassing of controls (users turn off security measures)
● Inadequate technology (substation is not firewalled)
To help tackle these issues, standards organisations have produced various standards. Compliance with these
standards significantly reduces the threats associated with lack of cyber-security.
730 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
3 STANDARDS
There are several standards, which apply to substation cyber-security. The standards currently applicable to
General Electric IEDs are NERC and IEEE1686.
Standard Country Description
NERC CIP (North American Electric Reliability
USA Framework for the protection of the grid critical Cyber Assets
Corporation)
BDEW (German Association of Energy and Water Requirements for Secure Control and Telecommunication
Germany
Industries) Systems
ICS oriented then Relevant for EPU completing existing
ANSI ISA 99 USA standard and identifying new topics such as patch
management
International Standard for substation IED cyber-security
IEEE 1686 International
capabilities
Power systems management and associated information
IEC 62351 International
exchange - Data and communications security
IEC 62443 International Security for industrial automation and control systems
ISO/IEC 27002 International Framework for the protection of the grid critical Cyber Assets
NIST SP800-53 (National Institute of Standards and Complete framework for SCADA SP800-82and ICS cyber-
USA
Technology) security
CPNI Guidelines (Centre for the Protection of National Clear and valuable good practices for Process Control and
UK
Infrastructure) SCADA security
P54-TM-EN-1.1 731
Chapter 25 - Cyber-Security P54
732 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
P54-TM-EN-1.1 733
Chapter 25 - Cyber-Security P54
● The audit trail is recorded, listing events in the order in which they occur, held in a circular buffer.
● Records contain all defined fields from the standard and record all defined function event types where the
function is supported.
● No password defeat mechanism exists. Instead a secure recovery password scheme is implemented.
● Unused ports (physical and logical) may be disabled.
734 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
4 CYBER-SECURITY IMPLEMENTATION
GE IEDs have always been and will continue to be equipped with state-of-the-art security measures. Due to the
ever-evolving communication technology and new threats to security, this requirement is not static. Hardware and
software security measures are continuously being developed and implemented to mitigate the associated threats
and risks.
MiCOM 5th Generation P40 products provide enhanced security through the following features:
● An Authentication, Authorization, Accounting (AAA) Remote Authentication Dial-In User Service (RADIUS)
client that is managed centrally, enables user attribution, provides accounting of all user activities, and uses
secure standards based on strong cryptography for authentication and credential protection. In other
words, this option uses a RADIUS.
● Server for user authentication. There is provision for both remote (RADIUS) and local (device) authentication.
● A Role-Based Access Control (RBAC) system in line with IEC 62351-8:2020 that provides a permission model
that allows access to the device operations and configurations based on specific roles and individual user
accounts configured on the AAA server.
● Security event reporting through both proprietary event logs and the Syslog protocol for supporting Security
Information Event Management (SIEM) systems for centralised cybersecurity monitoring.
● Encryption of passwords - stored within the IED, in network messages between the MiCOM S1 Agile software
and the IED, and in network messages between the RADIUS server and the IED (subject to the RADIUS server
configuration).
P54-TM-EN-1.1 735
Chapter 25 - Cyber-Security P54
5.1 ROLES
The P40 Agile products supports all the mandatory pre-defined roles as per IEC 62351-8:2020.
IEC 62351-8 Roles Value
VIEWER 0
OPERATOR 1
ENGINEER 2
INSTALLER 3
SECADM 4
SECAUD 5
RBACMNT 6
Individual user accounts can be configured to have one or more of these roles.
● VIEWER: Can view all values and settings
● OPERATOR: Can view values and perform control operations
● ENGINEER: Can view values, and change settings of the device
● INSTALLER: Specific role required to perform firmware updates
● SECADM: Security Administrator - Can edit/modify Users and roles and configure security settings
● SECAUD: Security Auditor - Can view Security Log files
● RBACMNT: RBAC Management can change role to permission assignment
Only one role of one type is allowed to be logged in at a time from any interface. For example, one Operator can be
logged in but not a second Operator at the same time from any other interface. This prevents subsets of settings
from being changed at the same time.
5.2 PERMISSIONS
Authentication and authorization are two different processes. An authenticated user cannot perform any action on
the IED unless a privilege has been explicitly granted to them. This is the concept of “least privileges” access.
Privileges must be granted to users through roles. A role is a collection of privileges, and roles are granted to users.
It is possible to have multiple roles for a user. The privilege/role matrix is stored on the IED. This is known as Role-
Based-Access Control (RBAC).
On successful user authentication, the IED will load the user’s role list. If the user’s role changes, the user must
logout and log back in to exercise his/her privileges.
The table below shows the predefined permissions assignment for the predefined Roles according to IEC
62351-8:2020
Permission
SETTINGGROUP
Role Name
Value
READVALUES
LISTOBJECTS
(revision = 1)
REPORTING
FILEWRITE
FILEMNGT
CONTROL
SECURITY
FILEREAD
DATASET
CONFIG
<0> VIEWER C C X C1
736 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
<1> OPERATOR X X X C1 X X
<2> ENGINEER X X X X X1 X1 X1 X X
<3> INSTALLER X X X X2 X2 X X
<4> SECADM X X X X4 X4 X4 X X
<5> SECAUD X X X X3
<6> RBACMNT X X X X4 X
<7 ...32767> Reserved For future use of IEC defined roles.
<-32768 .. -1> Private Defined by external agreement. Not guaranteed to be inoperable.
C = Conditional read access, clarification of specific data objects may be necessary (e.g., VIEWER may not access security
settings, but process values)
C1 = Conditional read access to files of filetype data
X1 = Access to files of type data and config
X2 = Access to files of type config and firmware (updates)
X3 = Access to files of type audit log
X4 = Access to files of type security (config)
The table below shows the predefined permissions description according to IEC 62351-8:2020
Permission Description
Allows the subject/role to discover what objects are present within an IED by presenting the type and
ID of those objects. If this permission is granted to a subject/role, the object for which the READVALUES
LISTOBJECTS
permission has not been granted are not readable. This permission basically relates to all objects
defined in IEC 61850 and allows a query on the existence of the data objects.
Allows the subject/role to obtain the values for all or some objects that are present within an IED in
READVALUES addition to the type and ID. This permission basically relates to all objects defined in IEC 61850 that
provide a value and allows a read action on the actual values of the data objects.
Allows the subject/role to have full service access (e.g., createDataSet, deleteDataSet) for both
DATASET
persistent and non-persistent DataSets.
Allows the subject/role to use buffered reporting as well as unbuffered reporting. Reporting relates to
REPORTING
buffered and unbuffered report control blocks of a logical node.
FILEREAD Allows the subject/role to perform read actions on file objects.
Allows the subject/role to perform write actions on file objects. This permission includes the FILEREAD
FILEWRITE
permission.
Allows the subject/role to perform control operations on all or some controllable objects that are
CONTROL (group) present within an IED. Control services are for instance select or operate and relate to data objects
defined in IEC 61850.
Allows the subject/role to locally or remotely configure all or some objects that are present within an
CONFIG
IED. This relates to data attributes of the IEC 61850 functional constraints CF, DC and SP.
Allows the subject/role to remotely configure SettingGroup control block. For example, this relates to
SETTINGGROUP the switching between different configured SettingGroups. SettingGroups also contains the IEC 61850
functional constraints SE.
FILEMNGT Allows the subject/role to delete existing files on the IEDS.
SECURITY Allows the subject/role to perform actions on all security related data objects, reportings, logs or files.
Specific product related permissions are listed in the tables below. Roles are mapped to Access Level definitions: A
cross indicates that specific actions can be done by a user with the role allocated.
Extract Files Role Name
None
File Type VIEWER OPERATOR ENGINEER INSTALLER SECADM SECAUD RBACMNT
Logged
P54-TM-EN-1.1 737
Chapter 25 - Cyber-Security P54
Setting X X X X X
PSL X X
MCL (IEC 61850) X X
DNP3.0 X X
SLD X X
Event X X X X
DR X X X
738 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
6 AUTHENTICATION
If Bypass Auth. is enabled, the IED ignores the Auth. Method setting.
The Auth. Method setting offers the following options for user authentication:
● Server + Device (This is the default setting for IEDs with NIC (Ethernet Board) fitted)
● Device Only (This is the default setting for IEDs without NIC (Ethernet Board) fitted)
Only users with a SECADM role may change the Auth. Method setting. If the SECADM user changes it, the role
remains logged in. Only when the user logs-out is their access-level revoked.
6.2 BYPASS
In Bypass Auth. mode, the IED does not provide user authentication - any user can login. IED does not validate
user and password. The bypass security feature provides an easier access, with no authentication and encryption
for situations when this is considered safe. Only users with SECADM role can enable Bypass mode.
There are three modes for authentication bypass:
1. Disabled - no interfaces in Bypass Auth. mode (normal authentication is active)
2. Local - Bypass authentication when using Front Port
3. Front Panel - will bypass authentication Front Panel
Bypass authentication for
Front Port Front Panel
Bypass mode:
Disabled
Local X
Front Panel X
The DDB signal Security Bypass is available to indicate that the IED is in Bypass Auth. mode.
6.3 LOGIN
A user can only login through the following methods:
● Front Panel User Interface
● Using MiCOM S1 Agile, connected to either the Front Port, Rear Port 1 or 2, or NIC (Ethernet) interface.
P54-TM-EN-1.1 739
Chapter 25 - Cyber-Security P54
For both Device authentication or Server authentication, the user can enter any valid username and password
combination. For ease of typing, it is preferable to do login using MiCOM S1 Agile.
After successful log in, a confirmation message is displayed, showing the logged in username. For example:
740 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
P54-TM-EN-1.1 741
Chapter 25 - Cyber-Security P54
User Role
Setting Name Description Min Max Default Units
Required
Number of failed authentications before the device blocks
0 (lockout
Attempts Limit subsequent authentication attempts for the lockout period. A 99 3 - SECADM
disabled)
value of 0 means Lockout is disabled.
The period of time in seconds a user is prevented from
Lockout Period 1 5940 30 sec SECADM
logging in, after being locked out.
FP Inactivity Timer is the time of idleness on Front Port before
0 (no Inactivity
FP InactivTimer a logged in user is automatically logged out and revert the 30 10 min SECADM
Timeout)
access level to the viewer role
UI Inactivity Timer is the time of idleness on Front Panel
0 (no Inactivity
UI InactivTimer before a logged in user is automatically logged out and revert 30 10 min SECADM
Timeout)
the access level to the viewer role
NIC Tunl Timeout is the time of idleness on Ethernet Port (NIC)
NIC Tunl Timeout before a logged in user is automatically logged out and revert 1 30 5 min SECADM
the access level to the viewer role
The recommended settings for Attempts Limit is 3 and Lockout Period is 30 sec to discourage brute force
attacks. If the Lockout period is too large, anybody can lockout Device users.
Only one role of one type is allowed to be logged in at a time from any interface. If the role has been logged in from
one interface, an attempt to login the same role will result in a message being displayed, as below.
742 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
For RP1, if Courier Protocol is selected, and for RP2, the KBUS InactTmr and RP2 InactivTimer settings are
available, in the COMMUNICATIONS column.
Each user account records how long it has been locked if the account is locked.
Each user account records how many times it has consecutively failed to login. User account failed times include
all interfaces login attempts. For example, if the Attempts Limit setting is 3 and the operator failed to login from
front panel 2 times, and they changed to login from the Courier interface, but failed again, then the Operator
would be locked out.
When the IED is powered on, these Attempts Limit counter resets to zero.
When the user account exceeds the Attempts Limit it is locked for Lockout period, at that time Attempt limit
resets to zero.
The locked user account will be unlocked automatically, after the configured “Lockout Period” is expired.
If the locked account attempts to login the IED from the Front Panel, the unsuccessful login attempt screen is
displayed.
6.6 LOGOUT
Each user should Log out after reading or configuring the IED.
The user can only log out from the front panel, if they logged in from the front panel. If the user logged in from S1
Agile, they have to logout from S1 Agile.
P54-TM-EN-1.1 743
Chapter 25 - Cyber-Security P54
If you decide not to log out (i.e. you cancel), the logout screen would be cancelled.
744 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
User Role
Setting Name Description Min Max Default Units
Required
For Server authentication, the password complexity and user locking policy is defined in the external RADIUS server.
User Role
Setting Name Description Min Max Default Units
Required
When the Max Password Age has been reached and if the user attempts to login using the front HMI, the following
window will be shown.
P54-TM-EN-1.1 745
Chapter 25 - Cyber-Security P54
The user will be presented with a screen to save the new password.
746 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
Any further password change can only be done from MiCOM S1 Agile using the Change/Set Password option in
the Supervise Device dialog box.
Users with SECADM and RBACMNT roles can change the password of any user. Users with other roles can change
only their own password.
Caution:
It is recommended that user passwords are changed periodically.
6.10 RADIUS
When the Auth. Method setting is configured as Server + Device, a user must log in with a username and
password that has been predefined on the RADIUS server.
This log in can be performed from any interface, as described in the Login section. The IED will authenticate the
user to the active RADIUS server, over the Ethernet connection.
Groups User
Access Request
User login RADIUS
IED Client
Access
Accept
(User Role)
User RADIUS Server Active Directory
V01100
P54-TM-EN-1.1 747
Chapter 25 - Cyber-Security P54
The RADIUS implementation queries the Role ID vendor attribute and establish the logged in user security context
with that role.
RADIUS Config. Value
Vendor ID 2910
Vendor Attribute 1
Standard Values
VIEWER 0
OPERATOR 1
ENGINEER 2
INSTALLER 3
SECADM 4
SECAUD 5
RBACMNT 6
The data cell RADIUS Status indicates the status of the currently-selected RADIUS server. This will display either
Disabled, Server OK, or Failed.
748 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
Note:
It is recommended that the shared secret be changed from the default before using RADIUS authentication.
The IED does not support exchange of CA certificates. The RADIUS server may send a certificate but the IED will not
verify it.
6.11 RECOVERY
P54-TM-EN-1.1 749
Chapter 25 - Cyber-Security P54
supply the Serial Number and the security code. The Contact Centre will use these items to generate a Recovery
Password.
The security code is a 16-character string of uppercase characters. It is a read-only parameter. The device
generates its own security code randomly. A new code is generated under the following conditions:
● On power up
● Whenever settings are set back to default
● On expiry of validity timer (see below)
● When the recovery password is entered
This reset procedure can be only accomplished through front panel exclusively and cannot be done over any other
interface. As soon as the security code is displayed on the front panel User Interface, a validity timer is started. This
validity timer is set to 72 hours and is not configurable. This provides enough time for the Contact Centre to
manually generate and send a recovery password. The Service Level Agreement (SLA) for recovery password
generation is one working day, so 72 hours is sufficient time, even allowing for closure of the Contact Centre over
weekends and public holidays.
The procedure is:
1. User navigates to Security Code cell in SECURITY CONFIG column
2. To prevent accidental reading of the IED Security Code, the cell will initially display a warning message
3. Press Enter to read the Security Code
4. User sends an email to the Contact Centre providing the full IED serial number and displayed Security Code,
using a recognisable corporate email account
5. Contact Centre emails the user with the Recovery Password. The recovery password is intended for recovery
only. It is not a replacement password that can be used continually. It can only be used once - for password
recovery
6. User logs in with the default SECADM username ADMIN1 or any created SECADM username, and the
recovery password in to the Password field, using the Login Banner
7. If the recovery password successfully validates, the default passwords are restored for each access level for
Device authentication. If the recovery password is incorrect, the standard failure screen will be displayed
Note:
Restoring passwords to defaults restores the whole SECURITY CONFIG column to default values including the default Device
users. It does not affect any other settings and does not provoke reboot of the IED. The protection and control functions of the
IED are always maintained.
750 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
KEY:
HMI = Human Machine Interface
FPort = Front Port
RPrt = Rear Port
Lvl = Level
None
Supervise Device VIEWER OPERATOR ENGINEER INSTALLER SECADM SECAUD RBACMNT
Logged
Active Group X X X
Reset Cell X
P54-TM-EN-1.1 751
Chapter 25 - Cyber-Security P54
Breakers X
Device Address X X X
Bypass Options X
Device User
X X
Management
Own Password
X X X X X X X
Change
RADIUS Secret X
SNMP Security X
Clear Records X
Restore Defaults X X
Restore Security
Settings X
Note:
1. It is not possible to update the firmware on the IED which is under Bypass mode
Note:
2. The device no longer clears the memory during the firmware update process. The configuration files as well as the stored
records remain available after the firmware upgrade
752 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
Note:
When setting the SNMP browser for RBAC compatible relays, the Context Name should be ‘px4x’.
P54-TM-EN-1.1 753
Chapter 25 - Cyber-Security P54
754 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
P54-TM-EN-1.1 755
Chapter 25 - Cyber-Security P54
where:
● int is the interface definition (UI, FP, RP1, RP2, TNL, TCP)
● prt is the port ID (FP, RP1, RP2, TNL, DNP3, IEC, ETHR)
● grp is the group number (1, 2, 3, 4)
● crv is the Curve group number (1, 2, 3, 4)
● n is the new access level (0, 1, 2, 3)
● p is the password level (1, 2, 3)
● nov is the number of events (1 – nnn)
Each new event has an incremented unique number, therefore missing events appear as gap in the sequence. The
unique identifier forms part of the event record that is read or uploaded from the IED.
9.2 SYSLOG
Security events are also logged to a remote syslog server.
756 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
All login and logout attempts from local and central authentication, whether successful or failed, are logged. The
contents of each successful or failed, login and logout security event include a specific username.
The security log cannot be cleaned by any of the available roles.
The contents of each login and/or logout security event include the relevant interface. The following interfaces are
supported:
Interface Abbr.
Front Port FP
Rear Port 1 RP1
Rear Port 2 RP2
Ethernet NET
Front Panel UI
P54-TM-EN-1.1 757
Chapter 25 - Cyber-Security P54
User Role
Setting Name Description Min Max Default Units
Required
The IP address of the target Syslog
SysLog Pri IP 0.0.0.0 223.255.255.254 0.0.0.0 - SECADM
server (Primary)
The IP address of the target Syslog
SysLog Sec IP 0.0.0.0 223.255.255.254 0.0.0.0 - SECADM
server (Secondary)
The UDP port number of the target
SysLog Port 1 65535 514 - SECADM
Syslog server
758 P54-TM-EN-1.1
P54 Chapter 25 - Cyber-Security
P54-TM-EN-1.1 759
Chapter 25 - Cyber-Security P54
760 P54-TM-EN-1.1
CHAPTER 26
INSTALLATION
Chapter 26 - Installation P54
762 P54-TM-EN-1.1
P54 Chapter 26 - Installation
1 CHAPTER OVERVIEW
This chapter provides information about installing the product.
This chapter contains the following sections:
Chapter Overview 763
Handling the Goods 764
Mounting the Device 765
Cables and Connectors 768
Case Dimensions 773
P54-TM-EN-1.1 763
Chapter 26 - Installation P54
Caution:
Before lifting or moving the equipment you should be familiar with the Safety
Information chapter of this manual.
764 P54-TM-EN-1.1
P54 Chapter 26 - Installation
Caution:
Do not use conventional self-tapping screws, because they have larger heads and could
damage the faceplate.
Alternatively, you can use tapped holes if the panel has a minimum thickness of 2.5 mm.
For applications where the product needs to be semi-projection or projection mounted, a range of collars are
available.
If several products are mounted in a single cut-out in the panel, mechanically group them horizontally or vertically
into rigid assemblies before mounting in the panel.
Caution:
Do not fasten products with pop rivets because this makes them difficult to remove if
repair becomes necessary.
Caution:
Risk of damage to the front cover molding. Do not use conventional self-tapping
screws, including those supplied for mounting MiDOS products because they have
slightly larger heads.
Once the tier is complete, the frames are fastened into the racks using mounting angles at each end of the tier.
P54-TM-EN-1.1 765
Chapter 26 - Installation P54
Products can be mechanically grouped into single tier (4U) or multi-tier arrangements using the rack frame. This
enables schemes using products from different product ranges to be pre-wired together before mounting.
Use blanking plates to fill any empty spaces. The spaces may be used for installing future products or because the
total size is less than 80TE on any tier. Blanking plates can also be used to mount ancillary components. The part
numbers are as follows:
766 P54-TM-EN-1.1
P54 Chapter 26 - Installation
P54-TM-EN-1.1 767
Chapter 26 - Installation P54
Caution:
Before carrying out any work on the equipment you should be familiar with the Safety
Section and the ratings on the equipment’s rating label.
MiCOM products are supplied with sufficient M4 screws for making connections to the rear mounted terminal
blocks using ring terminals, with a recommended maximum of two ring terminals per terminal.
If required, M4 90° crimp ring terminals can be supplied in three different sizes depending on wire size. Each type is
available in bags of 100.
Part number Wire size Insulation color
ZB9124 901 0.25 - 1.65 mm2 (22 – 16 AWG) Red
ZB9124 900 1.04 - 2.63 mm2 (16 – 14 AWG) Blue
768 P54-TM-EN-1.1
P54 Chapter 26 - Installation
Note:
IP2x shields and side cover panels may be fitted to provide IP20 ingress protection for MiCOM terminal blocks. The shields and
covers can be attached during installation or retrofitted to upgrade existing installations. The shields are supplied with four
language fitting instructions, publication number: IP2x-TM-4L-n (where n is the current issue number). For more information,
contact your local sales office or our worldwide Contact Centre.
Caution:
Protect the auxiliary power supply wiring with a maximum 16 A high rupture capacity
(HRC) type NIT or TIA fuse.
Use a wire size of at least 2.5 mm2 terminated with a ring terminal.
Due to the physical limitations of the ring terminal, the maximum wire size you can use is 6.0 mm2 using ring
terminals that are not pre-insulated. If using pre insulated ring terminals, the maximum wire size is reduced to 2.63
mm2 per ring terminal. If you need a greater cross-sectional area, use two wires in parallel, each terminated in a
separate ring terminal.
The wire should have a minimum voltage rating of 300 V RMS.
Note:
To prevent any possibility of electrolytic action between brass or copper ground conductors and the rear panel of the product,
precautions should be taken to isolate them from one another. This could be achieved in several ways, including placing a
nickel-plated or insulating washer between the conductor and the product case, or using tinned ring terminals.
Due to the physical limitations of the ring terminal, the maximum wire size you can use is 6.0 mm2 using ring
terminals that are not pre-insulated. If using pre insulated ring terminals, the maximum wire size is reduced to 2.63
mm2 per ring terminal. If you need a greater cross-sectional area, use two wires in parallel, each terminated in a
separate ring terminal.
The wire should have a minimum voltage rating of 300 V RMS.
Caution:
Current transformer circuits must never be fused.
P54-TM-EN-1.1 769
Chapter 26 - Installation P54
Note:
If there are CTs present, spring-loaded shorting contacts ensure that the terminals into which the CTs connect are shorted
before the CT contacts are broken.
Note:
For 5A CT secondaries, we recommend using 2 x 2.5 mm2 PVC insulated multi-stranded copper wire.
770 P54-TM-EN-1.1
P54 Chapter 26 - Installation
Caution:
Protect the opto-inputs and their wiring with a maximum 16 A high rupture capacity
(HRC) type NIT or TIA fuse.
Note:
For models equipped with redundant Ethernet connections the product must be partially dismantled to set the fourth octet of
the second IP address. This ideally, should be done before installation.
P54-TM-EN-1.1 771
Chapter 26 - Installation P54
772 P54-TM-EN-1.1
P54 Chapter 26 - Installation
5 CASE DIMENSIONS
Not all products are available in all case sizes.
P54-TM-EN-1.1 773
Chapter 26 - Installation P54
AB BA
168
159
AB BA
10.35 181.3
202
240
Incl. wiring
FRONT VIEW
177 157.5
max.
Sealing strip
177
(4U)
Note: If mounting plate is required use flush mounting cut-out dimensions All dimensions in mm.
V01484
774 P54-TM-EN-1.1
P54 Chapter 26 - Installation
159 168
305.5
157.5 MAX
177
P54-TM-EN-1.1 775
Chapter 26 - Installation P54
159 168
222
408.9
177 157.5
max
27 SIDE VIEW
413.2
FRONT VIEW
776 P54-TM-EN-1.1
CHAPTER 27
COMMISSIONING INSTRUCTIONS
Chapter 27 - Commissioning Instructions P54
778 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
1 CHAPTER OVERVIEW
This chapter contains the following sections:
Chapter Overview 779
General Guidelines 780
Commissioning Test Menu 781
Commissioning Equipment 785
Product Checks 787
Electrical Intermicom Communication Loopback 796
Intermicom 64 Communication 798
GPS Synchronisation 800
Setting Checks 801
IEC 61850 Edition 2 Testing 803
Current Differential Protection 808
Distance Protection 811
Delta Directional Comparison 819
DEF Aided Schemes 822
Out of Step Protection 825
Protection Timing Checks 827
System Check and Check Synchronism 830
Check Trip and Autoreclose Cycle 831
End-to-End Communication Tests 832
End-to-End Scheme Tests 835
Onload Checks 837
Final Checks 839
Commmissioning the P59x 840
P54-TM-EN-1.1 779
Chapter 27 - Commissioning Instructions P54
2 GENERAL GUIDELINES
General Electric IEDs are self-checking devices and will raise an alarm in the unlikely event of a failure. This is why
the commissioning tests are less extensive than those for non-numeric electronic devices or electro-mechanical
relays.
To commission the devices, you (the commissioning engineer) do not need to test every function. You need only
verify that the hardware is functioning correctly and that the application-specific software settings have been
applied. You can check the settings by extracting them using the settings application software, or by means of the
front panel interface (HMI panel).
The menu language is user-selectable, so you can change it for commissioning purposes if required.
Note:
Remember to restore the language setting to the customer’s preferred language on completion.
Caution:
Before carrying out any work on the equipment you should be familiar with the
contents of the Safety Section or Safety Guide SFTY/4LM as well as the ratings on the
equipment’s rating label.
Warning:
With the exception of the CT shorting contacts check, do not disassemble the device
during commissioning.
780 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Note:
When the Test Mode cell is set to Contacts Blocked, the relay output status indicates which contacts would operate if
the IED was in-service. It does not show the actual status of the output relays, as they are blocked.
Caution:
The monitor/download port is not electrically isolated against induced voltages on
the communications channel. It should therefore only be used for local
communications.
P54-TM-EN-1.1 781
Chapter 27 - Commissioning Instructions P54
Caution:
When the cell is in Test Mode, the Scheme Logic still drives the output relays, which
could result in tripping of circuit breakers. To avoid this, set the Test Mode cell to
Contacts Blocked.
Note:
Test mode and Contacts Blocked mode can also be selected by energising an opto-input mapped to the Test Mode
signal, and the Contact Block signal respectively.
Note:
When the Test Mode cell is set to Contacts Blocked the Relay O/P Status cell does not show the current status of the
output relays and therefore cannot be used to confirm operation of the output relays. Therefore it will be necessary to monitor
the state of each contact in turn.
782 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
The Trip 3 Pole option in the Test Autoreclose cell causes the device to perform the first three phase trip/
reclose cycle so that associated output contacts can be checked for operation at the correct times during the
cycle. Once the trip output has operated the command text will revert to No Operation whilst the rest of the
auto-reclose cycle is performed. To test subsequent three-phase autoreclose cycles, you repeat the Trip 3
Pole command. You can also test the single phases with Trip Pole A , Trip Pole B and Trip Pole C.
Note:
The default settings for the programmable scheme logic has the AR Trip Test signals mapped to the Trip Input
signals. If the programmable scheme logic has been changed, it is essential that these signals retain this mapping for the
Test Autoreclose facility to work.
Note:
Trip times may be up to ½ cycle longer when tested in the static mode, due to the nature of the test voltage and current, and
the slower filtering. This is normal, and perfectly acceptable.
Note:
If the cell is set to Internal, only the IED software is checked. If the cell is set to External, both the software and hardware
are checked.
When the device is switched into Loopback Mode, it automatically uses generic addresses 0-0. It responds as if it is
connected to a remote device. The sent and received IM64 signals continue to be routed to and from the signals
defined in the programmable logic.
P54-TM-EN-1.1 783
Chapter 27 - Commissioning Instructions P54
Note:
Loopback mode can also be selected by energising an opto-input mapped to the Loopback signal.
Note:
When the status in both Red LED Status and Green LED Status cells is ‘1’, this indicates the LEDs illumination is yellow.
784 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
4 COMMISSIONING EQUIPMENT
Specialist test equipment is required to commission this product. We recognise three classes of equipment for
commissioning :
● Recommended
● Essential
● Advisory
Recommended equipment constitutes equipment that is both necessary, and sufficient, to verify correct
performance of the principal protection functions.
Essential equipment represents the minimum necessary to check that the product includes the basic expected
protection functions and that they operate within limits.
Advisory equipment represents equipment that is needed to verify satisfactory operation of features that may be
unused, or supplementary, or which may, for example, be integral to a distributed control/automation scheme.
Operation of such features may, perhaps, be more appropriately verified as part of a customer defined
commissioning requirement, or as part of a system-level commissioning regime.
P54-TM-EN-1.1 785
Chapter 27 - Commissioning Instructions P54
● Timer
● Test switches
● Suitable electrical test leads
● Continuity tester
For products that use fibre-optic communications to implement unit protection schemes :
● Fibre optic test leads (minimum 2). 10m minimum length, multimode 50/125 µm or 62.5µm, OR single mode
(according to the model variant) terminated with connectors as required by the product.
● Fibre-optic power meter
Note that if the AC test source that you are using is not capable of dynamic fault simulation (cannot dynamically
switch from load to fault conditions) you must use the product’s static test mode feature
To do this, in COMMISSION TESTS, set Static Test Mode to Enabled.
786 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
5 PRODUCT CHECKS
These product checks are designed to ensure that the device has not been physically damaged prior to
commissioning, is functioning correctly and that all input quantity measurements are within the stated tolerances.
If the application-specific settings have been applied to the IED prior to commissioning, you should make a copy of
the settings. This will allow you to restore them at a later date if necessary. This can be done by:
● Obtaining a setting file from the customer.
● Extracting the settings from the IED itself, using a portable PC with appropriate setting software.
If the customer has changed the password that prevents unauthorised changes to some of the settings, either the
revised password should be provided, or the original password restored before testing.
Note:
If the password has been lost, a recovery password can be obtained from General Electric.
Warning:
The following group of tests should be carried out without the auxiliary supply being
applied to the IED and, if applicable, with the trip circuit isolated.
The current and voltage transformer connections must be isolated from the IED for these checks. If a P991 test
block is provided, the required isolation can be achieved by inserting test plug type P992. This open circuits all
wiring routed through the test block.
Before inserting the test plug, you should check the scheme diagram to ensure that this will not cause damage or
a safety hazard (the test block may, for example, be associated with protection current transformer circuits). The
sockets in the test plug, which correspond to the current transformer secondary windings, must be linked before
the test plug is inserted into the test block.
Warning:
Never open-circuit the secondary circuit of a current transformer since the high
voltage produced may be lethal and could damage insulation.
If a test block is not provided, the voltage transformer supply to the IED should be isolated by means of the panel
links or connecting blocks. The line current transformers should be short-circuited and disconnected from the IED
terminals. Where means of isolating the auxiliary supply and trip circuit (for example isolation links, fuses and MCB)
are provided, these should be used. If this is not possible, the wiring to these circuits must be disconnected and the
exposed ends suitably terminated to prevent them from being a safety hazard.
P54-TM-EN-1.1 787
Chapter 27 - Commissioning Instructions P54
Warning:
Check the rating information under the top access cover on the front of the IED.
Warning:
Check that the IED being tested is correct for the line or circuit.
Warning:
Record the circuit reference and system details.
Warning:
Check the CT secondary current rating and record the CT tap which is in use.
Carefully examine the IED to see that no physical damage has occurred since installation.
Ensure that the case earthing connections (bottom left-hand corner at the rear of the IED case) are used to
connect the IED to a local earth bar using an adequate conductor.
Note:
Use a magnetic bladed screwdriver to minimise the risk of the screws being left in the terminal block or lost.
Pull the terminal block away from the rear of the case and check with a continuity tester that all the shorting
switches being used are closed.
5.1.3 INSULATION
Insulation resistance tests are only necessary during commissioning if explicitly requested.
Isolate all wiring from the earth and test the insulation with an electronic or brushless insulation tester at a DC
voltage not exceeding 500 V. Terminals of the same circuits should be temporarily connected together.
The insulation resistance should be greater than 100 MW at 500 V.
On completion of the insulation resistance tests, ensure all external wiring is correctly reconnected to the IED.
Caution:
Check that the external wiring is correct according to the relevant IED and scheme
diagrams. Ensure that phasing/phase rotation appears to be as expected.
788 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Note:
The IED can withstand an AC ripple of up to 12% of the upper rated voltage on the DC auxiliary supply.
Warning:
Do not energise the IED or interface unit using the battery charger with the battery
disconnected as this can irreparably damage the power supply circuitry.
Caution:
Energise the IED only if the auxiliary supply is within the specified operating ranges.
If a test block is provided, it may be necessary to link across the front of the test plug
to connect the auxiliary supply to the IED.
Warning:
The current and voltage transformer connections must remain isolated from the IED
for these checks. The trip circuit should also remain isolated to prevent accidental
operation of the associated circuit breaker.
The following group of tests verifies that the IED hardware and software is functioning correctly and should be
carried out with the supply applied to the IED.
P54-TM-EN-1.1 789
Chapter 27 - Commissioning Instructions P54
Caution:
Before applying a contrast setting, make sure that it will not make the display so
light or dark such that menu text becomes unreadable. It is possible to restore the
visibility of a display by downloading a setting file, with the LCD Contrast set within
the typical range of 7 - 11.
Note:
If the auxiliary supply fails, the time and date will be maintained by the supercapacitor. Therefore, when the auxiliary supply is
restored, you should not have to set the time and date again. To test this, remove the IRIG-B signal, and then remove the
auxiliary supply. Leave the device de-energised for approximately 30 seconds. On re energisation, the time should be correct.
When using IRIG-B to maintain the clock, the IED must first be connected to the satellite clock equipment (usually
an RT430), which should be energised and functioning.
1. Set the IRIG-B Sync cell in the DATE AND TIME column to Enabled.
2. Ensure the IED is receiving the IRIG-B signal by checking that cell IRIG-B Status reads Active.
3. Once the IRIG-B signal is active, adjust the time offset of the universal co coordinated time (satellite clock
time) on the satellite clock equipment so that local time is displayed.
4. Check that the time, date and month are correct in the Date/Time cell. The IRIG-B signal does not contain
the current year so it will need to be set manually in this cell.
5. Reconnect the IRIG-B signal.
If the time and date is not being maintained by an IRIG-B signal, ensure that the IRIG-B Sync cell in the DATE AND
TIME column is set to Disabled.
1. Set the date and time to the correct local time and date using Date/Time cell or using the serial protocol.
790 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
P54-TM-EN-1.1 791
Chapter 27 - Commissioning Instructions P54
For K-Bus applications, pins 17 and 18 are not polarity sensitive and it does not matter which way round the wires
are connected. EIA(RS)485 is polarity sensitive, so you must ensure the wires are connected the correct way round
(pin 18 is positive, pin 17 is negative).
If K-Bus is being used, a Kitz protocol converter (KITZ101, KITZ102 OR KITZ201) will have been installed to convert
the K-Bus signals into RS232. Likewise, if RS485 is being used, an RS485-RS232 converter will have been installed.
In the case where a protocol converter is being used, a laptop PC running appropriate software (such as MiCOM S1
Agile) can be connected to the incoming side of the protocol converter. An example for K-bus to RS232 conversion
is shown below. RS485 to RS232 would follow the same principle, only using a RS485-RS232 converter. Most
modern laptops have USB ports, so it is likely you will also require a RS232 to USB converter too.
792 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Fibre Connection
Some models have an optional fibre optic communications port fitted (on a separate communications board). The
communications port to be used is selected by setting the Physical Link cell in the COMMUNICATIONS column, the
values being Copper or K-Bus for the RS485/K-bus port and Fibre Optic for the fibre optic port.
P54-TM-EN-1.1 793
Chapter 27 - Commissioning Instructions P54
Note:
If a PC connected to the IED using the rear communications port is being used to display the measured current, the process
will be similar. However, the setting of the Remote Values cell in the MEASURE’T SETUP column will determine whether the
displayed values are in primary or secondary Amperes.
The measurement accuracy of the IED is +/- 1%. However, an additional allowance must be made for the accuracy
of the test equipment being used.
794 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Note:
If a PC connected to the IED using the rear communications port is being used to display the measured current, the process
will be similar. However, the setting of the Remote Values cell in the MEASURE’T SETUP column will determine whether the
displayed values are in primary or secondary Amperes.
The measurement accuracy of the IED is +/- 1%. However, an additional allowance must be made for the accuracy
of the test equipment being used.
P54-TM-EN-1.1 795
Chapter 27 - Commissioning Instructions P54
Note:
If INTERMICOM COMMS > Loopback Mode is set to Internal, only the internal software of the device is checked. This is
useful for testing functionality if no communications connections are made. Use the 'External' setting during commissioning
because it checks both the software and hardware. When the IED is switched into either Internal or External Loopback Mode it
automatically inhibits InterMiCOM messages to the PSL by setting all eight InterMiCOM message command states to zero.
Set INTERMICOM COMMS > Loopback Mode to External and form a communications loopback by connecting
the transmit signal (pin 2) to the receive signal (pin 3).
Note:
The DCD signal must be held high (by connecting pin 1 to pin 4) if the connected equipment does not support DCD.
DCD 1
RxD 2
TxD 3
DTR 4
GND 5
6
RTS 7
8
9
E01450
The loopback mode is shown on the front panel by an Alarm LED and the message IM Loopback on the LCD.
Check that all connections are correct and the software is working correctly.
Check that INTERMICOM COMMS > Loopback Status shows OK.
796 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Note:
Some or all of these cells show Fail depending on the communications configuration and the way the link has failed.
P54-TM-EN-1.1 797
Chapter 27 - Commissioning Instructions P54
7 INTERMICOM 64 COMMUNICATION
If the IED is used in a scheme with InterMiCOM64 communication, you need to configure a loopback for testing
purposes.
IM64 is fibre-based. Several different fibre-optic interfaces are available. In general, 1550 nm single-mode fibres, or
1300 nm single-mode or multimode fibres are used for direct connection. 850 nm multimode fibres are generally
used with multiplexing telecommunications equipment.
Note:
It is important that fibres used for testing are correct for the specified interface(s).
Optical fibres should be terminated with BFOC2.5 (ST2.5) connectors. For multimode applications use 50/125 µm
core fibre. Make sure fibre test leads used for measurements are long enough for mode stripping (a method of
reducing loss within the core). We recommend a minimum length of 10 m (30ft) for this.
If IEDs communicate using multiplexed electrical communication channels, a bidirectional optical-to-electrical
signal converter, such as a P59x, is used. The P59x range consists of three devices: P591 for G703, P592 for V.35
and P593 for X.21.
The P59x is situated near the multiplexer, between the fibre from the IED and the electrical interface of the
multiplexer. Apply the loopback either at the P59x or the multiplexer to ensure as much of the circuit as possible is
tested. If the IED is connected to a multiplexer, the loopback testing is exactly the same whether connected directly
or via a multiplexer. The P59x interface units require additional tests (see P59x documentation).
If Current Differential protection is used, set CONFIGURATION > Current Diff to Enable.
If Current Differential protection is not used, set CONFIGURATION > InterMiCOM64 to Enable.
Warning:
NEVER look directly into the transmit port or the end of an optical fibre, as this could
severely damage your eyes.
798 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Note:
If CONFIGURATION > InterMiCOM64 is set to Enable, the signals normally sent and received by and from the
communications interface are routed to and from the signals defined in the Programmable Scheme Logic. If, however,
COMMISSION TESTS > IM64 Test Mode is set to Enabled, an IM64 test pattern is transmitted instead.
Note:
The propagation delay measurement is not valid in this mode of operation. The IED responds as if it is connected to a remote
IED. It indicates a loopback alarm which can only be cleared by setting COMMISSION TESTS > Loopback Mode to Disabled.
Note:
In loopback mode the signals sent and received through the protection communications interface continue to be routed to
and from the signals defined in the programmable logic.
Note:
A test pattern can also be sent to the remote end to test the whole InterMiCOM communication path. To do this, set
COMMISSION TESTS >IM64 Test Mode to Enable and connect two ends. Take special care because the test pattern is
executed using PSL at the remote end.
P54-TM-EN-1.1 799
Chapter 27 - Commissioning Instructions P54
8 GPS SYNCHRONISATION
The IED uses GPS timing information to align the local and remote current vectors in the current differential
algorithm. A RT430 GPS synchronising unit is used to decode GPS signals and provide the synchronising signal.
If the IED uses GPS synchronisation, the associated RT430 unit needs to be commissioned according to the
instructions in the RT430 Technical Manual.
Warning:
NEVER look directly into the transmit port or the end of an optical fibre, as this could
severely damage your eyes.
800 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
9 SETTING CHECKS
The setting checks ensure that all of the application-specific settings (both the IED’s function and programmable
scheme logic settings) have been correctly applied.
Note:
If applicable, the trip circuit should remain isolated during these checks to prevent accidental operation of the associated
circuit breaker.
Note:
The device name may not already exist in the system shown in System Explorer. In this case, perform a Quick Connect to the
IED, then manually add the settings file to the device name in the system. Refer to the Settings Application Software help for
details of how to do this.
P54-TM-EN-1.1 801
Chapter 27 - Commissioning Instructions P54
6. To confirm the new settings, press the Enter key. Navigate away from the currently active group settings or
press the Home key. A Settings update confirmation dialogue box will appear that requires choosing of one
of the following options:
a. Save - accept all settings including the recently changed settings
b. Abort – discard recent changes and keep existing settings
c. Stay on page – return to the active settings page without saving recent changes
7. To return to the top of the menu, hold down the Up cursor key for a second or so, or press the Clear key
once. It is possible to move across columns from anywhere in the menu by using the Menu context keys at
the bottom of the display.
8. To return to the default display, press the Home key at any time.
9. Press the Enter key to accept the new settings or press the Clear key to discard the new settings.
10. The Date and time can be adjusted by navigating to the top banner and selecting the displayed time. Press
the Enter key to adjust the date and time using the calendar/clock widget that pops up.
Note:
For the protection group and disturbance recorder settings, the changes are not saved unless confirmed using the Settings
update confirmation prompt.
Note:
All other Control and support settings (such as Communications and Control inputs), however, are updated immediately after
they are entered on the front HMI without the need to confirm using the Settings update confirmation prompt.
802 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
The following table summarises the P40 IED behaviour under the different modes:
IED Test Mode Setting IEC 61850 Mod Result
● Normal IED behaviour
Disabled on ● IED only responds to incoming GOOSE and SV messages
with quality q.test = false
P54-TM-EN-1.1 803
Chapter 27 - Commissioning Instructions P54
Setting the Test or Contacts Blocked mode puts the whole IED into test mode. The IEC 61850 data object Beh in all
Logical Nodes (except LPHD and any protection Logical Nodes that have Beh = 5 (off) due to the function being
disabled) will be set to 3 (test) or 4 (test/blocked) as applicable.
LPHD1
Incoming data
processed
Real GOOSE 2 messages
Reception buffer
V01058
804 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
P54-TM-EN-1.1 805
Chapter 27 - Commissioning Instructions P54
806 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Note:
When the IED Test Mode cell is set to Contacts Blocked, the Relay O/P Status cell does not show the current status of the
output relays so cannot be used to confirm operation of the output relays. Therefore it is necessary to monitor the state of
each contact in turn.
P54-TM-EN-1.1 807
Chapter 27 - Commissioning Instructions P54
P54x IED Ia
Ra
L A
Ph a
Ib
Rb
A
Ph b
N
V01452
808 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Note:
For 5 A applications, keep the duration of current injections short to avoid overheating of the variac or injection test set
Phase A
1. Retaining the same test circuit as before, prepare for an instantaneous injection of 3 pu current in the A
phase, with no current in the B phase (B phase switch open).
2. Set a timer to start when the fault injection is applied, and to stop when the trip occurs.
3. To verify the correct output contact mapping, use the trip contacts that would be expected to trip the circuit
breaker(s), as shown below. For two breaker applications, stop the timer once both CB1 and CB2 trip
contacts have closed. This can be achieved by connecting the contacts in series to stop the timer.
Single breaker Two circuit breakers
Three Pole Tripping Any Trip Any Trip (CB1) and Any Trip (CB2)
Single Pole Tripping Trip A Trip A (CB1) and Trip A (CB2)
P54-TM-EN-1.1 809
Chapter 27 - Commissioning Instructions P54
Phase B
1. Reconfigure the test equipment to inject fault current into the B phase.
2. Repeat the test, this time ensuring that the breaker trip contacts relative to B phase operation close
correctly.
3. Record the B phase trip time.
4. Switch OFF the ac supply and reset the alarms
Phase C
1. Repeat the above procedure for the C phase.
2. Switch OFF the ac supply and reset the alarms.
The average of the recorded operating times for the three phases should be less than 40 ms for 50 Hz, and less
than 35 ms for 60 Hz when set for instantaneous operation.
Note:
For applications using magnetising inrush current restraint, use a test current higher than the Inrush High setting to obtain
fast operating times. A setting of at least twice the Inrush High setting is recommended.
The expected operating time is typically within +/- 5% (for IDMT) or +/-2% (for DT) of that for the curve equation
plus the “instantaneous” delay quoted above.
When the tests are completed, restore the original settings of any elements which were disabled for testing
purposes. Use the CONFIGURATION column.
810 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
12 DISTANCE PROTECTION
If these elements are enabled with a dependency upon the above conditions, it is necessary to simulate the
condition to test the correct operation of the protection function.
A communications failure can be simulated by setting the Test Loopback cell to Disabled and checking that the IED
raises a Comms Fail alarm.
At the end of the test, clear the communications alarms and reset the statistics.
A VTS alarm can be raised by applying a 3-phase voltage to the VT inputs and then removing one phase voltage
for a duration exceeding the VTS Time Delay setting.
At the end of the tests, clear the VTS alarm.
12.2.1 PRELIMINARIES
You should now connect the IED to equipment able to supply phase-phase and phase-neutral volts with current in
the correct phase relation for a particular type of fault on the selected characteristic angle. The facility for altering
the loop impedance (phase-to-ground fault or phase-phase) presented to the IED is essential.
P54-TM-EN-1.1 811
Chapter 27 - Commissioning Instructions P54
Use a three-phase digital/electronic injection test set to make the commissioning procedure easier.
1. If testing the distance elements using using test sets that do not provide a dynamic model to generate true
fault delta conditions, set COMMISSION TESTS > Static Test Mode to Enabled. When set, this disables
phase selector control and forces the device to use a conventional (non-delta) directional line.
2. For lower specification test equipment that cannot apply a full three phase set of healthy simulated pre-
fault voltages, the VT supervision may need to be disabled to avoid spurious pickup. Set CONFIGURATION >
Supervision to Disabled.
3. Connect the test equipment to the device using the test block(s), taking care not to open-circuit any CT
secondary windings. If using MMLG type test blocks, the live side of the test plug must be provided with
shorting links before it is inserted into the test block.
4. When the test is complete, make sure COMMISSION TESTS > Static Test Mode is set back to Disabled.
812 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
P54-TM-EN-1.1 813
Chapter 27 - Commissioning Instructions P54
Note:
Zone 3 has an independent setting for the forward resistance reach (right-hand resistive reach line), and the reverse resistance
reach (left-hand resistive reach line).
12.3.1 PHASE A
1. Prepare a dynamic A-phase-to-neutral fault, as detailed above.
2. Set a timer to start when the fault injection is applied and to stop when the trip occurs.
3. To verify correct output contact mapping use the trip contacts that would be expected to trip the circuit
breaker(s) (Any Trip for 3-pole tripping, Trip A for single pole tripping).
814 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
4. For two breaker applications, stop the timer when CB1 and CB2 trip contacts have both closed. Monitor by
connecting the contacts in series to stop the timer if necessary.
5. Record the phase A trip time.
6. Switch OFF the AC supply and reset the alarms.
12.3.2 PHASE B
1. Reconfigure to test a B phase fault.
2. Repeat the test, this time ensuring that the breaker trip contacts relative to B phase operation close
correctly.
3. Record the phase B trip time.
4. Switch OFF the AC supply and reset the alarms.
12.3.3 PHASE C
1. Reconfigure to test a C phase fault.
2. Repeat the test, this time ensuring that the breaker trip contacts relative to C phase operation close
correctly.
3. Record the phase C trip time.
4. Switch OFF the AC supply and reset the alarms.
The average of the recorded operating times for the three phases should typically be less than 20 ms for 50 Hz,
and less than 16.7 ms for 60 Hz when set for instantaneous operation.
Note:
Where a non-zero time delay is set in the DISTANCE menu column, the expected operating time is typically within +/- 5% of
the delay setting plus the “instantaneous” delay.
Note:
The device allows separate time delay settings for phase (“Ph”) and ground (“Gnd”) fault elements. BOTH must be checked to
ensure that they have been set correctly.
P54-TM-EN-1.1 815
Chapter 27 - Commissioning Instructions P54
If an InterMiCOM64 scheme is used to provide the signalling, the scheme logic may not use opto-inputs for the
aided scheme implementation. In this case, internal DDB signals need to be set or reset to test the operation of the
protection scheme.
Use the IM64 Test Mode with the IM64 Test Pattern to assert or monitor the relevant signals.
Ensure that the injection test set timer is still connected to measure the time taken for the device to trip. A series of
fault injections are applied, with a Zone 1, end-of-line, or Zone 4 fault simulated. At this stage, note the method in
which each fault is applied, but do not inject yet:
● Zone 1 fault: A dynamic forward A-B fault at half the Zone 1 reach is simulated.
● End of line fault: A dynamic forward A-B fault at the remote end of the line is simulated. The fault
impedance simulated should match the LINE PARAMETERS > Line Impedance setting.
● Zone 4 fault: A dynamic reverse A-B fault at half the Zone 4 reach is simulated.
The following table indicates the expected response for various test situations for a conventional signalling
scheme.
IED RESPONSE
Forward fault in Forward fault at end of line
Fault type simulated Reverse fault in zone 4
zone 1 (within Z1X/Z2)
Signal receive opto ON OFF ON OFF ON OFF
Zone 1 extension Trip Trip No Trip Trip No Trip No Trip
Trip, Trip, No Trip, No Signal Trip, No Trip, Signal No Trip, Signal
Blocking scheme
No Signal Send No Signal Send Send No Signal Send Send Send
Permissive Scheme Trip, No Trip, No Signal No Trip, No Signal No Trip, No Signal
Trip, Signal Send Trip, Signal Send
(PUR/PUTT) No Signal Send Send Send Send
Permissive Scheme No Trip, Signal No Trip, No Signal No Trip, No Signal
Trip, Signal Send Trip, Signal Send Trip, Signal Send
(POR/POTT) Send Send Send
Note:
Here a non-zero tZ1 Ph or tZ1 Gnd time delay is set in the DISTANCE column, the expected operating time is typically within
+/- 5% of the tZ1 setting plus the “instantaneous” delay quoted above.
816 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Note:
Where a non-zero Aided Distance Dly time delay is set in the DISTANCE menu column, the expected operating time is typically
within +/- 5% of the tZ1 setting plus the “instantaneous” delay quoted above.
Note:
For blocking schemes, a non-zero Aided Distance Dly time delay is set, so the expected operating time is typically within +/-
5% of the delay setting plus the “instantaneous” operating delay. The trip time should thus be less than 20 ms for 50 Hz, and
less than 16.7 ms for 60 Hz, plus 1.05 x Delay setting.
P54-TM-EN-1.1 817
Chapter 27 - Commissioning Instructions P54
818 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
13.1.1 PRELIMINARIES
Use a three-phase digital/electronic injection test set to make the commissioning procedure easier.
Connect the test equipment to the device using the test block(s) taking care not to open-circuit any CT secondary.
If MMLG type test blocks are used, the live side of the test plug must be provided with shorting links before it is
inserted into the test block.
If an InterMiCOM64 scheme is used to provide the signalling, the scheme logic may not use opto-inputs for the
aided scheme implementation. In this case, internal DDB signals need to be set or reset to test the operation of the
protection scheme.
Use the IM64 Test Mode with the IM64 Test Pattern to assert or monitor the relevant signals.
IED RESPONSE
Direction of fault test
Forward fault Reverse fault
injection
Signal receive opto ON OFF ON OFF
No Trip, Trip, No Trip, No Trip,
Blocking scheme
No Signal Send No Signal Send Signal Send Signal Send
Permissive scheme (POR/ Trip, No Trip, No Trip, No Trip,
POTT) Signal Send Signal Send No Signal Send No Signal Send
P54-TM-EN-1.1 819
Chapter 27 - Commissioning Instructions P54
13.2.1 PHASE A
1. Prepare a dynamic A-phase-to-neutral fault, as detailed above.
2. Set a timer to start when the fault injection is applied and to stop when the trip occurs.
3. To verify correct output contact mapping use the trip contacts that would be expected to trip the circuit
breaker(s) (Any Trip for 3-pole tripping, Trip A for single pole tripping).
4. For two breaker applications, stop the timer when CB1 and CB2 trip contacts have both closed. Monitor by
connecting the contacts in series to stop the timer if necessary.
5. Record the phase A trip time.
6. Switch OFF the AC supply and reset the alarms.
13.2.2 PHASE B
1. Reconfigure to test a B phase fault.
2. Repeat the test, this time ensuring that the breaker trip contacts relative to B phase operation close
correctly.
3. Record the phase B trip time.
4. Switch OFF the AC supply and reset the alarms.
13.2.3 PHASE C
1. Reconfigure to test a C phase fault.
2. Repeat the test, this time ensuring that the breaker trip contacts relative to C phase operation close
correctly.
3. Record the phase C trip time.
4. Switch OFF the AC supply and reset the alarms.
The average of the recorded operating times for the three phases should typically be less than 20 ms for 50 Hz,
and less than 16.7 ms for 60 Hz when set for instantaneous operation.
Note:
Where a non-zero time delay is set in the DISTANCE menu column, the expected operating time is typically within +/- 5% of
the delay setting plus the “instantaneous” delay.
820 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Caution:
When the tests are completed, restore all settings that were disabled for testing
purposes.
Caution:
Remove any wires or leads temporarily fitted to energise the channel receive opto-
input.
P54-TM-EN-1.1 821
Chapter 27 - Commissioning Instructions P54
If these elements are enabled with a dependency upon the above conditions, it is necessary to simulate the
condition to test the correct operation of the protection function.
A communications failure can be simulated by setting the Test Loopback cell to Disabled and checking that the IED
raises a Comms Fail alarm.
At the end of the test, clear the communications alarms and reset the statistics.
A VTS alarm can be raised by applying a 3-phase voltage to the VT inputs and then removing one phase voltage
for a duration exceeding the VTS Time Delay setting.
At the end of the tests, clear the VTS alarm.
If an InterMiCOM64 scheme is used to provide the signalling, the scheme logic may not use opto-inputs for the
aided scheme implementation. In this case, internal logic signals (DDBs) need to be set or reset to test the
operation of the protection scheme.
The IM64 Test Mode in conjunction with the IM64 Test Pattern should be used to assert or monitor the relevant
signals.
This set of injection tests aims to determine that a single device, at one end of the scheme is performing correctly.
Note:
The device must be tested in isolation, with the communications channel to the remote line terminal disconnected.
822 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
14.2.1 PRELIMINARIES
1. Determine which output relays have been selected to operate when a DEF trip occurs, by viewing the
programmable scheme logic. If the trip outputs are phase segregated (a different output relay allocated for
each phase), the output relay assigned for tripping on ‘A’ phase faults should be used.
2. Connect the output relay so that its operation will trip the test set and stop the timer.
3. Connect the current output of the test set to the ‘A’ phase current transformer input
4. Connect, all three phase voltages Va, Vb, and Vc.
5. Depending on the test equipment used, make sure the timer is set to start when the current is applied.
P54-TM-EN-1.1 823
Chapter 27 - Commissioning Instructions P54
Caution:
When the tests are completed, restore all settings that were disabled for testing
purposes.
Caution:
Remove any wires or leads temporarily fitted to energise the channel receive opto-
input.
824 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
+jX
Z6
Z5
State 4
State 3
State 2
State 1
R
R6' R5' R5 R6
∆R
Z5'
Z6'
V01451
Depending on the Out of Step (OST) settings, use one of the following setting options.
● OST setting
● Predictive OST setting
● Predictive and OST setting
Now apply the 4-state sequence, check that all 3-phases have tripped and that an OST alarm is displayed on the
local LCD.
P54-TM-EN-1.1 825
Chapter 27 - Commissioning Instructions P54
Note:
The angle in the table above is the angle between voltages and their respective currents. In state 4 the currents are displaced
180° from their respective voltages.
Now apply the 3-state sequence, check that all 3-phases have tripped and that an OST alarm is displayed on the
local LCD.
826 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
If these elements are enabled with a dependency upon the above conditions, it is necessary to simulate the
condition to test the correct operation of the protection function.
A communications failure can be simulated by setting the Test Loopback cell to Disabled and checking that the IED
raises a Comms Fail alarm.
At the end of the test, clear the communications alarms and reset the statistics.
A VTS alarm can be raised by applying a 3-phase voltage to the VT inputs and then removing one phase voltage
for a duration exceeding the VTS Time Delay setting.
At the end of the tests, clear the VTS alarm.
Note:
If using the default PSL, use output relay 3 as this is already mapped to the DDB signal Trip Command Out.
P54-TM-EN-1.1 827
Chapter 27 - Commissioning Instructions P54
4. Connect the output relay so that its operation will trip the test set and stop the timer.
5. Connect the current output of the test set to the A-phase current transformer input.
If the I>1 Directional cell in the OVERCURRENT column is set to Directional Fwd, the current should
flow out of terminal 2. If set to Directional Rev, it should flow into terminal 2.
If the I>1 Directional cell in the OVERCURRENT column has been set to Directional Fwd or
Directional Rev, the rated voltage should be applied to terminals 20 and 21.
6. Ensure that the timer starts when the current is applied.
Note:
If the timer does not stop when the current is applied and stage 1 has been set for directional operation, the connections may
be incorrect for the direction of operation set. Try again with the current connections reversed.
Note:
With the exception of the definite time characteristic, the operating times given are for a Time Multiplier Setting (TMS) or Time
Dial Setting (TDS) of 1. For other values of TMS or TDS, the values need to be modified accordingly.
Note:
For definite time and inverse characteristics there is an additional delay of up to 0.02 second and 0.08 second respectively.
You may need to add this the IED's acceptable range of operating times.
828 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Caution:
On completion of the tests, you must restore all settings to customer specifications.
P54-TM-EN-1.1 829
Chapter 27 - Commissioning Instructions P54
In most cases the line VT input is three phase, whereas the bus VTs are single phase.
The bus VT inputs are normally single phase so the system voltage checks are made on single phases and the VT
may be connected to either a phase-to-phase or phase to neutral voltage.
For these reasons, the IED has to be programmed with the appropriate connection. The CS Input setting in the CT
AND VT RATIOS column can be set to A-N, B-N, C-N, A-B, B-C or C-A according to the application.
The single-phase bus VT inputs each have associated phase shift and voltage magnitude compensation settings
to compensate for healthy voltage angle and magnitude differences between the check sync VT input and the
selected main VT reference phase. These are:
● CS VT Ph Shift and CS VT Mag
Any voltage measurements or comparisons using bus VT inputs are made using the compensated values.
Each circuit breaker controlled can have two stages of check synchronism enabled according to the settings:
● System Checks, CS1 Status and CS2 Status
When the system voltage check conditions are satisfied, the relevant DDB signals are asserted high as follows:
● DDB (883): Check Sync 1 OK
● DDB (884): Check Sync 2 OK
These DDB signals should be mapped to the monitor/download port and used to indicate that the system check
synchronism condition has been satisfied.
830 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
1. To test the first three-phase auto-reclose cycle, set COMMISSION TESTS > Test Autoreclose to Trip 3
Pole. The IED performs a trip/reclose cycle.
2. Repeat this operation to test the subsequent three-phase auto-reclose cycles.
3. Check all output relays (used for such as circuit breaker tripping and closing, or blocking other devices)
operate at the correct times during the trip/close cycle.
Check the auto-reclose cycles for single phase trip conditions one at a time by sequentially setting COMMISSION
TESTS > Test Autoreclose to Trip Pole A, Trip Pole B and Trip Pole C.
P54-TM-EN-1.1 831
Chapter 27 - Commissioning Instructions P54
If the IED is being used in a scheme with InterMiCOM64 communications you must perform end-to-end testing of
the protection communications channels.
In this section all loopbacks are removed and satisfactory communications between line ends of the IEDs in the
scheme are confirmed.
Note:
End-to-end communication requires a working telecommunication channel between line ends (which may be a multiplexed
link or may be a direct connection). If the telecommunication channel is not available, it is not possible to establish end-to end
communication. Unless otherwise directed by local operational practise, follow the instructions in this section so the scheme
is ready for full operation when the telecommunications channels become available.
Note:
The trip circuit should remain isolated during these checks to prevent accidental operation of the associated circuit breaker.
Note:
Most of the required optical signal power levels have already been measured and recorded. If all signalling uses P59x
interface units, no further measurements are required. If, however, 56/64 kb/s or C37.94 direct fibre communications are
used, further measurements are needed.
Warning:
NEVER look directly into the transmit port or the end of an optical fibre, as this could
severely damage your eyes.
832 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Warning:
NEVER look directly into the transmit port or the end of an optical fibre, as this could
severely damage your eyes.
P54-TM-EN-1.1 833
Chapter 27 - Commissioning Instructions P54
3. Check that the first two bits in ‘Channel Status’ (Rx and Tx) are displaying ‘1’ (11************ where *
indicates a ‘don’t care’ state).
4. Clear the statistics and record the number of valid messages and the number of errored messages after a
minimum period of 1 hour.
5. Check that the ratio of errored/good messages is better than 10-4.
6. Record the measured message propagation delays for channel 1, and channel 2 (if fitted).
834 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
X = Don't Care
Now return the IED to service by setting COMMISSION TESTS > Test Mode to Disabled.
P54-TM-EN-1.1 835
Chapter 27 - Commissioning Instructions P54
836 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
21 ONLOAD CHECKS
Warning:
Onload checks are potentially very dangerous and may only be carried out by
qualified and authorised personnel.
Onload checks can only be carried out if there are no restrictions preventing the energisation of the plant, and the
other devices in the group have already been commissioned.
Remove all test leads and temporary shorting links, then replace any external wiring that has been removed to
allow testing.
Warning:
If any external wiring has been disconnected for the commissioning process, replace
it in accordance with the relevant external connection or scheme diagram.
If the Local Values cell is set to Secondary, the values displayed should be equal to the applied secondary
voltage. The values should be within 1% of the applied secondary voltages. However, an additional allowance must
be made for the accuracy of the test equipment being used.
If the Local Values cell is set to Primary, the values displayed should be equal to the applied secondary voltage
multiplied the corresponding voltage transformer ratio set in the CT & VT RATIOS column. The values should be
within 1% of the expected values, plus an additional allowance for the accuracy of the test equipment being used.
P54-TM-EN-1.1 837
Chapter 27 - Commissioning Instructions P54
If the Local Values cell is set to Secondary, the values displayed should be equal to the applied secondary
voltage. The values should be within 1% of the applied secondary voltages. However, an additional allowance must
be made for the accuracy of the test equipment being used.
If the Local Values cell is set to Primary, the values displayed should be equal to the applied secondary voltage
multiplied the corresponding voltage transformer ratio set in the CT & VT RATIOS column. The values should be
within 1% of the expected values, plus an additional allowance for the accuracy of the test equipment being used.
Note:
This check applies only for Measurement Modes 0 (default), and 2. This should be checked in the MEASURE’T SETUP column
(Measurement Mode = 0 or 2). If measurement modes 1 or 3 are used, the expected power flow signing would be opposite to
that shown above.
In the event of any uncertainty, check the phase angle of the phase currents with respect to their phase voltage.
838 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
22 FINAL CHECKS
1. Remove all test leads and temporary shorting leads.
2. If you have had to disconnect any of the external wiring in order to perform the wiring verification tests,
replace all wiring, fuses and links in accordance with the relevant external connection or scheme diagram.
3. The settings applied should be carefully checked against the required application-specific settings to ensure
that they are correct, and have not been mistakenly altered during testing.
4. Ensure that all protection elements required have been set to Enabled in the CONFIGURATION column.
5. Ensure that the IED has been restored to service by checking that the Test Mode cell in the COMMISSION
TESTS column is set to Disabled.
6. If the IED is in a new installation or the circuit breaker has just been maintained, the circuit breaker
maintenance and current counters should be zero. These counters can be reset using the Reset All Values
cell. If the required access level is not active, the device will prompt for a password to be entered so that the
setting change can be made.
7. If the menu language has been changed to allow accurate testing it should be restored to the customer’s
preferred language.
8. If a P991/MMLG test block is installed, remove the P992/MMLB test plug and replace the cover so that the
protection is put into service.
9. Ensure that all event records, fault records, disturbance records, alarms and LEDs and communications
statistics have been reset.
Note:
Remember to restore the language setting to the customer’s preferred language on completion.
P54-TM-EN-1.1 839
Chapter 27 - Commissioning Instructions P54
Warning:
Check the rating information under the top access cover on the front of the IED.
Warning:
Check that the IED being tested is correct for the line or circuit.
Warning:
Record the circuit reference and system details.
Warning:
Check the CT secondary current rating and record the CT tap which is in use.
Carefully examine the IED to see that no physical damage has occurred since installation.
Ensure that the case earthing connections (bottom left-hand corner at the rear of the IED case) are used to
connect the IED to a local earth bar using an adequate conductor.
23.2 INSULATION
Insulation resistance tests are only necessary during commissioning if explicitly requested.
Isolate all wiring from the earth and test the insulation with an electronic or brushless insulation tester at a DC
voltage not exceeding 500 V. Terminals of the same circuits should be temporarily connected together.
The insulation resistance should be greater than 100 MW at 500 V.
On completion of the insulation resistance tests, ensure all external wiring is correctly reconnected to the IED.
Note:
The V.35 circuits and the X.21 circuits of the P592 and P593 respectively are isolated from all other circuits but are electrically
connected to the outer case. The circuits must therefore not be insulation or impulse tested to the case.
Caution:
Check that the external wiring is correct according to the relevant IED and scheme
diagrams. Ensure that phasing/phase rotation appears to be as expected.
840 P54-TM-EN-1.1
P54 Chapter 27 - Commissioning Instructions
Warning:
Do not energise the device or interface unit using the battery charger with the
battery disconnected as this can irreparably damage the power supply circuitry.
P592 only
The four red LEDs can be tested by appropriate setting of the DIL switches on the front plate. Set the data rate
switch according to the communication channel bandwidth available. Set all other switches to 0. To illuminate the
‘DSR OFF’ and ‘CTS OFF’ LED’s, disconnect the V.35 connector from the rear of the P592 and set the ‘DSR’ and ‘CTS’
switches to ‘0’. The ‘OPTO LOOPBACK’ and ‘V.35 LOOPBACK’ LEDs can be illuminated by setting their corresponding
switches to ‘1’.
Once operation of the LEDs has been established set all DIL switches, except for the ‘OPTO LOOPBACK’ switch, to ‘0’
and reconnect the V.35 connector.
P593 only
Set the ‘X.21 LOOPBACK’ switch to ‘ON’. The green ‘CLOCK’ and red ‘X.21 LOOPBACK’ LED’s should illuminate. Reset
the ‘X.21 LOOPBACK’ switch to the ‘OFF’ position.
Set the ‘OPTO LOOPBACK’ switch to ‘ON’. The red ‘OPTO LOOPBACK’ LED should illuminate. Do not reset the “OPTO
LOOPBACK’ switch as it is required in this position for the next test.
Warning:
NEVER look directly into the transmit port or the end of an optical fibre, as this could
severely damage your eyes.
P54-TM-EN-1.1 841
Chapter 27 - Commissioning Instructions P54
P591
It is necessary to loop the transmitted electrical G.703 signal presented on terminals 3 and 4 of the P591 to the
received signal presented on terminals 7 and 8.
If test links have been designed into the scheme to facilitate this they should be used. Alternatively, remove any
external wiring from terminals 3, 4, 7 and 8 at the rear of each P591 unit. Loopback the G.703 signals on each
device by connecting a wire link between terminals 3 and 7, and a second wire between terminals 4 and 8.
P592
With the ‘OPTO LOOPBACK’ switch in the ‘1’ position, the receive and transmit optical ports are connected together.
This allows the optical fibre communications between the IED and the P592 to be tested, but not the internal
circuitry of the P592 itself.
P593
Set the ‘OPTO LOOPBACK’ switch to ‘OFF’ and ‘X.21 LOOPBACK’ switch to ‘ON’ respectively. With the ‘X.21
LOOPBACK’ switch in this position the ‘Receive Data’ and ‘Transmit Data’ lines of the X.21 communication interface
are connected together. This allows the optical fibre communications between the IED and the P593, and the
internal circuitry of the P593 itself to be tested.
842 P54-TM-EN-1.1
CHAPTER 28
844 P54-TM-EN-1.1
P54 Chapter 28 - Maintenance and Troubleshooting
1 CHAPTER OVERVIEW
The Maintenance and Troubleshooting chapter provides details of how to maintain and troubleshoot products
based on the Px4x and P40Agile platforms. Always follow the warning signs in this chapter. Failure to do so may
result injury or defective equipment.
Caution:
Before carrying out any work on the equipment you should be familiar with the
contents of the Safety Section or the Safety Guide SFTY/4LM and the ratings on the
equipment’s rating label.
The troubleshooting part of the chapter allows an error condition on the IED to be identified so that appropriate
corrective action can be taken.
If the device develops a fault, it is usually possible to identify which module needs replacing. It is not possible to
perform an on-site repair to a faulty module.
If you return a faulty unit or module to the manufacturer or one of their approved service centres, you should
include a completed copy of the Repair or Modification Return Authorization (RMA) form.
This chapter contains the following sections:
Chapter Overview 845
Maintenance 846
Troubleshooting 854
P54-TM-EN-1.1 845
Chapter 28 - Maintenance and Troubleshooting P54
2 MAINTENANCE
Although some functionality checks can be performed from a remote location, these are predominantly restricted
to checking that the unit is measuring the applied currents and voltages accurately, and checking the circuit
breaker maintenance counters. For this reason, maintenance checks should also be performed locally at the
substation.
Caution:
Before carrying out any work on the equipment you should be familiar with the
contents of the Safety Section or the Safety Guide SFTY/4LM and the ratings on the
equipment’s rating label.
2.1.1 ALARMS
First check the alarm status LED to see if any alarm conditions exist. If so, press the Read key repeatedly to step
through the alarms.
After dealing with any problems, clear the alarms. This will clear the relevant LEDs.
2.1.2 OPTO-ISOLATORS
Check the opto-inputs by repeating the commissioning test detailed in the Commissioning chapter.
846 P54-TM-EN-1.1
P54 Chapter 28 - Maintenance and Troubleshooting
Caution:
Replacing PCBs requires the correct on-site environment (clean and dry) as well as
suitably trained personnel.
Caution:
If the repair is not performed by an approved service centre, the warranty will be
invalidated.
Caution:
Before carrying out any work on the equipment, you should be familiar with the
contents of the Safety Information section of this guide or the Safety Guide SFTY/4LM,
as well as the ratings on the equipment’s rating label. This should ensure that no
damage is caused by incorrect handling of the electronic components.
Warning:
Before working at the rear of the device, isolate all voltage and current supplying it.
Note:
The current transformer inputs are equipped with integral shorting switches which will close for safety reasons, when the
terminal block is removed.
P54-TM-EN-1.1 847
Chapter 28 - Maintenance and Troubleshooting P54
Caution:
If the top and bottom access covers have been removed, some more screws with
smaller diameter heads are made accessible. Do NOT remove these screws, as they
secure the front panel to the device.
Note:
There are four possible types of terminal block: RTD/CLIO input, heavy duty, medium duty, and MiDOS. The terminal blocks are
fastened to the rear panel with slotted or cross-head screws depending on the type of terminal block. Not all terminal block
types are present on all products.
Warning:
Before removing the front panel to replace a PCB, you must first remove the auxiliary
power supply and wait 5 seconds for the internal capacitors to discharge. You should
also isolate voltage and current transformer connections and trip circuit.
848 P54-TM-EN-1.1
P54 Chapter 28 - Maintenance and Troubleshooting
Caution:
Before removing the front panel, you should be familiar with the contents of the Safety
Information section of this guide or the Safety Guide SFTY/4LM, as well as the ratings
on the equipment’s rating label.
Caution:
Do not remove the screws with the larger diameter heads which are accessible when
the access covers are fitted and open. These screws hold the relay in its mounting
(panel or cubicle).
Caution:
The internal circuitry is now exposed and is not protected against electrostatic
discharge and dust ingress. Therefore ESD precautions and clean working conditions
must be maintained at all times.
Note:
To ensure compatibility, always replace a faulty PCB with one of an identical part number.
P54-TM-EN-1.1 849
Chapter 28 - Maintenance and Troubleshooting P54
Note:
After replacing the main processor board, all the settings required for the application need to be re-entered. This may be done
either manually or by downloading a settings file.
V01601
850 P54-TM-EN-1.1
P54 Chapter 28 - Maintenance and Troubleshooting
6. Fit the replacement PCB carefully into the correct slot. Make sure it is pushed fully back and that the
securing screws are refitted.
7. Reconnect all connections at the rear.
8. Refit the front panel.
9. Refit and close the access covers then press the hinge assistance T-pieces so they click back into the front
panel moulding.
10. Once the unit has been reassembled, commission it according to the Commissioning chapter.
Caution:
With non-mounted IEDs, the case needs to be held firmly while the module is
withdrawn. Withdraw the input module with care as it suddenly comes loose once the
friction of the terminal blocks is overcome.
Note:
If individual boards within the input module are replaced, recalibration will be necessary. We therefore recommend
replacement of the complete module to avoid on-site recalibration.
Caution:
Before removing the front panel, you should be familiar with the contents of the Safety
Information section of this guide or the Safety Guide SFTY/4LM, as well as the ratings
on the equipment’s rating label.
P54-TM-EN-1.1 851
Chapter 28 - Maintenance and Troubleshooting P54
The power supply board is fastened to an output relay board with push fit nylon pillars. This doubled-up board is
secured on the extreme left hand side, looking from the front of the unit.
1. Remove front panel.
2. Pull the power supply module forward, away from the rear terminal blocks and out of the case. A
reasonable amount of force is needed due to the friction between the contacts of the terminal blocks.
3. Separate the boards by pulling them apart carefully. The power supply board is the one with two large
electrolytic capacitors.
4. Before reassembling the module, check that the number on the round label next to the front edge of the
PCB matches the slot number into which it will be fitted. If the slot number is missing or incorrect, write the
correct slot number on the label
5. Reassemble the module with a replacement PCB. Push the inter-board connectors firmly together. Fit the
four push fit nylon pillars securely in their respective holes in each PCB.
6. Slot the power supply module back into the housing. Push it fully back onto the rear terminal blocks.
7. Refit the front panel.
8. Refit and close the access covers then press the hinge assistance T-pieces so they click back into the front
panel moulding.
9. Once the unit has been reassembled, commission it according to the Commissioning chapter.
2.6 RECALIBRATION
Recalibration is not needed when a PCB is replaced, unless it is one of the boards in the input module. If any of the
boards in the input module is replaced, the unit must be recalibrated.
Although recalibration is needed when a board inside the input module is replaced, it is not needed if the input
module is replaced in its entirety.
Although it is possible to carry out recalibration on site, this requires special test equipment and software. We
therefore recommend that the work be carried out by the manufacturer, or entrusted to an approved service
centre.
852 P54-TM-EN-1.1
P54 Chapter 28 - Maintenance and Troubleshooting
threshold. The SuperCap Alarm will clear after approximately 30 minutes of IED being energised, and once cleared
there will be enough charge in the supercapacitor to maintain the RTC.
Note:
The Real Time Clock will be reset if the supercapacitor is fully discharged.
2.8 CLEANING
Warning:
Before cleaning the device, ensure that all AC and DC supplies and transformer
connections are isolated, to prevent any chance of an electric shock while cleaning.
Only clean the equipment with a lint-free cloth dampened with clean water. Do not use detergents, solvents or
abrasive cleaners as they may damage the product's surfaces and leave a conductive residue.
P54-TM-EN-1.1 853
Chapter 28 - Maintenance and Troubleshooting P54
3 TROUBLESHOOTING
854 P54-TM-EN-1.1
P54 Chapter 28 - Maintenance and Troubleshooting
P54-TM-EN-1.1 855
Chapter 28 - Maintenance and Troubleshooting P54
856 P54-TM-EN-1.1
P54 Chapter 28 - Maintenance and Troubleshooting
P54-TM-EN-1.1 857
Chapter 28 - Maintenance and Troubleshooting P54
858 P54-TM-EN-1.1
P54 Chapter 28 - Maintenance and Troubleshooting
If required, an acceptance of the quote must be delivered before going to the next stage.
5. Send the product to the repair centre
○ Address the shipment to the repair centre specified by your local contact
○ Make sure all items are packaged in an anti-static bag and foam protection
○ Make sure a copy of the import invoice is attached with the returned unit
○ Make sure a copy of the RMA form is attached with the returned unit
○ E-mail or fax a copy of the import invoice and airway bill document to your local contact.
P54-TM-EN-1.1 859
Chapter 28 - Maintenance and Troubleshooting P54
860 P54-TM-EN-1.1
CHAPTER 29
TECHNICAL SPECIFICATIONS
Chapter 29 - Technical Specifications P54
862 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
1 CHAPTER OVERVIEW
This chapter describes the technical specifications of the product.
This chapter contains the following sections:
Chapter Overview 863
Interfaces 864
Protection Functions 869
Performance of Voltage Protection Functions 875
Performance of Frequency Protection Functions 878
Power Protection Functions 880
Monitoring, Control and Supervision 881
Measurements and Recording 883
Ratings 884
Input/Output Connections 887
Mechanical Specifications 889
Type Tests 890
Environmental Conditions 891
Electromagnetic Compatibility 892
P54-TM-EN-1.1 863
Chapter 29 - Technical Specifications P54
2 INTERFACES
Graphical HMI
Screen size 4.0" diagonal
Display format 480 x 480 Dots
Number of colour 16.7M
Dimensions 77 mm (H) x 80 mm (V) x 2.3 mm (D)
Active area 71.86 mm (H) x 70.18 mm (V)
Display mode Transmissive/normally black
Viewing direction All round
Backlight type LED, white
Operating temperature -30°C ~ + 85°C
Storage temperature -40°C ~ + 90°C
864 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
P54-TM-EN-1.1 865
Chapter 29 - Technical Specifications P54
866 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
Optical budget
850nm MM 1300 nm MM 1300 nm SM 1550 nm SM
Minimum transmit output level (average power) -19.8 dBm -6 dBm -6 dBm -6 dBm
Receiver sensitivity (average power) -25.4 dBm -49 dBm -49 dBm -49 dBm
Optical budget 5.6 dB 43 dB 43 dB 43 dB
Less safety margin (3 dB) 2.6 dB 40 dB 40 dB 40 dB
Typical cable loss 2.6 dB/km 0.8 dB/km 0.4 dB/km 0.3 dB/km
P54-TM-EN-1.1 867
Chapter 29 - Technical Specifications P54
868 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
3 PROTECTION FUNCTIONS
Accuracy
Pick-up Formula +/- 10%
Drop-off 0.75 x Formula +/- 10%
IDMT characteristic shape +/- 5% or 40 ms, whichever is greater
DT operation +/- 2% or 20 ms, whichever is greater
Typical instantaneous operation with default settings,
back-to-back propagation delay included
50 Hz, 1 p.u. ≤ relay current < 2 p.u. <35 ms
60 Hz, 1 p.u. ≤ relay current < 2 p.u. <30 ms
50 Hz, relay current ≥ 2 p.u. <30 ms
60 Hz, relay current ≥ 2 p.u. <25 ms
Reset time <60 ms
Repeatability +/- 2.5%
UK curves IEC 60255-151: 2009
Characteristic
US curves IEEE C37.112 – 1996
Vector compensation No affect on accuracy
Current transformer ratio compensation No affect on accuracy
High set characteristic setting No affect on accuracy
Three ended scheme operation No affect on accuracy
Accuracy
Pick-up Formula +/- 10%
Drop-off 0.75 x Formula +/- 10%
DT operation +/- 2% or 40 ms, whichever is greater
Typical instantaneous operation with default settings
and IN Differential > 50% above threshold
50 Hz 30-50 ms
60 Hz 25-42 ms
Repeatability +/- 2.5%
Current transformer ratio compensation No affect on accuracy
Three ended scheme operation No affect on accuracy
P54-TM-EN-1.1 869
Chapter 29 - Technical Specifications P54
Tripping characteristics
50 Hz, SIR = 5
60 Hz, SIR = 5
Operating time for resistive faults > 20% inside the 50 Hz, up to SIR = 30 < 30 ms
characteristic 60 Hz, up to SIR = 30 < 25 ms
Accuracy
+/- 5% for on-angle fault (on the set line angle)
+/- 10% for off-angle fault
Characteristic shape, up to SIR = 30
Example: For a 70 degree set line angle, injection testing at 40 degrees
would be referred to as "off-angle".
Zone time delay deviations +/- 20 ms or 2%, whichever is greater
Accuracy
Accuracy of zones and timers As per Distance
870 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
Accuracy
Accuracy of zones and timers As per Distance
Operating range Up to 7 Hz
The table below shows the minimum and maximum transfer time for InterMiCOM64 (IM64). The times are
measured from opto initialization (with no opto filtering) to relay standard output and include a small propagation
delay for back-back test.
IDiff IM64 indicates InterMiCOM64 signals working in conjunction with the differential protection fibre optic
communications channel. IM64 indicates InterMiCOM64 signals working as a standalone feature.
MaxCh1 Prop Delay
Configuration Signals Permissive Op Times (ms) Direct Op Times (ms)
Measured
IM64 at 56kbps 8 18-21 21-24 1.6ms
IM64 at 64kbps 8 18-21 21-24 1.3ms
IM64 at 128kbps 24 17-20 20-23 1.4ms
IDiff IM64 at 56kbps 8 24-26 29-31 3.3ms
IDiff IM64 at 64kbps 8 24-26 29-31 2.9ms
IDiff IM64 at 128kbps 32 20-26 24-31 1.9ms
Accuracy
Timers +/- 20 ms or 2%, whichever is greater
Accuracy
IDMT pick-up 1.05 x Setting +/-5%
DT pick-up Setting +/-5%
Drop-off (IDMT and DT) 0.98 x setting +/-5%
IDMT operate +/-5% of expected operating time or 40 ms, whichever is greater*
IEEE reset +/-5% or 40 ms, whichever is greater**
+/-2% of setting or 40 ms, whichever is greater (Non Directional)**
DT operate time
+/-2% of setting or 60 ms, whichever is greater (Directional)
DT reset Setting +/-5%
Repeatability <5%
Characteristic UK IEC 60255-151: 2009
Characteristic US IEEE C37.112 1996
Note:
*Reference conditions: TMS = 1, TD = 7, I> = 1A, operating range = 2-20In
**Reference conditions: Injected value is 2 x pick-up value.
P54-TM-EN-1.1 871
Chapter 29 - Technical Specifications P54
Additional tolerance due to increasing X/R ratios +/-5% over the X/R ratio of 1 to 90
Overshoot of overcurrent elements < 30 ms
Accuracy
Directional boundary pickup (RCA +/-90%) +/-2°
Directional boundary hysteresis < 2°
Directional boundary repeatability <2%
Accuracy
IDMT pick-up 1.05 x Setting +/-5%
DT pick-up Setting +/-5%, or 20 mA, whichever is greater
Drop-off (IDMT and DT) 0.95 x setting +/-5%
+/- 5% or 60 ms, whichever is greater (1.05 - 2) Is
IDMT Operate
+/- 5% or 40 ms, whichever is greater (2 - 20) Is
IEEE reset +/-10% or 40 ms, whichever is greater
Repeatability < 5%
+/- 2% or 70 ms, whichever is greater (1.05 - 2) Is
DT operate
+/- 2% or 55 ms, whichever is greater (2 - 20) Is
DT reset +/- 5% or 50 ms, whichever is greater
872 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
Note:
SEF claims apply to SEF input currents of no more than 2 x In. For input ranges above 2 x In, the claim is not supported.
Wattmetric SEF
Pick-up P = 0 W ISEF > +/-5% or 5 mA
Pick-up P > 0 W P > +/-5%
Drop-off P = 0 W 0.95 x ISEF> +/- 5% or 5 mA
Drop-off P > 0 W 0.9 x P> +/- 5% or 5 mA
Boundary accuracy +/-5% with hysteresis < 1°
Repeatability < 1%
P54-TM-EN-1.1 873
Chapter 29 - Technical Specifications P54
Note:
Operating time measured with applied current of 20% above thermal setting.
874 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
P54-TM-EN-1.1 875
Chapter 29 - Technical Specifications P54
Reset < 75 ms
Repeatability < 1%
Overvoltage Accuracy
Pick-up Setting +/-3% or +/- 0.1 V, whichever is greater
Drop-off (0.98 x setting) +/-3% or +/- 0.1 V, whichever is greater
Repeatability < 1%
Undervoltage Accuracy
Pick-up Setting +/-3% or +/- 0.1 V, whichever is greater
Drop-off (1.02 x setting) +/-3% or +/- 0.1 V, whichever is greater
Repeatability < 1%
Accuracy (CS1/CS2)
Phase Angle
Pick-up (Setting-2°) ±1° *
Drop-off (Setting-1°) ±1° *
Repeatability <1%
Slip Frequency
Pick-up Setting ±0.01 Hz
Drop-off (0.95 x Setting) ±0.01 Hz
Repeatability <1%
Slip Timer
876 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
Accuracy (CS1/CS2)
Timers +/- 1% or 40 ms, whichever is greater
Reset Time <30 ms
Repeatability <10 ms
Note:
* CS VT Ph Shift setting = 0°
SS Undervoltage Accuracy
Pick-up Setting +/- 3 %
Drop-off 1.02 x setting
Repeatability < 1%
SS Timer
Timers Setting +/- 1% or 40 ms, whichever is greater
Reset time < 30 ms
Repeatability < 10 ms
P54-TM-EN-1.1 877
Chapter 29 - Technical Specifications P54
Accuracy
Pick-up Setting +/- 10 mHz
Drop-off Setting -20 mHz +/- 10 mHz
Operating timer +/- 2% or 50 ms, whichever is greater
Reference conditions: Tested using step changed in frequency with Freq. Av Cycles setting = 0 and no intentional
time delay.
Fs = start frequency – frequency setting
Ff = frequency setting – end frequency
Accuracy
Pick-up Setting +/- 10 mHz
Drop-off Setting + 20 mHz +/- 10 mHz
Operating timer +/- 2% or 50 ms, whichever is greater
Reference conditions: Tested using step changed in frequency with Freq. Av Cycles setting = 0 and no intentional
time delay.
Fs = start frequency – frequency setting
Ff = frequency setting – end frequency
Accuracy
Pick-up (df/dt) Setting +/- 50 mHz
Operating timer +/- 2% or 50 ms, whichever is greater
878 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
Operating
For 6 Cycles:
Operating time (for ramps 1.5 x setting and greater) <300 ms
For 12 Cycles:
Operating time (for ramps 1.5 x setting and greater) <500 ms
Reference Conditions: Tested with df/dt Average Cycles = 6 and 12 for df/dt settings greater than 0.1 Hz/s, and no
intentional time delay.
P54-TM-EN-1.1 879
Chapter 29 - Technical Specifications P54
880 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
Accuracy
I1> Pick-up Setting +/- 5%
I1> Drop-off 0.9 x setting +/- 5%
I2/I1> Pick-up Setting +/- 5%
I2/I1> Drop-off 0.9 x setting +/-5%
I2/I1>> Pick-up Setting +/- 5%
I2/I1 >> Drop-off 0.9 x setting +/-5%
Time delay operation Setting +/-2% or 20 ms, whichever is greater
CTS block diff operation < 1 cycle
CTS reset < 35 ms
Accuracy
Timers +/- 40 ms or 2%, whichever is greater
Broken current accuracy +/- 5%
Reset time < 30 ms
P54-TM-EN-1.1 881
Chapter 29 - Technical Specifications P54
882 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
8.1 GENERAL
Accuracy
+/- 2% of line length
Fault Location
Reference conditions: solid fault applied on line
P54-TM-EN-1.1 883
Chapter 29 - Technical Specifications P54
9 RATINGS
AC Measuring Inputs
Nominal frequency 50 Hz or 60 Hz (settable)
Operating range 45 to 65 Hz
Phase rotation ABC or CBA
AC Voltage Inputs
Nominal voltage (Vn) 100 V to 120 V or 380 V to 480 V phase-phase
Nominal burden per phase < 0.1 VA at Vn
240V (100/120V supply), 800V (380/480V supply) (continuous operation phase-phase)
Thermal withstand
2.6 x Vn (for 10 seconds)
Linear up to 200 V (100/120 V supply)
Linearity
Linear up to 800 V (380/400 V supply)
884 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
P54-TM-EN-1.1 885
Chapter 29 - Technical Specifications P54
Note:
Maximum loading = all inputs/outputs energised.
Note:
Quiescent or 1/2 loading = 1/2 of all inputs/outputs energised.
9.7 SUPERCAPACITOR
886 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
10 INPUT/OUTPUT CONNECTIONS
Nominal battery
Logic levels: 60-80% DO/PU Logic Levels: 50-70% DO/PU
voltage
24/27 V Logic 0 < 16.2V, Logic 1 > 19.2V Logic 0 <12V, Logic 1 > 16.8V
30/34 Logic 0 < 20.4V, Logic 1 > 24V Logic 0 < 15V, Logic 1 > 21V
48/54 Logic 0 < 32.4V, Logic 1 > 38.4V Logic 0 < 24V, Logic 1 > 33.6V
110/125 Logic 0 < 75V, Logic 1 > 88V Logic 0 < 55.V, Logic 1 > 77V
220/250 Logic 0 < 150V, Logic 1 > 176V Logic 0 < 110V, Logic 1 > 154V
Note:
Filter is required to make the opto-inputs immune to induced AC voltages.
In addition to the above thresholds, some models of this product provide the following threshold levels for FSK
applications:
● For 220/250 voltage inputs: Logic 0 < 145V, Logic 1 > 165V
P54-TM-EN-1.1 887
Chapter 29 - Technical Specifications P54
4 A for 1.5 s, 10000 operations (subject to the above limit for make and break, dc
Make, carry and break, dc resistive
resistive load)
0.5 A for 1 s, 10000 operations (subject to the above limit for make and break, dc
Make, carry and break, dc inductive
inductive load)
Make, carry and break ac resistive 30 A for 200 ms, 2000 operations (subject to the above limits)
Make, carry and break ac inductive 10 A for 1.5 s, 10000 operations (subject to the above limits)
Loaded contact 10000 operations min.
Unloaded contact 100000 operations min.
Operate time < 5 ms
Reset time < 10 ms
888 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
11 MECHANICAL SPECIFICATIONS
40TE
Case Types* 60TE
80TE
Weight (40TE case) 7 kg – 8 kg (depending on chosen options)
Weight (60TE case) 9 kg – 12 kg (depending on chosen options)
Weight (80TE case) 13 kg - 16 kg (depending on chosen options)
Dimensions in mm (w x h x l) (40TE case) W: 206.0 mm H: 177.0 mm D: 243.1 mm
Dimensions in mm (w x h x l) (60TE case) W: 309.6 mm H: 177.0 mm D: 243.1 mm
Dimensions in mm (w x h x l) (80TE case) W 413.2 mm H 177.0 mm D 243.1 mm
Mounting Panel, rack, or retrofit
Note:
*Case size is product dependent.
Against dust and dripping water (front face) IP52 as per IEC 60529:1989/A2:2013
Protection against dust (whole case) IP50 as per IEC 60529:1989/A2:2013
Protection for sides of the case (safety) IP30 as per IEC 60529:1989/A2:2013
Protection for rear of the case (safety) IP10 as per IEC 60529:1989/A2:2013
P54-TM-EN-1.1 889
Chapter 29 - Technical Specifications P54
12 TYPE TESTS
12.1 INSULATION
Note:
Exceptions are communications ports and normally-open output contacts, where applicable.
890 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
13 ENVIRONMENTAL CONDITIONS
P54-TM-EN-1.1 891
Chapter 29 - Technical Specifications P54
14 ELECTROMAGNETIC COMPATIBILITY
892 P54-TM-EN-1.1
P54 Chapter 29 - Technical Specifications
P54-TM-EN-1.1 893
Chapter 29 - Technical Specifications P54
Note:
Compliance is achieved using the opto-input filter.
894 P54-TM-EN-1.1
APPENDIX A
ORDERING OPTIONS
Appendix A - Ordering Options P54
896 P54-TM-EN-1.1
P54 Appendix A - Ordering Options
P54-TM-EN-1.1 A1
Appendix A - Ordering Options P54
A2 P54-TM-EN-1.1
APPENDIX B
Tables, containing a full list of settings for each model, are provided in a separate Excel file attached as an
embedded resource. To access the spreadsheet file, click on the button below.
Note:
An Open File dialogue box may open with a warning message about potential harm from programs, macros or viruses. The
file supplied does not contain any harmful content, and may be safely opened.
900 P54-TM-EN-1.1
APPENDIX C
WIRING DIAGRAMS
Appendix C - Wiring Diagrams P54
902 P54-TM-EN-1.1
CORTEC DRAWING-
MODEL OPTION * EXTERNAL CONNECTION DIAGRAM TITLE SHEET ISSUE
CURRENT DIFF 3 RELAY (80TE) 16 INPUTS, 16 OUTPUTS AND 4 HIGH
I/O Option J SPEED HIGH BREAK 10P54306-1 A
I/O Option K CURRENT DIFF 3 (80TE) 16 INPUTS AND 21 OUTPUTS 10P54307-1 A
I/O Option L CURRENT DIFF 3 (80TE) 16 INPUTS, 24 OUTPUTS 10P54308-1 A
CURRENT DIFF 3 (80TE) 24 INPUTS, 16 OUTPUTS AND 8 HIGH SPEED
I/O Option T HIGH BREAK 10P54309-1 A
CORTEC DRAWING-
MODEL OPTION * EXTERNAL CONNECTION DIAGRAM TITLE SHEET ISSUE
DISTANCE PROTECTION (80TE) 16 INPUTS, 16 OUTPUTS AND 4 HIGH
I/O Option J SPEED HIGH BREAK RELAYS 10P54611-1 A
P2 P1
A
S2 S1
B
C B
C PHASE ROTATION
SEE NOTE 6
A B C
P2 P1 A
A
S2 S1
B
C C B
PHASE ROTATION
NOTE 6
NOTES 1.
P2 P1
A
S2 S1
B
C B
C PHASE ROTATION
SEE NOTE 6
A B C
P2 P1 A
A
S2 S1
B
C C B
PHASE ROTATION
NOTE 6
NOTES 1.
P2 P1
A
S2 S1
B
C B
C PHASE ROTATION
SEE NOTE 6
A B C
P2 P1 A
A
S2 S1
B
C C B
PHASE ROTATION
NOTE 6
NOTES 1.
P2 P1
A
S2 S1
B
C B
C PHASE ROTATION
SEE NOTE 6
A B C
P2 P1 A
A
S2 S1
B
C C B
PHASE ROTATION
NOTE 6
NOTES 1.
P2 P1
A
S2 S1
B
C B
C PHASE ROTATION
SEE NOTE 6
A B C
P2 P1 A
A
S2 S1
B
C C B
PHASE ROTATION
NOTE 6
NOTES 1.
P2 P1
A
S2 S1
B
C B
C PHASE ROTATION
SEE NOTE 6
A B C
P2 P1 A
A
S2 S1
B
C C B
PHASE ROTATION
NOTE 6
NOTES 1.
P2 P1
A
S2 S1
B
C B
C PHASE ROTATION
SEE NOTE 6
A B C
P2 P1 A
A
S2 S1
B
C C B
PHASE ROTATION
NOTE 6
NOTES 1.
B C20
CONNECT TO RT430 GPS
C C21
N C22
C23 CASE
EARTH
V BUSBAR
(SEE NOTE 3.)
C24 * POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
NOTES 1.
B C20
CONNECT TO RT430 GPS
C C21
N C22
C23 CASE
EARTH
V BUSBAR
(SEE NOTE 3.)
C24 * POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
NOTES 1.
V BUSBAR
(SEE NOTE 3.)
C24 * POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
NOTES 1.
C C21
N C22
C23 CASE
EARTH
V BUSBAR
(SEE NOTE 3.)
C24 * POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
NOTES 1.
RX1
FIBRE OPTIC
B C20 COMMUNICATION
CURR DIFF
TX2
RX2
CASE
C C21 EARTH GPS CONNECT TO RT430
C23
V BUSBAR
(SEE NOTE 3.)
C24
NOTES 1.
RX1
B C20 FIBRE OPTIC
COMMUNICATION
CURR DIFF
TX2
RX2
C C21 CASE
EARTH GPS CONNECT TO RT430
N C22
* POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
C23
V BUSBAR
(SEE NOTE 3.)
C24
NOTES 1.
RX2
NOTES .
1. CASE
PIN TERMINAL (P.C.B. TYPE)
EARTH
2. FOR COMMS OPTIONS SEE DRAWING 10Px4001
RX2
NOTES .
NOTES .
SK7 D1
1 -
FAULT D2 OPTO 1 P11 K3 -
2 +
STATUS RELAY WATCHDOG
3 D3 CONTACT P12 RELAY 17
- K4
OPTO 2 P13 +
D4 WATCHDOG
+ CONTACT P14 K7 -
100 BASE-FX D5
TX N1
- RELAY 18
LAN A IEC 61850-9-2 LE D6 OPTO 3 RELAY 1 N2 K8
SLOT C + + HIGH BREAK
(SAMPLE ANALOGUE VALUE ONLY) RX N3
D7 K11 - CONTACTS
- RELAY 2 N4
D8 OPTO 4 RELAY 19
+ N5 K12
D9 +
100 BASE-FX RELAY 3 N6
TX - K15
D10 OPTO 5 N7 -
LAN B IEC 61850-9-2 LE
+ RELAY 20
SLOT C RELAY 4 N8
(SAMPLE ANALOGUE VALUE ONLY) RX D11 K16
- N9 +
D12 OPTO 6
+ RELAY 5 N10
D13 N11
-
D14 OPTO 7 RELAY 6 N12
+
N13
D15
- N14
D16 OPTO 8 RELAY 7
+ N15
D17 N16
COMMON N17
D18 CONNECTION RELAY 8
E1 N18
-
E2 OPTO 9 M1
+ RELAY 9 M2
E3
- M3
E4 OPTO 10 RELAY 10
+ M4
E5 M5
- P17
OPTO 11 RELAY 11 M6 -
E6
+ M7 SEE DRAWING EIA485/
E7 10Px4001 KBUS
- RELAY 12 M8 P18
E8 OPTO 12 + PORT
M9
+ P16
E9 RELAY 13 M10
SCN
-
OPTO 13 M11
E10
+ RELAY 14 M12 * P1
E11 -
M13 AC OR DC
- P2 x AUX SUPPLY
E12 OPTO 14 +
M14
+ RELAY 15
E13 M15
- M16
E14 OPTO 15
+ M17
RELAY 16
E15 M18
-
E16 OPTO 16
+
E17
COMMON
E18 CONNECTION
TX1
RX1
FIBRE OPTIC
COMMUNICATION
CURR DIFF
TX2
RX2
NOTES .
CASE
EARTH
TX1
RX1
FIBRE OPTIC
COMMUNICATION
CURR DIFF
TX2
RX2
NOTES .
CASE
1. EARTH
PIN TERMINAL (P.C.B. TYPE)
2. FOR COMMS OPTIONS SEE DRAWING 10Px4001 POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
TX1
RX1
FIBRE OPTIC
COMMUNICATION
CURR DIFF
TX2
RX2
NOTES .
CASE
1. PIN TERMINAL (P.C.B. TYPE)
EARTH
2. FOR COMMS OPTIONS SEE DRAWING 10Px4001 POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
NOTES .
CASE
EARTH
1. PIN TERMINAL (P.C.B. TYPE)
2. FOR COMMS OPTIONS SEE DRAWING 10Px4001 * POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
NOTES .
CASE
EARTH
1. PIN TERMINAL (P.C.B. TYPE)
2. FOR COMMS OPTIONS SEE DRAWING 10Px4001 * POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
NOTES .
CASE
EARTH
1. PIN TERMINAL (P.C.B. TYPE)
2. FOR COMMS OPTIONS SEE DRAWING 10Px4001 * POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY
P2 P1
A
S2 S1
B
C B
C PHASE ROTATION
SEE NOTE 6
A B C
P2 P1 A
A
S2 S1
B
C C B
PHASE ROTATION
NOTE 6
NOTES 1.
RX2
NOTES .
RX2
NOTES .
* POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY 1. FOR COMMS OPTIONS SEE DRAWING 10Px4001.
* POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY 1. FOR COMMS OPTIONS SEE DRAWING 10Px4001.
* POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY 1. FOR COMMS OPTIONS SEE DRAWING 10Px4001.
* POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY 1. FOR COMMS OPTIONS SEE DRAWING 10Px4001.
CASE
EARTH
* POWER SUPPLY VERSION 24-48V (NOMINAL) D.C. ONLY 1. FOR COMMS OPTIONS SEE DRAWING 10Px4001.
948 P54-TM-EN-1.1
Imagination at work
Grid Solutions
St Leonards Building
Redhill Business Park
Stafford, ST16 1WT, UK
+44 (0) 1785 250 070
contact.centre@ge.com
© 2022 General Electric. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or
should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial
circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without
express written authority, is strictly prohibited.
P54-TM-EN-1.1